CN111997624A - A construction method for shallowly buried large-section undercut rectangular tunnel - Google Patents

A construction method for shallowly buried large-section undercut rectangular tunnel Download PDF

Info

Publication number
CN111997624A
CN111997624A CN202010829595.7A CN202010829595A CN111997624A CN 111997624 A CN111997624 A CN 111997624A CN 202010829595 A CN202010829595 A CN 202010829595A CN 111997624 A CN111997624 A CN 111997624A
Authority
CN
China
Prior art keywords
steel
grouting
pipe
arch
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010829595.7A
Other languages
Chinese (zh)
Inventor
程争民
戴育昕
李旭
陈东东
杨涛
姜新宙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHEC Third Highway Engineering Co Ltd
Original Assignee
CCCC SHEC Third Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHEC Third Highway Engineering Co Ltd filed Critical CCCC SHEC Third Highway Engineering Co Ltd
Priority to CN202010829595.7A priority Critical patent/CN111997624A/en
Publication of CN111997624A publication Critical patent/CN111997624A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明提供一种浅埋大断面暗挖矩形隧道施工工法,包括以下步骤:S1:暗挖段隧道采用CRD法施工,施工前对暗挖区域进行全面降水处理,将地下水位降至基坑开挖面以下0.5m;S2:地表破碎岩层注浆加固,防止开挖施工过程中引起周边地面变形破坏;S3:采用超前大管棚、超前注浆小导管进行超前支护;S4:暗挖段在开挖或分部开挖完成后立即进行初喷,及时封闭围岩暴露面,型钢拱架、锚杆和钢筋网支护与开挖循环进尺协同进行;S5:复喷混凝土;S6:初期支护后及时对拱背空隙进行注浆。本发明通过以上技术措施,实现加固隧道围岩和控制地表下沉的作用,解决了浅埋大断面暗挖矩形隧道围岩变形控制难的问题,为浅埋大断面暗挖矩形隧道施工提供了有效的安全保障。

Figure 202010829595

The present invention provides a construction method for a shallow-buried and large-section undercut rectangular tunnel, which includes the following steps: S1: the undercut section of the tunnel is constructed by the CRD method. 0.5m below the excavation surface; S2: Grout reinforcement of the broken rock strata on the surface to prevent deformation and damage of the surrounding ground during the excavation construction; S3: Use advanced large pipe shed and advanced grouting small conduit for advanced support; S4: Concave excavation section After excavation or sub-excavation is completed, initial spraying is carried out immediately, the exposed surface of surrounding rock is closed in time, and the support of profiled steel arches, bolts and steel mesh is coordinated with the excavation cycle footage; S5: re-shot concrete; S6: initial stage After supporting, grouting shall be carried out in time for the gap of the back of the arch. Through the above technical measures, the invention realizes the functions of strengthening the surrounding rock of the tunnel and controlling the subsidence of the ground surface, solves the problem of difficult deformation control of the surrounding rock of the shallow-buried large-section rectangular tunnel, and provides the construction of the shallow-buried large-section rectangular tunnel. Effective security.

Figure 202010829595

Description

一种浅埋大断面暗挖矩形隧道施工方法A construction method for shallowly buried large-section undercut rectangular tunnel

技术领域technical field

本发明属于隧道工程技术领域,具体涉及一种浅埋大断面暗挖矩形隧道施工方法。The invention belongs to the technical field of tunnel engineering, and in particular relates to a construction method for a shallow-buried large-section undercut rectangular tunnel.

背景技术Background technique

随着我国城市化进程不断加快,城市轨道交通(地铁)建设进入迅速发展时期,常用的城市地下施工方法主要有明挖法、暗挖法、顶管法、矿山法等施工方法。但由于地铁车站主要位于主城区,主城区道路交通繁忙,地下管线交错纵横,明挖法对地面交通和地下管线影响较大,一般不适用于主城区隧道工程建设;顶管法对地下道路线性要求较高,对于埋深浅的工程适用性差;矿山法适用于埋深大,施工场所位于岩层中的隧道工程。暗挖法可以克服以上方法的不足,具有施工灵活,适用范围广的特点。With the accelerating process of urbanization in my country, the construction of urban rail transit (subway) has entered a period of rapid development. However, since the subway station is mainly located in the main urban area, the main urban area has busy road traffic, and the underground pipelines are crisscrossed. The requirements are high, and the applicability of the project with shallow burial depth is poor; the mining method is suitable for tunnel engineering with large burial depth and the construction site is located in the rock layer. The underground excavation method can overcome the shortcomings of the above methods, and has the characteristics of flexible construction and wide application range.

但采用常规暗挖法无法适用于降雨多的地段暗挖隧道施工,由于暗挖隧道近距离横穿通信管线、给水管线、污水管线、电力管线、雨水管线以及管线检修井,另有雨水箱涵横穿隧道上方,其距暗挖断面距离较短,受潮汐影响,地下水日变化量大,对暗挖施工过程控制要求高,隧道结构复杂,给施工带来极大的考验。However, the conventional underground excavation method cannot be applied to the construction of underground tunnels in areas with heavy rainfall, because the underground tunnels traverse communication pipelines, water supply pipelines, sewage pipelines, power pipelines, rainwater pipelines and pipeline maintenance wells at a short distance, and there are also rainwater tank culverts. Crossing the top of the tunnel, the distance from the undercut section is short, affected by tides, the daily variation of groundwater is large, the control requirements for the undercut construction process are high, and the tunnel structure is complex, which brings great challenges to the construction.

基于上述缘由,亟需一种浅埋大断面暗挖矩形隧道施工工法,在施工过程中确保开挖围岩稳定和上方浅覆土内的管线安全。Based on the above reasons, there is an urgent need for a shallow-buried large-section rectangular tunnel construction method to ensure the stability of the excavated surrounding rock and the safety of pipelines in the shallow overburden above during the construction process.

发明内容SUMMARY OF THE INVENTION

本发明提供一种浅埋大断面暗挖矩形隧道施工方法,以解决上述现有方法存在的问题,解决主城区内浅埋大断面暗挖矩形隧道施工难题。The invention provides a construction method for a shallow buried large-section undercut rectangular tunnel, so as to solve the problems existing in the above-mentioned existing methods and solve the construction problem of the shallow buried large-section undercut rectangular tunnel in the main urban area.

本发明的技术方案是:一种浅埋大断面暗挖矩形隧道施工方法,其主要施工步骤如下:The technical scheme of the present invention is: a shallow-buried large-section undercut rectangular tunnel construction method, the main construction steps of which are as follows:

S1:暗挖段隧道采用CRD法施工,施工前对暗挖区域进行全面降水处理,将地下水位降至基坑开挖面以下0.5m;S1: The CRD method is used for the construction of the tunnel in the undercut section. Before construction, the undercut area is fully dewatered, and the groundwater level is lowered to 0.5m below the excavation surface of the foundation pit;

