CN107916935B - Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method - Google Patents

Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method Download PDF

Info

Publication number
CN107916935B
CN107916935B CN201711116073.7A CN201711116073A CN107916935B CN 107916935 B CN107916935 B CN 107916935B CN 201711116073 A CN201711116073 A CN 201711116073A CN 107916935 B CN107916935 B CN 107916935B
Authority
CN
China
Prior art keywords
angle
pipe shed
pipe
grouting
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711116073.7A
Other languages
Chinese (zh)
Other versions
CN107916935A (en
Inventor
丁智
费豪
张霄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University City College ZUCC
Original Assignee
Zhejiang University City College ZUCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University City College ZUCC filed Critical Zhejiang University City College ZUCC
Priority to CN201711116073.7A priority Critical patent/CN107916935B/en
Publication of CN107916935A publication Critical patent/CN107916935A/en
Application granted granted Critical
Publication of CN107916935B publication Critical patent/CN107916935B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention relates to a soil body composite reinforcement structure for a soft soil shield to pass through the existing subway, which comprises the following components: the device comprises a shield tunnel contour line, an angle-adjustable pipe shed and a horizontal jet grouting pile; the outside of the outline of the shield tunnel to be dug is provided with a row of angle-adjustable pipe sheds, each angle-adjustable pipe shed comprises pipe shed steel pipes, horizontal jet grouting piles are arranged between the adjacent pipe shed steel pipes, and each horizontal jet grouting pile wraps the angle-adjustable pipe shed and is in meshed lap joint with the adjacent horizontal jet grouting piles; the horizontal jet grouting pile comprises a jet grouting drill rod and a drill rod jacket, and the pipe shed steel pipe and the jet grouting drill rod are connected in an alternate mode. The beneficial effects of the invention are as follows: the invention combines the angle-adjustable pipe shed with the horizontal rotary spraying, combines hardness and softness, applies both softness and hardness, fully plays the respective characteristics, can well cooperate to obtain good integral supporting effect, can well adapt to the environment of soft soil areas, strengthens soil, and can well control the deformation of the existing subways.

Description

Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method
Technical Field
The invention relates to the field of soil body composite reinforcement construction of a soft soil area shield crossing an existing subway, in particular to a soil body composite reinforcement structure of the soft soil area shield crossing the existing subway and a construction method.
Background
With the continuous promotion of the urban process, urban underground rail transit becomes more important, and the subway lines are always intersected when a complete subway network is built. In the construction of the subway tunnel shield, the condition that a newly built shield tunnel passes through the existing operation subway tunnel is increased. The newly built shield tunnel can produce many adverse effects to the subway tunnel of operation, such as section of jurisdiction fracture, joint open, bolt inefficacy, vertical differential settlement and horizontal displacement are too big etc. harm, especially the existing tunnel in weak soil area is more liable to take place deformation and section of jurisdiction damage, influences locomotive operation's comfort level, and the roughness aggravates train wearing and tearing, seriously will lead to locomotive derailment etc. serious accident. Therefore, before crossing, the soil body in the range of the existing operation subway needs to be reinforced, the deformation resistance capability of the existing subway is enhanced, and the normal operation of the existing subway is ensured.
Disclosure of Invention
The invention aims to overcome the defects in the prior art and provides a soil body composite reinforcing structure for a soft soil shield to penetrate through the existing subway and a construction method.
The invention further aims to provide a soil body composite reinforcing structure for the soft soil shield to penetrate through the existing subway. The invention aims at realizing the following technical scheme:
the soil body composite reinforcement structure that this kind of weak soil shield passed through existing subway includes: the device comprises a shield tunnel contour line, an angle-adjustable pipe shed and a horizontal jet grouting pile; the outside of the outline of the shield tunnel to be dug is provided with a row of angle-adjustable pipe sheds, each angle-adjustable pipe shed comprises pipe shed steel pipes, horizontal jet grouting piles are arranged between the adjacent pipe shed steel pipes, and each horizontal jet grouting pile wraps the angle-adjustable pipe shed and is in meshed lap joint with the adjacent horizontal jet grouting piles; the horizontal jet grouting pile comprises a jet grouting drill rod and a drill rod jacket, wherein the pipe shed steel pipes are connected with the jet grouting drill rod in an alternating mode, a limiting track is arranged on the outer side of each pipe shed steel pipe, the drill rod jacket is arranged on the outer surface of each jet grouting drill rod, and the limiting track and the drill rod jacket form an integral arch shell through limiting welding.
As preferable: the angle-adjustable pipe shed is divided into a plurality of sections from back to front along the longitudinal extension direction of the tunnel.
As preferable: the pipe shed steel pipe uses a hot-rolled seamless steel pipe, and both ends of the pipe shed steel pipe are all prefabricated into external threads.
As preferable: two tangent lines of the existing subway tunnel are made through the circle center of the shield tunnel, the included angle of the two tangent lines is alpha, and the angle formed by the circle center of the shield tunnel and the two edges of the adjustable angle pipe shed 8 is beta, wherein beta=2alpha.
A construction method for a soft soil shield to penetrate through a soil body composite reinforcing structure of an existing subway comprises the following steps:
s1, supporting a spiral soil outlet angle-adjustable pipe shed vault;
s1.1, erecting a drilling platform and sharing the platform for horizontal jet grouting construction;
s1.2, installing a drilling machine, and continuously carrying out horizontal rotary spraying construction by the drilling machine after the construction of the angle-adjustable pipe shed is finished;
s1.3, breaking plain concrete barriers of the face and the stratum entrance section: the tunnel face structural wall adopts a high-speed water drill to drill holes according to the designed positions, and the drilling angles drill according to the design construction angles of the angle-adjustable pipe shed; drilling plain concrete barriers at the inlet section of the broken stratum along the holes of the face by adopting a down-the-hole hammer;
s1.4, penetrating a spiral soil outlet drilling tool into a processed pipe shed steel pipe, wherein male and female threads are arranged at two ends of the pipe shed steel pipe, a reaming auger wedge-shaped drill bit is arranged at the end head of the spiral drilling tool, and an angle detecting instrument is arranged in the drilling tool;
s1.5, checking the mechanical condition of a drilling machine and the working state of an instrument before jacking the steel pipes of the pipe shed; when the drilling machine is in place and drilling is performed, the drilling machine is fixed with the tunnel face; after the steel pipe of the pipe shed is jacked into the soil layer, starting a drilling machine to rotate, and measuring the angle change of the steel pipe of the pipe shed;
s1.6, after jacking of the first pipe shed steel pipe is finished, disassembling the joint of the drilling machine and the pipe shed with adjustable angle, returning to the original position along the guide rail, manually loading the second pipe shed steel pipe, installing an auger in the pipe shed steel pipe, buckling and connecting the auger with the first pipe shed steel pipe into a whole, jacking, rotating and discharging soil;
s1.7, when inclination deviation occurs to the angle of the steel pipe of the pipe shed, starting a deviation correcting program, stopping rotation of the drilling tool, and operating the steel pipe of the pipe shed to jack in according to a design method: the steel pipe of the pipe shed deviates upwards, the inclination angle of the steel pipe of the pipe shed is reduced, and the angle position of the wedge-shaped drill bit of the auger is adjusted downwards; the steel pipes of the pipe shed are deflected downwards, the inclination angles of the steel pipes of the pipe shed are adjusted upwards, and the angle positions of wedge-shaped drill bits of the augers are adjusted upwards; when the steel pipe of the pipe shed deflects leftwards and rightwards, the wedge-shaped plate is adjusted to correct the position by referring to an inclination angle adjusting method, and the steel pipe of the pipe shed is jacked in to carry out correction operation;
s1.8, numbering the steel pipes of the pipe shed in construction hole by hole before installation, and taking over and jacking according to the numbering sequence;
s1.9, grouting an angle-adjustable pipe shed: checking pipeline and mechanical conditions before grouting, and performing grouting experiments after confirming normal grouting to determine reasonable grouting parameters; checking whether the thin part of the orifice, the adjacent hole and the covering layer has slurry mixing phenomenon or not at any time in the grouting process; the grouting process is responsible for a special person, and data such as grouting time, slurry consumption, grouting pressure and the like are recorded; after grouting, cleaning holes of the pump and the pipeline to finish the construction process of the angle-adjustable pipe shed;
