CN110259466A - A kind of subway station water-rich sand layer big cross section shield-tunneling construction technique - Google Patents

A kind of subway station water-rich sand layer big cross section shield-tunneling construction technique Download PDF

Info

Publication number
CN110259466A
CN110259466A CN201910606986.XA CN201910606986A CN110259466A CN 110259466 A CN110259466 A CN 110259466A CN 201910606986 A CN201910606986 A CN 201910606986A CN 110259466 A CN110259466 A CN 110259466A
Authority
CN
China
Prior art keywords
shield
section
water
portal
jurisdiction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910606986.XA
Other languages
Chinese (zh)
Other versions
CN110259466B (en
Inventor
马国松
石超
程杰
李双美
常顺
王文威
宋昱宇
吕帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 25th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd
Original Assignee
China Railway 25th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 25th Bureau Group Co Ltd, Fifth Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd filed Critical China Railway 25th Bureau Group Co Ltd
Priority to CN201910606986.XA priority Critical patent/CN110259466B/en
Publication of CN110259466A publication Critical patent/CN110259466A/en
Application granted granted Critical
Publication of CN110259466B publication Critical patent/CN110259466B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0635Tail sealing means, e.g. used as end shuttering

Abstract

The present invention relates to a kind of subway station water-rich sand layer big cross section shield-tunneling construction techniques, comprising the following steps: step 1, Farm Planning, step 2, place is hardened, step 3, it receives bracket to go into the well, put and reinforce, step 4, portal and end reinforce coring, step 5, step 6 attitude of shield machine adjustment receives measurement monitoring, step 7, arrival is constructed.The present invention have can construction when shield machine reaches ventilating shaft suitable for water-rich sand layer big cross section geology, avoid there is a situation where water burst, gush sand or the effect that generates of collapsing.

