CN111472812A - Construction method for filling and pouring concrete into inverted arch of tunnel - Google Patents

Construction method for filling and pouring concrete into inverted arch of tunnel Download PDF

Info

Publication number
CN111472812A
CN111472812A CN202010333338.4A CN202010333338A CN111472812A CN 111472812 A CN111472812 A CN 111472812A CN 202010333338 A CN202010333338 A CN 202010333338A CN 111472812 A CN111472812 A CN 111472812A
Authority
CN
China
Prior art keywords
concrete
inverted arch
construction
filling
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010333338.4A
Other languages
Chinese (zh)
Inventor
熊卫士
张庆明
王青松
杨帆
周波
唐益强
尹芃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Communications Construction Group Co Ltd
Original Assignee
Chongqing Communications Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Communications Construction Group Co ltd filed Critical Chongqing Communications Construction Group Co ltd
Priority to CN202010333338.4A priority Critical patent/CN111472812A/en
Publication of CN111472812A publication Critical patent/CN111472812A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/385Sealing means positioned between adjacent lining members
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/385Sealing means positioned between adjacent lining members
    • E21D11/386Sealing means positioned between adjacent lining members inflatable sealing means
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/01Methods or apparatus for enlarging or restoring the cross-section of tunnels, e.g. by restoring the floor to its original level

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention provides a construction method for filling and pouring concrete into an inverted arch of a tunnel, which comprises the following steps: measuring and lofting: before excavation, measurement lofting is carried out, rechecking is carried out on the center line, the elevation and the plane position of the tunnel excavation outline, and measurement control points are placed on the side wall of the tunnel every 5m before construction to serve as control points for inverted arch excavation and concrete construction; excavating: excavating by adopting an inverted arch excavation drilling and blasting method; supporting, inverted arch and inverted arch filling and pouring concrete: concrete is intensively mixed outside the hole by adopting a concrete mixing station, and a concrete mixing transport vehicle is transported into the hole for pouring; pouring the concrete tank truck through a movable chute, and vibrating a concrete vibrating rod; the inverted arch construction joint is provided with a buried water stop according to the design requirement. The construction method of the invention accelerates the tunnel construction progress and improves the efficiency under the condition of ensuring the safety and the quality of the whole construction.

