CN106592430A - 一种挂篮悬臂现浇冬季施工方法 - Google Patents
一种挂篮悬臂现浇冬季施工方法 Download PDFInfo
- Publication number
- CN106592430A CN106592430A CN201611000135.3A CN201611000135A CN106592430A CN 106592430 A CN106592430 A CN 106592430A CN 201611000135 A CN201611000135 A CN 201611000135A CN 106592430 A CN106592430 A CN 106592430A
- Authority
- CN
- China
- Prior art keywords
- temperature
- hanging basket
- cast
- concrete
- extruded sheet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
- E01D21/10—Cantilevered erection
Abstract
本发明公开了一种挂篮悬臂现浇冬季施工方法,其具体步骤如下:(1)挂篮模板的外表面粘贴阻燃挤塑板;(2)阻燃挤塑板外侧布设热水循环管道;(3)通过将钢筋点焊在模板纵横肋上固定挤塑板和热水循环管道;(4)悬浇节段整体采用帆布包裹;(5)电热风炮对梁体模板和钢筋加热;(6)布置测温点;(7)浇筑节段混凝土;(8)薄膜及棉被覆盖新浇梁段混凝土;(9)箱梁T构两悬臂端采用防火岩棉板封堵;(10)在箱室内采用煤火炉升温,同时采用电蒸汽发生器向箱室内输送蒸汽;(11)张拉压浆。本发明方法步骤简单、施工简便、施工质量易于保证;使用效果好且实用价值高。
Description
技术领域
本发明涉及桥梁现浇箱梁施工技术领域,具体是一种挂篮悬臂现浇冬季施工方法。
背景技术
根据规范,当室外昼夜日平均气温连续5天稳定低于5℃时,即进入冬期施工。因为冬期挂篮悬浇施工的箱梁是一个位于高空不断移动的空间结构,混凝土运输和浇筑更困难,施工风险更大,投入更高。因此,需设计一种步骤简单、施工简便、经济性好、安全性高、施工质量易于保证的方法来保障冬期箱梁挂篮悬臂现浇的施工。
发明内容
本发明的目的在于提供一种综合了蓄热法、蒸汽加热法和暖棚加热法三种养护方式的挂篮悬臂现浇冬季施工方法。
为实现上述目的,本发明提供如下技术方案:
一种挂篮悬臂现浇冬季施工方法,其具体步骤如下:
(1)挂篮模板翼缘板、侧模和底模的外表面粘贴阻燃挤塑板:阻燃挤塑板嵌入模板纵横肋之间;
(2)阻燃挤塑板外侧布设热水循环管道:在阻燃挤塑板外侧以25cm间距布设热水循环管道,通过热水锅炉输送热水进行循环加热,保持模板外侧空间的温度;
(3)通过将钢筋点焊在模板纵横肋上固定挤塑板和热水循环管道:采用Φ8钢筋与模板纵横肋点焊固定;
(4)悬浇节段整体采用帆布包裹:悬浇节段模板外表固定好挤塑板和热水循环管道后,整体采用帆布包裹,保证箱梁节段的整体挡风效果,减少和外界空气的对流,确保新浇梁段的蓄热保温效果;
(5)电热风炮对梁体模板和钢筋加热:确保混凝土在入模前模板、钢筋温度不低于5℃,此外,对上一节段悬臂端截面已浇筑混凝土表面用热水进行浇淋,保证该结合部温度在5℃以上;
(6)布置测温点:混凝土浇筑前在箱梁内设置温度传感器作为测温点,测温点布置在保温最差部位,以备养护时对梁体混凝土进行温度监测,即翼缘板左右侧各设置1个,顶板中设置1个,底板中设置1个,左右腹板处各设置2个,一组共计8个测温点,均采用测温线,腹板及底板测温线统一引到箱室内,顶板测温线由顶板引出;
(7)浇筑节段混凝土:混凝土浇筑选择在白天温度较高时段进行,有利于混凝土入模温度的控制;
(8)薄膜及棉被覆盖新浇梁段混凝土:针对箱梁翼缘板处结构较薄容易散热受冻,在翼缘板顶面先覆盖一层塑料薄膜,再在其上加装电热毯,然后覆盖棉被,以加强翼缘板部位保温;
(9)箱梁T构两悬臂端采用防火岩棉板封堵;
(10)在箱室内采用煤火炉升温,同时采用电蒸汽发生器向箱室内输送蒸汽:共计4台煤火炉,每天煤火炉顶放置一个不锈钢水桶,起到加湿和升温作用;浇筑后箱室内持续加热和蒸养,保证温度的同时用蒸汽提供湿度,确保箱内温度不低于5℃,并保持箱室内温度基本恒定;为了防止煤气中毒和二氧化碳浓度过高加速混凝土的碳化,务必把火炉的排气管引出箱室外;