Description

A kind of subway station water-rich sand layer big cross section shield-tunneling construction technique
Technical field
The present invention relates to the technical fields of shield machine construction, more particularly, to a kind of subway station water-rich sand layer big cross section shield Structure construction technology.
Background technique
It is major with the fast development of urban rail transit in China construction and stepping up for underground space utilization rate City joined subway work ranks one after another, shield method tunnel construction technology with its exclusive intelligence, safely, quickly, it is high The features such as effect and advantage are more and more widely promoted and are applied.
In subway work, shield construction is each construction most important thing;Meanwhile it according to different construction environments and applying Work condition needs construction personnel for different construction environments to adjust construction technology, and in a variety of construction environments, section is rich Water sand layer is more special construction environment, and due to catalase in fracture belt, rich groundwater, when shield crossing fracture belt is easy Gush, situations such as face collapses, inter alia, in that water-rich sand layer geological conditions is poor, when shield machine reaches cannot from steady, Easily liquefy with water, and in layer of sand be rich in underground water, good penetrability, reach ventilating shaft process easily there is a phenomenon where water burst, gush sand, It may cause the serious accidents such as ground collapsing when serious.
Summary of the invention
The object of the present invention is to provide a kind of subway station water-rich sand layer big cross section shield-tunneling construction techniques, and having can be applicable in Construction in water-rich sand layer big cross section geology when shield machine arrival ventilating shaft avoids there is a situation where water burst, gushes sand or production of collapsing Raw effect.
Foregoing invention purpose of the invention has the technical scheme that
A kind of subway station water-rich sand layer big cross section shield-tunneling construction technique, it is characterised in that: the following steps are included:
Step 1, Farm Planning: clearing up construction site, carries out repetition measurement to shield well main body, measures actual deviation amount, be Arrival provides data and supports;
Step 2, place harden: the level of ground water around portal is down to portal elevation of bottom hereinafter, place use compactness for It is mixed to be laid with the double-deck mesh sheet that 14 spacing of φ is 20cm × 20cm, the high spacing of layer is 15cm for the C30 concrete backfill of 2400kg/m3 Solidifying soil, thickness are not less than 20cm;
Step 3, it receives bracket to go into the well, put and reinforce: being accurately positioned the left-right position of originating station before mounting bracket;Shield is left The absolute altitude that right line bracket originates pedestal reduces 10mm, prevents shield machine from " gnawing " bracket, is then installed in bracket as required pre- It on fixed position, is checked, after completing positioning, bracket is fixed;
Step 4, portal and end reinforce coring: carrying out vertical and horizontal boring and coring to portal before shield receives, vertically take Core carries out boring and coring operation using geological drilling rig;
Step 5, attitude of shield machine adjusts: in shield driving to arrival range, carrying out to the position of shield machine accurate Measurement, the clear relationship at hole tunnel central axis and Tunnel Design central axis, while to reception portal and bracket locations into Row review measurement determines the perforation posture and driving correction plan of shield machine;
Step 6, receive measurement monitoring: during arrival driving, shield attitude and section of jurisdiction posture must assure that every ring one is surveyed, And the result of manual measurement is fed back into shield Central Control Room, lasting progress in ground monitoring 24 hours;
Step 7, arrival is constructed:
A, reaching section axis is straight line, when cutter head of shield machine contacts plain concrete wall, it is ensured that shield machine horizontal attitude and perpendicular attitude with Axis is overlapped, and deviation allowable value is ± 5mm;
B, it must assure that synchronous grouting amount 12m3 when reaching section construction, and second pulp feeding needs synchronized tracking slip casting, mend slurry slurries Using dual slurry;
C, after shield machine shield tail passes through plain concrete wall, survey crew positions plain concrete wall displacement, makes seal ring in plain concrete wall displacement, Prevent rear water;
D, the of short duration shutdown after cutterhead contacts building enclosure, downtime are 2~3 hours, observe pressure change in native storehouse, judgement Rear water situation can carry out next step construction procedure if soil pressure is held essentially constant, if soil pressure changes greatly, carry out immediately Second pulp feeding after stopping slip casting, continues to observe soil pressure variation, if soil pressure still has significant change, continues slip casting, until stopping infusing After slurry, soil pressure is unchanged, while checking whether equipment is problematic, prevents brokenly equipment after wall from stopping working suddenly, water burst is caused to gush It is husky;
E, after meeting condition of acceptance, start rotor mill building enclosure, driving speed is maintained at 5mm~10mm/min;
F, cutterhead is by if the gap water burst between excavation face and shield body gushes sand, continuing to tunnel, in cord rubber after building enclosure After the fully wrapped around firmly shield body of offset plate, a injected hole reserved from section of jurisdiction carries out slip casting, if hydraulic pressure is larger, and without quicksand phenomenon, then Polyurethane is injected into hole, if flowing water quicksand, injects dual slurry;It tunnels to shield machine to section of jurisdiction and only stays last one of shield tail brush When, stop driving, a circle wirerope, and tense wire rope are bundled on the outside of cord rubber slab, is prevented because grouting pressure is excessive, slurry Liquid is gushed out from cord rubber slab and shield body gap, finally continues to reserve injected hole injection slurries from section of jurisdiction, until anhydrous outflow;
G, grouting quality is checked in last endless tube piece slip casting hole site aperture, if from tapping flowing water, no flowing water then continues Driving, until last shield tail completely disengages section of jurisdiction;
H, after the completely out shield tail of shield tail, portal closure is carried out immediately, prevents from leading to portal reinforcing body because exposure duration is too long Failure, causes water burst to gush sand.
By using above-mentioned technical proposal, the construction that can be constructed when reaching ventilating shaft convenient for shield machine in water-rich sand layer is kept away Exempt from there is a phenomenon where water burst, gush sand.
The present invention is further arranged to: the step 7 further includes the installation of last ring plate, and the installation of last ring plate includes Following steps:
A, installation section of jurisdiction, which is finished, tightens all vertical and horizontal bolts with pneumatic impact wrench, and when next ring is tunneled to 1.2m or so Fastening bolt again need to tighten up three times section of jurisdiction, and be attached tricyclic section of jurisdiction with channel steel in injected hole, connect between every tricyclic It connects at no less than six, and arranged in dislocation, installation length is no less than 15 rings;
B, stringent segment assembly prevents between section of jurisdiction and the fissure of displacement, step difference occurs;During assembly, guarantee gap of the shield tail, The injection rate of shield tail grease is increased, and keeps synchronous grouting, shield tail water burst is prevented, gushes sand;
C, it should ensure that sealing rod is not damaged, is not pre-expanded before the installation of section of jurisdiction, and clean out the soil of the quarrel on section of jurisdiction and mortar in time Deng;It also needs to clean out at shield tail, guarantees pipe sheet assembling quality.
The present invention is further arranged to: the step 7 further includes portal sealing, portal sealing the following steps are included:
A, measures of preventing water when promoting during arrival, carries out dual slurry slip casting after shield tail, and every ring all repeatedly, is repeatedly mended Dual slurry is infused, by the radial hole of body in shield, dual slurry is infused to outside shield body, blocks the gap between shield body and the soil body, is guaranteed same Walk grouting amount and grind slurries quality;
B, stop driving measures of preventing water, after shield stops, dual slurry is injected in the section of jurisdiction tunnel of portal position, reinforce sealing effect Fruit thoroughly blocks the gap between section of jurisdiction and portal, every endless tube piece two sides hole for hoist aperture as inspection hole, Checking on effect.
The present invention is further arranged to: double slurries use cement and water ratio for the slurries of 1:0.8 and water and water Glass ratio is the slurries of 1:1 as second pulp feeding material.
The present invention is further arranged to: the grouting pressure value are as follows: 0.1~0.3Mpa.
The present invention is further arranged to: the step 4, portal and end reinforce coring the following steps are included:
(1) vertical and horizontal boring and coring is carried out to portal before shield receives, vertical coring is drilled using geological drilling rig Coring, reinforcing body amount detection must not be less than 1%, and must not be less than 5;
(2) ensure that drilling machine not run-off the straight, displacement, drill core hole perpendicularity deviation during drill core are not more than 0.5%;
(3) when stake top face is larger at a distance from rig substructure, mounting hole pipe is answered, orifice tube should be vertical and secured;
(4) in drilling process, the interior circulating water flow that drills must not be interrupted, and should adjust rate of penetration according to return water sand content and color;
(5) when mentioning brill and unloading coring sample, unloading drill bit and reamer are forbidden to beat and unload core;
(6) every footage per round trip preferably controls in 1.5m, when being drilled into bottom, drills through sediment and measures sediment thickness, and support to stake Power layer ground character is identified.
The present invention is further arranged to: the step 5, and shield attitude and tunnel are reinforced in the location 50m before shield machine reaches Road linear measurement, timely correction deviation, it is ensured that shield successfully enters from arrival mouth.
The present invention is further arranged to: shield when necessary adjustment tunnel holing through is carried out according to the station portal position of actual measurement Structure machine knife disk position, its cutterhead plane deviation permissible value is plane≤± 20mm, elevation≤± 20mm, shield slope when tunnel holing through Degree bigger compared with design grade 0.2%.
The present invention is further arranged to: the step 6, and 3 row monitoring points are arranged in earth's surface, and spacing 5m mono-, covering is entire Reception area, the situation of change of each measuring point is measured by datum mark, and is made a record, and with original number ready-made before engineering construction It compares according to record.
In conclusion advantageous effects of the invention are as follows:
With can suitable for water-rich sand layer big cross section geology shield machine reach ventilating shaft when construction, avoid occur water burst, gush The case where sand or collapsing, generates.
Specific embodiment
For a kind of subway station water-rich sand layer big cross section arrival construction technology disclosed by the invention, including following step It is rapid:
Step 1, Farm Planning:
(1) construction site prepares, and clears up construction site, and install the corollary equipments such as water pump and headlamp, to receive work It is ready work;
(2) portal repetition measurement and measure axis, project management department should organize survey crew to carry out repetition measurement to shield well main body, and measurement is practical inclined Residual quantity provides data for arrival and supports, main repetition measurement project includes: shield well floor level, bottom plate longitudinal slope, in portal The heart, side wall and headwall location and gradient, bottom girder position;
Step 2, end precipitation and the hardening of end place are reached:
Consolidate situation according to hydrogeologic condition and arrival end soil body power mouth, the level of ground water around portal is down to portal bottom Absolute altitude is hereinafter, the large-scale crane that shield machine lifting uses, lifting region use compactness to return for the C30 concrete of 2400kg/m3 It fills out, is laid with φ 14 and asks away from the double-deck mesh sheet concrete thickness for being 15cm for 20cm × 20cm, the high spacing of layer not less than 20cm, perform It can satisfy after 28 days needed for shield lifting;
Step 3, bracket is received to go into the well, put and reinforce:
(1) first by measurement group, bottom plate fixes two level control points (one is fixed on portal center AT STATION before mounting bracket On line, another is tunnel center line), the left-right position of originating station is accurately positioned according to the bracing wire of two o'clock;Shield or so line support The absolute altitude that frame originates pedestal reduces 10mm, prevents shield machine from " gnawing " bracket, then bracket is installed in scheduled position as required It sets, and is checked by measurement group, after completing positioning, bracket is fixed;
(2) before shield machine reception, hard lubricating oil is applied on the track of originating station to reduce shield machine on bracket to being pushed forward Into when resistance, rail level and carriage rail rail level be in the same plane on bracket;
Step 4, portal and end reinforce coring:
(1) vertical and horizontal boring and coring is carried out to portal before shield receives, vertical coring is drilled using geological drilling rig Coring, reinforcing body amount detection must not be less than 1%, and must not be less than 5, and the drill core hole count and bore position by inspection stake are answered Meet: the 1 drill core hole a every, b position of opening are located at two occlusion positions;
(2) drilling equipment installation must it is straight, firm, pedestal is horizontal, drilling machine vertical shaft center, head sheave center (overhead traveling crane forward position point of contact) It must be on same plumb line with orifice center, it should be ensured that drilling machine not run-off the straight, displacement, drill core hole during drill core is vertical It spends deviation and is not more than 0.5%;
(3) when stake top face is larger at a distance from rig substructure, mounting hole pipe is answered, orifice tube should be vertical and secured;
(4) in drilling process, the interior circulating water flow that drills must not be interrupted, and should adjust rate of penetration according to return water sand content and color;
(5) when mentioning brill and unloading coring sample, unloading drill bit and reamer is answered, forbids to beat and unloads core;
(6) every footage per round trip preferably controls in 1.5m, when being drilled into bottom, drills through sediment and measures sediment thickness, and support to stake Power layer ground character is identified;
Step 5, attitude of shield machine adjusts;
(1) in shield driving to arrival range, the position of shield machine is accurately measured, it is clear in hole tunnel The relationship of mandrel line and Tunnel Design central axis;
(2) review measurement is carried out to receiving portal and bracket locations, determine the perforation posture and driving attitude and driving of shield machine Correction plan, correction will be gradually completing;
(3) shield attitude and tunnel linear measurement are reinforced in the location 50m before shield machine reaches, and timely correction deviation ensures that shield is suitable Sharply enter from arrival mouth;
(4) cutter head of shield machine position when necessary adjustment tunnel holing through is carried out according to the station portal position of actual measurement, tunnel passes through Its cutterhead plane deviation permissible value is plane≤± 20mm, elevation≤± 20mm when logical, and the shield gradient is bigger compared with design grade 0.2%;
Step 6, measurement monitoring is received:
(1) during arrival driving, shield attitude and section of jurisdiction posture must assure that every ring one is surveyed, and in time by manual measurement Result feedback shield responsible person and Central Control Room, and report and submit management in time, ground monitoring want 24 hours two classes it is lasting carry out, monitoring Data will be conveyed in time;
(2) 3 row monitoring points are arranged in earth's surface, spacing 5m mono-, cover entire reception area, the variation of each measuring point is measured by datum mark Situation, and make a record, and compared with original data record ready-made before engineering construction;
Step 7, arrival is constructed:
(1) section working measure is reached:
A, reaching section axis is straight line, when cutter head of shield machine contacts plain concrete wall, it is ensured that shield machine horizontal attitude and perpendicular attitude with Axis is overlapped, and deviation allowable value is ± 5mm;
B, it must assure that synchronous grouting amount (12m3) when reaching section construction, and second pulp feeding needs synchronized tracking slip casting, mend slurry slurry Liquid uses dual slurry;
C, after shield machine shield tail passes through plain concrete wall, survey crew positions plain concrete wall displacement, makes seal ring in plain concrete wall displacement, Prevent rear water;
D, the of short duration shutdown after cutterhead contacts building enclosure, downtime are 2~3 hours, pressure change in main detection soil storehouse, Judge rear water situation, if soil pressure is held essentially constant, next step construction procedure can be carried out;If soil pressure changes greatly, immediately Carry out second pulp feeding, and follow a small amount of multiple principle, after stopping slip casting, continue to observe soil pressure variation, if soil pressure still have it is bright Aobvious variation, continues slip casting, after stopping slip casting, soil pressure is unchanged, while checking whether equipment is problematic, sets after preventing brokenly wall It is standby to stop working suddenly, cause water burst to gush sand;
E, after meeting condition of acceptance, start rotor mill building enclosure, driving speed is maintained at 5mm~10mm/min;
F, cutterhead is by if the gap water burst between excavation face and shield body gushes sand, continuing to tunnel, in cord rubber after building enclosure After the fully wrapped around firmly shield body of offset plate, a injected hole reserved from section of jurisdiction carries out slip casting, if hydraulic pressure is larger, and without quicksand phenomenon, then Polyurethane is injected into hole, if flowing water quicksand, injects dual slurry;It tunnels to shield machine to section of jurisdiction and only stays last one of shield tail brush When, stop driving, a circle wirerope, and tense wire rope are bundled on the outside of cord rubber slab, is prevented because grouting pressure is excessive, slurry Liquid is gushed out from cord rubber slab and shield body gap, finally continues to reserve injected hole injection slurries from section of jurisdiction, until anhydrous outflow;
G, grouting quality is checked in last endless tube piece slip casting hole site aperture, if from tapping flowing water, no flowing water then continues Driving, until last shield tail completely disengages section of jurisdiction;
H, after the completely out shield tail of shield tail, portal closure is carried out immediately, prevents from leading to portal reinforcing body because exposure duration is too long Failure, causes water burst to gush sand;
(2) installation of final tache section of jurisdiction:
A, installation section of jurisdiction, which is finished, tightens all vertical and horizontal bolts with pneumatic impact wrench, and when next ring is tunneled to 1.2m or so Fastening bolt again need to tighten up three times section of jurisdiction, and be attached tricyclic section of jurisdiction with channel steel in injected hole, connect between every tricyclic It connects at no less than six, and arranged in dislocation, installation length is no less than 15 rings;
B, it in strict accordance with operating instruction segment assembly, while preventing between section of jurisdiction and the fissure of displacement, step difference occurs;In assembled process In, guarantee gap of the shield tail, increase the injection rate of shield tail grease, and keep synchronous grouting, prevents shield tail water burst, gushes sand
C, it should ensure that sealing rod is not damaged, is not pre-expanded before the installation of section of jurisdiction, and clean out the soil of the quarrel on section of jurisdiction and mortar in time Deng;It also needs to clean out at shield tail, guarantees pipe sheet assembling quality.(2) portal sealing:
A, measures of preventing water when promoting during arrival, carries out dual slurry slip casting after shield tail, and every ring all repeatedly, is repeatedly mended Dual slurry is infused, by the radial hole of body in shield, dual slurry is infused to outside shield body, blocks the gap between shield body and the soil body, is guaranteed same Walk grouting amount and grind slurries quality;
B, stop driving measures of preventing water, after shield stops, dual slurry is injected in the section of jurisdiction tunnel of portal position, reinforce sealing effect Fruit thoroughly blocks the gap between section of jurisdiction and portal, every endless tube piece two sides hole for hoist aperture as inspection hole, Checking on effect;
C, dual slurry slip casting: the slurries for using cement and water ratio to be 1:1 for the slurries of 1:0.8 and water and waterglass ratio are made For second pulp feeding material, grouting pressure value are as follows: 0.1~0.3Mpa;
This technique can suitable for water-rich sand layer big cross section geology shield machine reach ventilating shaft when construction, avoid occur water burst, The case where gushing sand or collapsing generation.
The embodiment of present embodiment is presently preferred embodiments of the present invention, not limits protection of the invention according to this Range, therefore: the equivalence changes that all structures under this invention, shape, principle are done, should all be covered by protection scope of the present invention it It is interior.