S2:地表破碎岩层注浆加固,防止开挖施工过程中引起周边地面变形破坏,具体过程包括(1)钻孔定位:现场清理完毕后,根据复核过的控制点,测设定位轴线进行桩位放样,样桩尺寸应符合设计施工要求,允许偏差控制在10mm以内;(2)钻机就位:钻机进场调试完成后,安装就位,精心调平,并支撑牢固,确保施工中不发生倾斜,移位;(3)钻机钻进:钻机就位,调平设备,进行钻进,钻进到位后,安装钢管,钢管加工由加工厂内加工完毕后,运输到现场进行安装;(4)清孔:注浆前先冲洗无缝钢管内杂物,再将注浆管插入孔底;(5)注浆:由下往上顺序注浆,直至浆液从无缝钢管顶口流出浓浆为止;S2: Grout reinforcement of the broken rock layer on the surface to prevent the surrounding ground from being deformed and damaged during the excavation construction. The specific process includes (1) Drilling positioning: After the site is cleaned, according to the reviewed control points, measure the positioning axis to carry out the pile The size of the sample pile should meet the design and construction requirements, and the allowable deviation should be controlled within 10mm; (2) The drilling rig is in place: After the drilling rig is commissioned, it is installed in place, carefully leveled, and supported firmly to ensure that it does not occur during construction. Inclination, displacement; (3) Drilling of the drilling rig: the drilling rig is in place, the equipment is leveled, and the drilling is carried out. After the drilling is in place, the steel pipe is installed. After the steel pipe is processed in the processing plant, it is transported to the site for installation; (4) ) Hole cleaning: flush the debris in the seamless steel pipe before grouting, and then insert the grouting pipe into the bottom of the hole; (5) grouting: grouting sequentially from bottom to top until the slurry flows out of the top of the seamless steel pipe. until;

S3:采用超前大管棚、超前注浆小导管进行超前支护;S3: The advanced large pipe shed and the advanced grouting small pipe are used for advanced support;

S4:暗挖段在开挖或分部开挖完成后立即进行初喷,及时封闭围岩暴露面,型钢拱架、锚杆和钢筋网支护与开挖循环进尺协同进行;S4: The initial spraying is carried out immediately after the excavation or sub-excavation is completed in the underground excavation section, and the exposed surface of the surrounding rock is closed in time, and the support of profiled steel arches, bolts and steel mesh is carried out in coordination with the excavation cycle footage;

S5:待型钢拱架、锚杆和钢筋网支护完成后及时复喷混凝土;S5: Re-spray concrete in time after the steel arch, anchor rod and steel mesh support are completed;

S6:初期支护后及时对拱背空隙进行注浆,防止拱部留有空隙,使支护与围岩分析。S6: After the initial support, grouting should be carried out to the back of the arch in time to prevent the arch from leaving a gap, so that the support and surrounding rock can be analyzed.

方案进一步地,上述步骤S1中,出入口降水采用大口径管井降水,在基坑内井点按8~12m间距设置,井管直径为0.8m,降水井钢管插入深度低于基坑底不小于5m。The scheme further, in the above step S1, large-diameter pipe wells are used for dewatering at the entrance and exit, and the well points in the foundation pit are arranged at an interval of 8-12m, the diameter of the well pipe is 0.8m, and the depth of the pipe in the dewatering well is not less than 5m below the bottom of the foundation pit.

方案进一步地,上述步骤S2中,注浆范围为开挖轮廓线外2m,注浆工艺采用袖阀管注浆加固,旋喷桩内插Φ108钢管,钢管深入到基底下2m,注浆加固采用水泥-水玻璃双液浆,水灰比1:1,注浆压力1.0 MPa-2.0 MPa。The scheme further, in the above step S2, the grouting range is 2m outside the excavation contour line, the grouting process adopts the sleeve valve pipe grouting reinforcement, the rotary jet pile is inserted into the Φ108 steel pipe, the steel pipe goes deep into the base 2m, and the grouting reinforcement adopts Cement-water glass double slurry, water-cement ratio 1:1, grouting pressure 1.0 MPa-2.0 MPa.

方案进一步地,上述步骤S3中,超前大管棚的施工过程包括(1)测量放线;(2)休整管棚操作平台;(3)钻机就位进行钻孔,根据地质条件和施工条件,采用一台潜孔钻机进行作业,施工顺序根据基坑开挖顺序进行施工;(4)顶进管棚,为使钢管接头错开,加工钢管时将钢管进行钢节编号,下管时,当孔壁不易坍塌时,采用直接撞击法将导管撞击至设计位置,当孔壁容易坍塌时,用导管与钻头同时钻进的方法;(5)综合检查合格后进行注浆,注浆完成后进行检测,采用一次全钻孔注浆,管棚注浆达到浆液扩散半径不小于0.5m,根据岩石情况选定注浆方式,注浆采用水泥浆,水泥浆水灰比1:1,注浆压力:初压0.5~1MPa,终压2MPa,注浆前应先进行注浆现场试验,注浆参数应通过现场试验按实际情况进行调整。Scheme Further, in the above step S3, the construction process of the advanced large pipe shed includes (1) measuring and laying out lines; (2) resting and adjusting the pipe shed operating platform; (3) drilling rigs in place to drill holes. A down-the-hole drilling rig is used for the operation, and the construction sequence is carried out according to the excavation sequence of the foundation pit; (4) Jacking into the pipe shed, in order to stagger the steel pipe joints, the steel pipe shall be numbered when the steel pipe is processed. When the wall is not easy to collapse, use the direct impact method to hit the pipe to the design position. When the hole wall is easy to collapse, use the method of drilling the pipe and the drill at the same time; (5) After the comprehensive inspection is qualified, grouting is carried out, and the inspection is carried out after the grouting is completed. , using a full-hole grouting, the pipe shed grouting reaches a slurry diffusion radius of not less than 0.5m, and the grouting method is selected according to the rock conditions. The initial pressure is 0.5~1MPa, and the final pressure is 2MPa. Before grouting, the grouting field test should be carried out, and the grouting parameters should be adjusted according to the actual situation through the field test.

方案进一步地,上述步骤S3中,超前注浆小导管的施工过程包括(1)测量导管孔位,暗挖段拱部范围内设计超前注浆小导管,环向间距30cm,小导管外倾角10~15°,纵向水平搭接长度1m,注浆管一端做成锥头,另一端焊上铁箍;(2)钻孔,在距离铁箍1.0m处开始钻孔,钻孔沿管壁间隔150mm,呈梅花型布设,孔位互成90°,孔径8mm,可直接采用风钻顶进;(3)安设导管,用风钻将小导管顶入,导管尾端外露足够长度,尾部与钢架焊接在一起;(4)喷射混凝土封闭注浆面;(5)导管注浆,注浆浆液采用水泥-水玻璃双液浆,注浆压力拟定0.4~0.6MPa。Scheme Further, in the above-mentioned step S3, the construction process of the advance grouting small conduit includes (1) measuring the hole position of the conduit, and designing the advance grouting small conduit within the arch of the undercut section, the circumferential spacing is 30cm, and the camber angle of the small conduit is 10 cm. ~15°, the vertical and horizontal lap length is 1m, one end of the grouting pipe is made into a cone head, and the other end is welded with an iron hoop; (2) Drilling, start drilling at a distance of 1.0m from the iron hoop, and the drill holes are spaced along the pipe wall 150mm, arranged in a plum-shaped pattern, the holes are 90° to each other, the diameter of the hole is 8mm, and the pneumatic drill can be used for jacking directly; (3) Install the guide pipe, use the pneumatic drill to push the small guide pipe, and the tail end of the guide pipe is exposed for a sufficient length, and the tail is connected to the steel frame. Weld together; (4) Close the grouting surface with shotcrete; (5) grouting the conduit, the grouting slurry adopts cement-water glass double-liquid slurry, and the grouting pressure is proposed to be 0.4 ~ 0.6MPa.

方案进一步地,上述步骤S4中,型钢拱架的施工过程是(1)断面检查和测量定位,型钢拱架根据设计断面不同而异;(2)钢支撑拼装、架立就位、锚杆锁定,初支钢架采用I20a工字型钢,临时竖撑及临时仰拱采用I18工字型钢,间距0.5m,相邻两榀钢架间均采用Φ20钢筋连接,连接筋环向间距0.5m,两拱脚处和两边墙脚处预留安装钢架槽钢凹槽确保拱脚落实,初喷混凝土时,在凹槽处打入木楔,为架设钢架留出连接板或槽钢位置,为增强钢架的整体稳定性,将钢架与锚杆焊接在一起;(3)设置纵向连接钢筋、安设钢筋网,纵向每榀型钢拱架之间用φ8@200双层钢筋网连接,内外层交互布置,连接筋应与钢架焊接牢固;(4)喷混凝土固定,钢架架立后尽快喷锚作业,喷射顺序应从下向上对称进行,先喷射钢架与围岩间的空隙,后喷射钢架与钢架间的混凝土,并将钢架全部覆盖,其保护层厚度不得小于40mm,使钢架与喷锚共同受力,喷锚分层进行,每层厚度50~60mm左右,先从拱脚或墙脚处向上喷射以防止上部喷射料虚掩拱脚或墙脚不密实,造成强度不够,拱脚或墙脚失稳。Scheme Further, in the above-mentioned step S4, the construction process of the profiled steel arch is (1) section inspection and measurement and positioning, and the profiled steel arch varies according to the design section; (2) the steel support is assembled, erected in place, and the anchor rod is locked. , the initial support steel frame adopts I20a I-shaped steel, the temporary vertical support and temporary inverted arch use I18 I-shaped steel, the spacing is 0.5m, and the two adjacent steel frames are connected by Φ20 steel bars, and the circumferential spacing of the connecting bars is 0.5m. The channel steel grooves of the steel frame are reserved at the arch foot and the wall feet on both sides to ensure that the arch foot is implemented. When the concrete is initially sprayed, a wooden wedge shall be driven into the groove to leave a connecting plate or channel steel position for the erection of the steel frame. For the overall stability of the steel frame, the steel frame and the anchor rod are welded together; (3) Longitudinal connecting steel bars and steel meshes are installed. Alternately arranged, the connecting bars should be firmly welded with the steel frame; (4) Shotcrete is fixed, and the anchor is shot as soon as possible after the steel frame is erected. The spraying sequence should be symmetrical from the bottom to the top. The gap between the steel frame and the surrounding rock should be sprayed first, and then spray The concrete between the steel frame and the steel frame shall be completely covered with the steel frame, and the thickness of the protective layer shall not be less than 40mm, so that the steel frame and the shotcrete shall be stressed together. The arch foot or wall foot is sprayed upward to prevent the upper spray material from covering the arch foot or the wall foot is not compact, resulting in insufficient strength and instability of the arch foot or wall foot.

方案进一步地,上述初期支护中喷射混凝土采用强度等级C25混凝土,厚度300mm,采用湿喷法施工,喷射用混凝土由搅拌站现场拌制,运输至工作面,通过湿喷机进行喷锚施工,喷射顺序按由下而上先边墙、后拱脚、最后拱顶,喷头成螺旋形缓慢均匀移动,每圈压前面半圈,绕圈直径约30cm,有较大凹洼处,先喷射填平,喷嘴与岩面垂直,距受喷面1.5~2.0m。开挖后及时初喷,出碴后及时复喷;复喷混凝土在锚杆、挂网和钢架安装后进行,尽快形成喷锚支护整体受力,以抑制围岩变化,钢架间用混凝土喷平,并有足够的保护层,喷射混凝土分段、分片由下而上顺序进行,复喷混凝土时,先喷钢架支撑与拱墙壁间混凝土,后喷两拱架之间混凝土。Scheme Further, in the above-mentioned initial support, the shotcrete adopts the strength grade C25 concrete, the thickness is 300mm, and the wet spraying method is used for construction. The spraying sequence is from bottom to top, first the side wall, then the arch foot, and finally the vault. The nozzle moves slowly and evenly in a spiral shape. Each circle presses the front half circle. The diameter of the circle is about 30cm. Flat, the nozzle is perpendicular to the rock surface, 1.5-2.0m away from the sprayed surface. After the excavation, the initial spraying should be carried out in time, and the re-spraying should be carried out in time after the ballast is discharged; The concrete is sprayed flat and has enough protective layer. The sprayed concrete is segmented and segmented sequentially from bottom to top. When re-spraying concrete, the concrete between the steel frame support and the arch wall is sprayed first, and then the concrete between the two arch frames is sprayed.

方案进一步地,上述步骤S6中,拱背注浆,即初期支护施工时,拱部边墙预埋Ф32mm钢焊接作为注浆管,注浆管管长根据衬砌设计要求,一般0.8埋设一排,每排环向间距1m,初期支护封闭成环后,及时用注浆泵压注1:1水泥砂浆,充填初衬背后孔隙。The scheme further, in the above step S6, the back of the arch is grouted, that is, during the initial support construction, the side wall of the arch is pre-buried Ф32mm steel welded as a grouting pipe, and the length of the grouting pipe is generally 0.8 according to the lining design requirements. , The circumferential spacing of each row is 1m. After the initial support is closed into a ring, 1:1 cement mortar is injected with a grouting pump in time to fill the pores behind the initial lining.

本发明的优点是:本发明提出了一种浅埋大断面暗挖矩形隧道施工工法,采取分部开挖、增设临时仰拱、超前大管棚和小导管注浆加固的方法施工,控制了隧道围岩及地表变形,解决了浅埋大断面暗挖矩形隧道围岩变形控制难的问题,为浅埋大断面暗挖矩形隧道施工提供了有效的安全保障。The advantages of the present invention are as follows: the present invention proposes a construction method of shallowly buried large-section underground excavation rectangular tunnels, which adopts the method of sub-excavation, additional temporary inverted arches, advanced large pipe sheds and small pipes for grouting reinforcement, and controls the construction of the tunnel. The deformation of the surrounding rock and the surface of the tunnel solves the problem of difficulty in controlling the deformation of the surrounding rock of the shallow-buried large-section rectangular tunnel, and provides an effective safety guarantee for the construction of the shallow-buried large-section rectangular tunnel.

附图说明Description of drawings

图1是本发明一种浅埋大断面暗挖矩形隧道施工方法的地表注浆加固施工工艺流程图;Fig. 1 is the surface grouting reinforcement construction process flow diagram of a shallow buried large-section undercut rectangular tunnel construction method of the present invention;

图2是本发明一种浅埋大断面暗挖矩形隧道施工方法的超前大管棚施工工艺流程图;Fig. 2 is the construction process flow chart of the advanced large pipe shed construction method of a shallow-buried large-section undercut rectangular tunnel construction method of the present invention;

图3是本发明一种浅埋大断面暗挖矩形隧道施工方法的超前注浆小导管施工工艺流程图;Fig. 3 is the construction process flow chart of the advance grouting small conduit construction method of a shallow buried large-section undercut rectangular tunnel construction method of the present invention;

图4是本发明一种浅埋大断面暗挖矩形隧道施工方法的型钢拱架施工工艺流程图。Fig. 4 is a process flow chart of the construction of a profiled steel arch of a method for constructing a shallow-buried large-section rectangular tunnel according to the present invention.

具体实施方式Detailed ways

下面结合附图对本发明做清楚完整的描述,以使本领域的技术人员在不需要作出创造性劳动的条件下,能够充分实施本发明。The present invention will be clearly and completely described below with reference to the accompanying drawings, so that those skilled in the art can fully implement the present invention without creative work.