s2, reinforcing and improving the soil body by horizontal jet grouting;
s2.1, installing a rotary jetting drilling tool and a limit rail;
s2.2, drilling: perforating, preparing circulating slurry, drilling and setting;
s2.3, high-pressure jet grouting: checking a high-pressure grouting pump, and starting grouting when the pumping pressure reaches the design requirement; before spraying, checking the tightness of the drilling tool, and spraying the slurry after the pressurization reaches a design value; arranging special personnel to operate and observe the pump pressure change in the high-pressure guniting; the drill rod is sprayed to the designed final hole position in a rotary mode to stop grouting, and clean pipelines are washed by clean water under high pressure;
s2.4, hole sealing: after spraying the slurry to the position of the designed final hole, stopping spraying the slurry, pulling out the drill rod and the drill bit, and plugging the hole by adopting a woven bag or cotton threads;
s2.5, cleaning the pipeline and equipment to finish the construction process of horizontal jet grouting.
The beneficial effects of the invention are as follows: the invention combines the angle-adjustable pipe shed with the horizontal rotary spraying, combines hardness and softness, applies both softness and hardness, fully plays the respective characteristics, can well cooperate to obtain good integral supporting effect, can well adapt to the environment of soft soil areas, strengthens soil, and can well control the deformation of the existing subways.
Drawings
FIG. 1 is a flow chart of a spiral soil outlet angle adjustable pipe shed construction process;
FIG. 2 is a flow chart of a horizontal jet grouting construction process;
fig. 3 is a plan view of a Hangzhou subway No. 2 line through No. 1 line;
FIG. 4 is an angle-adjustable pipe shed construction layout;
FIG. 5 is a schematic diagram of a horizontal jet grouting pile and an angle-adjustable pipe shed;
FIG. 6 is a schematic view of the direction of a wedge bit when the steel pipe is deflected upwards;
FIG. 7 is a schematic view of the direction of a wedge bit when the steel pipe is deflected downwards;
FIG. 8 is a schematic view of the wedge bit position when the angle of the steel pipe is normal;
FIG. 9 is a horizontal rotary jetting construction layout;
reference numerals illustrate: hangzhou subway No. 2 line downlink 1, hangzhou subway No. 2 line uplink 2, hangzhou subway No. 1 line uplink 3, hangzhou subway No. 1 line downlink 4, hangzhou subway No. 2 line phoenix station 5, hangzhou subway No. 1 line phoenix station 6, shield tunnel contour 7, adjustable angle pipe canopy 8, horizontal jet grouting pile 9, tunnel face 10, auger wedge bit 11, pipe canopy steel pipe 12, limit weld 13, rotary jet drill pipe 14, drill pipe jacket 15, and limit track 16.
Detailed Description
The invention is further described below with reference to examples. The following examples are presented only to aid in the understanding of the invention. It should be noted that it will be apparent to those skilled in the art that various modifications and adaptations of the invention can be made without departing from the principles of the invention and these modifications and adaptations are intended to be within the scope of the invention as defined in the following claims.
As shown in fig. 1 to 9, the soft soil shield passes through the soil body composite reinforcing structure of the existing subway, so that the settlement and segment damage of the existing subway can be effectively controlled, and the shield can be smoothly propelled. The soil body composite reinforcement structure that soft soil shield passed through existing subway includes: hangzhou subway No. 2 line down line 1, hangzhou subway No. 2 line up line 2, hangzhou subway No. 1 line up line 3, hangzhou subway No. 1 line down line 4, hangzhou subway No. 2 line phoenix station 5, hangzhou subway No. 1 line phoenix station 6, shield tunnel contour 7, adjustable angle pipe canopy 8, horizontal jet grouting pile 9, tunnel face 10, auger wedge bit 11, pipe canopy steel pipe 12, limit weld 13, rotary jet drill pipe 14, drill pipe jacket 15 and limit track 16.
As shown in fig. 3, the hangzhou subway No. 2 line downlink 1 and the hangzhou subway No. 2 line uplink 2 at the hangzhou subway No. 2 line feng-up station 5 pass through the hangzhou subway No. 1 line uplink 3 and the hangzhou subway No. 1 line downlink 4 at the hangzhou subway No. 1 line feng-up station 6. As shown in fig. 4, in the existing subway tunnel No. 1 line penetrating under the newly-built shield tunnel No. 2 line, a row of advanced support adjustable angle pipe sheds 8 are arranged outside the to-be-dug shield tunnel contour line 7, the advanced support construction is performed on the shield penetrating through the existing subway soil body by dividing the shield into a plurality of sections from back to front along the longitudinal extending direction of the tunnel, and the construction methods of the adjustable angle pipe sheds 8 of the sections are the same. As shown in fig. 5 and 9, the angle-adjustable pipe shed 8 comprises pipe shed steel pipes 12, horizontal jet grouting piles 9 are arranged between adjacent pipe shed steel pipes 12, and the angle-adjustable pipe shed 8 is wrapped by the horizontal jet grouting piles 9 and is in meshed lap joint with the adjacent horizontal jet grouting piles 9, so that a supporting structure with high bearing and curtain partition effects is formed, and external loads are jointly borne. The spacing between adjacent horizontal jet grouting piles 9 is 300mm, the adjacent horizontal jet grouting piles 9 are mutually meshed by 200mm, the diameter of each horizontal jet grouting pile 9 is 500mm, and the single construction length is 45m. As shown in fig. 9, the horizontal jet grouting pile 9 comprises a jet grouting drill stem 14 and a drill stem jacket 15, the pipe shed steel pipes 12 and the jet grouting drill stem 14 are connected in an alternate mode, a limit rail 16 is arranged on the outer side of the pipe shed steel pipes 12, the drill stem jacket 15 is arranged on the outer surface of the jet grouting drill stem 14, and the limit rail 16 and the drill stem jacket 15 form an integral arch shell through limit welding 13. The pipe shed steel pipe 12 is made of hot-rolled seamless steel pipes, the outer diameter of the pipe shed steel pipe is 159mm, the wall thickness of the pipe shed steel pipe is 8mm, the length of each section of steel pipe is 6m, and two ends of each section of steel pipe are prefabricated into outer threads. The pipe shed 8 with adjustable angle and the horizontal jet grouting piles 9 jointly act to strengthen soil bodies, so that the aim of preventing the existing subway from sedimentation or other damages is fulfilled.
And the shield tunnel in the soft soil area passes through the working condition that the clear distance between the outer edges of the two tunnels is smaller than (equal to) 12m in the existing subway tunnel. The construction range of the angle-adjustable pipe shed 8 is determined by the clear distance between the outer edges of the two tunnels, and the larger the clear distance is, the smaller the construction range is, and the smaller the clear distance is, the larger the construction range is. As shown in fig. 4 and 5, two tangent lines of the existing subway tunnel are made through the center of the shield tunnel to form an angle α, the angle of the angle-adjustable pipe shed 8 is β, and β=2α, β is the range for constructing the angle-adjustable pipe shed 8.
The technology of a new Hangzhou subway No. 2 line in one period that a river road station-phoenix station interval shield is penetrated under a subway No. 1 line segment adopts a spiral soil outlet directional pipe shed as a framework, and a horizontal jet grouting pile curtain wraps and cuts off the road station-phoenix station interval shield is mainly divided into two parts: the spiral soil outlet pipe shed vault support and horizontal jet grouting soil body reinforcement improvement.
Spiral soil outlet pipe shed vault support
The spiral soil outlet directional pipe shed adopts a pipe shed steel pipe 12 with the diameter of 159mm as an outer sleeve, a spiral drilling tool is installed in the pipe, the pipe shed steel pipe 12 provided with a measuring probe is jacked into soil by a pipe jacking drilling machine, and meanwhile, the spiral drilling tool is rotated clockwise to crush and convey soil entering the pipe to the outside of the pipe; when the angle of the pipe shed steel pipe 12 deflects, angle correction is carried out by utilizing a wedge-shaped plate arranged at the end part of the drilling tool according to probe measurement and ground subsidence monitoring. In the construction of the adjustable angle pipe shed 8, the setting of the adjustable angle pipe shed 8 is completely carried out under the monitoring of a guiding instrument, optical measurement is needed, and the adjustable angle pipe shed 8 is ensured not to invade a shield below and is keptWithin the design scope. The construction of the horizontal jet grouting piles 9 is carried out under the monitoring of a guiding instrument, and certain consistency is ensured so as to form an arch supporting structure. The LED measuring lamp is arranged in the pipe shed spiral drilling tool, the elevation and the angle of the LED lamp point are measured from the pipe orifice through the theodolite, and the track of the pipe shed steel pipe 12 is measured together in cooperation with measuring data of the probe instrument. The pipe shed steel pipes 12 are hot-rolled seamless steel pipes, the outer diameter is 159mm, the wall thickness is 8mm, the length of each section of pipe shed steel pipes 12 is 6m, two ends of each section of pipe shed steel pipes are all prefabricated into external threads, the circumferential spacing of the angle-adjustable pipe shed 8 is 350mm, 25 pipe shed steel pipes are arranged in an arc direction, and the single construction length is 45m and 1260m in total. The external insertion angle is 1.5% -2%, the 0.1% precision probe is adopted for measurement, the grouting material is P.O42.5 cement, the water cement ratio is 0.8:1, and the grouting pressure is 0.5-1.0 MPa. The grouting amount of the single pipe shed steel pipe 12 is estimated according to the following formula: q=pi R k 2 Lηζ, wherein R k Taking R as the slurry diffusion radius k =1.2r, r is the steel tube radius; l is the length of the steel pipe; ζ is taken as 0.85, which is the grouting plump coefficient; η is the void fraction (%).
1. The construction key points of the angle-adjustable pipe shed 8 are as follows:
(1) The pipe shed steel pipe 12 is not provided with grouting small holes, and grouting holes with the diameter of about 4cm are formed in each meter to serve as grouting and pressure relief holes for horizontal rotary spraying;
(2) The angle-adjustable pipe shed 8 is constructed by hole jumping at intervals, so that the overlarge disturbance range of continuous construction is avoided;
(3) The entrance section of the angle-adjustable pipe shed 8 is provided with a plain concrete structure in the stratum, a down-the-hole hammer is used for breaking and forming holes, and the holes are sent into a pipe shed steel pipe 12 after the holes are formed, and a spiral soil-out construction process is adopted;
(4) The actual soil output of the spiral in the pipe is smaller than the theoretical soil output, so that settlement caused by excessive soil output is avoided;
(5) The construction of the angle-adjustable pipe shed 8 is planned or regulated according to the monitoring measurement data, and no construction is strictly forbidden.
2. The spiral soil outlet pipe shed construction process flow chart is shown in fig. 1, and is implemented as follows:
(1) Setting up a drilling platform and sharing the platform for horizontal jet grouting construction;
(2) Installing a drilling machine, and continuously carrying out horizontal rotary spraying construction by the drilling machine after the construction of the angle-adjustable pipe shed 8 is finished;
(3) Breaking plain concrete barriers of the face 10 and the entry section of the formation:
(1) the structural wall of the face 10 is drilled by adopting a high-speed water drill according to the design position, the diameter of the hole is 180mm, and the drilling angle is drilled according to the design construction angle of the pipe shed 8 with the adjustable angle;
(2) a plain concrete barrier is arranged in a stratum with a distance of 6-10 m from the face 10, and a phi 170mm down-the-hole hammer is adopted to drill and crush along the opening of the face 10.
(4) Penetrating a phi 138mm spiral soil outlet drilling tool into the processed pipe-shed steel pipe 12, leading male and female threads at two ends of the pipe-shed steel pipe 12, installing a reaming wedge drill bit 11 at the end of the spiral drilling tool, and installing an angle detecting instrument in the drilling tool;
(5) Checking the mechanical condition of the drilling machine and the working state of the instrument before jacking the pipe-shed steel pipe 12;
(6) When the drilling machine is in place for drilling, the drilling machine is fixed with the face 10, so that the construction precision is improved; after the pipe shed steel pipe 12 is jacked into the soil layer for 1m, starting a drilling machine to rotate, and measuring the angle change of the pipe shed steel pipe 12;
(7) After the jacking of the first pipe shed steel pipe 12 is finished, the joint of the drilling machine and the angle-adjustable pipe shed 8 is disassembled, the drilling machine returns to the original position along the guide rail, the second pipe shed steel pipe 12 is manually installed, an auger is installed in the pipe shed steel pipe 12, and the auger and the first pipe shed steel pipe 12 are buckled and connected into a whole, and jacking, rotating and discharging are carried out;
(8) When the inclination angle deviation occurs to the angle of the steel pipe 12 of the pipe shed, when the deviation exceeds the design value plus or minus 0.5%, starting a deviation correcting program, stopping the rotation of the drilling tool, and operating the jacking steel pipe 12 of the pipe shed according to the design method:
