WO2016095631A1 - Support structure for tunnel having ultra-large variable section - Google Patents

Support structure for tunnel having ultra-large variable section Download PDF

Info

Publication number
WO2016095631A1
WO2016095631A1 PCT/CN2015/094286 CN2015094286W WO2016095631A1 WO 2016095631 A1 WO2016095631 A1 WO 2016095631A1 CN 2015094286 W CN2015094286 W CN 2015094286W WO 2016095631 A1 WO2016095631 A1 WO 2016095631A1
Authority
WO
WIPO (PCT)
Prior art keywords
secondary lining
support
tunnel
arch
wall
Prior art date
Application number
PCT/CN2015/094286
Other languages
French (fr)
Chinese (zh)
Inventor
龚彦峰
江胜林
徐向东
李树鹏
张俊儒
焦齐柱
隗建波
颜志伟
孙文昊
王春梅
郭海满
洪军
陈利杰
Original Assignee
中铁第四勘察设计院集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from CN201420795169.6U external-priority patent/CN204436406U/en
Priority claimed from CN201410777881.8A external-priority patent/CN104405411B/en
Priority claimed from CN201420797002.3U external-priority patent/CN204327118U/en
Priority claimed from CN201410777849.XA external-priority patent/CN104500100A/en
Priority claimed from CN201410776845.XA external-priority patent/CN104653197B/en
Application filed by 中铁第四勘察设计院集团有限公司 filed Critical 中铁第四勘察设计院集团有限公司
Priority to SE1750912A priority Critical patent/SE543306C2/en
Priority to MYPI2017702979A priority patent/MY198020A/en
Publication of WO2016095631A1 publication Critical patent/WO2016095631A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for

Definitions

  • the invention relates to the field of super large section tunnel construction, in particular to a super large variable section tunnel support structure.
  • the composite lining based on the new Austrian method is basically adopted, and the anchor spray is used as the initial support, and the concrete is used as the secondary lining.
  • the shape of the support structure is similar, the difference lies only in the strength of the support. Different stiffness, such as the length of the bolt, the thickness of the shotcrete, the change of the steel frame form, whether the steel fiber is added, the thickness of the molded concrete, the change of the concrete label, and so on.
  • it is extremely rare, and there is no experience to learn from it, and it is in the hole section.
  • the surface rock of the mountain is mostly weathered, the strength is low, the stability is poor, and the traditional supporting structure and excavation method are used for excavation. After the arching of the arch is large, the deformation of the arch is not suitable for control, and even the lining is cracked and unstable, resulting in collapse.
  • the present invention provides an oversized variable-section tunnel support structure, which better overcomes the problem of insufficient bearing capacity of a weak foundation and provides a stable foundation for the superstructure.
  • the invention provides an oversized variable-section tunnel support structure, which comprises a dome at the top of the tunnel, an inverting arch at the bottom, a side wall on both sides, and a secondary lining including an inner layer along the radial direction of the tunnel.
  • the guide wall is provided on both side walls, and the side wall is provided with secondary lining and initial support of the guide hole in the radial direction from the inside to the outside.
  • the initial support and the secondary lining of the guide hole are filled with boots.
  • the wall legs, the vaults and the inverting arches are provided with secondary lining and initial support from the inside to the outside in the radial direction of the tunnel, and the initial support of the vault is supported by the large foot of the shoe.
  • An inner layer initial support is disposed between the secondary lining of the dome and the initial support, and the inner layer is initially supported by the shoe-shaped wall.
  • the secondary lining comprises an inverting secondary lining and a secondary lining of the arch wall connected end to end, and the cross-section of the secondary lining of the arch wall is inverted U-shaped and extends from the bottom of one side wall to the other side through the vault Bottom of the wall, secondary arch lining and arch wall II
  • the secondary lining construction joint is located in the middle of the inner side wall of the shoe-shaped large wall.
  • the initial support is constructed by a spray anchor structure comprising a steel mesh, a steel frame, and a sprayed concrete, the anchor structure including a system anchor.
  • the initial support of the guide hole is formed by a spray anchor structure containing a steel frame and sprayed concrete, and the anchor structure includes a system anchor.
  • the inner layer initial support is composed of a steel frame and shotcrete.
  • the invention solves the problem that the bearing capacity of the weak foundation is insufficient by providing the guiding hole outside the side wall, and the initial support of the arch roof and the initial support of the inner layer are supported by the shoe-shaped large wall foot inside the guiding hole, which is the upper part.
  • the structure provides a stable foundation and strengthens the connection with the inverting arch; the initial support of the arch of the present invention and the initial support of the inner layer form a double-layer composite stiffening dome structure, which reduces the risk of temporary vertical support of the demolished arch and ensures construction safety.
  • due to the realization of early demolition reducing the amount of temporary support and increasing the degree of subsequent construction freedom, it is conducive to speeding up the construction schedule and reducing construction costs.
  • Figure 1 is a schematic view of the present invention
  • the present invention provides an oversized variable-section tunnel support structure, including a dome 11 at the top of the tunnel, a bottom arch 12 at the bottom, a side wall 13 on both sides, and a guide hole outside the side wall 13, which are included along the radial direction of the tunnel.
  • the secondary lining 2 with the inner layer and the outer lining 2 of the two side linings 2 on both sides are provided with the initial support 42 of the guide hole in the radial direction of the tunnel, the secondary support 42 of the guide hole and the secondary lining of the side walls 13
  • the shoe-type large wall foot 41 is infused between the two, the secondary lining 2 of the dome 11 and the outer surface of the secondary lining 2 of the inverted arch 12 are provided with an initial support 31 along the radial direction of the tunnel, and the secondary lining of the dome 11
  • An inner layer initial support 32 is provided between the initial support 31 and the initial support 31 and the inner layer initial support 32 of the dome 11 are supported by the shoe-shaped large wall legs 41.
  • the secondary lining 2 comprises an inverting secondary lining 21 and an arched secondary lining 22 connected end to end.
  • the arched wall secondary lining 22 has an inverted U-shaped cross section and is arched by the bottom of one side wall 13 Extend to the other side At the bottom of the wall 13, the construction joints of the inverted arch secondary lining 21 and the arched wall secondary lining 22 are located in the middle of the inner side wall of the shoe-shaped large wall foot 41.
  • the initial support 31 is constructed by a spray anchor structure including a steel mesh, a steel frame, and a sprayed concrete, and the anchor structure includes a bolt.
  • the pilot hole initial support 42 is constructed by a spray anchor structure including a steel frame and sprayed concrete, and the anchor structure includes a bolt.
  • the inner layer initial support 32 employs a shotcrete structure containing a steel frame and shotcrete.
  • the present invention comprises three sides of the side wall 13, the dome 11, and the inverting arch 12, and the side wall 13 is from the outside to the inside, that is, from the grazing side to the back soil side, and the system-containing anchor is sequentially disposed.
  • the guide hole initial support 42, the shoe type large wall foot 41, and the secondary lining 2, that is, the shoe type large wall foot 41 are disposed inside the guide hole.
  • the initial support 42 of the guide hole is made of 25cm thick C30 shotcrete with I20 steel frame with a longitudinal spacing of 0.8m/ ⁇ .
  • the system anchor 5 is a 3m long ⁇ 22mm mortar anchor with a ring and longitudinal spacing of 1.5m and 1.2m respectively; the shoe type large wall foot 41 is filled with C30 concrete; the second lining 2 is divided into the inverting arch secondary lining 21 and the arch wall.
  • the secondary lining 22, which is separately filled, is made of 90 cm thick moulded C35 reinforced concrete, and the construction joint is located approximately in the middle of the inner side wall of the shoe-shaped large wall foot 41.
  • the dome 11 is provided from the outside to the inside, that is, from the grazing side to the back soil side, and the initial support 31 including the system anchor 5, the inner layer initial support 32, the secondary lining 2, and the initial support 31 and The inner layer initial support 32 is supported on the shoe-shaped large wall legs 41.
  • the initial support 31 is made of 35cm thick C30 sprayed concrete, and a ⁇ 8mm steel mesh is arranged therein, and the HW200 steel frame with a grid spacing of 20cm ⁇ 20cm and a longitudinal spacing of 0.8m/ ⁇ is supported on the shoe-shaped large wall foot 41.
  • the system anchor 5 adopts a 6m long ⁇ 32mm self-drilling anchor with a ring and longitudinal spacing of 1.5m and 1.2m respectively.
  • the inner layer initial support 32 is made of 25cm thick C30 shotcrete with a longitudinal spacing of 0.8m/ ⁇ .
  • the 180 grille steel frame is supported on the shoe type large wall foot 41; the secondary lining 2 is made of 90 cm thick mold C35 reinforced concrete, and the arch wall secondary lining 22 is once filled by the formwork trolley.
  • the inverting arch 12 is provided with an initial support 31 and a secondary lining 2 from the outside to the back, that is, from the grazing side to the back soil side.
  • the initial support 3135cm thick C30 shotcrete which is equipped with ⁇ 8mm steel mesh, grid spacing 20cm ⁇ 20cm, longitudinal spacing 0.8m / ⁇ HW200 steel frame; secondary lining 2 using 90cm thick mold C35 reinforced concrete, Yang
  • the arch secondary lining 21 is poured prior to the secondary lining 22 of the arch wall.
  • the secondary lining 2 is divided into an inverted arch secondary lining 21 and an arched wall secondary lining 22, which are separately filled, and the construction joint is approximately located in the middle part of the inner side wall of the shoe-shaped large wall foot 41; the arched wall secondary lining 22 passes the formwork trolley One-time filling; the secondary arch lining 21 is poured before the secondary lining 22 of the arch wall.
  • the left guide hole is first excavated and the initial support and temporary support of the guide hole are applied in time; then the left guide is completed.
  • the inside of the cave is filled with the large wall legs, and the same process is used to complete the construction of the right guide hole.
  • the two pilot holes not only meet the requirements of construction stability, but also the geological conditions in front, and leave room for the expansion of the base of the boots.
  • the large shoe-shaped foot legs inside the left and right guide holes provide a stable foundation for the superstructure and strengthen the connection with the inverting arch.
  • the upper part of the left side of the arch is excavated and the initial support, temporary vertical support, and temporary inverted arch are applied in time; then the lower half is excavated and the initial support and temporary vertical support are applied in time.
  • the middle part of the arch is excavated and the initial support is applied in time to make the three parts of the initial support connected into an arch structure. Then it is applied as an initial support for the inner layer and removes the temporary vertical support and temporary inversion of the arch.
  • the initial support and the initial support of the inner layer form a composite stiffened arch structure, which meets the complex force requirements of the large-span structure of the arch, and can flexibly control the timing of the next step structure according to the monitoring and measurement conditions. Then excavate the core soil and apply it as an initial support for the invert.
  • the secondary lining of the inverted arch is poured, and then the bottom of the tunnel is filled and filled; finally, the arch lining is once filled with the template trolley.
  • the composite stiffened arch structure reduces the safety risk of removing temporary support, reduces the use of temporary support, increases freedom of operation, and speeds up construction progress.
  • the super large variable section tunnel support structure proposed by the invention is different from the conventional "anchor spray initial support + mold second lining", and the structural system emphasizes the safety of the arch portion, the stability of the wall foot, the novel technical idea and the originality.
  • the Enhanced Arch provides conditions for the removal of the temporary support (to meet the requirements of the oversized non-supporting structure after the arch is dismantled, to prevent the arch from being unstable), and to reduce the temporary vertical support of the arch. Risk of transformation;
  • the safety of the project and the reliability of the structure are effectively ensured, and the proposed innovative technical measures are successfully tested in the engineering practice, and the engineering practice proves that the support principle proposed by the invention is reasonable and effective, and embodies the present invention.
  • the innovation and engineering effectiveness of the invention have good engineering practicability.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

