CN112031814B - Cave-entering construction method for crossing shallow-layer high-load highway - Google Patents

Cave-entering construction method for crossing shallow-layer high-load highway Download PDF

Info

Publication number
CN112031814B
CN112031814B CN202010980347.2A CN202010980347A CN112031814B CN 112031814 B CN112031814 B CN 112031814B CN 202010980347 A CN202010980347 A CN 202010980347A CN 112031814 B CN112031814 B CN 112031814B
Authority
CN
China
Prior art keywords
tunnel
grouting
steel plate
construction method
load
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010980347.2A
Other languages
Chinese (zh)
Other versions
CN112031814A (en
Inventor
郑绍元
宋建川
程严毅
李绍贵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panzhihua Iron And Steel Group Sichuan Chengwu Zhifu Industry Co ltd
Original Assignee
Pangang Group Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pangang Group Engineering Technology Co Ltd filed Critical Pangang Group Engineering Technology Co Ltd
Priority to CN202010980347.2A priority Critical patent/CN112031814B/en
Publication of CN112031814A publication Critical patent/CN112031814A/en
Application granted granted Critical
Publication of CN112031814B publication Critical patent/CN112031814B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/103Dams, e.g. for ventilation

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明公开了一种穿越浅层大载荷公路的进洞施工方法,涉及隧洞施工技术领域,穿越浅层大载荷公路的进洞施工方法包括:在隧洞的外侧浇筑混凝土墙,用以对隧洞进行初步维护;在隧洞的拱顶以及隧洞的直墙段相距起拱线下的预设位置处进行钻孔,得到安装孔;在任一安装孔内依次压入至少两根管棚,并且将相邻的两根管棚焊接;管棚中安装注浆导管,在注浆导管中进行固结注浆;进入隧洞进行破碎围岩,当出渣至隧洞外后,进行初期支护;在隧洞内安装衬砌模板并衬砌钢筋砼,并重复执行进入隧洞进行破碎围岩的步骤。上述进洞施工方法,解决了隧道穿越浅层大载荷矿山公路施工技术难题,确保隧道施工安全性,同时节省投资,提高了经济效益。

Figure 202010980347

The invention discloses a tunnel entry construction method for crossing a shallow high-load highway, and relates to the technical field of tunnel construction. The tunnel entry construction method for crossing a shallow high-load highway includes: pouring a concrete wall on the outer side of the tunnel, so as to carry out the tunnel construction. Preliminary maintenance; drill holes at preset positions below the arching line of the tunnel vault and the straight wall section of the tunnel to obtain installation holes; press at least two pipe sheds into any installation hole in sequence, and place adjacent ones. The two pipe sheds are welded; the grouting conduit is installed in the pipe shed, and the consolidation grouting is carried out in the grouting conduit; the surrounding rock is broken into the tunnel, and the initial support is carried out after the slag is discharged outside the tunnel; Lining the formwork and lining the reinforced concrete, and repeating the steps of entering the tunnel for crushing the surrounding rock. The above-mentioned tunnel-entry construction method solves the technical problem of tunnel crossing a shallow high-load mine highway construction, ensures the safety of tunnel construction, saves investment and improves economic benefits.