(1) the pipe-roof steel pipe 12 is deviated upward, the inclination angle of the pipe-roof steel pipe 12 needs to be reduced, and the angle position of the wedge-shaped drill bit 11 of the auger is adjusted downward, as shown in the direction of the wedge-shaped drill bit 11 in fig. 6.
(2) The pipe-shed steel pipe 12 is deflected downwards, the inclination angle of the pipe-shed steel pipe 12 needs to be adjusted upwards, and the angle position of the wedge-shaped drill bit 11 of the auger is adjusted upwards, as shown in the direction of the wedge-shaped drill bit 11 in fig. 7.
(3) The angle of the pipe shed steel pipe 12 is normal and does not need to be adjusted, as shown in fig. 8.
(4) When the steel pipe 12 of the pipe shed deflects leftwards and rightwards, the wedge-shaped plate is adjusted to correct the position by referring to the inclination angle adjusting method, and the steel pipe 12 of the pipe shed is jacked in to correct the position.
(9) The steel pipes 12 of the pipe shed in construction are required to be numbered hole by hole before being installed, and the pipe shed is connected with jacking according to the serial number sequence;
(10) Grouting an angle-adjustable pipe shed 8:
(1) checking pipeline and mechanical conditions before grouting, and performing grouting experiments after confirming normal grouting, so as to determine reasonable grouting parameters and construct;
(2) checking whether slurry is mixed at any time at the thin part of the orifice, the adjacent hole and the covering layer in the grouting process, and if necessary, adopting the measure of constant-speed coagulation by filling water glass; if the pressure is suddenly increased in the grouting process, the pipe blockage can occur, and the machine should be stopped for inspection;
(3) the grouting pressure reaches a design pressure value;
(4) the grouting process should be responsible for a special person, and data such as grouting time, slurry consumption, grouting pressure and the like are recorded in detail;
(5) after grouting is finished, cleaning holes of a pump and a pipeline;
(6) grouting sequence: and (3) grouting the jump holes from bottom to top.
(II) improvement of soil body reinforcement by horizontal jet grouting
The horizontal jet grouting pile curtain wrapping partition refers to construction of horizontal jet grouting piles 9 between adjacent angle-adjustable pipe sheds 8, ultra-high pressure cutting and stirring of cement slurry are utilized to disturb and solidify soil around the angle-adjustable pipe sheds 8, the angle-adjustable pipe sheds 8 are wrapped and meshed with the adjacent horizontal jet grouting piles 9 after jet grouting piles are formed, and a supporting structure with high bearing and curtain partition effects is formed. The construction of the horizontal jet grouting piles 9 realizes the construction precision by utilizing limit rails 16 arranged on the outer sides of the pipe shed steel pipes 12 of the existing angle-adjustable pipe shed 8 through limit welding 13. The horizontal jet grouting piles 9 are arranged on the upper side of a shield tunnel contour line 7 with the diameter of 170mm on the outer side of a shield steel ring, the distance between adjacent horizontal jet grouting piles 9 is 300mm, the diameter of each horizontal jet grouting pile 9 is 500mm, the adjacent horizontal jet grouting piles 9 are mutually meshed with each other by 200mm, the single construction length of each horizontal jet grouting pile 9 is 45m, the consolidation material of each horizontal jet grouting pile 9 is P.O42.5 cement, and the water cement ratio is 1:1; the construction track of the horizontal jet grouting pile 9 is the same as that of the adjacent adjustable angle pipe shed 8, and generally the construction rotating speed is required to be 5-15 r/min, and the pull-back speed is required to be 15-25 cm/min.
1. Technical requirements of the horizontal jet grouting pile 9 are as follows:
(1) The horizontal jet grouting pile 9 adopts an alloy drill bit to control sediment loss in cooperation with circulating fluid drilling, and the preset pile length is finished by adopting one-time setting in combination with the actual situation of the site;
(2) The horizontal setting precision is kept consistent with the track of the angle-adjustable pipe shed 8 through the limit arranged on the drill bit, and a proper limit device is determined through test pile construction according to the tunnel angle and construction experience;
(3) The horizontal jet grouting pile 9 adopts cement single-liquid slurry, and the water-cement ratio of grouting slurry is controlled to be 1:1;
(4) The drilling pressure is 3-5 MPa, the drilling pressure is controlled to be 35MPa plus or minus 5MPa, and the slurry returning amount and arch sedimentation are required to be controlled during slurry spraying; the grouting flow is 80L/min-90L/min;
(5) The position deviation of the horizontal jet grouting pile 9 is +/-50 mm; the inclination angle and the design error are +/-1%;
(6) The length of the horizontal jet grouting pile 9 is not smaller than the designed pile length; the unconfined compressive strength of the cement soil concretion body for 28 days is more than 3MPa, and the pile body is ensured to be continuous and uniformly achieve the supporting effect;
(7) The following record is made for each horizontal jet grouting pile 9 from drilling to piling: construction date, drilling time, finishing time, jet grouting pressure, jet grouting lifting speed, pile length and grouting amount;
(8) The pile body construction process needs to be continuous and can not be interrupted, so that the phenomenon of pile breakage and pile shorting is prevented. If the machine is stopped for 30-120 min due to mechanical failure or other reasons, the rotary spraying should be repeated for 1m for more than 2 hours, the pile is pressed and broken, and the pile is repaired by re-drilling.
2. The horizontal jet grouting construction process flow chart is shown in fig. 2, and is specifically implemented as follows:
(1) Installing a rotary spraying drilling tool and a limiting rail;
(2) Drilling:
(1) opening holes;
(2) preparing circulating slurry;
(3) drilling and setting.
(3) High-pressure rotary spraying:
(1) checking a high-pressure grouting pump, and starting grouting when the pumping pressure reaches the design requirement;
(2) checking the tightness of the drilling tool before spraying, slowly pressurizing to reach a design value, and then stably spraying the slurry;
(3) the special person is arranged to operate and observe the pump pressure change in the high-pressure spraying, and the found problems are timely notified to be solved;
(4) the drill rod is sprayed to the designed final hole position in a rotary mode to stop grouting, and clean pipelines are washed by clean water under high pressure;
(5) the construction pressure and the slurry proportion are strictly according to the design requirements.
(4) And (3) hole sealing:
and after the spraying is carried out to the position of the designed final hole, stopping spraying, rapidly pulling out the drill rod and the drill bit, and plugging the hole by adopting a woven bag or cotton threads.
(5) Cleaning the pipeline and the equipment.
And after the construction is finished, the pipeline and the equipment are washed by clean water under high pressure in time, and the pipeline and the equipment are moved to the next pile position after the construction is finished.

Claims (3)

1. The utility model provides a weak soil shield passes through soil body composite reinforcement structure of existing subway which characterized in that includes: the device comprises a shield tunnel contour line (7), an angle-adjustable pipe shed (8) and a horizontal jet grouting pile (9); a row of angle-adjustable pipe sheds (8) are arranged on the outer side of a contour line (7) of a shield tunnel to be dug, each angle-adjustable pipe shed (8) comprises pipe shed steel pipes (12), horizontal jet grouting piles (9) are arranged between adjacent pipe shed steel pipes (12), and each horizontal jet grouting pile (9) wraps the angle-adjustable pipe shed (8) and is in meshed lap joint with each adjacent horizontal jet grouting pile (9); the horizontal jet grouting pile (9) comprises a jet grouting drill stem (14) and a drill stem jacket (15), the pipe shed steel pipe (12) is connected with the jet grouting drill stem (14) at intervals, a limit rail (16) is arranged on the outer side of the pipe shed steel pipe (12), the drill stem jacket (15) is arranged on the outer surface of the jet grouting drill stem (14), and the limit rail (16) and the drill stem jacket (15) form an integral arch shell through limit welding (13); two tangent lines of the existing subway tunnel are made through the circle center of the shield tunnel, the angle between the two tangent lines is alpha, and the angle between the circle center of the shield tunnel and the two edges of the angle-adjustable pipe shed (8) is beta, wherein beta=2alpha; the angle-adjustable pipe shed (8) is divided into a plurality of sections from back to front along the longitudinal extension direction of the tunnel.
2. The soil body composite reinforcement structure of a soft soil shield crossing an existing subway according to claim 1, wherein: the pipe shed steel pipe (12) is a hot-rolled seamless steel pipe, and two ends of the pipe shed steel pipe (12) are all prefabricated into external threads.
3. The construction method for the soft soil shield to penetrate through the soil body composite reinforcement structure of the existing subway according to claim 1, which is characterized by comprising the following steps:
s1, supporting a vault of a spiral soil outlet angle-adjustable pipe shed (8);
s1.1, setting up a drilling and horizontal jet grouting construction shared platform;
s1.2, installing a drilling machine, and continuously carrying out horizontal rotary spraying construction by the drilling machine after the construction of the angle-adjustable pipe shed (8) is finished;
s1.3, breaking plain concrete barriers of the face (10) and the stratum entrance section: the structural wall of the tunnel face (10) is drilled by adopting a high-speed water drill according to the design position, and the drilling angle is drilled according to the design construction angle of the angle-adjustable pipe shed (8); drilling plain concrete barriers of the inlet section of the broken stratum along the holes of the face (10) by adopting a down-the-hole hammer;
s1.4, penetrating a spiral soil outlet drilling tool into a processed pipe shed steel pipe (12), leading male and female threads at two ends of the pipe shed steel pipe (12), installing a reaming auger wedge-shaped drill bit (11) at the end of the spiral drilling tool, and installing an angle detecting instrument in the drilling tool;
s1.5, checking the mechanical condition of a drilling machine and the working state of an instrument before jacking the pipe shed steel pipe (12); when the drilling machine is in place and drilling is performed, the drilling machine is fixed with the tunnel face (10); after the pipe shed steel pipe (12) is jacked into a soil layer, starting a drilling machine to rotate, and measuring the angle change of the pipe shed steel pipe (12) entering the soil;
s1.6, after jacking of the first pipe shed steel pipe (12) is finished, dismantling a joint of the drilling machine and the angle-adjustable pipe shed (8), returning to the original position along a guide rail, manually loading the second pipe shed steel pipe (12), installing an auger in the pipe shed steel pipe (12), buckling and connecting the auger with the first pipe shed steel pipe (12) into a whole, jacking, rotating and discharging;
s1.7, when the angle of the pipe shed steel pipe (12) is inclined, starting a deviation correcting program, stopping the rotation of the drilling tool, and operating the jacking pipe shed steel pipe (12) according to a design method: the pipe shed steel pipe (12) deviates upwards, the inclination angle of the pipe shed steel pipe (12) is reduced, and the angle position of the wedge-shaped drill bit (11) of the auger is adjusted downwards; the pipe shed steel pipe (12) deviates downwards, the inclination angle of the pipe shed steel pipe (12) is adjusted upwards, and the angle position of the auger wedge-shaped drill bit (11) is adjusted upwards; when the pipe shed steel pipe (12) deflects leftwards and rightwards, the wedge-shaped plate is adjusted to correct the position by referring to an inclination angle adjusting method, and the wedge-shaped plate is jacked into the pipe shed steel pipe (12) to correct the position;
s1.8, numbering the steel pipes (12) of the pipe shed in construction hole by hole before installation, and taking over and jacking according to the numbering sequence;
s1.9, grouting an angle-adjustable pipe shed (8): checking pipeline and mechanical conditions before grouting, and performing grouting experiments after confirming normal grouting to determine reasonable grouting parameters; checking whether the thin parts of the orifice, the adjacent orifice and the covering layer have slurry mixing phenomenon or not at any time in the grouting process; the grouting process is responsible for a special person, and grouting time, slurry consumption and grouting pressure data are recorded; after grouting, cleaning holes of the pump and the pipeline to finish the construction process of the angle-adjustable pipe shed (8);
s2, reinforcing and improving the soil body by horizontal jet grouting;
s2.1, installing a rotary jetting drilling tool and a limit rail;
s2.2, drilling: perforating, preparing circulating slurry, drilling and setting;
s2.3, high-pressure jet grouting: checking a high-pressure grouting pump, and starting grouting when the pumping pressure reaches the design requirement; before spraying, checking the tightness of the drilling tool, and spraying the slurry after the pressurization reaches a design value; arranging special personnel to operate and observe the pump pressure change in the high-pressure guniting; the drill rod is sprayed to the designed final hole position in a rotary mode to stop grouting, and clean pipelines are washed by clean water under high pressure;
s2.4, hole sealing: after spraying the slurry to the position of the designed final hole, stopping spraying the slurry, pulling out the drill rod and the drill bit, and plugging the hole by adopting a woven bag or cotton threads;
s2.5, cleaning the pipeline and equipment to finish the construction process of horizontal jet grouting.
CN201711116073.7A 2017-11-13 2017-11-13 Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method Active CN107916935B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711116073.7A CN107916935B (en) 2017-11-13 2017-11-13 Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711116073.7A CN107916935B (en) 2017-11-13 2017-11-13 Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method

