Prior art keywords
project
submodule
charter
expert
evaluation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810190183.6A
Other languages
Chinese (zh)
Inventor
焦林
王军
方云鹏
胡凤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Oriental Deep Blue Information Polytron Technologies Inc
Original Assignee
Qingdao Oriental Deep Blue Information Polytron Technologies Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Oriental Deep Blue Information Polytron Technologies Inc filed Critical Qingdao Oriental Deep Blue Information Polytron Technologies Inc
Priority to CN201810190183.6A priority Critical patent/CN108416571A/en
Publication of CN108416571A publication Critical patent/CN108416571A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis

Abstract

The invention belongs to Internet service technical fields, and in particular to a kind of application method of scientific research service integration management system, specifically used method carry out in accordance with the following steps:Business department's setting declaration item declares management issue, and declarer writes an application, and unit is relied on to audit application, and the center of accepting accepts project application book, accepts center queried for items application, experts' evaluation project application book, project verification management, charter management;This method manages system to realize by scientific research service integration, and main body includes:It declares and accepts module, project appraisal module, project verification approval module, charter management module and Back Administration Module, design concept of the present invention is ingenious, ease for use is good, high degree of automation, scientific research business is capable of providing from the complete service for submitting application to audit to the end, and can effective management and control effectively be carried out to each link of scientific research business, application environment is friendly, wide market.

Description

A kind of application method of scientific research service integration management system
Technical field:
The invention belongs to Internet service technical fields, and in particular to a kind of user of scientific research service integration management system Method efficient, expansible can carry out integrated management to scientific research business, and the scope of application is broad.
Background technology:
Since the nineties, Internet technology has become the hot issue of computer circle, how to be developed based on net Network technology, the management information system for meeting itself needs is all kinds of administrative staff's focus of attention.In recent years, Internet/ The development of Intranet technologies brings brand-new thinking for the information management of enterprises and institutions.The technical foundation of Intranet It is WEB technologies, the structure of use is browser-server (Browser/Server) structure, it continues to use and has developed client End-server (Client/Server) structure technology uses unified browser interface in the user terminal of mis system, Installation and operation web server software and data base management system on background server.With the mis system phase of current traditional technology Than mis system user interface based on Intranet technologies is unified, is not limited by operating system platform, simple to operate, subtract The advantages that development amount of few user front end, system maintenance is easy;And since Intranet technologies use and Internet phases Same technology, the mis system based on Intranet can both establish one's own system, and can also easily connect Intranet, to most Ensure to limits the shared of external information resources.Currently, being had widely in other every profession and trades based on the management information system of WEB Using, such as the every profession and trades such as telecommunications, bank, railway, enterprises and institutions.And application is with the passing of time, mechanism improvement, technology maturation.WEB skills The maturation of art provides technical guarantee for education and scientific research IT application in management.The first systematic that WEB is established is simply to be linked at Static HTML page together, so as to the shared document between the user of dispersion.With the increase of user, user's input can be responded Dynamic web page it is more prevalent.
Now just widely used development technique has asp technologies, php technologies, jsp technologies, asp.net technologies, J2EE technologies, MVCWeb wherein based on J2EE technologies designs a model since the advance, stability, the speed of service of its technology are fast, expansibility With the high efficiency of exploitation, Rapid Popularization is obtained, therefore, the present invention designs a kind of user of scientific research service integration management system Method, for the scientific research service integration management service that user provides overall process, one-stop, adaptable, stability is high.
Invention content:
It is an object of the invention to overcoming disadvantage of the existing technology, seek design provide it is a kind of based on WEB service Scientific research service integration manages the application method of system, and by fully using information-based means, scientific research uniform service is proposed in user When the demand of management and aid decision, provide overall process to the user, the scientific research business that one-stop, adaptable, stability is high it is comprehensive Management service is closed, realizes the coordinated management inside user and information resources share.
To achieve the goals above, the application method of scientific research service integration management system of the present invention is supported across portion Door, across level coordination sharing, the information system management of science and technology plan item whole process, " one-stop " declare service mechanism, unified net Upper evaluation, project application people by scientific research service integration when managing system submission project application book and evaluation unit carries out project When application is evaluated, the specifically used method of application method of scientific research service integration management system carries out in accordance with the following steps:
S1, business department's setting declaration item declare management issue
The first step:Management module is declared in being logged in using service management person role for business department;
Second step:Setting declare business year, business sections contact person, network date of declaration, then upload return sample, Declare the materials such as guide, report of feasibility sample;
S2, declarer write an application
The first step:Declarer enters to declare after logging in by the account of declarer accepts module;
Second step:Pass through the template of category item book required for being found in the project application submodule under the module;
Third walks:Simultaneously entry item application is established, the rule for passing through project application submodule after filling in checks work( It can be checked, to ensure the accuracy filled in, elementary item template, each field and class are provided in project application submodule There are not corresponding templates, project essential information is specifically included in the template, project is expected performance objective, project funds situation, institute APPENDIX MATERIALSThe is needed, while the information that the submodule can be to filling in is filled in accurately into line discipline inspection to improve project application table Rate;
4th step:Inspection finish it is errorless after project paper is submitted, after submission can by log on declarer's account come Check job schedule, audit opinion and download reading application pdf document that project paper examines;
S3, unit is relied on to audit application
The first step:It relies on the auditor of unit to be logged in the account for declaring unit and relies on unit audit submodule;
Second step:The auditor of unit is relied on it can be seen that charter generates declarer's submission that submodule transmits Project application book, auditor checks and audits to project application book and input audit opinion;
Third walks:The account of declarer is then fed back to by support unit audit submodule to filling in vicious project application book The account of family declarer, by row is submitted again after its modification;
4th step:Business department's review is then transmitted to by support unit audit submodule to filling in errorless project application book Submodule;
5th step:Business department responsible person is transmitted across by business department's review submodule to relying on unit to audit submodule The electronic tasks book that the audit come passes through carries out review, and review is unqualified, retreats to charter and generates submodule by project leader It modifies, and the content changed, review can be needed not to have by audit opinion module writes in business department's review submodule Problem, which is then audited, to be passed through and agrees to report;
S4, the center of accepting accept project application book
The first step:With accept center admissibility staff role log in declare accept mould it is in the block accept submodule and enter storage Project application book accepts list;
Second step:Corresponding project application book is selected, and assigns " receiving paper material " instruction and completes to accept;Or selection Multiple projects, and assign " receiving paper material " instruction and accept in batches;When as undesirable such as paper material, then pass through " retracting modification " instruction is returned to declarer and remodifies;
S5, center queried for items application is accepted
The first step:It declares using accepting center admissibility staff role and logging in and accepts mould query statistic submodule in the block;
Second step:It is inquired by query statistic submodule " inquiry of all items application " in the block, can check institute There is project application book classification to declare situation, including project name, job schedule, audit opinion;
S6, experts' evaluation project application book
Step 1: evaluation unit assigns evaluation expert
The first step:Evaluation unit logs in expert and submodule is assigned to carry out expert's appointment;
Second step:Expert assigns submodule that can check current expert's grouping information, and evaluation expert is searched with search function And it is assigned;
Step 2: appraised index is arranged in evaluation unit
The first step:Evaluation unit personnel, which enter, to be increased evaluation table submodule newly and evaluation table standard relevant information is arranged;
Second step:Evaluation table information is changed and preserves into overall setting submodule;
Third walks:Submodule is set into form item to add form item, and edits and store customized content;
4th step:Into evaluation table generic submodule being arranged and preserve evaluation table generic;
Step 3: evaluation unit notifies evaluation expert
The first step:Evaluation unit staff enters expert and assigns submodule;
Second step:It is matched according to the field of expert and project application book to assign corresponding expert, is then referred to by expert Submodule mail notification is sent to correspond to expert;
Third walks:If expert, which replys, confirms mail, expert assigns submodule to divide corresponding project to experts' evaluation submodule Expert is corresponded in block, is evaluated by the expert, if expert, which replys, cannot carry out evaluation mail, submodule is assigned by expert Again itself and the domain expert are matched, until the project is matched with corresponding expert;
Step 4: evaluation expert evaluates online
The first step:Evaluation expert by login window input identity information submodule log in, after login it can be seen that and its My identities match waits for Project evaluation;
Second step:Evaluation expert enters the evaluation of experts' evaluation submodule and waits for Project evaluation, and by all commentarys information with Evaluation opinion is recorded in the submodule;
Step 5: evaluation unit safeguards review information
The first step:Evaluation unit staff's registry entry, which is evaluated module and entered, appraises details submodule through discussion, passes through the mould What block checked the project application book experts' evaluation of all storages appraises information through discussion;
Second step:Can not autonomous typing appraise the expert of information through discussion and can log in generation record and appraise submodule through discussion, existed by the module In experts' evaluation generation record expert opinion, be included in can comment and on-site review during expert opinion;
Step 6: evaluation unit inquires evaluation progress
The first step:Accrediting and validating agency staff's registry entry evaluation module simultaneously participates in evaluation and electing situation record sub module into expert;
Second step:Accrediting and validating agency staff checks stored experts' evaluation process, including evaluation by the submodule Progress, review result, evaluation amount statistics;
Step 7: evaluation unit inquires review result
The first step:Accrediting and validating agency's staff's registry entry evaluation module simultaneously enters experts' evaluation submodule;
Second step:Accrediting and validating agency staff by the module check it is all be automatically stored all review informations, evaluation anticipate See and review result;
S7, project verification management
Step 1: opinion is subsidized in setting
The first step:Business department business personnel logs in project verification opinion submodule, log in can check after the module it is all specially The project application book that family's evaluation finishes;
Second step:Business department business personnel fills in project verification opinion and as a result, includes whether to agree to that project verification, agreement are then filled out Write the project verification amount of money, project verification batch and project verification responsible person;It is dissenting, fill in the opinion not set up the project;
Step 2: setting project number
The first step:Business department business personnel registry entry number submodule, log in can check after the module it is all really The project application book of fixed self-service opinion;
Second step:Agree to that the project application book of project verification is compiled to all by the number function of project number submodule Number, it is preserved after number;
Step 3: assigning project verification opinion
The first step:Business department business personnel logs in opinion and assigns submodule, and project has been carried out by all in the module The project application book of number is sent at corresponding applicant;
S8, charter management
Step 1: business department notifies applicant to fill in charter
The first step:Business department's personnel's account logs in charter management module and fills in notice submodule into charter;
Second step:All project application Book of Records by project verification are crossed after charter generates submodule processing and have been generated initially Change charter, business department personnel notify the applicant by the project application of project verification to fill in initialization and appoint by way of mail Business book;
Step 2: applicant fills in charter
The first step:Project application people logs in charter management module by account and fills in oneself corresponding charter;
Second step:Project application people can disposably fill in and finish direct submission, and also graded is filled in, and be finished filling in every time After preserve, the job schedule, audit opinion and download reading task pdf document of charter can be checked after filling in;
Step 3: unit is relied on to audit charter
The first step:It relies on unit to log in by account to rely on unit to audit submodule and can check all filled out in the module Write the charter finished and submitted;
Second step:All charter are checked and audited, examination reports are filled in after audit and are preserved, it will be unqualified Charter return to charter and generate corresponding project application in submodule and acknowledge a debt and modify at family, will appointing of passing through of audit Business book is transmitted to business department's review submodule;
Step 4: business department personnel review charter
The first step:Business department personnel account registering service department's review submodule can simultaneously be checked all by audit Charter;
Second step:The electronic tasks book passed through to the audit for relying on unit audit submodule to transmit carries out review, and Input and storage audit opinion and the content for needing to change, review is unqualified, retreats to charter and generates submodule by project application It modifies at people, review is out of question, and audit passes through;
Third walks:For the Project charter that audit passes through, the PDF in charter management module generates submodule will be automatic The pdf document that Project charter is generated according to scheduled format is printed as papery charter for downloading;
Step 5: business department personnel accept charter
The first step:Charter, which is logged in, using business department's personnel's account accepts module;
Second step:It notifies applicant to download by the module and fills in papery charter;
Third walks:Applicant finishes charter in download and fills in, and affixes one's seal report business department step by step, carries out online It accepts;If paper material is undesirable, carries out retracting charter in the module and be changed by applicant;
Step 6: all applications of business department's personnel inquiry
The first step:Charter statistical query submodule is logged in using business department's personnel's account;
Second step:Charter statistical query submodule includes not audit project paper module and audited project paper module, It has audited project paper module and has had audit project by module and audit project not by module, it can by above-mentioned submodule Statistic of classification, the case where business department personnel can grasp project paper in real time from above-mentioned submodule, are carried out to all items book;
Third walks:Established project, which is logged in, using business department's personnel's account inquires submodule;
4th step:Business personnel can inquire all project papers set up the project by the submodule, and can grasp in real time Information including project name, job schedule, audit opinion.
The application method of scientific research service integration management system of the present invention is needed through scientific research service integration management system It unites to realize, the main body of the scientific research service integration management system includes:It declares and accepts module, project appraisal module, sets up the project and examine Batch module, charter management module and Back Administration Module, it is described to declare that accept the agent structure of module include providing item Project application submodule that mesh is declared online, relying on unit to provide the audit submodule of audit for project application people and project Block, accepting the query statistic submodule for accepting submodule, being counted to project and providing retrieval and inquisition service of project With the identification submodule verified for paper document and electronic document comparison file collation, the paper document accepted with guarantee It is identical with electronic data version;Elementary item template is provided in project application submodule, each field and classification have correspondence Template, project essential information is specifically included in the template, project is expected performance objective, project funds situation, required APPENDIX MATERIALSThe, The information that the submodule can be to filling in simultaneously fills in accuracy rate into line discipline inspection to improve project application table;Audit submodule For block to be audited to the project application table made a report on, this submodule uses the conventional mechanism audited step by step, if any one Grade audit is not resubmited by being then fed directly to project leader, and when audit can remember common audit opinion, To improve review efficiency;The query statistic submodule can divide domain classification not count all project application books, while just Situation is made a report in the project that the responsible person of each field project of all categories is checked at any time in oneself compass of competency, including is made a report on In, it has reported, pending nuclear state, so as to general control annual statement situation.
Project appraisal module includes project grouping submodule, experts database submodule, expert's appointment submodule, experts' evaluation Submodule safeguards review information submodule;Project is grouped submodule can be according to by including fields, declaring guide specification Keyword and semantic grassroot project including direction are grouped, and division group is to be found most in established grouping first otherwise Close grouping, if establishing new grouping without and if be named with the field keyword of the project, and only by project It assigns in the field group best suited, without repeated packets, to reduce grouping workload and convenient for carrying out project Expert assigns.
The expert source evaluated is stored in experts database submodule, and expert source can be constantly updated, expert's Source includes the project team member and domestic and international moral character of outstanding experts during receiving the project application, and the information stored includes expert's base This information, contact method, the time that can carry out evaluation, the field being good at, the experts database submodule are good at according to expert The first field be grouped, at least corresponding one of each expert is good at field;Experts database submodule setting simultaneously is provided with History experts database, interim experts database, formal experts database to carry out multiple management to expert source, in order to it is convenient to expert data into Row is safeguarded.
Expert assigns submodule to be grouped submodule and the communication connection of experts database submodule with project respectively, is assigned by expert Submodule can search all project in project grouping submodule, and each project can be carried out it is random or manually with Expert in the art matches, which assigns submodule also to have communication module, can send confirmation evaluation mail notification To the expert for obtaining matching entries, if expert, which replys, confirms mail, expert assigns submodule to comment corresponding project point to expert It examines in submodule and corresponds to expert, evaluated by the expert, if expert, which replys, cannot carry out evaluation mail, assigned by expert Submodule matches itself and the domain expert again, until the project is matched with corresponding expert, the mailing address is experts database The expert's mailing address stored in submodule.
Experts' evaluation submodule carries out project appraisal to make expert pass through the module, is provided with experts' evaluation and logs in window Openning module is inputted after account information logs in then in expert it can be seen that wait for Project evaluation with he or she's identities match, the mould Block being capable of whole follow-up in real time and record experts' evaluation progress;The module also supports the mode that meeting is evaluated, evaluation to terminate simultaneously Afterwards, the present invention is logged in by review organizer person and enters experts' evaluation submodule typing review result;Experts' evaluation submodule is supported The appraised index for evaluating table is self-defined, the automatic point counting of review result;Project appraisal module further includes having project information to encrypt safely Submodule, the module is run always in evaluation course, and the project ensured by using the mode of watermark and password is detailed The access safety and confidentiality of information, to prevent project information from revealing;The experts' evaluation submodule is additionally provided with expert and participates in evaluation and electing Situation record sub module can automatically record experts' evaluation process and evaluation progress can be supported to check, review result processing, comment Examine Workload Account.
It safeguards that review information submodule includes to appraise details submodule through discussion and appraise submodule through discussion for record, appraises details submodule through discussion Be stored with the project application book experts' evaluation appraises information through discussion, is checked to accrediting and validating agency;Submodule is appraised in generation record, which through discussion, to be supported In experts' evaluation generation record expert opinion, be included in can comment and on-site review during expert opinion, help to solve certain Expert supports by accrediting and validating agency's generation record review comment using computer to have the problem of obstacle.
Project appraisal module further includes having appraised index that submodule is arranged, and includes newly-increased evaluation table under the submodule Module, overall setting submodule, form item setting submodule and evaluation table generic submodule, increase evaluation table submodule newly and use Table standard relevant information is evaluated with setting, it is overall that submodule is set to change and preserve evaluation table information;Form item setting Customized content is edited and stored to module to add form item;Evaluation table generic submodule is being arranged and preservation is commented Examine the table generic page.
Project after evaluation can be transmitted to project verification approval module, and audit processing is carried out by the approving person that sets up the project, described vertical Approval module includes mainly project verification opinion submodule and project number submodule, the project verification opinion submodule to fill in It stores the opinion of the project after evaluation and as a result, simultaneously finally determining whether to set up the project, project verification result further includes the project verification amount of money, stands Item batch and project verification responsible person;Project number submodule is numbered to the project paper to determining project verification, convenient for managing and looking into It askes.
Charter management module carries out communication interconnection with project verification approval module, can receive all projects by project verification Book, and the project paper by project verification can be found in the module, the charter management module main body includes:Charter Fill in notice submodule, charter generates submodule, charter fills in submodule, relies on unit audit submodule, business department Review submodule, PDF generate submodule and charter and accept module, charter fill in notice submodule it can be seen that it is all By the project application book of project verification, mail notification applicant is sent by the contact method of the application and fills in charter;It is receiving To after the project for agreeing to project verification, charter generates submodule can automatically extract the part in return according to the project paper received Substance generates and stores the corresponding initialization task book for thinking project;The project leader of charter is filled in notified The login present invention enters after charter fills in submodule and only needs to can be completed to needing the place adjusted to modify after mail Charter being filled in and submitting, and efficiency is filled in and submit to improve.
Unit audit submodule is relied on to communicate interconnection with charter generation submodule and business department's review submodule respectively, In relying on unit audit submodule, rely on unit can be by relying on unit account to be logged in, it then can be to corresponding single The charter that position project leader submits is checked and is audited, and can underproof charter charter be returned to after audit It generates in submodule and modifies at corresponding project leader's account, also the charter that audit passes through can be transmitted to industry Business department review submodule, business department responsible person are transmitted by business department's review submodule to relying on unit to audit submodule The electronic tasks book that the audit to come over passes through carries out review, and review is unqualified, retreats to charter generation submodule and is responsible for by project People modifies, and can need the content changed, review by audit opinion module writes in business department's review submodule Out of question, audit passes through;For the Project charter that audit passes through, the PDF in charter management module generates submodule will be certainly The dynamic pdf document that Project charter is generated according to scheduled format is printed as papery charter for downloading.
Charter accepts module to notify applicant to download and submit paper material, after download finishes charter, Shen It asks someone to fill in finish and affix one's seal step by step and reports business department, accepted on the net;If paper material is undesirable, in the mould Block carries out retracting charter to be changed by applicant.
The charter management module further includes having charter statistical query submodule and the submodule of established project inquiry, The charter statistical query submodule includes not audit project paper module and audited project paper module, has audited project paper Module has audit project by module and audit project not by module, to carry out statistic of classification to all items book, The case where to grasp project paper in real time;The inquiry of the established project submodule can inquire all project papers set up the project.
Back Administration Module is the platform of present invention operation and support, belongs to the basic function of the present invention, can be according to need It asks and the function module including unit management module, technocracy module, authority management module is defined, the backstage Management module specifically includes following function module:
(1) institutional framework module:The knot of tissue of corresponding management unit can be adjusted according to project particular situation is declared Structure;
(2) user management module:The present invention is managed using user;
(3) authority management module:By different demarcations such as role, users, the permission to subsidizing in-house user carries out pipe Reason and setting;
(4) business configuration module:The class of service of the present invention is safeguarded, including Business Name, way to manage (project Class, subsidy class, reward class), business department, further, be each class of service with plan classification establish correspond close System;
(5) workflow management module:Scientific and technological business overall process Workflow Management is provided, vocational work flow management and flow are provided Customization service, can be reconfigured by secondary development to modify to flow;
(6) log management module:The correlation log of management system, to inquire and record;
(7) version management module:The version for managing the present invention, to carry out Version Control;
(8) menu management module:The menu needed according to different user roles is managed configuration, is different roles Different menus is provided;
(9) system integration module:Various integrated Fabric Interface demands of the present invention;
(10) management module is declared:Management issue is declared in setting after logging in the present invention to business department personnel, includes It declares business year, business sections contact person, network date of declaration, return sample, declare guide, report of feasibility sample.
The operation workflow that the declaring of project application book of the present invention accepts module is as follows:
(1) entry item application:Project leader fills in the project application submodule and submits the project application The content of table, project application table includes project essential information, project expection performance objective, project funds situation, required attachment material Material, supports different classes of, has and different makes a report on format;Online fill in can be by special project, and category is into making a report on, into when making a report on Side can be selected to fill in frontier inspection and looked into line discipline inspection, when making a report on, be filled in after inspection passes through, selection is generated for printing PDF format file;
(2) project application book is audited:Audit submodule carries out the project application table that project leader has made a report on preliminary Audit, the audit are reported by carrying out audit by each unit department from bottom to top, if audit at different levels does not pass through, directly Project leader is returned to resubmit;The process of audit is carried out by project one by one, and when audit can remember common audit meaning See, to improve review efficiency;Audit opinion can feed back to project leader through the invention;
(3) window personnel are accepted and accept paper material:Project application table after the approval, is being audited by audit submodule The pdf document for printed material will be generated in submodule, while sending mail notification project leader and submitting papery application;
(4) all items are inquired:Each field responsible person of all categories logs in query statistic submodule, checks oneself at any time Project in compass of competency makes a report on situation, including makes a report on, and has reported, pending caseload, so as to general control year Degree declares situation.
The operation workflow that project application book review of the present invention examines module is as follows:
(1) project is grouped:By declare accept module by the project application table of audit be transmitted to project be grouped submodule In, automatic grouping is completed to project application table by the submodule, the administrative staff of the submodule also can be to dividing not automatically Appropriate project application table is grouped manually;
(2) expert assigns:Expert's appointment is carried out to grouped project application table, expert is randomly assigned to each project It assigns in submodule and corresponds to the expert in field, and assign 3-7 alternative experts, then assign submodule to appointment by expert Expert carries out mail notification and confirms to participate in evaluating, to that can not participate in then replacing and capable of joining from alternative expert for evaluation Add the expert of evaluation;
(3) setting evaluation time and evaluation table:Experts' evaluation table is set to each Project evaluation group, and sets each evaluation item Project opens the time of evaluation in mesh group;
(4) expert is notified:Hair each expert of mail notification completes evaluation to experts' evaluation submodule again, can pass through The content of online editing notice can also support that notice is repeated several times;
(5) experts' evaluation:Expert evaluates to experts' evaluation submodule to being assigned to the project evaluated self, according to The setting of table is evaluated, index is given a mark one by one, finally by comprehensive point of automatic calculating of the invention;
(7) generation record expert opinion:To Dai Luzhuan can not be carried out by this submodule from the expert of primary input review comment Family's opinion, to complete opinion input;
(8) progress queries are evaluated:Situation logging modle is participated in evaluation and electing by expert to check self registering experts' evaluation process, Evaluation progress, review result processing and evaluation amount statistics can be checked simultaneously;
(9) review result is printed:It prints to the review result of projects, then is sent to appropriate department room on affixing one's seal and achieves.
The operation workflow of the project verification approval module of project application book of the present invention is as follows:
(1) opinion is subsidized in setting:In opinion submodule of setting up the project by way of excel, batch, which imports, subsidizes opinion, leads Fashionable to be corresponded to by accepting to number to be used as uniquely to identify, same record can be repeated as many times importing, for there is conflict Automatic check can be carried out to filter;
(2) setting project verification opinion:Business department, which logs in project verification opinion submodule and carries out project verification opinion to quasi- Funded Projects, repaiies Change, formation summarizes;
(3) it determines and subsidizes result:It is divided according to year, file is assigned according to the generation of the batch of project verification, finally enters and assigns Code, finished item are assigned;
(4) last setting of not setting up the project:According to the final result of project verification, the opinion that do not set up the project finally is assigned into son by opinion Module feedback is to project leader and declares unit, is provided with after not setting up the project finally, additionally it is possible to revocation be supported not set up the project finally Operation;
The operation workflow of charter management module of the present invention is as follows:
(1) charter makes a report on notice:It first passes through mail and project or assigns batch one by one according to project and carry out notice project Responsible person or carrier fill in charter, mail notification masterplate can online editing, and tracing task book makes a report on feedback feelings Condition, the account to not filling in and sending charter carry out repeating to send notice, and report is urged to make a report on;
(2) charter is filled in:Charter is generated by charter from submodule auto-initiation, can be rapidly completed online Modification and submission, after the completion of modification, there is modification record, can pass through compare identification modification trace;
(3) unit is relied on to audit charter:Rely on unit audit submodule to generating what submodule received from charter It has filled in the charter finished to be checked and audited, underproof charter, which is returned to charter, after audit generates submodule In modify at corresponding project leader's account;
(4) business department's review:Business department responsible person is by business department's review submodule to relying on unit audit Electronic tasks book that the audit that module transfer comes passes through carries out review, and review is unqualified, retreat to charter generate submodule by Project leader modifies, and the content for needing to change by audit opinion module writes in business department's review submodule, Review is out of question, and audit passes through;When audit, charter and application can be compared;
(5) material notice is accepted:For the Project charter that audit passes through, the PDF in charter management module generates son Module will generate the pdf document of Project charter according to scheduled format automatically, and papery charter is printed as downloading;Simultaneously originally The automatic transmission of invention accepts the notice of charter, meanwhile, business department can submit situation according to charter material at any time, again Notice accepts charter;
(6) it accepts charter carrier to complete the printing of papery charter and affix one's seal step by step, reports business department, carry out net On accept;
(7) charter fills in progress chasing:After project is assigned, required to automatically form charter according to each service management, All levels of management personnel can be by charter statistical query submodule and established project inquires filling out for submodule tracing task book Situation is reported, including notifies, fail to give notice, makes a report on, make a report on, audit is not audited, the states such as accepts, do not accept.
The operation workflow of technocracy module of the present invention is as follows:
(1) new expert is increased newly:When each project appraisal, when needing expert, it on the one hand can pass through experts database submodule Expert is obtained, on the other hand also can directly be added in expert to Review Team, them is invited to become a member of experts database;
(2) expert is audited:Newly-increased new expert starts for " interim evaluation expert ", to be logged in specially by expert library manager Family's library submodule is audited, and after the approval, is become " formal expert ";
(3) expert info is safeguarded:Expert info is safeguarded by experts database submodule, updates relevant correspondent party Formula, assessment of bids situation, familiar field, good faith management etc.;
(4) expert's Account Administration:The account number cipher of expert can be reset, then send mail and inform expert's sheet People.
Compared with prior art, the present invention having following benefit:
1, declare accept module have include each field application template, can improve application fill in convenience and improve fill out Efficiency is write, wherein project grouping submodule can intelligently divide simultaneously management project application according to field, and user of service is also It can be adjusted as the case may be with needs, easy to use, high degree of humanity, personnel easy to use check and right Charter is managed;
2, it is provided with experts database in project appraisal module, and experts database can be constantly updated, for the item of different field Mesh examines, while the expert that can follow up in real time tries progress, and generation record is additionally provided in project appraisal module and appraises submodule through discussion, with for Can not personally input expert provide solution, high degree of humanity.
3, project verification approval module charter generates submodule and can be automatically extracted in return according to the project paper received Part substance generates and stores the corresponding initialization task book for thinking project, can effectively avoid being filled in manually easily occur it is wrong Defect accidentally fills in convenience raising, also improves the efficiency of filling in of charter, effectively improve office efficiency.
4, design concept of the present invention is ingenious, and ease for use is good, high degree of automation, is capable of providing scientific research business and applies from submission The complete service audited to the end, and can effective management and control effectively be carried out to each link of scientific research business, it can be very big Working efficiency is improved, application environment is friendly, wide market.
Description of the drawings:
Fig. 1 is that of the present invention declare accepts module workflow schematic block diagram.
Fig. 2 is charter management module workflow schematic block diagram of the present invention.
Fig. 3 is project appraisal submodule workflow schematic block diagram of the present invention.
Specific implementation mode:
Below by embodiment, the invention will be further described.
Embodiment 1:
Project application people by scientific research service integration when managing system submission project application book and evaluation unit carries out item When mesh application is evaluated, the specifically used method of application method of scientific research service integration management system carries out in accordance with the following steps:
S1, business department's setting declaration item declare management issue
The first step:Management module is declared in being logged in using service management person role for business department;
Second step:Setting declare business year, business sections contact person, network date of declaration, then upload return sample, Declare the materials such as guide, report of feasibility sample;
S2, declarer write an application
The first step:Declarer enters to declare after logging in by the account of declarer accepts module;
Second step:Pass through the template of category item book required for being found in the project application submodule under the module;
Third walks:Simultaneously entry item application is established, the rule for passing through project application submodule after filling in checks work( It can be checked, to ensure the accuracy filled in, elementary item template, each field and class are provided in project application submodule There are not corresponding templates, project essential information is specifically included in the template, project is expected performance objective, project funds situation, institute APPENDIX MATERIALSThe is needed, while the information that the submodule can be to filling in is filled in accurately into line discipline inspection to improve project application table Rate;
4th step:Inspection finish it is errorless after project paper is submitted, after submission can by log on declarer's account come Check job schedule, audit opinion and download reading application pdf document that project paper examines;
S3, unit is relied on to audit application
The first step:It relies on the auditor of unit to be logged in the account for declaring unit and relies on unit audit submodule;
Second step:The auditor of unit is relied on it can be seen that charter generates declarer's submission that submodule transmits Project application book, auditor checks and audits to project application book and input audit opinion;
Third walks:The account of declarer is then fed back to by support unit audit submodule to filling in vicious project application book The account of family declarer, by row is submitted again after its modification;
4th step:Business department's review is then transmitted to by support unit audit submodule to filling in errorless project application book Submodule;
5th step:Business department responsible person is transmitted across by business department's review submodule to relying on unit to audit submodule The electronic tasks book that the audit come passes through carries out review, and review is unqualified, retreats to charter and generates submodule by project leader It modifies, and the content changed, review can be needed not to have by audit opinion module writes in business department's review submodule Problem, which is then audited, to be passed through and agrees to report;
S4, the center of accepting accept project application book
The first step:With accept center admissibility staff role log in declare accept mould it is in the block accept submodule and enter storage Project application book accepts list;
Second step:Corresponding project application book is selected, and assigns " receiving paper material " instruction and completes to accept;Or selection Multiple projects, and assign " receiving paper material " instruction and accept in batches;When as undesirable such as paper material, then pass through " retracting modification " instruction is returned to declarer and remodifies;
S5, center queried for items application is accepted
The first step:It declares using accepting center admissibility staff role and logging in and accepts mould query statistic submodule in the block;
Second step:It is inquired by query statistic submodule " inquiry of all items application " in the block, can check institute There is project application book classification to declare situation, including project name, job schedule, audit opinion;
S6, experts' evaluation project application book
Step 1: evaluation unit assigns evaluation expert
The first step:Evaluation unit logs in expert and submodule is assigned to carry out expert's appointment;
Second step:Expert assigns submodule that can check current expert's grouping information, and evaluation expert is searched with search function And it is assigned;
Step 2: appraised index is arranged in evaluation unit
The first step:Evaluation unit personnel, which enter, to be increased evaluation table submodule newly and evaluation table standard relevant information is arranged;
Second step:Evaluation table information is changed and preserves into overall setting submodule;
Third walks:Submodule is set into form item to add form item, and edits and store customized content;
4th step:Into evaluation table generic submodule being arranged and preserve evaluation table generic;
Step 3: evaluation unit notifies evaluation expert
The first step:Evaluation unit staff enters expert and assigns submodule;
Second step:It is matched according to the field of expert and project application book to assign corresponding expert, is then referred to by expert Submodule mail notification is sent to correspond to expert;
Third walks:If expert, which replys, confirms mail, expert assigns submodule to divide corresponding project to experts' evaluation submodule Expert is corresponded in block, is evaluated by the expert, if expert, which replys, cannot carry out evaluation mail, submodule is assigned by expert Again itself and the domain expert are matched, until the project is matched with corresponding expert;
Step 4: evaluation expert evaluates online
The first step:Evaluation expert by login window input identity information submodule log in, after login it can be seen that and its My identities match waits for Project evaluation;
Second step:Evaluation expert enters the evaluation of experts' evaluation submodule and waits for Project evaluation, and by all commentarys information with Evaluation opinion is recorded in the submodule;
Step 5: evaluation unit safeguards review information
The first step:Evaluation unit staff's registry entry, which is evaluated module and entered, appraises details submodule through discussion, passes through the mould What block checked the project application book experts' evaluation of all storages appraises information through discussion;
Second step:Can not autonomous typing appraise the expert of information through discussion and can log in generation record and appraise submodule through discussion, existed by the module In experts' evaluation generation record expert opinion, be included in can comment and on-site review during expert opinion;
Step 6: evaluation unit inquires evaluation progress
The first step:Accrediting and validating agency staff's registry entry evaluation module simultaneously participates in evaluation and electing situation record sub module into expert;
Second step:Accrediting and validating agency staff checks stored experts' evaluation process, including evaluation by the submodule Progress, review result, evaluation amount statistics;
Step 7: evaluation unit inquires review result
The first step:Accrediting and validating agency's staff's registry entry evaluation module simultaneously enters experts' evaluation submodule;
Second step:Accrediting and validating agency staff by the module check it is all be automatically stored all review informations, evaluation anticipate See and review result;
S7, project verification management
Step 1: opinion is subsidized in setting
The first step:Business department business personnel logs in project verification opinion submodule, log in can check after the module it is all specially The project application book that family's evaluation finishes;
Second step:Business department business personnel fills in project verification opinion and as a result, includes whether to agree to that project verification, agreement are then filled out Write the project verification amount of money, project verification batch and project verification responsible person;It is dissenting, fill in the opinion not set up the project;
Step 2: setting project number
The first step:Business department business personnel registry entry number submodule, log in can check after the module it is all really The project application book of fixed self-service opinion;
Second step:Agree to that the project application book of project verification is compiled to all by the number function of project number submodule Number, it is preserved after number;
Step 3: assigning project verification opinion
The first step:Business department business personnel logs in opinion and assigns submodule, and project has been carried out by all in the module The project application book of number is sent at corresponding applicant;
S8, charter management
Step 1: business department notifies applicant to fill in charter
The first step:Business department's personnel's account logs in charter management module and fills in notice submodule into charter;
Second step:All project application Book of Records by project verification are crossed after charter generates submodule processing and have been generated initially Change charter, business department personnel notify the applicant by the project application of project verification to fill in initialization and appoint by way of mail Business book;
Step 2: applicant fills in charter
The first step:Project application people logs in charter management module by account and fills in oneself corresponding charter;
Second step:Project application people can disposably fill in and finish direct submission, and also graded is filled in, and be finished filling in every time After preserve, the job schedule, audit opinion and download reading task pdf document of charter can be checked after filling in;
Step 3: unit is relied on to audit charter
The first step:It relies on unit to log in by account to rely on unit to audit submodule and can check all filled out in the module Write the charter finished and submitted;
Second step:All charter are checked and audited, examination reports are filled in after audit and are preserved, it will be unqualified Charter return to charter and generate corresponding project application in submodule and acknowledge a debt and modify at family, will appointing of passing through of audit Business book is transmitted to business department's review submodule;
Step 4: business department personnel review charter
The first step:Business department personnel account registering service department's review submodule can simultaneously be checked all by audit Charter;
Second step:The electronic tasks book passed through to the audit for relying on unit audit submodule to transmit carries out review, and Input and storage audit opinion and the content for needing to change, review is unqualified, retreats to charter and generates submodule by project application It modifies at people, review is out of question, and audit passes through;
Third walks:For the Project charter that audit passes through, the PDF in charter management module generates submodule will be automatic The pdf document that Project charter is generated according to scheduled format is printed as papery charter for downloading;
Step 5: business department personnel accept charter
The first step:Charter, which is logged in, using business department's personnel's account accepts module;
Second step:It notifies applicant to download by the module and fills in papery charter;
Third walks:Applicant finishes charter in download and fills in, and affixes one's seal report business department step by step, carries out online It accepts;If paper material is undesirable, carries out retracting charter in the module and be changed by applicant;
Step 6: all applications of business department's personnel inquiry
The first step:Charter statistical query submodule is logged in using business department's personnel's account;
Second step:Charter statistical query submodule includes not audit project paper module and audited project paper module, It has audited project paper module and has had audit project by module and audit project not by module, it can by above-mentioned submodule Statistic of classification, the case where business department personnel can grasp project paper in real time from above-mentioned submodule, are carried out to all items book;
Third walks:Established project, which is logged in, using business department's personnel's account inquires submodule;
4th step:Business personnel can inquire all project papers set up the project by the submodule, and can grasp in real time Information including project name, job schedule, audit opinion.
The application method for the scientific research service integration management system that the present embodiment is related to needs to manage by scientific research service integration System realizes that the main body of the scientific research service integration management system includes:It declares and accepts module, project appraisal module, project verification Approval module, charter management module and Back Administration Module, it is described to declare that accept the agent structure of module include providing Project application submodule that project is declared online, relying on unit to provide the audit submodule of audit for project application people and project Block, accepting the query statistic submodule for accepting submodule, being counted to project and providing retrieval and inquisition service of project With the identification submodule verified for paper document and electronic document comparison file collation, the paper document accepted with guarantee It is identical with electronic data version;Elementary item template is provided in project application submodule, each field and classification have correspondence Template, project essential information is specifically included in the template, project is expected performance objective, project funds situation, required APPENDIX MATERIALSThe, The information that the submodule can be to filling in simultaneously fills in accuracy rate into line discipline inspection to improve project application table;Audit submodule For block to be audited to the project application table made a report on, this submodule uses the conventional mechanism audited step by step, if any one Grade audit is not resubmited by being then fed directly to project leader, and when audit can remember common audit opinion, To improve review efficiency;The query statistic submodule can divide domain classification not count all project application books, while just Situation is made a report in the project that the responsible person of each field project of all categories is checked at any time in oneself compass of competency, including is made a report on In, it has reported, pending nuclear state, so as to general control annual statement situation.
Project appraisal module includes project grouping submodule, experts database submodule, expert's appointment submodule, experts' evaluation Submodule safeguards review information submodule;Project is grouped submodule can be according to by including fields, declaring guide specification Keyword and semantic grassroot project including direction are grouped, and division group is to be found most in established grouping first otherwise Close grouping, if establishing new grouping without and if be named with the field keyword of the project, and only by project It assigns in the field group best suited, without repeated packets, to reduce grouping workload and convenient for carrying out project Expert assigns.
The expert source evaluated is stored in experts database submodule, and expert source can be constantly updated, expert's Source includes the project team member and domestic and international moral character of outstanding experts during receiving the project application, and the information stored includes expert's base This information, contact method, the time that can carry out evaluation, the field being good at, the experts database submodule are good at according to expert The first field be grouped, at least corresponding one of each expert is good at field;Experts database submodule setting simultaneously is provided with History experts database, interim experts database, formal experts database to carry out multiple management to expert source, in order to it is convenient to expert data into Row is safeguarded.
Expert assigns submodule to be grouped submodule and the communication connection of experts database submodule with project respectively, is assigned by expert Submodule can search all project in project grouping submodule, and each project can be carried out it is random or manually with Expert in the art matches, which assigns submodule also to have communication module, can send confirmation evaluation mail notification To the expert for obtaining matching entries, if expert, which replys, confirms mail, expert assigns submodule to comment corresponding project point to expert It examines in submodule and corresponds to expert, evaluated by the expert, if expert, which replys, cannot carry out evaluation mail, assigned by expert Submodule matches itself and the domain expert again, until the project is matched with corresponding expert, the mailing address is experts database The expert's mailing address stored in submodule.
Experts' evaluation submodule carries out project appraisal to make expert pass through the module, is provided with experts' evaluation and logs in window Openning module is inputted after account information logs in then in expert it can be seen that wait for Project evaluation with he or she's identities match, the mould Block being capable of whole follow-up in real time and record experts' evaluation progress;The module also supports the mode that meeting is evaluated, evaluation to terminate simultaneously Afterwards, the present embodiment is logged in by review organizer person and enters experts' evaluation submodule typing review result;Experts' evaluation submodule branch The appraised index for holding evaluation table is self-defined, the automatic point counting of review result;Project appraisal module further includes having project information to add safely Close submodule, the module is run always in evaluation course, and the project ensured by using the mode of watermark and password is detailed The access safety and confidentiality of thin information, to prevent project information from revealing;The experts' evaluation submodule is additionally provided with expert's ginseng Comment situation record sub module, experts' evaluation process can be automatically recorded and evaluation progress can be supported to check, review result processing, Evaluation amount counts.
It safeguards that review information submodule includes to appraise details submodule through discussion and appraise submodule through discussion for record, appraises details submodule through discussion Be stored with the project application book experts' evaluation appraises information through discussion, is checked to accrediting and validating agency;Submodule is appraised in generation record, which through discussion, to be supported In experts' evaluation generation record expert opinion, be included in can comment and on-site review during expert opinion, help to solve certain Expert supports by accrediting and validating agency's generation record review comment using computer to have the problem of obstacle.
Project appraisal module further includes having appraised index that submodule is arranged, and includes newly-increased evaluation table under the submodule Module, overall setting submodule, form item setting submodule and evaluation table generic submodule, increase evaluation table submodule newly and use Table standard relevant information is evaluated with setting, it is overall that submodule is set to change and preserve evaluation table information;Form item setting Customized content is edited and stored to module to add form item;Evaluation table generic submodule is being arranged and preservation is commented Examine the table generic page.
Project after evaluation can be transmitted to project verification approval module, and audit processing is carried out by the approving person that sets up the project, described vertical Approval module includes mainly project verification opinion submodule and project number submodule, the project verification opinion submodule to fill in It stores the opinion of the project after evaluation and as a result, simultaneously finally determining whether to set up the project, project verification result further includes the project verification amount of money, stands Item batch and project verification responsible person;Project number submodule is numbered to the project paper to determining project verification, convenient for managing and looking into It askes.
Charter management module carries out communication interconnection with project verification approval module, can receive all projects by project verification Book, and the project paper by project verification can be found in the module, the charter management module main body includes:Charter Fill in notice submodule, charter generates submodule, charter fills in submodule, relies on unit audit submodule, business department Review submodule, PDF generate submodule and charter and accept module, charter fill in notice submodule it can be seen that it is all By the project application book of project verification, mail notification applicant is sent by the contact method of the application and fills in charter;It is receiving To after the project for agreeing to project verification, charter generates submodule can automatically extract the part in return according to the project paper received Substance generates and stores the corresponding initialization task book for thinking project;The project leader of charter is filled in notified Logged in after mail the present embodiment enter charter fill in only the place adjusted to needs is needed to modify after submodule can be complete Efficiency is filled in and submitted to filling in and submitting at charter to improve.
Unit audit submodule is relied on to communicate interconnection with charter generation submodule and business department's review submodule respectively, In relying on unit audit submodule, rely on unit can be by relying on unit account to be logged in, it then can be to corresponding single The charter that position project leader submits is checked and is audited, and can underproof charter charter be returned to after audit It generates in submodule and modifies at corresponding project leader's account, also the charter that audit passes through can be transmitted to industry Business department review submodule, business department responsible person are transmitted by business department's review submodule to relying on unit to audit submodule The electronic tasks book that the audit to come over passes through carries out review, and review is unqualified, retreats to charter generation submodule and is responsible for by project People modifies, and can need the content changed, review by audit opinion module writes in business department's review submodule Out of question, audit passes through;For the Project charter that audit passes through, the PDF in charter management module generates submodule will be certainly The dynamic pdf document that Project charter is generated according to scheduled format is printed as papery charter for downloading.
Charter accepts module to notify applicant to download and submit paper material, after download finishes charter, Shen It asks someone to fill in finish and affix one's seal step by step and reports business department, accepted on the net;If paper material is undesirable, in the mould Block carries out retracting charter to be changed by applicant.
The charter management module further includes having charter statistical query submodule and the submodule of established project inquiry, The charter statistical query submodule includes not audit project paper module and audited project paper module, has audited project paper Module has audit project by module and audit project not by module, to carry out statistic of classification to all items book, The case where to grasp project paper in real time;The inquiry of the established project submodule can inquire all project papers set up the project.
Back Administration Module is the platform of the present embodiment operation and support, belongs to the basic function of the present embodiment, Neng Gougen The function module including unit management module, technocracy module, authority management module is defined according to demand, it is described Back Administration Module specifically includes following function module:
(1) institutional framework module:The knot of tissue of corresponding management unit can be adjusted according to project particular situation is declared Structure;
(2) user management module:The present embodiment is managed using user;
(3) authority management module:By different demarcations such as role, users, the permission to subsidizing in-house user carries out pipe Reason and setting;
(4) business configuration module:The class of service of the present embodiment is safeguarded, including Business Name, way to manage (item Mesh class, subsidy class, reward class), business department, further, be each class of service with plan classification establish correspond Relationship;
(5) workflow management module:Scientific and technological business overall process Workflow Management is provided, vocational work flow management and flow are provided Customization service, can be reconfigured by secondary development to modify to flow;
(6) log management module:The correlation log of management system, to inquire and record;
(7) version management module:The version for managing the present embodiment, to carry out Version Control;
(8) menu management module:The menu needed according to different user roles is managed configuration, is different roles Different menus is provided;
(9) system integration module:The various integrated Fabric Interface demands that the present embodiment is related to;
(10) management module is declared:Management issue is declared in setting after logging in the present embodiment to business department personnel, including It declares business year, business sections contact person, network date of declaration, return sample, declare guide, report of feasibility sample This.
Embodiment 2:
The operation workflow that the declaring of project application book involved in embodiment 1 accepts module is as follows:
(1) entry item application:Project leader fills in the project application submodule and submits the project application The content of table, project application table includes project essential information, project expection performance objective, project funds situation, required attachment material Material, supports different classes of, has and different makes a report on format;Online fill in can be by special project, and category is into making a report on, into when making a report on Side can be selected to fill in frontier inspection and looked into line discipline inspection, when making a report on, be filled in after inspection passes through, selection is generated for printing PDF format file;
(2) project application book is audited:Audit submodule carries out the project application table that project leader has made a report on preliminary Audit, the audit are reported by carrying out audit by each unit department from bottom to top, if audit at different levels does not pass through, directly Project leader is returned to resubmit;The process of audit is carried out by project one by one, and when audit can remember common audit meaning See, to improve review efficiency;Audit opinion can feed back to project leader through this embodiment;
(3) window personnel are accepted and accept paper material:Project application table after the approval, is being audited by audit submodule The pdf document for printed material will be generated in submodule, while sending mail notification project leader and submitting papery application;
(4) all items are inquired:Each field responsible person of all categories logs in query statistic submodule, checks oneself at any time Project in compass of competency makes a report on situation, including makes a report on, and has reported, pending caseload, so as to general control year Degree declares situation.
Embodiment 3:
The operation workflow that the project application book review that the present embodiment involved in embodiment 1 is related to examines module is as follows:
(1) project is grouped:By declare accept module by the project application table of audit be transmitted to project be grouped submodule In, automatic grouping is completed to project application table by the submodule, the administrative staff of the submodule also can be to dividing not automatically Appropriate project application table is grouped manually;
(2) expert assigns:Expert's appointment is carried out to grouped project application table, expert is randomly assigned to each project It assigns in submodule and corresponds to the expert in field, and assign 3-7 alternative experts, then assign submodule to appointment by expert Expert carries out mail notification and confirms to participate in evaluating, to that can not participate in then replacing and capable of joining from alternative expert for evaluation Add the expert of evaluation;
(3) setting evaluation time and evaluation table:Experts' evaluation table is set to each Project evaluation group, and sets each evaluation item Project opens the time of evaluation in mesh group;
(4) expert is notified:Hair each expert of mail notification completes evaluation to experts' evaluation submodule again, can pass through The content of online editing notice can also support that notice is repeated several times;
(5) experts' evaluation:Expert evaluates to experts' evaluation submodule to being assigned to the project evaluated self, according to The setting of table is evaluated, index is given a mark one by one, finally calculates comprehensive point automatically by the present embodiment;
(7) generation record expert opinion:To Dai Luzhuan can not be carried out by this submodule from the expert of primary input review comment Family's opinion, to complete opinion input;
(8) progress queries are evaluated:Situation logging modle is participated in evaluation and electing by expert to check self registering experts' evaluation process, Evaluation progress, review result processing and evaluation amount statistics can be checked simultaneously;
(9) review result is printed:It prints to the review result of projects, then is sent to appropriate department room on affixing one's seal and achieves.
Embodiment 4:
The operation workflow of the project verification approval module of project application book involved in embodiment 1 is as follows:
(1) opinion is subsidized in setting:In opinion submodule of setting up the project by way of excel, batch, which imports, subsidizes opinion, leads Fashionable to be corresponded to by accepting to number to be used as uniquely to identify, same record can be repeated as many times importing, for there is conflict Automatic check can be carried out to filter;
(2) setting project verification opinion:Business department, which logs in project verification opinion submodule and carries out project verification opinion to quasi- Funded Projects, repaiies Change, formation summarizes;
(3) it determines and subsidizes result:It is divided according to year, file is assigned according to the generation of the batch of project verification, finally enters and assigns Code, finished item are assigned;
(4) last setting of not setting up the project:According to the final result of project verification, the opinion that do not set up the project finally is assigned into son by opinion Module feedback is to project leader and declares unit, is provided with after not setting up the project finally, additionally it is possible to revocation be supported not set up the project finally Operation;
Embodiment 5:
The operation workflow of charter management module involved in embodiment 1 is as follows:
(1) charter makes a report on notice:It first passes through mail and project or assigns batch one by one according to project and carry out notice project Responsible person or carrier fill in charter, mail notification masterplate can online editing, and tracing task book makes a report on feedback feelings Condition, the account to not filling in and sending charter carry out repeating to send notice, and report is urged to make a report on;
(2) charter is filled in:Charter is generated by charter from submodule auto-initiation, can be rapidly completed online Modification and submission, after the completion of modification, there is modification record, can pass through compare identification modification trace;
(3) unit is relied on to audit charter:Rely on unit audit submodule to generating what submodule received from charter It has filled in the charter finished to be checked and audited, underproof charter, which is returned to charter, after audit generates submodule In modify at corresponding project leader's account;
(4) business department's review:Business department responsible person is by business department's review submodule to relying on unit audit Electronic tasks book that the audit that module transfer comes passes through carries out review, and review is unqualified, retreat to charter generate submodule by Project leader modifies, and the content for needing to change by audit opinion module writes in business department's review submodule, Review is out of question, and audit passes through;When audit, charter and application can be compared;
(5) material notice is accepted:For the Project charter that audit passes through, the PDF in charter management module generates son Module will generate the pdf document of Project charter according to scheduled format automatically, and papery charter is printed as downloading;Simultaneously originally Embodiment sends the notice for accepting charter automatically, meanwhile, business department can submit situation, weight according to charter material at any time New notice accepts charter;
(6) it accepts charter carrier to complete the printing of papery charter and affix one's seal step by step, reports business department, carry out net On accept;
(7) charter fills in progress chasing:After project is assigned, required to automatically form charter according to each service management, All levels of management personnel can be by charter statistical query submodule and established project inquires filling out for submodule tracing task book Situation is reported, including notifies, fail to give notice, makes a report on, make a report on, audit is not audited, the states such as accepts, do not accept.
Embodiment 6:
The operation workflow of technocracy module involved in embodiment 1 is as follows:
(1) new expert is increased newly:When each project appraisal, when needing expert, it on the one hand can pass through experts database submodule Expert is obtained, on the other hand also can directly be added in expert to Review Team, them is invited to become a member of experts database;
(2) expert is audited:Newly-increased new expert starts for " interim evaluation expert ", to be logged in specially by expert library manager Family's library submodule is audited, and after the approval, is become " formal expert ";
(3) expert info is safeguarded:Expert info is safeguarded by experts database submodule, updates relevant correspondent party Formula, assessment of bids situation, familiar field, good faith management etc.;
(4) expert's Account Administration:The account number cipher of expert can be reset, then send mail and inform expert's sheet People.

Claims (10)

1. a kind of application method of scientific research service integration management system, it is characterised in that project application people is submitting project application book When and evaluation unit carry out project application book review examine when, concrete operation step carries out as follows:
S1, business department's setting declaration item declare management issue
The first step:Management module is declared in being logged in using service management person role for business department;
Second step:Business year, business sections contact person, network date of declaration are declared in setting, then are uploaded return sample, declared The materials such as guide, report of feasibility sample;
S2, declarer write an application
The first step:Declarer enters to declare after logging in by the account of declarer accepts module;
Second step:Pass through the template of category item book required for being found in the project application submodule under the module;
Third walks:Establish and entry item application, after filling in by the regular audit function of project application submodule into Row checks, to ensure the accuracy filled in, elementary item template is provided in project application submodule, each field and classification are equal There are corresponding templates, project essential information is specifically included in the template, project is expected performance objective, project funds situation, required attached Part material, while the information that the submodule can be to filling in fills in accuracy rate into line discipline inspection to improve project application table;
4th step:Inspection finish it is errorless after project paper is submitted, can be checked by logging on declarer's account after submission Job schedule, audit opinion and the download reading application pdf document that project paper examines;
S3, unit is relied on to audit application
The first step:It relies on the auditor of unit to be logged in the account for declaring unit and relies on unit audit submodule;
Second step:The auditor of unit is relied on it can be seen that charter generates the item that the declarer that submodule transmits submits Mesh application, auditor check and audit to project application book and input audit opinion;
Third walks:The account Shen of declarer is then fed back to by support unit audit submodule to filling in vicious project application book The account of journalist, by row is submitted again after its modification;
4th step:Business department's review submodule is then transmitted to by support unit audit submodule to filling in errorless project application book Block;
5th step:Business department responsible person is by business department's review submodule to relying on unit to audit what submodule transmitted It audits the electronic tasks book passed through and carries out review, review is unqualified, retreats to charter generation submodule and is carried out by project leader Modification, and the content changed, review can be needed out of question by audit opinion module writes in business department's review submodule Then audit passes through and agrees to report;
S4, the center of accepting accept project application book
The first step:With accept center admissibility staff role log in declare accept mould it is in the block accept submodule and enter stored items Application accepts list;
Second step:Corresponding project application book is selected, and assigns " receiving paper material " instruction and completes to accept;Or selection is multiple Project, and assign " receiving paper material " instruction and accept in batches;When as undesirable such as paper material, then by " retracting Modification " instruction is returned to declarer and remodifies;
S5, center queried for items application is accepted
The first step:It declares using accepting center admissibility staff role and logging in and accepts mould query statistic submodule in the block;
Second step:It is inquired by query statistic submodule " inquiry of all items application " in the block, can check all items Mesh application classification declares situation, including project name, job schedule, audit opinion;
S6, experts' evaluation project application book
Step 1: evaluation unit assigns evaluation expert
The first step:Evaluation unit logs in expert and submodule is assigned to carry out expert's appointment;
Second step:Expert assigns submodule that can check current expert's grouping information, searches evaluation expert with search function and goes forward side by side Row is assigned;
Step 2: appraised index is arranged in evaluation unit
The first step:Evaluation unit personnel, which enter, to be increased evaluation table submodule newly and evaluation table standard relevant information is arranged;
Second step:Evaluation table information is changed and preserves into overall setting submodule;
Third walks:Submodule is set into form item to add form item, and edits and store customized content;
4th step:Into evaluation table generic submodule being arranged and preserve evaluation table generic;
Step 3: evaluation unit notifies evaluation expert
The first step:Evaluation unit staff enters expert and assigns submodule;
Second step:It is matched according to the field of expert and project application book to assign corresponding expert, son is then assigned by expert Module mail notification corresponds to expert;
Third walks:If expert, which replys, confirms mail, expert assigns submodule to divide corresponding project into experts' evaluation submodule Corresponding expert, is evaluated by the expert, if expert, which replys, cannot carry out evaluation mail, submodule is assigned again by expert Itself and the domain expert are matched, until the project is matched with corresponding expert;
Step 4: evaluation expert evaluates online
The first step:Evaluation expert inputs identity information submodule by login window and logs in, it can be seen that and he or she after login Identities match waits for Project evaluation;
Second step:Evaluation expert enters the evaluation of experts' evaluation submodule and waits for Project evaluation, and by all commentary information and evaluation Opinion is recorded in the submodule;
Step 5: evaluation unit safeguards review information
The first step:Evaluation unit staff's registry entry, which is evaluated module and entered, appraises details submodule through discussion, is looked by the module That reads the project application book experts' evaluation of all storages appraises information through discussion;
Second step:Can not autonomous typing appraise the expert of information through discussion and can log in generation record and appraise submodule through discussion, by the module in expert In evaluation generation record expert opinion, be included in can comment and on-site review during expert opinion;
Step 6: evaluation unit inquires evaluation progress
The first step:Accrediting and validating agency staff's registry entry evaluation module simultaneously participates in evaluation and electing situation record sub module into expert;
Second step:Accrediting and validating agency staff checks stored experts' evaluation process by the submodule, including evaluation progress, Review result, evaluation amount statistics;
Step 7: evaluation unit inquires review result
The first step:Accrediting and validating agency's staff's registry entry evaluation module simultaneously enters experts' evaluation submodule;
Second step:Accrediting and validating agency staff by the module check it is all be automatically stored all review informations, review comment and Review result;
S7, project verification management
Step 1: opinion is subsidized in setting
The first step:Business department business personnel logs in project verification opinion submodule, can check that all experts comment after logging in the module The project application book for finishing the trail complete;
Second step:Business department business personnel fills in project verification opinion and as a result, includes whether to agree to that project verification, then filling in for agreement are vertical The item amount of money, project verification batch and project verification responsible person;It is dissenting, fill in the opinion not set up the project;
Step 2: setting project number
The first step:Business department business personnel registry entry number submodule can check all determinations certainly after logging in the module Help the project application book of opinion;
Second step:Agree to that the project application book of project verification is numbered to all by the number function of project number submodule, compiles It is preserved after number;
Step 3: assigning project verification opinion
The first step:Business department business personnel logs in opinion and assigns submodule, and project number has been carried out by all in the module Project application book be sent at corresponding applicant;
S8, charter management
Step 1: business department notifies applicant to fill in charter
The first step:Business department's personnel's account logs in charter management module and fills in notice submodule into charter;
Second step:All project application Book of Records by project verification are crossed after charter generates submodule processing and have generated initialization times Business book, business department personnel notify the applicant of the project application by project verification to fill in initialization task by way of mail Book;
Step 2: applicant fills in charter
The first step:Project application people logs in charter management module by account and fills in oneself corresponding charter;
Second step:Project application people can disposably fill in and finish direct submission, and also graded is filled in, and be protected after filling in every time It deposits, the job schedule, audit opinion and download reading task pdf document of charter poor can be seen after filling in;
Step 3: unit is relied on to audit charter
The first step:It relies on unit to log in by account to rely on unit to audit submodule and can check all filled in the module The charter finished and submitted;
Second step:All charter are checked and audited, examination reports are filled in after audit and are preserved, by underproof Business book, which returns to charter and generates corresponding project application in submodule and acknowledge a debt, modifies at family, the charter that audit is passed through It is transmitted to business department's review submodule;
Step 4: business department personnel review charter
The first step:Business department personnel account registering service department's review submodule simultaneously can check all appointing by audit Business book;
Second step:The electronic tasks book passed through to the audit for relying on unit audit submodule to transmit carries out review, and inputs With storage audit opinion and the content for needing to change, review is unqualified, retreats to charter and generates submodule by project application people It modifies, review is out of question, and audit passes through;
Third walks:For the Project charter that passes through of audit, the PDF in charter management module generate submodule will automatically according to Scheduled format generates the pdf document of Project charter, and papery charter is printed as downloading;
Step 5: business department personnel accept charter
The first step:Charter, which is logged in, using business department's personnel's account accepts module;
Second step:It notifies applicant to download by the module and fills in papery charter;
Third walks:Applicant finishes charter in download and fills in, and affixes one's seal report business department step by step, carry out on the net by Reason;If paper material is undesirable, carries out retracting charter in the module and be changed by applicant;
Step 6: all applications of business department's personnel inquiry
The first step:Charter statistical query submodule is logged in using business department's personnel's account;
Second step:Charter statistical query submodule includes not audit project paper module and audited project paper module, has been examined Core project paper module has audit project by module and audit project not by module, can be to institute by above-mentioned submodule There is project paper to carry out statistic of classification, the case where business department personnel can grasp project paper in real time from above-mentioned submodule;
Third walks:Established project, which is logged in, using business department's personnel's account inquires submodule;
4th step:Business personnel can inquire all project papers set up the project by the submodule, and can grasp in real time including Information including project name, job schedule, audit opinion.
2. a kind of application method of scientific research service integration management system, it is characterised in that this method is managed by scientific research service integration System realizes that the agent structure of the scientific research service integration management system includes declaring to accept module, project appraisal module, project verification Approval module, charter management module and Back Administration Module, it includes providing project to declare and accept the agent structure of module The project application submodule declared online, to for project application people and project rely on unit provide audit audit submodule, To accept the query statistic submodule for accepting submodule, being counted to project and providing retrieval and inquisition service and use of project With the identification submodule verified for paper document and electronic document comparison file collation, to ensure the paper document and electricity that accept Subdata version is identical;Elementary item template is provided in project application submodule, each field and classification have corresponding templates, Project essential information, project expection performance objective, project funds situation, required APPENDIX MATERIALSThe are specifically included in the template, simultaneously The submodule can be to filling in information into line discipline inspection, fill in accuracy rate to improve project application table;Submodule is audited to use To be audited to the project application table made a report on, this submodule is using the conventional mechanism audited step by step, if any level-one is examined Core is not resubmited by being then fed directly to project leader, and when audit can remember common audit opinion, to carry High review efficiency;The query statistic submodule can divide domain classification not count all project application books, while convenient for each The project that the responsible person of field project of all categories is checked at any time in oneself compass of competency makes a report on situation, including makes a report on, It reports, pending nuclear state, so as to general control annual statement situation;Project appraisal module include project grouping submodule, specially Family's library submodule, expert assign submodule, experts' evaluation submodule, safeguard review information submodule;Project is grouped submodule energy It is enough according to by including fields, declare guide specification direction including keyword and semantic grassroot project grouping, division group It is to find immediate grouping in established grouping first otherwise, if establishing new grouping without and if with this Purpose field keyword is named, and is only assigned to project in the field group best suited, without repeated packets, To reduce grouping workload and convenient for project is carried out expert's appointment;It is stored with to be evaluated in experts database submodule Expert source, and expert source can be constantly updated, and the source of expert includes project team member and state during receiving the project application Inside and outside moral character of outstanding experts, the information stored include expert's essential information, contact method, can carry out the time of evaluation, arrogate to oneself Long field, the first field which is good at according to expert are grouped, and each expert at least corresponding one arrogates to oneself Long field;Experts database submodule setting simultaneously is provided with history experts database, interim experts database, formal experts database and comes to expert source Multiple management is carried out, expert data is safeguarded in order to convenient;Expert assigns submodule to be grouped submodule with project respectively It is communicated to connect with experts database submodule, assigns submodule that can search project by expert and be grouped item all in submodule Mesh, and each project can be carried out random or manually be matched with expert in the art, which assigns submodule also With communication module, the expert for confirming that evaluation mail notification extremely obtains matching entries can be sent, if expert, which replys, confirms mail, Then expert assigns submodule that will correspond to expert in corresponding project point to experts' evaluation submodule, is evaluated by the expert, if Expert, which replys, cannot carry out evaluation mail, then assigns submodule to match itself and the domain expert again by expert, until the project It is matched with corresponding expert, the mailing address is the expert's mailing address stored in experts database submodule;Experts' evaluation submodule Block carries out project appraisal to make expert pass through the module, is provided with experts' evaluation login window submodule, is inputted in expert Account information log in after then it can be seen that wait for Project evaluation with he or she's identities match, the module can whole follow-up in real time and Record experts' evaluation progress;The module also supports the mode that meeting is evaluated simultaneously, after evaluation, is logged in by review organizer person The present invention enters experts' evaluation submodule typing review result;Experts' evaluation submodule supports the appraised index of evaluation table to make by oneself Justice, the automatic point counting of review result;Project appraisal module further includes having project information encryption submodule safely, should in evaluation course Module is run always, and the access safety and secrecy of the Entry Details ensured by using the mode of watermark and password Property, to prevent project information from revealing;The experts' evaluation submodule is additionally provided with expert and participates in evaluation and electing situation record sub module, can from Dynamic record experts' evaluation process and evaluation progress can be supported to check, review result processing, evaluation amount count;Safeguard evaluation Message sub-module includes to appraise details submodule through discussion and appraise submodule through discussion for record, appraises details submodule through discussion and is stored with the project application Information is appraised in book experts' evaluation through discussion, is checked to accrediting and validating agency;Submodule is appraised in generation record, which through discussion, can support the generation record in experts' evaluation Expert opinion, be included in can comment and on-site review during expert opinion, help to solve certain experts to using computer to have The problem of obstacle, is supported by accrediting and validating agency's generation record review comment;Charter management module with project verification approval module communicate mutually Connection, can receive all project papers by project verification, and the project paper by project verification can be found in the module, described Charter management module main body includes:Charter fills in notice submodule, charter generates submodule, charter fills in submodule Block relies on unit audit submodule, business department's review submodule, PDF generation submodules and charter to accept module, charter It fills in and notifies in submodule that the contact method for passing through the application is sent it can be seen that all by the project application book of project verification Mail notification applicant fills in charter;After receiving the project for agreeing to project verification, charter generates submodule submodule being capable of root The part substance in return, which is automatically extracted, according to the project paper received appoints to generate and store the corresponding initialization for thinking project Business book;The project leader for filling in charter logs in the present invention after notified mail and fills in submodule submodule into charter It only needs the place adjusted to needs to modify after block and filling in and submitting for charter can be completed, fill in and submit to improve Efficiency;Unit audit submodule is relied on to communicate interconnection with charter generation submodule and business department's review submodule respectively, It relies in unit audit submodule, relies on unit can be by relying on unit account to be logged in, it then can be to corresponding unit The charter that project leader submits is checked and is audited, and can underproof charter task inteilectual be returned to after audit At modifying at corresponding project leader's account in submodule, also the charter that audit passes through can be transmitted to business Department's review submodule, business department responsible person are transmitted across by business department's review submodule to relying on unit to audit submodule The electronic tasks book that the audit come passes through carries out review, and review is unqualified, retreats to charter and generates submodule by project leader It modifies, and the content changed, review can be needed not to have by audit opinion module writes in business department's review submodule Problem, which is then audited, to be passed through;For the Project charter that audit passes through, the PDF in charter management module generates submodule will be automatic The pdf document that Project charter is generated according to scheduled format is printed as papery charter for downloading;Charter accepts module use To notify applicant to download and submit paper material, after download finishes charter, applicant fills in finish and affix one's seal step by step on Business department is reported, is accepted on the net;If paper material is undesirable, charter retract by applicant in the module Modification.
3. a kind of application method of scientific research service integration management system according to claim 2, it is characterised in that project is commented Careful module further includes having appraised index that submodule is arranged, and includes newly-increased evaluation table submodule, overall setting under the submodule Submodule, form item setting submodule and evaluation table generic submodule increase evaluation table submodule newly evaluation table is arranged Standard relevant information, it is overall that submodule is set to change and preserve evaluation table information;Submodule is arranged to add in form item Form item, and edit and store customized content;Evaluation table generic submodule is being arranged and preserve evaluation table generic The page;Project after evaluation can be transmitted to project verification approval module, carry out audit processing by the approving person that sets up the project, the project verification is examined Batch module includes mainly project verification opinion submodule and project number submodule, and the project verification opinion submodule is filling in and store For the opinion of project after evaluation with as a result, simultaneously finally determining whether to set up the project, project verification result further includes the project verification amount of money, project verification batch Secondary and project verification responsible person;Project number submodule is to determining that the project paper of project verification is numbered, being convenient for management and inquiring.
4. a kind of application method of scientific research service integration management system according to claim 2, it is characterised in that charter Management module further includes having charter statistical query submodule and the submodule of established project inquiry, charter statistical query submodule Block includes not audit project paper module and audited project paper module, has audited project paper module and has audit project and passes through Module and audit project be not by module, to carry out statistic of classification to all items book, to grasp the feelings of project paper in real time Condition;The inquiry of the established project submodule can inquire all project papers set up the project.
5. a kind of application method of scientific research service integration management system according to claim 2, it is characterised in that the system Further include have Back Administration Module be the present invention operation and support platform, belong to the present invention basic function, can be according to need It asks and the function module including unit management module, technocracy module, authority management module is defined, the backstage Management module specifically includes following function module:
(1) institutional framework module:The institutional framework of corresponding management unit can be adjusted according to project particular situation is declared;
(2) user management module:The present invention is managed using user;
(3) authority management module:By different demarcations such as role, users, the permission to subsidizing in-house user be managed and Setting;
(4) business configuration module:To the present invention class of service safeguard, including Business Name, way to manage (item class, Subsidize class, reward class), business department, further, be each class of service with plan classification establish one-to-one relationship;
(5) workflow management module:Scientific and technological business overall process Workflow Management is provided, vocational work flow management and flow custom are provided Service, can be reconfigured by secondary development to modify to flow;
(6) log management module:The correlation log of management system, to inquire and record;
(7) version management module:The version for managing the present invention, to carry out Version Control;
(8) menu management module:The menu needed according to different user roles is managed configuration, is provided for different roles Different menus;
(9) system integration module:Various integrated Fabric Interface demands of the present invention;
(10) management module is declared:Management issue is declared in setting after logging in the present invention to business department personnel, includes to declare Business sections contact person, network date of declaration, return sample, declare guide, report of feasibility sample in business year.
6. a kind of application method of scientific research service integration management system according to any claim in claim 2-5, It is characterized in that project application book declare accept module operation workflow it is as follows:
(1) entry item application:Project leader fills in the project application submodule and submits project application table, item The content of mesh declaration form includes project essential information, project expection performance objective, project funds situation, required APPENDIX MATERIALSThe, branch It holds different classes of, has and different make a report on format;It is online fill in by special project, category to enter make a report on, into can when making a report on Into line discipline inspection, when making a report on, side can be selected to fill in frontier inspection and looked into, filled in after inspection passes through, selection generates the PDF for printing Formatted file;
(2) project application book is audited:Audit submodule carries out preliminary audit survey to the project application table that project leader has made a report on, The audit is reported by carrying out audit by each unit department from bottom to top, if audit at different levels does not pass through, is directly retracted It is resubmited to project leader;The process of audit is carried out by project one by one, and when audit can remember common audit opinion, with Improve review efficiency;Audit opinion can feed back to project leader through the invention;
(3) window personnel are accepted and accept paper material:Project application table after the approval, is auditing submodule by audit submodule The pdf document for printed material will be generated in block, while sending mail notification project leader and submitting papery application;
(4) all items are inquired:Each field responsible person of all categories logs in query statistic submodule, checks that oneself is administered at any time Project in range makes a report on situation, including makes a report on, and has reported, pending caseload, so as to general control year Shen Report situation.
7. a kind of application method of scientific research service integration management system according to any claim in claim 2-5, It is characterized in that the operation workflow that project application book review examines module is as follows:
(1) project is grouped:It module will be accepted is transmitted to by the project application table of audit in project grouping submodule declaring, led to It crosses the submodule and automatic grouping is completed to project application table, the administrative staff of the submodule also can be inappropriate to dividing automatically Project application table is grouped manually;
(2) expert assigns:Expert's appointment is carried out to grouped project application table, being randomly assigned expert to each project assigns The expert in field is corresponded in submodule, and assigns 3-7 alternative experts, then expert of the submodule to appointment is assigned by expert It carries out mail notification and confirms to participate in evaluating, can participate in and comment to then being replaced from alternative expert for evaluation can not be participated in Careful expert;
(3) setting evaluation time and evaluation table:Experts' evaluation table is set to each Project evaluation group, and sets each Project evaluation group Middle project opens the time of evaluation;
(4) expert is notified:Hair each expert of mail notification completes evaluation to experts' evaluation submodule again, can be by online The content for editing notice can also support that notice is repeated several times;
(5) experts' evaluation:Expert evaluates, according to evaluation to experts' evaluation submodule to being assigned to the project evaluated self The setting of table, one by one index marking are finally divided by the automatic synthesis that calculates of the invention;
(7) generation record expert opinion:To Dai Lu expert's meaning can not be carried out by this submodule from the expert of primary input review comment See, to complete opinion input;
(8) progress queries are evaluated:Situation logging modle is participated in evaluation and electing by expert to check self registering experts' evaluation process, simultaneously It can check evaluation progress, review result processing and evaluation amount statistics;
(9) review result is printed:It prints to the review result of projects, then is sent to appropriate department room on affixing one's seal and achieves.
8. a kind of application method of scientific research service integration management system according to claim 2, it is characterised in that project Shen Please book project verification approval module operation workflow it is as follows:
(1) opinion is subsidized in setting:In opinion submodule of setting up the project by way of excel, batch, which imports, subsidizes opinion, when importing It is corresponded to by accepting to number to be used as uniquely to identify, same record can be repeated as many times importing, for there is conflict can Automatic check is carried out to filter;
(2) setting project verification opinion:Business department logs in project verification opinion submodule and carries out project verification opinion modification, shape to quasi- Funded Projects At summarizing;
(3) it determines and subsidizes result:It is divided according to year, file is assigned according to the generation of the batch of project verification, finally enters and assigns code, Finished item is assigned;
(4) last setting of not setting up the project:According to the final result of project verification, the opinion that do not set up the project finally is assigned into submodule by opinion It feeds back to project leader and declares unit, be provided with after not setting up the project finally, additionally it is possible to the behaviour for supporting revocation not set up the project finally Make.
9. a kind of application method of scientific research service integration management system according to claim 2, it is characterised in that charter The operation workflow of management module is as follows:
(1) charter makes a report on notice:First pass through mail one by one project or according to project assign batch carry out notice project be responsible for People or carrier fill in charter, mail notification masterplate can online editing, and tracing task book makes a report on feedback, right It does not fill in and the account for sending charter carries out repeating to send notice, report is urged to make a report on;
(2) charter is filled in:Charter is generated by charter from submodule auto-initiation, and online repair can be rapidly completed Change and submit, after the completion of modification, there is modification record, can identify modification trace by comparing;
(3) unit is relied on to audit charter:Unit audit submodule is relied on to be filled out to what is received from charter generation submodule Complete charter is write to be checked and audited, after audit by underproof charter return to charter generate submodule in it is right It modifies at the project leader's account answered;
(4) business department's review:Business department responsible person is by business department's review submodule to relying on unit to audit submodule The electronic tasks book that the audit transmitted passes through carries out review, and review is unqualified, retreats to charter and generates submodule by project Responsible person modifies, and the content for needing to change by audit opinion module writes in business department's review submodule, review Out of question, audit passes through;When audit, charter and application can be compared;
(5) material notice is accepted:For the Project charter that audit passes through, the PDF in charter management module generates submodule Automatically the pdf document of Project charter will be generated according to scheduled format, papery charter is printed as downloading;The present invention simultaneously Automatic transmission accepts the notice of charter, meanwhile, business department can submit situation according to charter material at any time, notify again Accept charter;
(6) accept charter carrier and complete papery charter and print and affix one's seal step by step, report business department, carry out on the net by Reason;
(7) charter fills in progress chasing:After project is assigned, required to automatically form charter according to each service management, it is at different levels Administrative staff can inquire submodule tracing task book by charter statistical query submodule and established project and make a report on feelings Condition, including notify, fail to give notice, makes a report on, does not make a report on, and audit is not audited, the states such as accepts, do not accept.
10. a kind of application method of scientific research service integration management system according to any claim in claim 2-3, It is characterized in that the operation workflow of technocracy module is as follows:
(1) new expert is increased newly:When each project appraisal, when needing expert, on the one hand it can be obtained by experts database submodule On the other hand expert also can directly add in expert to Review Team, them is invited to become a member of experts database;
(2) expert is audited:Newly-increased new expert starts that for " interim evaluation expert ", experts database is logged in by expert library manager Submodule is audited, and after the approval, is become " formal expert ";
(3) expert info is safeguarded:Expert info is safeguarded by experts database submodule, relevant contact method is updated, comments Mark situation, familiar field, good faith management etc.;
(4) expert's Account Administration:The account number cipher of expert can be reset, then send mail and inform expert.
CN201810190183.6A 2018-03-08 2018-03-08 A kind of application method of scientific research service integration management system Pending CN108416571A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810190183.6A CN108416571A (en) 2018-03-08 2018-03-08 A kind of application method of scientific research service integration management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810190183.6A CN108416571A (en) 2018-03-08 2018-03-08 A kind of application method of scientific research service integration management system

Publications (1)

Publication Number Publication Date
CN108416571A true CN108416571A (en) 2018-08-17

Family

ID=63130424

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810190183.6A Pending CN108416571A (en) 2018-03-08 2018-03-08 A kind of application method of scientific research service integration management system

Country Status (1)

Country Link
CN (1) CN108416571A (en)

Cited By (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109299921A (en) * 2018-09-30 2019-02-01 深圳市英威腾电动汽车驱动技术有限公司 A kind of Technical Review data processing method and relevant apparatus
CN109615347A (en) * 2019-02-12 2019-04-12 齐鲁股权交易中心有限公司 It is a kind of to declare management method for the listed of regional equity market
CN109741031A (en) * 2018-12-29 2019-05-10 国家电网有限公司 A kind of project outlay management system
CN110223048A (en) * 2019-06-18 2019-09-10 湖南晖龙集团股份有限公司 Special fund declares comprehensive management platform system
CN110781151A (en) * 2019-10-31 2020-02-11 浪潮云信息技术有限公司 Method for sharing and removing duplication of engineering construction project declaration material
CN111401842A (en) * 2020-03-14 2020-07-10 中国铁道科学研究院集团有限公司铁道建筑研究所 Science and technology type enterprise project overall process management system
CN111709703A (en) * 2020-06-01 2020-09-25 上海金曲信息技术有限公司 Project review management system capable of accurately guiding project design
CN111754058A (en) * 2019-03-29 2020-10-09 上海忆尧信息技术有限公司 Project management system based on project audit
CN111950976A (en) * 2020-07-23 2020-11-17 深圳供电局有限公司 Engineering project review system and method
CN112308527A (en) * 2020-11-04 2021-02-02 内蒙古电力(集团)有限责任公司内蒙古电力科学研究院分公司 Management system for laboratory certification qualification
CN112330303A (en) * 2020-11-27 2021-02-05 同济大学建筑设计研究院(集团)有限公司 Intelligent project evaluation cooperative management system
CN112508544A (en) * 2021-02-08 2021-03-16 卡斯柯信号(北京)有限公司 Method, device, equipment and medium for obtaining project authorization based on online release order
CN112801629A (en) * 2021-02-04 2021-05-14 江西清能高科技术有限公司 Science and technology innovation platform project declaration method and system based on multi-level encryption
CN113011794A (en) * 2021-04-30 2021-06-22 重庆市能源投资集团科技有限责任公司 Scientific and technological project collaborative management platform
CN113077242A (en) * 2021-04-30 2021-07-06 重庆市能源投资集团科技有限责任公司 Science and technology project declaration management system
CN113159726A (en) * 2021-04-30 2021-07-23 重庆市能源投资集团科技有限责任公司 Science and technology project management and control system
CN113269443A (en) * 2021-05-27 2021-08-17 广东韶钢工程技术有限公司 Intellectual property management system and management method
CN113592439A (en) * 2021-07-14 2021-11-02 青岛海尔科技有限公司 Software project flow management system and method
CN113657871A (en) * 2021-08-31 2021-11-16 广东电网有限责任公司东莞供电局 Scientific and technological innovation project management system and method
CN113793135A (en) * 2021-11-17 2021-12-14 浙江省标准化研究院(金砖国家标准化(浙江)研究中心、浙江省物品编码中心) Project process management method and system
CN113793116A (en) * 2021-08-18 2021-12-14 四川大学华西医院 Medical database sharing platform and scientific research project management system
CN114500756A (en) * 2022-04-18 2022-05-13 湖南畅迅信息技术有限公司 Call center data processing method and system
CN114567703A (en) * 2022-04-13 2022-05-31 湖南畅迅信息技术有限公司 Government affair call center optimization method and system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080091283A1 (en) * 2006-10-17 2008-04-17 Bulent Balci Brownfield workflow and production forecast tool
CN104657806A (en) * 2013-11-25 2015-05-27 北京建筑大学 Scientific information management method and system
CN105447627A (en) * 2015-11-13 2016-03-30 国网宁夏电力公司经济技术研究院 Design review process management and control mode research method
CN106022711A (en) * 2016-05-10 2016-10-12 广州市寰讯信息科技有限公司 Education scientific research management method
CN107766457A (en) * 2017-09-27 2018-03-06 华能国际电力股份有限公司上海石洞口第二电厂 A kind of thermal power plant's operation management system and its task executing method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080091283A1 (en) * 2006-10-17 2008-04-17 Bulent Balci Brownfield workflow and production forecast tool
CN104657806A (en) * 2013-11-25 2015-05-27 北京建筑大学 Scientific information management method and system
CN105447627A (en) * 2015-11-13 2016-03-30 国网宁夏电力公司经济技术研究院 Design review process management and control mode research method
CN106022711A (en) * 2016-05-10 2016-10-12 广州市寰讯信息科技有限公司 Education scientific research management method
CN107766457A (en) * 2017-09-27 2018-03-06 华能国际电力股份有限公司上海石洞口第二电厂 A kind of thermal power plant's operation management system and its task executing method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李芳君: "临沂市科技项目申报评审系统的设计与实现", 《中国优秀硕士学位论文全文数据库 信息科技辑》 *
邵检江: "高职院校科研管理系统的分析、设计与实现", 《中国优秀硕士学位论文全文数据库 信息科技辑》 *

Cited By (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109299921A (en) * 2018-09-30 2019-02-01 深圳市英威腾电动汽车驱动技术有限公司 A kind of Technical Review data processing method and relevant apparatus
CN109741031A (en) * 2018-12-29 2019-05-10 国家电网有限公司 A kind of project outlay management system
CN109615347A (en) * 2019-02-12 2019-04-12 齐鲁股权交易中心有限公司 It is a kind of to declare management method for the listed of regional equity market
CN111754058A (en) * 2019-03-29 2020-10-09 上海忆尧信息技术有限公司 Project management system based on project audit
CN110223048A (en) * 2019-06-18 2019-09-10 湖南晖龙集团股份有限公司 Special fund declares comprehensive management platform system
CN110781151A (en) * 2019-10-31 2020-02-11 浪潮云信息技术有限公司 Method for sharing and removing duplication of engineering construction project declaration material
CN111401842A (en) * 2020-03-14 2020-07-10 中国铁道科学研究院集团有限公司铁道建筑研究所 Science and technology type enterprise project overall process management system
CN111709703A (en) * 2020-06-01 2020-09-25 上海金曲信息技术有限公司 Project review management system capable of accurately guiding project design
CN111950976A (en) * 2020-07-23 2020-11-17 深圳供电局有限公司 Engineering project review system and method
CN111950976B (en) * 2020-07-23 2024-01-05 深圳供电局有限公司 Project review system and method
CN112308527A (en) * 2020-11-04 2021-02-02 内蒙古电力(集团)有限责任公司内蒙古电力科学研究院分公司 Management system for laboratory certification qualification
CN112330303A (en) * 2020-11-27 2021-02-05 同济大学建筑设计研究院(集团)有限公司 Intelligent project evaluation cooperative management system
CN112801629A (en) * 2021-02-04 2021-05-14 江西清能高科技术有限公司 Science and technology innovation platform project declaration method and system based on multi-level encryption
CN112508544A (en) * 2021-02-08 2021-03-16 卡斯柯信号(北京)有限公司 Method, device, equipment and medium for obtaining project authorization based on online release order
CN113077242A (en) * 2021-04-30 2021-07-06 重庆市能源投资集团科技有限责任公司 Science and technology project declaration management system
CN113011794A (en) * 2021-04-30 2021-06-22 重庆市能源投资集团科技有限责任公司 Scientific and technological project collaborative management platform
CN113077242B (en) * 2021-04-30 2024-03-01 重庆市能源投资集团科技有限责任公司 Science and technology project reporting management system
CN113159726A (en) * 2021-04-30 2021-07-23 重庆市能源投资集团科技有限责任公司 Science and technology project management and control system
CN113269443A (en) * 2021-05-27 2021-08-17 广东韶钢工程技术有限公司 Intellectual property management system and management method
CN113269443B (en) * 2021-05-27 2024-02-02 广东韶钢工程技术有限公司 Intellectual property management system and method
CN113592439A (en) * 2021-07-14 2021-11-02 青岛海尔科技有限公司 Software project flow management system and method
CN113592439B (en) * 2021-07-14 2024-03-26 青岛海尔科技有限公司 Software project flow management system and method
CN113793116A (en) * 2021-08-18 2021-12-14 四川大学华西医院 Medical database sharing platform and scientific research project management system
CN113793116B (en) * 2021-08-18 2023-10-20 四川大学华西医院 Application method of medical database sharing platform and scientific research project management system
CN113657871A (en) * 2021-08-31 2021-11-16 广东电网有限责任公司东莞供电局 Scientific and technological innovation project management system and method
CN113793135A (en) * 2021-11-17 2021-12-14 浙江省标准化研究院(金砖国家标准化(浙江)研究中心、浙江省物品编码中心) Project process management method and system
CN114567703B (en) * 2022-04-13 2022-10-18 湖南畅迅信息技术有限公司 Government affair call center optimization method and system
CN114567703A (en) * 2022-04-13 2022-05-31 湖南畅迅信息技术有限公司 Government affair call center optimization method and system
CN114500756B (en) * 2022-04-18 2022-06-17 湖南畅迅信息技术有限公司 Call center data processing method and system
CN114500756A (en) * 2022-04-18 2022-05-13 湖南畅迅信息技术有限公司 Call center data processing method and system

Similar Documents

Publication Publication Date Title
CN108416571A (en) A kind of application method of scientific research service integration management system
CN108388996A (en) A kind of scientific research service integration management system
US8762357B2 (en) Enterprise security management system using hierarchical organization and multiple ownership structure
US8117261B2 (en) Method and apparatus for collecting and dissemination of information over a computer network
CN108647277A (en) A kind of mobile campus comprehensive service platform and its working method
CN103814374B (en) information management system and method
CN108364193A (en) A kind of construction project cost auditing method and system
CN109584035A (en) The overdue method of disposal of micro-credit and system
CN104408587A (en) Government project management information system
CN109377178A (en) Power grid technological transformation major repair project electronization review system and reviewing method
CN110795422B (en) Data service management method and system
CN109189844A (en) A kind of inspection examining report business management system
CN108053127A (en) A kind of electronic file management system
CN109816351A (en) A kind of gauge check business cooperation system and method based on cloud platform
CN111340454A (en) Enterprise homework certificate safety management method
CN109191062A (en) A kind of power distribution network Computer Aided Design and project management control system
CN108595405A (en) A kind of equipment Monitoring detailed rules and regulations or outline management method
CN108492089A (en) Investment in fixed assets Evaluation on Energy Saving reports digitized information system
CN111861117A (en) Musical instrument evaluation data sharing method and system based on alliance chain
CN103971224A (en) Signing method and system
KR102298777B1 (en) Integrated system including user interface
CN113421053A (en) Service management method, system and computer readable storage medium
CN113537915A (en) Project evaluation system, method and storage medium
TWI698768B (en) Csr data verification system with tamper-proof capability, related verification party subsystem, computer program product, and data verification method
Yan On “Sourcing decisions with stochastic supplier reliability and stochastic demand”

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180817

RJ01 Rejection of invention patent application after publication