Claims (9)

1. a kind of subway station water-rich sand layer big cross section shield-tunneling construction technique, it is characterised in that: the following steps are included:
Step 1, Farm Planning: clearing up construction site, carries out repetition measurement to shield well main body, measures actual deviation amount, be Arrival provides data and supports;
Step 2, place harden: the level of ground water around portal is down to portal elevation of bottom hereinafter, place use compactness for It is mixed to be laid with the double-deck mesh sheet that 14 spacing of φ is 20cm × 20cm, the high spacing of layer is 15cm for the C30 concrete backfill of 2400kg/m3 Solidifying soil, thickness are not less than 20cm;
Step 3, it receives bracket to go into the well, put and reinforce: being accurately positioned the left-right position of originating station before mounting bracket;Shield is left The absolute altitude that right line bracket originates pedestal reduces 10mm, prevents shield machine from " gnawing " bracket, is then installed in bracket as required pre- It on fixed position, is checked, after completing positioning, bracket is fixed;
Step 4, portal and end reinforce coring: carrying out vertical and horizontal boring and coring to portal before shield receives, vertically take Core carries out boring and coring operation using geological drilling rig;
Step 5, attitude of shield machine adjusts: in shield driving to arrival range, carrying out to the position of shield machine accurate Measurement, the clear relationship at hole tunnel central axis and Tunnel Design central axis, while to reception portal and bracket locations into Row review measurement determines the perforation posture and driving correction plan of shield machine;
Step 6, receive measurement monitoring: during arrival driving, shield attitude and section of jurisdiction posture must assure that every ring one is surveyed, And the result of manual measurement is fed back into shield Central Control Room, lasting progress in ground monitoring 24 hours;
Step 7, arrival is constructed:
A, reaching section axis is straight line, when cutter head of shield machine contacts plain concrete wall, it is ensured that shield machine horizontal attitude and perpendicular attitude with Axis is overlapped, and deviation allowable value is ± 5mm;
B, it must assure that synchronous grouting amount 12m3 when reaching section construction, and second pulp feeding needs synchronized tracking slip casting, mend slurry slurries Using dual slurry;
C, after shield machine shield tail passes through plain concrete wall, survey crew positions plain concrete wall displacement, makes seal ring in plain concrete wall displacement, Prevent rear water;
D, the of short duration shutdown after cutterhead contacts building enclosure, downtime are 2~3 hours, observe pressure change in native storehouse, judgement Rear water situation can carry out next step construction procedure if soil pressure is held essentially constant, if soil pressure changes greatly, carry out immediately Second pulp feeding after stopping slip casting, continues to observe soil pressure variation, if soil pressure still has significant change, continues slip casting, until stopping infusing After slurry, soil pressure is unchanged, while checking whether equipment is problematic, prevents brokenly equipment after wall from stopping working suddenly, water burst is caused to gush It is husky;
E, after meeting condition of acceptance, start rotor mill building enclosure, driving speed is maintained at 5mm~10mm/min;
F, cutterhead is by if the gap water burst between excavation face and shield body gushes sand, continuing to tunnel, in cord rubber after building enclosure After the fully wrapped around firmly shield body of offset plate, a injected hole reserved from section of jurisdiction carries out slip casting, if hydraulic pressure is larger, and without quicksand phenomenon, then Polyurethane is injected into hole, if flowing water quicksand, injects dual slurry;It tunnels to shield machine to section of jurisdiction and only stays last one of shield tail brush When, stop driving, a circle wirerope, and tense wire rope are bundled on the outside of cord rubber slab, is prevented because grouting pressure is excessive, slurry Liquid is gushed out from cord rubber slab and shield body gap, finally continues to reserve injected hole injection slurries from section of jurisdiction, until anhydrous outflow;
G, grouting quality is checked in last endless tube piece slip casting hole site aperture, if from tapping flowing water, no flowing water then continues Driving, until last shield tail completely disengages section of jurisdiction;
H, after the completely out shield tail of shield tail, portal closure is carried out immediately, prevents from leading to portal reinforcing body because exposure duration is too long Failure, causes water burst to gush sand.
2. a kind of subway station water-rich sand layer big cross section shield-tunneling construction technique according to claim 1, it is characterised in that: institute The step 7 stated, further includes the installation of last ring plate, the installation of last ring plate the following steps are included:
A, installation section of jurisdiction, which is finished, tightens all vertical and horizontal bolts with pneumatic impact wrench, and when next ring is tunneled to 1.2m or so Fastening bolt again need to tighten up three times section of jurisdiction, and be attached tricyclic section of jurisdiction with channel steel in injected hole, connect between every tricyclic It connects at no less than six, and arranged in dislocation, installation length is no less than 15 rings;
B, stringent segment assembly prevents between section of jurisdiction and the fissure of displacement, step difference occurs;During assembly, guarantee gap of the shield tail, The injection rate of shield tail grease is increased, and keeps synchronous grouting, shield tail water burst is prevented, gushes sand;
C, it should ensure that sealing rod is not damaged, is not pre-expanded before the installation of section of jurisdiction, and clean out the soil of the quarrel on section of jurisdiction and mortar in time Deng;It also needs to clean out at shield tail, guarantees pipe sheet assembling quality.
3. a kind of subway station water-rich sand layer big cross section shield-tunneling construction technique according to claim 1, it is characterised in that: institute The step 7 stated, further includes portal sealing, portal sealing the following steps are included:
A, measures of preventing water when promoting during arrival, carries out dual slurry slip casting after shield tail, and every ring all repeatedly, is repeatedly mended Dual slurry is infused, by the radial hole of body in shield, dual slurry is infused to outside shield body, blocks the gap between shield body and the soil body, is guaranteed same Walk grouting amount and grind slurries quality;
B, stop driving measures of preventing water, after shield stops, dual slurry is injected in the section of jurisdiction tunnel of portal position, reinforce sealing effect Fruit thoroughly blocks the gap between section of jurisdiction and portal, every endless tube piece two sides hole for hoist aperture as inspection hole, Checking on effect.
4. a kind of subway station water-rich sand layer big cross section shield-tunneling construction technique according to claim 3, it is characterised in that: institute State double slurries use cement and water ratio for the slurries of 1:0.8 and water and waterglass ratio be 1:1 slurries as secondary benefit Pulp material.
5. a kind of subway station water-rich sand layer big cross section shield-tunneling construction technique according to claim 4, it is characterised in that: institute State grouting pressure value are as follows: 0.1~0.3Mpa.
6. a kind of subway station water-rich sand layer big cross section shield-tunneling construction technique according to claim 1, it is characterised in that: institute The step 4 stated, portal and end reinforce coring the following steps are included:
(1) vertical and horizontal boring and coring is carried out to portal before shield receives, vertical coring is drilled using geological drilling rig Coring, reinforcing body amount detection must not be less than 1%, and must not be less than 5;
(2) ensure that drilling machine not run-off the straight, displacement, drill core hole perpendicularity deviation during drill core are not more than 0.5%;
(3) when stake top face is larger at a distance from rig substructure, mounting hole pipe is answered, orifice tube should be vertical and secured;
(4) in drilling process, the interior circulating water flow that drills must not be interrupted, and should adjust rate of penetration according to return water sand content and color;
(5) when mentioning brill and unloading coring sample, unloading drill bit and reamer are forbidden to beat and unload core;
(6) every footage per round trip preferably controls in 1.5m, when being drilled into bottom, drills through sediment and measures sediment thickness, and support to stake Power layer ground character is identified.
7. a kind of subway station water-rich sand layer big cross section shield-tunneling construction technique according to claim 1, it is characterised in that: institute The step 5 stated, shield attitude and tunnel linear measurement, timely correction deviation, it is ensured that shield are reinforced in the location 50m before shield machine reaches Structure successfully enters from arrival mouth.
8. a kind of subway station water-rich sand layer big cross section shield-tunneling construction technique according to claim 7, it is characterised in that: root The station portal position factually surveyed carries out cutter head of shield machine position when necessary adjustment tunnel holing through, its cutterhead when tunnel holing through Plane deviation permissible value is plane≤± 20mm, elevation≤± 20mm, the shield gradient bigger compared with design grade 0.2%.
9. a kind of subway station water-rich sand layer big cross section shield-tunneling construction technique according to claim 1, it is characterised in that: institute The step 6 stated, earth's surface are arranged 3 row monitoring points, spacing 5m mono-, cover entire reception area, measure each measuring point by datum mark Situation of change, and make a record, and compared with original data record ready-made before engineering construction.
CN201910606986.XA 2019-07-06 2019-07-06 Large-section shield construction process for water-rich sand layer of subway station Active CN110259466B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910606986.XA CN110259466B (en) 2019-07-06 2019-07-06 Large-section shield construction process for water-rich sand layer of subway station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910606986.XA CN110259466B (en) 2019-07-06 2019-07-06 Large-section shield construction process for water-rich sand layer of subway station

Publications (2)

Publication Number Publication Date
CN110259466A true CN110259466A (en) 2019-09-20
CN110259466B CN110259466B (en) 2020-11-03

Family

ID=67924788

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910606986.XA Active CN110259466B (en) 2019-07-06 2019-07-06 Large-section shield construction process for water-rich sand layer of subway station

Country Status (1)

Country Link
CN (1) CN110259466B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111400645A (en) * 2020-03-20 2020-07-10 南京坤拓土木工程科技有限公司 Simplified method for estimating soil pressure distribution condition of water-rich sand layer at opening of cutter head
CN112943266A (en) * 2021-03-15 2021-06-11 广东工业大学 Method for reinforcing water-rich sand layer with high-flow-rate underground water through high-pressure rotary jet grouting
CN113482632A (en) * 2021-08-12 2021-10-08 中铁十二局集团有限公司 Shield tunneling machine starting construction method with external water-rich silt stratum grouting pipe
CN114320321A (en) * 2021-12-20 2022-04-12 中国水利水电第十四工程局有限公司 Receiving construction method for shield machine in composite stratum with sand layer

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101975067A (en) * 2010-10-20 2011-02-16 中铁隧道集团二处有限公司 Light-section mud shield powder fine sand layer receiving method
CN102913250A (en) * 2012-11-12 2013-02-06 中铁二局股份有限公司 Shield tunnel-entering construction method at stratum rich in water powder and soil powder sand
CN105863656A (en) * 2016-04-07 2016-08-17 国家电网公司 Shield tunneling method
CN106869949A (en) * 2017-02-10 2017-06-20 莫绍愚 A kind of method that shield machine is received with steel bushing
CN108625863A (en) * 2018-03-21 2018-10-09 浙江大学城市学院 A kind of weak soil shield receives control and reinforcement means

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101975067A (en) * 2010-10-20 2011-02-16 中铁隧道集团二处有限公司 Light-section mud shield powder fine sand layer receiving method
CN102913250A (en) * 2012-11-12 2013-02-06 中铁二局股份有限公司 Shield tunnel-entering construction method at stratum rich in water powder and soil powder sand
CN105863656A (en) * 2016-04-07 2016-08-17 国家电网公司 Shield tunneling method
CN105863656B (en) * 2016-04-07 2018-08-24 国家电网公司 A kind of shield driving method
CN106869949A (en) * 2017-02-10 2017-06-20 莫绍愚 A kind of method that shield machine is received with steel bushing
CN108625863A (en) * 2018-03-21 2018-10-09 浙江大学城市学院 A kind of weak soil shield receives control and reinforcement means

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111400645A (en) * 2020-03-20 2020-07-10 南京坤拓土木工程科技有限公司 Simplified method for estimating soil pressure distribution condition of water-rich sand layer at opening of cutter head
CN112943266A (en) * 2021-03-15 2021-06-11 广东工业大学 Method for reinforcing water-rich sand layer with high-flow-rate underground water through high-pressure rotary jet grouting
CN113482632A (en) * 2021-08-12 2021-10-08 中铁十二局集团有限公司 Shield tunneling machine starting construction method with external water-rich silt stratum grouting pipe
CN114320321A (en) * 2021-12-20 2022-04-12 中国水利水电第十四工程局有限公司 Receiving construction method for shield machine in composite stratum with sand layer

Also Published As

Publication number Publication date
CN110259466B (en) 2020-11-03

Similar Documents

Publication Publication Date Title
CN110259466A (en) A kind of subway station water-rich sand layer big cross section shield-tunneling construction technique
CN100501124C (en) Construction method for tunnel contact passage in shield section of underground railway
CN108678777B (en) Support method for tunnel fault fracture zone section
CN102277898B (en) Drain pipe jacking construction method
CN110230499B (en) Active protection structure of shield near-penetration operation tunnel in water-rich soft soil area and construction method
CN107916935B (en) Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method
CN109611102B (en) Construction method for cold excavation underpass overpass
CN103046638A (en) Pipe jacking construction method
CN104631470A (en) Deep foundation pit combination retaining and protecting construction method for geology with high water level and large particle size sand gravel
CN103015519A (en) Pipe-jacking construction of drain pipe
CN108590706A (en) One kind being used for speciality single-track railway tunnel drifter with booms Construction Techniques of Grouting in Heavy Curtain
CN110130901A (en) On across both wired Urban Underground mining sectbn construction methods
CN110439590A (en) Method for tunnel construction
CN111119900A (en) Earth pressure balance shield liquid nitrogen vertical freezing and underwater receiving comprehensive construction method
CN108547644A (en) A kind of Tunnel Passing crushed zone canopy protection structure and method for protecting support
CN112727470B (en) Construction reinforcing method for shield tunnel at overlapped section
CN109538229A (en) A kind of construction method of tunneling subway tunnel crossing ancient building
CN103615012B (en) Steel construction self-drilling hollow anchor bars reinforces the most wired gear safeguard structure
CN110644492B (en) Comprehensive grouting construction method for steep dip angle wide-crack stratum
CN116335679A (en) Pipe curtain support and horizontal jet grouting pile combined closed loop advanced support method
CN109751056A (en) A kind of water rich strata shield-tunneling construction active well end processing method
CN113338950A (en) Shield closed arrival construction method of freezing method and cement system combined steel sleeve
CN208330410U (en) A kind of Tunnel Passing crushed zone canopy protection structure
CN210440037U (en) Active protection structure of shield near-penetration operation tunnel in water-rich soft soil area
CN113047853A (en) Shield starting construction method for water-rich soft soil geological area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant