CN115262423A - 桥梁挂篮施工方法 - Google Patents
桥梁挂篮施工方法 Download PDFInfo
- Publication number
- CN115262423A CN115262423A CN202210926250.2A CN202210926250A CN115262423A CN 115262423 A CN115262423 A CN 115262423A CN 202210926250 A CN202210926250 A CN 202210926250A CN 115262423 A CN115262423 A CN 115262423A
- Authority
- CN
- China
- Prior art keywords
- bridge
- construction
- hanging basket
- cross beam
- cradle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 75
- 238000009415 formwork Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
- E01D21/10—Cantilevered erection
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明涉及公路交通施工装备领域,尤其是一种可以有效实现驱动各锁轨件沿轨道运动达到同步,从而有效保证外模移动的成形质量的桥梁挂篮施工方法,包括如下步骤:a、首先,完成桥墩柱和横梁的施工,并在横梁和桥墩柱之间施工首段桥梁单元即桥梁段;b、在横梁顶面靠近两侧边布置步进推进装置,步进推进装置的后座与桥轨可靠连接,桥轨固定在施工完的桥梁面,挂篮施工装置设置于桥轨上;c、将挂篮施工装置驱动到指定的施工位置,并进行桥梁段的砼浇灌作业;d、在完成砼浇灌作业后,松开挂篮施工装置至脱模状态,启动步进推进装置并将挂篮施工装置整体驱动到下一个施工段后,再次进行砼浇灌作业。本发明尤其适用于桥梁施工领域。
Description
技术领域
本发明涉及公路交通施工装备领域,尤其是一种桥梁挂篮施工方法。
背景技术
桥梁挂篮施工通常在每条行走轨道上安装多个千斤顶,带领桥梁挂篮系统各外模移动,当各组千斤顶行走不一致时,会影响各外模移动的成形质量。而内模安装推移装置带领桥梁挂篮系统各内模移动的方案,成本较高,工序繁琐。而桥梁挂篮用倒链升降效率低。此方法一直困扰着施工单位。
发明专利CNCN216586214U公开了一种波形钢腹板桥梁挂篮施工用的行走系统,包括挂篮本体以及设置在桥体上的多个轨道,桁架设置在挂篮本体的底部,桁架上设置有前支座和后支座,前支座和后支座与轨道可滑动地连接;锁轨件滑动连接在轨道上;驱动机构包括驱动横梁和驱动单元,驱动横梁与各锁轨件相连接,驱动单元可驱动各锁轨件沿轨道同步运动;顶升装置设置在锁轨件和前支座之间,液压装置与各顶升装置均相连接,各顶升装置可接受液压装置驱动以同步工作。本发明提供的行走系统,通过锁轨件、驱动机构和液压装置相互配合,可实现连续性驱动挂篮进行行走直至达到合适位置,如此可降低施工人员的工作量,提升工作效率。该驱动单元驱动各锁轨件沿轨道运动达到同步难度较大。
发明内容
本发明所要解决的技术问题是提供一种可以有效实现驱动各锁轨件沿轨道运动达到同步,从而有效保证外模移动的成形质量的桥梁挂篮施工方法。
本发明解决其技术问题所采用的技术方案是:桥梁挂篮施工方法,包括如下步骤:a、首先,完成桥墩柱和横梁的施工,并在横梁和桥墩柱之间施工首段桥梁单元即桥梁段;b、在横梁顶面靠近两侧边布置步进推进装置,步进推进装置的后座与桥轨可靠连接,桥轨固定在施工完的桥梁面,挂篮施工装置设置于桥轨上;c、将挂篮施工装置驱动到指定的施工位置,并进行桥梁段的砼浇灌作业;d、在完成砼浇灌作业后,松开挂篮施工装置至脱模状态,启动步进推进装置并将挂篮施工装置整体驱动到下一个施工段后,再次进行砼浇灌作业。
进一步的是,步骤b中,步进推进装置为步进式千斤顶。
进一步的是,步骤b中,挂篮施工装置均通过步进推进装置同步驱动。
进一步的是,步骤b中,挂篮施工装置包括外模滑梁以及与外模滑梁连接的外模板。
进一步的是,挂篮施工装置包括后横梁吊杆,后横梁吊杆一端与后端工作平台,后横梁吊杆另一端与升降装置连接。
进一步的是,所述升降装置与后横梁吊杆连接处设置有限位卡。
本发明的有益效果是:本方案解决了常规桥梁挂篮施工通常在每条行走轨道上安装多个千斤顶行走不一致时造成的质量问题,以及由此导致的内模安装推移装置成本较高的问题。在此基础上,通过相应的驱动装置即可实现桥梁挂篮准确升降移模。该方案在桥梁施工领域,能达到施工操作简便、质量高、工期短、费用低、安全性高的目的。本发明尤其适用于桥梁施工领域。
附图说明
图1是本发明的桥梁结构成形的立面图。
图2是本发明的桥梁挂篮施工的立面图。
图3是本发明的桥梁挂篮施工的剖面图。
图中标记为:横梁1、步进式千斤顶2、后锚3、后座4、外模滑梁5、后端工作平台6、吊梁7、外模板8、前张拉平台9、桥梁段10、前下横梁11、内模板12、后下横梁13、后吊杆14、后横梁吊杆15、桥墩柱16、埋管17、施工大棚18、升降装置19、限位卡20、桥梁面21、桥轨22。
具体实施方式
下面结合附图对本发明进一步说明。
如图1、图2、图3所示的桥梁挂篮施工方法,包括如下步骤:a、首先,完成桥墩柱16和横梁1的施工,并在横梁1和桥墩柱16之间施工首段桥梁单元即桥梁段10;b、在横梁1顶面靠近两侧边布置步进推进装置,步进推进装置的后座4与桥轨22可靠连接,桥轨固定在施工完的桥梁面21,挂篮施工装置设置于桥轨22上;c、将挂篮施工装置驱动到指定的施工位置,并进行桥梁段10的砼浇灌作业;d、在完成砼浇灌作业后,松开挂篮施工装置至脱模状态,启动步进推进装置并将挂篮施工装置整体驱动到下一个施工段后,再次进行砼浇灌作业。
就具体的布置而言,为了便于步进推进装置的驱动推进,优选所述桥轨22设置于桥梁段10顶部的桥梁面21上。一般的,优选所述步进推进装置为步进式千斤顶2。其中为了步进式千斤顶2在实际推进时的稳定性,防止出现脱落,优选所述步进式千斤顶2的后座4与桥轨22连接。增设的施工大棚18在雨雪及高温天气可以确保施工正常进行。
就具体的挂篮施工装置而言,为了便于进行相应的施工操作,优选挂篮施工装置包括外模滑梁5以及与外模滑梁5连接的外模板8。优选挂篮施工装置包括后横梁吊杆15,后横梁吊杆15一端与后端工作平台6,后横梁吊杆15另一端与升降装置19连接。其中,优选升降装置19与后横梁吊杆15连接处设置有限位卡20,从而保证桥梁挂篮下降的高度处于可控范围内。优选挂篮施工装置包括吊梁7,所述吊梁7分别与前下横梁11和后下横梁13连接。
在实际施工时,具体的操作步骤可以选择如下:一、首先,完成桥墩柱16施工,并在横梁1和桥墩柱16之间施工首段桥梁单元即桥梁段10;二、在横梁1顶面靠近两侧边布置步进式千斤顶2,步进式千斤顶后座4与桥轨22可靠连接,桥轨固定在施工完的桥梁面21;三、挂篮施工装置的外模板8与外模滑梁5应连接牢固,后横梁吊杆15与后横梁吊杆15顶部的后横梁连接牢固。吊梁7上的千斤顶组控制前下横梁11和后下横梁13的标高,同时也控制内模板12的标高。后吊杆14与后下横梁13可靠连接;四、内模板12顶部设置有埋管17,前张拉平台9用于钢筋束张拉用,完成桥梁砼内的工序后,进行桥梁段10砼浇灌;五、砼浇灌到达指定状态后,松开后锚3,并松开埋管17的吊杆,调整升降装置19使桥梁挂篮至脱模状态,限位卡20控制桥梁挂篮下降的高度;启动步进式千斤顶2推移吊篮系统整体移到下一个施工段。重复以上施工完成整个桥梁段施工。
Claims (6)
1.桥梁挂篮施工方法,其特征在于,包括如下步骤:
a、首先,完成桥墩柱(16)和横梁(1)的施工,并在横梁(1)和桥墩柱(16)之间施工首段桥梁单元即桥梁段(10);
b、在横梁(1)顶面靠近两侧边布置步进推进装置,步进推进装置的后座(4)与桥轨(22)可靠连接,桥轨固定在施工完的桥梁面(21),挂篮施工装置设置于桥轨(22)上;
c、将挂篮施工装置驱动到指定的施工位置,并进行桥梁段(10)的砼浇灌作业;
d、在完成砼浇灌作业后,松开挂篮施工装置至脱模状态,启动步进推进装置并将挂篮施工装置整体驱动到下一个施工段后,再次进行砼浇灌作业。
2.如权利要求1所述的桥梁挂篮施工方法,其特征在于:步骤b中,步进推进装置为步进式千斤顶(2)。
3.如权利要求1或2所述的桥梁挂篮施工方法,其特征在于:步骤b中,挂篮施工装置均通过步进推进装置同步驱动。
4.如权利要求1或2所述的桥梁挂篮施工方法,其特征在于:步骤b中,挂篮施工装置包括外模滑梁(5)以及与外模滑梁(5)连接的外模板(8)。
5.如权利要求4所述的桥梁挂篮施工方法,其特征在于:挂篮施工装置包括后横梁吊杆(15),后横梁吊杆(15)一端与后端工作平台(6),后横梁吊杆(15)另一端与升降装置(19)连接。
6.如权利要求5所述的桥梁挂篮施工方法,其特征在于:所述升降装置(19)与后横梁吊杆(15)连接处设置有限位卡(20)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210926250.2A CN115262423A (zh) | 2022-08-03 | 2022-08-03 | 桥梁挂篮施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210926250.2A CN115262423A (zh) | 2022-08-03 | 2022-08-03 | 桥梁挂篮施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN115262423A true CN115262423A (zh) | 2022-11-01 |
Family
ID=83750040
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210926250.2A Pending CN115262423A (zh) | 2022-08-03 | 2022-08-03 | 桥梁挂篮施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115262423A (zh) |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10219626A (ja) * | 1997-02-13 | 1998-08-18 | Taisei Corp | 橋梁の架設用移動式型枠支保工装置とその移動施工方法 |
CN101586330A (zh) * | 2008-05-22 | 2009-11-25 | 中铁十一局集团第一工程有限公司 | 预应力砼连续梁桥挂篮后退施工方法 |
KR20150134694A (ko) * | 2014-05-22 | 2015-12-02 | 김남열 | 폼 트래블러 및 이를 이용한 교량의 시공방법 |
CN207609168U (zh) * | 2017-11-10 | 2018-07-13 | 湖南联智智能科技有限公司 | 一种挂篮行走系统 |
CN208815424U (zh) * | 2018-08-10 | 2019-05-03 | 中铁十二局集团第二工程有限公司 | 一种桥梁下行式挂篮 |
CN110453613A (zh) * | 2019-07-30 | 2019-11-15 | 湖南交通国际经济工程合作有限公司 | 一种大跨径梁桥箱梁全断面一次悬浇施工方法 |
WO2021022608A1 (zh) * | 2019-08-05 | 2021-02-11 | 山东恒堃机械有限公司 | 一种过混凝土连续梁免拆装移动模架 |
CN112900287A (zh) * | 2021-03-11 | 2021-06-04 | 中铁十六局集团第五工程有限公司 | 悬臂灌注造桥机 |
CN215052242U (zh) * | 2021-03-16 | 2021-12-07 | 中交一公局第五工程有限公司 | 一种连续刚构桥梁施工的挂篮液压行走系统 |
CN114164772A (zh) * | 2021-12-07 | 2022-03-11 | 甘肃建投临夏建设管理有限公司 | 一种高架桥悬臂浇筑施工用菱形挂篮及安装方法 |
CN216586214U (zh) * | 2021-12-15 | 2022-05-24 | 中交一公局第五工程有限公司 | 波形钢腹板桥梁挂篮施工用的行走系统 |
CN114775428A (zh) * | 2022-03-30 | 2022-07-22 | 苏武 | 智能控制电动葫芦移动挂蓝的行走装置及施工方法 |
-
2022
- 2022-08-03 CN CN202210926250.2A patent/CN115262423A/zh active Pending
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10219626A (ja) * | 1997-02-13 | 1998-08-18 | Taisei Corp | 橋梁の架設用移動式型枠支保工装置とその移動施工方法 |
CN101586330A (zh) * | 2008-05-22 | 2009-11-25 | 中铁十一局集团第一工程有限公司 | 预应力砼连续梁桥挂篮后退施工方法 |
KR20150134694A (ko) * | 2014-05-22 | 2015-12-02 | 김남열 | 폼 트래블러 및 이를 이용한 교량의 시공방법 |
CN207609168U (zh) * | 2017-11-10 | 2018-07-13 | 湖南联智智能科技有限公司 | 一种挂篮行走系统 |
CN208815424U (zh) * | 2018-08-10 | 2019-05-03 | 中铁十二局集团第二工程有限公司 | 一种桥梁下行式挂篮 |
CN110453613A (zh) * | 2019-07-30 | 2019-11-15 | 湖南交通国际经济工程合作有限公司 | 一种大跨径梁桥箱梁全断面一次悬浇施工方法 |
WO2021022608A1 (zh) * | 2019-08-05 | 2021-02-11 | 山东恒堃机械有限公司 | 一种过混凝土连续梁免拆装移动模架 |
CN112900287A (zh) * | 2021-03-11 | 2021-06-04 | 中铁十六局集团第五工程有限公司 | 悬臂灌注造桥机 |
CN215052242U (zh) * | 2021-03-16 | 2021-12-07 | 中交一公局第五工程有限公司 | 一种连续刚构桥梁施工的挂篮液压行走系统 |
CN114164772A (zh) * | 2021-12-07 | 2022-03-11 | 甘肃建投临夏建设管理有限公司 | 一种高架桥悬臂浇筑施工用菱形挂篮及安装方法 |
CN216586214U (zh) * | 2021-12-15 | 2022-05-24 | 中交一公局第五工程有限公司 | 波形钢腹板桥梁挂篮施工用的行走系统 |
CN114775428A (zh) * | 2022-03-30 | 2022-07-22 | 苏武 | 智能控制电动葫芦移动挂蓝的行走装置及施工方法 |
Non-Patent Citations (2)
Title |
---|
朱俊;: "论桥梁挂篮施工技术方案与要点", 中外建筑, no. 03, 1 March 2020 (2020-03-01) * |
王磊;: "铁路桥梁悬臂浇筑挂篮新型行走装置的设计与应用", 建筑机械, no. 10, 9 October 2018 (2018-10-09) * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109267490B (zh) | 一种长导梁式移动模架及其施工方法 | |
CN105155423A (zh) | 用于连续箱梁施工的上行式移动模架 | |
CN113882279B (zh) | 能自行走和调节的混凝土连续梁悬臂浇筑施工装备及工艺 | |
CN109267491B (zh) | 一种移动模架及其施工方法 | |
CN107227690B (zh) | 一种上行式移动模架中支腿结构 | |
CN109629439B (zh) | 一种独塔斜拉桥施工方法 | |
CN106593469A (zh) | 一种用于仰拱施工的台车 | |
CN113370384A (zh) | 固定液压模板移动台车工装及t梁预制施工工艺 | |
CN114657884B (zh) | 一种桥台拼装分段推进的下行式移动模架施工方法 | |
CN109139050B (zh) | 自行一体式隧道仰拱装置 | |
CN110468748B (zh) | 一种涵洞台车 | |
JP3804883B2 (ja) | コンクリート高構造物構築装置およびコンクリート斜柱の構築方法 | |
CN109457619A (zh) | 一种用于混凝土主梁现浇施工的复合型多功能移动支架 | |
CN109355983A (zh) | 一种城市轨道的无轨施工方法 | |
CN112177046A (zh) | 一种明洞衬砌外模台车 | |
CN115262423A (zh) | 桥梁挂篮施工方法 | |
CN217870057U (zh) | 桥梁挂篮施工结构 | |
CN216765625U (zh) | 一种用于双柱桥墩施工的连体式液压爬模结构 | |
CN114016424B (zh) | 适用于小角度斜交跨线桥施工的自行式平台及方法 | |
CN215057422U (zh) | 一种移动式栈桥仰拱滑模台车 | |
JP3885554B2 (ja) | 橋梁の押出し工法 | |
CN108557640B (zh) | 现浇箱梁钢筋骨架整体吊装设备及吊装方法 | |
CN212335790U (zh) | 一种大悬臂盖梁施工台车 | |
CN113882286A (zh) | 桥梁拆建一体机及其过跨方法、桥梁拆除方法及新建方法 | |
CN109083023B (zh) | 采用劲性骨架的连续刚构桥及其施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |