CN205260041U - Method of freezing supporting construction is spouted soon to level - Google Patents
Method of freezing supporting construction is spouted soon to level Download PDFInfo
- Publication number
- CN205260041U CN205260041U CN201521096258.2U CN201521096258U CN205260041U CN 205260041 U CN205260041 U CN 205260041U CN 201521096258 U CN201521096258 U CN 201521096258U CN 205260041 U CN205260041 U CN 205260041U
- Authority
- CN
- China
- Prior art keywords
- level
- soon
- horizontal
- spouted
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
The utility model discloses a method of freezing supporting construction is spouted soon to level spouts to insert between the stake in adjacent level to be equipped with horizontal freezing pipe soon, through horizontal freezing pipe freeze make the soil body that adjacent level is spouted between the stake soon form a frozensoilwall. Construction principle as follows: (1 ), build the work well and receive the well, (2 ), the pile driving construction is spouted soon to the level, (3 ), horizontal freezing pipe construction between the stake is spouted soon to the level, (4 ), actively freeze, form method of freezing supporting construction is spouted soon to level, beneficial effect: the utility model discloses the freezing pipe materials significantly reduce, freeze to need cold volume also to significantly reduce, and the frozen swelling volume of sinking of melting is also very little, especially in the sealing effect, have practiced thrift the energy greatly guaranteeing to reinforce the effect to have better economic benefits, have great popularization and application and worth.
Description
Technical field
The utility model relates to a kind of supporting construction, particularly a kind of horizontal jet grouting freezing process supporting construction.
Background technology
At present, along with the acceleration of Urbanization Process In China, under downtown roads or important building, build large-scaleUnderground structure is more and more. For the large section of shallow embedding, short-range city tunnel, adopt shield method to executeWork is uneconomical, adopts cut and cover method to disturb larger to city productive life. When geological conditions is poor, buried depthWhen Sensitive Buildings is arranged at more shallow, top, if adopt shallow burial hidden digging construction, surface subsidence is difficult to control, and oneThere is construction accident in the dawn, will cause significant social influence. Therefore, how to find one to be suitable for saturated richnessThe constructing structure of wearing Sensitive Buildings under the shallow large-section underground structure of water soft soil layer is extremely important.
Horizontal jet grouting stake method is taking high-pressure pump as power source, prepares by horizontal drill drilling rod, nozzle handleSlurries are ejected in the soil body, and injection stream is penetrated the soil body in certain limit to wear with huge energy, and at nozzleCutting soil when making slow circumvolve and advance and retreat, forces a soil position to be mixed with slurry agitation. Treat that slurries solidifyAfter, forming horizontal circle column soil cement induration is horizontal jet grouting stake, can significantly improve the soil body intensity andArchitectural characteristic, when after the mutual interlock of rotary churning pile, just forms sealing with concentric circles form at tunnel vault and peripheryHorizontal jet grouting curtain body, play anti-quicksand, antiskid move, impermeable, anti-collapse and prevent because of tunnel excavationAnd make the effect of the ground settlement that the excessive dehydration in stratum causes.
Freezing process is to utilize artificial cooling technology, makes the water freezing in stratum, and natural ground is become to frozen soil,Increase its strength and stability, completely cut off contacting of underground water and underground engineering, so that under the protection of frost wallCarry out the special construction technology of underground engineering construction, its essence is and utilize artificial cooling Iterim Change rock and soil propertiesWith strengthening stratum. Artificial Soil freezing process, can be effective owing to not substantially being subject to the restriction of supporting scope and the supporting degree of depthPrevent the distortion of adjacent upper body during excavate in water burst and city, Drilling is constructed and be subject to increasing attention,Become one of technical way of underground engineering.
Summary of the invention
The purpose of this utility model is in order to solve shallow large-section underground structure in saturated rich water soft soil layerUnder wear the problem of Sensitive Buildings and a kind of horizontal jet grouting freezing process supporting construction of providing.
The horizontal jet grouting freezing process supporting construction that the utility model provides is to insert between adjacent horizontal jet grouting stakeBe provided with horizontal frozen pipe, by horizontal frozen pipe freeze make the soil body between adjacent level rotary churning pile form oneFrozen Soil Cylinder.
Construction Principle is as described below:
(1), construct active well and received well;
(2), horizontal jet grouting pile driving construction;
(3), horizontal frozen pipe construction between horizontal jet grouting stake, the number of horizontal frozen pipe is by the level designingRotary churning pile spacing and determining;
(4), actively freeze formation horizontal jet grouting freezing process supporting construction;
(5), in horizontal jet grouting freezing process supporting construction, excavate excavation limit, limit support (or employing box culvertJacking scheme performs internal structure);
(6) construct, piecemeal internal structure, and progressively remove horizontal jet grouting freezing process supporting construction inner support,The complete underground structure of final formation.
The beneficial effects of the utility model:
The utility model is that horizontal jet grouting stake support form and horizontal frozen support form are combined, and formsLarge rigidity watertightness horizontal jet grouting freezing process supporting construction, can effectively control the loss of underground water, ensures to executeWork and operation security, be particularly suitable as under the shallow large-section underground structure of saturated rich water soft soil layer, wear quickThe supporting construction of sense when construction, also can be applied to the soil stabilization of shield structure turnover termination, hole. If incite somebody to action thisUtility model supporting construction is vertically arranged, also can be applicable to the building enclosure of base pit engineering, and ground processingIn engineering. Compared with traditional horizontal freezing, the utility model freezing pipe materials greatly reduce, and freezing needsCold also greatly reduces, and frozen swell and melt settlement amount is also very little, ensureing that consolidation effect is particularly in stagnant water effect,Greatly save the energy, thereby there is good economic benefit, there is larger application value.
Brief description of the drawings
Fig. 1 is the utility model section structure schematic diagram.
1, horizontal jet grouting stake 2, horizontal frozen pipe 3, Frozen Soil Cylinder.
Detailed description of the invention
Refer to shown in Fig. 1:
The horizontal jet grouting freezing process supporting construction that the utility model provides is between adjacent horizontal jet grouting stake 1Be inserted with horizontal frozen pipe 2, freeze to make the soil body between adjacent level rotary churning pile 1 by horizontal frozen pipe 2Form a Frozen Soil Cylinder 3.
Construction Principle is as described below:
(1), construct active well and received well;
(2), horizontal jet grouting stake 1 is constructed;
(3), horizontal frozen pipe 2 is constructed between horizontal jet grouting stake 1, the number of horizontal frozen pipe 2 is by designingHorizontal jet grouting stake 1 spacing and determine;
(4), actively freeze formation horizontal jet grouting freezing process supporting construction;
(5), in horizontal jet grouting freezing process supporting construction, excavate excavation limit, limit support (or employing box culvertJacking scheme performs internal structure);
(6) construct, piecemeal internal structure, and progressively remove horizontal jet grouting freezing process supporting construction inner support,The complete underground structure of final formation.
Claims (1)
1. a horizontal jet grouting freezing process supporting construction, is characterized in that: be adjacent horizontal jet grouting stake itBetween be inserted with horizontal frozen pipe, freeze to make the soil body shape between adjacent level rotary churning pile by horizontal frozen pipeBecome a Frozen Soil Cylinder.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201521096258.2U CN205260041U (en) | 2015-12-26 | 2015-12-26 | Method of freezing supporting construction is spouted soon to level |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201521096258.2U CN205260041U (en) | 2015-12-26 | 2015-12-26 | Method of freezing supporting construction is spouted soon to level |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205260041U true CN205260041U (en) | 2016-05-25 |
Family
ID=56001571
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201521096258.2U Expired - Fee Related CN205260041U (en) | 2015-12-26 | 2015-12-26 | Method of freezing supporting construction is spouted soon to level |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205260041U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106351675A (en) * | 2016-09-30 | 2017-01-25 | 北京城建集团有限责任公司 | Total-depth curtain freezing and water stopping system of water and sand rich sandy gravel formation deeply-buried station excavated in concealed mode |
