EP3094788A1 - Konstruktionsverfahren zur verankerung einer hohlsäule zum tragen von meereskonstruktionen und offshore-plattformen auf dem meeresgrund - Google Patents

Konstruktionsverfahren zur verankerung einer hohlsäule zum tragen von meereskonstruktionen und offshore-plattformen auf dem meeresgrund

Info

Publication number
EP3094788A1
EP3094788A1 EP15737412.5A EP15737412A EP3094788A1 EP 3094788 A1 EP3094788 A1 EP 3094788A1 EP 15737412 A EP15737412 A EP 15737412A EP 3094788 A1 EP3094788 A1 EP 3094788A1
Authority
EP
European Patent Office
Prior art keywords
hollow column
seabed
steel
concrete
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP15737412.5A
Other languages
English (en)
French (fr)
Other versions
EP3094788A4 (de
Inventor
Carlos Wong
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cbj (hong Kong) Ocean Engineering Ltd
Original Assignee
Cbj (hong Kong) Ocean Engineering Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cbj (hong Kong) Ocean Engineering Ltd filed Critical Cbj (hong Kong) Ocean Engineering Ltd
Publication of EP3094788A1 publication Critical patent/EP3094788A1/de
Publication of EP3094788A4 publication Critical patent/EP3094788A4/de
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/40Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/04Equipment specially adapted for raising, lowering, or immobilising the working platform relative to the supporting construction
    • E02B17/06Equipment specially adapted for raising, lowering, or immobilising the working platform relative to the supporting construction for immobilising, e.g. using wedges or clamping rings
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/18Foundations formed by making use of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • E02D27/525Submerged foundations, i.e. submerged in open water using elements penetrating the underwater ground
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/06Constructions, or methods of constructing, in water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/44Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with enlarged footing or enlargements at the bottom of the pile

Definitions

  • the example embodiment in general relates to a construction method for fixing hollow cylindrical columns for supporting an offshore marine platform thereon, which in turn is adapted to support wind turbines, bridges and marine buildings thereon, to a seabed in a marine environment, and more particularly to a method in which the hollow column is employed as a temporary cofferdam during construction of the pile cap in a dry environment, thereby lowering construction costs and improving safety.
  • a type of commander base on site is needed to support the development of ocean resources that include offshore wind energy, ocean current and tidal energies, ocean fish farms, and even the building of an ocean city, etc.
  • the base may be fixed to the seabed or may be configured so as to float in the water.
  • a drawback of the floating-type base is that mooring the base for the purpose of anchorage is difficult where the water depth is shallower than 50m. The base drifts aimlessly if the mooring lines are broken as this would pose great danger to the public.
  • a fixed base is often more desirable and offers greater safety than the floating base.
  • a stationery fixed platform is desirable in that it offers riders the comfort similar to living on land, as opposed to the boat living on the floating base.
  • the conventional method for fixing the hollow column to the seabed in preparation for placing a platform deck of an offshore platform thereon utilizes a plurality of piles, whereby the pile cap is typically constructed under water on the seabed.
  • a temporary steel cofferdam-type of structure is used to provide a dry working environment within the interior of the hollow column.
  • use of a temporary cofferdam is costly. Therefore, what is needed is a method that eliminates the temporary cofferdam so as to drastically lower both cost and construction time. Further, if there is a precast factory on land to produce parts of the platform, with the platform thereafter assembled on top of the already fixed hollow column, improved mass production capabilities and speed of construction is possible.
  • An example embodiment is directed to a construction method for fixing a foundation for supporting waterborne structures such as an offshore platform to a seabed, the foundation having one or more hollow cylindrical columns that are to be fixed to the seabed, such as a seabed comprising a thick layer of soft marine deposits.
  • a plurality of steel tubes are driven into the founding layer in the seabed at an installation location of the hollow column, the steel tubes having a given free length above sea level, and the hollow column is then lowered down to the seabed so that the steel tubes are within the hollow column.
  • Underwater concrete is injected between the seabed and bottom of the hollow column so as to form a concrete plug.
  • the interior of the hollow column is dewatered so as to be used as a cofferdam, and then the steel tubes are cut above a pile cap level or determined design level. Thereafter, concrete is injected to cast the pile cap so as to complete the foundation.
  • Another example embodiment is directed to a construction method for fixing a foundation for supporting waterborne structures such as an offshore platform to a seabed, the foundation having one or more hollow cylindrical columns that are to be fixed to the seabed.
  • a plurality of steel tubes is driven into the founding layer in the seabed, and the hollow column is then lowered down to the seabed so as to surround the steel tubes.
  • a reinforced concrete plug is then formed in the bottom of the hollow column, the hollow column configured as a cofferdam.
  • the interior of the hollow column is then dewatered, pile cap reinforcement is fixed, and then concrete is cast to form a pile cap.
  • FIG. 1 is an indicative intermediate construction stage according to an example construction method of fixing a hollow column to a seabed.
  • FIG. 2 is an indicative final construction stage according to an example construction method of fixing a hollow column to a seabed.
  • FIG. 3 is an indicative sectional view F-F of FIG. 1.
  • FIG. 4 is an indicative sectional view G-G of FIG. 1.
  • FIG. 5 is an indicative elevation sectional view showing the formation of the pile cap.
  • FIG. 6A is an indicative side view showing the shear key at the surface of the steel casing or steel pipe pile in a section of the pile that is expected to be embedded in the concrete plug.
  • FIG. 6B is a cross-sectional view taken from line H-H in FIG. 6A to illustrate the layout of shear keys in the steel casing or steel pipe pile.
  • FIG. 6C is a magnified view of a portion of the shear keys in FIG. 6A.
  • FIG. 7A, 7B, 8 and 9 indicatively show three different skirting options for three different seabed geologies.
  • a and/or B means that: (i) A is true and B is false; or (ii) A is false and B is true; or (iii) A and B are both true.
  • the term “hollow column” refers to a hollow cylindrical column fixed to the seabed in a body of water on which a wind power turbine, marine building, and/or bridge may be mounted thereon.
  • the example construction method for fixing a hollow column to the seabed includes driving steel tubes (also referred to herein as steel pipe piles or “piles” ) into the founding layer in the seabed, lowering the hollow column to the seabed so as to surround the steel tubes, and forming a reinforced concrete plug in the bottom of the hollow column, the hollow column being configured as a cofferdam.
  • the interior of the hollow column is then dewatered, pile cap reinforcement is fixed, and concrete is finally cast to form a pile cap thereby completing the installation, in preparation for thereafter supporting a to-be-built platform deck of a waterborne structure such as an offshore marine platform thereon.
  • the hollow column serves as the cofferdam during the construction stage, e.g., without having to employ the typical costly temporary steel cofferdam; moreover, the hollow column is part of the support structure for a waterborne structure such as an offshore marine platform. It is further both safe and efficient.
  • the pile may be a steel pipe pile having a length portion within the pile cap that can be modified so as to be integrated into the reinforcement cage of the to-be-cast pile cap, to be cast in-situ.
  • a temporary pile head jacking prop with level and position adjusting jacks is fixed to the top of the pile to support the hollow column.
  • a monitoring camera may be used to investigate the bottom of the hollow column so as to determine if there are any large voids or gaps. If found, these voids and gaps are filled with sand gravel.
  • the concrete plug that is formed is not purely for stopping water coming in, as in the conventional construction method. Rather, the concrete plug also provides support to the hollow column. This is because reinforcement steel bars are pre-installed at the bottom of the hollow column in gaps between piles. These reinforcement steel bars translate the conventional concrete plug into a reinforced concrete slab. In an alternative, the bottom part of the concrete plug extends in a radial direction a short distance. To enhance the bond between the concrete plug and the piles, an expected section of the pile that is to be embedded in the concrete plug may be welded with triangular-shaped shear keys.
  • the bottom of the hollow column may be installed with a skirting.
  • the skirting includes a steel plate having a diameter larger than that of the hollow column, so as to prevent an excessive loss of concrete sideways during casting of the concrete plug.
  • the skirting includes a cantilever plate with stiffeners and is fixed by bolts to the bottom end of the hollow column.
  • the skirting has a steel skirting board that is oriented approximately perpendicular to the cantilever.
  • the skirting may be embodied as a steel ring with teething extending from the end of the hollow column.
  • the skirting may be embodied as a plurality of radially-distributed L-shaped steel plates bolted to the end of the hollow column.
  • the example construction method eliminates the need for a costly temporary cofferdam and also eliminates the need for underwater execution; hence, employment of the example method at an installation location substantially reduces the construction risks and substantially improves the quality of works.
  • FIGS. 1-9 should be referred to for describing an example method of fixing an offshore marine platform adapted to support wind turbines, bridges and marine buildings thereon to a seabed which may include a thick layer of soft materials within a marine environment.
  • the example method is based on fixing a precast, reinforced, concrete hollow cylindrical column having a diameter in a range of about 8-10m or larger to a seabed using a plurality of steel pipe piles or “piles” .
  • the example embodiment suits a seabed overlain with a layer of soft material, which is common in a near shore seabed.
  • FIGS. 1, 2 and 5 illustrate an example embodiment of the method as directed to a near shore application. It is understood that a person of skill in the art is capable of extending this example application to any similar type of water zones. It should be clear that the construction vessels used in this example could be of any similar construction vessels; hence, details of their function are omitted herein for purposes of brevity.
  • a plurality of pile 49 are sunk at the location of hollow column 108, e.g., for example, four (4) or more steel piles 49 may be arranged within the internal space of a hollow column 108 and driven into the seabed 2 to the suitable stratum.
  • the piles 49 could be oriented vertically or inclined, so long as they do not hinder the insertion of the hollow column 108 downward into seabed 2 so as to enclose the piles 49.
  • stabilization bracing 119 is prepared for stabilizing each pile 49 position, e.g., bracing 119 is bolted to the piles 49 after the insertion of the hollow column 108 enclosing the group of piles 49.
  • the bracing 119 can be configured in a triangular pattern or any other geometry.
  • a temporary pile head jacking prop 113 with level adjusting jacks is then fixed to the top of the steel piles 49.
  • the prop 113 is made by cutting the top of the steel piles 49 to a required level, then welding a thick steel plate to the pile head and placing a jack on the plate.
  • an installation vessel hoists the hollow column 108, which has been precast on land, and inserts the hollow column 108 into the group of piles 49 down to the seabed 2 so that the piles 49 are arranged within the interior of the hollow column 108.
  • the wall of the hollow column 108 should enclose the pile group without touching any of the piles 49.
  • part of the wall of the hollow column 108 penetrates the seabed 2. Thereafter the stabilization bracing 119 is installed.
  • the hollow column 108 is installed with a temporary cross frame 112, which may be fixed to the wall of the hollow column 108 by welding or bolting.
  • the cross frame 112 is supported by the pile head jacking support 113, the level of which is adjustable so that the hollow column 108 level can be adjusted to the required level above sea level 1.
  • a monitoring camera may be used to inspect if there are any gaps between the wall of the hollow column 108 and the seabed 2. If gaps are discovered, sand gravel is added to fill the gaps.
  • a tremie pipe is then used to inject tremie concrete (underwater concrete) into the bottom of the hollow column 108 to form a concrete plug 43. Concrete plug 43 is adapted to prevent water from coming in. As shown on FIG. 1, the concrete migrates outward under a gravity effect and is confined by a skirting plate.
  • the bottom end of the wall of the hollow column 108 is pre-installed with reinforcement steel bars 45, such that the conventional mass concrete plug is translated into reinforced concrete slab.
  • the conventional mass concrete plug 43 serves as a small pile cap capable of supporting the weight of the hollow column 108, and its buoyancy, plus any construction loads during construction.
  • the small pile cap/concrete plug 43 provides a water stop function that allows dewatering inside the hollow column 108. Accordingly, the wall of the hollow column 108 now functions in the role of a cofferdam to stop water from entering therein.
  • the construction vessels can be withdrawn.
  • the hollow column 108 is now standing firm in the sea and is prepared for the platform deck construction thereon.
  • a plurality of lapping bars 111 may be pre-installed for connection to the platform deck.
  • the steel casing is filled with reinforced concrete from the level of pile cap 44 down to the bottom of the bored hole.
  • the hollow column 108 may be embodied as a singular reinforced concrete element; however, it is also possible for the hollow column 108 to be divided into several segments.
  • a plurality of concrete shear keys and positioning blocks (both well known art and not shown for brevity) provided at the segment common end faces may be used to hold the segments together by pre-stressed bars. Segments can be assembled on the construction vessel and hoisted as a singular article for installation. Thereafter the procedures are similar to those described above.
  • the steel pile surface (similarly the steel casing surface in a concrete bored pile configuration) has a plurality of triangular shear keys 50 welded thereto in such an orientation that the sharp angles of the shear keys 50 are pointing downward; this orientation facilitates soil layer penetration.
  • These shear keys 50 may distributed on the surface of a section of the pile/casing 49A that comes into contact with the small pile cap/concrete plug 43; see FIGS. 6A-6C for example.
  • Shear keys 50 in this example are embodied as small triangular-shaped pieces of metal with the sharp angles pointing downward. Although the shear keys 50 offer little resistance to the pile 49/casing being driven downward through the soil layer, the keys 50 provide great resistance to hollow column 108 downward movement; the hollow column 108 is resisted by the surface and mechanical bonds of the shear keys 50. It should be clear that the shape of the shear keys 50 is not limited to that shown in FIGS. 6A-6C; any geometric form that increases the surface area of the contact face between the steel pile 49/steel casing and small pile cap/concrete plug 43 is also feasible.
  • the example embodiment is applicable to seabeds having different geological conditions, which may broadly be classified into three (3) categories: 1) a seabed composed of a soft material, mainly marine mud; 2) a seabed composed of sandy clay, and 3) a seabed formed of hard weathered rock.
  • a seabed composed of a soft material mainly marine mud
  • a seabed composed of sandy clay mainly kaolin
  • a seabed formed of hard weathered rock a seabed formed of hard weathered rock.
  • different skirting options are employed based on the category or geological condition of the seabed 2.
  • FIGS. 7A and 7B indicatively show a cantilever skirting for application in soft marine deposit.
  • the main function of skirting is to confine the underwater concrete within a skirting board during casting of the concrete plug (small pile cap) 43, although the skirting provides a secondary function of reducing the bearing pressure on the seabed 2 due to the increased contact area.
  • FIG. 7A shows a skirting in a circular form comprising a cantilever plate 121 bolted to the bottom end of the wall of the hollow column 108, with its outer edge at a radius greater than that of hollow column 108.
  • a plurality of stiffeners 123 may be distributed evenly in a circle.
  • the skirting in this example further includes a skirting board 122 attached to the outer edge of the cantilever plate 121.
  • the skirting may be prefabricated in factory and fixed to the bottom end of the wall of the hollow column 108 by bolts 124.
  • FIG. 8 shows another skirting option for sandy seabed.
  • This ring skirting comprises a steel ring 141 bolted to the bottom end of the wall of the hollow column 108. Teething 142 is attached to the steel ring 141. The teething 142 allows the wall of the hollow column 108 to penetrate into the sandy seabed, to make close contact with the seafloor so as to prevent the underwater concrete from escaping sideways during the casting of the concrete plug (small pile cap) 43.
  • FIG. 9 illustrates yet another skirting option for a seabed composed of weathered rock. Any kind of penetration cannot be used, since the weathered rock is extremely hard to penetrate. It is impossible for a single skirting to cover a general uneven terrain of the seabed.
  • the solution is to use a plurality of L-shaped skirting plates 131 attached to the bottom end of the wall of the hollow column 108. As shown in FIG. 9, this example skirting is divided into 64 L-shaped skirting plates 131 configured to ride over any uneven terrain in the seabed 2, thereby preventing an excessive loss of underwater concrete during casting of the concrete plug (small pile cap) 43.
  • the installation and construction of marine structures or offshore platforms using the example hollow column 108 eliminates the need for a temporary cofferdam, greatly reducing cost and construction time. Additionally, using the hollow column 108 to guard off water enhances the safety of workers inside the hollow column 108.
  • the formed concrete plug 43 is not merely a mass of concrete, but a specially designed, reinforced concrete plug having dual functions: a first function as a water stop and a second function as a temporary (small) pile cap supporting the hollow column 108 during the construction of the permanent pile cap 44. To enhance the first function, a skirting may be added to the end of the hollow column 108. To enhance the second function, shear keys 50 are welded to the surface of the piles 49 at the section of the piles 49A that is expected to be embedded in the concrete plug 43.
  • the present invention in various embodiments, configurations, and aspects, includes components, methods, processes, systems and/or apparatus substantially as depicted and described herein, including various embodiments, sub-combinations, and subsets thereof. Those of skill in the art will understand how to make and use the present invention after understanding the present disclosure.
  • the present invention in various embodiments, configurations, and aspects, includes providing devices and processes in the absence of items not depicted and/or described herein or in various embodiments, configurations, or aspects hereof, including in the absence of such items as may have been used in previous devices or processes, e.g., for improving performance, achieving ease and ⁇ or reducing cost of implementation.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)
  • Revetment (AREA)
  • Bridges Or Land Bridges (AREA)
EP15737412.5A 2014-01-15 2015-01-14 Konstruktionsverfahren zur verankerung einer hohlsäule zum tragen von meereskonstruktionen und offshore-plattformen auf dem meeresgrund Withdrawn EP3094788A4 (de)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201410018362.3A CN104775446B (zh) 2014-01-15 2014-01-15 水上结构固定用筒墩及其安装施工方法
PCT/CN2015/070659 WO2015106679A1 (en) 2014-01-15 2015-01-14 Construction method for fixing hollow column for supporting marine structures and offshore platforms to a seabed

Publications (2)

Publication Number Publication Date
EP3094788A1 true EP3094788A1 (de) 2016-11-23
EP3094788A4 EP3094788A4 (de) 2017-08-16

Family

ID=53542405

Family Applications (1)

Application Number Title Priority Date Filing Date
EP15737412.5A Withdrawn EP3094788A4 (de) 2014-01-15 2015-01-14 Konstruktionsverfahren zur verankerung einer hohlsäule zum tragen von meereskonstruktionen und offshore-plattformen auf dem meeresgrund

Country Status (8)

Country Link
US (1) US20160340852A1 (de)
EP (1) EP3094788A4 (de)
JP (1) JP2017503101A (de)
CN (1) CN104775446B (de)
HK (1) HK1212404A1 (de)
PH (1) PH12016501403A1 (de)
SG (1) SG11201605777XA (de)
WO (1) WO2015106679A1 (de)

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105887695A (zh) * 2016-05-25 2016-08-24 中交第航务工程局有限公司 应用于钢圆筒底部的钢抱箍支撑体系
CN105970998A (zh) * 2016-06-16 2016-09-28 江苏海上龙源风力发电有限公司 一种带隔板的箱式重力式海上风机基础
CN107476328A (zh) * 2017-09-20 2017-12-15 中恒建设集团有限公司 一种打入式预制墩基础施工工法
CN108425370A (zh) * 2018-05-17 2018-08-21 北京翔鲲水务建设有限公司 组合式围堰及其施工方法
CN108660941A (zh) * 2018-07-24 2018-10-16 东北大学 一种锁扣钢管拼接桩围堰及施工方法
CN109098201A (zh) * 2018-10-12 2018-12-28 西南交通大学 一种超大平面面积部分预应力混凝土沉井基础及其施工方法
CN109339033B (zh) * 2018-10-19 2022-03-25 中交第二航务工程局有限公司 一种低水位下高桩承台斜桩堵漏结构与施工方法
CN109403318B (zh) * 2018-12-17 2024-03-26 福建永福电力设计股份有限公司 一种海上风电植入型单桩基础及其施工方法
CN109440802A (zh) * 2018-12-25 2019-03-08 郭兆泉 性能优异的砂衬齿形桩及其施工方法
CN110565667B (zh) * 2019-09-29 2024-06-25 中铁大桥局第九工程有限公司 一种具有注浆平台的钢板桩围堰
CN111995339A (zh) * 2020-07-16 2020-11-27 天津大学前沿技术研究院有限公司 一种海洋平台抗冲刷的固化土及其制备方法
DE102020125842A1 (de) 2020-10-02 2022-04-07 Rwe Renewables Gmbh Gründung für ein Offshore-Bauwerk
CN112281898A (zh) * 2020-10-21 2021-01-29 中铁大桥勘测设计院集团有限公司 一种浮力补偿式组合基础及施工方法
CN112523204A (zh) * 2020-11-24 2021-03-19 中铁大桥局集团第六工程有限公司 一种灌注桩下放钢筋笼的施工平台及其施工方法
CN113062341B (zh) * 2021-03-31 2022-04-12 广州市市政集团有限公司 一种8字形ct锁扣钢管桩与拉森钢板桩组合围堰结构
CN113700033B (zh) * 2021-08-06 2022-09-23 中铁大桥勘测设计院集团有限公司 一种深水群桩基础
CN113815788A (zh) * 2021-09-22 2021-12-21 广州文船重工有限公司 一种套笼装船加固方法
CN115362292B (zh) * 2022-07-06 2023-08-18 中交第二航务工程局有限公司 一种高桩码头上部结构及其施工装备和施工方法

Family Cites Families (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2317016A (en) * 1939-10-20 1943-04-20 Herschel H Allen Bridge foundation and method of making same
JPS5143284B2 (de) * 1972-11-13 1976-11-20
US3946571A (en) * 1975-02-06 1976-03-30 Dresser Industries, Inc. Service module for hostile environment
US4266889A (en) * 1979-11-23 1981-05-12 The United States Of America As Represented By The Secretary Of The Navy System for placing freshly mixed concrete on the seafloor
JPS60203738A (ja) * 1984-09-27 1985-10-15 Tomoegumi Iron Works Ltd 杭基礎構造
JPH0613773B2 (ja) * 1986-07-22 1994-02-23 大成建設株式会社 水中構造物の基礎施工方法
CN1017360B (zh) * 1990-02-16 1992-07-08 交通部第一航务工程局第三工程公司 水中桥墩承台施工方法及设备
JP2718241B2 (ja) * 1990-03-23 1998-02-25 鹿島建設株式会社 軟弱海底地盤上の基礎施工法
JP2561176B2 (ja) * 1990-12-11 1996-12-04 五洋建設株式会社 鉛直係留式洋上浮遊構造物用テンプレート設置方法
JPH0718675A (ja) * 1993-06-30 1995-01-20 Mitsui Constr Co Ltd Sc杭及びその施工方法
JPH10121450A (ja) * 1996-10-24 1998-05-12 Maeda Corp ケーソンと基礎杭との結合工法
JPH10147920A (ja) * 1996-11-19 1998-06-02 Tokyo Electric Power Co Inc:The 重力式構造物及び重力式構造物の施工方法
US20030085482A1 (en) * 1997-05-07 2003-05-08 Paul Sincock Repair of structural members
JPH11193648A (ja) * 1997-12-29 1999-07-21 Takenaka Komuten Co Ltd 浮力を利用した免震・沈下対策構造物
JP3614007B2 (ja) * 1998-12-09 2005-01-26 株式会社大林組 水中基礎の構築工法
JP2000352062A (ja) * 1999-06-10 2000-12-19 Nippon Steel Corp 鋼管杭と基礎コンクリート構造との接合構造と接合方法
JP3275017B2 (ja) * 1999-07-08 2002-04-15 国土交通省関東地方整備局長 プレキャスト部材を使用したケーソンの製作方法
JP2001214419A (ja) * 2000-02-02 2001-08-07 Penta Ocean Constr Co Ltd ケーソンによる海洋構造物の設置工法
JP3848611B2 (ja) * 2002-09-25 2006-11-22 鹿島建設株式会社 構造物の基礎地盤の強度増加方法
JP2005023730A (ja) * 2003-07-02 2005-01-27 Ohbayashi Corp スカートサクション基礎構造体および同構造体の設置方法
JP4529529B2 (ja) * 2004-04-26 2010-08-25 株式会社大林組 水中構造物の構築方法
CN100591863C (zh) * 2007-10-19 2010-02-24 山东高速青岛公路有限公司 水下无封底混凝土套箱及其应用方法
KR101134780B1 (ko) * 2009-12-23 2012-04-13 대림산업 주식회사 수중 기초에 의해 지지되는 교각 시공방법
CN102251530B (zh) * 2011-04-27 2012-10-03 中铁二十局集团第二工程有限公司 黄河主河道水中墩承台施工用双壁钢围堰施工工艺
CN102425184A (zh) * 2011-12-13 2012-04-25 中交第二公路工程局有限公司 深水软土地基逆作法低桩承台复合基础承台预留孔施工方法
JP5976373B2 (ja) * 2012-04-20 2016-08-23 鹿島建設株式会社 杭基礎の補強構造および補強方法
CN102644293B (zh) * 2012-04-25 2014-09-10 中交第二航务工程局有限公司 桩基桶形基础的施工方法
CN102852094B (zh) * 2012-08-31 2015-03-18 中交第二航务工程局有限公司 无掩护海洋环境下预制墩台安装板桩组合结构施工方法

Also Published As

Publication number Publication date
CN104775446B (zh) 2021-06-15
HK1212404A1 (en) 2016-06-10
US20160340852A1 (en) 2016-11-24
SG11201605777XA (en) 2016-08-30
EP3094788A4 (de) 2017-08-16
WO2015106679A1 (en) 2015-07-23
JP2017503101A (ja) 2017-01-26
CN104775446A (zh) 2015-07-15
PH12016501403A1 (en) 2016-08-31

Similar Documents

Publication Publication Date Title
WO2015106679A1 (en) Construction method for fixing hollow column for supporting marine structures and offshore platforms to a seabed
JP2017503101A5 (de)
US9567720B2 (en) Offshore platform for a marine environment
EP3118374A1 (de) Hohler zylindrischer pfeiler zur befestigung einer offshore-plattformkonstruktion am meeresgrund sowie verfahren zur installation und konstruktion davon
CN102979069A (zh) 一种在深水急流无覆盖层陡峭裸岩上的钻孔桩平台施工方法
CN102953362B (zh) 一种设置在深水急流无覆盖层陡峭裸岩上的钻孔桩平台
CN102839681A (zh) 深水无覆盖层条件下组合钢管桩围堰及其施工方法
CN110820765A (zh) 一种狭小深基坑预制围护结构及施工方法
CN102561371A (zh) 岛遂结合部钢沉箱围护结构
CN104264683B (zh) 三面环绕文保建筑凹字形超深基坑分区支护方法
KR101256265B1 (ko) 임시 물막이공정이 생략된 교각의 수중설치공법.
KR100975988B1 (ko) 수중 구조물의 축조 공법
CN107059914A (zh) 一种用于水中浅覆盖层或裸岩地区的环状嵌入式设置基础
WO2016109962A1 (en) Construction method for fixing offshore marine platform to a seabed having layers of a soil/clay nature
CN104762942B (zh) 水上建筑海洋固定平台软土地基海底固定安装施工法
AU2012313196B2 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
JP2016084660A (ja) 洋上風力発電装置の基礎構造
EP2933379B1 (de) Schiffstragwerk in kombination mit in-situ-testplattform
JP2020128672A (ja) 洋上風力発電用のモノパイル基礎の施工方法および洋上風力発電用のモノパイル基礎
CN102146669B (zh) 可搬迁固定式人工岛筒型基础
CN203049560U (zh) 一种设置在深水急流无覆盖层陡峭裸岩上的钻孔桩平台
JPH09316894A (ja) 橋脚基礎構造およびその構築方法
Castillo Garcia et al. Effect of Seabed Trenching on Holding Capacity of Suction Anchors in Deepwater Gulf of Guinea Clays: A Numerical Study
CN202881899U (zh) 一种适用于外海开敞水域的码头结构
CN110397070A (zh) 一种筒边桩式海上风电基础

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20160720

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

DAX Request for extension of the european patent (deleted)
A4 Supplementary search report drawn up and despatched

Effective date: 20170717

RIC1 Information provided on ipc code assigned before grant

Ipc: E02D 27/14 20060101AFI20170711BHEP

Ipc: E02D 27/42 20060101ALI20170711BHEP

Ipc: E02D 19/04 20060101ALI20170711BHEP

Ipc: E02D 29/09 20060101ALI20170711BHEP

Ipc: E02D 5/44 20060101ALI20170711BHEP

Ipc: E02D 27/52 20060101ALI20170711BHEP

Ipc: E02D 5/40 20060101ALI20170711BHEP

Ipc: E02D 27/18 20060101ALI20170711BHEP

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20180801