CN116163761A - Quick switching structure and quick switching excavation method for tunnel in underground tunnel - Google Patents

Quick switching structure and quick switching excavation method for tunnel in underground tunnel Download PDF

Info

Publication number
CN116163761A
CN116163761A CN202310356777.0A CN202310356777A CN116163761A CN 116163761 A CN116163761 A CN 116163761A CN 202310356777 A CN202310356777 A CN 202310356777A CN 116163761 A CN116163761 A CN 116163761A
Authority
CN
China
Prior art keywords
tunnel
pilot
hole
channel
double
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202310356777.0A
Other languages
Chinese (zh)
Inventor
闫鑫雨
谭竹青
谭啸峰
刘毅
崔孟雷
芦佳帅
康安帅
张岩
磨卫俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Communications Guangzhou Construction Co ltd
Original Assignee
China Communications Guangzhou Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Communications Guangzhou Construction Co ltd filed Critical China Communications Guangzhou Construction Co ltd
Priority to CN202310356777.0A priority Critical patent/CN116163761A/en
Publication of CN116163761A publication Critical patent/CN116163761A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Abstract

The invention discloses a rapid conversion structure of a middle tunnel method of a subsurface tunnel, which comprises a double-side-wall pilot tunnel method tunnel, a middle tunnel method tunnel and a temporary transverse channel, wherein the double-side-wall pilot tunnel method tunnel is communicated with the middle tunnel method tunnel through the temporary transverse channel, when the subsurface tunnel is formed, the double-side-wall pilot tunnel method and the middle tunnel method are converted through the temporary transverse channel, and the temporary transverse channel is arranged between a guide hole (1) of the double-side-wall pilot tunnel method tunnel, a guide hole (2) of the double-side-wall pilot tunnel and the middle pilot tunnel of the middle tunnel method tunnel. According to the method, the temporary construction channel is additionally arranged, the middle-hole method section tunnel is excavated in advance before the construction of the double-side-wall pilot pit method section tunnel is finished, the influence of procedure conversion on the construction period is reduced, the construction period is saved, and the purpose of safe and orderly construction of the tunnel is ensured. The invention also discloses a method for quickly switching the excavation of the tunnel in the underground excavation tunnel.

Description

Quick switching structure and quick switching excavation method for tunnel in underground tunnel
Technical Field
The invention belongs to the technical field of tunnel construction, and particularly relates to a rapid switching structure and a rapid switching excavation method for a tunnel in a subsurface tunnel.
Background
When the subway large-section tunnel adopts a double-side-wall pilot tunnel normal middle-hole method to convert the construction process, the support structure of the variable section is complex in stress, more construction procedures are crossed, the construction progress is slow, the construction efficiency is limited, the tunnel excavation construction efficiency cannot be improved, and the purpose of safe and rapid construction is achieved.
2011-08-17 with the patent number of CN201110100807 discloses a subway tunnel excavation construction method, wherein a tunnel to be excavated comprises a first normal tunnel conventional section, a first normal tunnel expansion section, a second normal tunnel conventional section, a second normal tunnel expansion section and a crossover tunnel section, wherein the first normal tunnel conventional section or the second normal tunnel conventional section only accommodates a first normal line or a second normal line of a single line and is a single-hole single-line tunnel; the first positive line tunnel expansion section is required to accommodate a first positive line, a parking line, a crossover line connecting the first positive line and the parking line and a crossover line connecting the second positive line and the parking line, and the tunnel section is gradually expanded from a minimum section to a maximum section tunnel section; the second positive line tunnel expansion section is required to accommodate a second positive line and a crossover line connecting the second positive line and a stop line, and gradually expands from a minimum section to a maximum section tunnel section; the crossover tunnel section needs to accommodate a crossover connecting the second positive line and the park line. The method comprises the steps of firstly excavating a tunnel section with the largest section, and then transiting from the large section to the smaller section from the tunnel section with the largest section, so that the underground section tunnel with the transition line and the stop line is excavated in a large-small-shrinkage section mode. The above technical problems still cannot be solved.
Disclosure of Invention
Aiming at the defects existing in the prior art, the invention aims to provide a quick conversion structure and a quick conversion excavation method for a middle hole method of a hidden tunnel, which are simple in structure and convenient to operate.
In order to achieve the above purpose, the technical scheme of the invention is as follows: the utility model provides a quick conversion structure of hole method in undercut tunnel, includes double side wall pilot tunnel method tunnel, well hole method tunnel and interim transverse channel, communicates through interim transverse channel between double side wall pilot tunnel method tunnel and the well hole method tunnel, and when undercut tunnel, double side wall pilot tunnel method and well hole method change through interim transverse channel, and interim transverse channel sets up between the pilot tunnel of (1) of double side wall pilot tunnel method tunnel, (2) pilot tunnel and well pilot tunnel of well hole method tunnel.
Further, the temporary transverse channel comprises an upper channel and a lower channel, wherein the upper channel is positioned above the lower channel, and the upper channel is constructed first and then the lower channel is constructed.
Further, the temporary transverse channel further comprises a middle support, and one end of the middle support is placed on the transverse support between the guide hole (1) and the guide hole (2) in the double-side-wall guide pit method tunnel.
Further, the tunnel with the double-side-wall pilot tunnel method comprises a pilot hole (1), a pilot hole (2), a pilot hole (3), a pilot hole (4), a pilot hole (5), a pilot hole (6), a pilot hole (1), a pilot hole (3), a pilot hole (5) which are respectively positioned above the pilot hole (2), the pilot hole (4) and the pilot hole (6), a transverse support is arranged between the upper pilot hole and the lower pilot hole, and a vertical support is arranged between the left pilot hole and the right pilot hole.
Further, at the interface of the double-side-wall pilot tunnel method tunnel and the middle-hole method tunnel, the vertical support of the pilot tunnel number (1) of the double-side-wall pilot tunnel method tunnel is broken, the upper-layer channel of the temporary transverse channel is constructed, the vertical support of the pilot tunnel number (2) is broken, and the lower-layer channel of the temporary transverse channel is constructed.
Further, the middle tunnel method tunnel comprises a middle pilot tunnel, a left pilot tunnel and a right pilot tunnel, wherein the middle pilot tunnel is positioned between the left pilot tunnel and the right pilot tunnel, enters the middle pilot tunnel of the middle tunnel method tunnel from the temporary transverse channel, and then enters the left pilot tunnel and the right pilot tunnel from the middle pilot tunnel.
Further, a first steel frame, a second steel frame and a third steel frame are arranged in the middle pilot tunnel of the middle tunnel method tunnel, the third steel frames are sequentially arranged and gradually lifted to be in a vault from the first steel frames, and the third steel frames are in contact with the vault of the middle pilot tunnel.
Based on the rapid conversion structure of the hole-in-underground tunnel method, the invention also provides a rapid conversion excavation method of the hole-in-underground tunnel method, which comprises the following steps:
step 1, constructing the double side wall pilot tunnel by adopting (1) to (6) pilot tunnels, excavating the pilot tunnels on the left side (1) and the upper and lower pilot tunnels of the pilot tunnel (2) to a designed mileage, and sealing the end of the face of the pilot tunnel (1) and the face of the pilot tunnel (2) by adopting an I-shaped steel frame and shotcrete;
step 2, after the pilot tunnel (1) and the pilot tunnel (2) of the double-side-wall pilot tunnel method tunnel are excavated to a designed mileage, breaking the vertical supports of the pilot tunnel (1) and the pilot tunnel (2) of the double-side-wall pilot tunnel method tunnel at the interface of the pilot tunnel method tunnel and the pilot tunnel, and constructing a temporary transverse channel;
step 3, after the construction of the temporary transverse channel is finished, constructing an advanced guide pipe along the vault outline of the tunnel by a middle-hole method, grouting and reinforcing to break the temporary transverse channel, and performing later construction according to the construction method by the middle-hole method after the temporary transverse channel is completely broken;
step 4, when the guide hole is moved into the middle hole method from the temporary transverse channel, gradually lifting the guide hole from the first steel frame to the designed vault elevation in a manner of closely arranging 3 steel frames during construction, wherein the third steel frame is the first steel frame of the guide hole design grid in the middle hole method, and thus the quick conversion construction of the middle hole method is completed;
and 5, excavating other residual pilot tunnels of the double-side-wall pilot tunnel method to the temporary passage to perform temporary passage partition wall rupture and end plugging construction.
Further, the process of constructing the temporary transverse channel in the step 2 is as follows: when the tunnel is excavated, firstly constructing an upper layer passage of the temporary transverse passage, densely arranging double annular steel frames at two sides of the passage, and plugging a tunnel face by adopting I-steel after the upper layer passage is excavated to a designed length; after the upper layer channel is completely constructed, breaking the vertical support of the guide hole (2), constructing the lower layer channel, digging the lower layer channel to a designed mileage, and sealing the end of the tunnel face by adopting an I-shaped steel frame and shotcrete; when the height of the temporary transverse channel is higher, a middle support needs to be arranged, and the temporary transverse channel middle support is arranged on the transverse support between the pilot tunnel (1) and the pilot tunnel (2) of the double-side-wall pilot tunnel method tunnel.
Further, the process of breaking the temporary transverse channel in the step 3 is as follows: firstly, breaking an upper layer channel of the temporary transverse channel to a reserved core soil position; and (3) temporarily closing the face by a guide hole feeding ruler 3-5 m in the middle of the middle guide hole method, then performing the breaking work of the lower layer channel of the temporary transverse channel, and performing the excavation work of the lower half section of the guide hole in the middle hole method after the breaking work, wherein the primary support grid is timely closed into a ring.
The technical scheme of the invention has the advantages that:
1. according to the method, the temporary construction channel is additionally arranged by adjusting the guide hole excavation footage distance, the middle-hole method section tunnel is excavated in advance before the construction of the double-side-wall guide pit method section tunnel is finished, the influence of procedure conversion on the construction period is reduced, the construction period is saved, and the purpose of safe and orderly construction of the tunnel is ensured. .
2. The pilot tunnel primary support and the double-side wall pilot pit method can simultaneously and alternately operate, the working procedure conversion is less, the construction is safe and reliable, the excavation working face is increased, the total construction period is saved, and the quick conversion excavation method of the pilot tunnel method is also applicable to large-section mine tunnel engineering like roads, railways and the like.
Drawings
The invention is described in further detail below with reference to the attached drawings and detailed description:
FIG. 1 is a schematic illustration of a double sidewall pilot pit method construction;
FIG. 2 is a schematic elevational view of a temporary transverse channel according to the present invention;
FIG. 3 is a schematic three-dimensional view of a temporary transverse channel according to the present invention;
FIG. 4 is a schematic illustration of a temporary lateral approach hole-entering construction of the present invention;
FIG. 5 is a three-dimensional schematic diagram of a temporary lateral approach hole-entering construction of the present invention;
FIG. 6 is a schematic diagram of a tunnel construction according to the present invention.
The labels in the above figures are respectively: 1. the vertical support of the guide hole (1); 2. a transverse support; 3. (2) vertical support of the guide hole number; 4. an upper layer channel; 5. a lower layer channel; 6. a double-side-wall pilot tunnel bottom plate; 7. double side wall pilot tunnel dome; 8. temporary lateral passage; 9. double-side-wall pilot tunnel method tunnel; 10. a middle hole tunnel; 11. reserving core soil; 12. a lower half section of the pilot tunnel in the middle-hole method; 13. the first truss steel frame; 14. the third steel frame; 15. a middle pilot tunnel; 16. a left pilot hole; 17. a right pilot hole; 18. and the second steel frame.
Detailed Description
In the present invention, it is to be understood that the term "length"; "width"; "go up"; "Down"; "front"; "rear"; "left"; "right"; "vertical"; "horizontal"; "roof"; "bottom", "inner"; "outside"; "clockwise"; "counterclockwise"; "axial"; "planar orientation"; the orientation or positional relationship indicated by "circumferential" or the like is based on the orientation or positional relationship shown in the drawings, and is merely for convenience of description and simplification of description, and is not indicative or implying that the apparatus or element to be referred to must have a specific orientation; constructed and operated in a particular orientation and therefore should not be construed as limiting the invention.
As shown in fig. 1 to 6, a fast switching structure of a tunnel method in a subsurface tunnel comprises a double-side-wall pilot tunnel method tunnel 9, a tunnel method tunnel 10 and a temporary transverse channel 8, wherein the double-side-wall pilot tunnel method tunnel 9 and the tunnel method tunnel 10 are communicated through the temporary transverse channel 8, and when the tunnel is in subsurface, the double-side-wall pilot tunnel method and the tunnel method are switched through the temporary transverse channel 8, and the temporary transverse channel 8 is arranged between a pilot tunnel (1) of the double-side-wall pilot tunnel method tunnel 9, a pilot tunnel (2) of the double-side-wall pilot tunnel method tunnel 10 and the middle pilot tunnel of the tunnel method tunnel 10. One side of the temporary transverse channel 8 is communicated with a pilot tunnel (1) and a pilot tunnel (2) of the double-side-wall pilot tunnel method tunnel 9, and the other side of the temporary transverse channel 8 is communicated with a middle pilot tunnel of the middle-hole method tunnel 10. According to the method, the temporary construction channel is additionally arranged, the middle-hole method section tunnel is excavated in advance before the construction of the double-side-wall pilot pit method section tunnel is finished, the influence of procedure conversion on the construction period is reduced, the construction period is saved, and the purpose of safe and orderly construction of the tunnel is ensured.
The temporary transverse channel 8 comprises an upper channel 4 and a lower channel 5, wherein the upper channel 4 is positioned above the lower channel 5, and the upper channel 4 is constructed first and then the lower channel 5 is constructed. When the height of the temporary transverse channel 8 is higher, a middle support is required to be arranged for increasing the structural strength, the temporary transverse channel 8 further comprises the middle support, and one end of the middle support is placed on the transverse support 2 between the guide holes (1) and (2) in the double-side-wall guide pit method tunnel 9.
The double-side-wall pilot tunnel method tunnel 9 comprises a pilot hole (1), a pilot hole (2), a pilot hole (3), a pilot hole (4), a pilot hole (5), a pilot hole (6), a pilot hole (1), a pilot hole (3), a pilot hole (5) which are respectively positioned above the pilot hole (2), the pilot hole (4) and the pilot hole (6), a transverse support (2) is arranged between the upper pilot hole and the lower pilot hole, and a vertical support is arranged between the left pilot hole and the right pilot hole. And (3) breaking the vertical support 1 of the pilot tunnel of the double-side-wall pilot tunnel method tunnel (1), constructing the upper layer channel 4 of the temporary transverse channel 8, breaking the vertical support 3 of the pilot tunnel of the (2), and constructing the lower layer channel 5 of the temporary transverse channel 8 at the interface of the double-side-wall pilot tunnel method tunnel 9 and the middle-hole tunnel 10.
The middle tunnel method tunnel 10 comprises a middle pilot tunnel 15, a left pilot tunnel 16 and a right pilot tunnel 17, wherein the middle pilot tunnel 15 is positioned between the left pilot tunnel 16 and the right pilot tunnel 17, enters the middle pilot tunnel 15 of the middle tunnel method tunnel 10 from the temporary transverse channel 8, and then enters the left pilot tunnel 16 and the right pilot tunnel 17 of the middle pilot tunnel 15. The middle pilot tunnel 15 of the middle tunnel method tunnel 10 is provided with a first steel frame 13, a second steel frame 18 and a third steel frame 14, the three steel frames are sequentially arranged and gradually lifted from the first steel frame 13 to a designed vault, and the third steel frame 14 is in contact with the vault of the middle pilot tunnel 15. The third steel frame 14 has the same height as the designed vault, and the third steel frame 14 is the first steel frame of the guide hole design grid in the middle hole method.
The bottom plate of the pilot tunnel with the double-side wall pilot tunnel method is lower than the bottom plate of the pilot tunnel with the middle tunnel method, and the arch top of the pilot tunnel with the double-side wall pilot tunnel method is higher than the arch top of the pilot tunnel with the middle tunnel method.
Based on the rapid conversion structure of the hole-in-underground tunnel method, the invention also provides a rapid conversion excavation method of the hole-in-underground tunnel method, which comprises the following steps:
step 1, constructing the double side wall pilot tunnel by adopting (1) to (6) pilot tunnels, excavating the pilot tunnels on the left side (1) and the upper and lower pilot tunnels of the pilot tunnel (2) to a designed mileage, and sealing the end of the face of the pilot tunnel (1) and the face of the pilot tunnel (2) by adopting an I-shaped steel frame and shotcrete; the spacing between the end closed steel frames meets the design requirement;
step 2, after the pilot tunnel (1) and the pilot tunnel (2) of the double-side-wall pilot tunnel method tunnel are excavated to a designed mileage, breaking the vertical supports of the pilot tunnel (1) and the pilot tunnel (2) of the double-side-wall pilot tunnel method tunnel at the interface of the pilot tunnel method tunnel and constructing a temporary transverse channel 8; when the temporary transverse channel 8 is excavated, firstly constructing an upper channel 4 of the temporary transverse channel, densely arranging two annular steel frames on two sides of the channel, and plugging a tunnel face by adopting I-steel after the upper channel 4 is excavated to a designed length; after the upper layer channel 4 is completely constructed, breaking the vertical support 3 of the guide hole (2), constructing the lower layer channel 5, digging the lower layer channel 5 to a designed mileage, and sealing the end of the tunnel face by adopting an I-shaped steel frame and shotcrete; when the temporary transverse channel 8 is higher in height, a middle support is required to be arranged, and the middle support of the temporary transverse channel is placed on the transverse support 2 between the pilot tunnel (1) and the pilot tunnel (2) of the double-side-wall pilot tunnel method tunnel.
Step 3, after the construction of the temporary transverse channel 8 is finished, constructing an advance guide pipe along the vault outline of the tunnel by a middle hole method, grouting and reinforcing to break the temporary transverse channel 8, and firstly breaking the upper layer channel 4 of the temporary transverse channel 8 to the position of reserved core soil 11; and (3) temporarily sealing the face by a guide hole feeding ruler 3-5 m in the middle of the middle guide hole method, then performing the breaking work of the lower layer channel 5 of the temporary transverse channel 8, performing the excavation work of the lower half section 12 after the breaking work, timely sealing the primary support grid into a ring, and performing later-stage construction according to the middle hole method construction method after all the temporary transverse channels are broken.
Step 4, when the guide hole is moved into the middle hole method from the temporary transverse channel, gradually lifting the guide hole from the first steel frame 13 to the designed vault elevation by adopting a close-packed 3 steel frame gradually in construction, enabling the third steel frame 14 to be in contact with the vault, enabling the height of the third steel frame 14 to be consistent with the height of the designed vault, and enabling the third steel frame 14 to be the first steel frame of the guide hole design grid in the middle hole method, so as to finish the quick conversion construction of the middle hole method;
and 5, excavating other residual pilot tunnels of the double-side-wall pilot tunnel method to the temporary passage to perform temporary passage partition wall rupture and end plugging construction.
And (3) at the excavation section of the tunnel double-side-wall pilot tunnel method, firstly, the upper and lower pilot tunnels on the left side are communicated, then, the double-side-wall pilot tunnel method is broken out at the interface with the middle hole method to temporarily support, a temporary transverse channel is constructed and used as a working surface for excavating the middle pilot tunnel of the middle hole method, and the double-side-wall pilot tunnel method is communicated with the pilot tunnel and can be used as a slag discharging channel of the middle hole method.
The invention discloses a method for quickly switching excavation of a tunnel in an underground excavation tunnel, and particularly relates to a method for switching construction of the tunnel in the underground excavation tunnel in a large-section mining process of a subway, wherein temporary construction channels are additionally arranged by adjusting the excavation footage step distance of a pilot tunnel in the process of switching construction of the tunnel in the normal direction of the pilot tunnel in double-side-wall pilot tunnel, the tunnel in the middle-tunnel process is excavated in advance before the construction of the tunnel in the double-side-wall pilot tunnel process is finished, the influence of process switching on the construction period is reduced, and therefore the construction period is saved, and the purpose of safe and orderly construction of the tunnel is ensured.
The key point of the invention is that the end plugs at the temporary transverse channel and the variable section are suitable for large-section tunnel engineering similar to urban rail transit.
The method is based on adjusting the step pitch of the excavation of the double-side-wall pilot tunnel method, penetrating through two adjacent pilot tunnels in advance, and then adding the transverse construction channel to provide a working face for the excavation of the middle tunnel method in advance, so that the overall excavation construction efficiency of the tunnel is greatly improved on the premise of ensuring the safety and stability of the tunnel, and the method has practical significance in the rapid conversion construction of the middle tunnel method in the large-section mine tunnel of the subway.
The invention has great practicability and economy. By taking the construction of a large-section tunnel of a subway in a certain city as an example, the construction of the tunnel is quickly switched by adopting a method for quickly switching the tunnel in the underground excavation tunnel, the overall construction efficiency of the tunnel can be greatly improved, the investment of lower cost is reduced, the construction of urban rail transit engineering is excellently completed, and good economic benefit is obtained.
While the invention has been described above with reference to the accompanying drawings, it will be apparent that the invention is not limited to the above embodiments, but is capable of being modified in various ways, or of being applied to other applications without modification, without departing from the scope of the invention.

Claims (10)

1. A quick conversion structure of hole method in undercut tunnel, its characterized in that: the tunnel boring device comprises a double-side-wall pilot tunnel method tunnel (9), a middle-hole method tunnel (10) and a temporary transverse channel (8), wherein the double-side-wall pilot tunnel method tunnel (9) is communicated with the middle-hole method tunnel (10) through the temporary transverse channel (8), when a tunnel is dug, the double-side-wall pilot tunnel method and the middle-hole method are converted through the temporary transverse channel (8), and the temporary transverse channel (8) is arranged between a pilot tunnel (1) of the double-side-wall pilot tunnel method tunnel (9), a pilot tunnel (2) of the double-side-wall pilot tunnel method tunnel (9) and a middle pilot tunnel of the middle-hole method tunnel (10).
2. The rapid switching structure of the hole-in-tunnel method in a subsurface tunnel according to claim 1, wherein: the temporary transverse channel (8) comprises an upper channel (4) and a lower channel (5), wherein the upper channel (4) is positioned above the lower channel (5), and the upper channel (4) is constructed first and then the lower channel (5) is constructed.
3. The rapid switching structure of the hole-in-tunnel method in a subsurface tunnel according to claim 2, wherein: the temporary transverse channel (8) further comprises a middle support, and one end of the middle support is placed on the transverse support (2) between the guide holes (1) and (2) in the double-side-wall guide pit method tunnel (9).
4. A rapid switching structure for a hole in a undercut tunnel according to claim 2 or 3, wherein: the double-side-wall pilot tunnel method tunnel (9) comprises a pilot hole (1), a pilot hole (2), a pilot hole (3), a pilot hole (4), a pilot hole (5), a pilot hole (6), a pilot hole (1), a pilot hole (3) and a pilot hole (5) which are respectively positioned in the pilot hole (2),
(4) The upper part of the guide hole (6) is provided with a transverse support (2) between the upper guide hole and the lower guide hole, and a vertical support is arranged between the left guide hole and the right guide hole.
5. The rapid switching structure of the hole-in-tunnel method in a subsurface tunnel according to claim 4, wherein: the method is characterized in that the interface between the double-side-wall pilot tunnel method tunnel (9) and the middle-hole method tunnel (10) is used for breaking the pilot tunnel vertical support (1) of the double-side-wall pilot tunnel method tunnel (1), constructing the upper layer channel (4) of the temporary transverse channel (8), breaking the pilot tunnel vertical support (3) of the temporary transverse channel (2) and constructing the lower layer channel (5) of the temporary transverse channel (8).
6. The rapid switching structure of the hole-in-tunnel method in a subsurface tunnel according to claim 5, wherein: the middle tunnel method tunnel (10) comprises a middle pilot tunnel (15), a left pilot tunnel (16) and a right pilot tunnel (17), wherein the middle pilot tunnel (15) is positioned between the left pilot tunnel (16) and the right pilot tunnel (17), enters the middle pilot tunnel (15) of the middle tunnel method tunnel (10) from the temporary transverse channel (8), and then enters the left pilot tunnel (16) and the right pilot tunnel (17) of the middle pilot tunnel (15).
7. The rapid switching structure of the hole-in-tunnel method in a subsurface tunnel according to claim 6, wherein: the middle pilot tunnel (15) of the middle tunnel method tunnel (10) is provided with a first steel frame (13), a second steel frame (18) and a third steel frame (14), the three steel frames are sequentially arranged and gradually lifted to be in a vault from the first steel frame (13), and the third steel frame (14) is in contact with the vault of the middle pilot tunnel (15).
8. A method for quickly switching excavation by a hole in a subsurface tunnel is characterized in that: a rapid switching structure based on a hole-in-undercut tunnel method as claimed in any one of claims 1 to 7, said rapid switching excavation method comprising:
step 1, constructing the double side wall pilot tunnel by adopting (1) to (6) pilot tunnels, excavating the pilot tunnels on the left side (1) and the upper and lower pilot tunnels of the pilot tunnel (2) to a designed mileage, and sealing the end of the face of the pilot tunnel (1) and the face of the pilot tunnel (2) by adopting an I-shaped steel frame and shotcrete;
step 2, after the pilot tunnel (1) and the pilot tunnel (2) of the double-side-wall pilot tunnel method tunnel are excavated to a designed mileage, breaking the vertical supports of the pilot tunnel (1) and the pilot tunnel (2) of the double-side-wall pilot tunnel method tunnel at the interface of the pilot tunnel method tunnel and the pilot tunnel, and constructing a temporary transverse channel (8);
step 3, after the construction of the temporary transverse channel (8) is finished, constructing an advance guide pipe along the vault outline of the tunnel by a middle-hole method, grouting and reinforcing to break the temporary transverse channel (8), and performing later construction according to the construction method by the middle-hole method after the temporary transverse channel is completely broken;
step 4, when the guide hole is moved into the middle hole method from the temporary transverse channel, gradually lifting the guide hole from the first steel frame (13) to the designed vault elevation by adopting a close-packed 3 steel frame gradually-lifting mode during construction, wherein the third steel frame (14) is the first steel frame of the guide hole design grid in the middle hole method, so that the quick conversion construction of the middle hole method is completed;
and 5, excavating other residual pilot tunnels of the double-side-wall pilot tunnel method to the temporary passage to perform temporary passage partition wall rupture and end plugging construction.
9. The method for quickly switching the excavation of the tunnel in the underground tunnel according to claim 8, wherein the method comprises the following steps: the process of constructing the temporary transverse channel (8) in the step 2 is as follows: when the tunnel is excavated, firstly constructing an upper layer tunnel (4) of the temporary transverse tunnel, densely arranging two annular steel frames at two sides of the tunnel, and plugging a tunnel face by adopting I-steel after the upper layer tunnel (4) is excavated to a designed length; after the upper layer channel (4) is completely constructed, breaking the vertical support (3) of the guide hole (2), constructing the lower layer channel (5), and after the lower layer channel (5) is dug to a designed mileage, adopting an I-shaped steel frame and shotcrete for end sealing on the tunnel face; when the height of the temporary transverse channel (8) is higher, a middle support is required to be arranged, and the middle support of the temporary transverse channel is arranged on the transverse support (2) between the pilot tunnel of the double-side-wall pilot tunnel method tunnel (1) and the pilot tunnel of the number (2).
10. The method for quickly switching the excavation of the tunnel in the underground tunnel according to claim 8, wherein the method comprises the following steps: the process of breaking the temporary transverse channel (8) in the step 3 is as follows: firstly, breaking an upper layer channel (4) of a temporary transverse channel (8) to a position where core soil (11) is reserved; and (3) temporarily closing the face by a guide hole feeding ruler 3-5 m in the middle of the middle guide hole method, then breaking the lower layer channel (5) of the temporary transverse channel (8), and excavating the lower half section (12) of the guide hole in the middle guide hole method after breaking, wherein the primary support grid is timely closed into a ring.
CN202310356777.0A 2023-04-06 2023-04-06 Quick switching structure and quick switching excavation method for tunnel in underground tunnel Withdrawn CN116163761A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310356777.0A CN116163761A (en) 2023-04-06 2023-04-06 Quick switching structure and quick switching excavation method for tunnel in underground tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310356777.0A CN116163761A (en) 2023-04-06 2023-04-06 Quick switching structure and quick switching excavation method for tunnel in underground tunnel

Publications (1)

Publication Number Publication Date
CN116163761A true CN116163761A (en) 2023-05-26

Family

ID=86411673

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310356777.0A Withdrawn CN116163761A (en) 2023-04-06 2023-04-06 Quick switching structure and quick switching excavation method for tunnel in underground tunnel

Country Status (1)

Country Link
CN (1) CN116163761A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004211361A (en) * 2002-12-27 2004-07-29 Shimizu Corp Branch junction construction method for shield tunnel
CN103758530A (en) * 2014-01-22 2014-04-30 北京市市政工程设计研究总院有限公司 Primary support multiple-arch dual-liner independent underground excavation subway interval structure and construction method
WO2016095630A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Method for constructing extra-large variable cross section tunnel
JP2018138738A (en) * 2017-02-24 2018-09-06 大成建設株式会社 Invert construction method
CN111810187A (en) * 2020-07-20 2020-10-23 中国路桥工程有限责任公司 Urban non-center pilot tunnel bifurcation tunnel turning construction method
CN113389566A (en) * 2021-07-30 2021-09-14 中铁十二局集团有限公司 Construction method for rapid expanding excavation and conversion by CRD (China railway track) normal double-side-wall pit guiding method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004211361A (en) * 2002-12-27 2004-07-29 Shimizu Corp Branch junction construction method for shield tunnel
CN103758530A (en) * 2014-01-22 2014-04-30 北京市市政工程设计研究总院有限公司 Primary support multiple-arch dual-liner independent underground excavation subway interval structure and construction method
WO2016095630A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Method for constructing extra-large variable cross section tunnel
JP2018138738A (en) * 2017-02-24 2018-09-06 大成建設株式会社 Invert construction method
CN111810187A (en) * 2020-07-20 2020-10-23 中国路桥工程有限责任公司 Urban non-center pilot tunnel bifurcation tunnel turning construction method
CN113389566A (en) * 2021-07-30 2021-09-14 中铁十二局集团有限公司 Construction method for rapid expanding excavation and conversion by CRD (China railway track) normal double-side-wall pit guiding method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨浩等: "浅埋暗挖法隧道双侧壁导坑法转中洞法施工技术", 中国水运, pages 303 - 305 *

Similar Documents

Publication Publication Date Title
CN106640121B (en) Supporting structure for six-pilot tunnel large-section subway station to pass through existing line
CN100487224C (en) Rapid-construction method for rapid change of small-section into large-section tunnel
CN106988750B (en) Implementation mode of ultra-short-distance underpass of existing station of large-span interval tunnel
CN112253133B (en) Safe and efficient construction method for large-section underground excavation tunnel with upper soft and lower hard rock mass
CN109854253B (en) Extension method for existing underground excavation and island-stacking transfer station of subway
CN204457792U (en) A kind ofly dig large diameter shield tunnel with many pilot tunnel methods and the subway station of building
CN110486036B (en) Construction method for expanding arch foot primary support arch cover method
CN102817621B (en) Comprehensive construction method applicable to controlling arch basement sedimentation for tunnel in unfavorable geological conditions
CN113062354A (en) Assembly method for prefabricated subway station of open-cut pile support system
CN105240024A (en) Parallel shield tunneling method for extended construction of subway station
CN104632245A (en) Method using multi-pilot-tunnel expanding excavation large-diameter shield tunnel for building subway station
CN110439574A (en) It is originated for shield lateral translation and the tunnel structure and construction method of haul of slagging tap
CN111810163A (en) Nine-lane double-arch construction method for underground excavation through underground longitudinal and transverse channels
CN107083959A (en) A kind of gob-side entry retaining method
CN112922646B (en) Building method of underground excavation station excavated by large-section single-span support through superposed arch-wall integrated type
CN108979663B (en) Subway station main body structure construction method adopting temporary middle column support
CN204457789U (en) A kind of stake arch wall supports the subway station digging large diameter shield tunnel and build
CN206581945U (en) Both wired supporting construction is worn under a kind of six pilot tunnels big cross section subway station
CN112727484A (en) Shield-pipe-jacking up-down parallel overlapping tunnel structure and construction method thereof
CN111810200A (en) Shield tunnel expanding and excavating system and method based on middle upright posts and inverted arches
CN116163761A (en) Quick switching structure and quick switching excavation method for tunnel in underground tunnel
CN111577292B (en) Double-branch road construction method for underground excavation station of local water-rich sand layer
CN212508352U (en) Shield tunnel expands system of digging based on center pillar and inverted arch
CN106337373B (en) Construction method for obliquely penetrating existing line overhead jacking box culvert
CN212271003U (en) Porous rectangular jacking pipe and light and shade digging connection pipe gallery joint

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20230526