CN107916935A (en) * | 2017-11-13 | 2018-04-17 | 浙江大学城市学院 | A kind of soil body composite reinforcing structure and construction method of the existing subway of weak soil shield crossing |
CN108374672A (en) * | 2018-02-27 | 2018-08-07 | 中国矿业大学 | A method of reinforcing Deep Mine soft coal level roadway surrounding rock |
CN110030007A (en) * | 2019-05-06 | 2019-07-19 | 济南城建集团有限公司 | Shield horizontal freezing receives construction method |
CN112922608A (en) * | 2021-03-10 | 2021-06-08 | 上海隧道工程有限公司 | Method for reinforcing shield receiving tunnel portal |
CN114370280A (en) * | 2021-12-31 | 2022-04-19 | 刘侨 | Construction method of weak surrounding rock water-rich large-section tunnel |
-
2015
- 2015-12-26 CN CN201521096258.2U patent/CN205260041U/en not_active Expired - Fee Related
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106351675A (en) * | 2016-09-30 | 2017-01-25 | 北京城建集团有限责任公司 | Total-depth curtain freezing and water stopping system of water and sand rich sandy gravel formation deeply-buried station excavated in concealed mode |
CN107916935A (en) * | 2017-11-13 | 2018-04-17 | 浙江大学城市学院 | A kind of soil body composite reinforcing structure and construction method of the existing subway of weak soil shield crossing |
CN107916935B (en) * | 2017-11-13 | 2024-01-23 | 浙江大学城市学院 | Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method |
CN108374672A (en) * | 2018-02-27 | 2018-08-07 | 中国矿业大学 | A method of reinforcing Deep Mine soft coal level roadway surrounding rock |
CN108374672B (en) * | 2018-02-27 | 2019-04-30 | 中国矿业大学 | A method of reinforcing Deep Mine soft coal level roadway surrounding rock |
CN110030007A (en) * | 2019-05-06 | 2019-07-19 | 济南城建集团有限公司 | Shield horizontal freezing receives construction method |
CN112922608A (en) * | 2021-03-10 | 2021-06-08 | 上海隧道工程有限公司 | Method for reinforcing shield receiving tunnel portal |
CN114370280A (en) * | 2021-12-31 | 2022-04-19 | 刘侨 | Construction method of weak surrounding rock water-rich large-section tunnel |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205260041U (en) | Method of freezing supporting construction is spouted soon to level | |
CN102051886B (en) | Light well point drainage construction technology | |
CN103277120A (en) | Post-unfreezing water burst prevention method of non-full-depth freezing vertical shaft | |
CN206419017U (en) | Shallow tunnel with big cross-section freezing underground excavation constructing structure | |
CN102787846A (en) | Upper-blocking and lower-draining construction method for undersea tunnel fault fracture zone | |
CN114016513B (en) | Time-sequence-sharing excavation method of complex foundation pit group supporting system | |
CN103321233B (en) | The preparation method of groundwater resources retracting device in landslide deep layer draining and sliding mass | |
CN110984200B (en) | Method for draining water of foundation pit of binary geological structure layer | |
CN108867673A (en) | A kind of underwater prevention method in the foundation pit based on the curtain that draws water | |
CN203463016U (en) | Three-axle agitator drill suitable for piercing gravel layer soil | |
CN103572764A (en) | Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof | |
CN206204972U (en) | A kind of prefabricated tubular pile as well-points dewatering | |
CN105112652B (en) | A kind of rare earth ore in-situ leaching disposing mother liquor canal body structure | |
CN105971638A (en) | Application of WSS construction method in shield tool changing reinforcement of water-rich sand layer | |
CN105971637A (en) | Application of WSS construction method in shield end reinforcement of water-rich sand layer | |
CN105040705A (en) | Ground foundation treatment construction technology under multi-karst-cave geological conditions | |
CN206800431U (en) | A kind of sealing bottom type caisson wall | |
CN103437712B (en) | A kind ofly be applicable to the three axle mixer drill bits penetrating gravel layer soil property | |
CN207406345U (en) | Rich water sand-pebble layer shield tunnel end horizontal grouting ruggedized construction | |
CN111910665B (en) | Precipitation treatment method for steeply inclined strip-shaped interbedded composite stratum foundation pit | |
CN102995647A (en) | Underground water control method used for grouting and seepage insulation of pile hole | |
CN110259456B (en) | Karst cave treatment method for tunnel construction | |
CN204609897U (en) | A kind of pipe curtain freezing process supporting and protection structure | |
CN102425179B (en) | Reinforced soil infiltration ditch structure supported by miniature steel pipe cast-in-place pile | |
CN1130712A (en) | Drainage cut-off (deep ditch high-building method) drainage and supplying optimization combination for preventing and harnessing groud water |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160525 Termination date: 20171226 |