Figure 202010980347

Description

Cave-entering construction method for crossing shallow-layer high-load highway
Technical Field
The invention relates to the technical field of tunnel construction, in particular to a tunnel entering construction method for passing through a shallow-layer heavy-load road.
Background
At present, the construction difficulty of the tunnel shallow layer section is often greater under the condition that the tunnel outlet section is a completely weathered rock.
In actual construction, it is often encountered that: the weathering joint crack of the tunnel outlet section develops relatively, the rock mass is broken and is in a bulk structure, and the tunnel is positioned below the highway. According to actual measurement, the distance between the tunnel top and the hillside highway is about 6.18m, the width of the highway is 6m, the thickness of the highway concrete is 0.2m, the tunnel outlet is located in a multi-year earth filling area, the earth filling is coarse sandy soil surrounding rocks which are easy to collapse and cannot be self-stabilized, heavy vehicles pass through the upper portion of the mine highway at any time, the total load of the vehicles is 80 tons, the total load of the two vehicles is 160 tons when the vehicles are staggered, and the mine highway is not constructed for roadbeds and road surfaces according to the design of the highway and is subjected to simple roadbed treatment.
Aiming at the actual conditions that the geological conditions of the section are extremely poor and the tunnel is not easy to form, the current mechanical digging, drilling blasting, mechanical slag removal, tunnel supporting and other tunneling methods cannot meet the actual requirements, the tunnel is thin in soil layer and has dynamic load on the soil layer, and the tunnel is excavated in the form of blasting and the like under the condition of large load, so that the stratum is greatly disturbed, the tunnel collapse can be caused, and the safety of constructors and equipment is influenced.
Disclosure of Invention
The invention aims to provide a tunnel entering construction method for passing through a shallow layer high-load highway, which solves the technical problem of tunnel passing through a shallow layer high-load mine highway, ensures the safety of tunnel construction, saves investment and improves economic benefits.
In order to achieve the aim, the invention provides a cave-in construction method for traversing a shallow-layer high-load road, which comprises the following steps:
pouring a concrete wall on the outer side of the tunnel for performing primary maintenance on the tunnel;
drilling at preset positions, which are apart from the arch camber line, of the arch crown of the tunnel and the straight wall section of the tunnel to obtain mounting holes;
sequentially pressing at least two pipe sheds into any one mounting hole, and welding the two adjacent pipe sheds;
a grouting guide pipe is arranged in the pipe shed, and consolidation grouting is carried out in the grouting guide pipe;
entering the tunnel to crush surrounding rock, and performing primary support after slag is discharged out of the tunnel;
and installing a lining template and lining reinforced concrete in the tunnel, and repeatedly executing the step of entering the tunnel to crush the surrounding rock.
Optionally, the step of pouring a concrete wall outside the tunnel for performing preliminary maintenance on the tunnel includes:
Installing first anchor rods on the outer side of the tunnel, welding the first anchor rods and first arch frames, and arranging at least two groups of first arch frames at intervals along the direction close to the tunnel;
all the first arch frames are bound through a first steel mesh sheet;
and installing a pouring template, and pouring concrete to obtain the concrete wall.
Optionally, before the step of installing the first anchor rod on the outer side of the tunnel and welding the first anchor rod and the first arch, the method further comprises:
according to the elevation of the tunnel entrance, after leveling the elevation of the bottom plate of the tunnel, laying a first steel plate, wherein the two side edges of the first steel plate are 80-120mm wider than the tunnel of the tunnel;
and the step of installing the first anchor rod outside the tunnel comprises:
and a first anchor rod is arranged on the first steel plate.
Optionally, get into the tunnel and carry out broken country rock, after slagging tap to outside the tunnel, carry out preliminary bracing's step, include:
entering the tunnel to crush surrounding rock, and utilizing an air pick to trim, and conveying the slag out of the tunnel;
when the tunnel excavation length is 0.8m-1.5m, laying a second steel plate, extending along the interior of the tunnel compared with the first steel plate, and welding the second steel plate and the first steel plate;
A second anchor rod is arranged on the second steel plate, the second anchor rod and the second arch frames are welded, and at least two groups of the second arch frames are arranged at intervals in the inner direction of the tunnel;
and all the second arch frames are bound through a second steel bar net piece for primary support.
Optionally, the interval between two adjacent groups of the first arches is 900-; the first steel plate and the second steel plate are 40-60mm in thickness and 3-4m in length.
Optionally, the diameter of the mounting hole is 130-150mm, the distance between any two mounting holes is 280-320mm, and the length of the mounting hole is 25-30 m.
Optionally, a grouting conduit is installed in the pipe shed, and the step of performing consolidation grouting in the grouting conduit includes:
installing a grouting guide pipe in the pipe shed, and plugging a gap between the outer wall of the grouting guide pipe and the inner wall of the pipe shed;
performing consolidation grouting in the grouting guide pipe.
Optionally, the step of plugging a gap between an outer wall of the grouting guide pipe and an inner wall of the pipe shed comprises:
and a reducing port with reduced size is arranged at the pipe orifice of the pipe shed, and the reducing port is welded with the outer wall of the grouting guide pipe.
Optionally, the step of performing consolidation grouting in a grouting conduit comprises:
and (3) performing consolidation grouting in the grouting guide pipe through cement paste, wherein the water-cement ratio of the cement paste is (0.95-1.01):1, and the grouting pressure is 0.5-1 MPa.
Optionally, between the step of performing preliminary bracing and the step of installing a lining form and lining reinforced concrete in the tunnel, the method further includes:
when the tunnel excavation length is 2.8m-3.5m, the tunnel is bound with double-layer steel bars and outer-side steel bars located on the outer sides of the double-layer steel bars, and the section diameter of the double-layer steel bars is larger than that of the outer-side steel bars.
