MY198020A - Support structure for tunnel having ultra-large variable section - Google Patents

Support structure for tunnel having ultra-large variable section

Info

Publication number
MY198020A
MY198020A MYPI2017702979A MYPI2017702979A MY198020A MY 198020 A MY198020 A MY 198020A MY PI2017702979 A MYPI2017702979 A MY PI2017702979A MY PI2017702979 A MYPI2017702979 A MY PI2017702979A MY 198020 A MY198020 A MY 198020A
Authority
MY
Malaysia
Prior art keywords
tunnel
primary support
secondary lining
vault
support
Prior art date
Application number
MYPI2017702979A
Inventor
Shenglin Jiang
Xiangdong Xu
Yanfeng Gong
Shupeng Li
Qizhu Jiao
Zhiwei Yan
Junru Zhang
Jianbo Kui
Wenhao Sun
Chunmei Wang
Haiman Guo
Jun Hong
Lijie Chen
Original Assignee
China Railway Siyuan Survey And Design Group Co ?Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from CN201420795169.6U external-priority patent/CN204436406U/en
Priority claimed from CN201410777849.XA external-priority patent/CN104500100A/en
Priority claimed from CN201410777881.8A external-priority patent/CN104405411B/en
Priority claimed from CN201420797002.3U external-priority patent/CN204327118U/en
Priority claimed from CN201410776845.XA external-priority patent/CN104653197B/en
Application filed by China Railway Siyuan Survey And Design Group Co ?Ltd filed Critical China Railway Siyuan Survey And Design Group Co ?Ltd
Publication of MY198020A publication Critical patent/MY198020A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

Disclosed is a support structure for a tunnel having ultra-large variable section, the support structure comprising, along an annular shape of the tunnel, a vault (11) at a top portion, an inverted arch (12) at a bottom portion, side walls (13) at two sides and pilot tunnels outside of the side walls (13), and also comprising, along a radial direction of the tunnel, a secondary lining (2) at an inner layer. Pilot tunnel primary supports (42) are disposed outside the secondary linings of the two side walls (13); a boot-type large wall footing (41) is cast between the pilot tunnel primary support (42) and the secondary lining at the two side walls; a primary support (31) is disposed, along the radial direction of the tunnel, on an outer surface of a secondary lining of the vault (11) and a secondary lining (21) of the inverted arch; an inner layer primary support (32) is disposed between the secondary lining and the primary support (31) of the vault; the primary support (31) of the vault and the inner layer primary support (32) are both supported by the boot-type large wall footing (41); and the primary support of the inverted arch is supported by the pilot tunnel primary support (42). The support structure can better overcome insufficient bearing capacity of a soft foundation, and provide a stable foundation for the upper portion of the structure.
MYPI2017702979A 2014-12-15 2015-11-11 Support structure for tunnel having ultra-large variable section MY198020A (en)

Applications Claiming Priority (6)

Application Number Priority Date Filing Date Title
CN201420795169.6U CN204436406U (en) 2014-12-15 2014-12-15 Super large Varied section tunnel support structure
CN201410777849.XA CN104500100A (en) 2014-12-15 2014-12-15 Advanced support structure for oversized variable-section tunnel
CN201410777881.8A CN104405411B (en) 2014-12-15 2014-12-15 Oversized variable cross section tunnel supporting structure
CN201420797002.3U CN204327118U (en) 2014-12-15 2014-12-15 Super large Varied section tunnel advanced support structure
CN201410776845.XA CN104653197B (en) 2014-12-15 2014-12-15 Method for constructing extra-large variable cross section tunnel
PCT/CN2015/094286 WO2016095631A1 (en) 2014-12-15 2015-11-11 Support structure for tunnel having ultra-large variable section

Publications (1)

Publication Number Publication Date
MY198020A true MY198020A (en) 2023-07-26

Family

ID=56125861

Family Applications (2)

Application Number Title Priority Date Filing Date
MYPI2017702978A MY198470A (en) 2014-12-15 2015-11-11 Method for constructing extra-large variable cross section tunnel
MYPI2017702979A MY198020A (en) 2014-12-15 2015-11-11 Support structure for tunnel having ultra-large variable section

Family Applications Before (1)

Application Number Title Priority Date Filing Date
MYPI2017702978A MY198470A (en) 2014-12-15 2015-11-11 Method for constructing extra-large variable cross section tunnel

Country Status (3)

Country Link
MY (2) MY198470A (en)
SE (2) SE543306C2 (en)
WO (3) WO2016095630A1 (en)

Families Citing this family (95)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107447776A (en) * 2017-05-11 2017-12-08 吴震 The pull-type vertical retaining wall structure structure of anchor and construction method
CN106988750B (en) * 2017-05-26 2023-07-14 中铁四局集团有限公司 Implementation mode of ultra-short-distance underpass of existing station of large-span interval tunnel
CN107130977B (en) * 2017-06-27 2023-10-10 长江勘测规划设计研究有限责任公司 Hollow guide excavation structure and excavation method for ultra-large span dome of underground nuclear reactor cavity
CN107630706B (en) * 2017-10-24 2023-05-26 中交第二航务工程局有限公司 Tunnel bottom structure for eliminating tunnel inverted arch bulge in high-earth-pressure area and construction method
CN107605493A (en) * 2017-10-31 2018-01-19 淮矿西部煤矿投资管理有限公司 A kind of comprehensive pick construction system and method
CN107605509A (en) * 2017-11-08 2018-01-19 中铁十局集团有限公司 Sand-pebble layer small curve radius shallow tunnel subsurface excavation method advanced supporting construction method
CN107916935B (en) * 2017-11-13 2024-01-23 浙江大学城市学院 Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method
CN108005675A (en) * 2017-11-16 2018-05-08 中国电建集团昆明勘测设计研究院有限公司 Dynamic superposition coupling supporting method and supporting structure for fault fracture zone roadway
CN107939419A (en) * 2017-12-20 2018-04-20 贵州大学 A kind of tunnel U-shaped steel covers canopy supporting construction
CN107893669A (en) * 2017-12-20 2018-04-10 贵州大学 A kind of U-shaped steel for roadway support covers booth structure
CN108798720B (en) * 2018-03-30 2023-08-01 中国建筑股份有限公司 Anchor grid integrated arch foot reinforcement system for underground engineering arch cover method and construction method thereof
CN108590704A (en) * 2018-04-27 2018-09-28 中铁十二局集团有限公司 Light section per-fore pouring liquid with small pipe pays maintaining method in advance
CN108643934B (en) * 2018-04-28 2024-04-02 中铁二院重庆勘察设计研究院有限责任公司 Construction method based on combined step inverted arch in upper-layer and lower-layer overlapped tunnel
CN108561156B (en) * 2018-04-30 2024-03-19 安徽省公路桥梁工程有限公司 Separated tunnel arch-changing supporting structure and construction method thereof
CN108979659B (en) * 2018-07-04 2022-02-01 中铁第一勘察设计院集团有限公司 Reinforcing structure and method for underpass structure of soft soil water-rich large-section tunnel group
CN108645298A (en) * 2018-07-20 2018-10-12 中铁十八局集团有限公司 The micro- blasting construction method that shakes of the leading pilot tunnel of existing tunnel is closed at short skylight point interval
CN109026057A (en) * 2018-07-25 2018-12-18 西南交通大学 A kind of tunnel combined support structure suitable for drift-sand stratum
CN109404005B (en) * 2018-11-09 2023-09-15 中铁第一勘察设计院集团有限公司 Pre-reinforcing system for small hole and large hole of underground tunnel and construction method
CN109372521A (en) * 2018-11-22 2019-02-22 中铁十四局集团有限公司 New pipe-roof method construction technology and construction pipe suspension device
CN109538236B (en) * 2018-12-07 2024-04-02 中铁十局集团有限公司 Tunnel entering structure and tunnel entering construction method
CN109538246A (en) * 2018-12-26 2019-03-29 中铁科学研究院有限公司 Ledge method tunneling subway station arch springing ruggedized construction and construction method
CN109667603A (en) * 2018-12-28 2019-04-23 中铁第四勘察设计院集团有限公司 A kind of super shallow-buried tunnel structure and construction method
CN109505630B (en) * 2019-01-14 2023-09-08 中铁一局集团有限公司 Full-hydraulic crawler-type self-propelled trestle and construction method
CN109578014B (en) * 2019-01-28 2024-02-09 中铁第六勘察设计院集团有限公司 Anti-surging bottom sealing structure and construction method
CN109538250B (en) * 2019-01-28 2023-09-15 中南大学 Device and method for quick construction of tunnel primary support with mould sprayed concrete
CN109885329B (en) * 2019-02-28 2023-04-07 新华三信息技术有限公司 Upgrading method and system and electronic equipment
CN109763838B (en) * 2019-03-13 2023-09-15 中铁第一勘察设计院集团有限公司 Assembled inverted arch structure suitable for tunnel by drilling and blasting method and assembling method thereof
CN109869189A (en) * 2019-03-22 2019-06-11 云南建投基础工程有限责任公司 A kind of tunnel pernicious gas and underground moisture are from exhaust system device
CN109973111A (en) * 2019-03-22 2019-07-05 北京城建集团有限责任公司 A kind of pilot tunnel water storage system and its construction method
CN109882206B (en) * 2019-04-09 2020-05-22 湖南科技大学 Multi-support cooperative method for controlling coal mine broken surrounding rock
CN109973100B (en) * 2019-05-21 2024-02-09 中铁第六勘察设计院集团有限公司 Supporting form for realizing small-radius turning of tunnel by mining method and construction method
CN110017149A (en) * 2019-05-21 2019-07-16 成都市建筑设计研究院 A kind of ledge tunneling is suitable to build underground structure and construction method
CN112031831A (en) * 2019-06-03 2020-12-04 甘肃路桥建设集团有限公司 Tunnel steel pipe arch primary support structure and support method thereof
CN110230504A (en) * 2019-06-25 2019-09-13 深圳市综合交通设计研究院有限公司 A kind of soft lower hard full packet waterproof of compound stratum composite lining structure resistant to pressure and its construction method
CN110307003B (en) * 2019-08-12 2024-04-12 中铁二院工程集团有限责任公司 Pressure relief pilot tunnel suitable for preventing tunnel bottom from deforming and construction method thereof
CN110750820B (en) * 2019-09-19 2023-03-28 中国人民解放军军事科学院国防工程研究院工程防护研究所 Underground cave depot excavation support stability judging method based on energy mutation
CN110700852A (en) * 2019-10-14 2020-01-17 中铁第四勘察设计院集团有限公司 Single-hole double-line mine method tunnel section with mid-partition wall designed by urban D-type vehicle clearance
CN110700851B (en) * 2019-10-14 2024-07-09 中铁第四勘察设计院集团有限公司 Single-hole double-line jet fan tunnel section designed based on urban D-type vehicle limit
CN110714778B (en) * 2019-10-14 2024-07-09 中铁第四勘察设计院集团有限公司 Mine tunnel section without intermediate wall for city D-type vehicle limit design single-hole double-line
CN111206943B (en) * 2020-02-21 2024-06-25 上海市城市建设设计研究总院(集团)有限公司 Micro-interference post-compensation underground excavation interface connecting component and construction method thereof
CN111125827A (en) * 2020-02-28 2020-05-08 中国十七冶集团有限公司 Loess tunnel earthwork excavation and supporting method based on BIM technology
CN111188638A (en) * 2020-04-01 2020-05-22 黄河勘测规划设计研究院有限公司 Advanced support pipe shed structure under silty-fine sand geological condition and construction method thereof
CN111305219A (en) * 2020-04-01 2020-06-19 中铁第一勘察设计院集团有限公司 Existing tunnel crossing system based on foundation pit jumping excavation and arch cover conversion and construction method
CN111472812A (en) * 2020-04-24 2020-07-31 重庆交通建设(集团)有限责任公司 Construction method for filling and pouring concrete into inverted arch of tunnel
CN111691894A (en) * 2020-06-22 2020-09-22 中铁十八局集团有限公司 Construction process of hole pipe shed
CN112065443A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam second section construction method based on karst cave underground river environment tunnel construction
CN112031814B (en) * 2020-09-17 2022-07-29 攀钢集团工程技术有限公司 Cave-entering construction method for crossing shallow-layer high-load highway
CN111997646B (en) * 2020-09-27 2024-07-09 中铁第四勘察设计院集团有限公司 Mine tunnel supporting structure for running high-speed rail downwards and construction method thereof
CN112253172B (en) * 2020-10-16 2024-06-28 中铁第四勘察设计院集团有限公司 Tunnel bottom lining structure provided with tie beam and construction method thereof
CN112228117A (en) * 2020-10-28 2021-01-15 中铁十二局集团有限公司 Construction method for large-section primary support large arch springing
CN114439481B (en) * 2020-11-02 2024-06-07 上海宝冶集团有限公司 Variable cross section excavation method for underground excavation tunnel with small cross section and large cross section
CN112627857B (en) * 2020-12-07 2022-11-15 广东华隧建设集团股份有限公司 Construction method of tunnel secondary lining
CN112647985B (en) * 2020-12-28 2022-08-12 中国科学院武汉岩土力学研究所 Combined supporting device of lock pin anchor pipe/anchor rod and steel arch frame and construction method
CN112682048B (en) * 2020-12-31 2023-08-29 中铁大桥局集团第五工程有限公司 Replacement reinforcement construction method for small clear distance up-span existing tunnel of newly-built tunnel
CN112682062B (en) * 2020-12-31 2023-08-25 中铁大桥局集团第五工程有限公司 Construction method of small-clear-distance stereo cross tunnel
CN112832785B (en) * 2021-02-24 2024-05-24 中铁第六勘察设计院集团有限公司 Shield mine combined construction method tunnel submarine docking method and miniature dismounting machine cavity
CN112855225B (en) * 2021-03-01 2024-04-30 中铁上海工程局集团有限公司 Soft rock tunnel supporting construction method with high safety
CN112963177A (en) * 2021-04-19 2021-06-15 山东建筑大学 Supporting method and structure for weak stratum shallow-buried large-section tunnel with hole
CN113153317B (en) * 2021-05-11 2024-06-21 北华航天工业学院 Construction method and grouting device suitable for soft rock large-section tunnel
CN113309550B (en) * 2021-05-19 2024-02-27 甘肃路桥建设集团有限公司 Modular temporary supporting and assembling structure for ultra-large section loess tunnel
CN113187514B (en) * 2021-05-25 2024-02-23 中铁九局集团第七工程有限公司 Construction method for dovetail section of urban railway mine tunnel
CN115434709B (en) * 2021-06-01 2024-06-07 上海宝冶集团有限公司 Construction method for collapse body of through tunnel bedding section
CN113392449B (en) * 2021-06-01 2022-12-30 中铁二院工程集团有限责任公司 Optimization design method of large-span arch support composite foundation
CN113294175B (en) * 2021-06-03 2023-12-29 中国建筑股份有限公司 Construction method of tunnel secondary lining structure and tunnel secondary lining structure
CN113338951B (en) * 2021-06-30 2023-11-03 中交路桥建设有限公司 Three-step roof-picking construction method for rapid tunnel intersection
CN113565513A (en) * 2021-07-13 2021-10-29 中交路桥华南工程有限公司 Upper and lower step reserved core soil excavation method for tunnel excavation
CN113847050B (en) * 2021-07-16 2023-08-22 中交投资南京有限公司 Construction method of ultra-long highway tunnel in lava mountain area
CN113738399A (en) * 2021-09-01 2021-12-03 上海市政工程设计研究总院(集团)有限公司 Underground excavation tunnel large pipe shed guide wall structure and construction method thereof
CN113756868B (en) * 2021-09-14 2024-06-25 东莞理工学院 Geotechnical engineering underground side wall construction method
CN113803073B (en) * 2021-09-27 2024-01-19 长江勘测规划设计研究有限责任公司 Construction method of tunnel structure for manually clearing obstacle in water-rich sand layer
CN114060063A (en) * 2021-11-01 2022-02-18 中铁十九局集团第二工程有限公司 Double-layer steel frame concrete-sprayed primary support structure suitable for large deformation of tunnel and support method
CN114046162A (en) * 2021-11-19 2022-02-15 中电建路桥集团有限公司 High ground temperature tunnel bottom plate heat insulation structure
CN114086968B (en) * 2021-11-27 2024-04-09 中铁广州工程局集团有限公司 Construction method for undermining existing building undercut tunnel
CN114109421B (en) * 2021-12-03 2024-01-30 中铁隧道局集团有限公司 Construction method for open TBM through long fault fracture zone
CN114183149A (en) * 2021-12-14 2022-03-15 中铁工程装备集团有限公司 Underground space mechanized construction method based on pilot tunnel expanding excavation
CN114320340B (en) * 2021-12-28 2023-09-12 中铁第六勘察设计院集团有限公司 Large-span non-column underground tunnel structure and method based on advanced pilot tunnel and opposite-pulling anchor cable
CN114233302B (en) * 2021-12-29 2024-03-15 中铁四院集团西南勘察设计有限公司 Arch cover construction method suitable for underground excavation station
CN114320312A (en) * 2022-01-06 2022-04-12 江西省交通设计研究院有限责任公司 Tunnel entering construction method of primary support wall-pasting method tunnel
CN114320314A (en) * 2022-01-11 2022-04-12 龙元建设集团股份有限公司 Zoning excavation method for small-clear-distance and ultra-large-section highway tunnel
CN114575877A (en) * 2022-03-04 2022-06-03 中铁第一勘察设计院集团有限公司 Construction method of tunnel shock insulation structure
CN114704297B (en) * 2022-03-30 2024-07-16 中铁二十局集团第五工程有限公司 Integral inverted arch structure of tunnel and construction process thereof
CN114753401B (en) * 2022-04-08 2023-05-26 中铁十九局集团第五工程有限公司 Construction method for tunnel bottom karst cave treatment
CN114856580A (en) * 2022-04-26 2022-08-05 中建八局第三建设有限公司 Safe construction method for ultra-shallow buried excavation large-section tunnel of city core business district
CN115142878B (en) * 2022-07-04 2023-05-16 中铁十二局集团有限公司 CRD method subsection linkage rapid construction method for upper soft and lower hard strata
CN115163125B (en) * 2022-07-29 2024-05-14 中南大学 Differential grading control method and system suitable for asymmetric extrusion soft rock tunnel
CN115288705A (en) * 2022-08-09 2022-11-04 云南建投第四建设有限公司 Construction method for transitional part of intersection section of bifurcation tunnel and ultra-large span
CN115306442B (en) * 2022-08-22 2024-07-16 中铁第一勘察设计院集团有限公司 Tunnel pre-supporting structure of sandy loess stratum and construction method
CN115452219A (en) * 2022-08-24 2022-12-09 珠海大横琴股份有限公司 Two-lining contact pressure testing device and mounting method thereof
CN115306424B (en) * 2022-08-29 2023-07-21 中国建筑第二工程局有限公司 Large-section transverse channel horsehead door breaking operation platform and construction method
CN115405325A (en) * 2022-08-31 2022-11-29 中铁第一勘察设计院集团有限公司 Design method of tunnel seismic isolation structure
CN115478880B (en) * 2022-10-21 2024-05-31 中铁隧道局集团有限公司 Construction method for reducing rebound rate of sprayed concrete
CN115961513A (en) * 2022-11-22 2023-04-14 中铁二院工程集团有限责任公司 Method for carrying out quadruple interchange fluffing on railway by using tunnel engineering
CN116163761A (en) * 2023-04-06 2023-05-26 中交(广州)建设有限公司 Quick switching structure and quick switching excavation method for tunnel in underground tunnel
CN117107777B (en) * 2023-10-13 2024-04-05 中国铁路设计集团有限公司 Method for constructing underground excavation subway section from open excavation slope foundation pit
CN117248916B (en) * 2023-11-20 2024-07-23 中国铁路设计集团有限公司 Construction method of plane right-angle turning structure of underground excavation exit of subway

Family Cites Families (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4445723A (en) * 1982-07-26 1984-05-01 Mcquade Paul D Method of circle mining of ore
JP2648051B2 (en) * 1991-07-19 1997-08-27 株式会社フジタ Construction method of arch shell in tunnel precedent
JP2004052408A (en) * 2002-07-22 2004-02-19 Maeda Corp Tunnel excavating method
KR20060084203A (en) * 2005-01-19 2006-07-24 주식회사 하이콘엔지니어링 Method for constructing 2-arch tunnel using steel pile support
CN101666232B (en) * 2009-09-27 2012-08-22 中铁四局集团有限公司 Construction method for six-part excavation of super-large section tunnel
JP2012036624A (en) * 2010-08-06 2012-02-23 Taisei Corp Tunnel construction method
CN102182466B (en) * 2011-04-08 2013-05-01 中铁上海设计院集团有限公司 Excavating method for jump-digging of double-side wall guide pit combined arch part of tunnel
CN102226398A (en) * 2011-06-02 2011-10-26 中铁二院工程集团有限责任公司 Soft rock four-line large-span tunnel compound double-side wall bracing cable conversion excavation construction method
CN102345460A (en) * 2011-06-21 2012-02-08 北京交通大学 Settlement control method for shallow large-section loess tunnel
CN102797481B (en) * 2012-08-13 2015-03-25 中铁一局集团有限公司 Large-span tunnel arch secondary lining steel bar binding construction method based on skeleton beams
CN103306687B (en) * 2012-10-31 2015-09-16 北京中铁瑞威基础工程有限公司 Soft rock tunnel long cantilever horizontal jet grouting Deformation control construction method
CN103437783A (en) * 2013-08-22 2013-12-11 天津市市政工程设计研究院 Shallow-buried excavation long-span pilot tunnel arch cover combined construction method
CN103775095B (en) * 2014-02-26 2015-10-28 中铁第一勘察设计院集团有限公司 The advanced two pilot tunnel in Ruan Ji tunnel, the mountain ridge and construction method thereof
CN104653197B (en) * 2014-12-15 2017-02-08 中铁第四勘察设计院集团有限公司 Method for constructing extra-large variable cross section tunnel
CN104405411B (en) * 2014-12-15 2017-05-10 中铁第四勘察设计院集团有限公司 Oversized variable cross section tunnel supporting structure
CN104500100A (en) * 2014-12-15 2015-04-08 中铁第四勘察设计院集团有限公司 Advanced support structure for oversized variable-section tunnel
CN204436406U (en) * 2014-12-15 2015-07-01 中铁第四勘察设计院集团有限公司 Super large Varied section tunnel support structure
CN204327118U (en) * 2014-12-15 2015-05-13 中铁第四勘察设计院集团有限公司 Super large Varied section tunnel advanced support structure

Also Published As

Publication number Publication date
SE1750912A1 (en) 2017-07-12
SE543306C2 (en) 2020-11-24
SE543647C2 (en) 2021-05-18
MY198470A (en) 2023-08-31
WO2016095630A1 (en) 2016-06-23
WO2016095631A1 (en) 2016-06-23
SE1750913A1 (en) 2017-07-12
WO2016095629A1 (en) 2016-06-23

Similar Documents

Publication Publication Date Title
MY198020A (en) Support structure for tunnel having ultra-large variable section
BR112014018805A8 (en) CONCRETE GALLERY SECTION AND CONCRETE GALLERY ASSEMBLY
MX2017017043A (en) A fluid solids contacting device.
CL2015001995A1 (en) Base for container with variable displacement.
MX2014006384A (en) Low cost burner.
USD735999S1 (en) Floor tile
USD756134S1 (en) Floor tile
MX2018004454A (en) High capacity linear valve cage.
USD732296S1 (en) Floor tile
BR112017008715A2 (en) method and apparatus for the manufacture of soft capsules
BR112018067618A2 (en) support unit for a self-supporting shoring system, shoring system and pipe laying method
MY172102A (en) Semi rigid precast wall system
PL3838666T3 (en) Support for lifting container by upper holes of the container
CL2012001025A1 (en) Green roof pot module comprising: a pot that includes a bottom wall, a plurality of side walls each including, an upper part and a lower part, where the bottom wall and the plurality of side walls cooperate with each other to form an interior space, and an upwardly extending biodegradable collar member; method.
USD742123S1 (en) Floor tile
EP3812523C0 (en) Shaft bottom lining
BR112018008280A2 (en) sliding bearing made of synthetic resin
PL3580429T3 (en) Reinforcement system for the concrete lining of the inner shell of a tunnel construction
USD732839S1 (en) Floor tile
PT3475488T (en) Method for optimizing processes for increasing the load-bearing capacity of foundation grounds
PH12019000375A1 (en) Hollow brick with foot portions
PH22017000283U1 (en) Metallurgical furnace
USD732298S1 (en) Floor tile
UA100021U (en) FOUNDATION FOR CONSTRUCTION of tower type
TWD186051S (en) Support pillars for floating platforms for installing solar panels