本发明的具体实施方式是:如图1-4所示,一种浅埋大断面暗挖矩形隧道施工方法,其主要施工步骤如下:The specific embodiment of the present invention is: as shown in Figure 1-4, a kind of shallow buried large section undercut rectangular tunnel construction method, its main construction steps are as follows:

S1:暗挖段隧道采用CRD法施工,施工前对暗挖区域进行全面降水处理,将地下水位降至基坑开挖面以下0.5m;S1: The CRD method is adopted for the construction of the undercut section of the tunnel. Before construction, the undercut area is fully dewatered, and the groundwater level is lowered to 0.5m below the excavation surface of the foundation pit;

S2:地表破碎岩层注浆加固,防止开挖施工过程中引起周边地面变形破坏,具体过程包括(1)钻孔定位:现场清理完毕后,根据复核过的控制点,测设定位轴线进行桩位放样,样桩尺寸应符合设计施工要求,允许偏差控制在10mm以内;(2)钻机就位:钻机进场调试完成后,安装就位,精心调平,并支撑牢固,确保施工中不发生倾斜,移位;(3)钻机钻进:钻机就位,调平设备,进行钻进,钻进到位后,安装钢管,钢管加工由加工厂内加工完毕后,运输到现场进行安装,无缝钢管两端应加工15cm长的丝扣,在钢管上每隔10cm加工A10mm的泄浆孔,成梅花型布置,按照桩长情况,为了使相邻两桩在同一垂直面上的接头不超过总管数的50%;(4)清孔:注浆前先冲洗无缝钢管内杂物,再将注浆管插入孔底;(5)注浆:由下往上顺序注浆,直至浆液从无缝钢管顶口流出浓浆为止;S2: Grout reinforcement of the broken rock layer on the surface to prevent the surrounding ground from being deformed and damaged during the excavation construction. The specific process includes (1) Drilling positioning: After the site is cleaned, according to the reviewed control points, measure the positioning axis to carry out the pile The size of the sample pile should meet the design and construction requirements, and the allowable deviation should be controlled within 10mm; (2) The drilling rig is in place: After the drilling rig is commissioned, it is installed in place, carefully leveled, and supported firmly to ensure that it does not occur during construction. Inclination, displacement; (3) Drilling of the drilling rig: the drilling rig is in place, the equipment is leveled, and the drilling is carried out. After the drilling is in place, the steel pipe is installed. After the steel pipe is processed in the processing plant, it is transported to the site for installation. Both ends of the steel pipe should be processed with 15cm long threads, and A10mm slush holes should be machined on the steel pipe every 10cm to form a plum-shaped arrangement. According to the length of the piles, in order to make the joints of two adjacent piles on the same vertical plane not exceed the main pipe 50% of the number of holes; (4) hole cleaning: flush the debris in the seamless steel pipe before grouting, and then insert the grouting pipe into the bottom of the hole; (5) grouting: sequentially grouting from bottom to top until the grout is completely free of until the thick slurry flows out from the top of the seamed steel pipe;

S3:采用超前大管棚、超前注浆小导管进行超前支护;S3: The advanced large pipe shed and the advanced grouting small pipe are used for advanced support;

S4:暗挖段在开挖或分部开挖完成后立即进行初喷,及时封闭围岩暴露面,型钢拱架、锚杆和钢筋网支护与开挖循环进尺协同进行;S4: The initial spraying is carried out immediately after the excavation or sub-excavation is completed in the underground excavation section, and the exposed surface of the surrounding rock is closed in time, and the support of profiled steel arches, bolts and steel mesh is carried out in coordination with the excavation cycle footage;

S5:待型钢拱架、锚杆和钢筋网支护完成后及时复喷混凝土;S5: Re-spray concrete in time after the steel arch, anchor rod and steel mesh support are completed;

S6:初期支护后及时对拱背空隙进行注浆,防止拱部留有空隙,使支护与围岩分析。S6: After the initial support, grouting should be carried out to the back of the arch in time to prevent the arch from leaving a gap, so that the support and surrounding rock can be analyzed.

本发明进一步地,上述步骤S1中,出入口降水采用大口径管井降水,在基坑内井点按8~12m间距设置,井管直径为0.8m,降水井钢管插入深度低于基坑底不小于5m。Further, in the above step S1, large-diameter pipe wells are used for dewatering at the entrance and exit, and the well points in the foundation pit are arranged at an interval of 8 to 12m, the diameter of the well pipe is 0.8m, and the depth of the pipe in the dewatering well is not less than 5m below the bottom of the foundation pit. .

本发明进一步地,上述步骤S2中,注浆范围为开挖轮廓线外2m,注浆工艺采用袖阀管注浆加固,旋喷桩内插Φ108钢管,钢管深入到基底下2m,注浆加固采用水泥-水玻璃双液浆,水灰比1:1,注浆压力1.0 MPa-2.0 MPa。The present invention further, in the above step S2, the grouting range is 2m outside the excavation contour line, the grouting process adopts the sleeve valve pipe grouting reinforcement, the rotary jet pile is inserted into the Φ108 steel pipe, the steel pipe is deep into the base 2m, grouting reinforcement Cement-water glass double slurry is adopted, the water-cement ratio is 1:1, and the grouting pressure is 1.0 MPa-2.0 MPa.

本发明进一步地,上述步骤S3中,超前大管棚的施工过程包括(1)测量放线;(2)休整管棚操作平台,大管棚采用Ф108mm热轧无缝钢管,壁厚9mm,节长4m或6m,倾角向上<2°,钢管管壁四周钻Ф10-16mm注浆孔,钻孔沿管壁间隔150mm,呈梅花型布设,孔位互成90°,尾部预留1.5m的无孔止浆段;管中增设钢筋笼,以提高导管的抗弯能力,钢筋笼由四根主筋和固定环组成,大管棚环向间距40cm;(3)钻机就位进行钻孔,根据地质条件和施工条件,采用一台潜孔钻机进行作业,施工顺序根据基坑开挖顺序进行施工,钻孔时钻机距工作面距离一般情况下不少于2m,同时钻孔以风动潜孔冲击钻进法为主,辅以合金管钻,钻孔直径150mm,环向间距40cm,用φ108mm岩芯管进行扫孔,岩芯管长度不小于3m为宜,同时借助高压空气吹洗,直到孔内清扫干净,φ108mm钢管管壁打孔,孔径为10-16mm,孔间距150mm,呈梅花型布设,孔位互成90°,导管尾部留不钻孔的止浆段;(4)顶进管棚,为使钢管接头错开,加工钢管时将钢管进行钢节编号,下管时,当孔壁不易坍塌时,采用直接撞击法将导管撞击至设计位置,当孔壁容易坍塌时,用导管与钻头同时钻进的方法,为使钢管接头错开,为方便施工编号为奇数的第一节管采用4m管,编号为偶数的第一节管采用6m钢管,以后每节均采用6m长钢管,如钢管顶进遇到故障,顶不进时,查清原因,必要时重新扫孔后再将钢管顶进;(5)综合检查合格后进行注浆,注浆完成后进行检测,采用一次全钻孔注浆,管棚注浆达到浆液扩散半径不小于0.5m,根据岩石情况选定注浆方式,注浆采用水泥浆,水泥浆水灰比1:1,注浆压力:初压0.5~1MPa,终压2MPa,注浆前应先进行注浆现场试验,注浆参数应通过现场试验按实际情况进行调整,如地下水较大,可采用水泥-水玻璃浆液。注浆前将管棚钢管口用10mm钢板做出钢管堵头,与管棚钢管口焊接,堵头口烧孔焊接注浆管,注浆管丝扣上安装注浆阀门。在钢花管中沿管壁安设φ15mm的塑料硬管至孔底,在管口(外端)处与注浆管上焊接钢管,作为排气孔(安设注浆阀门)。注浆采用从孔口一次注入,为使管内浆液饱满密实,注浆时等排气孔有浆液流出,进行终压注浆,直至达到设计注浆压力或设计注浆量时终止。后闭其阀门。The present invention further, in the above step S3, the construction process of the advanced large pipe shed includes (1) measuring and laying out the line; (2) resting and adjusting the operating platform of the pipe shed. Length 4m or 6m, the inclination angle is upwards <2°, grouting holes of Ф10-16mm are drilled around the pipe wall of the steel pipe, and the drill holes are arranged at intervals of 150mm along the pipe wall in a plum-shaped arrangement. Slurry-stopping section of the hole; a steel cage is added in the pipe to improve the bending resistance of the conduit. The steel cage is composed of four main bars and a fixed ring, and the circumferential spacing of the large pipe shed is 40cm; (3) The drilling rig is in place to drill, according to the geological Conditions and construction conditions, a down-the-hole drilling rig is used for the operation. The construction sequence is carried out according to the excavation sequence of the foundation pit. The distance between the drilling rig and the working face is generally not less than 2m when drilling, and the drilling is impacted by pneumatic down-the-hole drilling. Drilling method is the main method, supplemented by alloy tube drill, the diameter of the drill hole is 150mm, the circumferential spacing is 40cm, and the core tube is used to sweep the hole. The length of the core tube is not less than 3m. The inside is cleaned and the pipe wall of φ108mm steel pipe is perforated, the hole diameter is 10-16mm, and the hole spacing is 150mm. Shed, in order to stagger the steel pipe joints, the steel pipe is numbered when processing the steel pipe. When the pipe is down, when the hole wall is not easy to collapse, the direct impact method is used to hit the pipe to the design position. When the hole wall is easy to collapse, use the pipe to In the method of drilling at the same time, in order to stagger the steel pipe joints, for the convenience of construction, the first pipe with an odd number uses a 4m pipe, the first pipe with an even number uses a 6m steel pipe, and each subsequent pipe uses a 6m long steel pipe. If there is a failure in the jacking of the steel pipe, if the jacking fails, find out the reason, and if necessary, re-scan the hole and then jack the steel pipe; (5) After the comprehensive inspection is qualified, grouting is carried out, and the inspection is carried out after the grouting is completed, and a full drilling is adopted. Hole grouting, pipe shed grouting to reach a slurry diffusion radius of not less than 0.5m, grouting method is selected according to rock conditions, grouting adopts cement slurry, cement slurry water-cement ratio 1:1, grouting pressure: initial pressure 0.5 ~ 1MPa , the final pressure is 2MPa, and the grouting field test should be carried out before grouting. The grouting parameters should be adjusted according to the actual situation through the field test. If the groundwater is large, cement-water glass slurry can be used. Before grouting, use 10mm steel plate to make a steel pipe plug at the pipe shed, weld it with the pipe shed, burn the hole to weld the grouting pipe, and install a grouting valve on the grouting pipe thread. Install a φ15mm plastic hard pipe along the pipe wall in the steel flower pipe to the bottom of the hole, and weld the steel pipe at the nozzle (outer end) and the grouting pipe as an exhaust hole (install a grouting valve). The grouting adopts one injection from the orifice. In order to make the slurry in the pipe full and dense, the final pressure grouting shall be carried out until the design grouting pressure or design grouting volume is reached. Close its valve.

本发明进一步地,上述步骤S3中,超前注浆小导管的施工过程包括(1)测量导管孔位,暗挖段拱部范围内设计超前注浆小导管,环向间距30cm,小导管外倾角10~15°,纵向水平搭接长度1m,注浆管一端做成锥头,另一端焊上铁箍;(2)钻孔,在距离铁箍1.0m处开始钻孔,钻孔沿管壁间隔150mm,呈梅花型布设,孔位互成90°,孔径8mm,可直接采用风钻顶进;(3)安设导管,用风钻将小导管顶入,导管尾端外露足够长度,尾部与钢架焊接在一起;(4)喷射混凝土封闭注浆面;(5)导管注浆,注浆浆液采用水泥-水玻璃双液浆,注浆压力拟定0.4~0.6MPa。The present invention further, in the above step S3, the construction process of the advance grouting small conduit includes (1) measuring the hole position of the conduit, designing the advance grouting small conduit within the arch of the undercut section, the circumferential spacing is 30cm, and the camber angle of the small conduit is 30 cm. 10 ~ 15°, the longitudinal and horizontal lap length is 1m, one end of the grouting pipe is made into a cone head, and the other end is welded with an iron hoop; (2) Drilling, start drilling at a distance of 1.0m from the iron hoop, and drill along the pipe wall The spacing is 150mm, and it is arranged in a plum blossom shape. The holes are 90° to each other, and the hole diameter is 8mm. It can be directly jacked with a pneumatic drill; (3) Install a guide pipe, use a pneumatic drill to push the small guide pipe, and the tail end of the guide pipe is exposed for a sufficient length. (4) Shotcrete closed grouting surface; (5) Pipe grouting, the grouting slurry adopts cement-water glass double-liquid slurry, and the grouting pressure is proposed to be 0.4-0.6MPa.

本发明进一步地,上述步骤S4中,型钢拱架的施工过程是(1)断面检查和测量定位,型钢拱架根据设计断面不同而异;(2)钢支撑拼装、架立就位、锚杆锁定,初支钢架采用I20a工字型钢,临时竖撑及临时仰拱采用I18工字型钢,间距0.5m,相邻两榀钢架间均采用Φ20钢筋连接,连接筋环向间距0.5m,两拱脚处和两边墙脚处预留安装钢架槽钢凹槽确保拱脚落实,初喷混凝土时,在凹槽处打入木楔,为架设钢架留出连接板或槽钢位置,为增强钢架的整体稳定性,将钢架与锚杆焊接在一起;(3)设置纵向连接钢筋、安设钢筋网,纵向每榀型钢拱架之间用φ8@200双层钢筋网连接,内外层交互布置,连接筋应与钢架焊接牢固;(4)喷混凝土固定,钢架架立后尽快喷锚作业,喷射顺序应从下向上对称进行,先喷射钢架与围岩间的空隙,后喷射钢架与钢架间的混凝土,并将钢架全部覆盖,其保护层厚度不得小于40mm,使钢架与喷锚共同受力,喷锚分层进行,每层厚度50~60mm左右,先从拱脚或墙脚处向上喷射以防止上部喷射料虚掩拱脚或墙脚不密实,造成强度不够,拱脚或墙脚失稳。The present invention further, in the above-mentioned step S4, the construction process of the profiled steel arch is (1) section inspection and measurement and positioning, and the profiled steel arch varies according to the design section; (2) the steel support assembly, erection, anchor rod Locked, I20a I-beam steel is used for the initial support steel frame, I18 I-beam steel is used for the temporary vertical support and temporary inverted arch, and the spacing is 0.5m. The two adjacent steel frames are connected by Φ20 steel bars, and the circumferential spacing of the connecting bars is 0.5m. The channel steel grooves of the steel frame are reserved at the two arch feet and the wall feet on both sides to ensure that the arch feet are implemented. When the concrete is initially sprayed, a wooden wedge shall be driven into the groove, and the connecting plate or channel steel position shall be reserved for the erection of the steel frame. Strengthen the overall stability of the steel frame, and weld the steel frame and the anchor rod together; (3) Set up longitudinal connecting steel bars and install steel mesh, and connect each longitudinal steel arch with a φ8@200 double-layer steel mesh. The layers are arranged alternately, and the connecting bars should be firmly welded to the steel frame; (4) Shotcrete is fixed, and the anchors are shot as soon as possible after the steel frame is erected. The spraying sequence should be symmetrical from the bottom to the top. Spray the concrete between the steel frame and the steel frame, and cover the steel frame completely. Spray upward from the arch foot or wall foot to prevent the upper spray material from concealing the arch foot or the wall foot is not dense, resulting in insufficient strength and instability of the arch foot or wall foot.

本发明进一步地,上述初期支护中喷射混凝土采用强度等级C25混凝土,厚度300mm,采用湿喷法施工,喷射用混凝土由搅拌站现场拌制,运输至工作面,通过湿喷机进行喷锚施工,喷射顺序按由下而上先边墙、后拱脚、最后拱顶,喷头成螺旋形缓慢均匀移动,每圈压前面半圈,绕圈直径约30cm,有较大凹洼处,先喷射填平,喷嘴与岩面垂直,距受喷面1.5~2.0m。开挖后及时初喷,出碴后及时复喷;复喷混凝土在锚杆、挂网和钢架安装后进行,尽快形成喷锚支护整体受力,以抑制围岩变化,钢架间用混凝土喷平,并有足够的保护层,喷射混凝土分段、分片由下而上顺序进行,复喷混凝土时,先喷钢架支撑与拱墙壁间混凝土,后喷两拱架之间混凝土。Further, in the above-mentioned initial support, the shotcrete adopts the strength grade C25 concrete, the thickness is 300mm, and the wet spraying method is used for construction. , the spraying sequence is from bottom to top, first the side wall, then the arch foot, and finally the vault. The nozzle moves slowly and evenly in a spiral shape. Each circle presses the front half circle. The diameter of the circle is about 30cm. If there are large depressions, spray first. Fill and level, the nozzle is perpendicular to the rock surface, and the distance from the spray surface is 1.5 to 2.0m. After the excavation, the initial spraying should be carried out in time, and the re-spraying should be carried out in time after the ballast is discharged; The concrete is sprayed flat and has enough protective layer. The sprayed concrete is segmented and segmented sequentially from bottom to top. When re-spraying concrete, the concrete between the steel frame support and the arch wall is sprayed first, and then the concrete between the two arch frames is sprayed.

本发明进一步地,上述步骤S6中,拱背注浆,即初期支护施工时,拱部边墙预埋Ф32mm钢焊接作为注浆管,注浆管管长根据衬砌设计要求,一般0.8埋设一排,每排环向间距1m,初期支护封闭成环后,及时用注浆泵压注1:1水泥砂浆,充填初衬背后孔隙。The present invention further, in the above step S6, the back of the arch is grouted, that is, during the initial support construction, the side wall of the arch is pre-buried Ф32mm steel welded as a grouting pipe, and the length of the grouting pipe is generally 0.8 according to the lining design requirements. The circumferential spacing of each row is 1m. After the initial support is closed into a ring, 1:1 cement mortar is injected with a grouting pump in time to fill the pores behind the initial lining.

以上对本发明的较佳实施例进行了描述,需要指出的是,本发明并不局限于上述特定实施方式,其中未尽详细描述的设备和结构应该理解为用本领域中的普通方式予以实施;任何熟悉本领域的技术人员,在不脱离本发明技术方案范围情况下,依据本发明的技术实质对以上实施例所做的任何简单修改、等同变化及修饰,均仍属于本发明技术方案保护的范围内。The preferred embodiments of the present invention have been described above. It should be pointed out that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures not described in detail should be understood as being implemented in ordinary ways in the art; Any person skilled in the art, without departing from the scope of the technical solution of the present invention, any simple modifications, equivalent changes and modifications made to the above embodiments according to the technical essence of the present invention still belong to the protection of the technical solution of the present invention. within the range.

Claims (8)

1. A construction method of a shallow-buried large-section underground rectangular tunnel is characterized by comprising the following main construction steps:
s1: constructing the tunnel at the underground excavation section by adopting a CRD method, carrying out comprehensive precipitation treatment on an underground excavation area before construction, and reducing the underground water level to 0.5m below the excavation surface of the foundation pit;
s2: broken rock stratum slip casting of earth's surface is consolidated, prevents to arouse among the excavation work progress that peripheral ground warp to destroy, and concrete process includes (1) drilling location: after the on-site cleaning is finished, according to the rechecked control points, measuring and setting a positioning axis to perform pile position lofting, wherein the size of a pile of the loft is required to meet the design and construction requirements, and the allowable deviation is controlled within 10 mm; (2) positioning a drilling machine: after the drilling machine enters a field and is debugged, the drilling machine is installed in place, carefully leveled and firmly supported, so that the drilling machine is ensured not to incline or shift in construction; (3) drilling by a drilling machine: the drilling machine is in place, equipment is leveled, drilling is carried out, steel pipes are installed after the drilling is in place, and the steel pipes are transported to the site for installation after being processed in a processing factory; (4) hole cleaning: before grouting, washing impurities in the seamless steel pipe, and inserting the grouting pipe into the bottom of the hole; (5) grouting: sequentially grouting from bottom to top until thick slurry flows out of the top opening of the seamless steel pipe;
s3: an advanced large pipe shed and an advanced grouting small pipe are adopted for advanced support;
s4: the underground excavation section immediately carries out primary spraying after the excavation or the subsection excavation is finished, the exposed surface of the surrounding rock is closed in time, and the support of the profile steel arch frame, the anchor rod and the reinforcing mesh is carried out in cooperation with the excavation circulation footage;
s5: after the steel arch frame, the anchor rod and the reinforcing mesh are supported, concrete is sprayed again in time;
s6: grouting the arch back gap in time after primary support to prevent gaps from being left in the arch part, so that support and surrounding rock analysis are realized.
2. The method for constructing a shallow-buried large-section underground rectangular tunnel according to claim 1, wherein in step S1, the precipitation at the entrance and exit is large-diameter well precipitation, the well points in the foundation pit are arranged at intervals of 8-12 m, the diameter of the well pipe is 0.8m, and the insertion depth of the precipitation well steel pipe is not less than 5m lower than the bottom of the foundation pit.
3. The method for constructing a shallow-buried large-section underground rectangular tunnel according to claim 1, wherein in the step S2, the grouting range is 2m outside the excavation contour line, the grouting process adopts sleeve valve pipe grouting reinforcement, a phi 108 steel pipe is inserted into a jet grouting pile, the steel pipe extends to 2m below the basement, the grouting reinforcement adopts cement-water glass double-liquid cement, the water cement ratio is 1: 1, grouting pressure is 1.0 MPa-2.0 MPa.
4. The method for constructing a shallow-buried large-section underground rectangular tunnel according to claim 1, wherein in the step S3, the construction process of the advanced large pipe shed includes (1) measuring and setting-out; (2) laying down a pipe shed operating platform; (3) the drilling machine is in place to drill holes, a down-the-hole drilling machine is adopted to operate according to geological conditions and construction conditions, and construction is carried out according to the foundation pit excavation sequence in the construction sequence; (4) jacking a pipe shed, numbering steel joints of the steel pipes when the steel pipes are processed in order to stagger the joints of the steel pipes, adopting a direct impact method to impact a conduit to a designed position when the wall of the hole is not easy to collapse during pipe descending, and simultaneously drilling the conduit and a drill bit when the wall of the hole is easy to collapse; (5) carry out the slip casting after the comprehensive inspection is qualified, detect after the slip casting is accomplished, adopt a full drilling slip casting, the pipe roof slip casting reaches the grout diffusion radius and is not less than 0.5m, select the slip casting mode according to the rock condition, the slip casting adopts the grout, grout water cement ratio 1: 1, grouting pressure: the initial pressure is 0.5-1 MPa, the final pressure is 2MPa, a grouting field test is performed before grouting, and grouting parameters are adjusted according to actual conditions through the field test.
5. The method for constructing a shallow-buried large-section underground excavation rectangular tunnel according to claim 1, wherein in the step S3, the construction process of the small advanced grouting pipes comprises (1) measuring pipe hole positions, designing the small advanced grouting pipes within the arch part of the underground excavation section, wherein the circumferential distance is 30cm, the camber angle of the small pipes is 10-15 degrees, the longitudinal horizontal lap joint length is 1m, one end of each grouting pipe is made into a conical head, and an iron hoop is welded at the other end; (2) drilling, namely, drilling at a position 1.0m away from the iron hoop, wherein the drill holes are distributed at intervals of 150mm along the pipe wall in a quincunx manner, the hole positions mutually form 90 degrees, the hole diameter is 8mm, and the drill holes can be directly jacked by a wind drill; (3) installing a guide pipe, jacking the small guide pipe by using an air drill, exposing the tail end of the guide pipe for a sufficient length, and welding the tail end of the guide pipe and the steel frame together; (4) spraying concrete to close the grouting surface; (5) and (3) grouting by using a guide pipe, wherein the grouting slurry is cement-water glass double-liquid slurry, and the grouting pressure is set to be 0.4-0.6 MPa.
6. The method for constructing a shallow-buried large-section underground rectangular tunnel according to claim 1, wherein in the step S4, the construction process of the steel arch is (1) section inspection and measurement positioning, and the steel arch is different according to the design section; (2) the steel supports are assembled, erected in place and locked by anchor rods, the primary support steel frames adopt I20a I-shaped steel, the temporary vertical supports and the temporary inverted arches adopt I18I-shaped steel, the distance is 0.5m, two adjacent steel frames are connected by phi 20 steel bars, the circumferential distance of connecting ribs is 0.5m, grooves for mounting steel frame channel steel are reserved at two arch feet and two side wall feet to ensure the arch feet to be solid, wood wedges are driven into the grooves when concrete is sprayed for the first time, connecting plates or channel steel positions are reserved for erecting the steel frames, and the steel frames and the anchor rods are welded together for enhancing the overall stability of the steel frames; (3) arranging longitudinal connecting steel bars and installing steel bar nets, wherein each longitudinal steel arch truss is connected by a phi 8@200 double-layer steel bar net, the inner layer and the outer layer are arranged alternately, and the connecting steel bars are firmly welded with the steel frame; (4) the concrete spraying is fixed, the anchor spraying operation is carried out as soon as possible after the steel frame is erected, the spraying sequence is carried out symmetrically from bottom to top, a gap between the steel frame and surrounding rocks is sprayed firstly, the concrete between the steel frame and the steel frame is sprayed later, the steel frame is covered completely, the thickness of a protective layer of the protective layer is not smaller than 40mm, the steel frame and the spray anchor are stressed together, the spray anchors are carried out in a layered mode, the thickness of each layer is about 50-60 mm, the spray anchors are sprayed upwards from the arch springing or the wall springing position firstly to prevent the upper spray material from covering the arch springing or the wall springing loosely, the strength is insufficient, and the arch spring.
7. The method for constructing a shallow-buried large-section underground excavation rectangular tunnel according to claim 1, wherein the sprayed concrete in the primary support is strength grade C25 concrete with the thickness of 300mm, the construction is performed by a wet spraying method, the sprayed concrete is mixed at the site by a mixing station, transported to a working surface, and subjected to spray anchor construction by a wet spraying machine, the spraying heads slowly and uniformly move in a spiral shape from bottom to top in the sequence of first side wall, rear arch foot and last arch top, each circle presses the front half circle, the diameter of each circle is about 30cm, a large concave part is formed, the sprayed concrete is firstly sprayed and filled, the spraying nozzles are perpendicular to the rock surface and 1.5-2.0 m away from the sprayed surface, the concrete is sprayed in time after excavation, and the concrete is sprayed again in time after slag is discharged; the re-spraying concrete is carried out after the anchor rods, the hanging net and the steel frames are installed, the whole stress of the anchor spraying support is formed as soon as possible to inhibit the change of surrounding rocks, the steel frames are sprayed with the concrete and are leveled by the concrete, enough protective layers are arranged, the concrete spraying is carried out in a segmentation and fragmentation mode from bottom to top, when the re-spraying concrete is carried out, the concrete between the steel frame support and the arch wall is sprayed firstly, and then the concrete between the two arch frames is sprayed.
8. The method for constructing a shallow-buried large-section underground rectangular tunnel according to claim 1, wherein in the step S6, arch back grouting, that is, during primary support construction, the pre-buried Φ 32mm steel of the arch side wall is welded as a grouting pipe, the length of the grouting pipe is generally embedded in one row according to the lining design requirement, 0.8, and the circumferential distance of each row is 1m, and after the primary support is closed into a ring, the grouting pump is used for grouting in time 1: 1 cement mortar, filling the pores after primary backing.
CN202010829595.7A 2020-08-18 2020-08-18 A construction method for shallowly buried large-section undercut rectangular tunnel Pending CN111997624A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010829595.7A CN111997624A (en) 2020-08-18 2020-08-18 A construction method for shallowly buried large-section undercut rectangular tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010829595.7A CN111997624A (en) 2020-08-18 2020-08-18 A construction method for shallowly buried large-section undercut rectangular tunnel

Publications (1)

Publication Number Publication Date
CN111997624A true CN111997624A (en) 2020-11-27

Family

ID=73473905

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010829595.7A Pending CN111997624A (en) 2020-08-18 2020-08-18 A construction method for shallowly buried large-section undercut rectangular tunnel

Country Status (1)

Country Link
CN (1) CN111997624A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112502746A (en) * 2020-12-17 2021-03-16 安徽省路桥工程集团有限责任公司 Shallow-buried underground excavation tunnel excavation supporting system and construction method
CN112663625A (en) * 2020-12-29 2021-04-16 哈尔滨工业大学 Construction and protection method for shallow-buried bias-pressure weak surrounding rock tunnel portal in alpine region
CN112855172A (en) * 2021-01-14 2021-05-28 中铁二十局集团第三工程有限公司 Tunnel advanced support structure and construction method
CN112963156A (en) * 2021-03-19 2021-06-15 华侨大学 Composite reinforcing method and composite reinforcing structure for shallow tunnel in soil-rock composite stratum
CN113803077A (en) * 2021-11-18 2021-12-17 中铁九局集团第七工程有限公司 Advanced support construction method for horizontal joint argillaceous shale water-rich tunnel
CN113931691A (en) * 2021-09-30 2022-01-14 中国一冶集团有限公司 Treatment method for tunnel broken zone side wall after water inrush
CN114086982A (en) * 2021-11-02 2022-02-25 中铁十九局集团第六工程有限公司 Construction control method of high in-situ stress fracture surrounding rock deformation
CN114109436A (en) * 2021-12-01 2022-03-01 中铁二局集团有限公司 Large-span underground excavation construction method for subway station
CN114251109A (en) * 2021-12-25 2022-03-29 中铁二局集团有限公司 Construction method for karst tunnel earth-rock binary structure
CN115126491A (en) * 2022-06-30 2022-09-30 中水电四局南方(珠海)工程有限公司 Rectangular large-section shallow-buried underground tunnel excavation method
CN116295230A (en) * 2023-02-17 2023-06-23 中国矿业大学 An Intelligent Monitoring System for Deformation of Weak Surrounding Rock in Shallow Buried Large Section Tunnel
CN116607948A (en) * 2023-05-23 2023-08-18 中电建十一局工程有限公司 Construction method for supporting pipe shed for rectangular pipe-jacking construction with oversized section
CN119641308A (en) * 2025-02-20 2025-03-18 中交第一公路勘察设计研究院有限公司 Underground engineering surrounding rock directional drilling slotting method based on stress transfer
CN119686747A (en) * 2024-11-26 2025-03-25 中国交通建设股份有限公司轨道交通分公司 Underground tunnel construction technology by mining method of shallow buried backfill layer of subway in urban complex environment
CN119981909A (en) * 2025-01-09 2025-05-13 中铁隧道局集团有限公司 Construction method of culvert dark excavation under backfill roadbed condition

