CN101215969A - Large diameter tunneling close range down-traversing small diameter subway tunnel distortion control method - Google Patents

Large diameter tunneling close range down-traversing small diameter subway tunnel distortion control method Download PDF

Info

Publication number
CN101215969A
CN101215969A CNA2008100327380A CN200810032738A CN101215969A CN 101215969 A CN101215969 A CN 101215969A CN A2008100327380 A CNA2008100327380 A CN A2008100327380A CN 200810032738 A CN200810032738 A CN 200810032738A CN 101215969 A CN101215969 A CN 101215969A
Authority
CN
China
Prior art keywords
tunnel
shield
subway
existing
tunneling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2008100327380A
Other languages
Chinese (zh)
Inventor
李庭平
沈水龙
张金辉
姜弘
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jiaotong University
Original Assignee
Shanghai Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiaotong University filed Critical Shanghai Jiaotong University
Priority to CNA2008100327380A priority Critical patent/CN101215969A/en
Publication of CN101215969A publication Critical patent/CN101215969A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a method for controlling distortion for deep large diameter shield tunnels to under-pass small diameter tunnels, which pertains to the technical field of tunnel engineering. According to the method, the control range of the stratum loss ratio of newly established tunnels and the optimum value of the support pressure of the shield cut surface are acquired by using the finite-element method; soil pressure in front of the shield cut surface is kept relatively balanced by setting the optimal value of the support pressure, and the support pressure fluctuation range of the cut surface is controlled to range from minus 10kPa to plus 10kPa; the stratum loss ratio of the newly established tunnels is controlled within the allowed range. According to the construction technique measures, a test propelling area is arranged before the shield reaches a cross position. In the area, construction is carried out according to the situation of the existing underground tunnels above; and construction parameters are controlled and regulated to adjust the support pressure, the propulsive velocity and the amount of the grout to be injected in time; the shield passes through the cross position in combination with the optimal values of the construction parameters of the test propelling area. The invention can not only ensure the construction of tunnels to be carried out safely and smoothly, but also minimize the influence of construction on ambient environment.

Description

The deformation control method in large diameter tunneling close range down-traversing small diameter subway tunnel
Technical field
What the present invention relates to is a kind of control method of construction of tunnel technical field, specifically is the deformation control method of wearing the minor diameter tunnel under the buried shield tunnel of a kind of major diameter.
Background technology
Along with the arriving of urban underground space exploitation climax, adopt shield method to build various city tunnels such as underground railway and more and more be subject to people's attention in countries in the world.In nearly ten years, shield method has obtained fast development in China, has successfully grasped technology such as soil pressure shield structure, slurry shield already; Only be example with Shanghai City, 2007 the end of the year metro shield tunnel reached more than the 200km, other has 5 of the big section shield tunnels that pass through at the bottom of Huangpu River.In the new urban planning in Shanghai, the track traffic total kilometrage reaches more than the 500km; Build, reach more than 11 in Huangpu River tunnel of crossing of building and planning to build, other has diameter to reach the Chongming Yangtze River Tunnel of 15.0m large section.
Networking, the scale day by day of track traffic; track traffic and the development of city tunnel synchronous high-speed; make the city be faced with the problem how underground space resource is effectively utilized; underground construction space crossed inevitable, the fast development of urban infrastructure and the restriction of surrounding enviroment often make this class engineering circle scheme of avoiding of doing the best become preferred or even unique feasible scheme.Yet the track traffic facility has strict demand to Deformation control, subway tunnel itself space crossed often is exactly control point, the difficult point in the design and construction, and large diameter shield tunnel passes through the space crossed key point of planning, design and construction especially of traversing small diameter subway tunnel.Shield-tunneling construction can cause disturbance to surrounding soil, causes surface settlement or protuberance, and many at present measures such as the shield tunneling face is stable, shield endnote slurry come controlled deformation by controlling.And the shield structure closely passes through inevitable the grand heavy of established tunnel that also can cause of established tunnel, particularly large diameter shield tunnel passes through the minor diameter existing tunnel and more makes Deformation control be difficult to hold, and how making new built tunnel pass through established tunnel smoothly and making established tunnel be in safe controllable state is a difficult problem always.
Find through literature search prior art, application number is CN200410015918.X, the name of patent application is called " a kind of method and anti-deformation structure of carrying out the deep big foundation pit construction above operation tunnel ", this technology adopts the method that respectively sets at least one row's uplift pile in the operation tunnel soil at both sides, above the operation tunnel between the resistance to plucking row of piles, carry out soil excavation, when soil excavation when exposing described uplift pile, between the resistance to plucking row of piles, place or the pouring structure base plate, thereby effectively prevent the rebound deformation and the tunnel deformation of the surrounding soil that tunnel upper causes owing to soil excavation.This method only is applicable to cut and cover tunneling, and is confined to new construction of structures above existing tunnel, to wearing existing minor diameter tunnel and inapplicable under the particularly newly-built major diameter of the hidden construction process construction tunnel.
Summary of the invention
The present invention is directed to the deficiencies in the prior art and defective, proposed the deformation control method in a kind of large diameter tunneling close range down-traversing small diameter subway tunnel.The present invention at first comes the ground under the simulate given construction parameter condition and the distortion in tunnel by three dimensional finite element numerical analysis, determines optimized parameter.In the certain zone of existing tunnel, setting pilot region according to on-site actual situations then, carry out tentative construction with the optimized parameter of determining, if the distortion in the pilot region meets the demands, then carry out formal crossing construction, like this, make it can guarantee existing tunnel safety smooth construction, and the influence to surrounding environment of can as far as possible reducing to construct.
The present invention is achieved by the following technical solutions, comprises the steps:
The first step calculates new built tunnel stratum loss late control range and shield tunneling face supporting pressure optimum value at relative position, soil nature condition, edpth of tunnel and the existing tunnel Deformation control standard application Finite Element of cross tunnel, and is specific as follows:
1. three-dimensional finite element model scope: horizontal direction should be greater than (2H+3D+L) rice, and depth direction should be greater than (2H+2D) rice, and wherein, H is the top buried depth of new built tunnel, and D is the diameter of new built tunnel, and L is tunnel, a newly-built left and right sides clear spacing; Height determines that according to engineering is actual new built shield tunnel places the centre of model, and the bottom surface is 2D at the bottom of the tunnel.
2. fringe conditions is set as follows in calculating: the inboard free boundary that adopts in tunnel, the bound level displacement of model both sides, the vertical and horizontal movement of model bottom constraint simultaneously.
3. the constitutive relation of soft soil layer adopts the modified cambridge model of considering elastic-plastic strain, and sandy soil layer adopts More's enclosed pasture model, and tunnel structure is taken as elastic body.
4. in the model new built tunnel is set the Different Strata loss late, then calculate the face of land and existing tunnel deflection, draw out stratum loss late and deflection graph of relation." Shanghai City operated subway protecting tunnel standard " regulation: operated subway structure facility absolute settlement amount must be less than 20mm, and a day structure of the subway settling amount must be less than 1mm.Determine the control range of new built tunnel stratum loss late according to this Deformation control standard.
5. the shield tunneling face is provided with according to earth pressue at rest and calculates the trapezoidal supporting pressure of gained in model, then make supporting pressure near earth pressue at rest, change, introduce the notion of supporting pressure ratio, actual supporting pressure of the face that promptly excavates and the ratio that calculates gained supporting pressure according to earth pressue at rest, draw the relation curve of existing tunnel and surface deformable and shield support pressure ratio, and draw the supporting force value that makes that existing tunnel distortion is minimum according to curved line relation.
Second step kept the shield tunneling relative equilibrium of water and soil pressure in front by supporting pressure optimum value is set, and strict control excavation face supporting pressure oscillation scope, can be controlled at ± 10kPa according to the construction needs.Simultaneously in existing subway tunnel, automatic monitoring system is installed, adjusts in real time according to monitored data.
The 3rd step, new built tunnel stratum loss late is controlled in the allowed band, concrete working measure is as follows: adopt synchronous grouting, and strict control grouting pressure, grouting amount and slurries quality assurance shield tail stratum are stable, rationally set grouting pressure according to earthing pressure, and in time adjust according to composite factors such as excavation face supporting pressure, grouting pressure generally is controlled at 0.2~0.4MPa; According to shield tail gap accurate Calculation grouting amount, grouting amount generally is taken as 150%~200% of voidage, can in time adjust according to the deformation measurement data of existing subway tunnel, should guarantee in the slip casting process that slurries are not diluted by muddy water; Should guarantee shield structure low speed, the stable propelling in the crossing process, fltting speed generally is controlled in the 10mm/min; The later stage distortion of ftercompction slip casting control soil layer.
The 4th step, according to above technology measure, before the shield structure is about to arrive crossover sites, set test and advance the zone, in this zone according to above exist the situation of existing subway tunnel to construct.Each construction parameter is adjusted in control, with the optimum value of construction parameters such as timely adjustment supporting pressure, fltting speed and grouting amount.
The 5th step, the shield structure formally passes through crossover sites, in the work progress, strengthen existing tunnel distortion and surface deformation monitoring, particularly with of the distortion of new built tunnel at a distance of nearest subway tunnel position, can carry out settlement observation by the automatic monitoring system that is installed in the subway tunnel, and in time adjust construction parameter, carry out smoothly to guarantee crossing construction safety according to monitoring result.When the subway tunnel subsidence is excessive, strengthen shield tail grouting amount, when subway tunnel produces the protuberance distortion, should reduce grouting pressure and grouting amount, and guarantee that the shield structure advances and carry out continuously, and speed is unsuitable too fast.After the shield structure passes through,, cross section is implemented micro-destabilization slip-casting to the soil body in new built tunnel, further stablize the posterior settlement of existing tunnel according to monitored data.
For guaranteeing the smooth implementation of above step, before carrying out finite element analysis, can carry out following aspects of works: field engineering exploration (comprising clay distribution, soil body mechanics index of physics etc.), clay distribution can determine that soil body mechanics index of physics can obtain by conventional soil test by cone penetration test; The trend of existing traversing small diameter subway tunnel, buried depth, the locus in newly-built major diameter tunnel, the at grade intersection position in two tunnels, information such as intersecting angle and minimum spacing.
The present invention has taken all factors into consideration each factor that causes the face of land and existing tunnel distortion, is applicable to silt clay, clay, sandy soil, silt, has solved the deficiency and the defective of former technology.By the every construction parameter of reasonable adjustment, guaranteed the smooth construction of new built tunnel, guaranteed the safety of existing tunnel and surrounding enviroment again.The present invention is applicable to similar operating mode, provides an important techniques to guarantee for large diameter shield tunnel in the weak soil closely passes through existing minor diameter constructing tunnel.
Description of drawings
The plan view of the existing subway tunnel of Fig. 1 large diameter tunneling close range down
The profile of the existing subway tunnel of Fig. 2 large diameter tunneling close range down
Fig. 3 three-dimensional finite element mesh
Fig. 4 existing subway tunnel maximum settlement amount and stratum loss late graph of a relation
Fig. 5 shield tunneling face mud hydraulic pressure ratio and existing subway tunnel settling amount graph of a relation
The specific embodiment
Below in conjunction with accompanying drawing embodiments of the invention are elaborated: present embodiment has provided detailed embodiment and process being to implement under the prerequisite with the technical solution of the present invention, but protection scope of the present invention is not limited to following embodiment.
Embodiment is an example to wear existing Metro Tunnel under the cross-river tunnel of Shanghai City.
(1) calculates new built tunnel stratum loss late control range and shield tunneling face supporting pressure optimum value according to the relative position and the on-site actual situations application Finite Element of cross tunnel.Built subway tunnel external diameter 6.2m in this project, upper and lower line plane, tunnel clear distance is 4.54m.The newly-built cross-river tunnel and the subway tunnel space intersection place plane angle of cut are 56 °, minimum vertical clear spacing 2.68m.Cross-river tunnel is line clear spacing 12.06m up and down, and tunnel diameter is 11.36m, and center, tunnel buried depth is 34.68m.Accompanying drawing 1 is the plan view of the existing subway tunnel of large diameter tunneling close range down, and accompanying drawing 2 is the profile of the existing subway tunnel of large diameter tunneling close range down.Newly-built tunnel top buried depth H=29m, tunnel diameter D=11.36m, L=12.06m, three-dimensional finite element model length is taken as 200m, wide 100m, high 70m, the FEM (finite element) calculation grid is as shown in Figure 3.Fringe conditions is set as follows in the calculating: the inboard free boundary that adopts in tunnel, the bound level displacement of model both sides, the vertical and horizontal movement of model bottom constraint simultaneously.The constitutive relation of soft soil layer adopts the modified cambridge model of considering elastic-plastic strain, and the sand constitutive relation adopts More's enclosed pasture model, and tunnel structure is taken as elastic body.
Stratum loss late controlling value is determined: in the model, newly-built cross-river tunnel stratum loss late is made as different value respectively, then calculates existing subway tunnel and surface settlement.The result shows that existing subway tunnel maximum settlement value is respectively 6.1mm, 14.8mm and 25.6mm when newly-built left line cross-river tunnel stratum loss late is 0.5%, 1.0% and 1.5%; Line cross-river tunnel stratum, newly-built left and right sides loss late is 0.5%, 1.0% and at 1.5% o'clock, and existing subway tunnel maximum settlement value is respectively 8.3mm, 23.7mm and 41.2mm.Draw existing subway tunnel maximum settlement amount and stratum loss late graph of a relation; as shown in Figure 4; and according to Shanghai City operated subway protecting tunnel standard; be that operated subway structure facility absolute settlement amount is no more than 20mm, the stratum loss late of left and right sides cross-river tunnel all must be controlled in 0.85% as can be known.
The mud hydraulic pressure optimum value is calculated: this engineering adopts major diameter slurry pressurization equilibration formula shield structure, in the FEM (finite element) calculation, earlier apply the supporting force value of calculating according to earth pressue at rest at the shield tunneling face, shield structure top mud hydraulic pressure is 445.5kPa, and the bottom is 610.2kPa.Excavation face mud hydraulic pressure is reduced gradually than (promptly excavating actual mud hydraulic pressure of face and the ratio that calculates the gained mud hydraulic pressure according to the stationary water soil pressure), existing like this subway tunnel settling amount can increase gradually, draw shield tunneling face mud hydraulic pressure ratio and existing subway tunnel settling amount curved line relation, as shown in Figure 5.Draw when the mud hydraulic pressure ratio is 0.9 (when the ratio of actual mud hydraulic pressure and stationary water soil pressure is 0.9) existing subway tunnel deformation values minimum by curve relation figure, therefore shield structure top mud hydraulic pressure optimum value is 445.5 * 0.9=401.0kPa, and bottom mud hydraulic pressure optimum value is 610.2 * 0.9=549.2kPa.
(2) guarantee excavation face soil stabilization, at the shield tunneling face supporting pressure optimum value is set, promptly excavate face top mud hydraulic pressure and be made as 401.0kPa, the bottom mud hydraulic pressure is made as 549.2kPa, and the control fltting speed is 5mm/min~10mm/min, the mud hydraulic pressure fluctuation range is controlled at ± 10kPa with interior to keep the stability of shield structure the place ahead soil layer.
(3) test advances, and advances at the shield structure and sets a 400m specific region before approaching to subway tunnel and test and pass through, and exists according to top fully and carries out the shield structure under the situation of subway tunnel and advance, and new built tunnel stratum loss late is controlled in 0.85%.By monitored data, the proportioning when exploring mud hydraulic pressure variations, the variation of muddy water parameter, the correction of shield structure, fltting speed, simultaneous grouting slurry injection rate, injection etc. are to the influence of soil body sedimentation, thus the construction parameter when determining to pass through.
(4) passing through the zone, otch water pressure fluctuations value is being controlled in the 10kPa; For the stratum loss late is controlled in 0.85%, adopt timely, uniform single liquid synchronous grouting form, the slip casting position is the injected hole on the section of jurisdiction.Every section of jurisdiction of through section has 4 injected holes, and every endless tube sheet amounts to 32 injected holes.Injecting paste material mainly is made up of hydrated lime, sand, flyash, swell soil, water and Admixture, after the slip casting early stage slurries for flowing, later strength is higher, its density is 2.006 * 10 3/ m 3, denseness is 9.3cm, and 3d intensity is 0.19MPa, and 14d intensity is 0.415MPa, and 28d intensity is 0.75MPa, 46d intensity is 1.06MPa, and has the performance that anti-preferably muddy water washes away dilution.Driving speed is controlled at 5mm/min~10mm/min, and according to constantly adjusting fltting speed with the ground monitoring data in the existing subway tunnel.
(5) after the shield structure passes through, the sedimentation of setting up special monitoring group to pay close attention to existing subway tunnel 24 hours every days changes, data according to ground monitoring and electronic horizontal ruler, cross section is implemented micro-destabilization slip-casting to the soil body in new built tunnel, grouting pump is arranged in the new built tunnel, grouting serous fluid adopts the biliquid slurry, further to stablize the posterior settlement of subway tunnel.Finally, the stratum loss late when left line cross-river tunnel passes through existing subway tunnel is 0.61%, and according to monitoring day after day after passing through, existing subway tunnel settling amount maximum value is 7.5mm; Stratum loss late when right line cross-river tunnel passes through existing subway tunnel is controlled to be 0.69%, and the sedimentation maximum value after passing through is 13.1mm.Newly-built cross-river tunnel passes through existing subway tunnel smoothly safely, and the settlement Control of existing subway tunnel is very desirable, meets the control requirement fully.

Claims (6)

1. the deformation control method in a large diameter tunneling close range down-traversing small diameter subway tunnel is characterized in that, comprises the steps:
The first step calculates new built tunnel stratum loss late control range and shield tunneling face supporting pressure optimum value at relative position, soil nature condition, edpth of tunnel and the existing tunnel Deformation control standard application Finite Element of cross tunnel, and is specific as follows:
1. three-dimensional finite element model scope: horizontal direction should be greater than 2H+3D rice, and depth direction should be greater than H+2D rice, wherein, H is the top buried depth of new built tunnel, and D is the diameter of new built tunnel, and height is determined according to engineering is actual, new built shield tunnel places the centre of model, and the bottom surface is 2D at the bottom of the tunnel;
2. fringe conditions is set as follows in calculating: the inboard free boundary that adopts in tunnel, the bound level displacement of model both sides, the vertical and horizontal movement of model bottom constraint simultaneously;
3. the constitutive relation of soft soil layer adopts the modified cambridge model of considering elastic-plastic strain, and sandy soil layer adopts More's enclosed pasture model, and tunnel structure is taken as elastic body;
4. in the model new built tunnel is set the Different Strata loss late, then calculate the face of land and existing tunnel deflection, draw out stratum loss late and deflection graph of relation, determine the control range of new built tunnel stratum loss late;
5. the shield tunneling face is provided with according to earth pressue at rest and calculates the trapezoidal supporting pressure of gained in model, then make supporting pressure in the earth pressue at rest accessory change, draw the relation curve of existing tunnel and surface deformable and shield support pressure, and draw the supporting force value that makes that existing tunnel distortion is minimum according to curved line relation;
In second step, by the relative equilibrium that supporting pressure optimum value keeps water and soil pressure in face of the shield tunneling is set, and control excavation face supporting pressure oscillation scope is at ± 10kPa;
The 3rd step was controlled at new built tunnel stratum loss late in the allowed band, was specially: adopt synchronous grouting, grouting pressure is controlled at 0.2MPa~0.4MPa, and grouting amount is taken as 150%~200% of voidage, the later stage distortion of ftercompction slip casting control soil layer;
The 4th step, according to above technology measure, before the shield structure is about to arrive crossover sites, set test and advance the zone, in this zone according to above exist the situation of existing subway tunnel to construct, each construction parameter is adjusted in control, with timely adjustment supporting pressure, fltting speed and grouting amount;
In the 5th step, the shield structure passes through crossover sites.
2. the deformation control method in large diameter tunneling close range down-traversing small diameter subway according to claim 1 tunnel, it is characterized in that, in the described first step, the described control range of determining new built tunnel stratum loss late, be meant: operated subway structure facility absolute settlement amount is less than 20mm, and day structure of the subway settling amount is less than 1mm.
3. the deformation control method in large diameter tunneling close range down-traversing small diameter subway according to claim 1 tunnel is characterized in that, in described second step, in existing subway tunnel automatic monitoring system is installed, and adjusts in real time according to monitored data.
4. the deformation control method in large diameter tunneling close range down-traversing small diameter subway according to claim 1 tunnel is characterized in that, in described the 3rd step, fltting speed is controlled in the 10mm/min in the crossing process.
5. the deformation control method in large diameter tunneling close range down-traversing small diameter subway according to claim 1 tunnel, it is characterized in that, in described the 5th step, the shield structure formally passes through in the crossover sites work progress, strengthen existing tunnel distortion and surface deformation monitoring, carry out settlement observation by the automatic monitoring system that is installed in the subway tunnel, and in time adjust construction parameter according to monitoring result, when the subway tunnel subsidence surpasses control range, strengthen shield tail grouting amount, when subway tunnel produces the protuberance distortion, reduce grouting pressure and grouting amount, and the propelling of assurance shield structure is carried out continuously.
6. the deformation control method in large diameter tunneling close range down-traversing small diameter subway tunnel according to claim 1 or 5, it is characterized in that, in described the 5th step, after the shield structure passes through, according to monitored data, cross section is implemented micro-destabilization slip-casting to the soil body in new built tunnel, further stablize the posterior settlement of existing tunnel.
CNA2008100327380A 2008-01-17 2008-01-17 Large diameter tunneling close range down-traversing small diameter subway tunnel distortion control method Pending CN101215969A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2008100327380A CN101215969A (en) 2008-01-17 2008-01-17 Large diameter tunneling close range down-traversing small diameter subway tunnel distortion control method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2008100327380A CN101215969A (en) 2008-01-17 2008-01-17 Large diameter tunneling close range down-traversing small diameter subway tunnel distortion control method

Publications (1)

Publication Number Publication Date
CN101215969A true CN101215969A (en) 2008-07-09

Family

ID=39622472

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2008100327380A Pending CN101215969A (en) 2008-01-17 2008-01-17 Large diameter tunneling close range down-traversing small diameter subway tunnel distortion control method

Country Status (1)

Country Link
CN (1) CN101215969A (en)

Cited By (43)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101915106A (en) * 2010-08-05 2010-12-15 中山大学 Optimal tunneling speed control method for built tunnel shield driving
CN102080548A (en) * 2010-12-29 2011-06-01 上海隧道工程股份有限公司 Construction method of tunnel to cross airport runway by shield method
CN101725357B (en) * 2008-10-23 2011-11-02 上海天演建筑物移位工程有限公司 Construction method for lower section of underground tunnel
CN102312673A (en) * 2010-07-09 2012-01-11 上海市基础工程有限公司 Construction method for allowing shield to pass through operated subway tunnel in short distance under complex working conditions
CN102619531A (en) * 2012-03-06 2012-08-01 北京交通大学 Multi-step sequence construction deformation control method for shallow-buried tunnel with big cross section
CN101598023B (en) * 2009-07-16 2012-10-10 上海交通大学 Control method for shield tunnel axis having underground structure on adjacent side
CN102733413A (en) * 2012-06-18 2012-10-17 河海大学 Method for controlling subsidence of operating subway tunnel
CN102966122A (en) * 2011-08-31 2013-03-13 北京市重大项目建设指挥部办公室 Method for controlling deformation of bridge during construction of tunnel close to foundation of bridge
CN103775090A (en) * 2014-01-06 2014-05-07 中国建筑第五工程局有限公司 Partition detecting method and device for flyover crossing tunnel construction
CN103775098A (en) * 2014-01-06 2014-05-07 中国建筑第五工程局有限公司 Method and device for detecting flyover crossing tunnel construction based on train vibration in partition mode
CN104653196A (en) * 2015-01-30 2015-05-27 北京交通大学 Initial design method of tunnel engineering considering all-parameter influence
CN104912562A (en) * 2015-06-30 2015-09-16 中铁一局集团有限公司 Construction method for deformation control over existing operation tunnel crossing under shield
CN105136370A (en) * 2015-07-13 2015-12-09 北京工业大学 Earth pressure load determination method of deeply-buried asymmetric multiple-arch tunnel
CN105138767A (en) * 2015-08-23 2015-12-09 北京工业大学 Deep-buried asymmetric closely spaced tunnel surrounding rock pressure calculation method
CN105571768A (en) * 2016-01-04 2016-05-11 安徽理工大学 Shallow-buried tunnel soil pressure calculating method based on displacement monitoring result
CN105952462A (en) * 2016-06-21 2016-09-21 中国电建集团华东勘测设计研究院有限公司 Method for controlling deformation of shield tunnels in adjacent engineering construction procedures
CN106919782A (en) * 2016-12-29 2017-07-04 中国人民解放军63926部队 Sandy soil stratum shield tunnel based on ground loss ratio loosens Forecasting Methodology
CN107191197A (en) * 2017-06-14 2017-09-22 中铁第四勘察设计院集团有限公司 A kind of shield duct piece and its pushed away in shield sky by the application in Tunneling by mining method
CN107657091A (en) * 2017-09-13 2018-02-02 河北建筑工程学院 The computational methods of small interval heavy haul railway cross tunnel tunnel bottom displacement
CN107916935A (en) * 2017-11-13 2018-04-17 浙江大学城市学院 A kind of soil body composite reinforcing structure and construction method of the existing subway of weak soil shield crossing
CN108397199A (en) * 2018-01-03 2018-08-14 中铁广州工程局集团有限公司 The method for tunnel construction in water hole is connected under a kind of short distance
CN109184743A (en) * 2018-09-25 2019-01-11 中铁十二局集团有限公司 Existing tunnel construction method is worn under circle boulder clay rock compound stratum slurry shield short distance
CN109723447A (en) * 2018-11-21 2019-05-07 上海市基础工程集团有限公司 Shield continuously intensively passes through the construction method that different type rail hands over facility
CN110159296A (en) * 2019-06-14 2019-08-23 中国建筑一局(集团)有限公司 Structural system for controlling deformation of subway shield tunnel and construction method thereof
CN111396063A (en) * 2020-03-25 2020-07-10 中铁三局集团有限公司 Construction method for short-distance upward-crossing existing line downward-passing sewage jacking pipe of water-rich sand layer shield
CN111764924A (en) * 2020-06-29 2020-10-13 中铁隆工程集团有限公司 Construction method for excavating and supporting existing tunnel passing through skew at bottom
CN112160758A (en) * 2020-10-19 2021-01-01 中建八局轨道交通建设有限公司 Construction method for slurry shield to penetrate through river dike
CN112228078A (en) * 2020-09-27 2021-01-15 宁波市政工程建设集团股份有限公司 Underground space construction method in short-distance crossing construction of soft soil shield
CN112554913A (en) * 2020-12-11 2021-03-26 中铁二十局集团第四工程有限公司 Reinforcing method for underground crossing channel under shield
CN112576258A (en) * 2020-12-09 2021-03-30 湖北省电力勘测设计院有限公司 Comprehensive pipe gallery large-section rectangular jacking pipe construction stress monitoring system
CN113153334A (en) * 2019-11-11 2021-07-23 北京住总集团有限责任公司 Risk management and control system for influence of shield underpass construction on structure
CN113217021A (en) * 2021-04-30 2021-08-06 中铁十六局集团有限公司 Underground space close-range disturbance construction method and equipment
CN113361151A (en) * 2020-03-06 2021-09-07 宏润建设集团股份有限公司 Analysis and evaluation method for shield underpass construction
CN113356864A (en) * 2021-07-14 2021-09-07 上海市城市建设设计研究总院(集团)有限公司 Construction method of shield method ramp
CN113374496A (en) * 2021-06-23 2021-09-10 上海隧道工程有限公司 Upper-crossing tunnel structure and construction method
CN113643606A (en) * 2021-09-15 2021-11-12 济南轨道交通集团有限公司 Shield tunneling existing pipeline penetrating construction simulation test device and method
CN114109419A (en) * 2021-11-16 2022-03-01 中铁十八局集团有限公司 Construction method for double-shield TBM to pass through existing operation line
CN114278323A (en) * 2021-12-31 2022-04-05 中铁五局集团有限公司 Shield construction method for underground through construction structure
CN114293998A (en) * 2021-12-31 2022-04-08 中铁五局集团有限公司 Subway underpass highway shield construction method
CN114657817A (en) * 2022-03-11 2022-06-24 中交第二公路勘察设计研究院有限公司 Method for controlling deformation of roadbed of shield underpass railway in close range
CN115262528A (en) * 2022-08-12 2022-11-01 浙江工业大学 Micro-disturbance grouting device for controlling horizontal deformation of subway tunnel and construction method
CN115928798B (en) * 2023-03-13 2023-05-23 北京城建设计发展集团股份有限公司 Method for passing through existing underground structure of rail transit through ultra-small clear distance long-distance oblique crossing
CN117972833A (en) * 2024-01-11 2024-05-03 北京杜普信科技有限公司 Grouting control method, grouting control system, grouting control terminal and storage medium

Cited By (59)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101725357B (en) * 2008-10-23 2011-11-02 上海天演建筑物移位工程有限公司 Construction method for lower section of underground tunnel
CN101598023B (en) * 2009-07-16 2012-10-10 上海交通大学 Control method for shield tunnel axis having underground structure on adjacent side
CN102312673B (en) * 2010-07-09 2013-10-23 上海市基础工程集团有限公司 Construction method for allowing shield to pass through operated subway tunnel in short distance under complex working conditions
CN102312673A (en) * 2010-07-09 2012-01-11 上海市基础工程有限公司 Construction method for allowing shield to pass through operated subway tunnel in short distance under complex working conditions
CN101915106A (en) * 2010-08-05 2010-12-15 中山大学 Optimal tunneling speed control method for built tunnel shield driving
CN101915106B (en) * 2010-08-05 2014-11-26 中山大学 Optimal tunneling speed control method for built tunnel shield driving
CN102080548A (en) * 2010-12-29 2011-06-01 上海隧道工程股份有限公司 Construction method of tunnel to cross airport runway by shield method
CN102966122B (en) * 2011-08-31 2015-09-16 北京市重大项目建设指挥部办公室 The method of bridge deformation is controlled when building tunnel near the basis of bridge
CN102966122A (en) * 2011-08-31 2013-03-13 北京市重大项目建设指挥部办公室 Method for controlling deformation of bridge during construction of tunnel close to foundation of bridge
CN102619531A (en) * 2012-03-06 2012-08-01 北京交通大学 Multi-step sequence construction deformation control method for shallow-buried tunnel with big cross section
CN102733413A (en) * 2012-06-18 2012-10-17 河海大学 Method for controlling subsidence of operating subway tunnel
CN103775090B (en) * 2014-01-06 2016-01-20 中国建筑第五工程局有限公司 For Subarea detecting method and the device of graded crossing constructing tunnel
CN103775090A (en) * 2014-01-06 2014-05-07 中国建筑第五工程局有限公司 Partition detecting method and device for flyover crossing tunnel construction
CN103775098A (en) * 2014-01-06 2014-05-07 中国建筑第五工程局有限公司 Method and device for detecting flyover crossing tunnel construction based on train vibration in partition mode
CN103775098B (en) * 2014-01-06 2016-03-02 中国建筑第五工程局有限公司 Based on Subarea detecting method and the device of the graded crossing constructing tunnel of train vibrations
CN104653196A (en) * 2015-01-30 2015-05-27 北京交通大学 Initial design method of tunnel engineering considering all-parameter influence
CN104912562A (en) * 2015-06-30 2015-09-16 中铁一局集团有限公司 Construction method for deformation control over existing operation tunnel crossing under shield
CN105136370A (en) * 2015-07-13 2015-12-09 北京工业大学 Earth pressure load determination method of deeply-buried asymmetric multiple-arch tunnel
CN105136370B (en) * 2015-07-13 2017-08-04 北京工业大学 A kind of buried asymmetric multiple-arch tunnel soil pressure load determines method
CN105138767B (en) * 2015-08-23 2018-06-29 北京工业大学 A kind of buried asymmetric closely-spaced tunnel pressure from surrounding rock computational methods
CN105138767A (en) * 2015-08-23 2015-12-09 北京工业大学 Deep-buried asymmetric closely spaced tunnel surrounding rock pressure calculation method
CN105571768A (en) * 2016-01-04 2016-05-11 安徽理工大学 Shallow-buried tunnel soil pressure calculating method based on displacement monitoring result
CN105571768B (en) * 2016-01-04 2018-08-03 安徽理工大学 A kind of shallow tunnel Calculating method of earth pressure based on displacement monitoring result
CN105952462A (en) * 2016-06-21 2016-09-21 中国电建集团华东勘测设计研究院有限公司 Method for controlling deformation of shield tunnels in adjacent engineering construction procedures
CN106919782A (en) * 2016-12-29 2017-07-04 中国人民解放军63926部队 Sandy soil stratum shield tunnel based on ground loss ratio loosens Forecasting Methodology
CN106919782B (en) * 2016-12-29 2019-04-26 中国人民解放军63926部队 Sandy soil stratum shield tunnel based on ground loss ratio loosens prediction technique
CN107191197A (en) * 2017-06-14 2017-09-22 中铁第四勘察设计院集团有限公司 A kind of shield duct piece and its pushed away in shield sky by the application in Tunneling by mining method
CN107657091A (en) * 2017-09-13 2018-02-02 河北建筑工程学院 The computational methods of small interval heavy haul railway cross tunnel tunnel bottom displacement
CN107657091B (en) * 2017-09-13 2021-02-02 河北建筑工程学院 Method for calculating tunnel bottom displacement of small-clear-distance heavy haul railway cross tunnel
CN107916935A (en) * 2017-11-13 2018-04-17 浙江大学城市学院 A kind of soil body composite reinforcing structure and construction method of the existing subway of weak soil shield crossing
CN107916935B (en) * 2017-11-13 2024-01-23 浙江大学城市学院 Soil body composite reinforcement structure for soft soil shield to penetrate existing subway and construction method
CN108397199A (en) * 2018-01-03 2018-08-14 中铁广州工程局集团有限公司 The method for tunnel construction in water hole is connected under a kind of short distance
CN109184743A (en) * 2018-09-25 2019-01-11 中铁十二局集团有限公司 Existing tunnel construction method is worn under circle boulder clay rock compound stratum slurry shield short distance
CN109723447A (en) * 2018-11-21 2019-05-07 上海市基础工程集团有限公司 Shield continuously intensively passes through the construction method that different type rail hands over facility
CN110159296A (en) * 2019-06-14 2019-08-23 中国建筑一局(集团)有限公司 Structural system for controlling deformation of subway shield tunnel and construction method thereof
CN113153334A (en) * 2019-11-11 2021-07-23 北京住总集团有限责任公司 Risk management and control system for influence of shield underpass construction on structure
CN113361151B (en) * 2020-03-06 2023-02-28 宏润建设集团股份有限公司 Analysis and evaluation method for shield underpass construction
CN113361151A (en) * 2020-03-06 2021-09-07 宏润建设集团股份有限公司 Analysis and evaluation method for shield underpass construction
CN111396063B (en) * 2020-03-25 2021-05-28 中铁三局集团有限公司 Construction method for short-distance upward-crossing existing line downward-passing sewage jacking pipe of water-rich sand layer shield
CN111396063A (en) * 2020-03-25 2020-07-10 中铁三局集团有限公司 Construction method for short-distance upward-crossing existing line downward-passing sewage jacking pipe of water-rich sand layer shield
CN111764924A (en) * 2020-06-29 2020-10-13 中铁隆工程集团有限公司 Construction method for excavating and supporting existing tunnel passing through skew at bottom
CN112228078A (en) * 2020-09-27 2021-01-15 宁波市政工程建设集团股份有限公司 Underground space construction method in short-distance crossing construction of soft soil shield
CN112160758A (en) * 2020-10-19 2021-01-01 中建八局轨道交通建设有限公司 Construction method for slurry shield to penetrate through river dike
CN112576258A (en) * 2020-12-09 2021-03-30 湖北省电力勘测设计院有限公司 Comprehensive pipe gallery large-section rectangular jacking pipe construction stress monitoring system
CN112576258B (en) * 2020-12-09 2023-03-14 湖北省电力勘测设计院有限公司 Comprehensive pipe gallery large-section rectangular jacking pipe construction stress monitoring system
CN112554913A (en) * 2020-12-11 2021-03-26 中铁二十局集团第四工程有限公司 Reinforcing method for underground crossing channel under shield
CN113217021A (en) * 2021-04-30 2021-08-06 中铁十六局集团有限公司 Underground space close-range disturbance construction method and equipment
CN113217021B (en) * 2021-04-30 2024-03-19 中铁十六局集团有限公司 Underground space close-range disturbance construction method and equipment
CN113374496A (en) * 2021-06-23 2021-09-10 上海隧道工程有限公司 Upper-crossing tunnel structure and construction method
CN113356864A (en) * 2021-07-14 2021-09-07 上海市城市建设设计研究总院(集团)有限公司 Construction method of shield method ramp
CN113643606A (en) * 2021-09-15 2021-11-12 济南轨道交通集团有限公司 Shield tunneling existing pipeline penetrating construction simulation test device and method
CN114109419A (en) * 2021-11-16 2022-03-01 中铁十八局集团有限公司 Construction method for double-shield TBM to pass through existing operation line
CN114293998A (en) * 2021-12-31 2022-04-08 中铁五局集团有限公司 Subway underpass highway shield construction method
CN114278323A (en) * 2021-12-31 2022-04-05 中铁五局集团有限公司 Shield construction method for underground through construction structure
CN114657817A (en) * 2022-03-11 2022-06-24 中交第二公路勘察设计研究院有限公司 Method for controlling deformation of roadbed of shield underpass railway in close range
CN115262528A (en) * 2022-08-12 2022-11-01 浙江工业大学 Micro-disturbance grouting device for controlling horizontal deformation of subway tunnel and construction method
CN115928798B (en) * 2023-03-13 2023-05-23 北京城建设计发展集团股份有限公司 Method for passing through existing underground structure of rail transit through ultra-small clear distance long-distance oblique crossing
CN117972833A (en) * 2024-01-11 2024-05-03 北京杜普信科技有限公司 Grouting control method, grouting control system, grouting control terminal and storage medium
CN117972833B (en) * 2024-01-11 2024-08-23 北京杜普信科技有限公司 Grouting control method, grouting control system, grouting control terminal and storage medium

Similar Documents

Publication Publication Date Title
CN101215969A (en) Large diameter tunneling close range down-traversing small diameter subway tunnel distortion control method
CN100580221C (en) Construction method for shallow soil-covered river bed under shield tunnel
CN102635124B (en) Construction method aiming to large open caisson in weak soil area
CN102352757B (en) Method for controlling upward floating of pipe piece during shield machine air pushing through mining tunnel
CN110700841B (en) Double-side-wall guide pit type excavation method for tunnel excavation
CN109056746A (en) The design and construction method of rectangle active well supporting construction can be recycled in a kind of flexible compound assembled
CN109779639A (en) Suitable for wearing the anti-floating control method in existing major diameter tunnel in arenaceous stratum shield
CN106761776A (en) Existing pipeline construction method is worn under super shallow-buried tunnel shield
Mei et al. Experimental study of the comprehensive technology of grouting and suspension under an operating railway in the cobble stratum
CN110984132B (en) Construction method for grooving underground diaphragm wall under complex geological condition
AU2021101945A4 (en) A Construction Control Method for Shield Tunneling Through Existing Operating Lines
CN105971638A (en) Application of WSS construction method in shield tool changing reinforcement of water-rich sand layer
CN114198124A (en) Construction method for grouting and water plugging of roof fall area of inclined shaft of coal mine
CN109356195A (en) Open-cut box culvert jacking method and system for crossing operation subway interval
CN111236262A (en) CSM + TRD underground continuous wall comprehensive construction method
CN109723447A (en) Shield continuously intensively passes through the construction method that different type rail hands over facility
Xu et al. Research on construction technology and formation deformation of shield tunneling under river
Liu et al. Deformation and numerical simulation analysis of deep foundation pit excavation of nanjing yangtze river floodplain metro station
CN105133629B (en) A kind of determination method of refuse landfill Groundwater Control System Halt water curtain
Huiqin et al. Application and Analysis of Curtain Grouting in Seepage Prevention and Reinforcement of Masonry Dam
Zhang Study on Ground Deformation during Shield Tunnel Construction
Huo et al. Analysis on construction of the subway shield underpassing the underground pedestrian passage at close range
Liu et al. Numerical simulation analysis of the effect of pipe shed support for underpassing existing tunnels
Zhang et al. Evaluation on Grouting Effect for Metro Tunnel in Loess Area Crossing Below Railway Station Platform
Moh et al. Geotechnical problems related to design and construction of the Taipei Transit Systems

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20080709