Publications (2)

Publication Number Publication Date
CN107916935A CN107916935A (en) 2018-04-17
CN107916935B true CN107916935B (en) 2024-01-23

Family

ID=61895438

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711116073.7A Active CN107916935B (en) 2017-11-13 2017-11-13 Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method

Country Status (1)

Country Link
CN (1) CN107916935B (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952765B (en) * 2018-07-18 2020-01-31 中铁十二局集团第二工程有限公司 Construction method for advanced support of super-large pipe shed on water-rich sand layer
CN108678666B (en) * 2018-07-28 2024-02-02 江苏徐工工程机械研究院有限公司 Multifunctional drilling machine and pipe shed mounting device
CN109723443B (en) * 2018-12-30 2021-07-20 中铁十四局集团有限公司 Tunnel construction method
CN111379571A (en) * 2018-12-30 2020-07-07 中铁十四局集团有限公司 Pipeline, pipe shed structure and pipe shed construction method with same
CN109723454A (en) * 2019-01-09 2019-05-07 中水电四局武汉轨道交通工程有限公司 A kind of bored tunnel advance support is with pipe canopy with the accurate drilling construction method of pipe
CN111706335B (en) * 2019-02-26 2022-04-08 朔黄铁路发展有限责任公司 Process and device for underpass of existing railway
CN109869156B (en) * 2019-04-02 2024-04-26 北京首尔工程技术有限公司 Jacking pipe row for controlling soil discharge amount for pipe row pipe curtain construction and jacking method thereof
CN110578536A (en) * 2019-10-15 2019-12-17 中铁十二局集团有限公司 Excavation support reinforcing method for underground excavation section of subway to penetrate existing street crossing channel
CN112857223A (en) * 2021-01-19 2021-05-28 吉力此且 Optical fiber gyroscope positioning device and method for subway pipe shed positioning measurement
CN113279693B (en) * 2021-05-09 2022-05-03 苏州中车建设工程有限公司 Structure for enabling newly built subway tunnel in soft soil body area to transversely penetrate existing tunnel and construction method of structure
CN114780907B (en) * 2022-06-22 2022-09-02 中国铁路设计集团有限公司 Method for determining surface settlement limit value of underpass road of subway interval tunnel

Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05112929A (en) * 1991-10-24 1993-05-07 Nippon Steel Corp Steel pipe pile column construction method
KR20070002328A (en) * 2005-06-30 2007-01-05 한미기초개발주식회사 Construction method of pipe roof structures
KR100825074B1 (en) * 2007-08-31 2008-04-24 윤인병 Pipe roof structures and construction method of piperoof structures
CN101215969A (en) * 2008-01-17 2008-07-09 上海交通大学 Large diameter tunneling close range down-traversing small diameter subway tunnel distortion control method
KR20090060608A (en) * 2007-12-10 2009-06-15 한미기초개발주식회사 Pipe roof structure and construction method thereof
CN202441393U (en) * 2012-02-10 2012-09-19 中南大学 Forepoling structure of horizontal rotary jet grouting and big pipe shed combined tunnel
CN202690065U (en) * 2012-05-25 2013-01-23 中铁四局集团有限公司 Reinforced structure formed by advanced treatment of weathering ball of impact drill in tunneling range of shield tunneling machine
CN204753606U (en) * 2015-07-06 2015-11-11 济南轨道交通集团有限公司 Modular curtain
CN205117357U (en) * 2015-11-21 2016-03-30 中铁二十局集团第二工程有限公司 Weak surrounding rock tunnel advance support structure based on self -drilling spiral pipe canopy
CN205172598U (en) * 2015-12-16 2016-04-20 海南大学 Pipe curtain spouts a supporting construction soon
CN205260041U (en) * 2015-12-26 2016-05-25 海南大学 Method of freezing supporting construction is spouted soon to level
WO2016095630A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Method for constructing extra-large variable cross section tunnel
CN105781557A (en) * 2016-03-25 2016-07-20 广东水电二局股份有限公司 Method for constructing underground excavated tunnel by adopting chemical grouting for sand layer consolidation
CN105781573A (en) * 2016-03-18 2016-07-20 中铁九局集团第六工程有限公司 Railway down-traversing highway tunnel double-layer casing pipe reinforcement double-pipe shed follow-pipe drilling construction method
CN105909259A (en) * 2016-06-12 2016-08-31 中铁十九局集团轨道交通工程有限公司 Pipe curtain construction settlement control system and method for close-range underpassing of existing shield tunnel
CN205936640U (en) * 2016-05-09 2017-02-08 铁道第三勘察设计院集团有限公司 Interior tub leading deep pre -reinforcing secant pile supporting construction in tunnel of canopy core that establishes
CN206158753U (en) * 2016-09-30 2017-05-10 中铁第一勘察设计院集团有限公司 Shield constructs well end bassoon canopy system of consolidating based on major structure
KR20170087786A (en) * 2016-01-21 2017-07-31 이평우 Reinforcement method of Tunnel
CN207620794U (en) * 2017-11-13 2018-07-17 浙江大学城市学院 The soil body composite reinforcing structure of the existing subway of weak soil shield crossing