(11)张拉压浆:挂篮节段混凝土强度达到设计要求后进行张拉压浆,压浆拌合用水采用搅拌站供应热水,温度在30℃左右,保证浆体温度在15℃以上,同时防止温度过高对浆体造成影响,压浆过程中和压浆后48h内,结构混凝土的温度不得低于5℃,保温应延续至灌浆后、且强度达到25MPa后才能停止,孔道灌浆应在正温下进行,其强度达到25MPa前,不得受冻,为了防止箱梁混凝土灌浆后被冻坏的质量事故发生,特采用耐低温压浆料进行压浆试块试验,以确保压浆质量。
作为本发明进一步的方案:步骤(1)中所述挤塑板为B1级阻燃挤塑板。
作为本发明进一步的方案:步骤(2)中所述的热水循环管道采用直径20mm地暖管。
作为本发明进一步的方案:步骤(3)中所述采用Φ8钢筋点焊固定挤塑板时,应避免电火花触碰到挤塑板。
作为本发明进一步的方案:步骤(4)中所述帆布为含棉帆布,帆布周边间距50cm各设绑扎带1条,绑扎带应远离帆布边缘30cm,以确保相邻帆布绑扎后重叠不漏风;悬臂端端部帆布与顺桥向自翼缘板两侧垂落帆布绑扎后形成封闭的保温空间;为防止大风将帆布刮走或刮坏,帆布内侧绑扎带应与挂篮模板绑扎牢固。
作为本发明进一步的方案:步骤(5)中所述电热风炮为30kW工业热风机。
作为本发明进一步的方案:步骤(6)中所述温度传感器监测的温度有:外界气温、箱室内气温、混凝土出罐温度、混凝土入模温度以及箱梁实体内各观测点温度。
作为本发明进一步的方案:步骤(7)中所述混凝土入模温度为5~30℃;浇筑时间安排在白天上午9:00至下午16:00;浇筑前,要清扫钢筋和模板上的残留物,对于冰雪的处理,切勿直接将冰雪融化,因为直接融化的水在低温下会再次冻结。
作为本发明进一步的方案:步骤(10)中所述电蒸汽发生器的功率为24kW。
与现有技术相比,本发明的有益效果是:
1、方法步骤简单、施工简便、施工质量易于保证;
2、使用效果好且实用价值高。
附图说明
图1为本发明对所施工现浇箱梁冬期施工方法流程框图。
具体实施方式
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
请参阅图1,本发明实施例中,一种挂篮悬臂现浇冬季施工方法,其具体步骤如下:
(1)挂篮模板翼缘板、侧模和底模的外表面粘贴B1级阻燃挤塑板:阻燃挤塑板嵌入模板纵横肋之间;
(2)阻燃挤塑板外侧布设热水循环管道:在阻燃挤塑板外侧以25cm间距布设热水循环管道,通过热水锅炉输送热水进行循环加热,保持模板外侧空间的温度;所述的热水循环管道采用直径20mm地暖管;
(3)通过将钢筋点焊在模板纵横肋上固定挤塑板和热水循环管道:采用Φ8钢筋与模板纵横肋点焊固定;所述采用Φ8钢筋点焊固定挤塑板时,应避免电火花触碰到挤塑板;
(4)悬浇节段整体采用帆布包裹:悬浇节段模板外表固定好挤塑板和热水循环管道后,整体采用帆布包裹,保证箱梁节段的整体挡风效果,减少和外界空气的对流,确保新浇梁段的蓄热保温效果;所述帆布为含棉帆布,帆布周边间距50cm各设绑扎带1条,绑扎带应远离帆布边缘30cm,以确保相邻帆布绑扎后重叠不漏风;悬臂端端部帆布与顺桥向自翼缘板两侧垂落帆布绑扎后形成封闭的保温空间;为防止大风将帆布刮走或刮坏,帆布内侧绑扎带应与挂篮模板绑扎牢固;
(5)电热风炮对梁体模板和钢筋加热:确保混凝土在入模前模板、钢筋温度不低于5℃,此外,对上一节段悬臂端截面已浇筑混凝土表面用热水进行浇淋,保证该结合部温度在5℃以上;所述电热风炮为30kW工业热风机;
(6)布置测温点:混凝土浇筑前在箱梁内设置温度传感器作为测温点,测温点布置在保温最差部位,以备养护时对梁体混凝土进行温度监测,即翼缘板左右侧各设置1个,顶板中设置1个,底板中设置1个,左右腹板处各设置2个,一组共计8个测温点,均采用测温线,腹板及底板测温线统一引到箱室内,顶板测温线由顶板引出;所述温度传感器监测的温度有:外界气温、箱室内气温、混凝土出罐温度、混凝土入模温度以及箱梁实体内各观测点温度;
(7)浇筑节段混凝土:混凝土浇筑选择在白天温度较高时段进行,有利于混凝土入模温度的控制,所述混凝土入模温度为5~30℃;浇筑时间安排在白天上午9:00至下午16:00;浇筑前,要清扫钢筋和模板上的残留物,对于冰雪的处理,切勿直接将冰雪融化,因为直接融化的水在低温下会再次冻结;
(8)薄膜及棉被覆盖新浇梁段混凝土:针对箱梁翼缘板处结构较薄容易散热受冻,在翼缘板顶面先覆盖一层塑料薄膜,再在其上加装电热毯,然后覆盖棉被,以加强翼缘板部位保温;
(9)箱梁T构两悬臂端采用防火岩棉板封堵;
(10)在箱室内采用煤火炉升温,同时采用电蒸汽发生器向箱室内输送蒸汽:共计4台煤火炉,每天煤火炉顶放置一个不锈钢水桶,起到加湿和升温作用;浇筑后箱室内持续加热和蒸养,保证温度的同时用蒸汽提供湿度,确保箱内温度不低于5℃,并保持箱室内温度基本恒定;为了防止煤气中毒和二氧化碳浓度过高加速混凝土的碳化,务必把火炉的排气管引出箱室外;所述电蒸汽发生器的功率为24kW;
(11)张拉压浆:挂篮节段混凝土强度达到设计要求后进行张拉压浆,压浆拌合用水采用搅拌站供应热水,温度在30℃左右,保证浆体温度在15℃以上,同时防止温度过高对浆体造成影响,压浆过程中和压浆后48h内,结构混凝土的温度不得低于5℃,保温应延续至灌浆后、且强度达到25MPa后才能停止,孔道灌浆应在正温下进行,其强度达到25MPa前,不得受冻,为了防止箱梁混凝土灌浆后被冻坏的质量事故发生,特采用耐低温压浆料进行压浆试块试验,以确保压浆质量。
对于本领域技术人员而言,显然本发明不限于上述示范性实施例的细节,而且在不背离本发明的精神或基本特征的情况下,能够以其他的具体形式实现本发明。因此,无论从哪一点来看,均应将实施例看作是示范性的,而且是非限制性的,本发明的范围由所附权利要求而不是上述说明限定,因此旨在将落在权利要求的等同要件的含义和范围内的所有变化囊括在本发明内。不应将权利要求中的任何附图标记视为限制所涉及的权利要求。
此外,应当理解,虽然本说明书按照实施方式加以描述,但并非每个实施方式仅包含一个独立的技术方案,说明书的这种叙述方式仅仅是为清楚起见,本领域技术人员应当将说明书作为一个整体,各实施例中的技术方案也可以经适当组合,形成本领域技术人员可以理解的其他实施方式。
Claims (9)
1.一种挂篮悬臂现浇冬季施工方法,其特征在于,其具体步骤如下:
(1)挂篮模板翼缘板、侧模和底模的外表面粘贴阻燃挤塑板:阻燃挤塑板嵌入模板纵横肋之间;
(2)阻燃挤塑板外侧布设热水循环管道:在阻燃挤塑板外侧以25cm间距布设热水循环管道,通过热水锅炉输送热水进行循环加热,保持模板外侧空间的温度;
(3)通过将钢筋点焊在模板纵横肋上固定挤塑板和热水循环管道:采用Φ8钢筋与模板纵横肋点焊固定;
(4)悬浇节段整体采用帆布包裹:悬浇节段模板外表固定好挤塑板和热水循环管道后,整体采用帆布包裹,保证箱梁节段的整体挡风效果,减少和外界空气的对流,确保新浇梁段的蓄热保温效果;
(5)电热风炮对梁体模板和钢筋加热:确保混凝土在入模前模板、钢筋温度不低于5℃,此外,对上一节段悬臂端截面已浇筑混凝土表面用热水进行浇淋,保证该结合部温度在5℃以上;
(6)布置测温点:混凝土浇筑前在箱梁内设置温度传感器作为测温点,测温点布置在保温最差部位,以备养护时对梁体混凝土进行温度监测,即翼缘板左右侧各设置1个,顶板中设置1个,底板中设置1个,左右腹板处各设置2个,一组共计8个测温点,均采用测温线,腹板及底板测温线统一引到箱室内,顶板测温线由顶板引出;
(7)浇筑节段混凝土:混凝土浇筑选择在白天温度较高时段进行,有利于混凝土入模温度的控制;
(8)薄膜及棉被覆盖新浇梁段混凝土:针对箱梁翼缘板处结构较薄容易散热受冻,在翼缘板顶面先覆盖一层塑料薄膜,再在其上加装电热毯,然后覆盖棉被,以加强翼缘板部位保温;
(9)箱梁T构两悬臂端采用防火岩棉板封堵;
(10)在箱室内采用煤火炉升温,同时采用电蒸汽发生器向箱室内输送蒸汽:共计4台煤火炉,每天煤火炉顶放置一个不锈钢水桶,起到加湿和升温作用;浇筑后箱室内持续加热和蒸养,保证温度的同时用蒸汽提供湿度,确保箱内温度不低于5℃,并保持箱室内温度基本恒定;为了防止煤气中毒和二氧化碳浓度过高加速混凝土的碳化,务必把火炉的排气管引出箱室外;
(11)张拉压浆:挂篮节段混凝土强度达到设计要求后进行张拉压浆,压浆拌合用水采用搅拌站供应热水,温度在30℃左右,保证浆体温度在15℃以上,同时防止温度过高对浆体造成影响,压浆过程中和压浆后48h内,结构混凝土的温度不得低于5℃,保温应延续至灌浆后、且强度达到25MPa后才能停止,孔道灌浆应在正温下进行,其强度达到25MPa前,不得受冻,为了防止箱梁混凝土灌浆后被冻坏的质量事故发生,特采用耐低温压浆料进行压浆试块试验,以确保压浆质量。
2.根据权利要求1所述的一种挂篮悬臂现浇冬季施工方法,其特征在于,步骤(1)中所述挤塑板为B1级阻燃挤塑板。
3.根据权利要求1所述的一种挂篮悬臂现浇冬季施工方法,其特征在于,步骤(2)中所述的热水循环管道采用直径20mm地暖管。
4.根据权利要求1所述的一种挂篮悬臂现浇冬季施工方法,其特征在于,步骤(3)中所述采用Φ8钢筋点焊固定挤塑板时,应避免电火花触碰到挤塑板。
5.根据权利要求1所述的一种挂篮悬臂现浇冬季施工方法,其特征在于,步骤(4)中所述帆布为含棉帆布,帆布周边间距50cm各设绑扎带1条,绑扎带应远离帆布边缘30cm,以确保相邻帆布绑扎后重叠不漏风;悬臂端端部帆布与顺桥向自翼缘板两侧垂落帆布绑扎后形成封闭的保温空间;为防止大风将帆布刮走或刮坏,帆布内侧绑扎带应与挂篮模板绑扎牢固。
6.根据权利要求1所述的一种挂篮悬臂现浇冬季施工方法,其特征在于,步骤(5)中所述电热风炮为30kW工业热风机。
7.根据权利要求1所述的一种挂篮悬臂现浇冬季施工方法,其特征在于,步骤(6)中所述温度传感器监测的温度有:外界气温、箱室内气温、混凝土出罐温度、混凝土入模温度以及箱梁实体内各观测点温度。
8.根据权利要求1所述的一种挂篮悬臂现浇冬季施工方法,其特征在于,步骤(7)中所述混凝土入模温度为5~30℃;浇筑时间安排在白天上午9:00至下午16:00;浇筑前,要清扫钢筋和模板上的残留物,对于冰雪的处理,切勿直接将冰雪融化,因为直接融化的水在低温下会再次冻结。
9.根据权利要求1所述的一种挂篮悬臂现浇冬季施工方法,其特征在于,步骤(10)中所述电蒸汽发生器的功率为24kW。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611000135.3A CN106592430B (zh) | 2016-11-14 | 2016-11-14 | 一种挂篮悬臂现浇冬季施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611000135.3A CN106592430B (zh) | 2016-11-14 | 2016-11-14 | 一种挂篮悬臂现浇冬季施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106592430A true CN106592430A (zh) | 2017-04-26 |
CN106592430B CN106592430B (zh) | 2018-04-13 |
Family
ID=58590011
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611000135.3A Active CN106592430B (zh) | 2016-11-14 | 2016-11-14 | 一种挂篮悬臂现浇冬季施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106592430B (zh) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107503297A (zh) * | 2017-09-12 | 2017-12-22 | 中建八局第三建设有限公司 | 挂篮防护与梁体蒸汽养护一体化养护棚及其施工方法 |
CN107721331A (zh) * | 2017-10-19 | 2018-02-23 | 清华大学 | 严寒地区混凝土伸缩缝施工水化进程保障方法 |
CN108018779A (zh) * | 2017-11-30 | 2018-05-11 | 苏交科集团股份有限公司 | 一种低温大温差环境下混凝土施工方法 |
CN111519540A (zh) * | 2020-04-29 | 2020-08-11 | 中国水利水电第八工程局有限公司 | 一种连续梁悬臂保温施工装置 |
CN111927125A (zh) * | 2020-06-19 | 2020-11-13 | 中铁隧道集团二处有限公司 | 一种混凝土冬季养护施工方法 |
CN112854748A (zh) * | 2021-03-10 | 2021-05-28 | 中铁二十局集团第六工程有限公司 | 一种悬浇箱梁冬季施工用养护方法 |
CN113027156A (zh) * | 2021-03-10 | 2021-06-25 | 中铁二十局集团第六工程有限公司 | 一种箱梁冬季施工用养护系统 |
CN114525741A (zh) * | 2022-02-19 | 2022-05-24 | 中铁二十局集团第六工程有限公司 | 邻近既有线悬臂梁的梁体保温施工方法 |
CN114657898A (zh) * | 2022-02-19 | 2022-06-24 | 中铁二十局集团第六工程有限公司 | 高寒地区悬浇梁施工方法 |
CN114657897A (zh) * | 2022-02-19 | 2022-06-24 | 中铁二十局集团第六工程有限公司 | 高寒地区悬浇梁保温施工方法 |
CN114673159A (zh) * | 2022-05-07 | 2022-06-28 | 华能鹤岗发电有限公司 | 一种用于冬季施工的混凝土保温施工方法 |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20020036206A (ko) * | 2000-11-08 | 2002-05-16 | 장문삼 | 동절기 교량슬래브 양생장치 |
JP2003247211A (ja) * | 2002-02-25 | 2003-09-05 | Shintouyou Gosei Kk | 剥落防止コンクリート構造物およびコンクリート構造物の剥落防止方法 |
CN101545246A (zh) * | 2009-05-05 | 2009-09-30 | 中国铁道科学研究院铁道建筑研究所 | 一种支座灌浆材料冬季施工方法 |
CN101586330A (zh) * | 2008-05-22 | 2009-11-25 | 中铁十一局集团第一工程有限公司 | 预应力砼连续梁桥挂篮后退施工方法 |
CN201835519U (zh) * | 2010-06-10 | 2011-05-18 | 中国建筑土木建设有限公司 | 铁路客运专线支座灌浆保温箱 |
CN102108678A (zh) * | 2011-01-18 | 2011-06-29 | 龙建路桥股份有限公司 | 高空冬季施工成套装置及方法 |
CN102162301A (zh) * | 2011-03-04 | 2011-08-24 | 葛洲坝集团第五工程有限公司 | 冬季混凝土施工保温保湿防护方法及装置 |
CN103171041A (zh) * | 2013-04-09 | 2013-06-26 | 中建三局第二建设工程有限责任公司 | 一种冬季混凝土电加热带辅助养护方法 |
CN204023410U (zh) * | 2014-06-23 | 2014-12-17 | 中铁十二局集团有限公司 | 冬季桥面铺装用保温施工装置 |
CN104675118A (zh) * | 2015-02-11 | 2015-06-03 | 刘明瑞 | 一种混凝土冬季施工电加热工艺 |
CN205259609U (zh) * | 2015-11-16 | 2016-05-25 | 中铁十四局集团有限公司 | 冬季混凝土施工智能温控模板加热保温系统 |
CN205385618U (zh) * | 2016-01-05 | 2016-07-13 | 山东科技大学 | 一种土木工程施工专用电热毯 |
-
2016
- 2016-11-14 CN CN201611000135.3A patent/CN106592430B/zh active Active
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20020036206A (ko) * | 2000-11-08 | 2002-05-16 | 장문삼 | 동절기 교량슬래브 양생장치 |
JP2003247211A (ja) * | 2002-02-25 | 2003-09-05 | Shintouyou Gosei Kk | 剥落防止コンクリート構造物およびコンクリート構造物の剥落防止方法 |
CN101586330A (zh) * | 2008-05-22 | 2009-11-25 | 中铁十一局集团第一工程有限公司 | 预应力砼连续梁桥挂篮后退施工方法 |
CN101545246A (zh) * | 2009-05-05 | 2009-09-30 | 中国铁道科学研究院铁道建筑研究所 | 一种支座灌浆材料冬季施工方法 |
CN201835519U (zh) * | 2010-06-10 | 2011-05-18 | 中国建筑土木建设有限公司 | 铁路客运专线支座灌浆保温箱 |
CN102108678A (zh) * | 2011-01-18 | 2011-06-29 | 龙建路桥股份有限公司 | 高空冬季施工成套装置及方法 |
CN102162301A (zh) * | 2011-03-04 | 2011-08-24 | 葛洲坝集团第五工程有限公司 | 冬季混凝土施工保温保湿防护方法及装置 |
CN103171041A (zh) * | 2013-04-09 | 2013-06-26 | 中建三局第二建设工程有限责任公司 | 一种冬季混凝土电加热带辅助养护方法 |
CN204023410U (zh) * | 2014-06-23 | 2014-12-17 | 中铁十二局集团有限公司 | 冬季桥面铺装用保温施工装置 |
CN104675118A (zh) * | 2015-02-11 | 2015-06-03 | 刘明瑞 | 一种混凝土冬季施工电加热工艺 |
CN205259609U (zh) * | 2015-11-16 | 2016-05-25 | 中铁十四局集团有限公司 | 冬季混凝土施工智能温控模板加热保温系统 |
CN205385618U (zh) * | 2016-01-05 | 2016-07-13 | 山东科技大学 | 一种土木工程施工专用电热毯 |
Non-Patent Citations (2)
Title |
---|
胡涛,蒋陈: "贵阳至毕节二级公路乌溪特大桥挂篮冬季施工", 《公路交通技术》 * |
袁正国: "大跨连续梁挂篮悬臂浇筑冬季施工方案研究", 《黑龙江科技信息》 * |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107503297A (zh) * | 2017-09-12 | 2017-12-22 | 中建八局第三建设有限公司 | 挂篮防护与梁体蒸汽养护一体化养护棚及其施工方法 |
CN107721331A (zh) * | 2017-10-19 | 2018-02-23 | 清华大学 | 严寒地区混凝土伸缩缝施工水化进程保障方法 |
CN108018779A (zh) * | 2017-11-30 | 2018-05-11 | 苏交科集团股份有限公司 | 一种低温大温差环境下混凝土施工方法 |
CN111519540A (zh) * | 2020-04-29 | 2020-08-11 | 中国水利水电第八工程局有限公司 | 一种连续梁悬臂保温施工装置 |
CN111927125A (zh) * | 2020-06-19 | 2020-11-13 | 中铁隧道集团二处有限公司 | 一种混凝土冬季养护施工方法 |
CN112854748A (zh) * | 2021-03-10 | 2021-05-28 | 中铁二十局集团第六工程有限公司 | 一种悬浇箱梁冬季施工用养护方法 |
CN113027156A (zh) * | 2021-03-10 | 2021-06-25 | 中铁二十局集团第六工程有限公司 | 一种箱梁冬季施工用养护系统 |
CN114525741A (zh) * | 2022-02-19 | 2022-05-24 | 中铁二十局集团第六工程有限公司 | 邻近既有线悬臂梁的梁体保温施工方法 |
CN114657898A (zh) * | 2022-02-19 | 2022-06-24 | 中铁二十局集团第六工程有限公司 | 高寒地区悬浇梁施工方法 |
CN114657897A (zh) * | 2022-02-19 | 2022-06-24 | 中铁二十局集团第六工程有限公司 | 高寒地区悬浇梁保温施工方法 |
CN114673159A (zh) * | 2022-05-07 | 2022-06-28 | 华能鹤岗发电有限公司 | 一种用于冬季施工的混凝土保温施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN106592430B (zh) | 2018-04-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106592430B (zh) | 一种挂篮悬臂现浇冬季施工方法 | |
CN106246209B (zh) | 一种隧道内衬混凝土保温养护施工装置及其施工方法 | |
CN207376869U (zh) | 柔性连接的高防火保温墙板 | |
CN206111210U (zh) | 一种严寒地区长隧道冬季混凝土保温抗冻装置 | |
CN106760377A (zh) | 能够防治地面裂缝的埋管式地暖施工方法 | |
CN104675118B (zh) | 一种混凝土冬季施工电加热工艺 | |
CN107524248A (zh) | 柔性连接的高防火保温墙板及其施工方法 | |
CN204023410U (zh) | 冬季桥面铺装用保温施工装置 | |
CN109610894A (zh) | 一种拌和站保温施工工艺 | |
CN107310045A (zh) | 一种全封闭地暖保温式混凝土工厂 | |
CN205919447U (zh) | 一种楼板热辐射新风系统构造 | |
CN105625189B (zh) | 一种空心高墩混凝土浇筑保温养护系统 | |
CN115464757A (zh) | 一种寒冷低温地区悬臂现浇桥梁施工保温养生方法 | |
CN107938937A (zh) | 一种预制非组合夹心电采暖保温墙板及制作方法 | |
CN207686125U (zh) | 一种预制非组合夹心电采暖保温墙板 | |
CN210282694U (zh) | 一种管片生产用保温棚 | |
CN207244473U (zh) | 挂篮防护与梁体蒸汽养护一体化养护棚 | |
CN203585579U (zh) | 一种建筑物穿墙管线外防水结构 | |
CN208329313U (zh) | 安装在楼板下侧的天棚采暖制冷结构 | |
CN112983497A (zh) | 冻土区隧道防水防寒保温结构及其铺设方法 | |
RU114074U1 (ru) | Устройство для утепления наружной стены здания | |
CN201424731Y (zh) | 保温、调温、通风的屋面结构 | |
CN105157097B (zh) | 一种应用于火墙的可拆卸式相变蓄热装置 | |
CN206398180U (zh) | 一种大坡度热力管道支架管部结构 | |
CN205066457U (zh) | 整体喷射浇筑内衬 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: A new era of Business Center No. 456 430000 Hubei province Wuhan city Wuchang District Wu Luo Road, 40 floor Applicant after: China Construction three Bureau infrastructure construction investment Co., Ltd. Address before: A new era of Business Center No. 456 430000 Hubei province Wuhan city Wuchang District Wu Luo Road, 40 floor Applicant before: CCTEB INFRASTRUCTURE CONSTRUCTION CO., LTD. |
|
GR01 | Patent grant | ||
GR01 | Patent grant |