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104452767A (en) * 2014-10-14 2015-03-25 中铁四局集团有限公司 Construction technology for waste slurry treatment of bored piles in karst areas
CN108166981A (en) * 2017-12-31 2018-06-15 中铁十九局集团第二工程有限公司 Tunnel soft rock large deformation section construction technology
CN108643935A (en) * 2018-04-27 2018-10-12 中铁六局集团天津铁路建设有限公司 The construction method in tunnel under rich water shallow embedding geology
CN108797598A (en) * 2018-07-09 2018-11-13 江苏地基工程有限公司 The construction technology of pre-loaded support struts in a kind of deep basal pit
CN110805029A (en) * 2019-11-12 2020-02-18 北京石油化工学院 Subway underground-excavated station drilling and grouting fender post construction method
CN111287759A (en) * 2020-02-12 2020-06-16 中铁五局集团有限公司 A kind of construction method of shallow buried close-cut tunnel
CN111502674A (en) * 2020-04-24 2020-08-07 中国十九冶集团有限公司 Advanced support structure and construction method for shallow-buried underground tunnel in water-rich and impurity-filled soil area

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104452767A (en) * 2014-10-14 2015-03-25 中铁四局集团有限公司 Construction technology for waste slurry treatment of bored piles in karst areas
CN108166981A (en) * 2017-12-31 2018-06-15 中铁十九局集团第二工程有限公司 Tunnel soft rock large deformation section construction technology
CN108643935A (en) * 2018-04-27 2018-10-12 中铁六局集团天津铁路建设有限公司 The construction method in tunnel under rich water shallow embedding geology
CN108797598A (en) * 2018-07-09 2018-11-13 江苏地基工程有限公司 The construction technology of pre-loaded support struts in a kind of deep basal pit
CN110805029A (en) * 2019-11-12 2020-02-18 北京石油化工学院 Subway underground-excavated station drilling and grouting fender post construction method
CN111287759A (en) * 2020-02-12 2020-06-16 中铁五局集团有限公司 A kind of construction method of shallow buried close-cut tunnel
CN111502674A (en) * 2020-04-24 2020-08-07 中国十九冶集团有限公司 Advanced support structure and construction method for shallow-buried underground tunnel in water-rich and impurity-filled soil area

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李慧民等: "《穿越既有结构施工安全控制技术》", 冶金工业出版社 *

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112502746A (en) * 2020-12-17 2021-03-16 安徽省路桥工程集团有限责任公司 Shallow-buried underground excavation tunnel excavation supporting system and construction method
CN112663625A (en) * 2020-12-29 2021-04-16 哈尔滨工业大学 Construction and protection method for shallow-buried bias-pressure weak surrounding rock tunnel portal in alpine region
CN112855172A (en) * 2021-01-14 2021-05-28 中铁二十局集团第三工程有限公司 Tunnel advanced support structure and construction method
CN112963156A (en) * 2021-03-19 2021-06-15 华侨大学 Composite reinforcing method and composite reinforcing structure for shallow tunnel in soil-rock composite stratum
CN113931691A (en) * 2021-09-30 2022-01-14 中国一冶集团有限公司 Treatment method for tunnel broken zone side wall after water inrush
CN114086982A (en) * 2021-11-02 2022-02-25 中铁十九局集团第六工程有限公司 Construction control method of high in-situ stress fracture surrounding rock deformation
CN113803077A (en) * 2021-11-18 2021-12-17 中铁九局集团第七工程有限公司 Advanced support construction method for horizontal joint argillaceous shale water-rich tunnel
CN114109436A (en) * 2021-12-01 2022-03-01 中铁二局集团有限公司 Large-span underground excavation construction method for subway station
CN114251109A (en) * 2021-12-25 2022-03-29 中铁二局集团有限公司 Construction method for karst tunnel earth-rock binary structure
CN115126491A (en) * 2022-06-30 2022-09-30 中水电四局南方(珠海)工程有限公司 Rectangular large-section shallow-buried underground tunnel excavation method
CN116295230A (en) * 2023-02-17 2023-06-23 中国矿业大学 An Intelligent Monitoring System for Deformation of Weak Surrounding Rock in Shallow Buried Large Section Tunnel
CN116295230B (en) * 2023-02-17 2024-12-27 中国矿业大学 An intelligent monitoring system for soft surrounding rock deformation in shallow large-section tunnels
CN116607948A (en) * 2023-05-23 2023-08-18 中电建十一局工程有限公司 Construction method for supporting pipe shed for rectangular pipe-jacking construction with oversized section
CN119686747A (en) * 2024-11-26 2025-03-25 中国交通建设股份有限公司轨道交通分公司 Underground tunnel construction technology by mining method of shallow buried backfill layer of subway in urban complex environment
CN119981909A (en) * 2025-01-09 2025-05-13 中铁隧道局集团有限公司 Construction method of culvert dark excavation under backfill roadbed condition
CN119641308A (en) * 2025-02-20 2025-03-18 中交第一公路勘察设计研究院有限公司 Underground engineering surrounding rock directional drilling slotting method based on stress transfer

Similar Documents

Publication Publication Date Title
CN111997624A (en) A construction method for shallowly buried large-section undercut rectangular tunnel
JP7257086B2 (en) Comprehensive Construction Method for Low Overburden Sections of Tunnels
CN110056369B (en) Construction method for entrance and exit hole of tunnel
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN104818991B (en) A kind of construction method in Shallow-buried residual soil slope tunnel
CN112663625A (en) Construction and protection method for shallow-buried bias-pressure weak surrounding rock tunnel portal in alpine region
CN109538246B (en) Arch foot reinforcement structure and construction method of underground subway station with arch cover method
WO2020259059A1 (en) Tbm parallel heading tunnel trunk construction method
CN110195604B (en) Construction method for tunnel main tunnel TBM (tunnel boring machine) tunneling section
CN101929340A (en) Pre-grouting advance support construction process for pipe shed of underground flat inclined roadway of coal mine
CN205172598U (en) Pipe curtain spouts a supporting construction soon
CN111206937A (en) Pile group construction method for removing intruding main body structure in shield interval
CN113153355B (en) A kind of advanced pipe curtain construction method for underpassing tunnels
CN110566223B (en) Deep-buried PBA subway station section design method
CN105370289B (en) A kind of existing pipeline overlength Dryopteris sublaetaChing et Hsu method of complex environment
CN111287759A (en) A kind of construction method of shallow buried close-cut tunnel
CN114370288A (en) A kind of strengthening device and construction method for initial support collapse treatment of highway tunnel
CN116816397A (en) A construction method for ultra-shallow burial and long-span underground excavation subway stations
CN119122545A (en) A rapid construction method for close connection of urban large-section ultra-shallow buried tunnels
CN114086968B (en) Construction method for undermining existing building undercut tunnel
CN119435012B (en) A method for concealed excavation of a three-layer six-hole subway station
CN115749842A (en) Construction method for semi-bright and semi-dark tunnel entrance of bias tunnel
CN209523759U (en) A super shallow buried tunnel structure
CN119195810A (en) A large-section cavern arch support structure for underground water-sealed caverns and its construction method
CN119333172A (en) A shallow tunnel construction method under residual geological conditions

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201127