JP2900226B2 - 既設管ライニング補修工法のピグ導入方式 - Google Patents
既設管ライニング補修工法のピグ導入方式Info
- Publication number
- JP2900226B2 JP2900226B2 JP6293500A JP29350094A JP2900226B2 JP 2900226 B2 JP2900226 B2 JP 2900226B2 JP 6293500 A JP6293500 A JP 6293500A JP 29350094 A JP29350094 A JP 29350094A JP 2900226 B2 JP2900226 B2 JP 2900226B2
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- resin
- lining
- liquid
- pig
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Protection Of Pipes Against Damage, Friction, And Corrosion (AREA)
- Pipe Accessories (AREA)
- Application Of Or Painting With Fluid Materials (AREA)
- Coating Apparatus (AREA)
Description
給管を補修対象とし、該供給管の管内をライニングする
に要する必要量の液状樹脂を、第1工程では供給管の末
端の地上開口部より管内にプラグ状に導入してその後方
より圧入する液体流により樹脂プラグの全量を導管側の
分岐位置まで移送し、第2工程では上記地上開口部に接
続された吸引ポンプにより管内の液体流を吸引排出さ
せ、その吸引力により供給管の末端側に引き戻される樹
脂プラグの流動により管内面に樹脂を塗布してライニン
グを形成するように補修施工するライニング工法におい
て、その第1工程時の、ライニング施工用の均しピグの
管内導入方式に関するものである。
出願人は、特開平4−114773号公報に記載されて
いるような補修工法を提案している。
導管より需要先に向けて分岐された供給管を対象とする
場合、非掘削による補修方式として、供給管の末端側に
備えたメータを外してこれを地上開口部とし、この地上
開口部より、供給管の管内をライニングするに要する必
要量の液状樹脂を、第1工程では管内にプラグ状に導入
してその後方管内に圧入する液体流により樹脂プラグの
全量を導管側の分岐位置まで移送し、第2工程では地上
開口部に接続された吸引ポンプにより液体流を吸引排出
させ、その吸引力で供給管の末端側に引き戻される樹脂
プラグの流動により管内面に樹脂を塗布して所要のライ
ニング膜を形成するように補修施工を行っている。
によりライニング施工を行う際には、次のようなトラブ
ルが発生する。すなわち、上記した第1工程では、樹脂
の管内注入に先行して管内に導入されるライニング施工
用の均しピグは1個しかない。管路上にチーズ部などが
存在するような場合は、樹脂プラグの先頭側に位置する
均しピグがこのチーズ部の凹みに入り込むことがしばし
ば発生するので、その後の吸引ライニング施工が適正に
行われない事態が生じかねない。
とを目的とし、樹脂プラグの先頭側に位置するライニン
グ施工用の均しピグが少なくとも1個が確保されるピグ
導入方式を提供することを目的とするものである。
めに、本発明は、導管より分岐された供給管を補修対象
とし、該供給管の管内をライニングするに要する必要量
の液状樹脂を、第1工程では供給管の末端の地上開口部
より管内にプラグ状に導入してその後方より圧入する液
体流により樹脂プラグの全量を導管側の分岐位置まで移
送し、第2工程では上記地上開口部に接続された吸引ポ
ンプにより管内の液体流を吸引排出させ、その吸引力に
より供給管の末端側に引き戻される樹脂プラグの流動に
より管内面に樹脂を塗布してライニングを形成する管内
面のライニング補修工法において、上記第1工程では、
樹脂の管内導入時に、導入される樹脂プラグの先頭側に
位置するようにライニング施工用の均しピグを独立した
状態で前後2個配置して管内に導入することを特徴とす
る。
1工程では、樹脂の管内注入時には、導入される樹脂プ
ラグの先頭側に位置するようにライニング施工用の均し
ピグを前後2個配置して管内に導入することから、樹脂
の管内移送中に1個の均しピグが管路上のチーズ部等の
凹みに入り込んでも、残りの1個が入り込まないこと
で、その後の吸引ライニング施工が適正に行われること
を確保できる。
づいて説明する。図1は、第1工程(液体流により、樹
脂の管内注入・移送)の施工状態を示している。第1工
程では、ライニング施工用の均しピグ3を、管内に導入
される樹脂プラグの先頭側に位置するように前後2個配
置して管内に導入する。そして、樹脂注入装置11を使
って、送液ポンプ10の作動により得られた液圧で樹脂
Aを地上開口部14より管内に注入する。その後、ピグ
カセット8を使って同じ液圧で樹脂搬送ピグ4、吸液材
5および遮液ピグ6を管内に導入する。次に、続けて送
液ポンプ10を作動させることによって、液体タンク9
から液体Bが吸引・加圧されて、液体流制御装置20を
介して供給管7に注入されるので、樹脂Aが導管1側の
分岐位置2まで移送される。図中のRは、送液中の液体
圧力を一定に維持するように余分の液体を液体タンクに
戻すためのホースである。
2などが存在するような場合は、樹脂プラグの先頭側に
位置する一個の均しピグ3がこのチーズ部の凹みに入り
込むことがあるとしても、残りの1個が入り込むことが
ないので、その後の吸引ライニング施工が適正に行われ
ることが確保される。
の施工状態を示している。第2工程では、ピグ止め装置
18と、回収タンク17と、吸引ポンプ16とが直列の
形式で管路側に接続されている。吸引ポンプ16により
管内の液体流Bを吸引排出させ、その吸引力で供給管の
末端側に引き戻される樹脂プラグの流動により管内面に
樹脂を塗布してライニング膜を形成する。
ないように確保された1個の均しピグ3によって、管内
面に塗布されるライニング膜の厚さが均一なものとな
る。
入される樹脂プラグの先頭側に位置するようにライニン
グ施工用の均しピグを前後2個配置して管内に導入する
ことから、樹脂の管内移送中に1個の均しピグが管路上
のチーズ部等の凹みに入り込んでも、残りの1個が入り
込まないことで、その後の吸引ライニング施工が適正に
行われることを確保できる。確保された均しピグによっ
て、管内面に塗布されるライニング膜の厚さが均一なも
のとなる。
体流により、樹脂の管内注入・移送)を示す説明図であ
る。
る。
Claims (1)
- 【請求項1】 導管より分岐された供給管を補修対象と
し、該供給管の管内をライニングするに要する必要量の
液状樹脂を、第1工程では供給管の末端の地上開口部よ
り管内にプラグ状に導入してその後方より圧入する液体
流により樹脂プラグの全量を導管側の分岐位置まで移送
し、第2工程では上記地上開口部に接続された吸引ポン
プにより管内の液体流を吸引排出させ、その吸引力によ
り供給管の末端側に引き戻される樹脂プラグの流動によ
り管内面に樹脂を塗布してライニングを形成する管内面
のライニング補修工法において、 上記第1工程では、樹脂の管内導入時に、導入される樹
脂プラグの先頭側に位置するようにライニング施工用の
均しピグを独立した状態で前後2個配置して管内に導入
することを特徴とする既設管ライニング補修工法のピグ
導入方式。
Priority Applications (9)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6293500A JP2900226B2 (ja) | 1994-11-28 | 1994-11-28 | 既設管ライニング補修工法のピグ導入方式 |
ES95308218T ES2149325T3 (es) | 1994-11-28 | 1995-11-15 | Procedimientos de revestimiento de la superficie interna de un tubo. |
DE69517393T DE69517393T2 (de) | 1994-11-28 | 1995-11-15 | Verfahren zur Innenbeschichtung eines Rohres |
EP95308218A EP0715115B1 (en) | 1994-11-28 | 1995-11-15 | Methods of lining the internal surface of a pipe |
CA002163309A CA2163309C (en) | 1994-11-28 | 1995-11-20 | Methods of lining the internal surface of a pipe |
US08/560,928 US5700405A (en) | 1994-11-28 | 1995-11-20 | Method of lining the internal surface of a pipe |
US08/746,194 US5716672A (en) | 1994-11-28 | 1996-11-06 | Methods of lining the internal surface of a pipe |
US08/746,193 US5667841A (en) | 1994-11-28 | 1996-11-06 | Methods of lining the internal surface of a pipe |
US08/746,195 US5853629A (en) | 1994-11-28 | 1996-11-06 | Method of lining the internal surface of a pipe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6293500A JP2900226B2 (ja) | 1994-11-28 | 1994-11-28 | 既設管ライニング補修工法のピグ導入方式 |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH08141501A JPH08141501A (ja) | 1996-06-04 |
JP2900226B2 true JP2900226B2 (ja) | 1999-06-02 |
Family
ID=17795549
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP6293500A Expired - Lifetime JP2900226B2 (ja) | 1994-11-28 | 1994-11-28 | 既設管ライニング補修工法のピグ導入方式 |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2900226B2 (ja) |
-
1994
- 1994-11-28 JP JP6293500A patent/JP2900226B2/ja not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH08141501A (ja) | 1996-06-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2900226B2 (ja) | 既設管ライニング補修工法のピグ導入方式 | |
JPH11169788A (ja) | 既設管路の更生修理工法 | |
JP2852616B2 (ja) | 既設管ライニング補修工法 | |
JP2852618B2 (ja) | 既設管ライニング補修工法の樹脂搬送ピグ | |
JP2782326B2 (ja) | 管内面ライニング補修工法の液体流制御装置 | |
JP2963375B2 (ja) | 既設管路の修理工法 | |
JP3107485B2 (ja) | 管内面ライニング補修工法 | |
JP3167253B2 (ja) | 既設配管の更生修理工法 | |
JP2781907B2 (ja) | 既設配管のライニング装置 | |
JP2813675B2 (ja) | 既設管ライニング補修工法の樹脂注入装置 | |
JPS6124066B2 (ja) | ||
JP3515604B2 (ja) | 管内ライニング方法 | |
JP2821569B2 (ja) | 既設管ライニング工法の吸引装置 | |
EP0761417B1 (en) | A method of repairing a pipe | |
JP3264907B2 (ja) | 既設管路の更生修理工法 | |
JP3081349B2 (ja) | 管内のライニング方法 | |
JP3117895B2 (ja) | 既設配管の修理工法 | |
JP2807755B2 (ja) | 既設管ライニング工法の吸引装置 | |
JP2001519014A (ja) | 反転装置 | |
JP3300308B2 (ja) | 既設管路の更生修理工法 | |
JP2796577B2 (ja) | 管内面ライニング補修工法 | |
JPH10180168A (ja) | 部分更生修理治具及び更生修理工法 | |
JP3534930B2 (ja) | 分岐管路の補修方法、補修用バッグ及び補修材 | |
JP2843930B2 (ja) | 管路のライニング工法 | |
JP2900212B2 (ja) | 既設配管の内面ライニング補修工法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080319 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090319 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090319 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100319 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100319 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110319 Year of fee payment: 12 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110319 Year of fee payment: 12 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120319 Year of fee payment: 13 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120319 Year of fee payment: 13 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130319 Year of fee payment: 14 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130319 Year of fee payment: 14 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140319 Year of fee payment: 15 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |