CN107447776A - The pull-type vertical retaining wall structure structure of anchor and construction method - Google Patents

The pull-type vertical retaining wall structure structure of anchor and construction method Download PDF

Info

Publication number
CN107447776A
CN107447776A CN201710710394.3A CN201710710394A CN107447776A CN 107447776 A CN107447776 A CN 107447776A CN 201710710394 A CN201710710394 A CN 201710710394A CN 107447776 A CN107447776 A CN 107447776A
Authority
CN
China
Prior art keywords
construction method
anchor
anchor pole
basis
pull
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710710394.3A
Other languages
Chinese (zh)
Inventor
吴震
胡鹏
吴贞瑶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of CN107447776A publication Critical patent/CN107447776A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls

Abstract

The present invention relates to slope supporting construction applications, disclose the pull-type vertical retaining wall structure structure of anchor and construction method, and it connects the sliding-resistant system formed with anchor pole by basis, armoured concrete slab.The present invention can obtain larger supporting and retaining system height with less section structure and vertical chest slope, realize that quantities is small, technique is simple, the duration is shorter, cost is relatively low, safety coefficient is high, and alien invasion is smooth attractive in appearance, is advantageous to mould preferable landscape effect.Its construction method:1st, the construction method in the preferable location of geological conditions:1., excavation slope to designed elevation, 3., on the basis of described 2., apply basis and anchor pole, apply armoured concrete slab, and be allowed to be connected with anchor pole;2nd, the construction method of geology defective sector:1., apply and anchor pole, 2., excavation slope to designed elevation pre-reinforcement is carried out to excavation slope, 3., earth-retaining foundation of wall is applied, 4. on the basis of described, applies armoured concrete slab, and be allowed to be connected with anchor pole.

Description

The pull-type vertical retaining wall structure structure of anchor and construction method
Technical field
The present invention relates to Geotechnical Engineering field, more particularly to the pull-type vertical retaining wall structure structure of the anchor in side slope consolidation projects and Construction method.
Background technology
In the side slope consolidation projects in scenic spot or top-grade building area, side slope is frequently encountered because of the limited supporting and retaining system knot in space Structure must be vertically arranged or the only slope space of very little, and the situation higher to retaining structure appearance requirement, the conventional practice That supporting and retaining system is carried out using the structure such as pile plate wall, anchor cable pile plate wall, but the stake of these structures and anchor cable, stake and plate, plate and Guan Liang it Between junction it is all uneven, alien invasion aesthetics is poor, in addition, apply man-hour requirement by pore digging, reinforcing bar cage hoisting, filling Note pile concrete, colligation Guan Liang reinforcing bar, cast Guan Liang concrete, breast boards bar planting, assembling reinforcement, shuttering, cast earth-retaining The technique such as board concrete, construction anchor cable, not only complex procedures, controlled factordisease are more, the duration is longer, and cost is higher, also exist outer Facade is uneven, the deficiencies of influenceing landscape effect.
The content of the invention
Technical problem:The technical problems to be solved by the invention are to provide a kind of pull-type vertical retaining wall structure structure of anchor and construction Method, with less retaining wall section width, less earthwork evacuation amount, obtain larger supporting and retaining system height, higher safety Coefficient, vertical smooth alien invasion attractive in appearance, and the working procedure of simple and fast, shorter duration and economic cost side slope Carry out supporting and retaining system.
Technical scheme:The present invention is realized by following technical proposals:It is by basis, armoured concrete slab, anchor The supporting and retaining system system of bar connection composition.
Construction method:1st, the construction method in the preferable location of geological conditions:1., excavation slope to designed elevation, 2., apply base 3., on the basis of described plinth and anchor pole, armoured concrete slab is applied, and be allowed to be connected with anchor pole;2nd, geology defective sector Construction method:1., apply and anchor pole, 2., excavation slope to designed elevation pre-reinforcement is carried out to excavation slope, 3., applies gear Cob wall basis, 4. on the basis of described, applies armoured concrete slab, and be allowed to be connected with anchor pole.
The beneficial effects of the invention are as follows:Not only side slope plays effective supporting and retaining system effect, can be with less section structure With vertical chest slope, larger supporting and retaining system height is obtained, realizes that quantities is small, technique is simple, the duration is shorter, cost is relatively low, safety Coefficient is high, vertical smooth alien invasion, is advantageous to arrange with other landscapes and arranges in pairs or groups, moulds preferable landscape effect.
Brief description of the drawings
The present invention is further illustrated below in conjunction with the accompanying drawings.
Fig. 1 is the cross-sectional configuration schematic diagram of the pull-type vertical retaining wall structure structure of anchor of the present invention and construction method embodiment.
Fig. 2 is the scene photograph figure after the completion of the pull-type vertical retaining wall structure constructive embodiment construction of anchor of the present invention.
Code description in figure:1-basis;2-anchor pole;3-armoured concrete slab;4-former slopes;5-embankment recently; Excavation platform before 6-wall.
Embodiment
It is new to the present invention with reference to the accompanying drawings and examples to be described further.
As shown in Fig. 1, armoured concrete slab 3 is set in the former side of slopes 4, armoured concrete slab is placed on basis 1, and It is connected with anchor pole 2, is constructing soil 5 recently between former slopes 4 and breast boards 3, armoured concrete slab 3 is beneficial to filling out recently Build soil 5 and wall before excavation platform 6 greening, landscape arrangement carry out beautification matching.
The present invention is realized by following technical proposals:It is connected by basis 1, armoured concrete slab 3, anchor pole 2 The supporting and retaining system system of composition.
Further, construction method of the present invention in the preferable location of geological conditions:1., excavation slope 4 to designed elevation, 2., apply basis 1 and anchor pole 2,3., on described basic 1, apply armoured concrete slab 3, and be allowed to be connected with anchor pole 2.
Further, construction method of the present invention in geology defective sector:1., apply with anchor pole 2, excavation slope 4 is entered 2., excavation slope 4 to designed elevation row pre-reinforcement, 3., earth-retaining foundation of wall 1 is applied, 4. on described basic 1, applies reinforcing bar and mix Concrete board 3, and be allowed to be connected with anchor pole 2.
Further, the present invention is connected by armoured concrete slab 3 and anchor pole 2, improves the pull-type vertical earth-retaining of anchor The resistant slide and stability against overturning of wall construction, with less retaining wall section width, less earthwork evacuation amount, obtain compared with Big supporting and retaining system height, has largely saved quantities.
Further, the present invention can not only play effective supporting and retaining system effect with side slope, with smaller quantities, obtain larger Supporting and retaining system height, and the vertical smooth alien invasion of retaining wall is elegant in appearance, is advantageous to arrange with other landscapes and arranges in pairs or groups, is not only suitable for Require that landscape higher place uses, and also is adapted for cross-section in scenic spot, bustling business district and high-end residential cell etc. Face direction does not have slope space, and the place that control of investment is tight, safety requirements is high, construction period is short is promoted the use of.
Some principles of the anchor of the present invention pull-type vertical retaining wall structure structure described above that simply explains through diagrams, are not intended to By the present invention be confined to shown in and described scheme and construction method within, therefore every corresponding modification for being possible to be utilized with And equivalent, belong to the apllied the scope of the claims of the present invention.

Claims (7)

1. the pull-type vertical retaining wall structure structure of anchor and construction method, its design is by basis, armoured concrete slab and anchor pole Connect the supporting and retaining system system of composition;Construction method:1st, the construction method in the preferable location of geological conditions:1., excavation slope to design mark 3., on the basis of described height, 2., basis and anchor pole are applied, applies armoured concrete slab, and be allowed to be connected with anchor pole;2、 The construction method of geology defective sector:1., apply and anchor pole, pre-reinforcement is carried out to excavation slope, 2., excavation slope is to designing mark Height, 3., earth-retaining foundation of wall is applied, 4. on the basis of described, apply armoured concrete slab, and be allowed to be connected with anchor pole.
2. the pull-type vertical retaining wall structure structure of anchor and construction method according to claim 1, it is characterized in that:Armored concrete On the basis of plate is placed in.
3. the pull-type vertical retaining wall structure structure of anchor and construction method according to claim 1, it is characterized in that:Armored concrete Plate is the structure being connected with anchor pole.
4. the pull-type vertical retaining wall structure structure of anchor and construction method according to claim 1, it is characterized in that:Retaining structure is horizontal The very little or none slope space in section direction.
5. the pull-type vertical retaining wall structure structure of anchor and construction method according to claim 1, it is characterized in that:Alien invasion is smooth It is attractive in appearance, it is easy to arrange with other landscapes and arranges in pairs or groups.
6. the pull-type vertical retaining wall structure structure of anchor and construction method according to claim 1, it is characterized in that in geological conditions The construction method in preferable location:1., excavation slope to designed elevation, 3., on the basis of described 2., apply basis and anchor pole, apply Make armoured concrete slab, and be allowed to be connected with anchor pole.
7. the pull-type vertical retaining wall structure structure of anchor and construction method according to claim 1, it is characterized in that:Geology is poorly The construction method of section:1., apply and anchor pole, 2., excavation slope to designed elevation pre-reinforcement is carried out to excavation slope, 3., applied Earth-retaining foundation of wall, 4. on the basis of described, armoured concrete slab is applied, and be allowed to be connected with anchor pole.
CN201710710394.3A 2017-05-11 2017-08-18 The pull-type vertical retaining wall structure structure of anchor and construction method Pending CN107447776A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201720519098 2017-05-11
CN2017205190980 2017-05-11

Publications (1)

Publication Number Publication Date
CN107447776A true CN107447776A (en) 2017-12-08

Family

ID=60492786

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201710710394.3A Pending CN107447776A (en) 2017-05-11 2017-08-18 The pull-type vertical retaining wall structure structure of anchor and construction method
CN201721036186.1U Active CN207672602U (en) 2017-05-11 2017-08-18 The pull-type vertical retaining wall structure structure of anchor

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201721036186.1U Active CN207672602U (en) 2017-05-11 2017-08-18 The pull-type vertical retaining wall structure structure of anchor

Country Status (1)

Country Link
CN (2) CN107447776A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110093871A (en) * 2019-04-18 2019-08-06 中铁四院集团西南勘察设计有限公司 The culvert closing-in structure and its construction method of steep slope region are filled out suitable for height
CN110258628A (en) * 2019-07-18 2019-09-20 中国电建集团成都勘测设计研究院有限公司 Anchor draws road shoulder retaining wall

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102352632A (en) * 2011-07-29 2012-02-15 重庆大学 Anchor rod sheet pile combined structure and method for reinforcing high filling body on one side of slope
CN203729324U (en) * 2014-01-02 2014-07-23 中交第二航务工程勘察设计院有限公司 Anchor rod lattice type retaining wall structure
WO2016095629A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Advanced support structure for oversized variable-cross-section tunnel

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102352632A (en) * 2011-07-29 2012-02-15 重庆大学 Anchor rod sheet pile combined structure and method for reinforcing high filling body on one side of slope
CN203729324U (en) * 2014-01-02 2014-07-23 中交第二航务工程勘察设计院有限公司 Anchor rod lattice type retaining wall structure
WO2016095629A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Advanced support structure for oversized variable-cross-section tunnel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110093871A (en) * 2019-04-18 2019-08-06 中铁四院集团西南勘察设计有限公司 The culvert closing-in structure and its construction method of steep slope region are filled out suitable for height
CN110258628A (en) * 2019-07-18 2019-09-20 中国电建集团成都勘测设计研究院有限公司 Anchor draws road shoulder retaining wall

Also Published As

Publication number Publication date
CN207672602U (en) 2018-07-31

Similar Documents

Publication Publication Date Title
CN105040706B (en) A kind of Retaining Structure with Double-row Piles and its construction method that can make full use of basement space
CN206655248U (en) A kind of assembly concrete empty van soil-baffling structure
CN104563130B (en) A kind of cross fender post and the double construction method doing agent structure of space enclosing structure
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN202559377U (en) Mutually-embedded ecological building block
CN204590038U (en) A kind of permanent foundation pit supporting construction
CN204738302U (en) Multi -storey frame formula double row pile supporting construction
CN104563131A (en) Rectangular enclosure pile, and construction method using rectangular enclosure pile as main structure
CN104863177A (en) Composite retaining wall structure and construction method thereof
CN102953385B (en) Construction method for changing support of foundation pit at irregular place of rampway
CN107447776A (en) The pull-type vertical retaining wall structure structure of anchor and construction method
CN210104786U (en) Road shoulder retaining component capable of greening
KR101807504B1 (en) Retaining wall block assembly for plants with easy installation
CN201891130U (en) Flexible precast block retaining wall structure
CN209243910U (en) A kind of side slope building structure
CN208235579U (en) A kind of variable slope wave mutually-embedded ecological building block retaining wall system
CN207727612U (en) Rib column formula anchored bolt retaining wall structure
CN202543946U (en) Supporting structure for drainage type fender posts in soft soil area
CN203821399U (en) Deep foundation pit supporting structure
KR20020076530A (en) Afforestation Retaining-Wall laying Concrete-block
CN204435390U (en) A kind of rectangle fender pile
CN106592626B (en) A kind of construction method of the retaining wall structure for superelevation embankment
CN108396774A (en) A kind of variable slope wave mutually-embedded ecological building block retaining wall system and its construction method
CN204982906U (en) Double row pile supporting construction in ability make full use of basement space
KR200413303Y1 (en) Stone stacked wall structure using steel beam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20171208

WD01 Invention patent application deemed withdrawn after publication