WO2015025985A1 - 作業車両および作業車両の制御方法 - Google Patents

作業車両および作業車両の制御方法 Download PDF

Info

Publication number
WO2015025985A1
WO2015025985A1 PCT/JP2014/074006 JP2014074006W WO2015025985A1 WO 2015025985 A1 WO2015025985 A1 WO 2015025985A1 JP 2014074006 W JP2014074006 W JP 2014074006W WO 2015025985 A1 WO2015025985 A1 WO 2015025985A1
Authority
WO
WIPO (PCT)
Prior art keywords
speed
arm
cylinder
bucket
amount
Prior art date
Application number
PCT/JP2014/074006
Other languages
English (en)
French (fr)
Inventor
健 ▲高▼浦
悠人 藤井
義樹 上
Original Assignee
株式会社小松製作所
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社小松製作所 filed Critical 株式会社小松製作所
Priority to PCT/JP2014/074006 priority Critical patent/WO2015025985A1/ja
Priority to DE112014000176.7T priority patent/DE112014000176B4/de
Priority to US14/423,452 priority patent/US9447562B2/en
Priority to CN201480002025.3A priority patent/CN104619921B/zh
Priority to KR1020157004882A priority patent/KR101658326B1/ko
Priority to JP2014546643A priority patent/JP5865510B2/ja
Publication of WO2015025985A1 publication Critical patent/WO2015025985A1/ja

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/2004Control mechanisms, e.g. control levers
    • E02F9/2012Setting the functions of the control levers, e.g. changing assigned functions among operations levers, setting functions dependent on the operator or seat orientation
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/28Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
    • E02F3/36Component parts
    • E02F3/42Drives for dippers, buckets, dipper-arms or bucket-arms
    • E02F3/43Control of dipper or bucket position; Control of sequence of drive operations
    • E02F3/435Control of dipper or bucket position; Control of sequence of drive operations for dipper-arms, backhoes or the like
    • E02F3/437Control of dipper or bucket position; Control of sequence of drive operations for dipper-arms, backhoes or the like providing automatic sequences of movements, e.g. linear excavation, keeping dipper angle constant
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/2004Control mechanisms, e.g. control levers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/2025Particular purposes of control systems not otherwise provided for
    • E02F9/2029Controlling the position of implements in function of its load, e.g. modifying the attitude of implements in accordance to vehicle speed
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/22Hydraulic or pneumatic drives
    • E02F9/2246Control of prime movers, e.g. depending on the hydraulic load of work tools
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/22Hydraulic or pneumatic drives
    • E02F9/226Safety arrangements, e.g. hydraulic driven fans, preventing cavitation, leakage, overheating
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/26Indicating devices
    • E02F9/264Sensors and their calibration for indicating the position of the work tool
    • E02F9/265Sensors and their calibration for indicating the position of the work tool with follow-up actions (e.g. control signals sent to actuate the work tool)

Definitions

  • the present invention relates to a work vehicle and a control method of the work vehicle.
  • a work vehicle such as a hydraulic shovel comprises a work implement having a boom, an arm and a bucket.
  • automatic control which moves a bucket based on a target design topography which is a target shape to be excavated is known.
  • Patent Document 1 proposes a method for automatically controlling work to create a surface corresponding to a flat reference surface by scraping the soil that contacts the blade tip of a bucket by moving the blade tip of the bucket along the reference surface. It is done.
  • the bucket falls by its own weight. Due to the weight drop of the bucket, the speed of the hydraulic cylinder is equal to or higher than the assumed speed of the hydraulic cylinder by the arm control lever. The deviation between the assumed speed and the actual speed of the hydraulic cylinder assumed based on the amount of operation of the arm control lever is large in the case of fine operation where the amount of operation of the arm control lever is small. For this reason, in the follow operation, the blade tip of the bucket may not be stable and hunting may occur.
  • the present invention was made in order to solve the above-mentioned subject, and it aims at providing a control method of a work vehicle which can control hunting, and a work vehicle.
  • a work vehicle includes a boom, an arm, a bucket, an arm cylinder, a direction control valve, a calculation unit, and a speed determination unit.
  • the arm cylinder drives the arm.
  • the direction control valve has a movable spool, and movement of the spool supplies hydraulic fluid to the arm cylinder to operate the arm cylinder.
  • the calculation unit calculates the estimated speed of the arm cylinder based on the correlation between the movement amount of the spool of the direction control valve according to the operation amount of the arm operation lever and the speed of the arm cylinder.
  • the speed determination unit determines a target speed of the boom based on the estimated speed of the arm cylinder.
  • the calculation unit is more than the speed of the arm cylinder according to the correlation between the movement amount of the spool of the direction control valve according to the operation amount of the arm operation lever and the speed of the arm cylinder.
  • a large velocity is calculated as the estimated velocity of the arm cylinder.
  • the arm when the operation amount of the arm control lever is less than the predetermined amount, the arm according to the correlation between the movement amount of the spool of the direction control valve according to the operation amount of the arm control lever and the speed of the arm cylinder
  • the speed determination unit can determine the speed of the boom appropriately, and can stabilize the blade edge of the bucket and suppress hunting.
  • the calculation unit correlates the moving amount of the spool of the direction control valve with the velocity of the arm cylinder defined based on the supply amount of hydraulic oil flowing into the arm cylinder according to the moving amount of the spool of the direction control valve. Based on the estimated speed of the arm cylinder is calculated.
  • the correlation between the movement amount of the spool of the direction control valve in accordance with the operation amount of the arm operation lever and the speed of the arm cylinder corresponds to a first speed table.
  • the calculation unit calculates the speed of the arm cylinder according to the first speed table as the estimated speed when the operation amount of the arm operation lever is equal to or more than a predetermined amount.
  • the estimated velocity of the arm cylinder with high accuracy is calculated by calculating the velocity of the arm cylinder according to the first velocity table as the estimated velocity. Control, and stable control of the blade edge of the bucket is possible.
  • the calculation unit calculates the estimated speed of the arm cylinder based on the second speed table when the operation amount of the arm operation lever is less than the predetermined amount.
  • the second speed table indicates the correlation between the movement amount of the spool of the direction control valve and the speed of the arm cylinder defined based on the discharge amount from the arm cylinder according to the movement amount of the spool of the direction control valve.
  • the speed determination unit can determine the speed of the boom appropriately, and can stabilize the blade edge of the bucket and suppress hunting.
  • a control method of a work vehicle is a control method of a work vehicle including a boom, an arm, and a bucket, wherein an amount of movement of a spool of a direction control valve and an arm according to an operation amount of an arm control lever.
  • the step of calculating is based on the speed of the arm cylinder according to the correlation between the moving amount of the spool of the direction control valve according to the operation amount of the arm operation lever and the speed of the arm cylinder when the operation amount of the arm operation lever is less than a predetermined amount. Calculating the higher velocity as the estimated velocity of the arm cylinder.
  • the correlation between the movement amount of the spool of the direction control valve and the speed of the arm cylinder according to the operation amount of the arm operation lever By calculating a velocity greater than the velocity of the arm cylinder according to the relationship as the estimated velocity of the arm cylinder, deviation from the actual velocity of the arm cylinder can be suppressed according to the adjustment of the target velocity even when the bucket falls by its own weight. As a result, it is possible to determine an appropriate boom speed, and it becomes possible to stabilize the blade edge of the bucket and to suppress hunting.
  • FIG. 1 is an external view of a work vehicle 100 based on the embodiment.
  • a hydraulic shovel is mainly described as an example of the work vehicle 100.
  • the work vehicle 100 has a vehicle body 1 and a work implement 2 operated by hydraulic pressure. As will be described later, the work vehicle 100 is equipped with a control system 200 (FIG. 3) for executing digging control.
  • a control system 200 FIG. 3
  • the vehicle body 1 has a revolving unit 3 and a traveling device 5.
  • the traveling device 5 has a pair of crawler belts 5Cr. Work vehicle 100 can travel by the rotation of crawler belt 5Cr.
  • the traveling device 5 may have wheels (tires).
  • the revolving unit 3 is disposed on the traveling device 5 and supported by the traveling device 5.
  • the pivoting body 3 is pivotable relative to the traveling device 5 about the pivot axis AX.
  • the swing body 3 has a cab 4.
  • a driver's seat 4S on which an operator is seated is provided. The operator can operate the work vehicle 100 in the cab 4.
  • the front-rear direction refers to the front-rear direction of the operator seated in the driver's seat 4S.
  • the left-right direction refers to the left-right direction of the operator seated in the driver's seat 4S.
  • the direction facing the operator sitting on the driver's seat 4S is referred to as the front direction, and the direction facing the front direction is referred to as the back direction.
  • the right side and the left side when the operator sitting on the driver's seat 4S faces the front are respectively right direction and left direction.
  • the swing body 3 has an engine room 9 in which the engine is accommodated, and a counterweight provided at the rear of the swing body 3.
  • a handrail 19 is provided in front of the engine room 9.
  • an engine and a hydraulic pump (not shown) are arranged.
  • the work implement 2 is supported by the rotating body 3.
  • the work machine 2 has a boom 6, an arm 7, a bucket 8, a boom cylinder 10, an arm cylinder 11, and a bucket cylinder 12.
  • the boom 6 is connected to the revolving unit 3.
  • the arm 7 is connected to the boom 6.
  • the bucket 8 is connected to the arm 7.
  • the boom cylinder 10 drives the boom 6.
  • the arm cylinder 11 drives the arm 7.
  • the bucket cylinder 12 drives the bucket 8.
  • Each of boom cylinder 10, arm cylinder 11, and bucket cylinder 12 is a hydraulic cylinder driven by hydraulic fluid.
  • the base end of the boom 6 is connected to the revolving unit 3 via the boom pin 13.
  • the proximal end of the arm 7 is connected to the distal end of the boom 6 via an arm pin 14.
  • the bucket 8 is connected to the tip of the arm 7 via a bucket pin 15.
  • the boom 6 is rotatable around the boom pin 13.
  • the arm 7 is rotatable about an arm pin 14.
  • the bucket 8 is rotatable around a bucket pin 15.
  • Each of the arm 7 and the bucket 8 is a movable member movable on the tip end side of the boom 6.
  • Drawing 2 (A) and Drawing 2 (B) are figures which explain work vehicle 100 based on an embodiment typically.
  • the side view of the work vehicle 100 is shown by FIG. 2 (A).
  • a rear view of the work vehicle 100 is shown in FIG. 2 (B).
  • the length L1 of the boom 6 is the distance between the boom pin 13 and the arm pin 14.
  • the length L 2 of the arm 7 is the distance between the arm pin 14 and the bucket pin 15.
  • the length L3 of the bucket 8 is the distance between the bucket pin 15 and the cutting edge 8 a of the bucket 8.
  • the bucket 8 has a plurality of blades, and in this example, the tip of the bucket 8 is referred to as a cutting edge 8a.
  • the bucket 8 may not have a blade.
  • the tip of the bucket 8 may be formed of a straight steel plate.
  • the work vehicle 100 has a boom cylinder stroke sensor 16, an arm cylinder stroke sensor 17, and a bucket cylinder stroke sensor 18.
  • the boom cylinder stroke sensor 16 is disposed on the boom cylinder 10.
  • the arm cylinder stroke sensor 17 is disposed on the arm cylinder 11.
  • a bucket cylinder stroke sensor 18 is disposed on the bucket cylinder 12.
  • the boom cylinder stroke sensor 16, the arm cylinder stroke sensor 17, and the bucket cylinder stroke sensor 18 are also collectively referred to as a cylinder stroke sensor.
  • the stroke length of the boom cylinder 10 is determined based on the detection result of the boom cylinder stroke sensor 16.
  • the stroke length of arm cylinder 11 is determined based on the detection result of arm cylinder stroke sensor 17.
  • the stroke length of the bucket cylinder 12 is determined based on the detection result of the bucket cylinder stroke sensor 18.
  • the stroke lengths of the boom cylinder 10, the arm cylinder 11, and the bucket cylinder 12 are also referred to as a boom cylinder length, an arm cylinder length, and a bucket cylinder length, respectively.
  • the boom cylinder length, the arm cylinder length, and the bucket cylinder length are collectively referred to as cylinder length data L.
  • the work vehicle 100 includes a position detection device 20 that can detect the position of the work vehicle 100.
  • the position detection device 20 includes an antenna 21, a global coordinate operation unit 23, and an IMU (Inertial Measurement Unit) 24.
  • IMU Inertial Measurement Unit
  • the antenna 21 is, for example, an antenna for Global Navigation Satellite Systems (GNSS).
  • GNSS Global Navigation Satellite Systems
  • RTK-GNSS Real Time Kinematic-Global Navigation Satellite Systems
  • the antenna 21 is provided on the revolving unit 3.
  • the antenna 21 is provided on the handrail 19 of the rotating body 3.
  • the antenna 21 may be provided in the rear direction of the engine room 9.
  • the antenna 21 may be provided on the counterweight of the revolving unit 3.
  • the antenna 21 outputs a signal corresponding to the received radio wave (GNSS radio wave) to the global coordinate operation unit 23.
  • the global coordinate operation unit 23 detects the installation position P1 of the antenna 21 in the global coordinate system.
  • the global coordinate system is a three-dimensional coordinate system (Xg, Yg, Zg) based on the reference position Pr installed in the work area.
  • the reference position Pr is the position of the tip of the reference pile set in the work area.
  • the local coordinate system is a three-dimensional coordinate system represented by (X, Y, Z) with reference to the work vehicle 100.
  • the reference position of the local coordinate system is data indicating a reference position P2 located on the pivot axis (turning center) AX of the pivoting body 3.
  • the antenna 21 has a first antenna 21A and a second antenna 21B provided on the revolving unit 3 so as to be separated from each other in the vehicle width direction.
  • the global coordinate calculation unit 23 detects the installation position P1a of the first antenna 21A and the installation position P1b of the second antenna 21B.
  • the global coordinate operation unit 23 acquires reference position data P represented by global coordinates.
  • the reference position data P is data indicating a reference position P2 located on the pivot axis (turning center) AX of the pivoting body 3.
  • the reference position data P may be data indicating the installation position P1.
  • the global coordinate operation unit 23 generates revolving unit orientation data Q based on the two installation positions P1a and P1b.
  • the revolving unit orientation data Q is determined based on an angle formed by a straight line determined by the installation position P1a and the installation position P1b with respect to a reference orientation (for example, north) of the global coordinates.
  • the swinging body orientation data Q indicates the direction in which the swinging body 3 (the work machine 2) is facing.
  • the global coordinate calculation unit 23 outputs reference position data P and revolving unit orientation data Q to a display controller 28 described later.
  • the IMU 24 is provided on the rotating body 3.
  • the IMU 24 is disposed below the cab 4.
  • a highly rigid frame is disposed in the lower part of the cab 4.
  • the IMU 24 is placed on the frame.
  • the IMU 24 may be disposed to the side (right or left) of the pivot axis AX (reference position P2) of the pivot body 3.
  • the IMU 24 detects an inclination angle ⁇ 4 inclining in the left-right direction of the vehicle body 1 and an inclination angle ⁇ 5 inclining in the front-rear direction of the vehicle body 1.
  • FIG. 3 is a functional block diagram showing a configuration of a control system 200 based on the embodiment.
  • the control system 200 controls the digging process using the work implement 2.
  • the control of the drilling process has a follow control.
  • Flattening control means that the blade edge of the bucket moves along the design topography to scrape the soil that abuts the blade edge, and automatically controls the work to create a surface corresponding to the flat design topography, It is also called limited excavation control.
  • the rule control is performed when the operator operates the arm and the distance between the blade tip of the bucket and the design topography and the speed of the blade tip are within the standard.
  • the operator usually operates the arm while always operating the boom in the direction to lower the boom during trace control.
  • the control system 200 includes a boom cylinder stroke sensor 16, an arm cylinder stroke sensor 17, a bucket cylinder stroke sensor 18, an antenna 21, a global coordinate calculation unit 23, an IMU 24, an operating device 25, and a work machine controller 26.
  • the operating device 25 is disposed in the cab 4.
  • the operating device 25 is operated by the operator.
  • the operating device 25 receives an operator operation to drive the work machine 2.
  • the operating device 25 is a pilot hydraulic operating device.
  • the directional control valve 64 adjusts the amount of hydraulic fluid supplied to the hydraulic cylinder.
  • the direction control valve 64 is actuated by the oil supplied to the first hydraulic chamber and the second hydraulic chamber.
  • the oil supplied to the hydraulic cylinders is also referred to as hydraulic oil.
  • the oil supplied to the directional control valve 64 to operate the directional control valve 64 is referred to as pilot oil.
  • the pressure of the pilot oil is also referred to as pilot hydraulic pressure.
  • the hydraulic oil and the pilot oil may be delivered from the same hydraulic pump.
  • a part of the hydraulic oil delivered from the hydraulic pump may be depressurized by the pressure reducing valve, and the depressurized hydraulic oil may be used as a pilot oil.
  • the hydraulic pump (main hydraulic pump) for delivering the hydraulic oil and the hydraulic pump (pilot hydraulic pump) for delivering the pilot oil may be different hydraulic pumps.
  • the operating device 25 has a first operating lever 25R and a second operating lever 25L.
  • the first control lever 25R is disposed, for example, on the right side of the driver's seat 4S.
  • the second control lever 25L is disposed, for example, on the left side of the driver's seat 4S.
  • the front, rear, left, and right motions correspond to two-axis motions.
  • the boom 6 and the bucket 8 are operated by the first operation lever 25R.
  • the operation in the front-rear direction of the first control lever 25R corresponds to the operation of the boom 6, and the lowering operation and the raising operation of the boom 6 are executed according to the operation in the front-rear direction.
  • the lever 6 is operated to operate the boom 6, and when the pilot oil is supplied to the pilot oil passage 450, the detected pressure generated in the pressure sensor 66 is MB.
  • the operation in the left-right direction of the first control lever 25R corresponds to the operation of the bucket 8, and the digging operation and the opening operation of the bucket 8 are performed according to the operation in the left-right direction.
  • the lever 8 is operated to operate the bucket 8, and the detected pressure generated in the pressure sensor 66 when the pilot oil is supplied to the pilot oil passage 450 is taken as MT.
  • the arm 7 and the swing body 3 are operated by the second control lever 25L.
  • the operation of the second control lever 25L in the front-rear direction corresponds to the operation of the arm 7, and the raising operation and the lowering operation of the arm 7 are executed according to the operation in the front-rear direction.
  • the lever 7 is operated to operate the arm 7, and the detected pressure generated in the pressure sensor 66 when the pilot oil is supplied to the pilot oil passage 450 is MA.
  • the operation in the left-right direction of the second control lever 25L corresponds to the turning of the swing body 3, and the right turn operation and the left turn operation of the swing body 3 are executed according to the operation in the left-right direction.
  • the operation of the boom 6 in the vertical direction is also referred to as raising operation and lowering operation as lowering operation.
  • the movement of the arm 7 in the vertical direction is also referred to as dumping operation and digging operation, respectively.
  • the operation of the bucket 8 in the vertical direction is also referred to as dumping operation and digging operation, respectively.
  • the pilot oil which is delivered from the main hydraulic pump and reduced in pressure by the pressure reducing valve, is supplied to the operating device 25.
  • the pilot hydraulic pressure is adjusted based on the amount of operation of the operating device 25.
  • a pressure sensor 66 and a pressure sensor 67 are disposed in the pilot oil passage 450.
  • the pressure sensor 66 and the pressure sensor 67 detect a pilot hydraulic pressure.
  • the detection results of the pressure sensor 66 and the pressure sensor 67 are output to the work machine controller 26.
  • the first control lever 25R is operated in the front-rear direction to drive the boom 6.
  • Direction control valve 64 adjusts the flow direction and flow rate of hydraulic oil supplied to boom cylinder 10 for driving boom 6 according to the operation amount (boom operation amount) of first control lever 25R in the front-rear direction .
  • the first control lever 25R is operated in the left-right direction to drive the bucket 8.
  • Direction control valve 64 adjusts the flow direction and flow rate of hydraulic oil supplied to bucket cylinder 12 for driving bucket 8 according to the operation amount (bucket operation amount) of first control lever 25R in the left-right direction .
  • the second control lever 25L is operated in the front-rear direction to drive the arm 7.
  • Direction control valve 64 adjusts the flow direction and flow rate of hydraulic oil supplied to arm cylinder 11 for driving arm 7 in accordance with the operation amount (arm operation amount) of second control lever 25L in the front-rear direction .
  • the second control lever 25L is operated in the left-right direction to drive the swing body 3.
  • the direction control valve 64 adjusts the flow direction and flow rate of the hydraulic oil supplied to the hydraulic actuator for driving the swing structure 3 in accordance with the amount of operation of the second control lever 25L in the left-right direction.
  • the operation in the left-right direction of the first operation lever 25R may correspond to the operation of the boom 6, and the operation in the front-rear direction may correspond to the operation of the bucket 8.
  • the left and right direction of the second control lever 25L may correspond to the operation of the arm 7, and the operation in the front and rear direction may correspond to the operation of the revolving unit 3.
  • the control valve 27 adjusts the amount of hydraulic fluid supplied to the hydraulic cylinders (the boom cylinder 10, the arm cylinder 11, and the bucket cylinder 12). Control valve 27 operates based on a control signal from work implement controller 26.
  • the man-machine interface unit 32 has an input unit 321 and a display unit (monitor) 322.
  • the input unit 321 has operation buttons arranged around the display unit 322.
  • the input unit 321 may have a touch panel.
  • the man-machine interface unit 32 is also referred to as multi-monitor.
  • the display unit 322 displays the remaining amount of fuel, the temperature of the cooling water, and the like as basic information.
  • the input unit 321 is operated by the operator.
  • the command signal generated by the operation of the input unit 321 is output to the work machine controller 26.
  • the sensor controller 30 calculates the boom cylinder length based on the detection result of the boom cylinder stroke sensor 16.
  • the boom cylinder stroke sensor 16 outputs a pulse associated with the orbiting operation to the sensor controller 30.
  • the sensor controller 30 calculates the boom cylinder length based on the pulse output from the boom cylinder stroke sensor 16.
  • the sensor controller 30 calculates the arm cylinder length based on the detection result of the arm cylinder stroke sensor 17.
  • the sensor controller 30 calculates the bucket cylinder length based on the detection result of the bucket cylinder stroke sensor 18.
  • the sensor controller 30 calculates the inclination angle ⁇ 1 of the boom 6 with respect to the vertical direction of the rotating body 3 from the boom cylinder length acquired based on the detection result of the boom cylinder stroke sensor 16.
  • the sensor controller 30 calculates the inclination angle ⁇ 2 of the arm 7 with respect to the boom 6 from the arm cylinder length acquired based on the detection result of the arm cylinder stroke sensor 17.
  • the sensor controller 30 calculates the inclination angle ⁇ 3 of the cutting edge 8 a of the bucket 8 with respect to the arm 7 from the bucket cylinder length acquired based on the detection result of the bucket cylinder stroke sensor 18.
  • the positions of the boom 6, the arm 7, and the bucket 8 of the work vehicle 100 are specified based on the inclination angles ⁇ 1, ⁇ 2, ⁇ 3, the reference position data P, the revolving body orientation data Q, and the cylinder length data L which are the above calculation results. It is possible to generate bucket position data indicating the three-dimensional position of the bucket 8.
  • the inclination angle ⁇ 1 of the boom 6, the inclination angle ⁇ 2 of the arm 7, and the inclination angle ⁇ 3 of the bucket 8 may not be detected by the cylinder stroke sensor.
  • the tilt angle ⁇ 1 of the boom 6 may be detected by an angle detector such as a rotary encoder.
  • the angle detector detects the bending angle of the boom 6 with respect to the swing body 3 to detect the inclination angle ⁇ 1.
  • the inclination angle ⁇ 2 of the arm 7 may be detected by an angle detector attached to the arm 7.
  • the inclination angle ⁇ 3 of the bucket 8 may be detected by an angle detector attached to the bucket 8.
  • FIG. 4 is a diagram showing a configuration of a hydraulic system based on the embodiment.
  • the hydraulic system 300 includes a boom cylinder 10, an arm cylinder 11, a bucket cylinder 12 (a plurality of hydraulic cylinders 60), and a swing motor 63 for swinging the swing body 3.
  • the boom cylinder 10 is also referred to as a hydraulic cylinder 10 (60). The same applies to the other hydraulic cylinders.
  • the hydraulic cylinder 60 is operated by hydraulic oil supplied from a main hydraulic pump (not shown).
  • the swing motor 63 is a hydraulic motor and is operated by hydraulic fluid supplied from the main hydraulic pump.
  • a direction control valve 64 is provided to control the direction and flow rate of hydraulic fluid flowing to each hydraulic cylinder 60.
  • the hydraulic oil supplied from the main hydraulic pump is supplied to each hydraulic cylinder 60 via the direction control valve 64.
  • a direction control valve 64 is provided for the swing motor 63.
  • Each hydraulic cylinder 60 has a cap side (bottom side) oil chamber 40A and a rod side (head side) oil chamber 40B.
  • the direction control valve 64 is a spool system that moves a rod-like spool to switch the flow direction of the hydraulic fluid.
  • the axial movement of the spool switches between the supply of hydraulic fluid to the cap-side oil chamber 40A and the supply of hydraulic fluid to the rod-side oil chamber 40B.
  • the supply amount (supply amount per unit time) of the hydraulic oil to the hydraulic cylinder 60 is adjusted.
  • the cylinder speed is adjusted.
  • the direction control valve 64 functions as an adjusting device capable of adjusting the amount of hydraulic oil supplied to the hydraulic cylinder 60 that drives the work machine 2 by the movement of the spool.
  • Each direction control valve 64 is provided with a spool stroke sensor 65 that detects the movement distance (spool stroke) of the spool.
  • a detection signal of the spool stroke sensor 65 is output to the work machine controller 26.
  • each direction control valve 64 is adjusted by the operating device 25.
  • the operating device 25 is a pilot hydraulic operating device.
  • the pilot oil which is delivered from the main hydraulic pump and reduced in pressure by the pressure reducing valve, is supplied to the operating device 25.
  • the operating device 25 has a pilot hydraulic pressure adjustment valve.
  • the pilot hydraulic pressure is adjusted based on the amount of operation of the operating device 25.
  • the pilot hydraulic pressure drives the direction control valve 64.
  • the pilot hydraulic pressure is adjusted by the operating device 25 to adjust the amount and speed of movement of the spool in the axial direction. Further, the supply of the hydraulic oil to the cap side oil chamber 40A and the supply of the hydraulic oil to the rod side oil chamber 40B are switched by the operating device 25.
  • the controller 25 and each directional control valve 64 are connected via a pilot oil passage 450.
  • the control valve 27, the pressure sensor 66, and the pressure sensor 67 are disposed in the pilot oil passage 450.
  • a pressure sensor 66 and a pressure sensor 67 for detecting a pilot hydraulic pressure are provided on both sides of each control valve 27.
  • the pressure sensor 66 is disposed in an oil passage 451 between the operating device 25 and the control valve 27.
  • the pressure sensor 67 is disposed in an oil passage 452 between the control valve 27 and the direction control valve 64.
  • the pressure sensor 66 detects the pilot pressure before it is adjusted by the control valve 27.
  • the pressure sensor 67 detects the pilot oil pressure adjusted by the control valve 27.
  • the detection results of the pressure sensor 66 and the pressure sensor 67 are output to the work machine controller 26.
  • the control valve 27 adjusts the pilot hydraulic pressure based on a control signal (EPC current) from the work machine controller 26.
  • the control valve 27 is an electromagnetic proportional control valve, and is controlled based on a control signal from the work machine controller 26.
  • the control valve 27 has a control valve 27B and a control valve 27A.
  • the control valve 27B adjusts the pilot oil pressure of the pilot oil supplied to the second pressure receiving chamber of the direction control valve 64 to supply the amount of hydraulic oil supplied to the cap-side oil chamber 40A via the direction control valve 64. It is adjustable.
  • the control valve 27A adjusts the pilot oil pressure of the pilot oil supplied to the first pressure receiving chamber of the direction control valve 64 to supply the amount of hydraulic oil supplied to the rod side oil chamber 40B via the direction control valve 64. It is adjustable.
  • pilot oil passage 450 in the pilot oil passage 450, the pilot oil passage 450 between the operating device 25 and the control valve 27 is referred to as an oil passage (upstream oil passage) 451.
  • the pilot oil passage 450 between the control valve 27 and the direction control valve 64 is referred to as an oil passage (downstream oil passage) 452.
  • the pilot oil is supplied to each direction control valve 64 via an oil passage 452.
  • the oil passage 452 includes an oil passage 452A connected to the first pressure receiving chamber and an oil passage 452B connected to the second pressure receiving chamber.
  • the spool moves in accordance with the pilot oil pressure.
  • the hydraulic fluid is supplied to the cap side oil chamber 40A via the direction control valve 64.
  • the supply amount of the hydraulic oil to the cap side oil chamber 40A is adjusted by the movement amount of the spool corresponding to the operation amount of the operation device 25.
  • the pilot oil whose pilot hydraulic pressure has been adjusted by the operating device 25 is supplied to the direction control valve 64, whereby the position of the spool in the axial direction is adjusted.
  • the oil passage 451 has an oil passage 451A connecting the oil passage 452A and the operation device 25 and an oil passage 451B connecting the oil passage 452B and the operation device 25.
  • the boom 6 performs two types of operations, the lowering operation and the raising operation, by the operation of the operating device 25.
  • pilot oil is supplied to the direction control valve 64 connected to the boom cylinder 10 via the oil passage 451B and the oil passage 452B. Ru.
  • pilot oil is supplied to the direction control valve 64 connected to the boom cylinder 10 via the oil passage 451A and the oil passage 452A. Ru.
  • the boom 6 is raised by the extension of the boom cylinder 10, and the boom 6 is lowered by the retraction of the boom cylinder 10.
  • the hydraulic fluid is supplied to the cap-side oil chamber 40A of the boom cylinder 10, whereby the boom cylinder 10 is extended and the boom 6 is raised.
  • the hydraulic fluid is supplied to the rod side oil chamber 40B of the boom cylinder 10, thereby retracting the boom cylinder 10 and lowering the boom 6.
  • the arm 7 executes two types of operations, the lowering operation and the raising operation.
  • the pilot oil is supplied to the direction control valve 64 connected to the arm cylinder 11 via the oil passage 451B and the oil passage 452B.
  • the pilot oil is supplied to the direction control valve 64 connected to the arm cylinder 11 via the oil passage 451A and the oil passage 452A.
  • the arm 7 is lowered (excavating operation) by the extension of the arm cylinder 11, and the arm 7 is raised (dumping operation) by the retraction of the arm cylinder 11.
  • the hydraulic fluid is supplied to the cap-side oil chamber 40A of the arm cylinder 11, whereby the arm cylinder 11 is extended and the arm 7 is lowered.
  • the hydraulic fluid is supplied to the rod side oil chamber 40B of the arm cylinder 11, whereby the arm cylinder 11 is retracted and the arm 7 is raised.
  • the bucket 8 executes two types of operations of the lowering operation and the raising operation by the operation of the operation device 25.
  • pilot oil is supplied to the direction control valve 64 connected to the bucket cylinder 12 via the oil passage 451B and the oil passage 452B.
  • pilot oil is supplied to the direction control valve 64 connected to the bucket cylinder 12 via the oil passage 451A and the oil passage 452A.
  • the directional control valve 64 operates based on the pilot pressure.
  • the bucket 8 is lowered (excavating operation) by the extension of the bucket cylinder 12, and the bucket 8 is raised (dumping operation) by the retraction of the bucket cylinder 12.
  • the hydraulic fluid is supplied to the cap-side oil chamber 40A of the bucket cylinder 12, whereby the bucket cylinder 12 is extended and the bucket 8 is lowered.
  • the hydraulic fluid is supplied to the rod-side oil chamber 40B of the bucket cylinder 12, whereby the bucket cylinder 12 is retracted and the bucket 8 is raised.
  • the swing body 3 executes two types of operations, a right turning operation and a left turning operation.
  • Hydraulic fluid is supplied to the swing motor 63 by operating the operating device 25 so that the right swing operation of the swing body 3 is performed.
  • the operating device 25 is operated such that the left turning operation of the swing body 3 is performed, whereby the hydraulic oil is supplied to the swing motor 63.
  • the work implement 2 operates in accordance with the amount of operation of the operating device 25.
  • the work unit controller 26 opens the control valve 27.
  • the pilot oil pressure of the oil passage 451 and the pilot oil pressure of the oil passage 452 become equal.
  • the pilot hydraulic pressure is adjusted based on the amount of operation of the operating device 25.
  • the direction control valve 64 can be adjusted to perform the raising operation and the lowering operation of the boom 6, the arm 7 and the bucket 8 described above.
  • the trace control (limited excavation control)
  • the work machine 2 is controlled by the work machine controller 26 based on the operation of the operating device 25.
  • the work unit controller 26 outputs a control signal to the control valve 27.
  • the oil passage 451 has a predetermined pressure, for example, by the action of a pilot hydraulic pressure adjustment valve.
  • the control valve 27 operates based on a control signal of the work implement controller 26.
  • the hydraulic oil in the oil passage 451 is supplied to the oil passage 452 via the control valve 27. Therefore, the pressure of the hydraulic oil in the oil passage 452 can be adjusted (reduced) by the control valve 27.
  • the pressure of the hydraulic fluid in the oil passage 452 acts on the direction control valve 64.
  • the directional control valve 64 operates based on the pilot hydraulic pressure controlled by the control valve 27.
  • work implement controller 26 can output a control signal to at least one of control valve 27A and control valve 27B to adjust the pilot hydraulic pressure for direction control valve 64 connected to arm cylinder 11.
  • the hydraulic fluid whose pressure is adjusted by the control valve 27A is supplied to the direction control valve 64, whereby the spool is moved to one side in the axial direction.
  • the hydraulic fluid whose pressure is adjusted by the control valve 27B is supplied to the direction control valve 64, whereby the spool is moved to the other side in the axial direction. Thereby, the position of the spool in the axial direction is adjusted.
  • the work unit controller 26 can output a control signal to at least one of the control valve 27A and the control valve 27B to adjust the pilot hydraulic pressure for the direction control valve 64 connected to the bucket cylinder 12.
  • the work machine controller 26 can output a control signal to at least one of the control valve 27A and the control valve 27B to adjust the pilot hydraulic pressure for the direction control valve 64 connected to the boom cylinder 10.
  • the work unit controller 26 outputs a control signal to the control valve 27 C to adjust the pilot hydraulic pressure for the direction control valve 64 connected to the boom cylinder 10.
  • the work machine controller 26 controls the movement of the boom 6 (intervention control) such that the cutting edge 8 a of the bucket 8 does not intrude into the target design topography U.
  • control of the position of the boom 6 is controlled by outputting a control signal to the control valve 27 connected to the boom cylinder 10 so that intrusion of the cutting edge 8a into the target design topography U is suppressed. It is called.
  • the work machine controller 26 generates a target design topography U based on a target design topography U indicating a design topography which is a target shape to be excavated and a bucket position data S indicating the position of the cutting edge 8 a of the bucket 8.
  • the speed of the boom 6 is controlled so that the speed at which the bucket 8 approaches the target design topography U decreases according to the distance d to the bucket 8.
  • the hydraulic system 300 has oil passages 501 and 502, a control valve 27C, a shuttle valve 51, and a pressure sensor 68 as a mechanism for performing intervention control with respect to the raising operation of the boom 6.
  • the oil passage 501 is connected to the control valve 27C, and supplies pilot oil supplied to the direction control valve 64 connected to the boom cylinder 10.
  • the oil passage 501 has an oil passage 501 in which the pilot oil before passing through the control valve 27C flows, and an oil passage 502 in which the pilot oil after passing through the control valve 27C flows.
  • the oil passage 502 is connected to the control valve 27C and the shuttle valve 51, and is connected to the oil passage 452B connected to the direction control valve 64 via the shuttle valve 51.
  • the pressure sensor 68 detects the pilot oil pressure of the pilot oil of the oil passage 501.
  • the control valve 27C is controlled based on the control signal output from the work unit controller 26 to execute the intervention control.
  • Shuttle valve 51 has two inlet ports and one outlet port. One inlet port is connected to the oil passage 502. The other inlet port is connected to the control valve 27B via an oil passage 452B. The outlet port is connected to the directional control valve 64 via an oil passage 452B. The shuttle valve 51 connects the oil passage with the higher pilot oil pressure among the oil passages 452 B connected to the oil passage 502 and the control valve 27 B, and the oil passage 452 B.
  • the shuttle valve 51 is a high pressure priority type shuttle valve.
  • the shuttle valve 51 compares the pilot oil pressure of the oil passage 502 connected to one of the inlet ports with the pilot oil pressure of the oil passage 452B of the control valve 27B connected to the other of the inlet ports, and select.
  • the shuttle valve 51 communicates the high pressure side flow passage with the outlet port, and flows through the high pressure side flow passage. To the direction control valve 64.
  • control valve 27B when the work machine controller 26 does not execute the intervention control, the control valve 27B is fully opened so that the directional control valve 64 is driven based on the pilot hydraulic pressure adjusted by the operation of the operating device 25. , And outputs a control signal to the control valve 27C so as to close the oil passage 501.
  • the work unit controller 26 sends a control signal to each control valve 27 so that the directional control valve 64 is driven based on the pilot hydraulic pressure adjusted by the control valve 27C. Output.
  • the work implement controller 26 controls the pilot hydraulic pressure adjusted by the control valve 27C to be higher than the pilot hydraulic pressure adjusted by the operating device 25. Control the valve 27C. Thereby, the pilot oil from the control valve 27C is supplied to the directional control valve 64 via the shuttle valve 51.
  • FIG. 5 is a diagram schematically showing the operation of the work unit 2 when the control according to the embodiment (limited excavation control) is performed.
  • intervention control including the raising operation of the boom 6 is performed so that the bucket 8 does not intrude into the design topography.
  • the hydraulic system 300 is controlled to lower the arm 7 and raise the boom 6.
  • FIG. 6 is a functional block diagram showing a configuration of a control system 200 that executes the trace control based on the embodiment.
  • the intervention control of the boom 6 mainly by the follow control (the limited excavation control) will be mainly described.
  • the intervention control is to control the movement of the boom 6 so that the cutting edge 8 a of the bucket 8 does not intrude into the target design topography U.
  • the work machine controller 26 generates a target design topography U based on a target design topography U indicating a design topography which is a target shape to be excavated and a bucket position data S indicating the position of the cutting edge 8 a of the bucket 8.
  • the distance d to the bucket 8 is calculated.
  • the control command CBI to the control valve 27 by the intervention control of the boom 6 is output so that the speed at which the bucket 8 approaches the target design topography U decreases according to the distance d.
  • the work unit controller 26 calculates an estimated speed of the blade edge 8 a of the bucket by the operation of the arm 7 and the bucket 8 based on the operation command by the operation of the operation device 25. Then, based on the calculation result, a boom target speed for controlling the speed of the boom 6 is calculated so that the cutting edge 8a of the bucket 8 does not intrude into the target design topography U. Then, the control command CBI to the control valve 27 is output so that the boom 6 operates at the boom target speed.
  • the display controller 28 includes a target construction information storage unit 28A, a bucket position data generation unit 28B, and a target design topography data generation unit 28C.
  • the display controller 28 receives an input from the sensor controller 30.
  • the sensor controller 30 acquires cylinder length data L and inclination angles ⁇ 1, ⁇ 2, ⁇ 3 from the detection results of the cylinder stroke sensors 16, 17, 18. Also, the sensor controller 30 acquires data of the inclination angle ⁇ 4 and data of the inclination angle ⁇ 5 output from the IMU 24.
  • the sensor controller 30 outputs, to the display controller 28, cylinder length data L, data of inclination angles ⁇ 1, ⁇ 2, and ⁇ 3, data of inclination angle ⁇ 4, and data of inclination angle ⁇ 5.
  • the detection results of the cylinder stroke sensors 16, 17, 18 and the detection result of the IMU 24 are output to the sensor controller 30, and the sensor controller 30 performs predetermined arithmetic processing.
  • the function of the sensor controller 30 may be substituted by the work machine controller 26.
  • the detection result of the cylinder stroke sensor (16, 17, 18) is output to the work machine controller 26, and the work machine controller 26 controls the cylinder length (the cylinder length (16, 17, 18) based on the detection result of the cylinder stroke sensor
  • the boom cylinder length, the arm cylinder length, and the bucket cylinder length) may be calculated.
  • the detection result of the IMU 24 may be output to the work machine controller 26.
  • the global coordinate calculation unit 23 acquires reference position data P and revolving unit orientation data Q, and outputs the acquired data to the display controller 28.
  • the target construction information storage unit 28A stores target construction information (three-dimensional design topography data) T indicating a three-dimensional design topography which is a target shape of the work area.
  • the target construction information T has coordinate data and angle data required to generate a target design topography (design topography data) U indicating a design topography which is a target shape to be excavated.
  • the target construction information T may be supplied to the display controller 28 via, for example, a wireless communication device.
  • the bucket position data generation unit 28B indicates a three-dimensional position of the bucket 8 based on the inclination angles ⁇ 1, ⁇ 2, ⁇ 3, ⁇ 4, ⁇ 5, the reference position data P, the revolving unit orientation data Q, and the cylinder length data L.
  • Position data S is generated.
  • the position information of the cutting edge 8a may be transferred from a connection type recording device such as a memory.
  • the bucket position data S is data indicating a three-dimensional position of the cutting edge 8a.
  • the target design topography data generation unit 28C uses the bucket position data S acquired from the bucket position data generation unit 28B and the target construction information T to be described later stored in the target construction information storage unit 28A to indicate a target shape to be excavated Generate a design topography U.
  • the target design topography data generation unit 28C outputs the generated data on the target design topography U to the display unit 29. Thereby, the display unit 29 displays the target design topography.
  • the display unit 29 is, for example, a monitor, and displays various information of the work vehicle 100.
  • the display unit 29 includes an HMI (Human Machine Interface) monitor as a guidance monitor for computerization construction.
  • HMI Human Machine Interface
  • the target design topography data generation unit 28C outputs data on the target design topography U to the work machine controller 26.
  • the bucket position data generation unit 28B outputs the generated bucket position data S to the work machine controller 26.
  • the work machine controller 26 includes an estimated speed determination unit 52, a distance acquisition unit 53, a target speed determination unit 54, a work machine control unit 57, and a storage unit 58.
  • the work machine controller 26 acquires the bucket position data S and the target design topography U from the operation command (pressure MA, MT) of the operation device 25 and the display controller 28, and outputs the control command CBI to the control valve 27. In addition, the work machine controller 26 acquires various parameters necessary for arithmetic processing from the sensor controller 30 and the global coordinate arithmetic unit 23 as necessary.
  • the estimated speed determination unit 52 calculates an estimated arm speed Vc_am and an estimated bucket speed Vc_bkt corresponding to the lever operation of the operating device 25 for driving the arm 7 and the bucket 8.
  • the arm estimated speed Vc_am is the speed of the cutting edge 8 a of the bucket 8 when only the arm cylinder 11 is driven.
  • the estimated bucket speed Vc_bkt is the speed of the cutting edge 8 a of the bucket 8 when only the bucket cylinder 12 is driven.
  • the estimated speed determination unit 52 calculates an estimated arm speed Vc_am corresponding to the arm operation command (pressure MA). Similarly, the estimated speed determination unit 52 calculates a bucket estimated speed Vc_bkt corresponding to the bucket operation command (pressure MT). As a result, it is possible to calculate the estimated speed of the cutting edge 8 a of the bucket 8 corresponding to each operation command of the arm 7 and the bucket 7.
  • the storage unit 58 stores data such as various tables for the calculation processing of the estimated speed determination unit 52, the target speed determination unit 54, and the work machine control unit 57.
  • the distance acquisition unit 53 acquires data of the target design topography U from the target design topography data generation unit 28C.
  • the distance acquiring unit 53 determines the position of the bucket 8 in the direction perpendicular to the target design topography U based on the bucket position data S indicating the position of the cutting edge 8a of the bucket 8 acquired from the bucket position data generating unit 28B and the target design topography U.
  • a distance d between the cutting edge 8a and the target design topography U is calculated.
  • the target speed determination unit 54 determines the target speed Vc_bm_lmt of the boom 6 so that the speed at which the bucket 8 approaches the target design topography U decreases according to the speed limit table.
  • the target speed determination unit 54 uses the speed limit table indicating the relationship between the target design topography U and the distance d between the bucket 8 and the speed limit of the cutting edge, and the speed limit of the cutting edge based on the current distance d. Calculate Then, the target velocity Vc_bm_lmt of the boom 6 is determined by calculating the difference between the speed limit of the cutting edge and the estimated arm velocity Vc_am and the estimated bucket velocity Vc_bkt.
  • the speed limit table is stored (stored) in advance in the storage unit 58.
  • the work unit control unit 57 generates a control command CBI to the boom cylinder 10 according to the boom target speed Vc_bm_lmt, and outputs the control command CBI to the control valve 27 connected to the boom cylinder 10.
  • control valve 27 connected to the boom cylinder 10 is controlled, and the intervention control of the boom 6 by the trace control (the limited excavation control) is executed.
  • FIG. 7 is a diagram for explaining acquisition of the distance d between the cutting edge 8a of the bucket 8 and the target design topography U based on the embodiment.
  • the distance acquiring unit 53 determines the shortest distance d between the blade edge 8 a of the bucket 8 and the surface of the target design topography U based on the position information (bucket position data S) of the blade edge 8 a. calculate.
  • tracing control (restricted excavation control) is performed based on the shortest distance d between the blade edge 8 a of the bucket 8 and the surface of the target design topography U.
  • FIG. 8 is a functional block diagram for explaining the calculation process of the estimated speed determination unit 52 based on the embodiment.
  • the estimated speed determination unit 52 calculates an estimated arm speed Vc_am corresponding to the arm operation command (pressure MA) and a estimated bucket speed Vc_bkt corresponding to the bucket operation command (pressure MT).
  • the estimated arm speed Vc_am is the speed of the cutting edge 8a of the bucket 8 when only the arm cylinder 11 is driven.
  • the estimated bucket speed Vc_bkt is the speed of the cutting edge 8 a of the bucket 8 when only the bucket cylinder 12 is driven.
  • the estimated speed determination unit 52 includes a spool stroke calculation unit 52A, a cylinder speed calculation unit 52B, and an estimated speed determination unit 52C.
  • the spool stroke calculation unit 52A calculates the spool stroke amount of the spool 80 of the hydraulic cylinder 60 based on the spool stroke table according to the operation command (pressure) stored in the storage unit 58.
  • the pressure of the pilot oil for moving the spool 80 is also referred to as PPC pressure.
  • the amount of movement of the spool 80 is adjusted by the pressure (pilot hydraulic pressure) of the oil passage 452 controlled by the operating device 25 or the control valve 27.
  • the pilot oil pressure of the oil passage 452 is the pressure of the pilot oil of the oil passage 452 for moving the spool, and is adjusted by the operating device 25 or the control valve 27. Therefore, the amount of movement of the spool and the PPC pressure are correlated.
  • the cylinder speed calculation unit 52B calculates the cylinder speed of the hydraulic cylinder 60 based on the cylinder speed table according to the calculated spool stroke amount.
  • the cylinder speed of the hydraulic cylinder 60 is adjusted based on the amount of hydraulic fluid supplied per unit time supplied from the main hydraulic pump via the direction control valve 64.
  • the directional control valve 64 has a movable spool 80. Based on the amount of movement of the spool 80, the amount of hydraulic oil supplied to the hydraulic cylinder 60 per unit time is adjusted. Therefore, the cylinder speed and the amount of movement of the spool (spool stroke) are correlated.
  • the estimated speed determination unit 52C calculates an estimated speed based on the estimated speed table according to the calculated cylinder speed of the hydraulic cylinder 60.
  • the working unit 2 (boom 6, arm 7, bucket 8) operates according to the cylinder speed of the hydraulic cylinder 60, the cylinder speed and the estimated speed are correlated.
  • the estimated speed determination unit 52 calculates the estimated arm speed Vc_am corresponding to the arm operation command (pressure MA) and the estimated bucket speed Vc_bkt corresponding to the bucket operation command (pressure MT).
  • the spool stroke table, the cylinder speed table, and the estimated speed table are provided for the boom 6, the arm 7, and the bucket 8, respectively, are obtained based on experiments or simulations, and are stored in the storage unit 58 in advance. .
  • FIGS. 9A to 9C are diagrams for explaining a method of calculating the vertical velocity components Vcy_am and Vcy_bkt based on the embodiment.
  • the target velocity determination unit 54 estimates the arm estimated velocity Vc_am to a velocity component (vertical velocity component) Vcy_am in a direction perpendicular to the surface of the target design topography U and the surface of the target design topography U And the velocity component (horizontal velocity component) Vcx_am.
  • the target speed determination unit 54 determines the vertical axis of the local coordinate system (the pivot axis AX of the revolving unit 3) with respect to the vertical axis of the global coordinate system from the tilt angle and the target design topography U acquired from the sensor controller 30. The inclination and the inclination of the surface of the target design topography U in the vertical direction with respect to the vertical axis of the global coordinate system are determined. The target velocity determination unit 54 obtains an angle ⁇ 1 representing the inclination between the vertical axis of the local coordinate system and the vertical direction of the surface of the target design topography U from these inclinations.
  • the target velocity determining unit 54 estimates the arm estimated velocity Vc_am from the angle ⁇ 2 between the vertical axis of the local coordinate system and the direction of the arm estimated velocity Vc_am, using a trigonometric function, It is converted into a velocity component VL1_am in the vertical axis direction of the local coordinate system and a velocity component VL2_am in the horizontal axis direction.
  • the target velocity determination unit 54 determines the vertical of the local coordinate system from the inclination ⁇ 1 between the vertical axis of the local coordinate system and the vertical direction of the surface of the target design topography U.
  • the velocity component VL1_am in the axial direction and the velocity component VL2_am in the horizontal axis direction are converted into a vertical velocity component Vcy_am and a horizontal velocity component Vcx_am with respect to the target design topography U.
  • the target speed determination unit 54 converts the bucket estimated speed Vc_bkt into a vertical speed component Vcy_bkt and a horizontal speed component Vcx_bkt in the vertical axis direction of the local coordinate system.
  • FIG. 10 is a diagram for explaining an example of the speed limit table of the entire work machine 2 in the profile control based on the embodiment.
  • the vertical axis represents the speed limit Vcy_lmt
  • the horizontal axis represents the distance d between the cutting edge and the design topography.
  • the distance d is a positive value when the blade edge 8a of the bucket 8 is located outward of the surface of the target design topography U (the work machine 2 side of the work vehicle 100), and the blade edge 8a is the target
  • the distance d is a negative value when it is located inward of the surface of the design topography U (the inner side of the target design topography U to be excavated).
  • the distance d is positive when the cutting edge 8a is positioned above the surface of the target design topography U, and the distance d is negative when the cutting edge 8a is positioned below the surface of the target design topography U.
  • the distance d is positive when the cutting edge 8a is at a position where it does not erode with respect to the target design topography U, and the distance d when the cutting edge 8a is at a position where it erodes the target design topography U is a negative value.
  • the distance d is zero.
  • the velocity when the blade edge 8a goes outward from the inside of the target design topography U is a positive value
  • the velocity when the blade edge 8a goes from the outside to the inside of the target design terrain U is negative It will be a value.
  • the velocity when the cutting edge 8a is upward of the target design topography U is a positive value
  • the velocity when the cutting edge 8a is downward of the target design topography U is a negative value.
  • the slope of the speed limit Vcy_lmt when the distance d is between d1 and d2 is smaller than the slope when the distance d is d1 or more or d2 or less.
  • d1 is greater than 0.
  • d2 is less than zero.
  • the inclination when the distance d is d1 or more or d2 or less make it smaller than the slope.
  • the speed limit Vcy_lmt is a negative value, and the absolute value of the speed limit Vcy_lmt increases as the distance d increases.
  • the speed limit Vcy_lmt is a positive value, and the absolute value of the speed limit Vcy_lmt increases as the distance d decreases.
  • the speed limit Vcy_lmt is Vmin.
  • the predetermined value dth1 is a positive value and is larger than d1.
  • intervention control of the operation of the work machine 2 is performed. Specifically, when the distance d is smaller than the predetermined value dth1, intervention control of the operation of the boom 6 is performed.
  • FIGS. 11A to 11D are diagrams for explaining a method of calculating the boom target speed Vc_bm_lmt based on the embodiment.
  • the target speed determination unit 54 calculates the speed limit Vcy_lmt of the entire work machine 2 according to the speed limit table.
  • the speed limit Vcy_lmt of the work implement 2 as a whole is the movement speed of the cutting edge 8a that can be tolerated in the direction in which the cutting edge 8a of the bucket 8 approaches the target design topography U.
  • FIG. 11B shows the vertical velocity component Vcy_am of the arm estimated velocity Vc_am and the vertical velocity component Vcy_bkt of the bucket estimated velocity Vc_bkt.
  • the target speed determination unit 54 calculates the vertical speed component Vcy_am of the arm estimated speed Vc_am and the vertical speed component Vcy_bkt of the bucket estimated speed Vc_bkt based on the arm estimated speed Vc_am and the bucket estimated speed Vc_bkt as described in FIG. It is possible.
  • FIG. 11C shows the case where the limited vertical velocity component Vcy_bm_lmt of the boom 6 is calculated. Specifically, the limited vertical velocity component Vcy_bm_lmt of the boom 6 is calculated by subtracting the vertical velocity component Vcy_am of the arm estimated velocity Vc_am and the vertical velocity component Vcy_bkt of the bucket estimated velocity Vc_bkt from the limited velocity Vcy_lmt of the work machine 2 overall. Be done.
  • FIG. 11D shows the case where the boom target speed Vc_bm_lmt is calculated based on the limited vertical speed component Vcy_bm_lmt of the boom 6.
  • the limit speed Vcy_lmt of the work implement 2 as a whole is smaller than the sum of the vertical speed component Vcy_am of the arm estimated speed and the vertical speed component Vcy_bkt of the bucket estimated speed, the limited vertical speed component Vcy_bm_lmt of the boom 6 causes the boom to rise. Is a positive value.
  • the work machine controller 26 Since the boom target speed Vc_bm_lmt is a positive value, the work machine controller 26 performs intervention control to raise the boom 6 even if the control device 25 is operated in the direction to lower the boom 6. For this reason, the expansion of the erosion of the target design topography U can be rapidly suppressed.
  • FIG. 12 is a functional block diagram showing a configuration of the working machine control unit 57 based on the embodiment.
  • the working machine control unit 57 includes a cylinder speed calculation unit 262A, an EPC calculation unit 262B, and an EPC command unit 262C.
  • the work unit control unit 57 outputs a control command CBI to the control valve 27 so that the boom 6 is driven at the boom target speed Vc_bm_lmt when performing intervention control.
  • the cylinder speed calculation unit 262A calculates the cylinder speed of the hydraulic cylinder 60 in accordance with the boom target speed Vc_bm_lmt. Specifically, according to boom target speed Vc_bm_lmt based on an estimated speed table indicating the relationship between the speed of blade edge 8a of bucket 8 and the speed of hydraulic cylinder 60 only by the operation of boom 6 previously stored in storage unit 58. The cylinder speed of the hydraulic cylinder 60 is calculated.
  • the EPC calculation unit 262B calculates the EPC current value based on the calculated cylinder speed. Specifically, calculation processing is performed based on the correlation data stored in advance in the storage unit 58.
  • the EPC command unit 262C outputs the EPC current value calculated by the EPC calculating unit 262B to the control valve 27.
  • the storage unit 58 includes correlation data indicating the relationship between the cylinder speed of the hydraulic cylinder 60 and the movement amount of the spool 80, correlation data indicating the relationship between the movement amount of the spool 80 and the PPC pressure controlled by the control valve 27;
  • the correlation data indicating the relationship between the PPC pressure and the control signal (EPC current) output from the EPC calculation unit 262B is stored.
  • the cylinder speed table and the correlation data are obtained based on experiments or simulations, and are stored in advance in the storage unit 58.
  • the cylinder speed of the hydraulic cylinder 60 is adjusted based on the amount of hydraulic fluid supplied from the main hydraulic pump via the directional control valve 64 per unit time.
  • the directional control valve 64 has a movable spool 80. Based on the amount of movement of the spool 80, the amount of hydraulic oil supplied to the hydraulic cylinder 60 per unit time is adjusted. Therefore, the cylinder speed and the amount of movement of the spool (spool stroke) are correlated.
  • the amount of movement of the spool 80 is adjusted by the pressure (pilot hydraulic pressure) of the oil passage 452 controlled by the operating device 25 or the control valve 27.
  • the pilot oil pressure of the oil passage 452 is the pressure of the pilot oil of the oil passage 452 for moving the spool, and is adjusted by the operating device 25 or the control valve 27.
  • the pressure of the pilot oil for moving the spool 80 is also referred to as PPC pressure. Therefore, the amount of movement of the spool and the PPC pressure are correlated.
  • the control valve 27 operates based on the control signal (EPC current) output from the EPC calculation unit 262B of the work machine controller 26. Thus, PPC pressure and EPC current are correlated.
  • the work machine control unit 57 calculates the EPC current value corresponding to the boom target speed Vc_bm_lmt calculated by the target speed determination unit 54, and outputs the EPC current from the EPC command unit 262C to the control valve 27 as a control command CBI.
  • the work machine controller 26 can control the boom 6 so that the blade edge 8a of the bucket 8 does not intrude into the target design topography U by the intervention control.
  • the work machine controller 26 controls the arm 7 and the bucket 8 as necessary.
  • the work machine controller 26 controls the arm cylinder 11 by transmitting an arm control command to the control valve 27.
  • the arm control command has a current value corresponding to the arm command speed.
  • the work implement controller 26 controls the bucket cylinder 12 by transmitting a bucket control command to the control valve 27.
  • the bucket control command has a current value corresponding to the bucket command speed.
  • the arm control command and the bucket control command having the current value for controlling the control valve 27 are controlled according to the same method as the EPC current is calculated from the boom target speed Vc_bm_lmt. It is possible to output to
  • FIG. 13 is a flow diagram for explaining the trace control (limited excavation control) of the work vehicle 100 based on the embodiment.
  • a design topography is set (step SA1). Specifically, the target design topography U is set by the target design topography data generation unit 28C of the display controller 28.
  • the distance d between the cutting edge and the design topography is acquired (step SA2). Specifically, the distance acquiring unit 53 is based on the position information of the cutting edge 8a according to the bucket position data S from the bucket position data generating unit 28B and the target design topography U, and the surface of the blade 8a of the bucket 8 and the target design topography U And the shortest distance d between.
  • an estimated speed is determined (step SA3). Specifically, the estimated speed determination unit 52 of the work machine controller 26 determines the estimated arm speed Vc_am and the estimated bucket speed Vc_bkt.
  • the estimated arm speed Vc_am is the speed of the cutting edge 8a when only the arm cylinder 11 is driven.
  • the estimated bucket speed Vc_bkt is the speed of the cutting edge 8a when only the bucket cylinder 12 is driven.
  • the estimated arm speed Vc_am and the estimated bucket speed Vc_bkt are calculated based on the operation command (pressure MA, MT) of the controller 25 in accordance with various tables stored in the storage unit 58.
  • the target velocity is converted into a vertical velocity component (step SA4).
  • the target speed determination unit 54 converts the arm estimated speed Vc_am and the bucket estimated speed Vc_bkt into the vertical speed components Vcy_am and Vcy_bkt with respect to the target design topography U as described in FIG. 9.
  • step SA5 the speed limit Vcy_lmt of the entire work machine 2 is calculated. Specifically, the target speed determination unit 54 calculates the speed limit Vcy_lmt according to the speed limit table based on the distance d.
  • the target velocity component Vcy_bm_lmt of the boom is determined (step SA6). Specifically, as described in FIG. 11, the target speed determination unit 54 determines the vertical speed component of the target speed of the boom 6 from the speed limit Vcy_lmt of the working machine 2 overall, the arm estimated speed Vc_am, and the bucket estimated speed Vc_bkt Vertical velocity component) Vcy_bm_lmt is calculated.
  • the target vertical velocity component Vcy_bm_lmt of the boom is converted into the target velocity Vc_bm_lmt (step SA7).
  • the target speed determination unit 54 converts the target vertical speed component Vcy_bm_lmt of the boom 6 into a target speed (boom target speed) Vc_bm_lmt of the boom 6 as described with reference to FIG.
  • work implement control unit 57 calculates an EPC current value corresponding to boom target speed Vc_bm_lmt, and outputs the EPC current from control EPC command unit 262C as control instruction CBI to control valve 27 (step SA10). Thereby, the work machine controller 26 can control the boom 6 such that the cutting edge 8 a of the bucket 8 does not intrude into the target design topography U.
  • the work machine controller 26 sets a target based on the target design topography U indicating the design topography which is the target shape to be excavated and the bucket position data S indicating the position of the cutting edge 8 a of the bucket 8.
  • the speed of the boom 6 is controlled such that the relative speed at which the bucket 8 approaches the target design topography U becomes smaller according to the distance d between the design topography U and the blade edge 8 a of the bucket 8.
  • the work machine controller 26 uses the target design topography U and the cutting edge 8 a of the bucket 8 based on the target design topography U indicating the design topography which is the target shape to be excavated and the bucket position data S indicating the position of the cutting edge 8 a of the bucket 8.
  • the speed limit is determined in accordance with the distance d, and the work implement 2 is controlled so that the speed in the direction in which the work implement 2 approaches the target design topography U becomes equal to or less than the limit speed. Thereby, the follow control (excitation restriction control) is executed, and the speed adjustment of the boom cylinder is performed.
  • the position of the cutting edge 8a with respect to the target design topography U is controlled to suppress the intrusion of the cutting edge 8a into the target design topography U, and it is possible to perform a work of creating a surface according to the design topography.
  • the hydraulic cylinder 60 may operate at a speed higher than the assumed speed of the hydraulic cylinder 60 according to the operation amount (arm operation amount) at which the second control lever 25L is operated when the bucket 8 falls by its own weight. is there.
  • the boom target speed Vc_bm_lmt determined by the target speed determination unit 54 of the work machine controller 26 based on the arm estimated speed Vc_am according to the operation amount of the second control lever 25L does not become an appropriate value. It is conceivable that hunting may occur because the eight cutting edges 8a are not stable.
  • FIG. 14 is a diagram for explaining a cylinder speed table in which the relationship between the movement amount (spool stroke) of the spool 80 and the cylinder speed of the hydraulic cylinder 60 is shown based on the embodiment.
  • the cylinder speed table is stored in the storage unit 58, and is used by the estimated speed determination unit 52.
  • the horizontal axis indicates the spool stroke amount
  • the vertical axis indicates the cylinder speed.
  • the state where the spool stroke is zero (origin) is the state where the spool is at the initial position.
  • the hydraulic oil is supplied to the hydraulic cylinder 60 with a supply amount corresponding to the movement amount of the spool 80.
  • the cylinder speed is adjusted.
  • the cylinder speed table can be one determined by the operation of the operator.
  • the second operating lever 25L of the operating device 25 is operated such that the spool 80 moves a predetermined amount.
  • the amount of movement of the spool 80 (spool stroke amount) can be detected by the spool stroke sensor 65.
  • a cylinder speed sensor 17 detects a cylinder speed corresponding to the spool stroke amount of the spool 80.
  • the cylinder stroke sensor 17 can detect the velocity (cylinder velocity) of the cylinder rod 10Y with high accuracy.
  • the cylinder speed table can be acquired based on the detection result of the spool stroke sensor 65 and the detection result of the cylinder stroke sensor 17.
  • the arm 7 is lowered (excavating operation) by moving the spool so that the spool stroke amount becomes positive.
  • the work machine 2 performs the raising operation (dumping operation).
  • meter-in control As a method of controlling the cylinder speed of the hydraulic cylinder 60, there are meter-in control in which the hydraulic oil is controlled by the inflow of hydraulic oil flowing into the hydraulic cylinder 60 according to the spool stroke amount, and the outflow of hydraulic oil flowing out of the hydraulic cylinder 60. There is meter out control to control.
  • Line LA is a first cylinder speed table (first speed table) showing the relationship between the spool stroke amount and the cylinder speed in meter-in control.
  • a line LB is a second cylinder speed table (second speed table) showing the relationship between the spool stroke amount and the cylinder speed in the meter out control.
  • bucket 8 When the method of calculating the cylinder speed based on the first cylinder speed table by meter-in control of the line LA is adopted when the operation amount (arm operation amount) at which the second operation lever 25L is operated is less than the predetermined amount, bucket 8
  • the speed of the hydraulic cylinder 60 when the self weight drop occurs may be higher than the estimated speed according to the operation amount (arm operation amount) at which the second operation lever 25L is operated. This is because the moving speed of the cylinder rod 10Y is smaller than the moving speed of the cylinder rod 10Y according to the inflow of hydraulic oil (the speed of the hydraulic cylinder 60) as a result of the load to pull the cylinder rod 10Y by the weight of the bucket 8 applied. Due to the big.
  • the speed of the hydraulic cylinder 60 when the bucket 8 falls by its own weight is It is considered to be approximately equal to the estimated speed according to the amount of operation (the amount of arm operation) by which the second control lever 25L is operated. This is because the speed at which the cylinder rod 10Y moves (the speed of the hydraulic cylinder 60) is controlled by the amount of hydraulic fluid outflow even when a load for pulling the cylinder rod 10Y is applied by its own weight of the bucket 8 Because the speed is properly controlled.
  • the estimated speed determination unit 52 of the work machine controller 26 performs the second measurement by the meter-in control of the line LA when the operation amount (the arm operation amount) at which the second operation lever 25L is operated is less than the predetermined amount.
  • a value larger than the value of the cylinder speed based on the one cylinder speed table is set as the estimated speed of the hydraulic cylinder 60.
  • the cylinder speed calculation unit 52B of the estimated speed determination unit 52 performs the first by meter-in control of the line LA.
  • a value larger than the value of the cylinder speed based on the cylinder speed table is set as the estimated speed of the hydraulic cylinder 60.
  • the target speed determination unit 54 of the work machine controller 26 determines the boom target speed Vc_bm_lmt based on the arm estimated speed Vc_am adjusted in accordance with the operation amount of the second control lever 25L in the intervention control described above. Thereby, it becomes possible to stabilize the blade edge 8a of the bucket 8 and to suppress hunting.
  • an operation amount (arm operation amount) for operating the second operation lever 25L when the spool stroke amount becomes the predetermined value X is set to the predetermined amount.
  • the cylinder speed calculator 52B of the estimated speed determination unit 52 sets the first cylinder speed table by meter-in control of the line LA when the operation amount (arm operation amount) for operating the second operation lever 25L is less than the predetermined amount.
  • a value larger than the value of the cylinder speed based on the above and smaller than the cylinder speed Y is set as the estimated speed of the hydraulic cylinder 60.
  • the cylinder speed calculator 52B of the estimated speed determination unit 52 performs meter-in control of the line LA.
  • the value of the cylinder speed based on the first cylinder speed table is set to the estimated speed of the hydraulic cylinder 60.
  • the target speed determination unit 54 of the work machine controller 26 determines the boom target speed Vc_bm_lmt.
  • the cylinder rod 10Y moves by the weight of the bucket 8 due to the weight of the bucket 8 pulling the cylinder rod 10Y according to the inflow of hydraulic oil (the speed of the hydraulic cylinder 60). Since it is larger than the moving speed, by setting the cylinder speed based on the first cylinder speed table as the estimated speed, the arm estimated speed Vc_am according to the highly accurate cylinder speed is calculated.
  • the target speed determination unit 54 of the work machine controller 26 can set the boom target speed Vc_bm_lmt with high accuracy to execute more stable trace control.
  • An area in which the spool stroke amount in FIG. 14 is less than a predetermined value X is referred to as a fine operation area.
  • the spool stroke amount that is less than the predetermined value X corresponds to the amount of operation of the second operation lever 25L that has been finely operated.
  • An area where the spool stroke amount is larger than the fine operation area is also referred to as a normal operation area.
  • the spool stroke amount that is equal to or greater than the predetermined value X corresponds to the operation amount at which the second operation lever 25L is normally operated.
  • the value of the cylinder speed corresponding to the spool stroke amount of the line LB in the fine operation area is larger than the value of the cylinder speed corresponding to the spool stroke amount of the line LA.
  • the estimated speed determination unit 52 of the work machine controller 26 is based on the second cylinder speed table by the meter-out control of the line LB when the operation amount (arm operation amount) for operating the second operation lever 25L is less than the predetermined amount.
  • the value of the cylinder speed may be set to the estimated speed of the hydraulic cylinder 60.
  • the cylinder speed calculation unit 52B of the estimated speed determination unit 52 performs the second by meter out control of the line LB.
  • the cylinder speed value based on the two-cylinder speed table is set to the estimated speed of the hydraulic cylinder 60.
  • the target speed determination unit 54 of the work unit controller 26 determines the boom target speed Vc_bm_lmt based on the arm estimated speed Vc_am according to the operation amount of the second control lever 25L. Thereby, it becomes possible to stabilize the blade edge 8a of the bucket 8 and to suppress hunting.
  • the method of calculating the cylinder speed using the cylinder speed table showing the relationship between the cylinder speed and the spool stroke has been described, but in the storage unit 58, the cylinder speed and the PPC pressure (pilot pressure) A cylinder speed table indicating the relationship is stored, and the correlation data can be used to calculate the cylinder speed.
  • control valve 27 may be fully opened, the pressure may be detected by the pressure sensor 66 and the pressure sensor 67, and the pressure sensor 66 and the pressure sensor 67 may be calibrated based on the detected values. .
  • the control valve 27 When the control valve 27 is fully opened, the pressure sensor 66 and the pressure sensor 67 output the same detection value.
  • the control valve 27 When the control valve 27 is fully opened, when the pressure sensor 66 and the pressure sensor 67 output different detection values, correlation data indicating the relationship between the detection value of the pressure sensor 66 and the detection value of the pressure sensor 67 is obtained. May be
  • the operating device 25 is a pilot hydraulic system.
  • the operating device 25 may be an electric lever system.
  • an operation lever detection unit such as a potentiometer that detects an operation amount of the operation lever of the operation device 25 and outputs a voltage value according to the operation amount to the work machine controller 26 may be provided.
  • the work machine controller 26 may adjust the pilot hydraulic pressure by outputting a control signal to the control valve 27 based on the detection result of the operation lever detection unit. This control is performed by the work machine controller, but may be performed by another controller such as the sensor controller 30.
  • Acquisition of the position of the hydraulic shovel in the global coordinate system may be performed by other positioning means in addition to GNSS. Therefore, acquisition of distance d of blade edge 8a and design topography may be performed not only by GNSS but by other positioning means.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Operation Control Of Excavators (AREA)

Abstract

 作業車両は、ブームと、アームと、バケットと、アームシリンダと、方向制御弁と、算出部と、速度決定部とを備える。アームシリンダは、アームを駆動する。方向制御弁は、移動可能なスプールを有し、スプールの移動によりアームシリンダに作動油を供給してアームシリンダを動作させる。算出部は、アーム操作レバーの操作量に従う方向制御弁のスプールの移動量とアームシリンダの速度との相関関係に基づいてアームシリンダの推定速度を算出する。速度決定部は、アームシリンダの推定速度に基づいて、ブームの目標速度を決定する。算出部は、アーム操作レバーの操作量が所定量未満の場合には、アーム操作レバーの操作量に従う方向制御弁のスプールの移動量とアームシリンダの速度との相関関係に従うアームシリンダの速度よりも大きい速度をアームシリンダの推定速度として算出する。

Description

作業車両および作業車両の制御方法
 本発明は、作業車両および作業車両の制御方法に関する。
 油圧ショベルのような作業車両は、ブームとアームとバケットとを有する作業機を備える。作業車両の制御において、掘削対象の目標形状である目標設計地形に基づいてバケットを移動させる自動制御が知られている。
 特許文献1には、バケットの刃先を基準面に沿って移動させることによりバケットの刃先に当接する土砂を掻き均し、平らな基準面に対応する面を作るならい作業を自動制御する方式が提案されている。
特開平9-328774号公報
 上記ならい作業において、アーム操作レバーを操作した際に、バケットが自重により落下する。バケットの自重落下により、油圧シリンダの速度は、アーム操作レバーによる油圧シリンダの想定された速度以上となっている。アーム操作レバーの操作量に基づいて想定される油圧シリンダの想定速度と実速度との乖離は、アーム操作レバーの操作量が少ない微操作の場合に大きい。このため、ならい作業において、バケットの刃先が安定せずハンチングが生じる可能性がある。
 本発明は、上記の課題を解決するためになされたものであって、ハンチングを抑制することが可能な作業車両および作業車両の制御方法を提供することを目的とする。
 その他の課題と新規な特徴は、本明細書の記述および添付図面から明らかになるであろう。
 本発明のある局面に従う作業車両は、ブームと、アームと、バケットと、アームシリンダと、方向制御弁と、算出部と、速度決定部とを備える。アームシリンダは、アームを駆動する。方向制御弁は、移動可能なスプールを有し、スプールの移動によりアームシリンダに作動油を供給してアームシリンダを動作させる。算出部は、アーム操作レバーの操作量に従う方向制御弁のスプールの移動量とアームシリンダの速度との相関関係に基づいてアームシリンダの推定速度を算出する。速度決定部は、アームシリンダの推定速度に基づいて、ブームの目標速度を決定する。算出部は、アーム操作レバーの操作量が所定量未満の場合には、アーム操作レバーの操作量に従う方向制御弁のスプールの移動量とアームシリンダの速度との相関関係に従うアームシリンダの速度よりも大きい速度をアームシリンダの推定速度として算出する。
 本発明の作業車両によれば、アーム操作レバーの操作量が所定量未満の場合には、アーム操作レバーの操作量に従う方向制御弁のスプールの移動量とアームシリンダの速度との相関関係に従うアームシリンダの速度よりも大きい速度をアームシリンダの推定速度として算出することにより、バケットの自重落下が生じた場合でも目標速度の調整に従いアームシリンダの実速度との乖離が抑制される。これにより、速度決定部は、適正なブームの速度に決定することが可能となりバケットの刃先を安定させてハンチングを抑制することが可能となる。
 好ましくは、算出部は、方向制御弁のスプールの移動量と、方向制御弁のスプールの移動量に従ってアームシリンダに流入する作動油の供給量に基づき規定されるアームシリンダの速度との相関関係に基づいて、アームシリンダの推定速度を算出する。
 上記によれば、いわゆるメータイン制御によりアームシリンダの推定速度を算出して制御することにより圧損の少ない効率的な制御が可能である。
 好ましくは、アーム操作レバーの操作量に従う方向制御弁のスプールの移動量とアームシリンダの速度との相関関係は、第1速度テーブルに相当する。算出部は、アーム操作レバーの操作量が所定量以上の場合には、第1速度テーブルに従うアームシリンダの速度を推定速度として算出する。
 上記によれば、アーム操作レバーの操作量が所定量以上の場合には、第1速度テーブルに従うアームシリンダの速度を推定速度として算出することにより、精度の高いアームシリンダの推定速度を算出することが可能となり、バケットの刃先を安定させた制御が可能である。
 好ましくは、算出部は、アーム操作レバーの操作量が所定量未満の場合には、第2速度テーブルに基づいてアームシリンダの推定速度を算出する。第2速度テーブルは、方向制御弁のスプールの移動量と、方向制御弁のスプールの移動量に従ってアームシリンダから排出量に基づき規定されるアームシリンダの速度との相関関係を示すものである。
 上記によれば、アーム操作レバーの操作量が所定量未満の場合には、第2速度テーブルに基づいてアームシリンダの目標速度を算出することにより、バケットの自重落下が生じた場合でも目標速度の調整に従い実測度との乖離を抑制される。これにより、速度決定部は、適正なブームの速度に決定することが可能となりバケットの刃先を安定させてハンチングを抑制することが可能となる。
 本発明のある局面に従う作業車両の制御方法は、ブームと、アームと、バケットとを備える、作業車両の制御方法であって、アーム操作レバーの操作量に従う方向制御弁のスプールの移動量とアームシリンダの速度との相関関係に基づいてアームシリンダの推定速度を算出するステップと、アームシリンダの推定速度に基づいて、ブームの目標速度を決定するステップとを備える。算出するステップは、アーム操作レバーの操作量が所定量未満の場合には、アーム操作レバーの操作量に従う方向制御弁のスプールの移動量とアームシリンダの速度との相関関係に従うアームシリンダの速度よりも大きい速度をアームシリンダの推定速度として算出するステップを含む。
 本発明の作業車両の制御方法によれば、アーム操作レバーの操作量が所定量未満の場合には、アーム操作レバーの操作量に従う方向制御弁のスプールの移動量とアームシリンダの速度との相関関係に従うアームシリンダの速度よりも大きい速度をアームシリンダの推定速度として算出することにより、バケットの自重落下が生じた場合でも目標速度の調整に従いアームシリンダの実速度との乖離が抑制される。これにより、適正なブームの速度に決定することが可能となりバケットの刃先を安定させてハンチングを抑制することが可能となる。
 作業車両および作業車両の制御方法に関して、ハンチングを抑制することが可能である。
実施形態に基づく作業車両100の外観図である。 実施形態に基づく作業車両100を模式的に説明する図である。 実施形態に基づく制御システム200の構成を示す機能ブロック図である。 実施形態に基づく油圧システムの構成を示す図である。 実施形態に基づくならい制御(制限掘削制御)が行われている場合の作業機2の動作を模式的に示す図である。 実施形態に基づくならい制御を実行する制御システム200の構成を示す機能ブロック図である。 実施形態に基づくバケット8の刃先8aと目標設計地形Uとの間の距離dを取得することを説明する図である。 実施形態に基づく推定速度決定部52の演算処理を説明する機能ブロック図である。 実施形態に基づく垂直速度成分Vcy_am、Vcy_bktの算出方式を説明する図である。 実施形態に基づくならい制御における作業機2全体の制限速度テーブルの一例を説明する図である。 実施形態に基づくブーム目標速度Vc_bm_lmtを算出する方式を説明する図である 実施形態に基づく作業機制御部57の構成を示す機能ブロック図である。 実施形態に基づく作業車両100のならい制御(制限掘削制御)を説明するフロー図である。 実施形態に基づくスプール80の移動量(スプールストローク)と油圧シリンダ60のシリンダ速度との関係が示されたシリンダ速度テーブルを説明する図である。
 以下、本発明に係る実施形態について図面を参照しながら説明する。なお、本発明はこれに限定されない。以下で説明する各実施形態の要件は、適宜組み合わせることが可能である。また、一部の構成要素を用いない場合もある。
 <作業車両の全体構成>
 図1は、実施形態に基づく作業車両100の外観図である。
 図1に示されるように、作業車両100として、本例においては、おもに油圧ショベルを例に挙げて説明する。
 作業車両100は、車両本体1と、油圧により作動する作業機2とを有する。なお、後述するように、作業車両100には掘削制御を実行する制御システム200(図3)が搭載されている。
 車両本体1は、旋回体3と、走行装置5とを有する。走行装置5は、一対の履帯5Crを有する。作業車両100は、履帯5Crの回転により走行可能である。なお、走行装置5が車輪(タイヤ)を有していてもよい。
 旋回体3は、走行装置5の上に配置され、かつ走行装置5により支持されている。旋回体3は、旋回軸AXを中心として走行装置5に対して旋回可能である。
 旋回体3は、運転室4を有する。この運転室4には、オペレータが着座する運転席4Sが設けられる。オペレータは、運転室4において作業車両100を操作可能である。
 本例においては、運転席4Sに着座したオペレータを基準として各部の位置関係について説明する。前後方向とは、運転席4Sに着座したオペレータの前後方向をいう。左右方向とは、運転席4Sに着座したオペレータの左右方向をいう。運転席4Sに着座したオペレータに正対する方向を前方向とし、前方向に対向する方向を後方向とする。運転席4Sに着座したオペレータが正面に正対したときの右側、左側をそれぞれ右方向、左方向とする。
 旋回体3は、エンジンが収容されるエンジンルーム9と、旋回体3の後部に設けられるカウンタウェイトとを有する。旋回体3において、エンジンルーム9の前方に手すり19が設けられる。エンジンルーム9には、図示しないエンジン及び油圧ポンプなどが配置されている。
 作業機2は、旋回体3に支持されている。作業機2は、ブーム6と、アーム7と、バケット8と、ブームシリンダ10と、アームシリンダ11と、バケットシリンダ12とを有する。ブーム6は旋回体3に接続されている。アーム7はブーム6に接続されている。バケット8はアーム7に接続されている。
 ブームシリンダ10は、ブーム6を駆動する。アームシリンダ11は、アーム7を駆動する。バケットシリンダ12は、バケット8を駆動する。ブームシリンダ10、アームシリンダ11、及びバケットシリンダ12のそれぞれは、作動油によって駆動される油圧シリンダである。
 ブーム6の基端部は、ブームピン13を介して旋回体3に接続される。アーム7の基端部は、アームピン14を介してブーム6の先端部に接続される。バケット8は、バケットピン15を介してアーム7の先端部に接続される。
 ブーム6は、ブームピン13を中心に回転可能である。アーム7は、アームピン14を中心に回転可能である。バケット8は、バケットピン15を中心に回転可能である。
 アーム7及びバケット8のそれぞれは、ブーム6の先端側で移動可能な可動部材である。
 図2(A)および図2(B)は、実施形態に基づく作業車両100を模式的に説明する図である。図2(A)には、作業車両100の側面図が示される。図2(B)には、作業車両100の背面図が示される。
 図2(A)および図2(B)に示されるように、ブーム6の長さL1は、ブームピン13とアームピン14との距離である。アーム7の長さL2は、アームピン14とバケットピン15との距離である。バケット8の長さL3は、バケットピン15とバケット8の刃先8aとの距離である。バケット8は、複数の刃を有し、本例においては、バケット8の先端部を刃先8aと称する。
 なお、バケット8は、刃を有していなくてもよい。バケット8の先端部は、ストレート形状の鋼板で形成されていてもよい。
 作業車両100は、ブームシリンダストロークセンサ16と、アームシリンダストロークセンサ17と、バケットシリンダストロークセンサ18とを有する。ブームシリンダストロークセンサ16はブームシリンダ10に配置される。アームシリンダストロークセンサ17はアームシリンダ11に配置される。バケットシリンダストロークセンサ18はバケットシリンダ12に配置される。なお、ブームシリンダストロークセンサ16、アームシリンダストロークセンサ17およびバケットシリンダストロークセンサ18は総称してシリンダストロークセンサとも称する。
 ブームシリンダストロークセンサ16の検出結果に基づいて、ブームシリンダ10のストローク長さが求められる。アームシリンダストロークセンサ17の検出結果に基づいて、アームシリンダ11のストローク長さが求められる。バケットシリンダストロークセンサ18の検出結果に基づいて、バケットシリンダ12のストローク長さが求められる。
 なお、本例においては、ブームシリンダ10、アームシリンダ11およびバケットシリンダ12のストローク長さをそれぞれブームシリンダ長、アームシリンダ長およびバケットシリンダ長とも称する。また、本例においては、ブームシリンダ長、アームシリンダ長、及びバケットシリンダ長を総称してシリンダ長データLとも称する。なお、角度センサを用いてストローク長さを検出する方式を採用することも可能である。
 作業車両100は、作業車両100の位置を検出可能な位置検出装置20を備えている。
 位置検出装置20は、アンテナ21と、グローバル座標演算部23と、IMU(Inertial Measurement Unit)24とを有する。
 アンテナ21は、たとえばGNSS(Global Navigation Satellite Systems:全地球航法衛星システム)用のアンテナである。アンテナ21は、たとえばRTK-GNSS(Real Time Kinematic-Global Navigation Satellite Systems)用アンテナである。
 アンテナ21は、旋回体3に設けられる。本例においては、アンテナ21は、旋回体3の手すり19に設けられる。なお、アンテナ21は、エンジンルーム9の後方向に設けられてもよい。例えば、旋回体3のカウンタウェイトにアンテナ21が設けられてもよい。アンテナ21は、受信した電波(GNSS電波)に応じた信号をグローバル座標演算部23に出力する。
 グローバル座標演算部23は、グローバル座標系におけるアンテナ21の設置位置P1を検出する。グローバル座標系は、作業エリアに設置した基準位置Prを元にした3次元座標系(Xg、Yg、Zg)である。本例においては、基準位置Prは、作業エリアに設定された基準杭の先端の位置である。また、ローカル座標系とは、作業車両100を基準とした、(X、Y、Z)で示される3次元座標系である。ローカル座標系の基準位置は、旋回体3の旋回軸(旋回中心)AXに位置する基準位置P2を示すデータである。
 本例においては、アンテナ21は、車幅方向に互いに離れるように旋回体3に設けられた第1アンテナ21A及び第2アンテナ21Bを有する。
 グローバル座標演算部23は、第1アンテナ21Aの設置位置P1a及び第2アンテナ21Bの設置位置P1bを検出する。グローバル座標演算部23は、グローバル座標で表される基準位置データPを取得する。本例においては、基準位置データPは、旋回体3の旋回軸(旋回中心)AXに位置する基準位置P2を示すデータである。なお、基準位置データPは、設置位置P1を示すデータでもよい。
 本例においては、グローバル座標演算部23は、2つの設置位置P1a及び設置位置P1bに基づいて旋回体方位データQを生成する。旋回体方位データQは、設置位置P1aと設置位置P1bとで決定される直線がグローバル座標の基準方位(例えば北)に対してなす角に基づいて決定される。旋回体方位データQは、旋回体3(作業機2)が向いている方位を示す。グローバル座標演算部23は、後述する表示コントローラ28に基準位置データP及び旋回体方位データQを出力する。
 IMU24は、旋回体3に設けられる。本例においては、IMU24は、運転室4の下部に配置される。旋回体3において、運転室4の下部に高剛性のフレームが配置される。IMU24は、そのフレーム上に配置される。なお、IMU24は、旋回体3の旋回軸AX(基準位置P2)の側方(右側又は左側)に配置されてもよい。IMU24は、車両本体1の左右方向に傾斜する傾斜角θ4と、車両本体1の前後方向に傾斜する傾斜角θ5とを検出する。
 <制御システムの構成>
 次に、実施形態に基づく制御システム200の概要について説明する。
 図3は、実施形態に基づく制御システム200の構成を示す機能ブロック図である。
 図3に示されるように、制御システム200は、作業機2を用いる掘削処理を制御する。本例においては、掘削処理の制御は、ならい制御を有する。
 ならい制御は、バケットの刃先が設計地形に沿って移動することによりバケットの刃先に当接する土砂を掻き均し、平らな設計地形に対応する面を作るならい作業を自動制御することを意味し、制限掘削制御とも称される。
 ならい制御は、オペレータによるアーム操作があり、バケットの刃先と設計地形との距離および刃先の速度が基準内である場合に実行される。オペレータは、ならい制御中は通常、ブームを下げる方向に常にブームを操作しつつ、アームを操作する。
 制御システム200は、ブームシリンダストロークセンサ16と、アームシリンダストロークセンサ17と、バケットシリンダストロークセンサ18と、アンテナ21と、グローバル座標演算部23と、IMU24と、操作装置25と、作業機コントローラ26と、圧力センサ66及び圧力センサ67と、制御弁27と、方向制御弁64と、表示コントローラ28と、表示部29と、センサコントローラ30と、マンマシンインターフェース部32とを有する。
 操作装置25は、運転室4に配置される。オペレータにより操作装置25が操作される。操作装置25は、作業機2を駆動するオペレータ操作を受け付ける。本例においては、操作装置25は、パイロット油圧方式の操作装置である。
 方向制御弁64により、油圧シリンダに対する作動油の供給量が調整される。方向制御弁64は、第1油圧室および第2油圧室に供給される油によって作動する。なお、本例においては、油圧シリンダ(ブームシリンダ10、アームシリンダ11、及びバケットシリンダ12)を作動するために、その油圧シリンダに供給される油は作動油とも称される。また、方向制御弁64を作動するためにその方向制御弁64に供給される油はパイロット油と称される。また、パイロット油の圧力はパイロット油圧とも称される。
 作動油及びパイロット油は、同一の油圧ポンプから送出されてもよい。例えば、油圧ポンプから送出された作動油の一部が減圧弁で減圧され、その減圧された作動油がパイロット油として使用されてもよい。また、作動油を送出する油圧ポンプ(メイン油圧ポンプ)と、パイロット油を送出する油圧ポンプ(パイロット油圧ポンプ)とが別の油圧ポンプでもよい。
 操作装置25は、第1操作レバー25Rと、第2操作レバー25Lとを有する。第1操作レバー25Rは、例えば運転席4Sの右側に配置される。第2操作レバー25Lは、例えば運転席4Sの左側に配置される。第1操作レバー25R及び第2操作レバー25Lでは、前後左右の動作が2軸の動作に対応する。
 第1操作レバー25Rにより、ブーム6及びバケット8が操作される。
 第1操作レバー25Rの前後方向の操作は、ブーム6の操作に対応し、前後方向の操作に応じてブーム6の下げ動作及び上げ動作が実行される。ブーム6を操作するためにレバー操作され、パイロット油路450にパイロット油が供給された場合に圧力センサ66に発生する検出圧力をMBとする。
 第1操作レバー25Rの左右方向の操作は、バケット8の操作に対応し、左右方向の操作に応じてバケット8の掘削動作及び開放動作が実行される。バケット8を操作するためにレバー操作され、パイロット油路450にパイロット油が供給された場合に圧力センサ66に発生する検出圧力をMTとする。
 第2操作レバー25Lにより、アーム7及び旋回体3が操作される。
 第2操作レバー25Lの前後方向の操作は、アーム7の操作に対応し、前後方向の操作に応じてアーム7の上げ動作及び下げ動作が実行される。アーム7を操作するためにレバー操作され、パイロット油路450にパイロット油が供給された場合に圧力センサ66に発生する検出圧力をMAとする。
 第2操作レバー25Lの左右方向の操作は、旋回体3の旋回に対応し、左右方向の操作に応じて旋回体3の右旋回動作及び左旋回動作が実行される。
 本例においては、ブーム6の上下方向への動作は、それぞれ上げ動作、下降する動作は下げ動作とも称する。また、アーム7の上下方向への動作は、それぞれダンプ動作、掘削動作とも称する。バケット8の上下方向への動作は、それぞれダンプ動作、掘削動作とも称する。
 メイン油圧ポンプから送出され、減圧弁によって減圧されたパイロット油が操作装置25に供給される。操作装置25の操作量に基づいてパイロット油圧が調整される。
 パイロット油路450には、圧力センサ66及び圧力センサ67が配置される。圧力センサ66及び圧力センサ67は、パイロット油圧を検出する。圧力センサ66及び圧力センサ67の検出結果は、作業機コントローラ26に出力される。
 第1操作レバー25Rは、ブーム6の駆動のために前後方向に操作される。前後方向に関する第1操作レバー25Rの操作量(ブーム操作量)に応じて、ブーム6を駆動するためのブームシリンダ10に供給される作動油の流れ方向および流量が方向制御弁64によって調整される。
 第1操作レバー25Rは、バケット8の駆動のために左右方向に操作される。左右方向に関する第1操作レバー25Rの操作量(バケット操作量)に応じて、バケット8を駆動するためのバケットシリンダ12に供給される作動油の流れ方向および流量が方向制御弁64によって調整される。
 第2操作レバー25Lは、アーム7の駆動のために前後方向に操作される。前後方向に関する第2操作レバー25Lの操作量(アーム操作量)に応じて、アーム7を駆動するためのアームシリンダ11に供給される作動油の流れ方向および流量が方向制御弁64によって調整される。
 第2操作レバー25Lは、旋回体3の駆動のために左右方向に操作される。左右方向に関する第2操作レバー25Lの操作量に応じて、旋回体3を駆動するための油圧アクチュエータに供給される作動油の流れ方向および流量が方向制御弁64によって調整される。
 なお、第1操作レバー25Rの左右方向の操作がブーム6の操作に対応し、前後方向の操作がバケット8の操作に対応してもよい。なお、第2操作レバー25Lの左右方向がアーム7の操作に対応し、前後方向の操作が旋回体3の操作に対応してもよい。
 制御弁27は、油圧シリンダ(ブームシリンダ10、アームシリンダ11、及びバケットシリンダ12)に対する作動油の供給量を調整する。制御弁27は、作業機コントローラ26からの制御信号に基づいて作動する。
 マンマシンインターフェース部32は、入力部321と表示部(モニタ)322とを有する。
 本例においては、入力部321は、表示部322の周囲に配置される操作ボタンを有する。なお、入力部321はタッチパネルを有していてもよい。マンマシンインターフェース部32を、マルチモニタとも称する。
 表示部322は、基本情報として燃料残量および冷却水温度等を表示する。
 入力部321は、オペレータによって操作される。入力部321の操作により生成された指令信号は、作業機コントローラ26に出力される。
 センサコントローラ30は、ブームシリンダストロークセンサ16の検出結果に基づいて、ブームシリンダ長を算出する。ブームシリンダストロークセンサ16は、周回動作に伴うパルスをセンサコントローラ30に出力する。センサコントローラ30は、ブームシリンダストロークセンサ16から出力されたパルスに基づいて、ブームシリンダ長を算出する。
 同様に、センサコントローラ30は、アームシリンダストロークセンサ17の検出結果に基づいて、アームシリンダ長を算出する。センサコントローラ30は、バケットシリンダストロークセンサ18の検出結果に基づいて、バケットシリンダ長を算出する。
 センサコントローラ30は、ブームシリンダストロークセンサ16の検出結果に基づいて取得されたブームシリンダ長から、旋回体3の垂直方向に対するブーム6の傾斜角θ1を算出する。
 センサコントローラ30は、アームシリンダストロークセンサ17の検出結果に基づいて取得されたアームシリンダ長から、ブーム6に対するアーム7の傾斜角θ2を算出する。
 センサコントローラ30は、バケットシリンダストロークセンサ18の検出結果に基づいて取得されたバケットシリンダ長から、アーム7に対するバケット8の刃先8aの傾斜角θ3を算出する。
 上記算出結果である傾斜角θ1、θ2、θ3と、基準位置データP、旋回体方位データQ、及びシリンダ長データLに基づいて、作業車両100のブーム6、アーム7およびバケット8の位置を特定することが可能となり、バケット8の3次元位置を示すバケット位置データを生成することが可能である。
 なお、ブーム6の傾斜角θ1、アーム7の傾斜角θ2、及びバケット8の傾斜角θ3は、シリンダストロークセンサで検出されなくてもよい。ロータリーエンコーダのような角度検出器でブーム6の傾斜角θ1が検出されてもよい。角度検出器は、旋回体3に対するブーム6の屈曲角度を検出して、傾斜角θ1を検出する。同様に、アーム7の傾斜角θ2がアーム7に取り付けられた角度検出器で検出されてもよい。バケット8の傾斜角θ3がバケット8に取り付けられた角度検出器で検出されてもよい。
 <油圧回路の構成>
 図4は、実施形態に基づく油圧システムの構成を示す図である。
 図4に示されるように、油圧システム300は、ブームシリンダ10、アームシリンダ11、及びバケットシリンダ12(複数の油圧シリンダ60)と、旋回体3を旋回させる旋回モータ63とを備える。なお、ここで、ブームシリンダ10を油圧シリンダ10(60)とも表記する。他の油圧シリンダについても同様である。
 油圧シリンダ60は、図示しないメイン油圧ポンプから供給された作動油によって作動する。旋回モータ63は、油圧モータであり、メイン油圧ポンプから供給された作動油によって作動する。
 本例においては、各油圧シリンダ60に対して作動油が流れる方向および流量を制御する方向制御弁64が設けられる。メイン油圧ポンプから供給された作動油は、方向制御弁64を介して、各油圧シリンダ60に供給される。また、旋回モータ63に対して方向制御弁64が設けられる。
 各油圧シリンダ60は、キャップ側(ボトム側)油室40Aと、ロッド側(ヘッド側)油室40Bとを有する。
 方向制御弁64は、ロッド状のスプールを動かして作動油が流れる方向を切り替えるスプール方式である。スプールが軸方向に移動することにより、キャップ側油室40Aに対する作動油の供給と、ロッド側油室40Bに対する作動油の供給とが切り替わる。また、スプールが軸方向に移動することにより、油圧シリンダ60に対する作動油の供給量(単位時間当たりの供給量)が調整される。油圧シリンダ60に対する作動油の供給量が調整されることにより、シリンダ速度が調整される。シリンダ速度を調整することにより、ブーム6、アーム7およびバケット8の速度が制御される。本例においては、方向制御弁64が、スプールの移動により作業機2を駆動する油圧シリンダ60に対する作動油の供給量を調整可能な調整装置として機能する。
 各方向制御弁64には、スプールの移動距離(スプールストローク)を検出するスプールストロークセンサ65が設けられる。スプールストロークセンサ65の検出信号は、作業機コントローラ26に出力される。
 各方向制御弁64の駆動は、操作装置25によって調整される。本例においては、操作装置25は、パイロット油圧方式の操作装置である。
 メイン油圧ポンプから送出され、減圧弁によって減圧されたパイロット油が操作装置25に供給される。
 操作装置25は、パイロット油圧調整弁を有する。操作装置25の操作量に基づいて、パイロット油圧が調整される。パイロット油圧によって、方向制御弁64が駆動される。操作装置25によりパイロット油圧が調整されることによって、軸方向に関するスプールの移動量及び移動速度が調整される。また、操作装置25によりキャップ側油室40Aに対する作動油の供給と、ロッド側油室40Bに対する作動油の供給とが切り替わる。
 操作装置25と各方向制御弁64とは、パイロット油路450を介して接続される。本例においては、パイロット油路450に、制御弁27、圧力センサ66、及び圧力センサ67が配置される。
 各制御弁27の両側に、パイロット油圧を検出する圧力センサ66及び圧力センサ67が設けられる。本例においては、圧力センサ66は、操作装置25と制御弁27との間の油路451に配置される。圧力センサ67は、制御弁27と方向制御弁64との間の油路452に配置される。圧力センサ66は、制御弁27によって調整される前のパイロット油圧を検出する。圧力センサ67は、制御弁27によって調整されたパイロット油圧を検出する。圧力センサ66及び圧力センサ67の検出結果は、作業機コントローラ26に出力される。
 制御弁27は、作業機コントローラ26からの制御信号(EPC電流)に基づいて、パイロット油圧を調整する。制御弁27は、電磁比例制御弁であり、作業機コントローラ26からの制御信号に基づいて制御される。制御弁27は、制御弁27Bと、制御弁27Aとを有する。制御弁27Bは、方向制御弁64の第2受圧室に供給されるパイロット油のパイロット油圧を調整して、方向制御弁64を介してキャップ側油室40Aに供給される作動油の供給量を調整可能である。制御弁27Aは、方向制御弁64の第1受圧室に供給されるパイロット油のパイロット油圧を調整して、方向制御弁64を介してロッド側油室40Bに供給される作動油の供給量を調整可能である。
 なお、本例においては、パイロット油路450のうち、操作装置25と制御弁27との間のパイロット油路450は油路(上流油路)451と称される。また、制御弁27と方向制御弁64との間のパイロット油路450は油路(下流油路)452と称される。
 パイロット油は、油路452を介して各方向制御弁64に供給される。
 油路452は、第1受圧室に接続される油路452Aと、第2受圧室に接続される油路452Bとを有する。
 方向制御弁64の第2受圧室に対して、パイロット油が油路452Bを介して供給されると、そのパイロット油圧に応じてスプールが移動する。方向制御弁64を介してキャップ側油室40Aに作動油が供給される。キャップ側油室40Aに対する作動油の供給量は、操作装置25の操作量に応じたスプールの移動量により調整される。
 方向制御弁64の第1受圧室に対して、パイロット油が油路452Aを介して供給されると、そのパイロット油圧に応じてスプールが移動する。方向制御弁64を介してロッド側油室40Bに作動油が供給される。ロッド側油室40Bに対する作動油の供給量は、操作装置25の操作量によるスプールの移動量により調整される。
 したがって、操作装置25によりパイロット油圧が調整されたパイロット油が方向制御弁64に供給されることにより、軸方向に関するスプールの位置が調整される。
 油路451は、油路452Aと操作装置25とを接続する油路451Aと、油路452Bと操作装置25とを接続する油路451Bとを有する。
 [操作装置25の操作と油圧システムの動作について]
 上述のように、操作装置25の操作により、ブーム6は、下げ動作及び上げ動作の2種類の動作を実行する。
 ブーム6の上げ動作が実行されるように操作装置25が操作されることにより、ブームシリンダ10に接続された方向制御弁64に、油路451B及び油路452Bを介して、パイロット油が供給される。
 これにより、メイン油圧ポンプからの作動油がブームシリンダ10に供給され、ブーム6の上げ動作が実行される。
 ブーム6の下げ動作が実行されるように操作装置25が操作されることにより、ブームシリンダ10に接続された方向制御弁64に、油路451A及び油路452Aを介して、パイロット油が供給される。
 これにより、メイン油圧ポンプからの作動油がブームシリンダ10に供給され、ブーム6の下げ動作が実行される。
 本例においては、ブームシリンダ10が伸長することにより、ブーム6が上げ動作し、ブームシリンダ10が縮退することにより、ブーム6が下げ動作する。ブームシリンダ10のキャップ側油室40Aに作動油が供給されることにより、ブームシリンダ10が伸長し、ブーム6が上げ動作する。ブームシリンダ10のロッド側油室40Bに作動油が供給されることにより、ブームシリンダ10が縮退し、ブーム6が下げ動作する。
 また、操作装置25の操作により、アーム7は、下げ動作及び上げ動作の2種類の動作を実行する。
 アーム7の下げ動作が実行されるように操作装置25を操作することにより、アームシリンダ11に接続された方向制御弁64に、油路451B及び油路452Bを介して、パイロット油が供給される。
 これにより、メイン油圧ポンプからの作動油がアームシリンダ11に供給され、アーム7の下げ動作が実行される。
 アーム7の上げ動作が実行されるように操作装置25を操作することにより、アームシリンダ11に接続された方向制御弁64に、油路451A及び油路452Aを介して、パイロット油が供給される。
 これにより、メイン油圧ポンプからの作動油がアームシリンダ11に供給され、アーム7の上げ動作が実行される。
 本例においては、アームシリンダ11が伸長することにより、アーム7が下げ動作(掘削動作)し、アームシリンダ11が縮退することにより、アーム7が上げ動作(ダンプ動作)する。アームシリンダ11のキャップ側油室40Aに作動油が供給されることにより、アームシリンダ11が伸長し、アーム7が下げ動作する。アームシリンダ11のロッド側油室40Bに作動油が供給されることにより、アームシリンダ11が縮退し、アーム7が上げ動作する。
 また、操作装置25の操作により、バケット8は、下げ動作及び上げ動作の2種類の動作を実行する。
 バケット8の下げ動作が実行されるように操作装置25を操作することにより、バケットシリンダ12に接続された方向制御弁64に、油路451B及び油路452Bを介して、パイロット油が供給される。
 これにより、メイン油圧ポンプからの作動油がバケットシリンダ12に供給され、バケット8の下げ動作が実行される。
 バケット8の上げ動作が実行されるように操作装置25を操作することにより、バケットシリンダ12に接続された方向制御弁64に、油路451A及び油路452Aを介して、パイロット油が供給される。方向制御弁64はパイロット油圧に基づいて作動する。
 これにより、メイン油圧ポンプからの作動油がバケットシリンダ12に供給され、バケット8の上げ動作が実行される。
 本例においては、バケットシリンダ12が伸長することにより、バケット8が下げ動作(掘削動作)し、バケットシリンダ12が縮退することにより、バケット8が上げ動作(ダンプ動作)する。バケットシリンダ12のキャップ側油室40Aに作動油が供給されることにより、バケットシリンダ12が伸長し、バケット8が下げ動作する。バケットシリンダ12のロッド側油室40Bに作動油が供給されることにより、バケットシリンダ12が縮退し、バケット8が上げ動作する。
 また、操作装置25の操作により、旋回体3は、右旋回動作及び左旋回動作の2種類の動作を実行する。
 旋回体3の右旋回動作が実行されるように操作装置25が操作されることにより、作動油が旋回モータ63に供給される。旋回体3の左旋回動作が実行されるように操作装置25が操作されることにより、作動油が旋回モータ63に供給される。
 [通常制御およびならい制御(制限掘削制御)と油圧システムの動作について]
 ならい制御(制限掘削制御)を実行しない、通常制御について説明する。
 通常制御の場合、作業機2は、操作装置25の操作量に従って動作する。
 具体的には、作業機コントローラ26は、制御弁27を開放する。制御弁27を開放することにより、油路451のパイロット油圧と油路452のパイロット油圧とは等しくなる。制御弁27が開放された状態で、パイロット油圧(PPC圧)は、操作装置25の操作量に基づいて調整される。これにより、方向制御弁64が調整されて、上記で説明したブーム6、アーム7、バケット8の上げ動作および下げ動作を実行することが可能である。
 一方、ならい制御(制限掘削制御)について説明する。
 ならい制御(制限掘削制御)の場合、作業機2は、操作装置25の操作に基づいて作業機コントローラ26によって制御される。
 具体的には、作業機コントローラ26は、制御弁27に制御信号を出力する。油路451は、例えばパイロット油圧調整弁の作用により所定の圧力を有する。
 制御弁27は、作業機コントローラ26の制御信号に基づいて作動する。油路451の作動油は、制御弁27を介して、油路452に供給される。したがって、油路452の作動油の圧力は、制御弁27により調整(減圧)することが可能である。
 油路452の作動油の圧力が、方向制御弁64に作用する。これにより、方向制御弁64は、制御弁27で制御されたパイロット油圧に基づいて作動する。
 たとえば、作業機コントローラ26は、制御弁27A及び制御弁27Bの少なくとも一方に制御信号を出力して、アームシリンダ11に接続された方向制御弁64に対するパイロット油圧を調整することができる。制御弁27Aにより圧力が調整された作動油が方向制御弁64に供給されることにより、スプールは軸方向に関して一方側に移動する。制御弁27Bにより圧力が調整された作動油が方向制御弁64に供給されることにより、スプールは軸方向に関して他方側に移動する。これにより、軸方向に関するスプールの位置が調整される。
 また、同様に作業機コントローラ26は、制御弁27A及び制御弁27Bの少なくとも一方に制御信号を出力して、バケットシリンダ12に接続された方向制御弁64に対するパイロット油圧を調整することができる。
 また、同様に作業機コントローラ26は、制御弁27A及び制御弁27Bの少なくとも一方に制御信号を出力して、ブームシリンダ10に接続された方向制御弁64に対するパイロット油圧を調整することができる。
 さらに、作業機コントローラ26は、制御弁27Cに制御信号を出力して、ブームシリンダ10に接続された方向制御弁64に対するパイロット油圧を調整する。
 これにより、作業機コントローラ26は、バケット8の刃先8aが目標設計地形Uに侵入しないように、ブーム6の動きを制御(介入制御)する。
 本例において、目標設計地形Uに対する刃先8aの侵入が抑制されるように、ブームシリンダ10に接続された制御弁27に制御信号を出力して、ブーム6の位置を制御することを介入制御と称する。
 具体的には、作業機コントローラ26は、掘削対象の目標形状である設計地形を示す目標設計地形Uとバケット8の刃先8aの位置を示すバケット位置データSとに基づいて、目標設計地形Uとバケット8との距離dに応じてバケット8が目標設計地形Uに近づく速度が小さくなるように、ブーム6の速度を制御する。
 油圧システム300は、ブーム6の上げ動作に対して介入制御する機構として、油路501,502と、制御弁27Cと、シャトル弁51と、圧力センサ68とを有している。
 油路501は、制御弁27Cに接続され、ブームシリンダ10に接続された方向制御弁64に供給されるパイロット油を供給する。
 油路501は、制御弁27Cを通過する前のパイロット油が流れる油路501と、制御弁27Cを通過した後のパイロット油が流れる油路502とを有する。油路502は、制御弁27Cとシャトル弁51とに接続され、方向制御弁64と接続された油路452Bにシャトル弁51を介して接続される。
 圧力センサ68は、油路501のパイロット油のパイロット油圧を検出する。
 制御弁27Cは、介入制御を実行するために作業機コントローラ26から出力された制御信号に基づいて制御される。
 シャトル弁51は、2つの入口ポートと、1つの出口ポートとを有する。一方の入口ポートは、油路502と接続される。他方の入口ポートは、油路452Bを介して制御弁27Bと接続される。出口ポートは、油路452Bを介して方向制御弁64と接続される。シャトル弁51は、油路502及び制御弁27Bと接続された油路452Bのうち、パイロット油圧が高い方の油路と、油路452Bとを接続する。
 シャトル弁51は、高圧優先形のシャトル弁である。シャトル弁51は、入口ポートの一方に接続された油路502のパイロット油圧と、入口ポートの他方に接続された制御弁27B側の油路452Bのパイロット油圧とを比較し、高圧側の圧力を選択する。シャトル弁51は、油路502のパイロット油圧と、制御弁27B側の油路452Bのパイロット油圧とのうち、高圧側の流路を出口ポートに連通し、当該高圧側の流路を流れるパイロット油を方向制御弁64に供給する。
 本例においては、作業機コントローラ26は、介入制御を実行しない場合には、操作装置25の操作によって調整されたパイロット油圧に基づいて方向制御弁64が駆動されるように、制御弁27Bを全開にするとともに、制御弁27Cに対して油路501を閉じるように制御信号を出力する。
 また、作業機コントローラ26は、介入制御を実行する場合には、制御弁27Cによって調整されたパイロット油圧に基づいて方向制御弁64が駆動されるように、各制御弁27に対して制御信号を出力する。
 例えば、ブーム6の移動を制限する介入制御を実行する場合、作業機コントローラ26は、制御弁27Cによって調整されたパイロット油圧が、操作装置25によって調整されるパイロット油圧よりも高くなるように、制御弁27Cを制御する。これにより、制御弁27Cからのパイロット油がシャトル弁51を介して方向制御弁64に供給される。
 <ならい制御>
 図5は、実施形態に基づくならい制御(制限掘削制御)が行われている場合の作業機2の動作を模式的に示す図である。
 図5に示されるように、ならい制御(制限掘削制御)において、バケット8が設計地形に侵入しないように、ブーム6の上げ動作を含む介入制御が実行される。具体的には、本例においては、操作装置25によるアーム7の掘削操作による掘削において、油圧システム300は、アーム7が下がり、ブーム6が上がるように制御する場合が示されている。
 図6は、実施形態に基づくならい制御を実行する制御システム200の構成を示す機能ブロック図である。
 図6に示されるように、制御システム200が有する作業機コントローラ26および表示コントローラ28の機能ブロックが示される。
 ここでは、主にならい制御(制限掘削制御)によるブーム6の介入制御について主に説明する。上記で説明したように、介入制御は、バケット8の刃先8aが目標設計地形Uに侵入しないように、ブーム6の動きを制御するものである。
 具体的には、作業機コントローラ26は、掘削対象の目標形状である設計地形を示す目標設計地形Uとバケット8の刃先8aの位置を示すバケット位置データSとに基づいて、目標設計地形Uとバケット8との距離dを算出する。そして、距離dに応じてバケット8が目標設計地形Uに近づく速度が小さくなるように、ブーム6の介入制御による制御弁27への制御指令CBIを出力する。
 まず、作業機コントローラ26は、操作装置25の操作による操作指令に基づくアーム7、バケット8の動作によるバケットの刃先8aの推定速度を算出する。そして、算出結果に基づいてバケット8の刃先8aが目標設計地形Uに侵入しないように、ブーム6の速度を制御するブーム目標速度を算出する。そして、ブーム目標速度でブーム6が動作するように制御弁27への制御指令CBIを出力する。
 以下、機能ブロックについて図6を用いて具体的に説明する。
 図6に示されるように、表示コントローラ28は、目標施工情報格納部28Aと、バケット位置データ生成部28Bと、目標設計地形データ生成部28Cとを有する。
 表示コントローラ28は、センサコントローラ30からの入力を受ける。
 センサコントローラ30は、各シリンダストロークセンサ16、17、18の検出結果から各シリンダ長データLおよび傾斜角θ1、θ2、θ3を取得する。また、センサコントローラ30は、IMU24から出力される傾斜角θ4のデータ及び傾斜角θ5のデータを取得する。センサコントローラ30は、シリンダ長データL、傾斜角θ1、θ2、θ3のデータと、傾斜角θ4のデータ、及び傾斜角θ5のデータを、表示コントローラ28に出力する。
 上述のように、本例においては、シリンダストロークセンサ16、17、18の検出結果、及びIMU24の検出結果がセンサコントローラ30に出力され、センサコントローラ30が所定の演算処理を行う。
 本例においては、センサコントローラ30の機能が、作業機コントローラ26で代用されてもよい。例えば、シリンダストロークセンサ(16、17、18)の検出結果が作業機コントローラ26に出力され、作業機コントローラ26が、シリンダストロークセンサ(16、17、18)の検出結果に基づいて、シリンダ長(ブームシリンダ長、アームシリンダ長、及びバケットシリンダ長)を算出してもよい。IMU24の検出結果が、作業機コントローラ26に出力されてもよい。
 グローバル座標演算部23は、基準位置データP及び旋回体方位データQを取得し、表示コントローラ28に出力する。
 目標施工情報格納部28Aは、作業エリアの目標形状である立体設計地形を示す目標施工情報(立体設計地形データ)Tを格納している。目標施工情報Tは、掘削対象の目標形状である設計地形を示す目標設計地形(設計地形データ)Uを生成するために必要とされる座標データ及び角度データを有する。目標施工情報Tは、例えば無線通信装置を介して表示コントローラ28に供給されてもよい。
 バケット位置データ生成部28Bは、傾斜角θ1、θ2、θ3、θ4、θ5と、基準位置データP、旋回体方位データQ、及びシリンダ長データLに基づいて、バケット8の3次元位置を示すバケット位置データSを生成する。なお、刃先8aの位置情報は、メモリ等の接続式記録装置から転送されてもよい。
 本例においては、バケット位置データSは、刃先8aの3次元位置を示すデータである。
 目標設計地形データ生成部28Cは、バケット位置データ生成部28Bより取得するバケット位置データSと目標施工情報格納部28Aに格納する後述する目標施工情報Tを用いて、掘削対象の目標形状を示す目標設計地形Uを生成する。
 また、目標設計地形データ生成部28Cは、生成した目標設計地形Uに関するデータを表示部29に出力する。これにより、表示部29は、目標設計地形を表示する。
 表示部29は、例えばモニタであり、作業車両100の各種の情報を表示する。本例においては、表示部29は、情報化施工用のガイダンスモニタとしてのHMI(Human Machine Interface)モニタを有する。
 目標設計地形データ生成部28Cは、作業機コントローラ26に対して目標設計地形Uに関するデータを出力する。また、バケット位置データ生成部28Bは、生成したバケット位置データSを作業機コントローラ26に出力する。
 作業機コントローラ26は、推定速度決定部52と、距離取得部53と、目標速度決定部54と、作業機制御部57と、記憶部58とを有する。
 作業機コントローラ26は、操作装置25の操作指令(圧力MA、MT)および表示コントローラ28からバケット位置データSおよび目標設計地形Uを取得し、制御弁27への制御指令CBIを出力する。また、作業機コントローラ26は、必要に応じてセンサコントローラ30およびグローバル座標演算部23から演算処理に必要な各種パラメータを取得する。
 推定速度決定部52は、アーム7、バケット8の駆動のための操作装置25のレバー操作に対応したアーム推定速度Vc_am、バケット推定速度Vc_bktを算出する。
 ここで、アーム推定速度Vc_amは、アームシリンダ11のみが駆動される場合のバケット8の刃先8aの速度である。バケット推定速度Vc_bktは、バケットシリンダ12のみが駆動される場合のバケット8の刃先8aの速度である。
 推定速度決定部52は、アーム操作指令(圧力MA)に対応するアーム推定速度Vc_amを算出する。また、同様に推定速度決定部52は、バケット操作指令(圧力MT)に対応するバケット推定速度Vc_bktを算出する。これによりアーム7およびバケット7の各操作指令に対応するバケット8の刃先8aの推定速度を算出することが可能である。
 記憶部58は、推定速度決定部52、目標速度決定部54および作業機制御部57が演算処理するための各種テーブル等のデータを格納する。
 距離取得部53は、目標設計地形データ生成部28Cから目標設計地形Uのデータを取得する。距離取得部53は、バケット位置データ生成部28Bより取得されるバケット8の刃先8aの位置を示すバケット位置データS及び目標設計地形Uに基づいて、目標設計地形Uに垂直な方向におけるバケット8の刃先8aと目標設計地形Uとの距離dを算出する。
 目標速度決定部54は、制限速度テーブルに従ってバケット8が目標設計地形Uに近づく速度が小さくなるように、ブーム6の目標速度Vc_bm_lmtを決定する。
 具体的には、目標速度決定部54は、目標設計地形Uとバケット8との距離dと刃先の制限速度との関係を示す制限速度テーブルを用いて、現在の距離dに基づき刃先の制限速度を算出する。そして、刃先の制限速度と、アーム推定速度Vc_amおよびバケット推定速度Vc_bktとの差分を演算することにより、ブーム6の目標速度Vc_bm_lmtを決定する。
 なお、制限速度テーブルは、記憶部58に予め記憶(格納)されている。
 作業機制御部57は、ブーム目標速度Vc_bm_lmtに従ってブームシリンダ10への制御指令CBIを生成して、ブームシリンダ10に接続された制御弁27に出力する。
 これにより、ブームシリンダ10に接続された制御弁27が制御され、ならい制御(制限掘削制御)によるブーム6の介入制御が実行される。
 [バケット8の刃先8aと目標設計地形Uとの間の距離dの算出]
 図7は、実施形態に基づくバケット8の刃先8aと目標設計地形Uとの間の距離dを取得することを説明する図である。
 図7に示されるように、距離取得部53は、刃先8aの位置情報(バケット位置データS)に基づいてバケット8の刃先8aと目標設計地形Uの表面との間の最短となる距離dを算出する。
 本例においては、バケット8の刃先8aと目標設計地形Uの表面との間の最短となる距離dに基づいて、ならい制御(制限掘削制御)が実行される。
 [目標速度の算出方式]
 図8は、実施形態に基づく推定速度決定部52の演算処理を説明する機能ブロック図である。
 図8において、推定速度決定部52は、アーム操作指令(圧力MA)に対応するアーム推定速度Vc_amおよびバケット操作指令(圧力MT)に対応するバケット推定速度Vc_bktを算出する。上記したように、アーム推定速度Vc_amは、アームシリンダ11のみが駆動される場合のバケット8の刃先8aの速度である。バケット推定速度Vc_bktは、バケットシリンダ12のみが駆動される場合のバケット8の刃先8aの速度である。
 推定速度決定部52は、スプールストローク演算部52Aと、シリンダ速度演算部52Bと、推定速度決定部52Cとを有する。
 スプールストローク演算部52Aは、記憶部58に格納されている操作指令(圧力)に従うスプールストロークテーブルに基づいて油圧シリンダ60のスプール80のスプールストローク量を算出する。なお、スプール80を移動するためのパイロット油の圧力はPPC圧力とも称される。
 スプール80の移動量は、操作装置25又は制御弁27によって制御される油路452の圧力(パイロット油圧)によって調整される。油路452のパイロット油圧は、スプールを移動するための油路452のパイロット油の圧力であり、操作装置25又は制御弁27によって調整される。したがって、スプールの移動量とPPC圧とは相関する。
 シリンダ速度演算部52Bは、算出されたスプールストローク量に従うシリンダ速度テーブルに基づいて油圧シリンダ60のシリンダ速度を算出する。
 油圧シリンダ60のシリンダ速度は、メイン油圧ポンプから方向制御弁64を介して供給される単位時間当たりの作動油の供給量に基づいて調整される。方向制御弁64は、移動可能なスプール80を有する。スプール80の移動量に基づいて、油圧シリンダ60に対する単位時間当たりの作動油の供給量が調整される。したがって、シリンダ速度とスプールの移動量(スプールストローク)とは相関する。
 推定速度決定部52Cは、算出された油圧シリンダ60のシリンダ速度に従う推定速度テーブルに基づいて推定速度を算出する。
 油圧シリンダ60のシリンダ速度に従って作業機2(ブーム6、アーム7、バケット8)が動作するためシリンダ速度と推定速度とは相関する。
 上記処理により、推定速度決定部52は、アーム操作指令(圧力MA)に対応するアーム推定速度Vc_amおよびバケット操作指令(圧力MT)に対応するバケット推定速度Vc_bktを算出する。なお、スプールストロークテーブル、シリンダ速度テーブル、推定速度テーブルは、ブーム6、アーム7、バケット8に対してそれぞれ設けられており、実験又はシミュレーションに基づいて求められ、記憶部58に予め記憶されている。
 これにより各操作指令に対応するバケット8の刃先8aの推定速度を算出することが可能である。
 [ブーム目標速度の算出方式]
 ブーム目標速度を算出するにあたり、アーム7及びバケット8の各々の推定速度Vc_am、Vc_bktの目標設計地形Uの表面に垂直な方向の速度成分(垂直速度成分)Vcy_am、Vcy_bktを算出する必要がある。このため、まずは上記垂直速度成分Vcy_am、Vcy_bktを算出する方式について説明する。
 図9(A)~図9(C)は、実施形態に基づく上記垂直速度成分Vcy_am、Vcy_bktの算出方式を説明する図である。
 図9(A)に示すように、目標速度決定部54は、アーム推定速度Vc_amを、目標設計地形Uの表面に垂直な方向の速度成分(垂直速度成分)Vcy_amと、目標設計地形Uの表面に平行な方向の速度成分(水平速度成分と)Vcx_amとに変換する。
 この点で、目標速度決定部54は、センサコントローラ30から取得した傾斜角及び目標設計地形Uなどから、グローバル座標系の垂直軸に対するローカル座標系の垂直軸(旋回体3の旋回軸AX)の傾きと、グローバル座標系の垂直軸に対する目標設計地形Uの表面の垂直方向における傾きとを求める。目標速度決定部54は、これらの傾きからローカル座標系の垂直軸と目標設計地形Uの表面の垂直方向との傾きを表す角度β1を求める。
 バケット推定速度Vc_bktについても同様である。
 そして、図9(B)に示すように、目標速度決定部54は、ローカル座標系の垂直軸とアーム推定速度Vc_amの方向とのなす角度β2とから、三角関数により、アーム推定速度Vc_amを、ローカル座標系の垂直軸方向の速度成分VL1_amと、水平軸方向の速度成分VL2_amとに変換する。
 そして、図9(C)に示すように、目標速度決定部54は、ローカル座標系の垂直軸と目標設計地形Uの表面の垂直方向との傾きβ1から、三角関数により、ローカル座標系の垂直軸方向における速度成分VL1_amと、水平軸方向における速度成分VL2_amとを、目標設計地形Uに対する垂直速度成分Vcy_am及び水平速度成分Vcx_amに変換する。同様にして、目標速度決定部54は、バケット推定速度Vc_bktを、ローカル座標系の垂直軸方向における垂直速度成分Vcy_bkt及び水平速度成分Vcx_bktに変換する。
 このようにして、上記垂直速度成分Vcy_am、Vcy_bktが算出される。
 さらにブーム目標速度を算出するにあたり、作業機2全体の制限速度が必要となるため、次に作業機2全体の制限速度テーブルについて説明する。
 図10は、実施形態に基づくならい制御における作業機2全体の制限速度テーブルの一例を説明する図である。
 図10に示されるように、ここでは、縦軸が制限速度Vcy_lmtを表し、横軸が刃先と設計地形との間の距離dを表している。
 本例においては、バケット8の刃先8aが目標設計地形Uの表面の外方(作業車両100の作業機2側)に位置している場合の距離dは正の値であり、刃先8aが目標設計地形Uの表面の内方(目標設計地形Uよりも掘削対象の内部側)に位置している場合の距離dは負の値である。刃先8aが目標設計地形Uの表面の上方に位置している場合の距離dは正、刃先8aが目標設計地形Uの表面の下方に位置している場合の距離dは負の値である。
 また、刃先8aが目標設計地形Uに対して侵食しない位置にある場合の距離dは正、刃先8aが目標設計地形Uに対して侵食する位置にある場合の距離dは負の値である。
 また、刃先8aが目標設計地形U上に位置している場合(刃先8aが目標設計地形Uと接している場合)の距離dは0である。
 本例においては、刃先8aが目標設計地形Uの内方から外方に向かう場合の速度を正の値とし、刃先8aが目標設計地形Uの外方から内方に向かう場合の速度を負の値とする。刃先8aが目標設計地形Uの上方に向かう場合の速度を正の値とし、刃先8aが目標設計地形Uの下方に向かう場合の速度を負の値とする。
 制限速度情報において、距離dがd1とd2との間である場合の制限速度Vcy_lmtの傾きは、距離dがd1以上又はd2以下の場合の傾きより小さい。d1は0より大きい。d2は0より小さい。
 目標設計地形Uの表面付近の操作においては制限速度をより詳細に設定するために、距離dがd1とd2との間である場合の傾きを、距離dがd1以上又はd2以下である場合の傾きよりも小さくする。
 距離dがd1以上の場合、制限速度Vcy_lmtは負の値であり、距離dが大きくなるほど制限速度Vcy_lmtの絶対値は大きくなる。
 距離dがd1以上の場合、目標設計地形Uより上方において刃先8aが目標設計地形Uの表面から遠いほど、目標設計地形Uの下方へ向かう速度が大きくなり、制限速度Vcy_lmtの絶対値は大きくなる。
 距離dが0以下の場合、制限速度Vcy_lmtは正の値であり、距離dが小さくなるほど制限速度Vcy_lmtの絶対値は大きくなる。
 バケット8の刃先8aが目標設計地形Uより遠ざかる距離dが0以下の場合、目標設計地形Uより下方において刃先8aが目標設計地形Uから遠いほど、目標設計地形Uの上方へ向かう速度が大きくなり、制限速度Vcy_lmtの絶対値は大きくなる。
 距離dが所定値dth1では、制限速度Vcy_lmtは、Vminとなる。所定値dth1は正の値であり、d1より大きい。
 距離dが所定値dth1以上では、作業機2の動作の介入制御は行わない。したがって、刃先8aが目標設計地形Uの上方において目標設計地形Uから大きく離れている場合には、作業機2の動作の介入制御は行わない。
 距離dが所定値dth1より小さい場合に、作業機2の動作の介入制御が行われる。具体的には、距離dが所定値dth1より小さい場合に、ブーム6の動作の介入制御が行われる。
 次に、上記のようにして求めた上記垂直速度成分Vcy_bm、Vcy_am、Vcy_bktと、作業機2全体の制限速度テーブルとを用いて、ブーム目標速度Vc_bm_lmtを算出する方式について説明する。
 図11(A)~図11(D)は、実施形態に基づくブーム目標速度Vc_bm_lmtを算出する方式を説明する図である。
 図11(A)に示されるように、目標速度決定部54は、上記制限速度テーブルに従って作業機2全体の制限速度Vcy_lmtを算出する。作業機2全体の制限速度Vcy_lmtは、バケット8の刃先8aが目標設計地形Uに接近する方向において許容できる刃先8aの移動速度である。
 図11(B)には、アーム推定速度Vc_amの垂直速度成分Vcy_amとバケット推定速度Vc_bktの垂直速度成分Vcy_bktとが示されている。
 目標速度決定部54は、図9で説明したように、アーム推定速度Vc_am、バケット推定速度Vc_bktとに基づいてアーム推定速度Vc_amの垂直速度成分Vcy_amとバケット推定速度Vc_bktの垂直速度成分Vcy_bktとを算出することが可能である。
 図11(C)には、ブーム6の制限垂直速度成分Vcy_bm_lmtを算出する場合が示されている。具体的には、作業機2全体の制限速度Vcy_lmtからアーム推定速度Vc_amの垂直速度成分Vcy_amとバケット推定速度Vc_bktの垂直速度成分Vcy_bktとを減算することにより、ブーム6の制限垂直速度成分Vcy_bm_lmtが算出される。
 図11(D)には、ブーム6の制限垂直速度成分Vcy_bm_lmtに基づいてブーム目標速度Vc_bm_lmtを算出する場合が示されている。
 作業機2全体の制限速度Vcy_lmtが、アーム推定速度の垂直速度成分Vcy_amとバケット推定速度の垂直速度成分Vcy_bktとの和よりも小さい場合には、ブーム6の制限垂直速度成分Vcy_bm_lmtは、ブームが上昇する正の値となる。
 ブーム目標速度Vc_bm_lmtが正の値となるため、操作装置25がブーム6を下降させる方向に操作されていても、作業機コントローラ26は介入制御し、ブーム6を上昇させる。このため、目標設計地形Uの侵食の拡大を迅速に抑えることができる。
 作業機2全体の制限速度Vcy_lmtが、アーム推定速度の垂直速度成分Vcy_amとバケット推定速度の垂直速度成分Vcy_bktとの和よりも大きい場合には、ブーム6の制限垂直速度成分Vcy_bm_lmtは、ブームが下降する負の値となる。
 ブーム目標速度Vc_bm_lmtが負の値となるため、ブーム6が下降する。
 [制御指令CBIの生成]
 図12は、実施形態に基づく作業機制御部57の構成を示す機能ブロック図である。
 図12に示されるように、作業機制御部57は、シリンダ速度算出部262Aと、EPC演算部262Bと、EPC指令部262Cとを有する。
 作業機制御部57は、介入制御する場合にブーム目標速度Vc_bm_lmtでブーム6が駆動するように制御弁27に対して制御指令CBIを出力する。
 シリンダ速度算出部262Aは、ブーム目標速度Vc_bm_lmtに従う油圧シリンダ60のシリンダ速度を算出する。具体的には、記憶部58に予め格納されているブーム6の動作のみによるバケット8の刃先8aの速度と油圧シリンダ60の速度との関係を示す推定速度テーブルに基づいて、ブーム目標速度Vc_bm_lmtに従う油圧シリンダ60のシリンダ速度を算出する。
 EPC演算部262Bは、算出されたシリンダ速度に基づいて、EPC電流値を演算処理する。具体的には、記憶部58に予め格納されている相関データに基づいて演算処理する。
 EPC指令部262Cは、EPC演算部262Bで算出されたEPC電流値を制御弁27に出力する。
 記憶部58は、油圧シリンダ60のシリンダ速度とスプール80の移動量との関係を示す相関データと、スプール80の移動量と制御弁27によって制御されるPPC圧力との関係を示す相関データと、PPC圧力とEPC演算部262Bから出力される制御信号(EPC電流)との関係を示す相関データとを記憶する。なお、シリンダ速度テーブル、相関データは、実験又はシミュレーションに基づいて求められ、記憶部58に予め記憶されている。
 上述したように、油圧シリンダ60のシリンダ速度は、メイン油圧ポンプから方向制御弁64を介して供給される単位時間当たりの作動油の供給量に基づいて調整される。方向制御弁64は、移動可能なスプール80を有する。スプール80の移動量に基づいて、油圧シリンダ60に対する単位時間当たりの作動油の供給量が調整される。したがって、シリンダ速度とスプールの移動量(スプールストローク)は相関する。
 スプール80の移動量は、操作装置25又は制御弁27によって制御される油路452の圧力(パイロット油圧)によって調整される。油路452のパイロット油圧は、スプールを移動するための油路452のパイロット油の圧力であり、操作装置25又は制御弁27によって調整される。なお、スプール80を移動するためのパイロット油の圧力をPPC圧力とも称する。したがって、スプールの移動量とPPC圧とは相関する。
 制御弁27は、作業機コントローラ26のEPC演算部262Bから出力された制御信号(EPC電流)に基づいて作動する。したがって、PPC圧力とEPC電流とは相関する。
 作業機制御部57は、目標速度決定部54で算出されたブーム目標速度Vc_bm_lmtに対応するEPC電流値を算出し、EPC指令部262CからEPC電流を制御指令CBIとして制御弁27に出力する。
 これにより、作業機コントローラ26は、介入制御によりバケット8の刃先8aが目標設計地形Uに侵入しないように、ブーム6を制御することが可能である。
 また、必要に応じて、作業機コントローラ26は、アーム7及びバケット8を制御する。作業機コントローラ26は、アーム制御指令を制御弁27に送信することによって、アームシリンダ11を制御する。アーム制御指令は、アーム指令速度に応じた電流値を有する。作業機コントローラ26は、バケット制御指令を制御弁27に送信することによって、バケットシリンダ12を制御する。バケット制御指令は、バケット指令速度に応じた電流値を有する。
 この場合の演算についても、上述したように、ブーム目標速度Vc_bm_lmtからEPC電流を算出したのと同様の方式に従って、制御弁27を制御する電流値を有するアーム制御指令およびバケット制御指令を制御弁27に出力することが可能である。
 図13は、実施形態に基づく作業車両100のならい制御(制限掘削制御)を説明するフロー図である。
 図13に示されるように、まず、設計地形を設定する(ステップSA1)。具体的には、表示コントローラ28の目標設計地形データ生成部28Cにより目標設計地形Uを設定する。
 次に、刃先と設計地形との距離dを取得する(ステップSA2)。具体的には、距離取得部53は、バケット位置データ生成部28Bからのバケット位置データSに従う刃先8aの位置情報と目標設計地形Uとに基づいてバケット8の刃先8aと目標設計地形Uの表面との間の最短となる距離dを算出する。
 次に、推定速度を決定する(ステップSA3)。具体的には、作業機コントローラ26の推定速度決定部52は、アーム推定速度Vc_am、及びバケット推定速度Vc_bktを決定する。アーム推定速度Vc_amは、アームシリンダ11のみが駆動される場合の刃先8aの速度である。バケット推定速度Vc_bktは、バケットシリンダ12のみが駆動される場合の刃先8aの速度である。
 アーム推定速度Vc_am、バケット推定速度Vc_bktは、記憶部58に格納されている各種テーブルに従って操作装置25の操作指令(圧力MA、MT)に基づいて算出される。
 次に、目標速度を垂直速度成分に変換する(ステップSA4)。具体的には、目標速度決定部54は、図9で説明したようにアーム推定速度Vc_am、バケット推定速度Vc_bktを目標設計地形Uに対する垂直速度成分Vcy_am、Vcy_bktに変換する。
 次に、作業機2全体の制限速度Vcy_lmtを算出する(ステップSA5)。具体的には、目標速度決定部54は、距離dに基づいて、制限速度テーブルに従って制限速度Vcy_lmtを算出する。
 次に、ブームの目標速度成分Vcy_bm_lmtを決定する(ステップSA6)。具体的には、目標速度決定部54は、図11で説明したように作業機2全体の制限速度Vcy_lmtとアーム推定速度Vc_amとバケット推定速度Vc_bktとからブーム6の目標速度の垂直速度成分(目標垂直速度成分)Vcy_bm_lmtを算出する。
 次に、ブームの目標垂直速度成分Vcy_bm_lmtを目標速度Vc_bm_lmtに変換する(ステップSA7)。具体的には、目標速度決定部54は、図11で説明したようにブーム6の目標垂直速度成分Vcy_bm_lmtを、ブーム6の目標速度(ブーム目標速度)Vc_bm_lmtに変換する。
 次に、作業機制御部57は、ブーム目標速度Vc_bm_lmtに対応するEPC電流値を算出し、EPC指令部262CからEPC電流を制御指令CBIとして制御弁27に出力する(ステップSA10)。これにより、作業機コントローラ26は、バケット8の刃先8aが目標設計地形Uに侵入しないように、ブーム6を制御することが可能である。
 そして、処理を終了する(エンド)。
 このように、本例においては、作業機コントローラ26は、掘削対象の目標形状である設計地形を示す目標設計地形Uとバケット8の刃先8aの位置を示すバケット位置データSとに基づいて、目標設計地形Uとバケット8の刃先8aとの距離dに応じてバケット8が目標設計地形Uに近づく相対速度が小さくなるように、ブーム6の速度を制御する。
 作業機コントローラ26は、掘削対象の目標形状である設計地形を示す目標設計地形Uとバケット8の刃先8aの位置を示すバケット位置データSとに基づいて、目標設計地形Uとバケット8の刃先8aとの距離dに応じて制限速度を決定し、作業機2が目標設計地形Uに接近する方向の速度が制限速度以下になるように、作業機2を制御する。これによりならい制御(掘削制限制御)が実行され、ブームシリンダの速度調整が行われる。当該方式により、目標設計地形Uに対する刃先8aの位置が制御されて目標設計地形Uに対する刃先8aの侵入を抑制して、設計地形に応じた面を作るならい作業を実行することが可能となる。
 [油圧シリンダ60の速度調整]
 操作装置25の第2操作レバー25Lを操作してアーム7を操作することにより、バケット8の刃先8aに当接する土砂を掻き均し、平らな設計地形に対応する面を作るならい作業を実行することが可能である。
 一方で、第2操作レバー25Lを操作した際には、バケット8の刃先8aが自重により落下する可能性がある。
 油圧シリンダ60は、バケット8の自重落下が生じた場合には、第2操作レバー25Lを操作した操作量(アーム操作量)に従う油圧シリンダ60の想定された速度以上となって動作する可能性がある。
 この第2操作レバー25Lのアーム操作による油圧シリンダ60の想定された速度と実速度との乖離は第2操作レバー25Lが微操作の場合に大きくなる。
 その結果、介入制御において第2操作レバー25Lの操作量に従うアーム推定速度Vc_amに基づく、作業機コントローラ26の目標速度決定部54で決定されたブーム目標速度Vc_bm_lmtが適正な値とならずに、バケット8の刃先8aが安定せずにハンチングが生じる可能性が考えられる。
 実施形態においては、第2操作レバー25Lのアーム操作が微操作の場合には、実速度との乖離を抑制するためにアーム推定速度Vc_amを調整する方式について説明する。
 図14は、実施形態に基づくスプール80の移動量(スプールストローク)と油圧シリンダ60のシリンダ速度との関係が示されたシリンダ速度テーブルを説明する図である。
 当該シリンダ速度テーブルは、記憶部58に格納されているものであり、推定速度決定部52において利用される。
 図14では、シリンダ速度テーブルにおいて、横軸はスプールストローク量を示し、縦軸はシリンダ速度が示されている。スプールストロークが零(原点)である状態は、スプールが初期位置に存在する状態である。上述したように、スプール80の移動量に応じた供給量で作動油が油圧シリンダ60に供給される。油圧シリンダ60に対する作動油の供給量が調整されることにより、シリンダ速度が調整される。
 本例においては、シリンダ速度テーブルは、オペレータの作業によって求めたものを用いることが可能である。たとえば、スプール80が所定量移動するように、操作装置25の第2操作レバー25Lが操作される。スプール80の移動量(スプールストローク量)は、スプールストロークセンサ65で検出可能である。また、そのスプール80のスプールストローク量に応じたシリンダ速度は、シリンダストロークセンサ17で検出する。シリンダストロークセンサ17は、シリンダロッド10Yの速度(シリンダ速度)を高精度に検出可能である。
 スプールストロークセンサ65の検出結果およびシリンダストロークセンサ17の検出結果に基づいて、シリンダ速度テーブルを取得することができる。
 スプールストローク量がプラスになるようにスプールが移動することにより、アーム7は、下げ動作(掘削動作)する。一方、スプールストローク量がマイナスになるようにスプールが移動することにより、作業機2は上げ動作(ダンプ動作)する。
 本例においては、下げ動作におけるシリンダ速度とスプールストロークとの関係が示されている。
 油圧シリンダ60のシリンダ速度を制御する手法としては、スプールストローク量に従って作動油が油圧シリンダ60に流入する作動油の流入量で制御するメータイン制御と、油圧シリンダ60から流出する作動油の流出量で制御するメータアウト制御とがある。
 ラインLAは、メータイン制御におけるスプールストローク量とシリンダ速度との関係を示す第1シリンダ速度テーブル(第1速度テーブル)である。
 ラインLBは、メータアウト制御におけるスプールストローク量とシリンダ速度との関係を示す第2シリンダ速度テーブル(第2速度テーブル)である。
 第2操作レバー25Lを操作した操作量(アーム操作量)が所定量未満の場合において、ラインLAのメータイン制御による第1シリンダ速度テーブルに基づいてシリンダ速度を算出する方式を採用した場合、バケット8の自重落下が生じた場合における油圧シリンダ60の速度は、第2操作レバー25Lを操作した操作量(アーム操作量)に従う想定速度よりも大きくなる可能性がある。これは、作動油の流入量に従ってシリンダロッド10Yが動く速度(油圧シリンダ60の速度)よりも、バケット8の自重によりシリンダロッド10Yを牽引する負荷がかけられた結果によりシリンダロッド10Yが動く速度が大きいことに起因する。
 一方で、実施形態において、ラインLBのメータアウト制御による第2シリンダ速度テーブルに基づいてシリンダ速度を算出する方式を採用した場合、バケット8の自重落下が生じた場合における油圧シリンダ60の速度は、第2操作レバー25Lを操作した操作量(アーム操作量)に従う想定速度にほぼ等しいと考えられる。これは、バケット8の自重によりシリンダロッド10Yに対して牽引する負荷がかけられた場合であってもシリンダロッド10Yが動く速度(油圧シリンダ60の速度)は、作動油の流出量で制御されるためその速度は適正に制御されるからである。
 したがって、実施形態においては、作業機コントローラ26の推定速度決定部52は、第2操作レバー25Lを操作した操作量(アーム操作量)が所定量未満の場合には、ラインLAのメータイン制御による第1シリンダ速度テーブルに基づくシリンダ速度の値よりも大きい値を油圧シリンダ60の推定速度に設定する。
 具体的には、推定速度決定部52のシリンダ速度演算部52Bは、第2操作レバー25Lを操作した操作量(アーム操作量)が所定量未満の場合には、ラインLAのメータイン制御による第1シリンダ速度テーブルに基づくシリンダ速度の値よりも大きい値を油圧シリンダ60の推定速度に設定する。
 これにより、バケット8の自重落下が生じた場合でも油圧シリンダ60の推定速度の調整に従い実測度との乖離を抑制することが可能となる。
 その結果、上記で説明した介入制御において第2操作レバー25Lの操作量に従う調整されたアーム推定速度Vc_amに基づいて作業機コントローラ26の目標速度決定部54は、ブーム目標速度Vc_bm_lmtを決定する。これにより、バケット8の刃先8aを安定させてハンチングを抑制することが可能となる。
 本例においては、スプールストローク量が所定値Xとなる場合の第2操作レバー25Lを操作した操作量(アーム操作量)を上記所定量に設定する。
 また、推定速度決定部52のシリンダ速度演算部52Bは、第2操作レバー25Lを操作した操作量(アーム操作量)が所定量未満の場合には、ラインLAのメータイン制御による第1シリンダ速度テーブルに基づくシリンダ速度の値よりも大きく、シリンダ速度Yよりも小さい値を油圧シリンダ60の推定速度に設定する。
 第2操作レバー25Lを操作した操作量が所定量以上の場合のスプールストローク量が所定値X以上となる領域においては、推定速度決定部52のシリンダ速度演算部52Bは、ラインLAのメータイン制御による第1シリンダ速度テーブルに基づくシリンダ速度の値を油圧シリンダ60の推定速度に設定する。そして、油圧シリンダ60の推定速度に従うアーム推定速度Vc_amに基づいて作業機コントローラ26の目標速度決定部54は、ブーム目標速度Vc_bm_lmtを決定する。
 この場合には、作動油の流入量に従ってシリンダロッド10Yが動く速度(油圧シリンダ60の速度)の方が、バケット8の自重によりシリンダロッド10Yを牽引する負荷がかけられた結果によりシリンダロッド10Yが動く速度よりも大きいため、第1シリンダ速度テーブルに基づくシリンダ速度を推定速度に設定することにより、精度の高いシリンダ速度に従うアーム推定速度Vc_amが算出される。これにより、作業機コントローラ26の目標速度決定部54は、精度の高いブーム目標速度Vc_bm_lmtに設定してより安定したならい制御を実行することが可能である。
 図14におけるスプールストローク量が所定値X未満の領域を微操作領域と称する。所定値X未満となるスプールストローク量は、第2操作レバー25Lを微操作した操作量に対応するものである。
 スプールストローク量が微操作領域よりも大きい領域を通常操作領域とも称する。
 所定値X以上となるスプールストローク量は、第2操作レバー25Lを通常操作した操作量に対応するものである。
 図14に示すように、微操作領域におけるラインLBのスプールストローク量に対応するシリンダ速度の値は、ラインLAのスプールストローク量に対応するシリンダ速度の値よりも大きい。
 作業機コントローラ26の推定速度決定部52は、第2操作レバー25Lを操作した操作量(アーム操作量)が所定量未満の場合には、ラインLBのメータアウト制御による第2シリンダ速度テーブルに基づくシリンダ速度の値を油圧シリンダ60の推定速度に設定するようにしてもよい。
 具体的には、推定速度決定部52のシリンダ速度演算部52Bは、第2操作レバー25Lを操作した操作量(アーム操作量)が所定量未満の場合には、ラインLBのメータアウト制御による第2シリンダ速度テーブルに基づくシリンダ速度の値を油圧シリンダ60の推定速度に設定する。
 これにより、バケット8の自重落下が生じた場合でも油圧シリンダ60の速度を実測度に近い推定速度に設定することにより、実測度との乖離を抑制することが可能となる。
 その結果、上記で説明した介入制御において第2操作レバー25Lの操作量に従うアーム推定速度Vc_amに基づいて作業機コントローラ26の目標速度決定部54は、ブーム目標速度Vc_bm_lmtを決定する。これにより、バケット8の刃先8aを安定させてハンチングを抑制することが可能となる。
 なお、本例においては、シリンダ速度とスプールストロークとの関係を示すシリンダ速度テーブルを用いてシリンダ速度を算出する方式について説明したが、記憶部58に、シリンダ速度とPPC圧力(パイロット圧力)との関係を示すシリンダ速度テーブルが記憶され、その相関データを使ってシリンダ速度を算出することも可能である。
 なお、本例においては、制御弁27を全開にして、圧力センサ66及び圧力センサ67で圧力を検出し、その検出値に基づいて、圧力センサ66及び圧力センサ67のキャリブレーションを行ってもよい。制御弁27を全開にした場合、圧力センサ66と圧力センサ67とは同じ検出値を出力する。制御弁27を全開にした場合において、圧力センサ66と圧力センサ67とが異なる検出値を出力した場合、圧力センサ66の検出値と、圧力センサ67の検出値との関係を示す相関データを求めてもよい。
 以上、本発明の一実施形態について説明したが、本発明は上記実施形態に限定されるものではなく、発明の要旨を逸脱しない範囲で種々の変更が可能である。
 例えば、上述の本例においては、操作装置25は、パイロット油圧方式であることとした。操作装置25は、電気レバー方式でもよい。例えば、操作装置25の操作レバーの操作量を検出し、その操作量に応じた電圧値を作業機コントローラ26に出力するポテンショメータ等の操作レバー検出部が設けられてもよい。作業機コントローラ26は、その操作レバー検出部の検出結果に基づいて、制御弁27に制御信号を出力して、パイロット油圧を調整してもよい。本制御は作業機コントローラで行われたが、センサコントローラ30等他のコントローラで行われてもよい。
 上記の実施形態では、作業車両の一例として油圧ショベルを挙げているが油圧ショベルに限らず、他の種類の作業車両に本発明が適用されてもよい。
 グローバル座標系における油圧ショベルの位置の取得は、GNSSに限らず、他の測位手段によって行われてもよい。従って、刃先8aと設計地形との距離dの取得は、GNSSに限らず、他の測位手段によって行われてもよい。
 以上、本発明の実施形態について説明したが、今回開示された実施形態は全ての点で例示であって制限的なものではないと考えられるべきである。本発明の範囲は請求の範囲によって示され、請求の範囲と均等の意味および範囲内での全ての変更が含まれることが意図される。
 1 車両本体、2 作業機、3 旋回体、4 運転室、4S 運転席、5 走行装置、5Cr 履帯、6 ブーム、7 アーム、8 バケット、8a 刃先、9 エンジンルーム、10 ブームシリンダ、10V ピストン、10W シリンダヘッド、10X シリンダチューブ、10Y シリンダロッド、11 アームシリンダ、12 バケットシリンダ、13 ブームピン、14 アームピン、15 バケットピン、16 ブームシリンダストロークセンサ、17 アームシリンダストロークセンサ、18 バケットシリンダストロークセンサ、19 手すり、20 位置検出装置、21 アンテナ、21A 第1アンテナ、21B 第2アンテナ、23 グローバル座標演算部、25 操作装置、25L 第2操作レバー、25R 第1操作レバー、26 作業機コントローラ、27,27A,27B,27C 制御弁、28 表示コントローラ、28A 目標施工情報格納部、28B バケット位置データ生成部、28C 目標設計地形データ生成部、29,322 表示部、30 センサコントローラ、32 マンマシンインターフェース部、40A キャップ側油室、40B ロッド側油室、51 シャトル弁、52 推定速度決定部、52A スプールストローク演算部、52B シリンダ速度演算部、52C 目標速度演算部、53 距離取得部、54 目標速度決定部、57 作業機制御部、58 記憶部、60 油圧シリンダ、63 旋回モータ、64 方向制御弁、65 スプールストロークセンサ、66,67,68 圧力センサ、80 スプール、100 作業車両、161 回転ローラ、162 回転中心軸、163 回転センサ部、163a 磁石、164 ケース、200 制御システム、262 制御弁制御部、262A シリンダ速度算出部、262B EPC演算部、262C EPC指令部、300 油圧システム、321 入力部、450 パイロット油路。

Claims (5)

  1.  ブームと、アームと、バケットと、
     前記アームを駆動するアームシリンダと、
     移動可能なスプールを有し、前記スプールの移動により前記アームシリンダに作動油を供給して前記アームシリンダを動作させる方向制御弁と、
     アーム操作レバーの操作量に従う前記方向制御弁のスプールの移動量と前記アームシリンダの速度との相関関係に基づいて前記アームシリンダの推定速度を算出する算出部と、
     前記アームシリンダの推定速度に基づいて、前記ブームの目標速度を決定する速度決定部とを備え、
     前記算出部は、前記アーム操作レバーの操作量が所定量未満の場合には、前記アーム操作レバーの操作量に従う前記方向制御弁のスプールの移動量と前記アームシリンダの速度との相関関係に従う前記アームシリンダの速度よりも大きい速度を、前記アームシリンダの推定速度として算出する、作業車両。
  2.  前記算出部は、前記方向制御弁のスプールの移動量と、前記方向制御弁のスプールの移動量に従って前記アームシリンダに流入する前記作動油の供給量に基づき規定される前記アームシリンダの速度との相関関係に基づいて、前記アームシリンダの推定速度を算出する、請求項1記載の作業車両。
  3.  前記アーム操作レバーの操作量に従う前記方向制御弁のスプールの移動量と前記アームシリンダの速度との相関関係は、第1速度テーブルに相当し、
     前記算出部は、前記アーム操作レバーの操作量が所定量以上の場合には、前記第1速度テーブルに従う前記アームシリンダの速度を推定速度として算出する、請求項1記載の作業車両。
  4.  前記算出部は、前記アーム操作レバーの操作量が所定量未満の場合には、第2速度テーブルに基づいて前記アームシリンダの推定速度を算出し、
     前記第2速度テーブルは、前記方向制御弁のスプールの移動量と、前記方向制御弁のスプールの移動量に従って前記アームシリンダから排出量に基づき規定される前記アームシリンダの速度との相関関係を示すものである、請求項1記載の作業車両。
  5.  ブームと、アームと、バケットとを備える、作業車両の制御方法であって、
     アーム操作レバーの操作量に従う方向制御弁のスプールの移動量とアームシリンダの速度との相関関係に基づいて前記アームシリンダの推定速度を算出するステップと、
     前記アームシリンダの推定速度に基づいて、前記ブームの目標速度を決定するステップとを備え、
     前記算出するステップは、前記アーム操作レバーの操作量が所定量未満の場合には、前記アーム操作レバーの操作量に従う前記方向制御弁のスプールの移動量と前記アームシリンダの速度との相関関係に従う前記アームシリンダの速度よりも大きい速度を前記アームシリンダの推定速度として算出するステップを含む、作業車両の制御方法。
     
PCT/JP2014/074006 2014-09-10 2014-09-10 作業車両および作業車両の制御方法 WO2015025985A1 (ja)

Priority Applications (6)

Application Number Priority Date Filing Date Title
PCT/JP2014/074006 WO2015025985A1 (ja) 2014-09-10 2014-09-10 作業車両および作業車両の制御方法
DE112014000176.7T DE112014000176B4 (de) 2014-09-10 2014-09-10 Baufahrzeug sowie Verfahren zum Steuern des Baufahrzeugs
US14/423,452 US9447562B2 (en) 2014-09-10 2014-09-10 Work vehicle and method of controlling work vehicle
CN201480002025.3A CN104619921B (zh) 2014-09-10 2014-09-10 作业车辆及作业车辆的控制方法
KR1020157004882A KR101658326B1 (ko) 2014-09-10 2014-09-10 작업 차량 및 작업 차량의 제어 방법
JP2014546643A JP5865510B2 (ja) 2014-09-10 2014-09-10 作業車両および作業車両の制御方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2014/074006 WO2015025985A1 (ja) 2014-09-10 2014-09-10 作業車両および作業車両の制御方法

Publications (1)

Publication Number Publication Date
WO2015025985A1 true WO2015025985A1 (ja) 2015-02-26

Family

ID=52483753

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2014/074006 WO2015025985A1 (ja) 2014-09-10 2014-09-10 作業車両および作業車両の制御方法

Country Status (6)

Country Link
US (1) US9447562B2 (ja)
JP (1) JP5865510B2 (ja)
KR (1) KR101658326B1 (ja)
CN (1) CN104619921B (ja)
DE (1) DE112014000176B4 (ja)
WO (1) WO2015025985A1 (ja)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019012701A1 (ja) * 2017-07-14 2019-01-17 株式会社小松製作所 作業機械および作業機械の制御方法
WO2019202673A1 (ja) 2018-04-17 2019-10-24 日立建機株式会社 作業機械
JP2021055427A (ja) * 2019-09-30 2021-04-08 日立建機株式会社 建設機械
WO2021065952A1 (ja) 2019-09-30 2021-04-08 日立建機株式会社 作業機械

Families Citing this family (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2012202213B2 (en) * 2011-04-14 2014-11-27 Joy Global Surface Mining Inc Swing automation for rope shovel
WO2015099440A1 (ko) * 2013-12-26 2015-07-02 두산인프라코어 주식회사 건설기계의 메인컨트롤밸브의 제어 방법 및 제어 장치
US20160201298A1 (en) * 2015-01-08 2016-07-14 Caterpillar Inc. Systems and Methods for Constrained Dozing
CN113107045A (zh) * 2015-12-28 2021-07-13 住友建机株式会社 挖土机以及挖土机用的控制装置和挖土机的控制方法
WO2018051511A1 (ja) * 2016-09-16 2018-03-22 日立建機株式会社 作業機械
CN108603358B (zh) * 2016-11-09 2020-11-17 株式会社小松制作所 作业车辆以及数据校正方法
KR101985349B1 (ko) * 2016-11-09 2019-06-03 가부시키가이샤 고마쓰 세이사쿠쇼 작업 차량 및 제어 방법
WO2018087830A1 (ja) * 2016-11-09 2018-05-17 株式会社小松製作所 作業車両およびデータ較正方法
WO2018117294A1 (ko) * 2016-12-21 2018-06-28 볼보 컨스트럭션 이큅먼트 에이비 건설기계용 티칭 및 플레이백 장치 및 이를 포함하는 건설기계용 티칭 및 플레이백 시스템
US11111646B2 (en) * 2017-02-24 2021-09-07 Cnh Industrial America Llc System and method for controlling an arm of a work vehicle
CN110352281B (zh) * 2017-03-31 2022-03-11 住友建机株式会社 挖土机、挖土机的显示装置及挖土机的图像显示方法
US10988915B2 (en) 2017-04-10 2021-04-27 Doosan Infracore Co., Ltd. Hydraulic system of construction machinery
WO2019012699A1 (ja) * 2017-07-14 2019-01-17 株式会社小松製作所 作業機械および作業機械の制御方法
CN109790698B (zh) * 2017-09-13 2021-04-23 日立建机株式会社 作业机械
EP3460258B1 (en) 2017-09-22 2020-09-02 Caterpillar Inc. Machine with hydraulic control system and method
JP6894464B2 (ja) * 2019-04-22 2021-06-30 株式会社小松製作所 作業機械、作業機械の制御方法、施工管理装置および施工管理装置の制御方法
JP7146701B2 (ja) * 2019-06-27 2022-10-04 日立建機株式会社 油圧ショベル
CN111258336B (zh) * 2020-02-28 2023-08-25 雷沃重工集团有限公司 一种控制铲斗位置的方法、系统和可读存储介质
US11236492B1 (en) * 2020-08-25 2022-02-01 Built Robotics Inc. Graphical user interface for real-time management of an earth shaping vehicle
KR20230061909A (ko) * 2021-10-29 2023-05-09 볼보 컨스트럭션 이큅먼트 에이비 건설기계
CN114562453B (zh) * 2022-02-09 2024-01-30 三一汽车制造有限公司 一种工程车辆及其泵送作业的控制方法、装置

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000336690A (ja) * 1999-06-01 2000-12-05 Hitachi Constr Mach Co Ltd 建設機械の領域制限掘削制御装置
JP2012172382A (ja) * 2011-02-21 2012-09-10 Sumitomo Heavy Ind Ltd 掘削機
JP2014095396A (ja) * 2012-11-07 2014-05-22 Hitachi Constr Mach Co Ltd 閉回路油圧駆動装置

Family Cites Families (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1995030059A1 (fr) * 1994-04-28 1995-11-09 Hitachi Construction Machinery Co., Ltd. Dispositif de commande d'excavation a limitation de surface de travail pour engin de terrassement
JP3112814B2 (ja) * 1995-08-11 2000-11-27 日立建機株式会社 建設機械の領域制限掘削制御装置
KR100240085B1 (ko) 1995-12-30 2000-01-15 토니헬 굴삭기의 조작장치
JPH09328774A (ja) * 1996-06-07 1997-12-22 Hitachi Constr Mach Co Ltd 油圧建設機械の自動軌跡制御装置
JP3310565B2 (ja) 1996-12-27 2002-08-05 株式会社クボタ バックホウ
WO1998059118A1 (fr) 1997-06-20 1998-12-30 Hitachi Construction Machinery Co., Ltd. Dispositif permettant de reguler un puits de fondation a l'aide d'une machine de construction
US6336077B1 (en) * 1999-06-07 2002-01-01 BOUCHER GAéTAN Automatic monitoring and display system for use with a diggins machine
KR100621976B1 (ko) 2002-04-24 2006-09-13 볼보 컨스트럭션 이키프먼트 홀딩 스웨덴 에이비 포지티브 제어방식의 붐 다운기능을 갖는 건설중장비
US6945335B2 (en) * 2003-10-06 2005-09-20 Komatsu Ltd. Oil-pressure controlling device for earthmoving machine
US7059124B2 (en) * 2003-12-01 2006-06-13 Komatsu Ltd. Hydraulic control apparatus for work machines
US7441404B2 (en) * 2004-11-30 2008-10-28 Caterpillar Inc. Configurable hydraulic control system
US7729833B2 (en) * 2006-09-11 2010-06-01 Caterpillar Inc. Implement control system based on input position and velocity
EP3239408B1 (en) 2009-03-26 2018-10-31 Komatsu Ltd. Control method and control apparatus for work vehicle
KR101715940B1 (ko) 2010-06-23 2017-03-13 두산인프라코어 주식회사 티칭 및 플레이백을 이용한 건설기계의 작업궤적 제어 장치 및 그 방법
CN102947513B (zh) 2010-06-23 2015-07-08 斗山英维高株式会社 建筑机械的作业轨迹控制装置及其方法
US8639393B2 (en) * 2010-11-30 2014-01-28 Caterpillar Inc. System for automated excavation planning and control
JP5572586B2 (ja) 2011-05-19 2014-08-13 日立建機株式会社 作業機械の油圧駆動装置
US9110468B2 (en) * 2013-01-31 2015-08-18 Caterpillar Inc. Universal remote operator station

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000336690A (ja) * 1999-06-01 2000-12-05 Hitachi Constr Mach Co Ltd 建設機械の領域制限掘削制御装置
JP2012172382A (ja) * 2011-02-21 2012-09-10 Sumitomo Heavy Ind Ltd 掘削機
JP2014095396A (ja) * 2012-11-07 2014-05-22 Hitachi Constr Mach Co Ltd 閉回路油圧駆動装置

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019012701A1 (ja) * 2017-07-14 2019-01-17 株式会社小松製作所 作業機械および作業機械の制御方法
US10787788B2 (en) 2017-07-14 2020-09-29 Komatsu Ltd. Work machine and control method for work machine
JPWO2019012701A1 (ja) * 2017-07-14 2020-05-07 株式会社小松製作所 作業機械および作業機械の制御方法
CN111032970A (zh) * 2018-04-17 2020-04-17 日立建机株式会社 作业机械
KR20200032149A (ko) 2018-04-17 2020-03-25 히다찌 겐끼 가부시키가이샤 작업 기계
JPWO2019202673A1 (ja) * 2018-04-17 2020-09-03 日立建機株式会社 作業機械
WO2019202673A1 (ja) 2018-04-17 2019-10-24 日立建機株式会社 作業機械
CN111032970B (zh) * 2018-04-17 2022-02-25 日立建机株式会社 作业机械
US11453995B2 (en) 2018-04-17 2022-09-27 Hitachi Construction Machinery Co., Ltd. Work machine
JP2021055427A (ja) * 2019-09-30 2021-04-08 日立建機株式会社 建設機械
WO2021065952A1 (ja) 2019-09-30 2021-04-08 日立建機株式会社 作業機械
KR20210115009A (ko) 2019-09-30 2021-09-24 히다찌 겐끼 가부시키가이샤 작업 기계
JP7083326B2 (ja) 2019-09-30 2022-06-10 日立建機株式会社 建設機械
EP4039892A4 (en) * 2019-09-30 2023-10-11 Hitachi Construction Machinery Co., Ltd. WORKING MACHINE

Also Published As

Publication number Publication date
JP5865510B2 (ja) 2016-02-17
KR101658326B1 (ko) 2016-09-22
KR20160043924A (ko) 2016-04-22
CN104619921B (zh) 2016-10-12
DE112014000176B4 (de) 2021-06-17
DE112014000176T5 (de) 2015-05-07
CN104619921A (zh) 2015-05-13
US20160069044A1 (en) 2016-03-10
US9447562B2 (en) 2016-09-20
JPWO2015025985A1 (ja) 2017-03-02

Similar Documents

Publication Publication Date Title
WO2015025985A1 (ja) 作業車両および作業車両の制御方法
JP5864775B2 (ja) 作業車両
JP5791827B2 (ja) 作業車両
JP5732598B1 (ja) 作業車両
JP5732599B1 (ja) 作業車両
JP5990642B2 (ja) 建設機械の制御システム、建設機械、及び建設機械の制御方法
JP5856685B1 (ja) 建設機械の制御システム、建設機械、及び建設機械の制御方法
KR101746324B1 (ko) 건설 기계의 제어 시스템, 건설 기계, 및 건설 기계의 제어 방법
JP5654144B1 (ja) 建設機械の制御システム及び制御方法
US20160040398A1 (en) Construction machine control system and method of controlling construction machine
KR20160004297A (ko) 작업 기계의 제어 시스템, 작업 기계 및 작업 기계의 제어 방법
WO2019012701A1 (ja) 作業機械および作業機械の制御方法
JP6826050B2 (ja) 建設機械および制御方法
KR101584946B1 (ko) 작업 차량

Legal Events

Date Code Title Description
ENP Entry into the national phase

Ref document number: 2014546643

Country of ref document: JP

Kind code of ref document: A

WWE Wipo information: entry into national phase

Ref document number: 14423452

Country of ref document: US

ENP Entry into the national phase

Ref document number: 20157004882

Country of ref document: KR

Kind code of ref document: A

WWE Wipo information: entry into national phase

Ref document number: 112014000176

Country of ref document: DE

Ref document number: 1120140001767

Country of ref document: DE

121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 14837546

Country of ref document: EP

Kind code of ref document: A1

122 Ep: pct application non-entry in european phase

Ref document number: 14837546

Country of ref document: EP

Kind code of ref document: A1