Compared with the background art, the tunnel entering construction method for traversing the shallow heavy-load highway provided by the embodiment of the invention comprises the following steps of firstly, before the tunnel enters, performing pipe shed grouting reinforcement on soil around the tunnel; namely, a concrete wall is poured at the outer side of the tunnel at first for carrying out primary maintenance on the tunnel; then, excavating the tunnel, and drilling at preset positions, which are arranged below the arch crown of the tunnel and the straight wall section of the tunnel and are separated from the arch lifting line, to obtain mounting holes; sequentially pressing at least two pipe sheds into any one mounting hole, and welding two adjacent pipe sheds; mounting a grouting guide pipe in the pipe shed, and performing consolidation grouting in the grouting guide pipe; entering a tunnel to crush surrounding rock, and performing primary support after slag is discharged out of the tunnel; and installing a lining template in the tunnel, lining the reinforced concrete, and repeatedly performing the step of entering the tunnel to crush the surrounding rock.
The tunnel entering construction method for passing through the shallow layer heavy-load highway can effectively reduce the influence of the heavy load above the tunnel on the deformation of the excavated earth surface, ensure the stability of shallow layer excavation at the tunnel entering section, accelerate the construction progress, solve the technical problem of tunnel passing through the shallow layer heavy-load mine highway, ensure the safety of tunnel construction, save investment and improve economic benefit.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the provided drawings without creative efforts.
Fig. 1 is a schematic cross-sectional view of a tunnel during construction according to the construction method for entering a tunnel through a shallow heavy-load road provided by the embodiment of the invention;
wherein:
1-second steel plate, 2-second anchor rod, 3-pipe shed, 4-second reinforcing mesh, 5-double-layer reinforcing steel bar, 6-outer reinforcing steel bar, 7-reinforced concrete and 8-second arch frame.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In order that those skilled in the art will better understand the disclosure, the invention will be described in further detail with reference to the accompanying drawings and specific embodiments.
The embodiment of the invention provides a tunnel entering construction method for passing through a shallow layer heavy-load road, which refers to the attached figure 1 of the specification, wherein a tunnel is positioned below a heavy-load mine road, and the construction method comprises the following steps:
pouring a concrete wall on the outer side of the tunnel for performing primary maintenance on the tunnel;
drilling at preset positions, which are apart from the arch wire, of the vault of the tunnel and the straight wall section of the tunnel to obtain mounting holes;
sequentially pressing at least two pipe sheds into any one mounting hole, and welding two adjacent pipe sheds;
mounting a grouting guide pipe in the pipe shed, and performing consolidation grouting in the grouting guide pipe;
Entering a tunnel to crush surrounding rock, and performing primary support after slag is discharged out of the tunnel;
and installing a lining template in the tunnel, lining the reinforced concrete, and repeatedly performing the step of entering the tunnel to crush the surrounding rock.
Aiming at the step of pouring a concrete wall on the outer side of a tunnel for carrying out primary maintenance on the tunnel, namely before the tunnel enters the tunnel, carrying out pipe shed grouting reinforcement on soil around the tunnel, wherein the grouting range is 3-5 times of the width of the tunnel, grouting is respectively carried out on the left side and the right side of the tunnel by about 15m, grouting is carried out on the upper part of the tunnel to a road, grouting is carried out on the bottom of the tunnel to a basement rock by about 13.5m, grouting is carried out on the extension box culvert direction of the tunnel by 10m, and the width of the tunnel is 4 m; the method specifically comprises the following steps:
installing first anchor rods on the outer side of the tunnel, welding the first anchor rods and the first arch frames, and arranging at least two groups of first arch frames at intervals along the direction close to the tunnel;
all the first arch frames are bound through the first steel mesh sheet;
and installing a pouring template, and pouring concrete to obtain the concrete wall.
Certainly, in order to realize the installation of the first anchor rod and the first arch, firstly, a first steel plate is paved after the elevation of a bottom plate of the tunnel is leveled according to the elevation of a tunnel entrance, and the two side edges of the first steel plate are 80-120mm wider than the tunnel; and mounting a first anchor on the first steel plate.
In other words, in the first step, according to the elevation of the tunnel portal, after leveling the elevation of the bottom plate, the first steel plate with the thickness of 50mm can be laid, the two sides of the first steel plate are 100mm wider than the roadway, and the size of the first steel plate can be set to be 3.6m long by 0.2m wide by 0.05m thick.
Secondly, drilling at an exposed section 3m outside the tunnel by adopting an YT28 drilling machine, and installing phi 20 first anchor rods, wherein 2 anchor rods are arranged in each group, the number of the anchor rods is two, the end parts of the first anchor rods are welded and connected with a first arch centering (specifically a 16# I-steel arch centering), and the distance between the first arch centering can be set to be 1000 mm;
thirdly, binding by using a first steel bar net piece (which can be a phi 8 x @150 steel bar net piece) after 3I-steel arch frames are installed;
and fourthly, installing a pouring template, reserving a follow-up sleeve hole, pouring concrete and curing the concrete wall.
And finishing the primary maintenance of the tunnel.
Carry out broken country rock to getting into the tunnel, after slagging tap outside the tunnel, carry out preliminary bracing's step, include:
entering a tunnel to crush surrounding rock, finishing by using an air pick, and conveying the slag out of the tunnel;
when the tunnel excavation length is 0.8m-1.5m, laying a second steel plate 1, extending the second steel plate 1 along the interior of the tunnel compared with the first steel plate, and welding the second steel plate 1 and the first steel plate;
The second anchor rods 2 are installed on the second steel plate 1, the second anchor rods 2 and the second arch frames 8 are welded, and the inner directions of the tunnels of at least two groups of second arch frames 8 are arranged at intervals;
and all the second arch frames 8 are bound through the second reinforcing mesh 4 for primary support.
Referring to the description and the attached drawing 1, the vault of the tunnel can be drilled by a 90A guide drilling machine through a reserved hole and a following pipe, the diameter of the drilled hole is phi 146, the drilled holes are arranged at intervals of 300mm, and the length of the drilled hole is 28.3 m;
drilling holes with diameter phi 146 in a straight wall section of the tunnel through reserved holes and follow pipes at a distance of 600mm below the arch wire, wherein the holes are arranged at intervals of 300mm, and the length of the holes is 28.3 m;
cleaning the hole after the drilling of the pipe is finished;
the installation holes can be obtained through the above method, and it can be seen that the diameter of the installation hole can be set to 130-.
Then, a first 9m flower pipe shed with the length phi of 89mm, namely the pipe shed 3, is pressed into each mounting hole, and the position of the pipe shed 3 is the position of the mounting hole. The pipe shed 3 can adopt seamless steel pipes, the wall thickness delta is 5mm, the outer ring is provided with annular grouting holes with the diameter of phi 10mm, and the distance between the annular grouting holes is 600 mm.
The second pipe shed 3 is welded with the first pipe shed 3 until the 28.3m shallow pipe shed is installed hole by hole;
Next, the follow-up casing can be pulled out hole by a 90A pilot drill;
then installing a phi 20 grouting guide pipe in each mounting hole;
before grouting, a pipe orifice of the pipe shed 3 can be made into a 6cm reducing port by using a 2mm steel plate and welded with the outer wall of a grouting guide pipe, and a reducing port welding plugging plug is connected with a grouting guide pipe screw thread; namely, a grouting guide pipe is arranged in the pipe shed, and a gap between the outer wall of the grouting guide pipe and the inner wall of the pipe shed is sealed; and carrying out consolidation grouting in the grouting guide pipe. It can be seen that the pipe orifice of the pipe shed can be provided with a reducing orifice with reduced size, and the reducing orifice is welded with the outer wall of the grouting guide pipe.
Adopting cement paste for grouting, wherein the water cement ratio of the cement paste is l: the water-cement ratio of the cement paste can be in the range of (0.95-1.01):1, the grouting pressure: 0.5-1.0 MPa, injecting the slurry from the orifice at one time to ensure that the slurry in the pipe is full and compact until the designed grouting pressure or the designed grouting amount is reached;
after the grouting reaches the concrete strength, breaking the surrounding rock by a breaking hammer of a small excavator after entering the hole, manually finishing by an air pick, and conveying slag to the outside of the hole by a loader;
when the excavation length of the tunnel is 1m, extending and laying a second steel plate 1, and welding the second steel plate 1 and the first steel plate together to prevent uneven settlement; wherein the first steel plate and the second steel plate have a thickness of 40-60mm and a length of 3-4 m.
The second anchor rods 2 are welded with the second steel plates 1, the length of each second anchor rod 2 can be set to be 2m, 2 anchor rods are arranged in each group, 6 anchor rods are arranged in total, the end portions of the second anchor rods 2 are connected with second arch arches 8 (specifically, 22# I-steel arch arches) in a welding mode, the distance between the two second arch arches 8 is 300mm, and binding can be carried out through second steel bar meshes (specifically, 4 phi 8@150 steel bar meshes) for primary support; wherein, the interval between two adjacent first arches is 900-.
And when the construction length reaches 3m, binding double-layer steel bars 5 (specifically phi 22 double-layer steel bars) and outer-side steel bars 6 (specifically phi 14 steel bars), wherein the distance between the double-layer steel bars 5 is 120mm, and the distance between the outer-side steel bars 6 is 150 mm. That is, the sectional diameter of the double-layered reinforcing bars 5 is greater than that of the outer reinforcing bars 6.
Installing lining form, lining with reinforced concrete 7,
and (5) performing circular construction according to the method, and repeatedly executing the step of entering the tunnel to crush the surrounding rock until the shallow construction is finished.
According to the tunnel entering construction method for passing through the shallow layer high-load road, provided by the embodiment of the invention, before a tunnel enters a tunnel, a first steel plate is laid on a bottom plate, a first anchor rod and a first arch frame are installed, a concrete wall is poured, drilling is carried out by reserving phi 146 follow-up sleeve holes, a phi 89 steel pipe shed is pressed in, after a sleeve is pulled out, a phi 20 grouting guide pipe is installed for consolidation grouting. After entering the tunnel, the excavator crushes the surrounding rock, the air pick is used manually for cooperation operation, when the operation is 1m, slag is discharged to the outside of the tunnel, a second steel plate is laid, a second arch frame is installed, primary support is carried out, binding reinforcing steel bars and two lining linings are carried out when the construction is 4m, dynamic monitoring is carried out during the construction, and vault and earth surface subsidence measurement is carried out. According to the arrangement, the influence of the large load above the tunnel on the deformation of the excavated earth surface is effectively reduced, the stability of shallow excavation of the tunnel entering section is guaranteed, the construction progress is accelerated, the technical problem that the tunnel penetrates through the shallow large-load mine highway is solved, the safety of tunnel construction is ensured, the investment is saved, and the economic benefit is improved. Obviously, the construction process steps are simplified, the construction is convenient, the safety and the reliability are realized, and the cost is low.
It is noted that, in this specification, relational terms such as first and second, and the like are used solely to distinguish one entity from another entity without necessarily requiring or implying any actual such relationship or order between such entities.
The construction method for entering the hole of the shallow-layer heavy-load road provided by the invention is described in detail above. The principles and embodiments of the present invention are explained herein using specific examples, which are presented only to assist in understanding the method and its core concepts. It should be noted that, for those skilled in the art, it is possible to make various improvements and modifications to the present invention without departing from the principle of the present invention, and those improvements and modifications also fall within the scope of the claims of the present invention.

Claims (8)

1.一种穿越浅层大载荷公路的进洞施工方法,其特征在于,包括:1. a construction method for tunneling through a shallow high-load highway, is characterized in that, comprising: 在隧洞的外侧浇筑混凝土墙,用以对所述隧洞进行初步维护;pouring concrete walls on the outside of the tunnel for preliminary maintenance of said tunnel; 在所述隧洞的拱顶以及所述隧洞的直墙段相距起拱线下的预设位置处进行钻孔,得到安装孔;Drilling holes at preset positions below the arching line between the dome of the tunnel and the straight wall section of the tunnel to obtain installation holes; 在任一所述安装孔内依次压入至少两根管棚,并且将相邻的两根所述管棚焊接;Pressing at least two pipe sheds into any one of the installation holes in sequence, and welding the two adjacent pipe sheds; 所述管棚中安装注浆导管,在所述注浆导管中进行固结注浆;A grouting conduit is installed in the pipe shed, and consolidation grouting is performed in the grouting conduit; 进入所述隧洞进行破碎围岩,当出渣至所述隧洞外后,进行初期支护;Enter the tunnel to break the surrounding rock, and after the slag is discharged to the outside of the tunnel, perform initial support; 在所述隧洞内安装衬砌模板并衬砌钢筋砼,并重复执行所述进入所述隧洞进行破碎围岩的步骤;Installing lining formwork and lining reinforced concrete in the tunnel, and repeating the steps of entering the tunnel to break the surrounding rock; 其中,所述在隧洞的外侧浇筑混凝土墙,用以对所述隧洞进行初步维护的步骤,包括:Wherein, the steps of pouring concrete walls on the outside of the tunnel for preliminary maintenance of the tunnel include: 在隧洞的外侧安装第一锚杆,将所述第一锚杆和第一拱架焊接,至少两组所述第一拱架沿着靠近所述隧洞的方向间隔设置;A first anchor rod is installed on the outside of the tunnel, and the first anchor rod and the first arch frame are welded, and at least two groups of the first arch frames are arranged at intervals along the direction close to the tunnel; 全部所述第一拱架通过第一钢筋网片绑扎;All the first arches are bound by the first steel mesh; 安装浇筑模板,并浇筑混凝土,得到混凝土墙;Install the pouring formwork and pour concrete to obtain a concrete wall; 所述在隧洞的外侧安装第一锚杆,并且将所述第一锚杆和第一拱架焊接的步骤之前,还包括:Before the steps of installing the first anchor rod on the outside of the tunnel and welding the first anchor rod and the first arch, the method further includes: 根据隧洞的洞口标高,找平所述隧洞的底板标高之后,铺设第一钢板,所述第一钢板的两侧边相较于所述隧洞的巷道宽80-120mm;According to the elevation of the opening of the tunnel, after leveling the elevation of the bottom plate of the tunnel, a first steel plate is laid, and the two sides of the first steel plate are 80-120mm wider than the roadway of the tunnel; 且所述在隧洞的外侧安装第一锚杆的步骤,包括:And the step of installing the first anchor rod on the outside of the tunnel includes: 在所述第一钢板上安装第一锚杆。A first anchor rod is installed on the first steel plate. 2.根据权利要求1所述的穿越浅层大载荷公路的进洞施工方法,其特征在于,所述进入隧洞进行破碎围岩,当出渣至所述隧洞外后,进行初期支护的步骤,包括:2. The tunnel-entry construction method for crossing a shallow high-load highway according to claim 1, wherein the said entry into the tunnel is to break the surrounding rock, and after the slag is discharged to the outside of the tunnel, the step of initial support is performed ,include: 进入所述隧洞进行破碎围岩,利用风镐修整,将出渣运送至所述隧洞外;Enter the tunnel to break the surrounding rock, trim it with an air pick, and transport the slag to the outside of the tunnel; 当所述隧洞开挖长度在0.8m-1.5m时,铺设第二钢板,所述第二钢板相较于所述第一钢板沿着所述隧洞的内部延伸,将所述第二钢板和所述第一钢板焊接;When the excavation length of the tunnel is 0.8m-1.5m, a second steel plate is laid. Compared with the first steel plate, the second steel plate extends along the interior of the tunnel, and the second steel plate and the Welding the first steel plate; 所述第二钢板安装第二锚杆,将所述第二锚杆和第二拱架焊接,至少两组所述第二拱架所述隧洞的内部方向间隔设置;The second steel plate is installed with a second anchor rod, and the second anchor rod and the second arch frame are welded, and at least two groups of the second arch frame are arranged at intervals in the inner direction of the tunnel; 全部所述第二拱架通过第二钢筋网片绑扎,进行初期支护。All the second arches are bound by second steel mesh sheets for initial support. 3.根据权利要求2所述的穿越浅层大载荷公路的进洞施工方法,其特征在于,相邻的两组所述第一拱架的间隔为900-1100mm,相邻的两组所述第二拱架的间隔为280-320mm;所述第一钢板和所述第二钢板的厚度为40-60mm,且长度为3-4m。3. The tunnel-entry construction method for crossing a shallow high-load highway according to claim 2, wherein the interval between the adjacent two groups of the first arches is 900-1100mm, and the adjacent two groups of the first arches The interval between the second arches is 280-320mm; the thickness of the first steel plate and the second steel plate is 40-60mm, and the length is 3-4m. 4.根据权利要求1-3任意一项所述的穿越浅层大载荷公路的进洞施工方法,其特征在于,所述安装孔的直径为130-150mm,任意两个所述安装孔的间距为280-320mm,所述安装孔的长度为25-30m。4. The construction method for tunneling through a shallow high-load highway according to any one of claims 1-3, wherein the diameter of the installation hole is 130-150mm, and the distance between any two installation holes is 130-150mm. is 280-320mm, and the length of the mounting hole is 25-30m. 5.根据权利要求1-3任意一项所述的穿越浅层大载荷公路的进洞施工方法,其特征在于,所述管棚中安装注浆导管,在所述注浆导管中进行固结注浆的步骤,包括:5. The construction method for tunneling through a shallow high-load highway according to any one of claims 1 to 3, wherein a grouting conduit is installed in the pipe shed, and consolidation is performed in the grouting conduit The steps of grouting include: 在所述管棚中安装注浆导管,并且将所述注浆导管的外壁和所述管棚的内壁之间的缝隙进行封堵;installing a grouting conduit in the tube shed, and sealing the gap between the outer wall of the grouting conduit and the inner wall of the tube shed; 在所述注浆导管中进行固结注浆。Consolidation grouting is carried out in the grouting conduit. 6.根据权利要求5所述的穿越浅层大载荷公路的进洞施工方法,其特征在于,所述将注浆导管的外壁和所述管棚的内壁之间的缝隙进行封堵的步骤,包括:6. The construction method for tunneling through a shallow high-load highway according to claim 5, wherein the step of sealing the gap between the outer wall of the grouting conduit and the inner wall of the pipe shed, include: 在所述管棚的管口处设有尺寸缩小的变径口,所述变径口和所述注浆导管的外壁焊接。A diameter-reduced opening is provided at the opening of the tube shed, and the diameter-reduced opening is welded with the outer wall of the grouting conduit. 7.根据权利要求5所述的穿越浅层大载荷公路的进洞施工方法,其特征在于,所述在注浆导管中进行固结注浆的步骤,包括:7. The construction method for tunneling through a shallow high-load highway according to claim 5, wherein the step of carrying out consolidation grouting in the grouting conduit comprises: 通过水泥浆向所述注浆导管中进行固结注浆,水泥浆的水灰比为(0.95-1.01):1,注浆压力为0.5-1MPa。Consolidation grouting is performed into the grouting conduit through cement slurry, the water-cement ratio of the cement slurry is (0.95-1.01):1, and the grouting pressure is 0.5-1 MPa. 8.根据权利要求1-3任意一项所述的穿越浅层大载荷公路的进洞施工方法,其特征在于,在所述进行初期支护的步骤和所述在隧洞内安装衬砌模板并衬砌钢筋砼的步骤之间,还包括:8. The tunnel-entry construction method for crossing a shallow high-load highway according to any one of claims 1-3, characterized in that, in the step of performing initial support and in the step of installing a lining formwork in the tunnel and lining the Between the steps of reinforced concrete, it also includes: 当所述隧洞开挖长度在2.8m-3.5m时,在所述隧洞绑扎双层钢筋和位于所述双层钢筋外侧的外侧钢筋,所述双层钢筋的截面直径大于所述外侧钢筋的截面直径。When the excavation length of the tunnel is 2.8m-3.5m, the double-layer steel bars and the outer steel bars located outside the double-layer steel bars are bound in the tunnel, and the cross-sectional diameter of the double-layer steel bars is larger than that of the outer steel bars. diameter.
CN202010980347.2A 2020-09-17 2020-09-17 Cave-entering construction method for crossing shallow-layer high-load highway Active CN112031814B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010980347.2A CN112031814B (en) 2020-09-17 2020-09-17 Cave-entering construction method for crossing shallow-layer high-load highway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010980347.2A CN112031814B (en) 2020-09-17 2020-09-17 Cave-entering construction method for crossing shallow-layer high-load highway

Publications (2)

Publication Number Publication Date
CN112031814A CN112031814A (en) 2020-12-04
CN112031814B true CN112031814B (en) 2022-07-29

Family

ID=73590086

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010980347.2A Active CN112031814B (en) 2020-09-17 2020-09-17 Cave-entering construction method for crossing shallow-layer high-load highway

Country Status (1)

Country Link
CN (1) CN112031814B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112664202A (en) * 2020-12-23 2021-04-16 攀钢集团工程技术有限公司 Reverse small shed tunneling method for shallow buried section
CN112963170A (en) * 2021-02-28 2021-06-15 中铁十四局集团第一工程发展有限公司 Anti-riot structure of plateau cave depot opening and construction method
CN114320339A (en) * 2021-12-20 2022-04-12 攀钢集团工程技术有限公司 Buffering damping device for preventing blasting damage of tunnel portal
CN114673528B (en) * 2022-03-28 2023-04-28 中国电建集团成都勘测设计研究院有限公司 Tunnel top cavity supporting method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016095629A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Advanced support structure for oversized variable-cross-section tunnel
CN209892228U (en) * 2019-04-16 2020-01-03 中国十七冶集团有限公司 Underground comprehensive pipe gallery structure constructed by adopting underground excavation method
CN111485919A (en) * 2020-06-28 2020-08-04 中国矿业大学(北京) Anti-shearing lock of tunnel advanced support guide pipe, grouting guide pipe and construction method

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4196291B2 (en) * 2004-06-07 2008-12-17 清水建設株式会社 Tunnel receiving method
CN203925514U (en) * 2014-05-21 2014-11-05 中国能源建设集团广东省电力设计研究院 A kind of supporting and protection structure of electric power plant circulating water system tunnel mouth
CN206957731U (en) * 2017-05-08 2018-02-02 中国水利水电建设工程咨询中南有限公司 A kind of supporting construction for section of being caved in hole
CN207229131U (en) * 2017-08-07 2018-04-13 中交一航局第三工程有限公司 A kind of precipitous broken formation tunnel portal section supporting construction
CN110056369B (en) * 2019-05-05 2020-10-13 中交第三航务工程局有限公司 Construction method for entrance and exit hole of tunnel
CN110374633B (en) * 2019-07-19 2020-09-22 中铁隧道集团二处有限公司 Tunnel opening section construction method for tunnel to pass through loose body
CN110985057A (en) * 2019-12-25 2020-04-10 云南交投公路建设第四工程有限公司 Construction method for tunneling hidden excavation and hole entering under combined advanced support of cover beam and pipe shed
CN112663625A (en) * 2020-12-29 2021-04-16 哈尔滨工业大学 Construction and protection method for shallow-buried bias-pressure weak surrounding rock tunnel portal in alpine region

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016095629A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Advanced support structure for oversized variable-cross-section tunnel
CN209892228U (en) * 2019-04-16 2020-01-03 中国十七冶集团有限公司 Underground comprehensive pipe gallery structure constructed by adopting underground excavation method
CN111485919A (en) * 2020-06-28 2020-08-04 中国矿业大学(北京) Anti-shearing lock of tunnel advanced support guide pipe, grouting guide pipe and construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
西二线九江盾构设备进洞技术研究;王乐等;《天然气与石油》;20111225(第06期);全文 *
隧道建设盾构进出洞施工技术研究;张庆贺,唐益群,杨林德;《地下空间》;19940630(第02期);全文 *

Also Published As

Publication number Publication date
CN112031814A (en) 2020-12-04

Similar Documents

Publication Publication Date Title
CN112031814B (en) Cave-entering construction method for crossing shallow-layer high-load highway
CN112502734B (en) Construction method for water-rich sand layer shield zone connecting channel
CN110905530B (en) Stability control construction method for water-rich soft rock tunnel penetrating fault fracture zone
CN111502696A (en) Dense-mesh type advanced support system of underground excavation tunnel and construction method
CN111997624A (en) A construction method for shallowly buried large-section undercut rectangular tunnel
CN208702421U (en) The tunnel support structure of existing pile foundation building is worn under a kind of
CN112502732B (en) Construction method of shield tunnel in water-rich sand layer
CN114622917A (en) Construction Methods for Handling Tunnel Collapse
CN211144503U (en) High steep topography bridge tunnel meets section open cut tunnel and connects long structure
CN109736884B (en) Treatment structure for water gushing in underground river close to tunnel and construction method of treatment structure
CN112502717B (en) Construction method for excavating connecting channels between shield sections of water-rich sand layer
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN104631440A (en) Stiffening core lengthening foundation pit support structure for existing large-diameter bored concrete pile and construction method
CN106014443A (en) Method for preventing roadway floor heaving and wall sliding of gob-side entry retaining
CN110847929A (en) Tunnel portal section pre-reinforcing and excavating construction method based on partition blasting
KR100656194B1 (en) Open type method using tunnel method
CN114737979B (en) Construction method for continuously passing large-diameter water conveying pipeline downwards in shield region
CN113309526B (en) Construction method for excavation and supporting of buckling arch of subway station
CN211598669U (en) Tunnel collapse cavity backfill structure
CN119435012B (en) A method for concealed excavation of a three-layer six-hole subway station
CN111894598A (en) Shaft reinforcing method
CN116537819A (en) Half reverse construction method for primary support of urban mountain tunnel by ultra-large span and small clear distance cover excavation method
CN115030731A (en) Pilot tunnel construction method in cross tunnel engineering
CN115614047A (en) A large-span tunnel collapse treatment method excavated by step method
CN110735641B (en) The construction method of the transfer channel under the pipeline

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: No. 28, east section of Panzhihua Avenue, East District, Panzhihua City, Sichuan Province

Patentee after: Panzhihua Iron and Steel Group Sichuan Chengwu Zhifu Industry Co.,Ltd.

Country or region after: China

Address before: 617067 Sichuan Province, Panzhihua City, Dong District, Jiangnan Second Road

Patentee before: PANGANG GROUP ENGINEERING TECHNOLOGY Co.,Ltd.

Country or region before: China

CP03 Change of name, title or address