Description

Construction method for filling and pouring concrete into inverted arch of tunnel
Technical Field
The invention relates to the technical field of tunnel safety monitoring, in particular to a construction method for filling and pouring concrete in an inverted arch of a tunnel.
Background
In practical construction, the tunnel structure is generally composed of an arch ring, a side wall, an inverted arch, inverted arch filling, a forepoling system and an electromechanical ventilation and illumination system. At present, a tunnel is excavated by adopting a drilling and blasting method, most of an inverted arch is constructed by adopting a cast-in-place method, and the construction process comprises two steps: the other method is that an inverted arch trestle method is adopted, inverted arch trestle passing transport vehicles are utilized, inverted arch concrete is constructed below the trestle, parallel crossing is changed into three-dimensional crossing construction, inverted arch concrete reinforcement binding, concrete pouring and maintenance are not interfered with tunnel slag discharge transportation, continuous tunnel excavation construction can be met, inverted arch concrete quality can be guaranteed, the construction process is mature and generally adopted at present, but the method needs to carry out concrete pouring on the inverted arch on site, certain influence is caused on the environment, requirements on the operation environment and weather are met in construction, and limitation is achieved. The other method is to excavate inverted arch backfill hole slag by utilizing a twice-excavated slag discharge gap of the tunnel, pour an inverted arch by adopting dry and hard concrete, and discharge slag after cast-in-place concrete reaches certain strength; the method can not solve the problem of interference of tunnel excavation and inverted arch construction, can not avoid cross influence of the tunnel excavation and inverted arch construction, can cause inverted arch concrete damage and influence quality due to the fact that a slag car passes and rolls because of insufficient initial concrete strength, and is less in field use.
Most of tunnel invert construction is having the operation under the water environment, and is great to concrete quality influence, and need install the invert inner formword during the construction, and fixed and construction are all more difficult, and the template easy come-up has been strengthened in the vibration, and the concrete is not closely knit to the vibration weak point, so present tunnel construction can't satisfy present tunnel to the requirement of construction, has great potential safety hazard.
Disclosure of Invention
In order to solve the problems mentioned in the background art, the invention aims to provide a construction method for filling and pouring concrete in an inverted arch of a tunnel, so as to improve the construction efficiency.
In order to achieve the purpose, the invention provides the following technical scheme:
a construction method for filling and pouring concrete into an inverted arch of a tunnel comprises the following steps:
(1) measuring and lofting: before excavation, measurement lofting is carried out, rechecking is carried out on the center line, the elevation and the plane position of the tunnel excavation outline, and measurement control points are placed on the side wall of the tunnel every 5m before construction to serve as control points for inverted arch excavation and concrete construction;
(2) excavating: excavating by adopting an inverted arch excavation drilling and blasting method, removing rocks invading into the structural dimension in time after excavating, checking the dimension of each part to reach the design dimension requirement, and treating underexcavated parts;
(3) and (3) supporting: supporting according to different surrounding rock types, effectively connecting the full-ring steel frame section with the reserved joint of the side wall steel frame, and then performing concrete spraying operation; the base reaches the supporting condition and reports for inspection after the steel frame is installed;
(4) filling and pouring concrete into the inverted arch and the inverted arch: concrete is intensively mixed outside the hole by adopting a concrete mixing station, and a concrete mixing transport vehicle is transported into the hole for pouring; pouring the concrete tank truck through a movable chute, and vibrating a concrete vibrating rod; mounting a middle-buried water stop according to design requirements on an inverted arch construction joint;
the tamping duration of each vibration point of concrete vibration is 20-30 s, and the vibration is stopped when the concrete does not sink, no air bubbles appear and the surface presents floating slurry; the moving distance of the vibrators is smaller than 1.5 times of the acting radius of the vibrators, the depth of the vibrators inserted into the lower layer of concrete is 50-100 mm, the vibrators are kept at a distance of 50-100 mm from the side mold, and collision is avoided in construction; after the vibration is finished, the material is slowly pulled out vertically, so that the mixture accumulated at the discharging opening can not be horizontally dragged to push the mixture to a distance by using an inserted vibrating rod; and (5) starting to cure the concrete within 12 hours after the concrete is poured, and continuously curing the concrete according to the minimum curing period of 14 days.
Furthermore, before supporting operation construction, the excavation depth of the inverted arch is checked, and the bottom of the inverted arch is required to be cleaned up to expose bedrock without accumulated water.
Furthermore, accumulated water, sundries and sludge on the surface of the primary support of the inverted arch are removed before the inverted arch concrete is poured, reinforcing steel bars are bound according to the design requirements, and the concrete is poured after the reinforcing steel bars are checked to be qualified.
Furthermore, before the construction of filling concrete into the inverted arch, cleaning the upper virtual slag and sundries of the inverted arch, draining accumulated water, and pouring the concrete after the inspection is qualified; the elevation of the top surface of the filling concrete is poured and filled at one time, the elevation of the top surface of the filling concrete and longitudinal and transverse slopes need to be well controlled, and the surface meets the requirement of flatness.
Furthermore, the inverted arch construction joint and the concrete filling construction joint are required to be on the same section, the construction joint is guaranteed to be straight and flat in construction, and the construction joint must guarantee effective installation of a buried water stop; the inverted arch template is spliced by adopting a wood template, the template is not arranged in the middle part, inverted templates are arranged on two sides, the template is fixedly connected with a secondary reinforcing steel bar by a phi 18 reinforcing steel bar, and the distance between the fixed reinforcing steel bars is controlled to be about 1-1.5 m.
Further, still include inverted arch reservation and two lining arch wall reinforcing bars: the thickness of the net protective layer of the steel bar is 40 mm; the main reinforcement adopts mechanical connection, and adjacent steel bar joint staggers 1m, and the steel bar joint rate of same joint section is not more than 50%.
Further, still include waterproof drainage: a back-attached water stop belt is adopted for the circumferential construction joint of the inverted arch, and the water stop belt is ensured to be positioned in the center of the joint of the outer side of the inverted arch structure and exposed for 15cm when being installed; and a 20-30 water-swelling water stop strip is arranged in the middle of the inverted arch structure.
Further, still include deformation joint waterproof drainage: deformation joints are arranged at the light and dark boundary of the tunnel and at the surrounding rock level change positions, a middle-buried rubber water stop is adopted for water prevention of the inverted arch deformation joints, and the installation requirements are the same as those of construction joints; the position of the deformation joint requires the inverted arch steel bar to be disconnected.
According to the construction method for filling and pouring concrete into the inverted arch of the tunnel, the construction of the inverted arch is not limited by the field operation environment and the construction conditions, and the influence of the traditional field concrete pouring on the operation environments such as temperature and the like is avoided, so that the safety and the durability of the tunnel inverted arch construction are ensured, and the tunnel construction progress is accelerated under the condition that the safety and the quality of the whole construction are ensured.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
FIG. 1 is a schematic view of a construction joint configuration of the present invention;
fig. 2 is a schematic view of the deformation joint structure in the present invention.
Detailed Description
The technical solutions of the present invention will be described clearly and completely with reference to the accompanying drawings, and it is to be understood that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The invention relates to a construction method for filling and pouring concrete into an inverted arch of a tunnel, which comprises the following steps:
(1) measuring and lofting: before excavation, measurement lofting is carried out, rechecking is carried out on the center line, the elevation and the plane position of the tunnel excavation outline, and measurement control points are placed on the side wall of the tunnel every 5m before construction to serve as control points for inverted arch excavation and concrete construction;
(2) excavating: excavating by adopting an inverted arch excavation drilling and blasting method, removing rocks invading into the structural dimension in time after excavating, checking the dimension of each part to reach the design dimension requirement, and treating underexcavated parts;
(3) and (3) supporting: before the supporting operation construction, the excavation depth of the inverted arch is checked, and the bottom of the inverted arch is required to be cleaned up to expose bedrock without accumulated water.
Supporting according to different surrounding rock types, effectively connecting the full-ring steel frame section with the reserved joint of the side wall steel frame, and then performing concrete spraying operation; the base reaches the supporting condition and reports for inspection after the steel frame is installed;
(4) filling and pouring concrete into the inverted arch and the inverted arch: concrete is intensively mixed outside the hole by adopting a concrete mixing station, and a concrete mixing transport vehicle is transported into the hole for pouring; pouring the concrete tank truck through a movable chute, and vibrating a concrete vibrating rod; mounting a middle-buried water stop according to design requirements on an inverted arch construction joint;
the tamping duration of each vibration point of concrete vibration is 20-30 s, and the vibration is stopped when the concrete does not sink, no air bubbles appear and the surface presents floating slurry; the moving distance of the vibrators is smaller than 1.5 times of the acting radius of the vibrators, the depth of the vibrators inserted into the lower layer of concrete is 50-100 mm, the vibrators are kept at a distance of 50-100 mm from the side mold, and collision is avoided in construction; after the vibration is finished, the material is slowly pulled out vertically, so that the mixture accumulated at the discharging opening can not be horizontally dragged to push the mixture to a distance by using an inserted vibrating rod; and (5) starting to cure the concrete within 12 hours after the concrete is poured, and continuously curing the concrete according to the minimum curing period of 14 days.
Before the inverted arch concrete is poured, accumulated water, sundries and sludge on the surface of an inverted arch primary support are removed, reinforcing steel bars are bound according to the design requirements, and after the inspection is qualified, the concrete is poured.
Before the construction of filling concrete into the inverted arch, cleaning the upper deficiency slag and sundries of the inverted arch, removing accumulated water, and pouring the concrete after the inspection is qualified; the elevation of the top surface of the filling concrete is poured and filled at one time, the elevation of the top surface of the filling concrete and longitudinal and transverse slopes need to be well controlled, and the surface meets the requirement of flatness.
The inverted arch construction joint and the concrete filling construction joint are required to be on the same section, the construction joint is guaranteed to be straight and flat in construction, and the construction joint must ensure effective installation of a middle-buried water stop; the inverted arch template is spliced by adopting a wood template, the template is not arranged in the middle part, inverted templates are arranged on two sides, the template is fixedly connected with a secondary reinforcing steel bar by a phi 18 reinforcing steel bar, and the distance between the fixed reinforcing steel bars is controlled to be about 1-1.5 m.
Still include the inverted arch reservation and two lining arch wall reinforcing bars: the thickness of the net protective layer of the steel bar is 40 mm; the main reinforcement adopts mechanical connection, and adjacent steel bar joint staggers 1m, and the steel bar joint rate of same joint section is not more than 50%.
Still include waterproof drainage: as shown in fig. 1, a back-attached water stop is adopted for an annular construction joint of an inverted arch, and the water stop is ensured to be positioned in the center of a joint on the outer side of an inverted arch structure and exposed for 15cm when being installed; and a 20-30 water-swelling water stop strip is arranged in the middle of the inverted arch structure.
Still include that movement joint prevents drainage: as shown in fig. 2, deformation joints are arranged at the light and dark boundary of the tunnel and at the surrounding rock level change position, a middle-buried rubber water stop is adopted for water prevention of the inverted arch deformation joints, and the installation requirements are the same as those of construction joints; the position of the deformation joint requires the inverted arch steel bar to be disconnected.
The above description is only for the specific embodiments of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art can easily conceive of the changes or substitutions within the technical scope of the present invention, and all the changes or substitutions should be covered within the scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims (8)

1. A construction method for filling and pouring concrete in an inverted arch of a tunnel is characterized by comprising the following steps: the method comprises the following steps:
(1) measuring and lofting: before excavation, measurement lofting is carried out, rechecking is carried out on the center line, the elevation and the plane position of the tunnel excavation outline, and measurement control points are placed on the side wall of the tunnel every 5m before construction to serve as control points for inverted arch excavation and concrete construction;
(2) excavating: excavating by adopting an inverted arch excavation drilling and blasting method, removing rocks invading into the structural dimension in time after excavating, checking the dimension of each part to reach the design dimension requirement, and treating underexcavated parts;
(3) and (3) supporting: supporting according to different surrounding rock types, effectively connecting the full-ring steel frame section with the reserved joint of the side wall steel frame, and then performing concrete spraying operation; the base reaches the supporting condition and reports for inspection after the steel frame is installed;
(4) filling and pouring concrete into the inverted arch and the inverted arch: concrete is intensively mixed outside the hole by adopting a concrete mixing station, and a concrete mixing transport vehicle is transported into the hole for pouring; pouring the concrete tank truck through a movable chute, and vibrating a concrete vibrating rod; mounting a middle-buried water stop according to design requirements on an inverted arch construction joint;
the tamping duration of each vibration point of concrete vibration is 20-30 s, and the vibration is stopped when the concrete does not sink, no air bubbles appear and the surface presents floating slurry; the moving distance of the vibrators is smaller than 1.5 times of the acting radius of the vibrators, the depth of the vibrators inserted into the lower layer of concrete is 50-100 mm, the vibrators are kept at a distance of 50-100 mm from the side mold, and collision is avoided in construction; after the vibration is finished, the material is slowly pulled out vertically, so that the mixture accumulated at the discharging opening can not be horizontally dragged to push the mixture to a distance by using an inserted vibrating rod; and (5) starting to cure the concrete within 12 hours after the concrete is poured, and continuously curing the concrete according to the minimum curing period of 14 days.
2. The construction method for filling and pouring concrete into the inverted arch of the tunnel according to claim 1, wherein: before the supporting operation construction, the excavation depth of the inverted arch is checked, and the bottom of the inverted arch is required to be cleaned up to expose bedrock without accumulated water.
3. The construction method for filling and pouring concrete into the inverted arch of the tunnel according to claim 1, wherein: before the inverted arch concrete is poured, accumulated water, sundries and sludge on the surface of an inverted arch primary support are removed, reinforcing steel bars are bound according to the design requirements, and after the inspection is qualified, the concrete is poured.
4. The construction method for filling and pouring concrete into the inverted arch of the tunnel according to claim 1, wherein: before the construction of filling concrete into the inverted arch, cleaning the upper deficiency slag and sundries of the inverted arch, removing accumulated water, and pouring the concrete after the inspection is qualified; the elevation of the top surface of the filling concrete is poured and filled at one time, the elevation of the top surface of the filling concrete and longitudinal and transverse slopes need to be well controlled, and the surface meets the requirement of flatness.
5. The construction method for filling and pouring concrete into the inverted arch of the tunnel according to claim 1, wherein: the inverted arch construction joint and the concrete filling construction joint are required to be on the same section, the construction joint is guaranteed to be straight and flat in construction, and the construction joint must ensure effective installation of a middle-buried water stop; the inverted arch template is spliced by adopting a wood template, the template is not arranged in the middle part, inverted templates are arranged on two sides, the template is fixedly connected with a secondary reinforcing steel bar by a phi 18 reinforcing steel bar, and the distance between the fixed reinforcing steel bars is controlled to be about 1-1.5 m.
6. The construction method for filling and pouring concrete into the inverted arch of the tunnel according to claim 1, wherein: still include the inverted arch reservation and two lining arch wall reinforcing bars: the thickness of the net protective layer of the steel bar is 40 mm; the main reinforcement adopts mechanical connection, and adjacent steel bar joint staggers 1m, and the steel bar joint rate of same joint section is not more than 50%.
7. The construction method for filling and pouring concrete into the inverted arch of the tunnel according to claim 1, wherein: still include waterproof drainage: a back-attached water stop belt is adopted for an inverted arch circumferential construction joint, the back-attached water stop belt is installed by adopting hot air welding, and the back-attached water stop belt is ensured to be positioned in the center of a joint on the outer side of an inverted arch structure and exposed for 15cm during installation; and a water-swelling water stop strip is arranged in the middle of the inverted arch structure.
8. The construction method for filling and pouring concrete into the inverted arch of the tunnel according to claim 1, wherein: still include that movement joint prevents drainage: deformation joints are arranged at the light and dark boundary of the tunnel and at the surrounding rock level change positions, a middle-buried rubber water stop is adopted for water prevention of the inverted arch deformation joints, and the installation requirements are the same as those of construction joints; the position of the deformation joint requires the inverted arch steel bar to be disconnected.
CN202010333338.4A 2020-04-24 2020-04-24 Construction method for filling and pouring concrete into inverted arch of tunnel Pending CN111472812A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010333338.4A CN111472812A (en) 2020-04-24 2020-04-24 Construction method for filling and pouring concrete into inverted arch of tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010333338.4A CN111472812A (en) 2020-04-24 2020-04-24 Construction method for filling and pouring concrete into inverted arch of tunnel

Publications (1)

Publication Number Publication Date
CN111472812A true CN111472812A (en) 2020-07-31

Family

ID=71764050

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010333338.4A Pending CN111472812A (en) 2020-04-24 2020-04-24 Construction method for filling and pouring concrete into inverted arch of tunnel

Country Status (1)

Country Link
CN (1) CN111472812A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113833499A (en) * 2021-10-18 2021-12-24 重庆交通大学 Grouting device for pipe shed arch center for tunnel construction and grouting method thereof
CN114060059A (en) * 2021-11-15 2022-02-18 中铁十九局集团第六工程有限公司 Construction method of tunnel bottom deformation monitoring device

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016095629A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Advanced support structure for oversized variable-cross-section tunnel
CN106837352A (en) * 2017-01-22 2017-06-13 中南大学 Fault belt surrounding rock tunnel construction method
CN206722852U (en) * 2017-05-05 2017-12-08 中铁十二局集团有限公司 A kind of mobile inverted arch trestle of growing up for carrying inverted arch template
CN109736847A (en) * 2019-02-14 2019-05-10 中铁十一局集团有限公司 Primary concreting concrete inverted arch and its construction method
CN110397449A (en) * 2019-08-06 2019-11-01 中铁十四局集团有限公司 Tunnel inverted arch construction method
CN110593902A (en) * 2019-09-25 2019-12-20 中铁隧道集团三处有限公司 Construction method for filling inverted arch and integrally pouring
CN110748359A (en) * 2019-12-06 2020-02-04 中铁十八局集团建筑安装工程有限公司 Tunnel water-proof and drainage construction process

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016095629A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Advanced support structure for oversized variable-cross-section tunnel
CN106837352A (en) * 2017-01-22 2017-06-13 中南大学 Fault belt surrounding rock tunnel construction method
CN206722852U (en) * 2017-05-05 2017-12-08 中铁十二局集团有限公司 A kind of mobile inverted arch trestle of growing up for carrying inverted arch template
CN109736847A (en) * 2019-02-14 2019-05-10 中铁十一局集团有限公司 Primary concreting concrete inverted arch and its construction method
CN110397449A (en) * 2019-08-06 2019-11-01 中铁十四局集团有限公司 Tunnel inverted arch construction method
CN110593902A (en) * 2019-09-25 2019-12-20 中铁隧道集团三处有限公司 Construction method for filling inverted arch and integrally pouring
CN110748359A (en) * 2019-12-06 2020-02-04 中铁十八局集团建筑安装工程有限公司 Tunnel water-proof and drainage construction process

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王峰等: "铁路客运专线桥涵工程质量检查与控制", vol. 2008, 西南交通大学出版社, pages: 323 - 326 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113833499A (en) * 2021-10-18 2021-12-24 重庆交通大学 Grouting device for pipe shed arch center for tunnel construction and grouting method thereof
CN113833499B (en) * 2021-10-18 2023-10-24 重庆交通大学 Grouting device for tunnel construction pipe shed arch centering and grouting method thereof
CN114060059A (en) * 2021-11-15 2022-02-18 中铁十九局集团第六工程有限公司 Construction method of tunnel bottom deformation monitoring device

Similar Documents

Publication Publication Date Title
CN106677787B (en) Vertical shaft repairing and reinforcement structure and repairing and reinforcement construction method
CN113833480B (en) Construction method for initial tunneling and arrival of shield
CN107905799B (en) Reinforced structure of high-speed rail tunnel bottom water passing karst cave and construction method thereof
CN107059903A (en) Bottom plate plugging dewatering well construction method is worn in foundation ditch
CN109736884B (en) Treatment structure for water gushing in underground river close to tunnel and construction method of treatment structure
CN211038657U (en) Cover encircles based deeply buries loess tunnel deformation control construction structures
CN106150523B (en) A kind of Railway Tunnel ditch cable trench integral mold plate construction
CN110656959B (en) Large-section loess tunnel primary support limit-invasion arch-changing construction method
CN211144503U (en) High steep topography bridge tunnel meets section open cut tunnel and connects long structure
CN111472812A (en) Construction method for filling and pouring concrete into inverted arch of tunnel
CN109610263A (en) A kind of construction method of fabricated construction sidewalk
CN107059881A (en) The foundation pit supporting method that a kind of campshed is combined with steel sheet pile
CN108301440A (en) With waterproof, the underground pipe gallery construction method of drain function
CN110761808A (en) Large-section loess tunnel supporting system and supporting construction method
CN112610240A (en) Secondary lining construction process for mountain tunnel
CN104452591A (en) Cast-in-place box beam construction technology applied to bridge constructions
CN114059654A (en) Rapid construction method for improved AAO biological pond chamber jumping method of sewage treatment station
CN113847050A (en) Construction method of extra-long highway tunnel in lava mountain area
CN110593902B (en) Construction method for filling inverted arch and integrally pouring
CN109881547B (en) Uneven settlement control structure of roadbed of airport pavement passing under high-speed railway tunnel and construction process
CN110952995A (en) Construction method for external tunnel door post-cast ring beam
CN110747762A (en) Cement member crossing highway and its installation method
CN107100649B (en) Construction process for inclined shaft concrete pouring
CN110671132B (en) Deep loess tunnel deformation control construction structure and method based on sleeve arch
CN218027813U (en) Reverse mould building retaining wall formwork structure between stake of PC worker method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination