CN101586330A - 预应力砼连续梁桥挂篮后退施工方法 - Google Patents

预应力砼连续梁桥挂篮后退施工方法 Download PDF

Info

Publication number
CN101586330A
CN101586330A CNA2008100478037A CN200810047803A CN101586330A CN 101586330 A CN101586330 A CN 101586330A CN A2008100478037 A CNA2008100478037 A CN A2008100478037A CN 200810047803 A CN200810047803 A CN 200810047803A CN 101586330 A CN101586330 A CN 101586330A
Authority
CN
China
Prior art keywords
bridge
truss
door frame
cradle
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2008100478037A
Other languages
English (en)
Other versions
CN101586330B (zh
Inventor
李明
罗长友
周晗
曾理飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 11th Bureau Group Co Ltd
First Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd filed Critical First Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Priority to CN2008100478037A priority Critical patent/CN101586330B/zh
Publication of CN101586330A publication Critical patent/CN101586330A/zh
Application granted granted Critical
Publication of CN101586330B publication Critical patent/CN101586330B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

一种预应力砼连续梁桥挂篮后退施工方法,其特征在于:在已施工混凝土预制桥梁桥面上安装轨道、门形桁架行走装置,在门形桁架行走装置中的顶横梁大于桥面宽度90cm-110cm;前底横梁和后底横梁必须延伸至外模外侧45cm-55cm,形成挂篮主桁架;在挂篮主桁架外侧加设外伸副门架,在混凝土预制桥梁合拢段施工完成后,用Φ32精轧螺纹钢在外伸副门架处箱梁外侧连接后底横梁,拆除后吊带;利用手动螺旋式千斤顶松动门架处和前顶横梁处精轧螺纹钢,使底模架脱离梁体;利用导链或卷扬机带动挂篮桁架,使挂篮在滑道上后退退到第一个现浇段;用导链或卷扬机下落底模和外模,拆除主桁架。

Description

预应力砼连续梁桥挂篮后退施工方法
所属技术领域
本发明涉及预应力砼连续梁桥挂篮悬臂现浇施工的方法,特别是涉及到跨铁路或公路的悬臂梁现浇完毕后挂篮后退施工的方法。
背景技术
现有的预应力砼连续梁桥主要采用挂篮悬臂浇筑施工,特别是在跨既有铁路线或跨高速公路的大跨径连续桥梁施工中,悬臂浇筑法施工已成为一种有效的施工手段,而挂篮是悬臂浇筑施工的主要设备。
挂篮是一个能沿梁顶滑动或滚动的承重结构,其锚固悬挂在已施工的前端梁段上,在挂篮上进行下一梁段的模板、钢筋、预应力管道的安装,混凝土灌浆和预应力张拉、灌浆作业完成一个阶段的循环后,挂篮前移并固定,进行下一节段的悬臂灌筑,如此循环至悬臂灌筑完成。但一般的悬臂施工只考虑到挂篮前行,在合拢施工后,用吊车等设备将挂篮系统卸落。而在既跨过铁路线或跨高速公路的施工中,由于受场地限制,同时还不能影响到既有铁路或公路的交通,就不能采用传统的吊车、卷扬机等设备来拆卸。故一般的挂篮设备在跨既有铁路线或高速公路等的桥梁施工中受到很大限制。致使建造桥梁施工工期延长,施工设备投入大,对国家交通运输和安全造很大的影响。
发明内容
本发明的目的针对在跨既有铁路线或跨高速公路的梁桥施工中,在悬臂施工中只考虑到挂篮前行,在合拢施工后,不能退回到第一个悬臂施工节段,安全有效的将挂篮系统卸落问题。提供一种在挂篮主桁架外侧加设副门架,实现在不中断既有铁路行车或高速公路通行的条件下能顺利安全、实用有效的施工方法,将挂篮退回到第一个悬臂施工节段,将机械设备安全顺利拆卸下来。
本发明解决其技术问题所采用的技术方案是:一种预应力砼连续梁桥挂篮后退施工方法,其特征在于施工步骤为:
1、一种预应力砼连续梁桥挂篮后退施工方法,其特征在于施工步骤为:
(1)、施工桥梁,混凝土强度要达到要求;
(2)、在已施工混凝土预制桥梁强度达到要求桥面上搭设门形桁架行走装置,门形桁架行走装置安装在预制桥梁上的轨道(7)滑槽内,根据桥梁的结构形式来设计门形桁架行走装置中的顶横梁(2)、且顶横梁(2)大于桥面宽度90cm-110cm;前底横梁(15)和后底横梁(20)必须延伸至外模外侧45cm-55cm,形成挂篮主桁架(1);
(3)、挂篮主桁架(1)外侧加设副门架(25),副门架使用槽钢、角钢按照尺寸进行加工、拼装焊接,在连接钢板上钻孔,使用高强螺栓(32)将挂篮连接在前顶横梁(2)上;
(4)、挂篮的前吊带(16)均位于箱梁的正前方,在进行合拢段施工前用Φ32精轧螺纹钢在箱梁外侧连接前顶横梁(2)、前底横梁(15),然后拆除前吊带(16);
(5)、混凝土预制桥梁合拢段施工完成后,用Φ32精轧螺纹钢在外伸副门架处箱梁外侧连接后底横梁(20),拆除后吊带(21);
(6)、利用手动螺旋式千斤顶松动门架处和前顶横梁处精轧螺纹钢,使底模架脱离梁体;
(7)、安装滑道(9),利用导链或卷扬机带动挂篮主桁架(1),移动挂篮后退;
(8)、在该混凝土预制桥梁施工完成后,在预制桥梁桥面上铺设轨道,用水平移动设备移动到下一个设计位置。
(9)、施工下一段桥梁。
本发明所述的一种预应力砼连续梁桥挂篮后退施工方法,在混凝土预制桥梁施工完成后,安装滑道(9)、松动外模(13)和底模(12),每边滑道各使用1个手动葫芦作牵引,手动葫芦一端与在箱梁顶预埋吊耳连接,另一端与挂篮桁架(1)上的竖向桁架上的吊耳连接,两边同时匀速拉动手动葫芦使得挂篮后退,后支座(6)沿轨道(7)后退滑行,前支座(11)以反钩板的形式在轨道顶板滑动,不需加设平衡重,直至退到第一个现浇段;利用导链或卷扬机下落底模(12)和外模(13),拆除主桁架(1)。
在上述步骤(2、3、4、5、6、)中,本发明的门形桁架行走装置由主桁架梁外侧加设副门架,桁架梁包括梁、斜牵拉梁、立柱或槽钢立柱连接而成,外侧加设副门架即制作外伸副门架;外伸副门架用槽钢、角钢制作成。
其中:1、主桁架分两片竖于箱梁腹板位置,其间用角钢组成平面联结系,桁架弦杆均采用2根槽钢组焊而成,槽钢端头采用节点板螺栓连接,桁架前端节点处设置一根顶横梁,顶横梁由2根I(工字钢)钢组焊而成。
2、走行系统分三角形桁架走行系统、底模外模走行系统及内模走行系统。主桁架走行系统:在两片桁架下的箱梁顶面铺设两根轨道(轨道用钢板组焊),轨道顶面放置前后支座,支座用螺栓与桁架节点板连接,前支座沿轨道滑行,后支座以反钩板的形式在轨道顶板滑动,不需加设平衡重,用两个手动葫芦牵引,挂篮主桁架即可向前移动,轨道长度按梁段长度划分制作,且备用一根倒用。
利用竖向预应力钢筋将轨道底板锚固,挂篮悬臂灌筑施工时每片桁架后端用精轧螺纹钢筋,将轨道下钢轨与桁架后结点锚定,使后支座钩板不受力。
3、底模、外模走行系统:脱模前用倒链将底模架吊在外模走行梁上,解除后吊带,脱模后随桁架一起向前走行,不需另配牵引动力。
4、内模走行系统:内模脱模后,内模架落在内模走行梁上,用人工推动,即可将内模移至下一梁段。
5、外模采用大块钢模板,用槽钢,角钢、钢板制作,在梁高范围内分成三块,以便随梁高变化调整,外侧模支撑在外模走行梁上,走行梁前端通过吊杆悬吊在桁架横梁上,后端通过吊杆悬吊在已浇好的箱梁顶板预留孔上,后吊杆与走行梁间设有后吊架,后吊架上装有滚动轴承,挂篮行走时,外侧模走行梁与外模一起沿后吊架滑行。
6、内模由内模架、模板、横、竖带及调整丝杆等组成。内模架吊在两根内模走行梁上,走行梁前端吊在桁架前横梁上,后端吊在已浇筑梁段预留孔上,内模架可沿走行梁滑行,模板全部采用组合钢模。
7、底模由底模平台和底模板组成,底模纵向梁采用槽钢组焊件,底模板模系用方木放在底模架上,方木上面铺厚木板,木板上设厚镀锌铁皮制作,底模宽度为箱梁底板宽度,灌注砼时,外侧模夹紧,以防漏浆。
8、挂篮最前端悬吊的张拉平台采用型钢及钢筋焊成,平台通过钢丝绳悬吊在桁架上,并用手动葫芦调整平台高度,以适应梁段高度变化及张拉的需要。
9、前底横梁为槽钢组焊件,前吊带由钢板做成,下端与底模架前底横梁销座连接,上端吊在主桁架横梁上,每根吊带用手动千斤顶及扁担梁梁调节底模标高。前吊杆由精轧螺纹钢组成,分别提吊内外模行走梁。
10、后底横梁采用槽钢组焊件,后吊带的作用在于将挂篮承受的一部分荷载传递给箱梁底板,使用材料为钢板,下端与底模架后底横梁销座连接,上端穿过箱梁底板预留孔,每根吊带用手动千斤顶及扁担梁梁支撑在已浇好的梁段底板上。
本发明的有益效果是:1、在不改变现有的预应力砼连续梁桥主要采用挂篮悬臂基础上,加长顶横梁、前底横梁和后底横梁,安设外伸副门架,安装吊带、梁销座、千斤顶,安装轨道,松动外模和底模,每边滑道使用手动葫芦作牵引,一端与在箱梁顶预埋吊耳连接,另一端与竖向主桁架上的吊耳连接,两边同时匀速拉动手动葫芦使得挂篮后退,后支座沿轨道后退滑行,前支座以反钩板的形式在轨道顶板滑动,不需加设平衡重,直至退回到第一个现浇段,利用导链或卷扬机下落底模和外模,拆除主桁架。
2、利用此施工方法在跨既有铁路线或高速公路施工时,能安全、迅速、有效的将挂篮系统移至第一段现浇段拆除,不会对既有线行车或现有道路交通造成影响。
附图说明
以下结合附图和实施例对本发明的施工方法作进一步的详细说明。
图1是本发明的挂篮施工状态图;
图2是图1的左视图;
图3为挂篮外伸副门架结构示意图;
图4是图3的左视图;
图5是门架结构示意图;
图6是挂篮后退时前吊带装置左视图;
图7是挂篮后退时前吊带装置结构示意图
图8是挂篮后退时后吊带装置左视图
图9是挂篮后退时后吊带装置结构示意图
图10是挂篮后退施工状态图
图11是图10的左视图
在图中1、挂篮主桁架,2、前顶横梁,3、后千斤顶(32吨手动千斤顶),4、后锚筋(φ32精轧螺纹钢筋),5、后钢锚扁担梁,6、后支座,7、轨道(轨道用钢板组焊),8、轨道锚筋(φ20精轧螺纹钢筋),9、走行梁,10、走行梁滑轮,11、前支座,12、底模装置(5mm钢模板和底模支架),13、外模装置(5mm整体钢模板和外模支架),14、内模装置(5mm钢模板和内模支架),15、前底横梁,16、前吊带(200×40mm16Mn钢板制作),17、钢垫枕,18、前千斤顶(32吨手动千斤顶),19、钢扁担梁,20、后底横梁,21、后吊带(200×40mm16Mn钢板制作),22、钢扁担梁,23、后千斤顶(32吨手动千斤顶),24、挂篮门架(横联),25、外伸副门架,26、吊筋(φ32精轧螺纹钢筋),27、外伸副门架扁担梁梁,28、外伸副门架竖向弦杆,29、外伸副门架底弦杆,30、外伸副门架连接板,31、外伸副门架斜拉杆,32、高强螺栓。
在图2、图4、图5、图11中的数字标号为中心线一侧标号,另一侧相对称相同部件标号省略。
具体实施方式
本发明的门形架桁架行走装置由主桁架梁外侧加设副门架,主桁架包括上下横梁梁、前后斜牵拉梁、立柱或槽钢立柱连接而成,外侧加设副门架即制作外伸副门架;外伸副门架由槽钢、角钢制作外伸副门架。
在本发明的施工设备中,主要包括加长顶横梁(2)、前底横梁(15)和后底横梁(20),安设外伸副门架(25),安装Φ32精轧螺纹钢转换底模连接系统(吊带、梁销座、千斤顶连接),挂篮后退等步骤。
在图3、图4、图5所示的实施利中,在制作外伸副门架(25)时,首先利用两根(12)槽钢并排焊接成外伸副门架扁担梁(27)组合,两根槽钢间距在40mm--50mm,外伸副门架扁担梁(27)顶部使用厚30mm钢板连接(33),外侧钢板上设有预留孔,预留孔作为安装吊耳用(φ32精轧螺纹钢筋);然后使用两根[12槽钢并排焊接组合成外伸副门架竖向弦杆(28)和外伸副门架底弦杆(29),外伸副门架竖向弦杆与外伸副门架扁担梁(27)垂直连接、外伸副门架底弦杆(29)组合与外伸副门架扁担梁垂直连接,利用两根∠10角钢与外伸副门架扁担梁(27)组合内侧角和外伸副门架竖向弦杆、外伸副门架底弦杆)组合交点连接、外伸副门架扁担梁(27)、外伸副门架竖向弦杆(28)、外伸副门架底弦杆(29)、外伸副门架斜拉杆(31)组合之间联结采用5mm厚钢板钻孔,使用螺栓连接。最后使用高强螺栓使外伸副门架扁担梁(27)与挂篮原门架横梁两端连接板(30)连接安装成外伸副门架,该处连接板采用两块10mm钢板钻孔制作而成。
在图6、图7所示的实施利中,在前顶横梁外侧用吊筋(26)连接在前底横梁上,吊筋采用Φ32精轧螺纹钢按照实际需要长度截取或者接长而成,吊筋接长采用定型套管连接两端精轧螺纹钢(图中未表示)。拆除前吊带。顶横梁上采用钢枕(17)作为支垫,钢枕(17)利用两根[12槽钢合拼焊接而成,钢枕(17)中心设有35mm预留通孔,吊耳从钢枕预留孔中心和顶横梁外侧预留孔穿过,顶端采用高强螺栓(32)固定。吊耳与前底横梁(15)采用高强螺栓(32)直接固定,前底横梁预留孔底部要采用10mm钢板加强处理。
在图8、图9所示的实施利中,用吊筋(26)在外伸副门架处和箱梁外侧连接后底横梁。吊筋(26)采用Φ32精轧螺纹钢按照实际需要长度截取或者接长而成,吊筋(26)接长采用定型套管连接两端精轧螺纹钢(图中未表示)。拆除后吊带。吊筋(26)与外伸副门架(24)采用高强螺栓(32)直接固定,吊筋(26)与后底横梁(20)采用高强螺栓(32)直接固定,后底横梁预留孔底部要采用10mm钢板加强处理。
在图10、图11所示的实施利中,通过上述门形架桁架行走装置,主桁架梁、外侧加设副门架,来实现预应力砼连续梁桥挂篮后退退回到第一个现浇段,其施工步骤为:
第一步:在桥梁的第一个现浇段混凝土强度要达到设计要求后,进入下一步:
第二步:在已施工混凝土预制桥梁强度达到要求的桥面上搭设门形桁架行走装置,门形桁架行走装置安装在预制桥梁上的轨道(7)滑槽内,根据桥梁的结构形式来设计门形桁架行走装置中的顶横梁(2)、且顶横梁(2)大于桥面宽度90cm-110cm;前底横梁(15)和后底横梁(20)必须延伸至外模外侧45cm-55cm,形成挂篮主桁架(1);
第三步:在挂篮主桁架(1)外侧加设副门架(25),副门架使用槽钢、角钢按照尺寸进行加工、拼装焊接,在连接钢板上钻孔,使用高强螺栓(32)将挂篮连接在前顶横梁(2)上;
第四步:在挂篮的前吊带均位于箱梁的正前方,在进行合拢段施工前用Φ32精轧螺纹钢在箱梁外侧连接前顶横梁(2)、前底横梁(15),然后拆除前吊带;
第五步:混凝土预制桥梁合拢段施工完成后,用Φ32精轧螺纹钢在外伸副门架处箱梁外侧连接后底横梁(20),拆除后吊带(21);
第六步:利用手动螺旋式千斤顶松动门架处和前顶横梁(2)处精轧螺纹钢,使底模装置(12)脱离梁体;
第七步:安装滑道,利用导链或卷扬机带动挂篮主桁架(1),移动挂篮后退;
第八步:在该混凝土预制桥梁施工完成后,在一预制桥梁桥面上铺设轨道(7),用水平移动设备移动到下一个设计位置,施工下一段桥梁桥;
第九步:安装滑道(9),松动外模(13)和底模(12),每边滑道各使用1个手动葫芦作牵引,手动葫芦一端与在箱梁顶预埋吊耳连接,另一端与挂篮桁架(1)上的竖向桁架上的吊耳连接,两边同时匀速拉动手动葫芦使得挂篮后退,后支座(6)沿轨道(7)后退滑行,前支座(11)以反钩板的形式在轨道顶板滑动,不需加设平衡重,直至退到第一个现浇段;利用导链或卷扬机下落底模(12)和外模(13),拆除主桁架(1)。

Claims (2)

1、一种预应力砼连续梁桥挂篮后退施工方法,其特征在于施工步骤为:
(1)、施工桥梁的混凝土强度要达到设计要求;
(2)、在已施工混凝土预制桥梁强度达到要求桥面上搭设门形桁架行走装置,门形桁架行走装置安装在预制桥梁上的轨道(7)滑槽内,根据桥梁的结构形式来设计门形桁架行走装置中的顶横梁(2)、且顶横梁(2)大于桥面宽度90cm-110cm;前底横梁(15)和后底横梁(20)必须延伸至外模外侧45cm-55cm,形成挂篮主桁架(1);
(3)、挂篮主桁架(1)外侧加设副门架(25),副门架使用槽钢、角钢按照尺寸进行加工、拼装焊接,在连接钢板上钻孔,使用高强度螺栓(32)将挂篮连接在前顶横梁(2)上;
(4)、挂篮的前吊带(16)均位于箱梁的正前方,在进行合拢段施工前用Φ32精轧螺纹钢在箱梁外侧连接顶横梁(2)、前底横梁(15),然后拆除前吊带(16);
(5)、混凝土预制桥梁合拢段施工完成后,用Φ32精轧螺纹钢在外伸副门架(25)处箱梁外侧连接后底横梁(20),拆除后吊带(21);
(6)、利用手动螺旋式千斤顶松动门架处和前顶横梁(2)处精轧螺纹钢,使底模架脱离梁体;
(7)、安装滑道,松动外模(13)和底模(12),利用导链或卷扬机带动挂篮桁架(1),移动挂篮后退;
(8)、在该混凝土预制桥梁施工完成后,在预制桥梁桥面上铺设轨道,用水平移动设备移动到下一个设计位置;
(9)、施工下一段桥梁。
2、根据权利要求1所述的一种预应力砼连续梁桥挂篮后退施工方法,其特征在于:安装轨道(7),松动外模(13)和底模(12),每边滑道各使用1个手动葫芦作牵引,手动葫芦一端与在箱梁顶预埋吊筋连接,另一端与挂篮桁架(1)上的竖向桁架上的吊耳连接,两边同时匀速拉动手动葫芦使得挂篮后退,后支座(6)沿轨道(7)后退滑行,前支座(11)以反钩板的形式在轨道顶板滑动,不需加设平衡重,直至退到第一个现浇段;利用导链或卷扬机下落底模(12)和外模(13),拆除主桁架(1)。
CN2008100478037A 2008-05-22 2008-05-22 预应力砼连续梁桥挂篮后退施工方法 Active CN101586330B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008100478037A CN101586330B (zh) 2008-05-22 2008-05-22 预应力砼连续梁桥挂篮后退施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008100478037A CN101586330B (zh) 2008-05-22 2008-05-22 预应力砼连续梁桥挂篮后退施工方法

Publications (2)

Publication Number Publication Date
CN101586330A true CN101586330A (zh) 2009-11-25
CN101586330B CN101586330B (zh) 2011-01-26

Family

ID=41370739

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008100478037A Active CN101586330B (zh) 2008-05-22 2008-05-22 预应力砼连续梁桥挂篮后退施工方法

Country Status (1)

Country Link
CN (1) CN101586330B (zh)

Cited By (32)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102102342A (zh) * 2010-12-30 2011-06-22 广东省航盛建设集团有限公司 菱形挂篮整体结构式后上横梁
CN102330414A (zh) * 2011-08-09 2012-01-25 中铁十二局集团第二工程有限公司 大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法
CN102493363A (zh) * 2011-12-12 2012-06-13 中铁大桥局股份有限公司 连续梁0号块快速施工方法
CN102535338A (zh) * 2010-12-23 2012-07-04 上海市基础工程有限公司 挂篮悬吊侧模板
CN103132460A (zh) * 2011-11-28 2013-06-05 上海市基础工程有限公司 悬臂浇筑梁钢管混凝土临时固结系统
ES2424774A1 (es) * 2012-04-02 2013-10-08 Ulma C Y E, S. Coop Estructura desplazable adaptada para soportar en voladizo un encofrado de un tramo nuevo de puente
CN103374883A (zh) * 2012-04-13 2013-10-30 中铁十局集团第五工程有限公司 一种挂篮行走牵引装置
CN103614971A (zh) * 2013-12-11 2014-03-05 山东省路桥集团有限公司 门式吊装施工挂篮设备与配置方法
CN103924531A (zh) * 2014-04-28 2014-07-16 中建三局集团有限公司 一种超宽幅前支点挂篮
CN104631343A (zh) * 2015-02-15 2015-05-20 河海大学 自走行菱形销结桁架式挂篮结构及挂篮走行和施工方法
CN104947594A (zh) * 2015-07-03 2015-09-30 金少平 一种菱形建筑架
CN104963297A (zh) * 2015-07-03 2015-10-07 金少平 新型菱形建筑架
EP2787122A4 (en) * 2011-11-30 2015-10-14 Rubrica Ingenieria Y Arquitectura Sl TROLLEY FOR CONSTRUCTION OF CONSTRUCTION WORKS
CN105040593A (zh) * 2015-07-03 2015-11-11 金少平 桥梁用菱形建筑架
CN106284101A (zh) * 2015-07-03 2017-01-04 金少平 一种新型菱形建筑架
CN106592430A (zh) * 2016-11-14 2017-04-26 中建三局基础设施工程有限公司 一种挂篮悬臂现浇冬季施工方法
CN106592962A (zh) * 2016-12-24 2017-04-26 中铁十八局集团有限公司 一种大高差、大跨度劲性骨架外包混凝土模板施工方法及施工设备
CN106812069A (zh) * 2017-03-01 2017-06-09 杭州市交通工程集团有限公司 山区高支墩挂篮的底拦下放装置及方法
CN107447666A (zh) * 2017-08-22 2017-12-08 河南省公路工程局集团有限公司 一种单索面斜拉桥挂篮拆除方法
CN107747399A (zh) * 2017-11-10 2018-03-02 湖南联智智能科技有限公司 一种挂篮行走系统及其工作方法
CN108411795A (zh) * 2018-03-16 2018-08-17 中铁二十五局集团第三工程有限公司 一种曲线连续梁挂篮长距离一次快速回退方法
CN108951561A (zh) * 2018-09-21 2018-12-07 长江勘测规划设计研究有限责任公司 利用浮力回收水利水电启闭机的方法及配套使用的启闭机
CN109610323A (zh) * 2018-12-07 2019-04-12 江西集银科技有限公司 一种桥梁悬臂施工挂篮设备悬吊系统
CN109734003A (zh) * 2019-01-31 2019-05-10 中铁广州工程局集团桥梁工程有限公司 一种悬拼吊机和基于其的下河吊机前端悬臂安装方法
CN110878527A (zh) * 2019-11-21 2020-03-13 上海建工四建集团有限公司 用于大跨径连续箱梁合龙的同步提升系统和方法
CN111188284A (zh) * 2020-01-08 2020-05-22 中铁十六局集团路桥工程有限公司 一种用于悬臂施工时挂篮的锚固方法
CN112609577A (zh) * 2020-11-23 2021-04-06 中国水利水电第四工程局有限公司 一种连续梁节段预制拼装方法
CN112900285A (zh) * 2021-03-10 2021-06-04 中铁二十局集团第六工程有限公司 一种邻近既有线箱梁预应力束张拉方法
CN114000439A (zh) * 2021-11-23 2022-02-01 江苏省交通工程集团有限公司 一种自锚式挂篮吊带装置
CN114032792A (zh) * 2021-12-06 2022-02-11 中国核工业华兴建设有限公司 一种悬臂现浇梁预应力施工作业平台及其制作方法
CN115262423A (zh) * 2022-08-03 2022-11-01 中国十九冶集团有限公司 桥梁挂篮施工方法
CN115771836A (zh) * 2022-11-30 2023-03-10 中铁四局集团有限公司 一种悬臂造桥机吊运设备

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104947596A (zh) * 2015-07-03 2015-09-30 金少平 菱形建筑架

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1123861A (zh) * 1995-08-28 1996-06-05 铁道部大桥工程局 预应力混凝土斜拉桥短平台复合型牵索挂篮施工工艺
CN100465377C (zh) * 2006-12-27 2009-03-04 重庆交通大学 底板索水平布置预应力混凝土变截面箱梁桥及其施工方法
CN101148861A (zh) * 2007-06-06 2008-03-26 宏润建设集团股份有限公司 贝雷桁架型挂篮及其组拼方法

Cited By (45)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535338A (zh) * 2010-12-23 2012-07-04 上海市基础工程有限公司 挂篮悬吊侧模板
CN102102342A (zh) * 2010-12-30 2011-06-22 广东省航盛建设集团有限公司 菱形挂篮整体结构式后上横梁
CN102330414A (zh) * 2011-08-09 2012-01-25 中铁十二局集团第二工程有限公司 大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法
CN102330414B (zh) * 2011-08-09 2013-04-03 中铁十二局集团第二工程有限公司 大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法
CN103132460A (zh) * 2011-11-28 2013-06-05 上海市基础工程有限公司 悬臂浇筑梁钢管混凝土临时固结系统
EP2787122A4 (en) * 2011-11-30 2015-10-14 Rubrica Ingenieria Y Arquitectura Sl TROLLEY FOR CONSTRUCTION OF CONSTRUCTION WORKS
CN102493363B (zh) * 2011-12-12 2014-04-16 中铁大桥局股份有限公司 连续梁0号块快速施工方法
CN102493363A (zh) * 2011-12-12 2012-06-13 中铁大桥局股份有限公司 连续梁0号块快速施工方法
ES2424774A1 (es) * 2012-04-02 2013-10-08 Ulma C Y E, S. Coop Estructura desplazable adaptada para soportar en voladizo un encofrado de un tramo nuevo de puente
CN103374883A (zh) * 2012-04-13 2013-10-30 中铁十局集团第五工程有限公司 一种挂篮行走牵引装置
CN103374883B (zh) * 2012-04-13 2016-05-25 中铁十局集团第五工程有限公司 一种挂篮行走牵引装置
CN103614971A (zh) * 2013-12-11 2014-03-05 山东省路桥集团有限公司 门式吊装施工挂篮设备与配置方法
CN103614971B (zh) * 2013-12-11 2016-01-06 山东省路桥集团有限公司 门式吊装施工挂篮设备与配置方法
CN103924531A (zh) * 2014-04-28 2014-07-16 中建三局集团有限公司 一种超宽幅前支点挂篮
CN104631343A (zh) * 2015-02-15 2015-05-20 河海大学 自走行菱形销结桁架式挂篮结构及挂篮走行和施工方法
CN104631343B (zh) * 2015-02-15 2016-08-24 河海大学 自走行菱形销结桁架式挂篮结构及挂篮走行和施工方法
CN104963297A (zh) * 2015-07-03 2015-10-07 金少平 新型菱形建筑架
CN105040593A (zh) * 2015-07-03 2015-11-11 金少平 桥梁用菱形建筑架
CN104947594A (zh) * 2015-07-03 2015-09-30 金少平 一种菱形建筑架
CN106284101A (zh) * 2015-07-03 2017-01-04 金少平 一种新型菱形建筑架
CN106592430A (zh) * 2016-11-14 2017-04-26 中建三局基础设施工程有限公司 一种挂篮悬臂现浇冬季施工方法
CN106592962A (zh) * 2016-12-24 2017-04-26 中铁十八局集团有限公司 一种大高差、大跨度劲性骨架外包混凝土模板施工方法及施工设备
CN106812069A (zh) * 2017-03-01 2017-06-09 杭州市交通工程集团有限公司 山区高支墩挂篮的底拦下放装置及方法
CN106812069B (zh) * 2017-03-01 2019-04-12 杭州市交通工程集团有限公司 山区高支墩挂篮的底篮下放装置及方法
CN107447666A (zh) * 2017-08-22 2017-12-08 河南省公路工程局集团有限公司 一种单索面斜拉桥挂篮拆除方法
CN107447666B (zh) * 2017-08-22 2019-06-18 河南省公路工程局集团有限公司 一种单索面斜拉桥挂篮拆除方法
CN107747399A (zh) * 2017-11-10 2018-03-02 湖南联智智能科技有限公司 一种挂篮行走系统及其工作方法
CN107747399B (zh) * 2017-11-10 2023-06-02 湖南联智智能科技有限公司 一种挂篮行走系统及其工作方法
CN108411795A (zh) * 2018-03-16 2018-08-17 中铁二十五局集团第三工程有限公司 一种曲线连续梁挂篮长距离一次快速回退方法
CN108951561A (zh) * 2018-09-21 2018-12-07 长江勘测规划设计研究有限责任公司 利用浮力回收水利水电启闭机的方法及配套使用的启闭机
CN108951561B (zh) * 2018-09-21 2023-04-25 长江勘测规划设计研究有限责任公司 利用浮力回收水利水电启闭机的方法及配套使用的启闭机
CN109610323A (zh) * 2018-12-07 2019-04-12 江西集银科技有限公司 一种桥梁悬臂施工挂篮设备悬吊系统
CN109734003A (zh) * 2019-01-31 2019-05-10 中铁广州工程局集团桥梁工程有限公司 一种悬拼吊机和基于其的下河吊机前端悬臂安装方法
CN110878527A (zh) * 2019-11-21 2020-03-13 上海建工四建集团有限公司 用于大跨径连续箱梁合龙的同步提升系统和方法
CN111188284A (zh) * 2020-01-08 2020-05-22 中铁十六局集团路桥工程有限公司 一种用于悬臂施工时挂篮的锚固方法
CN111188284B (zh) * 2020-01-08 2021-07-16 中铁十六局集团路桥工程有限公司 一种用于悬臂施工时挂篮的锚固方法
CN112609577A (zh) * 2020-11-23 2021-04-06 中国水利水电第四工程局有限公司 一种连续梁节段预制拼装方法
CN112900285A (zh) * 2021-03-10 2021-06-04 中铁二十局集团第六工程有限公司 一种邻近既有线箱梁预应力束张拉方法
CN114000439B (zh) * 2021-11-23 2022-08-05 江苏省交通工程集团有限公司 一种自锚式挂篮吊带装置
CN114000439A (zh) * 2021-11-23 2022-02-01 江苏省交通工程集团有限公司 一种自锚式挂篮吊带装置
CN114032792A (zh) * 2021-12-06 2022-02-11 中国核工业华兴建设有限公司 一种悬臂现浇梁预应力施工作业平台及其制作方法
CN114032792B (zh) * 2021-12-06 2023-11-24 中国核工业华兴建设有限公司 一种悬臂现浇梁预应力施工作业平台及其制作方法
CN115262423A (zh) * 2022-08-03 2022-11-01 中国十九冶集团有限公司 桥梁挂篮施工方法
CN115771836A (zh) * 2022-11-30 2023-03-10 中铁四局集团有限公司 一种悬臂造桥机吊运设备
CN115771836B (zh) * 2022-11-30 2023-06-30 中铁四局集团有限公司 一种悬臂造桥机吊运设备

Also Published As

Publication number Publication date
CN101586330B (zh) 2011-01-26

Similar Documents

Publication Publication Date Title
CN101586330B (zh) 预应力砼连续梁桥挂篮后退施工方法
CN105421249B (zh) 一种拖吊结合式挂篮结构及施工方法
CN107059640B (zh) 用于预制节段梁逐跨施工的架桥机及其施工方法
CN104631343B (zh) 自走行菱形销结桁架式挂篮结构及挂篮走行和施工方法
CN101781878B (zh) 独塔无背索斜拉桥主塔整体提升模板及其提升施工方法
CN201908664U (zh) 移动栈桥仰拱模板台车
CN201003145Y (zh) 上行自行式移动模架
CN108004927B (zh) 双肢三角挂篮及大跨度连续刚构桥悬臂梁段施工方法
CN202936736U (zh) 一种斜拉桥组合梁施工桥面吊机
CN102094392B (zh) 桥梁施工中的下承式挂篮及其应用
CN109267490B (zh) 一种长导梁式移动模架及其施工方法
CN205223872U (zh) 一种拖吊结合式新型挂篮结构
CN105568870B (zh) 用于跨线桥施工的三角挂篮法悬浇装置及其施工方法
CN110528402A (zh) 一种超宽箱梁多桁片组合挂篮的施工方法
CN107905124B (zh) 一种对称式刚构连续梁施工工艺
CN110700119B (zh) 一种组装式贝雷梁挂篮上走行系统的设计工法
CN107905111B (zh) 一种刚构连续梁边跨施工工艺
CN109653105A (zh) 箱梁桥悬臂施工挂篮主桁系统及其使用方法
CN109267491B (zh) 一种移动模架及其施工方法
CN110820602A (zh) 一种单台节段箱梁架桥机及其操作方法
CN106758872A (zh) 波形钢腹板scc工法随车回旋吊移动挂篮及利用其施工的方法
CN210288140U (zh) 一种简易的预制桥面板吊装台车
CN203393639U (zh) 一种用于路桥施工的菱形自锚式挂篮
CN105019357B (zh) 一种拱桥敞口格构式钢梁上异形预制桥面板的安装方法
CN207987749U (zh) 骑索式桥面吊机

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA RAILROAD 11 BUREAU GROUP CO. LTD.

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20110426

Address after: 441104 Xiangfan city in Hubei Province town of Xiangyang District Zhangwan Aviation Road No. 43

Co-patentee after: China Railroad 11 Bureau Group Co., Ltd.

Patentee after: No.1 Engineering Co., Ltd. Of China Railway Construction 11 Bureau Group

Address before: 441104 Xiangfan city in Hubei Province town of Xiangyang District Zhangwan Aviation Road No. 43

Patentee before: No.1 Engineering Co., Ltd. Of China Railway Construction 11 Bureau Group