EP2708658A1 - Struktur zur gebündelten installation grosskalibriger unterwassergehäuse unter verwendung von spundwänden und konstruktionsverfahren dafür - Google Patents
Struktur zur gebündelten installation grosskalibriger unterwassergehäuse unter verwendung von spundwänden und konstruktionsverfahren dafür Download PDFInfo
- Publication number
- EP2708658A1 EP2708658A1 EP11865671.9A EP11865671A EP2708658A1 EP 2708658 A1 EP2708658 A1 EP 2708658A1 EP 11865671 A EP11865671 A EP 11865671A EP 2708658 A1 EP2708658 A1 EP 2708658A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- steel pipes
- piles
- installation
- caliber
- sheet piles
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/002—Ground foundation measures for protecting the soil or subsoil water, e.g. preventing or counteracting oil pollution
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/02—Restraining of open water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/18—Foundations formed by making use of caissons
Definitions
- the present invention relates to a large-caliber casing construction for preventing a collapse or an inflow of an earth layer during excavation of the ground for laying a foundation in the process of building a underwater structure, such as a dam, a bridge, and an offshore wind structure under water, such as sea and river, and more particularly, to a temporary structure of a large-caliber casing type and a method of constructing the same, which enables batch installation after prefabrication to thereby reduce field work and can flexibly cope with irregular underwater ground.
- a stable foundation work on the underwater ground must be preceded.
- the foundation work of the underwater ground is carried out through a method of constructing mono piles after excavating the underwater ground.
- a temporary structure of a large-caliber casing type Before excavation of the underwater ground, it is necessary to install a temporary structure of a large-caliber casing type in the foundation work area in order to prevent an inflow of weak soil or water into the foundation work area or a collapse of the underwater ground.
- a method of embedding large-caliber casing steel pipes (large-caliber steel pipe pile type) is a representative method of constructing temporary structures.
- the large-caliber steel pipe pile type is a method of manufacturing integrally large-caliber casing steel pipes with steel materials around a factory or a construction field, carrying the manufactured steel pipes into the construction field and constructing them while sinking them in water.
- Such a method can reduce field work but has several problems in that it needs large-scale equipment for carrying and lifting the large-sized casing steel pipes and in that stabilization work of the underwater ground must be previously carried out in order to stably settle and install the casing steel pipes in the underwater ground.
- the method cannot prevent a collapse or an inflow of an earth layer while the casing steel pipes excavate the underwater ground.
- the present invention has been made in an effort to solve the above-mentioned problems occurring in the prior arts, and it is an object of the present invention to provide a temporary structure of a large-caliber casing type and a method of constructing the same, which enables batch installation after prefabrication to thereby reduce field work and can flexibly cope with irregular underwater ground.
- the present invention provides a underwater large-caliber casing structure which is completed by installing sheet piles between steel pipes through a claw connection method and a construction method of a large-caliber casing including the steps of prefabricating steel pipes and sheet piles, installing them in a lump, and embedding and installing center piles and the sheet piles in the ground under water.
- the temporary structure of the large-caliber casing type and the method of constructing the same according to the present invention have the following effects.
- the large-caliber casing work can be carried out in the minimized field work because sheet piles are installed after being prefabricated. Accordingly, the present invention can reduce the construction period of time and construction expenses in relation with foundation work of the underwater structure.
- the underwater large-caliber casing is constructed in such a manner that the sheet piles and the steel pipes are first installed in an assembled state and H-piles are installed inside the steel pipes of the assembled body, there is little possibility to cause a construction error, and as a result, the present invention can enhance the construction quality due to a schemeful construction.
- the present invention can install sheet piles while coping with an irregular underwater ground even though the surface of a hard layer (or a rock layer) on the seabed or a riverbed is in a very irregular state, it can prevent a collapse of soil during excavation of the underwater ground inside the casing for laying the foundation.
- the present invention provides a temporary batch-installation-type underwater large-caliber casing structure using sheet piles including: steel pipes having a plurality of claw connectors disposed on the outer peripheral surface thereof, the steel pipes being spaced apart from each other at predetermined intervals and installed in the ground under water in such a manner that the claw connectors are opposed to each other; sheet piles having a plurality of claw connectors disposed at end portions thereof, the sheet piles being installed in such a way as to close spaces between the steel pipes and being embedded in the ground under water while engaging with the steel pipes through the claw connectors; a horizontal strut fixed inside or outside the casing to horizontally connect the steel pipes; and center piles respectively inserted into the steel pipes and fixed to the steel pipes while being embedded into the ground under water.
- the present invention provides a construction method of a temporary batch-installation-type underwater large-caliber casing structure including the steps of: (S11) assembling steel pipes, sheet piles and a horizontal strut in such a manner that the sheet piles are not located lower than the steel pipes; (S12) carrying the assembled body of the step (S11) into a construction field and seating the steel pipes on the ground under water; (S13) inserting and driving center piles into the steel pipes so as to embed them into the ground under water; (S14) fixing the center piles to the steel pipes; and (S15) driving the sheet piles so as to embed them into the ground under water.
- FIGS. 1 and 2 are a plan view and a perspective view of a temporary underwater large-caliber casing structure according to the present invention.
- the underwater large-caliber casing is a temporary structure for preventing a collapse or an inflow of an earth layer during excavation of the ground for laying a foundation in the process of building an underwater structure, such as a dam, a bridge, and an offshore wind structure under water, such as sea and river.
- the underwater large-caliber casing assembling structure includes steel pipes 10, sheet piles 20, a horizontal strut 30, and center piles 50.
- the steel pipe 10 is an empty hollow member and has a claw connector 13 disposed on the outer peripheral surface thereof.
- a plurality of the steel pipes 10 are arranged at predetermined intervals and are seated on the bottom under water in such a manner that the claw connectors 13 are opposed to each other.
- Such steel pipes 10 serve as a guide pipe of the center piles 50 respectively inserted and mounted inside the steel pipes.
- the sheet piles 20 are sheet type pile members which respectively have claw connectors 23 disposed at ends thereof so as to be joined to each other through a claw connection, and are generally the same as typical sheet piles used for retaining walls or cofferdams.
- the sheet piles 20 are arranged in mutual claw connection one by one and are installed under the ground while being driven into the ground.
- the sheet piles 20 are embedded and installed to the underwater ground while being engaged and connected with the steel pipes 10 through the claw connectors 13 and 23 between the steel pipes 10 so as to form a casing of a closed structure together with the steel pipes 10.
- the sheet piles 20 are joined one another in engagement with one another and with the steel pipes 10 so as to close spaces between the steel pipes 10 by the sheet piles 20.
- the horizontal strut 30 is fixedly mounted while horizontally connecting the steel pipes 10 inside or outside the casing.
- a plurality of the steel pipes 10 are restricted and reinforced into one body by the horizontal strut 30.
- the horizontal strut 30 includes an outer strut 31 which is continuously mounted from the outside of the casing.
- the horizontal strut 30 is fixed only to the steel pipes 10 and simply gets in contact with the sheet piles 20, such that the sheet piles 20 can be embedded and installed in the underwater ground while being driven even in a state where the steel pipes 10, the horizontal strut 30 and the sheet piles 20 are assembled together.
- the horizontal strut 30 may be disposed parallel to each other in multistage, and in this instance, vertical strut 40 may be additionally disposed for vertically connecting the multistage horizontal strut 30.
- the horizontal strut 30 and the vertical strut 40 may be adopted from general steel members having a proper cross section, such as H-shaped steels, ⁇ -shaped channels, angles, and others, according to structural designs, and FIG. 1 illustrates the outer strut 31 having the H-shaped steel and the vertical strut 40 having the ⁇ -shaped channel.
- the center pile 50 is inserted into the steel pipe 10 and fixed to the steel pipe 10 while being embedded to the underwater ground.
- the center piles 50 are embedded and mounted in the underwater ground together with the sheet piles 20 and serve to stably settle the temporary casing structure to the underwater ground. It is possible that the center piles 50 are embedded deeper than the sheet piles 20 if possible because the center piles 50 are H beams.
- the center piles 50 are properly adopted from general steel members, such as H-shaped steels, and FIG. 1 illustrates the center piles 50 having the H-shaped steels. Meanwhile, the center piles 50 are fixed to the steel pipes 10, and for this, couplers may be used properly.
- the underwater large-caliber casing according to the present invention is the temporary structure which will be demolished before long, it is preferable that the couplers are mounted by a wedge type fixing method or a bolt fastening method so as to be easily attached and detached rather than the welding method.
- the temporary underwater large-caliber casing structure is finished.
- the casing of the closed structure is completed through the claw connection of the steel pipes 10 and the sheet piles 20, and the temporary structure can keep a stable construction state through settlement of the center piles 50 and the sheet piles 20 in the underwater ground.
- the temporary underwater large-caliber casing structure according to the present invention may have a circular closed structure or a polygonal closed structure.
- FIGS. 1 and 2 show a temporary casing structure of the polygonal closed structure.
- the steel pipes 10 are arranged in such a way as to be located at edges of a polygon and the sheet piles 20 are arranged in such a way as to be located as sides of the polygon to thereby complete the polygonal closed structure.
- the polygonal closed structure can be easily completed when general straight steel members are applied as the horizontal struts 30 as they are.
- the horizontal strut 30 has inner and outer struts 31 and 32 which are spaced apart from each other and respectively mounted in parallel with each other inside and outside the casing, and the sheet piles 20 are contactingly mounted between the inner and outer struts 31 and 32.
- Such an installation structure of the horizontal strut 30 is favorable in securing a stable reinforcing structure by the inner and outer struts 31 and 32 and keeping perpendicularity of the sheet piles 20 during the process of embedding and installing the sheet piles 20.
- FIG. 3 is a detailed diagram showing a connected state of a steel pipe and a sheet pile of the temporary underwater large-caliber casing structure according to the present invention.
- the steel pipes 10 are formed by properly transforming conventional steel pipes.
- the steel pipe 10 includes: a steel pipe body 11; a wing sheet 12 welded on the outer peripheral surface of the steel pipe body 11; and a claw connector 13 formed by an end portion of the wing sheet 12 curved.
- the sheet pile 20 is divided in half and joined to both sides of the steel pipe body 11, such that the steel pipe 10 having the claw connector 13 is completed.
- the steel pipe 10 is simply joined during the claw connection of the sheet pile 20.
- FIGS. 4 to 7 are flow charts showing a construction method of the temporary underwater large-caliber casing structure according to the present invention, and illustrate the method of constructing the temporary underwater large-caliber casing structure of FIGS. 1 and 2 . Now, the construction method of the temporary underwater large-caliber casing structure according to the present invention will be described.
- the steel pipes 10, the sheet piles 20 and the horizontal strut 30 are assembled, and the vertical struts 40 may be further assembled in the case that the vertical struts 40 are installed (S11, See FIG. 4 ).
- the sheet piles 20 are equal to or longer than the steel pipes 10, and preferably, are not located lower than the steel pipes 10. The reason is not to be interfered by the sheet piles 20 and to stably install the steel pipes 10 in the ground under water.
- the assembled body assembled in the step S11 is carried into a construction field, and the steel pipes 10 are seated and installed in the ground under water (S12, See FIG. 5 ).
- the steel pipes 10 are installed while being lifted by a crane, and the assembled body is held not to be moved after the installation.
- the center piles 50 of the H-shaped steels are inserted and driven into the steel pipes 10 so as to be embedded in the ground under water (S13, See FIG. 6 ).
- the center piles 50 are fixed in the steel pipes 10 (S14), and the sheet piles 20 are driven to be embedded and installed in the ground under water (S15, See FIG. 7 ).
- a crane, a hammer, or others may be used properly.
- the temporary large-caliber casing structure is completely constructed. Because arrangement of the previously assembled body, insertion and driving of the center piles 50, and driving of the sheet piles 20 are just carried out in the construction field, the present invention can reduce a work amount in the construction field and allow rapid construction work.
- FIGS. 8 to 10 are flow charts showing a process of constructing an underwater structure while applying the construction method of the temporary underwater large-caliber casing structure according to FIGS. 4 to 7 , wherein the flow charts respectively show construction sequences of a mono-pile for offshore wind and a pier for a bridge.
- FIGS. 8 and 9 illustrate a construction sequence of the mono-pile (MP).
- the temporary underwater large-caliber casing structure is constructed in a construction position (See FIG> 8), and the construction method is the same as FIGS. 4 to 7 .
- a drilling rig is inserted into the temporary casing structure and fixed to the top of a jackup barge, and then, a drilling base machine and the drilling rig are connected with each other so as to drill the inside of the temporary casing structure (See FIG. 9(a) ).
- drilling water is supplied to the inside of the temporary casing structure in a reverse cycle, and then, drilling water and rock fragments are discharged out through a drill pipe.
- the mono-pile (MP) is inserted and installed inside an excavation hole ( FIG.
- FIG. 9(b) various grouting materials, such as concrete, mortar, or other filling materials, fill between the mono-pile and the excavation hole ( FIG. 9(c) ), and then, the temporary casing structure is removed ( FIG. 9(d) ).
- the removal work is carried out in reverse. In other words, first, the sheet piles 20 are drawn out from the ground under water, the fixed state of the center piles 50 is released to draw out the center piles 50 from the ground under water and remove the center piles 50 from the steel pipes 10, and then, the assembled body of the steel pipes 10, the sheet piles 20 and the horizontal strut 30 is lifted and carried. Through the above process, the underwater structure like the mono-pile can be constructed completely.
- FIG. 10 illustrates a construction sequence of a pier under water.
- the temporary underwater large-caliber casing structure is constructed at the construction position.
- water is supplied to the inside of the temporary casing structure by a water lift pump ( FIG.10(a) ), and then, when the underwater ground is exposed inside the temporary casing structure, a foundation of the pier (P1) and a pier body (P2) are constructed in the ground under water (FIGS. 19(b) and (c)).
- the temporary casing structure is removed ( FIG. 10(e) ). In this instance, the removal of the temporary structure is the same as the construction process of the mono-pile described above. Through the above process, the underwater structure such as the pier of the bridge is constructed completely.
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Foundations (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
- Earth Drilling (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020110045103A KR101106219B1 (ko) | 2011-05-13 | 2011-05-13 | 시트파일을 이용한 일괄설치형 수중 대구경 케이싱 가설구조물 및 그 시공방법 |
PCT/KR2011/009993 WO2012157829A1 (ko) | 2011-05-13 | 2011-12-22 | 시트파일을 이용한 일괄설치형 수중 대구경 케이싱 가설구조물 및 그 시공방법 |
Publications (1)
Publication Number | Publication Date |
---|---|
EP2708658A1 true EP2708658A1 (de) | 2014-03-19 |
Family
ID=45614347
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP11865671.9A Withdrawn EP2708658A1 (de) | 2011-05-13 | 2011-12-22 | Struktur zur gebündelten installation grosskalibriger unterwassergehäuse unter verwendung von spundwänden und konstruktionsverfahren dafür |
Country Status (4)
Country | Link |
---|---|
EP (1) | EP2708658A1 (de) |
KR (1) | KR101106219B1 (de) |
AU (1) | AU2011368478B2 (de) |
WO (1) | WO2012157829A1 (de) |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102016972B1 (ko) * | 2017-01-13 | 2019-09-03 | 권혁빈 | 수중 토목구조물의 시공방법 |
CN109356166B (zh) * | 2018-11-06 | 2023-12-29 | 福建卓越建设工程开发有限公司 | 钢管桩-拉森钢板桩曲直结合打设组合支护体系及施工方法 |
KR102205948B1 (ko) | 2018-11-16 | 2021-01-21 | 한국건설기술연구원 | 중구경 및 소구경 핀파일을 이용한 초대구경 모노파일의 암반 고정 방법 |
KR20200134761A (ko) | 2019-05-23 | 2020-12-02 | 양필규 | 파일 거푸집 상단에 장착되는 작업대 |
CN110485305A (zh) * | 2019-08-27 | 2019-11-22 | 中铁大桥局集团有限公司 | 用于水中桥梁基础施工的钢护筒防掉落平台及其施工方法 |
CN113431071B (zh) * | 2021-05-24 | 2022-05-13 | 徐州中矿岩土技术股份有限公司 | 堤坝管涌事故的救援管子和应急救援管件及其使用方法 |
CN114960890B (zh) * | 2022-04-15 | 2024-09-03 | 中国港湾工程有限责任公司 | 近海排水口的施工方法 |
CN115369858B (zh) * | 2022-07-29 | 2023-12-12 | 中国化学工程第六建设有限公司 | 钢管混凝土柱施工工艺 |
CN117166462B (zh) * | 2023-09-08 | 2024-05-07 | 湖北省工业建筑集团有限公司 | 一种硬质岩结合地层的旋挖钻桩基施工装置及方法 |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4231194B2 (ja) | 2000-09-06 | 2009-02-25 | 新日本製鐵株式会社 | 護岸構造 |
KR100652454B1 (ko) * | 2005-03-25 | 2006-12-01 | 재현토건(주) | 대구경 강관을 이용한 수중구조물의 가물막이 시공방법 |
KR100923078B1 (ko) * | 2007-10-11 | 2009-11-02 | 현대건설주식회사 | 시트파일과 띠장을 이용한 가물막이의 시공방법 및 이를 이용한 수중 구조물 시공방법 |
KR100929141B1 (ko) * | 2007-10-26 | 2009-12-01 | 삼성물산 주식회사 | 분리형 가물막이용 가설 구조물 및 이를 이용한 가물막이시공방법 |
KR100884289B1 (ko) | 2008-06-23 | 2009-02-17 | 가원이엔씨 주식회사 | 복합형 강가시설 및 그 시공방법 |
KR100936161B1 (ko) * | 2009-07-31 | 2010-01-12 | 현대엔지니어링 주식회사 | 항만, 하천 및 댐 공사용 친환경 다변형 셀식 가물막이 공법 |
-
2011
- 2011-05-13 KR KR1020110045103A patent/KR101106219B1/ko not_active IP Right Cessation
- 2011-12-22 WO PCT/KR2011/009993 patent/WO2012157829A1/ko active Application Filing
- 2011-12-22 EP EP11865671.9A patent/EP2708658A1/de not_active Withdrawn
- 2011-12-22 AU AU2011368478A patent/AU2011368478B2/en not_active Ceased
Non-Patent Citations (1)
Title |
---|
See references of WO2012157829A1 * |
Also Published As
Publication number | Publication date |
---|---|
WO2012157829A1 (ko) | 2012-11-22 |
AU2011368478B2 (en) | 2014-10-02 |
AU2011368478A1 (en) | 2013-03-28 |
KR101106219B1 (ko) | 2012-01-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU2011368478B2 (en) | Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same | |
US9567720B2 (en) | Offshore platform for a marine environment | |
JP6762800B2 (ja) | 既設杭基礎の補強工法及び補強構造 | |
JP5057223B2 (ja) | 鋼製セグメントを用いた仮締切壁の施工方法 | |
KR102011321B1 (ko) | 변단면 각관을 이용한 환형 기초의 시공방법 및 그 기초 | |
KR100927186B1 (ko) | 흙막이 및 차수용 연속 벽체 시공방법 | |
CN110359476B (zh) | 一种钢板桩围堰内支撑与钻孔桩钢护筒安装用施工平台的施工方法 | |
JP5257407B2 (ja) | 腹起し材の設置方法および設置構造 | |
JP5986429B2 (ja) | ケーソン及びその製造方法 | |
JP2012117209A (ja) | 潜函工法及び潜函工法用設備 | |
CN212200387U (zh) | 一种深水软弱淤泥地区的地连墙基础钢导墙结构 | |
JP6760529B1 (ja) | 防水壁および防水壁の構築方法 | |
JP2023140927A (ja) | 地中構造物の構築方法および地中構造物 | |
CN211873023U (zh) | 基坑支护装置 | |
JP2007107233A (ja) | 土留構造物の構築方法 | |
JP7275844B2 (ja) | 壁状構造物及び壁状構造物の構築方法 | |
JP2017197910A (ja) | 土留壁構造の構築方法および土留壁構造 | |
CN111119159A (zh) | 一种深水软弱淤泥地区的地连墙基础钢导墙结构 | |
JP4475116B2 (ja) | 立坑構造及びその構築方法 | |
CN111119200A (zh) | 基坑支护装置 | |
CN111206594A (zh) | 基坑支护施工方法 | |
KR20210015135A (ko) | 말뚝 보강재 가이드 장치 및 이의 시공방법 | |
JP6800365B1 (ja) | 既設ケーソン基礎の補強方法 | |
CN215669530U (zh) | 一种可周转基坑支护体系 | |
CN115324087B (zh) | 深水嵌岩组合式轻型围堰 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 20130307 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
DAX | Request for extension of the european patent (deleted) | ||
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN |
|
18D | Application deemed to be withdrawn |
Effective date: 20150701 |