Disclosed is a support structure for a tunnel having ultra-large variable section, the support structure comprising, along an annular shape of the tunnel, a vault (11) at a top portion, an inverted arch (12) at a bottom portion, side walls (13) and pilot tunnels outside of the side walls (13) at two sides, and also comprising, along a radial direction of the tunnel, a secondary lining (2) at an inner layer; pilot tunnel primary supports (42) are disposed outside the secondary linings of the two side walls (13); a boot-type large wall footing (41) is cast between the pilot tunnel primary support (42) and the secondary lining at the two side walls; a primary support (31) is disposed, along the radial direction of the tunnel, on an outer surface of a secondary lining of the vault (11) and a secondary lining (21) of the inverted arch; an inner layer primary support (32) is disposed between the secondary lining and the primary support (31) of the vault; the primary support (31) of the vault and the inner layer primary support (32) are both supported by the boot-type large wall footing (41); and the primary support of the inverted arch is supported by the pilot tunnel primary support (42). The support structure can better overcome insufficient bearing capacity of a soft foundation, and provide a stable foundation for the upper portion of the structure.

Description

超大变断面隧道支护结构Super large variable section tunnel support structure 技术领域Technical field
本发明涉及超大断面隧道施工领域,具体涉及一种超大变断面隧道支护结构。The invention relates to the field of super large section tunnel construction, in particular to a super large variable section tunnel support structure.
背景技术Background technique
随着隧道工程建设的发展,超大断面隧道的支护方案有了长足的进步。但是大的来说基本上都采用基于新奥法的复合式衬砌,且均以锚喷作为初期支护,模筑混凝土作为二次衬砌,支护结构形态也是大同小异,差别仅在于支护的强度刚度不同,如,锚杆长短、喷射混凝土厚度变化、钢架形式变化、是否添加钢纤维、模筑混凝土厚度变化、混凝土标号改变等等。而对于本工程如此大跨度的隧道极其罕见,几无可借鉴经验,且处于洞口段,山体表层岩石大都风化极为严重,强度低,稳定性差,采用传统的支护结构和开挖方式,开挖后拱脚下沉大,拱顶变形不宜控制,甚至导致衬砌开裂、失稳,造成坍塌事故。With the development of tunnel construction, the support scheme for super-large section tunnels has made great progress. However, in large terms, the composite lining based on the new Austrian method is basically adopted, and the anchor spray is used as the initial support, and the concrete is used as the secondary lining. The shape of the support structure is similar, the difference lies only in the strength of the support. Different stiffness, such as the length of the bolt, the thickness of the shotcrete, the change of the steel frame form, whether the steel fiber is added, the thickness of the molded concrete, the change of the concrete label, and so on. For the tunnel with such a large span of this project, it is extremely rare, and there is no experience to learn from it, and it is in the hole section. The surface rock of the mountain is mostly weathered, the strength is low, the stability is poor, and the traditional supporting structure and excavation method are used for excavation. After the arching of the arch is large, the deformation of the arch is not suitable for control, and even the lining is cracked and unstable, resulting in collapse.
发明内容Summary of the invention
针对上述技术问题,本发明提供了一种超大变断面隧道支护结构,更好地克服软弱地基承载力不足问题,并为上部结构提供稳定基础。In view of the above technical problems, the present invention provides an oversized variable-section tunnel support structure, which better overcomes the problem of insufficient bearing capacity of a weak foundation and provides a stable foundation for the superstructure.
本发明提供了一种超大变断面隧道支护结构,沿隧道环向包括顶部的拱顶、底部的仰拱、两侧的边墙,沿隧道径向包括有内层的二次衬砌,其特征在于两侧边墙均设置有导洞,边墙由内而外沿隧道径向依次设置有二次衬砌和导洞初期支护,导洞初期支护和二次衬砌之间灌注有靴型大墙脚,拱顶和仰拱由内而外沿隧道径向依次设置有二次衬砌和初期支护,拱顶的初期支护支承于靴型大墙脚。The invention provides an oversized variable-section tunnel support structure, which comprises a dome at the top of the tunnel, an inverting arch at the bottom, a side wall on both sides, and a secondary lining including an inner layer along the radial direction of the tunnel. The guide wall is provided on both side walls, and the side wall is provided with secondary lining and initial support of the guide hole in the radial direction from the inside to the outside. The initial support and the secondary lining of the guide hole are filled with boots. The wall legs, the vaults and the inverting arches are provided with secondary lining and initial support from the inside to the outside in the radial direction of the tunnel, and the initial support of the vault is supported by the large foot of the shoe.
所述拱顶的二次衬砌和初期支护之间设置有内层初期支护,所述内层初期支护支承于靴型大墙脚。An inner layer initial support is disposed between the secondary lining of the dome and the initial support, and the inner layer is initially supported by the shoe-shaped wall.
所述二次衬砌包括首尾相连的仰拱二次衬砌和拱墙二次衬砌,拱墙二次衬砌的横截面呈倒U形并由一侧边墙的底部经拱顶延伸至另一侧边墙底部,仰拱二次衬砌和拱墙二 次衬砌的施工缝位于靴型大墙脚内侧壁的中部。The secondary lining comprises an inverting secondary lining and a secondary lining of the arch wall connected end to end, and the cross-section of the secondary lining of the arch wall is inverted U-shaped and extends from the bottom of one side wall to the other side through the vault Bottom of the wall, secondary arch lining and arch wall II The secondary lining construction joint is located in the middle of the inner side wall of the shoe-shaped large wall.
所述初期支护采用含有钢筋网、钢架、喷混凝土的喷锚结构构成,所述锚固结构包括系统锚杆。The initial support is constructed by a spray anchor structure comprising a steel mesh, a steel frame, and a sprayed concrete, the anchor structure including a system anchor.
所述导洞初期支护采用含有钢架、喷混凝土的喷锚结构构成,所述锚固结构包括系统锚杆。The initial support of the guide hole is formed by a spray anchor structure containing a steel frame and sprayed concrete, and the anchor structure includes a system anchor.
所述内层初期支护由钢架和喷混凝土构成。The inner layer initial support is composed of a steel frame and shotcrete.
本发明通过在边墙外侧设置导洞,更好地解决软弱地基承载力不足的问题,拱顶的的初期支护和内层初期支护均支承于导洞内部的靴型大墙脚,为上部结构提供稳定基础,同时强化与仰拱的连接;本发明拱顶的初期支护和内层初期支护配合形成双层复合加劲拱顶结构,降低拆除拱顶临时竖撑风险,确保施工安全,且由于实现了提早拆撑,减少临时支撑使用量,增加后续施工自由度,有利于加快施工进度,降低施工成本。The invention solves the problem that the bearing capacity of the weak foundation is insufficient by providing the guiding hole outside the side wall, and the initial support of the arch roof and the initial support of the inner layer are supported by the shoe-shaped large wall foot inside the guiding hole, which is the upper part. The structure provides a stable foundation and strengthens the connection with the inverting arch; the initial support of the arch of the present invention and the initial support of the inner layer form a double-layer composite stiffening dome structure, which reduces the risk of temporary vertical support of the demolished arch and ensures construction safety. Moreover, due to the realization of early demolition, reducing the amount of temporary support and increasing the degree of subsequent construction freedom, it is conducive to speeding up the construction schedule and reducing construction costs.
附图说明DRAWINGS
图1为本发明示意图Figure 1 is a schematic view of the present invention
其中,11-拱顶,12-仰拱,13-边墙,2-二次衬砌,21-仰拱二次衬砌,22-拱墙二次衬砌,31-初期支护,32-内层初期支护,41-靴型大墙脚,42-导洞初期支护,5-系统锚杆。Among them, 11-arch, 12-inverted arch, 13-side wall, 2-second lining, 21-inverted arch secondary lining, 22-arch wall secondary lining, 31-initial support, 32-inner initial Support, 41-boot type large wall feet, 42-guide initial support, 5-system anchor.
具体实施方式detailed description
下面结合说明书附图和具体实施例对本发明作进一步说明:The present invention is further described below in conjunction with the drawings and specific embodiments of the specification:
本发明提供了一种超大变断面隧道支护结构,沿隧道环形包括顶部的拱顶11、底部的仰拱12、两侧的边墙13和边墙13外侧的导洞,沿隧道径向包括有内层的二次衬砌2,两侧边墙13的二次衬砌2外侧均沿隧道径向设置有导洞初期支护42,导洞初期支护42和两侧边墙13的二次衬砌2之间灌注有靴型大墙脚41,拱顶11的二次衬砌2和仰拱12的二次衬砌2外侧表面均沿隧道径向设置有初期支护31,拱顶11的二次衬砌2和初期支护31之间设置有内层初期支护32,拱顶11的初期支护31和内层初期支护32均支承于靴型大墙脚41。所述二次衬砌2包括首尾相连的仰拱二次衬砌21和拱墙二次衬砌22,拱墙二次衬砌22的横截面呈倒U形并由一侧边墙13的底部经拱顶11延伸至另一侧边 墙13底部,仰拱二次衬砌21和拱墙二次衬砌22的施工缝位于靴型大墙脚41内侧壁的中部。所述初期支护31采用含有钢筋网、钢架、喷混凝土的喷锚结构构成,所述锚固结构包括锚杆。所述导洞初期支护42采用含有钢架、喷混凝土的喷锚结构构成,所述锚固结构包括锚杆。所述内层初期支护32采用含有钢架和喷混凝土的喷射混凝土结构。The present invention provides an oversized variable-section tunnel support structure, including a dome 11 at the top of the tunnel, a bottom arch 12 at the bottom, a side wall 13 on both sides, and a guide hole outside the side wall 13, which are included along the radial direction of the tunnel. The secondary lining 2 with the inner layer and the outer lining 2 of the two side linings 2 on both sides are provided with the initial support 42 of the guide hole in the radial direction of the tunnel, the secondary support 42 of the guide hole and the secondary lining of the side walls 13 The shoe-type large wall foot 41 is infused between the two, the secondary lining 2 of the dome 11 and the outer surface of the secondary lining 2 of the inverted arch 12 are provided with an initial support 31 along the radial direction of the tunnel, and the secondary lining of the dome 11 An inner layer initial support 32 is provided between the initial support 31 and the initial support 31 and the inner layer initial support 32 of the dome 11 are supported by the shoe-shaped large wall legs 41. The secondary lining 2 comprises an inverting secondary lining 21 and an arched secondary lining 22 connected end to end. The arched wall secondary lining 22 has an inverted U-shaped cross section and is arched by the bottom of one side wall 13 Extend to the other side At the bottom of the wall 13, the construction joints of the inverted arch secondary lining 21 and the arched wall secondary lining 22 are located in the middle of the inner side wall of the shoe-shaped large wall foot 41. The initial support 31 is constructed by a spray anchor structure including a steel mesh, a steel frame, and a sprayed concrete, and the anchor structure includes a bolt. The pilot hole initial support 42 is constructed by a spray anchor structure including a steel frame and sprayed concrete, and the anchor structure includes a bolt. The inner layer initial support 32 employs a shotcrete structure containing a steel frame and shotcrete.
如图所示,本发明包括两侧边墙13、拱顶11、仰拱12三部分,边墙13部位由外至内,即从迎土侧到背土侧,依次设置有含系统锚杆5的导洞初期支护42、靴型大墙脚41、二次衬砌2,即靴型大墙脚41设置于导洞的内部。其中,导洞初期支护42采用25cm厚C30喷混凝土,其内设有纵向间距0.8m/榀的I20钢架。系统锚杆5为3m长φ22mm砂浆锚杆,环、纵向间距分别为1.5m、1.2m;靴型大墙脚41采用C30混凝土灌筑;二次衬砌2分为仰拱二次衬砌21和拱墙二次衬砌22,两者分开灌筑,均为90cm厚模筑C35钢筋混凝土,施工缝近似位于靴型大墙脚41内侧壁中间部位。As shown in the figure, the present invention comprises three sides of the side wall 13, the dome 11, and the inverting arch 12, and the side wall 13 is from the outside to the inside, that is, from the grazing side to the back soil side, and the system-containing anchor is sequentially disposed. The guide hole initial support 42, the shoe type large wall foot 41, and the secondary lining 2, that is, the shoe type large wall foot 41 are disposed inside the guide hole. Among them, the initial support 42 of the guide hole is made of 25cm thick C30 shotcrete with I20 steel frame with a longitudinal spacing of 0.8m/榀. The system anchor 5 is a 3m long φ22mm mortar anchor with a ring and longitudinal spacing of 1.5m and 1.2m respectively; the shoe type large wall foot 41 is filled with C30 concrete; the second lining 2 is divided into the inverting arch secondary lining 21 and the arch wall. The secondary lining 22, which is separately filled, is made of 90 cm thick moulded C35 reinforced concrete, and the construction joint is located approximately in the middle of the inner side wall of the shoe-shaped large wall foot 41.
拱顶11由外至内,即从迎土侧到背土侧,依次设置有含系统锚杆5的初期支护31、内层初期支护32、二次衬砌2,且初期支护31和内层初期支护32组成均支承于靴型大墙脚41上。其中,初期支护31采用35cm厚C30喷混凝土,其内设置φ8mm钢筋网,网格间距20cm×20cm,纵向间距0.8m/榀的HW200钢架,支承于靴型大墙脚41上。系统锚杆5采用6m长φ32mm自钻式锚杆,环、纵向间距分别为1.5m、1.2m;内层初期支护32采用25cm厚C30喷混凝土,其内设有纵向间距0.8m/榀的180格栅钢架,支承于靴型大墙脚41上;二次衬砌2采用90cm厚模筑C35钢筋混凝土,拱墙二次衬砌22通过模板台车一次性灌筑。The dome 11 is provided from the outside to the inside, that is, from the grazing side to the back soil side, and the initial support 31 including the system anchor 5, the inner layer initial support 32, the secondary lining 2, and the initial support 31 and The inner layer initial support 32 is supported on the shoe-shaped large wall legs 41. Among them, the initial support 31 is made of 35cm thick C30 sprayed concrete, and a φ8mm steel mesh is arranged therein, and the HW200 steel frame with a grid spacing of 20cm×20cm and a longitudinal spacing of 0.8m/榀 is supported on the shoe-shaped large wall foot 41. The system anchor 5 adopts a 6m long φ32mm self-drilling anchor with a ring and longitudinal spacing of 1.5m and 1.2m respectively. The inner layer initial support 32 is made of 25cm thick C30 shotcrete with a longitudinal spacing of 0.8m/榀. The 180 grille steel frame is supported on the shoe type large wall foot 41; the secondary lining 2 is made of 90 cm thick mold C35 reinforced concrete, and the arch wall secondary lining 22 is once filled by the formwork trolley.
仰拱12由外至内,即从迎土侧到背土侧,依次设置初期支护31、二次衬砌2。其中,初期支护3135cm厚C30喷混凝土,其内设置φ8mm钢筋网,网格间距20cm×20cm,纵向间距0.8m/榀的HW200钢架;二次衬砌2采用90cm厚模筑C35钢筋混凝土,仰拱二次衬砌21先于拱墙二次衬砌22灌筑。The inverting arch 12 is provided with an initial support 31 and a secondary lining 2 from the outside to the back, that is, from the grazing side to the back soil side. Among them, the initial support 3135cm thick C30 shotcrete, which is equipped with φ8mm steel mesh, grid spacing 20cm × 20cm, longitudinal spacing 0.8m / 榀 HW200 steel frame; secondary lining 2 using 90cm thick mold C35 reinforced concrete, Yang The arch secondary lining 21 is poured prior to the secondary lining 22 of the arch wall.
二次衬砌2分为仰拱二次衬砌21和拱墙二次衬砌22,两者分开灌筑,施工缝近似位于靴型大墙脚41内侧壁中间部位;拱墙二次衬砌22通过模板台车一次性灌筑;仰拱二次衬砌21先于拱墙二次衬砌22灌筑。The secondary lining 2 is divided into an inverted arch secondary lining 21 and an arched wall secondary lining 22, which are separately filled, and the construction joint is approximately located in the middle part of the inner side wall of the shoe-shaped large wall foot 41; the arched wall secondary lining 22 passes the formwork trolley One-time filling; the secondary arch lining 21 is poured before the secondary lining 22 of the arch wall.
施工时,首先开挖左侧导洞并及时施作导洞初期支护、临时支护;之后完成左侧导 洞内部靴型大墙脚的灌筑,并采用相同工序完成右侧导洞施工。两个导洞既满足了施工稳定要求,探明了前方地质条件,也为扩大的靴型基础施作留下了空间。左右导洞内部的靴型大墙脚为上部结构提供稳定基础,同时强化与仰拱的连接。开挖拱部左侧上半部分并及时施作初期支护、临时竖撑、临时仰拱;之后开挖其下半部并及时施作初期支护、临时竖撑。采用相同程序完成拱部右侧上半部施工后开挖拱部中部并及时施作初期支护,使三部分初期支护连接成拱形结构。然后一次性施作内层初期支护并拆除拱部临时竖撑、临时仰拱。初期支护和内层初期支护形成复合的加劲拱部结构,满足拱部大跨结构的复杂受力要求,并能根据监控量测情况灵活掌控下步结构施作时机。然后开挖核心土,并及时施作仰拱的初期支护。拆除左、右导洞的临时支护后,灌筑仰拱二次衬砌,之后进行隧底填充灌注;最后用模板台车一次性灌筑拱墙二次衬砌。复合的加劲拱部结构降低拆除临时支撑的安全风险,减少临时支撑的使用,增加作业自由度,加快施工进度。During construction, the left guide hole is first excavated and the initial support and temporary support of the guide hole are applied in time; then the left guide is completed. The inside of the cave is filled with the large wall legs, and the same process is used to complete the construction of the right guide hole. The two pilot holes not only meet the requirements of construction stability, but also the geological conditions in front, and leave room for the expansion of the base of the boots. The large shoe-shaped foot legs inside the left and right guide holes provide a stable foundation for the superstructure and strengthen the connection with the inverting arch. The upper part of the left side of the arch is excavated and the initial support, temporary vertical support, and temporary inverted arch are applied in time; then the lower half is excavated and the initial support and temporary vertical support are applied in time. After the construction of the upper part of the right side of the arch is completed by the same procedure, the middle part of the arch is excavated and the initial support is applied in time to make the three parts of the initial support connected into an arch structure. Then it is applied as an initial support for the inner layer and removes the temporary vertical support and temporary inversion of the arch. The initial support and the initial support of the inner layer form a composite stiffened arch structure, which meets the complex force requirements of the large-span structure of the arch, and can flexibly control the timing of the next step structure according to the monitoring and measurement conditions. Then excavate the core soil and apply it as an initial support for the invert. After the temporary support of the left and right guide holes is removed, the secondary lining of the inverted arch is poured, and then the bottom of the tunnel is filled and filled; finally, the arch lining is once filled with the template trolley. The composite stiffened arch structure reduces the safety risk of removing temporary support, reduces the use of temporary support, increases freedom of operation, and speeds up construction progress.
本发明提出的一种超大变断面隧道支护结构不同于以往常规的“锚喷初支+模筑二衬”,该结构体系着重强调拱部安全、墙脚稳定,技术思路新颖,具有原创性,主要体现在:(1)在软弱基底中通过扩大隧道支护墙脚形成靴型大墙脚(Dilated Wall),为上部结构提供稳定基础,同时强化与仰拱的连接;(2)采用双层复合加劲拱部结构(Enhanced Arch),为拆除临时支撑提供条件(满足拱部拆撑后的超大跨无内撑结构受力要求,防止拱部失稳),同时减小拱部拆除临时竖撑带来的受力转化风险;The super large variable section tunnel support structure proposed by the invention is different from the conventional "anchor spray initial support + mold second lining", and the structural system emphasizes the safety of the arch portion, the stability of the wall foot, the novel technical idea and the originality. Mainly reflected in: (1) Forming a shoe-shaped Dilated Wall in the weak base by expanding the foot of the tunnel to provide a stable foundation for the superstructure and strengthening the connection with the inverting arch; (2) using double-layer composite stiffening The Enhanced Arch provides conditions for the removal of the temporary support (to meet the requirements of the oversized non-supporting structure after the arch is dismantled, to prevent the arch from being unstable), and to reduce the temporary vertical support of the arch. Risk of transformation;
按照本发明提出的支护方案,有效保证了工程的安全和结构的可靠性,提出的创新技术措施在工程实践中得到成功检验,工程实践证明本发明提出的支护原理合理有效,体现了本发明的创新性和工程有效性,具有良好的工程实用性。 According to the support scheme proposed by the invention, the safety of the project and the reliability of the structure are effectively ensured, and the proposed innovative technical measures are successfully tested in the engineering practice, and the engineering practice proves that the support principle proposed by the invention is reasonable and effective, and embodies the present invention. The innovation and engineering effectiveness of the invention have good engineering practicability.

Claims (6)

  1. 一种超大变断面隧道支护结构,沿隧道环向包括顶部的拱顶(11)、底部的仰拱(12)、两侧的边墙(13),沿隧道径向包括有内层的二次衬砌(2),其特征在于两侧边墙(13)均设置有导洞,边墙(13)由内而外沿隧道径向依次设置有二次衬砌(2)和导洞初期支护(42),导洞初期支护(42)和二次衬砌(2)之间灌注有靴型大墙脚(41),拱顶(11)和仰拱(12)由内而外沿隧道径向依次设置有二次衬砌(2)和初期支护(31),拱顶(11)的初期支护(31)支承于靴型大墙脚(41)。An oversized variable-section tunnel support structure, including a dome (11) at the top, a bottom arch (12) at the bottom, and a side wall (13) on both sides along the tunnel, including an inner layer along the radial direction of the tunnel Secondary lining (2), characterized in that both side walls (13) are provided with guide holes, and the side walls (13) are provided with secondary lining (2) and initial support of the guide holes in the radial direction from the inside to the outside. (42), between the initial support of the pilot hole (42) and the secondary lining (2), there is a shoe-type large wall foot (41), and the dome (11) and the invert arch (12) are radially from the inside to the outside along the tunnel. A secondary lining (2) and an initial support (31) are provided in this order, and the initial support (31) of the dome (11) is supported by the shoe-shaped wall legs (41).
  2. 根据权利要求1所述的超大变断面隧道支护结构,其特征在于拱顶(11)的二次衬砌(2)和初期支护(31)之间设置有内层初期支护(32),所述内层初期支护(32)支承于靴型大墙脚(41)。The super large variable section tunnel support structure according to claim 1, characterized in that an inner layer initial support (32) is arranged between the secondary lining (2) of the dome (11) and the initial support (31), The inner layer initial support (32) is supported by the shoe-shaped large wall legs (41).
  3. 根据权利要求1所述的超大变断面隧道支护结构,其特征在于二次衬砌(2)包括首尾相连的仰拱二次衬砌(21)和拱墙二次衬砌(22),拱墙二次衬砌的横截面呈倒U形并由一侧边墙(13)的底部经拱顶(11)延伸至另一侧边墙(13)底部,仰拱二次衬砌(21)和拱墙二次衬砌(22)的施工缝位于靴型大墙脚(41)内侧壁的中部。The super large variable section tunnel support structure according to claim 1, characterized in that the secondary lining (2) comprises an inverted arch secondary lining (21) and an arched wall secondary lining (22), and the arch wall is twice. The cross-section of the lining is inverted U-shaped and extends from the bottom of one side wall (13) through the vault (11) to the bottom of the other side wall (13), the secondary arch lining (21) and the arch wall twice. The construction joint of the lining (22) is located in the middle of the inner side wall of the shoe-shaped wall foot (41).
  4. 根据权利要求1所述的超大变断面隧道支护结构,其特征在于初期支护(41)采用含有钢筋网、钢架、喷混凝土的喷锚结构构成,所述锚固结构包括系统锚杆(5)。The super large variable section tunnel support structure according to claim 1, wherein the initial support (41) is formed by a spray anchor structure comprising a steel mesh, a steel frame and a sprayed concrete, the anchor structure comprising a system anchor (5) ).
  5. 根据权利要求1所述的超大变断面隧道支护结构,其特征在于导洞初期支护(42)采用含有钢架、喷混凝土的喷锚结构构成,所述锚固结构包括系统锚杆(5)。The super large variable section tunnel support structure according to claim 1, wherein the initial support (42) of the guide hole is formed by a spray anchor structure comprising a steel frame and a sprayed concrete, the anchor structure comprising a system anchor (5) .
  6. 根据权利要求1所述的超大变断面隧道支护结构,其特征在于内层初期支护(32)由钢架和喷混凝土构成。 The super large variable section tunnel support structure according to claim 1, wherein the inner layer initial support (32) is composed of a steel frame and shotcrete.
PCT/CN2015/094286 2014-12-15 2015-11-11 Support structure for tunnel having ultra-large variable section WO2016095631A1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
SE1750912A SE543306C2 (en) 2014-12-15 2015-11-11 Support structure for tunnel having ultra-large variable section
MYPI2017702979A MY198020A (en) 2014-12-15 2015-11-11 Support structure for tunnel having ultra-large variable section

Applications Claiming Priority (10)

Application Number Priority Date Filing Date Title
CN201420795169.6U CN204436406U (en) 2014-12-15 2014-12-15 Super large Varied section tunnel support structure
CN201410777849.X 2014-12-15
CN201410777881.8A CN104405411B (en) 2014-12-15 2014-12-15 Oversized variable cross section tunnel supporting structure
CN201420795169.6 2014-12-15
CN201420797002.3U CN204327118U (en) 2014-12-15 2014-12-15 Super large Varied section tunnel advanced support structure
CN201410777881.8 2014-12-15
CN201410777849.XA CN104500100A (en) 2014-12-15 2014-12-15 Advanced support structure for oversized variable-section tunnel
CN201410776845.X 2014-12-15
CN201410776845.XA CN104653197B (en) 2014-12-15 2014-12-15 Method for constructing extra-large variable cross section tunnel
CN201420797002.3 2014-12-15

Publications (1)

Publication Number Publication Date
WO2016095631A1 true WO2016095631A1 (en) 2016-06-23

Family

ID=56125861

Family Applications (3)

Application Number Title Priority Date Filing Date
PCT/CN2015/094284 WO2016095629A1 (en) 2014-12-15 2015-11-11 Advanced support structure for oversized variable-cross-section tunnel
PCT/CN2015/094285 WO2016095630A1 (en) 2014-12-15 2015-11-11 Method for constructing extra-large variable cross section tunnel
PCT/CN2015/094286 WO2016095631A1 (en) 2014-12-15 2015-11-11 Support structure for tunnel having ultra-large variable section

Family Applications Before (2)

Application Number Title Priority Date Filing Date
PCT/CN2015/094284 WO2016095629A1 (en) 2014-12-15 2015-11-11 Advanced support structure for oversized variable-cross-section tunnel
PCT/CN2015/094285 WO2016095630A1 (en) 2014-12-15 2015-11-11 Method for constructing extra-large variable cross section tunnel

Country Status (3)

Country Link
MY (2) MY198470A (en)
SE (2) SE543306C2 (en)
WO (3) WO2016095629A1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110410110A (en) * 2019-08-23 2019-11-05 中铁第四勘察设计院集团有限公司 A kind of large cross-section tunnel composite lining and its construction method
CN113153317A (en) * 2021-05-11 2021-07-23 北华航天工业学院 Construction method and grouting device suitable for soft rock large-section tunnel
CN113187514A (en) * 2021-05-25 2021-07-30 中铁九局集团第七工程有限公司 Construction method for city railway mine method tunnel dovetail section
CN113803073A (en) * 2021-09-27 2021-12-17 长江勘测规划设计研究有限责任公司 Construction method of tunnel structure for manually removing obstacles on water-rich sand layer

Families Citing this family (96)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207672602U (en) * 2017-05-11 2018-07-31 吴震 The pull-type vertical retaining wall structure structure of anchor
CN106988750B (en) * 2017-05-26 2023-07-14 中铁四局集团有限公司 Implementation mode of ultra-short-distance underpass of existing station of large-span interval tunnel
CN107130977B (en) * 2017-06-27 2023-10-10 长江勘测规划设计研究有限责任公司 Hollow guide excavation structure and excavation method for ultra-large span dome of underground nuclear reactor cavity
CN107630706B (en) * 2017-10-24 2023-05-26 中交第二航务工程局有限公司 Tunnel bottom structure for eliminating tunnel inverted arch bulge in high-earth-pressure area and construction method
CN107605493A (en) * 2017-10-31 2018-01-19 淮矿西部煤矿投资管理有限公司 A kind of comprehensive pick construction system and method
CN107605509A (en) * 2017-11-08 2018-01-19 中铁十局集团有限公司 Sand-pebble layer small curve radius shallow tunnel subsurface excavation method advanced supporting construction method
CN107916935B (en) * 2017-11-13 2024-01-23 浙江大学城市学院 Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method
CN108005675A (en) * 2017-11-16 2018-05-08 中国电建集团昆明勘测设计研究院有限公司 Dynamic superposition coupling supporting method and supporting structure for fault fracture zone roadway
CN107939419A (en) * 2017-12-20 2018-04-20 贵州大学 A kind of tunnel U-shaped steel covers canopy supporting construction
CN107893669A (en) * 2017-12-20 2018-04-10 贵州大学 A kind of U-shaped steel for roadway support covers booth structure
CN108798720B (en) * 2018-03-30 2023-08-01 中国建筑股份有限公司 Anchor grid integrated arch foot reinforcement system for underground engineering arch cover method and construction method thereof
CN108590704A (en) * 2018-04-27 2018-09-28 中铁十二局集团有限公司 Light section per-fore pouring liquid with small pipe pays maintaining method in advance
CN108643934B (en) * 2018-04-28 2024-04-02 中铁二院重庆勘察设计研究院有限责任公司 Construction method based on combined step inverted arch in upper-layer and lower-layer overlapped tunnel
CN108561156B (en) * 2018-04-30 2024-03-19 安徽省公路桥梁工程有限公司 Separated tunnel arch-changing supporting structure and construction method thereof
CN108843338A (en) * 2018-06-27 2018-11-20 北京市政路桥股份有限公司 A kind of integrated excavation construction method of Construction of Silo channel conversion large cross-section tunnel
CN108979659B (en) * 2018-07-04 2022-02-01 中铁第一勘察设计院集团有限公司 Reinforcing structure and method for underpass structure of soft soil water-rich large-section tunnel group
CN108645298A (en) * 2018-07-20 2018-10-12 中铁十八局集团有限公司 The micro- blasting construction method that shakes of the leading pilot tunnel of existing tunnel is closed at short skylight point interval
CN109026057A (en) * 2018-07-25 2018-12-18 西南交通大学 A kind of tunnel combined support structure suitable for drift-sand stratum
CN109404005B (en) * 2018-11-09 2023-09-15 中铁第一勘察设计院集团有限公司 Pre-reinforcing system for small hole and large hole of underground tunnel and construction method
CN109372521A (en) * 2018-11-22 2019-02-22 中铁十四局集团有限公司 New pipe-roof method construction technology and construction pipe suspension device
CN109538236B (en) * 2018-12-07 2024-04-02 中铁十局集团有限公司 Tunnel entering structure and tunnel entering construction method
CN109538246A (en) * 2018-12-26 2019-03-29 中铁科学研究院有限公司 Ledge method tunneling subway station arch springing ruggedized construction and construction method
CN109667603A (en) * 2018-12-28 2019-04-23 中铁第四勘察设计院集团有限公司 A kind of super shallow-buried tunnel structure and construction method
CN109505630B (en) * 2019-01-14 2023-09-08 中铁一局集团有限公司 Full-hydraulic crawler-type self-propelled trestle and construction method
CN109538250B (en) * 2019-01-28 2023-09-15 中南大学 Device and method for quick construction of tunnel primary support with mould sprayed concrete
CN109578014B (en) * 2019-01-28 2024-02-09 中铁第六勘察设计院集团有限公司 Anti-surging bottom sealing structure and construction method
CN109885329B (en) * 2019-02-28 2023-04-07 新华三信息技术有限公司 Upgrading method and system and electronic equipment
CN109763838B (en) * 2019-03-13 2023-09-15 中铁第一勘察设计院集团有限公司 Assembled inverted arch structure suitable for tunnel by drilling and blasting method and assembling method thereof
CN109869189A (en) * 2019-03-22 2019-06-11 云南建投基础工程有限责任公司 A kind of tunnel pernicious gas and underground moisture are from exhaust system device
CN109973111A (en) * 2019-03-22 2019-07-05 北京城建集团有限责任公司 A kind of pilot tunnel water storage system and its construction method
CN109882206B (en) * 2019-04-09 2020-05-22 湖南科技大学 Multi-support cooperative method for controlling coal mine broken surrounding rock
CN109973100B (en) * 2019-05-21 2024-02-09 中铁第六勘察设计院集团有限公司 Supporting form for realizing small-radius turning of tunnel by mining method and construction method
CN110017149A (en) * 2019-05-21 2019-07-16 成都市建筑设计研究院 A kind of ledge tunneling is suitable to build underground structure and construction method
CN112031831A (en) * 2019-06-03 2020-12-04 甘肃路桥建设集团有限公司 Tunnel steel pipe arch primary support structure and support method thereof
CN110230504B (en) * 2019-06-25 2024-08-06 深圳市综合交通设计研究院有限公司 Waterproof and water pressure resistant composite lining structure with upper soft and lower hard composite stratum and construction method thereof
CN110307003B (en) * 2019-08-12 2024-04-12 中铁二院工程集团有限责任公司 Pressure relief pilot tunnel suitable for preventing tunnel bottom from deforming and construction method thereof
CN110750820B (en) * 2019-09-19 2023-03-28 中国人民解放军军事科学院国防工程研究院工程防护研究所 Underground cave depot excavation support stability judging method based on energy mutation
CN110700852A (en) * 2019-10-14 2020-01-17 中铁第四勘察设计院集团有限公司 Single-hole double-line mine method tunnel section with mid-partition wall designed by urban D-type vehicle clearance
CN110714778B (en) * 2019-10-14 2024-07-09 中铁第四勘察设计院集团有限公司 Mine tunnel section without intermediate wall for city D-type vehicle limit design single-hole double-line
CN110700851B (en) * 2019-10-14 2024-07-09 中铁第四勘察设计院集团有限公司 Single-hole double-line jet fan tunnel section designed based on urban D-type vehicle limit
CN111206943B (en) * 2020-02-21 2024-06-25 上海市城市建设设计研究总院(集团)有限公司 Micro-interference post-compensation underground excavation interface connecting component and construction method thereof
CN111125827A (en) * 2020-02-28 2020-05-08 中国十七冶集团有限公司 Loess tunnel earthwork excavation and supporting method based on BIM technology
CN111456743A (en) * 2020-03-12 2020-07-28 中铁四局集团有限公司 Large-section loess tunnel micro-step excavation method and step structure thereof
CN111188638A (en) * 2020-04-01 2020-05-22 黄河勘测规划设计研究院有限公司 Advanced support pipe shed structure under silty-fine sand geological condition and construction method thereof
CN111305219B (en) * 2020-04-01 2024-08-30 中铁第一勘察设计院集团有限公司 Existing tunnel crossing system based on foundation pit jump digging and arch cover conversion and construction method
CN111472812A (en) * 2020-04-24 2020-07-31 重庆交通建设(集团)有限责任公司 Construction method for filling and pouring concrete into inverted arch of tunnel
CN111691894A (en) * 2020-06-22 2020-09-22 中铁十八局集团有限公司 Construction process of hole pipe shed
CN112065443A (en) * 2020-08-19 2020-12-11 中铁五局集团有限公司 Continuous beam second section construction method based on karst cave underground river environment tunnel construction
CN112031814B (en) * 2020-09-17 2022-07-29 攀钢集团工程技术有限公司 Cave-entering construction method for crossing shallow-layer high-load highway
CN111997646B (en) * 2020-09-27 2024-07-09 中铁第四勘察设计院集团有限公司 Mine tunnel supporting structure for running high-speed rail downwards and construction method thereof
CN112253172B (en) * 2020-10-16 2024-06-28 中铁第四勘察设计院集团有限公司 Tunnel bottom lining structure provided with tie beam and construction method thereof
CN112228117A (en) * 2020-10-28 2021-01-15 中铁十二局集团有限公司 Construction method for large-section primary support large arch springing
CN114439481B (en) * 2020-11-02 2024-06-07 上海宝冶集团有限公司 Variable cross section excavation method for underground excavation tunnel with small cross section and large cross section
CN112627857B (en) * 2020-12-07 2022-11-15 广东华隧建设集团股份有限公司 Construction method of tunnel secondary lining
CN112647985B (en) * 2020-12-28 2022-08-12 中国科学院武汉岩土力学研究所 Combined supporting device of lock pin anchor pipe/anchor rod and steel arch frame and construction method
CN112682062B (en) * 2020-12-31 2023-08-25 中铁大桥局集团第五工程有限公司 Construction method of small-clear-distance stereo cross tunnel
CN112682048B (en) * 2020-12-31 2023-08-29 中铁大桥局集团第五工程有限公司 Replacement reinforcement construction method for small clear distance up-span existing tunnel of newly-built tunnel
CN112832785B (en) * 2021-02-24 2024-05-24 中铁第六勘察设计院集团有限公司 Shield mine combined construction method tunnel submarine docking method and miniature dismounting machine cavity
CN112855225B (en) * 2021-03-01 2024-04-30 中铁上海工程局集团有限公司 Soft rock tunnel supporting construction method with high safety
CN112963177A (en) * 2021-04-19 2021-06-15 山东建筑大学 Supporting method and structure for weak stratum shallow-buried large-section tunnel with hole
CN113309550B (en) * 2021-05-19 2024-02-27 甘肃路桥建设集团有限公司 Modular temporary supporting and assembling structure for ultra-large section loess tunnel
CN115434709B (en) * 2021-06-01 2024-06-07 上海宝冶集团有限公司 Construction method for collapse body of through tunnel bedding section
CN113392449B (en) * 2021-06-01 2022-12-30 中铁二院工程集团有限责任公司 Optimization design method of large-span arch support composite foundation
CN113294175B (en) * 2021-06-03 2023-12-29 中国建筑股份有限公司 Construction method of tunnel secondary lining structure and tunnel secondary lining structure
CN113338951B (en) * 2021-06-30 2023-11-03 中交路桥建设有限公司 Three-step roof-picking construction method for rapid tunnel intersection
CN113565513A (en) * 2021-07-13 2021-10-29 中交路桥华南工程有限公司 Upper and lower step reserved core soil excavation method for tunnel excavation
CN113847050B (en) * 2021-07-16 2023-08-22 中交投资南京有限公司 Construction method of ultra-long highway tunnel in lava mountain area
CN113738399A (en) * 2021-09-01 2021-12-03 上海市政工程设计研究总院(集团)有限公司 Underground excavation tunnel large pipe shed guide wall structure and construction method thereof
CN113756868B (en) * 2021-09-14 2024-06-25 东莞理工学院 Geotechnical engineering underground side wall construction method
CN114060063A (en) * 2021-11-01 2022-02-18 中铁十九局集团第二工程有限公司 Double-layer steel frame concrete-sprayed primary support structure suitable for large deformation of tunnel and support method
CN114046162A (en) * 2021-11-19 2022-02-15 中电建路桥集团有限公司 High ground temperature tunnel bottom plate heat insulation structure
CN114086968B (en) * 2021-11-27 2024-04-09 中铁广州工程局集团有限公司 Construction method for undermining existing building undercut tunnel
CN114109421B (en) * 2021-12-03 2024-01-30 中铁隧道局集团有限公司 Construction method for open TBM through long fault fracture zone
CN114183149A (en) * 2021-12-14 2022-03-15 中铁工程装备集团有限公司 Underground space mechanized construction method based on pilot tunnel expanding excavation
CN114320340B (en) * 2021-12-28 2023-09-12 中铁第六勘察设计院集团有限公司 Large-span non-column underground tunnel structure and method based on advanced pilot tunnel and opposite-pulling anchor cable
CN114233302B (en) * 2021-12-29 2024-03-15 中铁四院集团西南勘察设计有限公司 Arch cover construction method suitable for underground excavation station
CN114320320B (en) * 2021-12-31 2024-07-30 北京住总集团有限责任公司 Supporting structure and method suitable for locally enlarging and excavating underground excavation section
CN114320312B (en) * 2022-01-06 2024-08-16 江西省交通设计研究院有限责任公司 Primary support adherence method tunnel hole entering construction method
CN114320314A (en) * 2022-01-11 2022-04-12 龙元建设集团股份有限公司 Zoning excavation method for small-clear-distance and ultra-large-section highway tunnel
CN114575877A (en) * 2022-03-04 2022-06-03 中铁第一勘察设计院集团有限公司 Construction method of tunnel shock insulation structure
CN114635719B (en) * 2022-03-09 2024-08-02 甘肃路桥建设集团有限公司 Tunnel secondary lining steel bar protection layer thickness five-point circumference control standardized construction method
CN114704297B (en) * 2022-03-30 2024-07-16 中铁二十局集团第五工程有限公司 Integral inverted arch structure of tunnel and construction process thereof
CN114753401B (en) * 2022-04-08 2023-05-26 中铁十九局集团第五工程有限公司 Construction method for tunnel bottom karst cave treatment
CN114856580A (en) * 2022-04-26 2022-08-05 中建八局第三建设有限公司 Safe construction method for ultra-shallow buried excavation large-section tunnel of city core business district
CN115142878B (en) * 2022-07-04 2023-05-16 中铁十二局集团有限公司 CRD method subsection linkage rapid construction method for upper soft and lower hard strata
CN115163125B (en) * 2022-07-29 2024-05-14 中南大学 Differential grading control method and system suitable for asymmetric extrusion soft rock tunnel
CN115288705B (en) * 2022-08-09 2024-08-16 云南建投第四建设有限公司 Construction method of transition part of junction section of bifurcation tunnel and ultra-large span
CN115306442B (en) * 2022-08-22 2024-07-16 中铁第一勘察设计院集团有限公司 Tunnel pre-supporting structure of sandy loess stratum and construction method
CN115452219A (en) * 2022-08-24 2022-12-09 珠海大横琴股份有限公司 Two-lining contact pressure testing device and mounting method thereof
CN115306424B (en) * 2022-08-29 2023-07-21 中国建筑第二工程局有限公司 Large-section transverse channel horsehead door breaking operation platform and construction method
CN115405325A (en) * 2022-08-31 2022-11-29 中铁第一勘察设计院集团有限公司 Design method of tunnel seismic isolation structure
CN115478880B (en) * 2022-10-21 2024-05-31 中铁隧道局集团有限公司 Construction method for reducing rebound rate of sprayed concrete
CN115961513A (en) * 2022-11-22 2023-04-14 中铁二院工程集团有限责任公司 Method for carrying out quadruple interchange fluffing on railway by using tunnel engineering
CN116163761A (en) * 2023-04-06 2023-05-26 中交(广州)建设有限公司 Quick switching structure and quick switching excavation method for tunnel in underground tunnel
CN117107777B (en) * 2023-10-13 2024-04-05 中国铁路设计集团有限公司 Method for constructing underground excavation subway section from open excavation slope foundation pit
CN117248916B (en) * 2023-11-20 2024-07-23 中国铁路设计集团有限公司 Construction method of plane right-angle turning structure of underground excavation exit of subway

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0525993A (en) * 1991-07-19 1993-02-02 Fujita Corp Arch shell constructing method in work preceding tunnelling
CN102226398A (en) * 2011-06-02 2011-10-26 中铁二院工程集团有限责任公司 Soft rock four-line large-span tunnel compound double-side wall bracing cable conversion excavation construction method
JP2012036624A (en) * 2010-08-06 2012-02-23 Taisei Corp Tunnel construction method
CN102797481A (en) * 2012-08-13 2012-11-28 中铁一局集团有限公司 Large-span tunnel arch secondary lining steel bar binding construction method based on skeleton beams
CN103437783A (en) * 2013-08-22 2013-12-11 天津市市政工程设计研究院 Shallow-buried excavation long-span pilot tunnel arch cover combined construction method
CN104405411A (en) * 2014-12-15 2015-03-11 中铁第四勘察设计院集团有限公司 Oversized variable cross section tunnel supporting structure
CN104500100A (en) * 2014-12-15 2015-04-08 中铁第四勘察设计院集团有限公司 Advanced support structure for oversized variable-section tunnel
CN204327118U (en) * 2014-12-15 2015-05-13 中铁第四勘察设计院集团有限公司 Super large Varied section tunnel advanced support structure
CN104653197A (en) * 2014-12-15 2015-05-27 中铁第四勘察设计院集团有限公司 Method for constructing extra-large variable cross section tunnel
CN204436406U (en) * 2014-12-15 2015-07-01 中铁第四勘察设计院集团有限公司 Super large Varied section tunnel support structure

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4445723A (en) * 1982-07-26 1984-05-01 Mcquade Paul D Method of circle mining of ore
JP2004052408A (en) * 2002-07-22 2004-02-19 Maeda Corp Tunnel excavating method
KR20060084203A (en) * 2005-01-19 2006-07-24 주식회사 하이콘엔지니어링 Method for constructing 2-arch tunnel using steel pile support
CN101666232B (en) * 2009-09-27 2012-08-22 中铁四局集团有限公司 Construction method for six-part excavation of super-large section tunnel
CN102182466B (en) * 2011-04-08 2013-05-01 中铁上海设计院集团有限公司 Excavating method for jump-digging of double-side wall guide pit combined arch part of tunnel
CN102345460A (en) * 2011-06-21 2012-02-08 北京交通大学 Settlement control method for shallow large-section loess tunnel
CN103306687B (en) * 2012-10-31 2015-09-16 北京中铁瑞威基础工程有限公司 Soft rock tunnel long cantilever horizontal jet grouting Deformation control construction method
CN103775095B (en) * 2014-02-26 2015-10-28 中铁第一勘察设计院集团有限公司 The advanced two pilot tunnel in Ruan Ji tunnel, the mountain ridge and construction method thereof

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0525993A (en) * 1991-07-19 1993-02-02 Fujita Corp Arch shell constructing method in work preceding tunnelling
JP2012036624A (en) * 2010-08-06 2012-02-23 Taisei Corp Tunnel construction method
CN102226398A (en) * 2011-06-02 2011-10-26 中铁二院工程集团有限责任公司 Soft rock four-line large-span tunnel compound double-side wall bracing cable conversion excavation construction method
CN102797481A (en) * 2012-08-13 2012-11-28 中铁一局集团有限公司 Large-span tunnel arch secondary lining steel bar binding construction method based on skeleton beams
CN103437783A (en) * 2013-08-22 2013-12-11 天津市市政工程设计研究院 Shallow-buried excavation long-span pilot tunnel arch cover combined construction method
CN104405411A (en) * 2014-12-15 2015-03-11 中铁第四勘察设计院集团有限公司 Oversized variable cross section tunnel supporting structure
CN104500100A (en) * 2014-12-15 2015-04-08 中铁第四勘察设计院集团有限公司 Advanced support structure for oversized variable-section tunnel
CN204327118U (en) * 2014-12-15 2015-05-13 中铁第四勘察设计院集团有限公司 Super large Varied section tunnel advanced support structure
CN104653197A (en) * 2014-12-15 2015-05-27 中铁第四勘察设计院集团有限公司 Method for constructing extra-large variable cross section tunnel
CN204436406U (en) * 2014-12-15 2015-07-01 中铁第四勘察设计院集团有限公司 Super large Varied section tunnel support structure

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110410110A (en) * 2019-08-23 2019-11-05 中铁第四勘察设计院集团有限公司 A kind of large cross-section tunnel composite lining and its construction method
CN113153317A (en) * 2021-05-11 2021-07-23 北华航天工业学院 Construction method and grouting device suitable for soft rock large-section tunnel
CN113187514A (en) * 2021-05-25 2021-07-30 中铁九局集团第七工程有限公司 Construction method for city railway mine method tunnel dovetail section
CN113187514B (en) * 2021-05-25 2024-02-23 中铁九局集团第七工程有限公司 Construction method for dovetail section of urban railway mine tunnel
CN113803073A (en) * 2021-09-27 2021-12-17 长江勘测规划设计研究有限责任公司 Construction method of tunnel structure for manually removing obstacles on water-rich sand layer
CN113803073B (en) * 2021-09-27 2024-01-19 长江勘测规划设计研究有限责任公司 Construction method of tunnel structure for manually clearing obstacle in water-rich sand layer

Also Published As

Publication number Publication date
SE1750913A1 (en) 2017-07-12
SE543647C2 (en) 2021-05-18
MY198470A (en) 2023-08-31
WO2016095629A1 (en) 2016-06-23
MY198020A (en) 2023-07-26
SE543306C2 (en) 2020-11-24
WO2016095630A1 (en) 2016-06-23
SE1750912A1 (en) 2017-07-12

Similar Documents

Publication Publication Date Title
WO2016095631A1 (en) Support structure for tunnel having ultra-large variable section
CN108533272B (en) Exit construction method for tunnel with extremely small clear distance
CN104405411B (en) Oversized variable cross section tunnel supporting structure
CN107255035B (en) Extrusion type weak surrounding rock oversized-section tunnel supporting system and construction method thereof
CN103244130B (en) Quick excavation and expanding construction method of herringbone tunnel section
CN104653197A (en) Method for constructing extra-large variable cross section tunnel
CN110735656B (en) Method for reversely building underground excavation station tunnel with ultra-large section in soft rock area based on arch cover method
CN102758642A (en) Long-span tunnel overlapping carrying arch structure for upper-soft and lower-hard stratum and construction method thereof
CN101864963A (en) Large-section loess tunnel construction method
CN104533446A (en) Construction method and structure of two-layer preliminary support for preventing geological disaster of large-section weak surrounding rock tunnel
CN102733827A (en) Tunnel arch exchanging construction method and construction structure in tunnel arch exchanging construction
CN105696602A (en) Composite pile-anchor supporting method and structure for deepening excavation
CN104632227B (en) Subway station excavation technology of single-layer beam arch structure
CN108518230A (en) A kind of highly stress soft rock stress Tunnel Second Lining deformation control method and structure
CN104061000B (en) Touch wall sinking passage formula tunnel partition wall and method of construction thereof
CN103775095A (en) Ridge soft-foundation tunnel advance double guide tunnel and construction method thereof
CN108561156A (en) Separate tunnel changes arch supporting construction and its construction method
CN107120119A (en) The construction method of Underground Subway Station
CN104295112A (en) Reinforced concrete column upper-connected concrete filled steel tube column connecting structure and construction method thereof
CN207609428U (en) The ground handling well Shed-pipe Advanced Support pre-add solid system of existing object is worn under shield section
CN214245749U (en) Support replacing structure for deep and shallow foundation pit construction
CN204436407U (en) The structure that the pre-Geological disaster prevention of the double-deck preliminary bracing of a kind of big cross section Support System in Soft Rock Tunnels occurs
CN204327112U (en) Tunnel hole-exiting advance support system
CN109594995B (en) Weak surrounding rock tunnel perturbation motive machinery subsection tunneling construction method
CN205117354U (en) Reinforcing bar grid crowd with encircle foot strengthens device temporarily

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 15869140

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

WWE Wipo information: entry into national phase

Ref document number: 1750912-6

Country of ref document: SE

WWE Wipo information: entry into national phase

Ref document number: 2017/0595.1

Country of ref document: KZ

122 Ep: pct application non-entry in european phase

Ref document number: 15869140

Country of ref document: EP

Kind code of ref document: A1