Patent Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05112929A (en) * 1991-10-24 1993-05-07 Nippon Steel Corp Steel pipe pile column construction method
KR20070002328A (en) * 2005-06-30 2007-01-05 한미기초개발주식회사 Construction method of pipe roof structures
KR100825074B1 (en) * 2007-08-31 2008-04-24 윤인병 Pipe roof structures and construction method of piperoof structures
KR20090060608A (en) * 2007-12-10 2009-06-15 한미기초개발주식회사 Pipe roof structure and construction method thereof
CN101215969A (en) * 2008-01-17 2008-07-09 上海交通大学 Large diameter tunneling close range down-traversing small diameter subway tunnel distortion control method
CN202441393U (en) * 2012-02-10 2012-09-19 中南大学 Forepoling structure of horizontal rotary jet grouting and big pipe shed combined tunnel
CN202690065U (en) * 2012-05-25 2013-01-23 中铁四局集团有限公司 Reinforced structure formed by advanced treatment of weathering ball of impact drill in tunneling range of shield tunneling machine
WO2016095630A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Method for constructing extra-large variable cross section tunnel
CN204753606U (en) * 2015-07-06 2015-11-11 济南轨道交通集团有限公司 Modular curtain
CN205117357U (en) * 2015-11-21 2016-03-30 中铁二十局集团第二工程有限公司 Weak surrounding rock tunnel advance support structure based on self -drilling spiral pipe canopy
CN205172598U (en) * 2015-12-16 2016-04-20 海南大学 Pipe curtain spouts a supporting construction soon
CN205260041U (en) * 2015-12-26 2016-05-25 海南大学 Method of freezing supporting construction is spouted soon to level
KR20170087786A (en) * 2016-01-21 2017-07-31 이평우 Reinforcement method of Tunnel
CN105781573A (en) * 2016-03-18 2016-07-20 中铁九局集团第六工程有限公司 Railway down-traversing highway tunnel double-layer casing pipe reinforcement double-pipe shed follow-pipe drilling construction method
CN105781557A (en) * 2016-03-25 2016-07-20 广东水电二局股份有限公司 Method for constructing underground excavated tunnel by adopting chemical grouting for sand layer consolidation
CN205936640U (en) * 2016-05-09 2017-02-08 铁道第三勘察设计院集团有限公司 Interior tub leading deep pre -reinforcing secant pile supporting construction in tunnel of canopy core that establishes
CN105909259A (en) * 2016-06-12 2016-08-31 中铁十九局集团轨道交通工程有限公司 Pipe curtain construction settlement control system and method for close-range underpassing of existing shield tunnel
CN206158753U (en) * 2016-09-30 2017-05-10 中铁第一勘察设计院集团有限公司 Shield constructs well end bassoon canopy system of consolidating based on major structure
CN207620794U (en) * 2017-11-13 2018-07-17 浙江大学城市学院 The soil body composite reinforcing structure of the existing subway of weak soil shield crossing

Non-Patent Citations (7)

* Cited by examiner, † Cited by third party
Title
中铁二局股份有限公司.土木工程施工工艺.隧道及地铁工程.北京:中国铁道出版社,2009,(第1版),第177-184页. *
城市地铁硬岩隧道下穿既有隧道施工控制技术;马骏;国防交通工程与技术;第14卷(第1期);第49-52页 *
富水软弱围岩铁路隧道预加固技术;陈伟庚;铁道建筑(第5期);第104-106页 *
富水软弱地层隧道水平旋喷与大管棚预支护研究及应用;石钰锋等;岩土工程学报;第37卷(第S2期);第101-106页 *
武广铁路客运专线有限责任公司.武广铁路客运专线工程总结.北京:中国铁道出版社,2012,(第1版),第752页. *
软弱围岩隧道洞口段预加固技术研究;刘斌;《中国优秀硕士学位论文全文数据库工程科技Ⅱ辑》(第3期);第1-79页 *
长距离管棚加固技术在盾构下穿既有运营地铁线路中的应用;李建平等;施工技术;第46卷(第S1期);第782-784页 *

Also Published As

Publication number Publication date
CN107916935A (en) 2018-04-17

Similar Documents

Publication Publication Date Title
CN107916935B (en) Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method
CN100501124C (en) Construction method for tunnel contact passage in shield section of underground railway
CN101737060B (en) Beneath-soil through-tunnel superlarge diameter pipe curtain construction method
CN110056369B (en) Construction method for entrance and exit hole of tunnel
CN109322671B (en) Method for getting rid of worn and trapped shield cutter
CN112855188B (en) Subway engineering soft soil stratum earth pressure balance shield construction method
CN112554885B (en) Tunnel vertical shaft and transverse channel excavation method
CN111997624A (en) Shallow-buried large-section underground excavation rectangular tunnel construction method
CN110259466A (en) A kind of subway station water-rich sand layer big cross section shield-tunneling construction technique
WO2022117124A1 (en) Construction method for outward expansion pipe in drill hole in goaf
CN113107501B (en) Initial tunneling construction method for tunnel portal extension steel ring
CN112727470B (en) Construction reinforcing method for shield tunnel at overlapped section
CN112942441B (en) Pre-grouting water-stopping construction method for water-rich powder sand stratum
CN110777775A (en) Foundation pit structure and construction method thereof
CN207620794U (en) The soil body composite reinforcing structure of the existing subway of weak soil shield crossing
CN113266019B (en) Construction method of foundation pit steel pipe support system
CN115012955B (en) Construction method of multi-arch tunnel entrance big pipe shed
CN210459265U (en) Reinforced structure of high-voltage line tower
CN113338950A (en) Shield closed arrival construction method of freezing method and cement system combined steel sleeve
CN209397608U (en) A kind of high-pressure rotary-spray is put more energy into anchoring pile
CN113586080A (en) Pipe shed construction method
CN208330410U (en) A kind of Tunnel Passing crushed zone canopy protection structure
CN112554884B (en) Excavation method of tunnel vertical shaft
CN110144824A (en) Beret slice single side formwork method
CN118166783B (en) Construction method for active foundation reinforcement comprehensive support between new and old buildings

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant