AU2011368478B2 - Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same - Google Patents

Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same

Info

Publication number
AU2011368478B2
AU2011368478B2 AU2011368478A AU2011368478A AU2011368478B2 AU 2011368478 B2 AU2011368478 B2 AU 2011368478B2 AU 2011368478 A AU2011368478 A AU 2011368478A AU 2011368478 A AU2011368478 A AU 2011368478A AU 2011368478 B2 AU2011368478 B2 AU 2011368478B2
Authority
AU
Australia
Prior art keywords
underwater
steel pipes
casing
caliber
temporary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
AU2011368478A
Other versions
AU2011368478A1 (en
Inventor
Sun Keun Park
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CORE GEOTECHNICS CO Ltd
Original Assignee
CORE GEOTECHNICS CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CORE GEOTECHNICS CO Ltd filed Critical CORE GEOTECHNICS CO Ltd
Publication of AU2011368478A1 publication Critical patent/AU2011368478A1/en
Application granted granted Critical
Publication of AU2011368478B2 publication Critical patent/AU2011368478B2/en
Ceased legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/002Ground foundation measures for protecting the soil or subsoil water, e.g. preventing or counteracting oil pollution
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/18Foundations formed by making use of caissons

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Foundations (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Earth Drilling (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The present invention relates to a large-caliber casing installation construction for preventing a collapse or an inflow of an earth layer during excavation of the ground for laying a foundation in the process of building a underwater structure, such as a dam, a bridge, an offshore wind structure under water, such as sea and river. The present invention completes a casing structure by installing a sheet pile between steel pipes and insertingly installing a center piles inside the steel pipes, and as a result, enables batch installation after first assembling the casing structure, and thus, can reduce field work and flexibly respond to irregular grounds underwater during construction.

Description

1 [DESCRIPTION] [Invention Title] Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for 5 constructing the same [Technical Field] The present invention relates to a large-caliber casing construction for preventing a collapse or an inflow of an 10 earth layer during excavation of the ground for laying a foundation in the process of building a underwater structure, such as a dam, a bridge, and an offshore wind structure under water, such as sea and river, and more particularly, to a temporary structure of a large-caliber casing type and a 15 method of constructing the same, which enables batch installation after prefabrication to thereby reduce field work and can flexibly cope with irregular underwater ground. [Background Art] 20 In order to stably construct an underwater structure, such as a dam, a bridge, and an offshore wind structure under water, such as sea and river, a stable foundation work on the underwater ground must be preceded. The foundation work of the underwater ground is carried out through a method of 25 constructing mono piles after excavating the underwater ground. Before excavation of the underwater ground, it is necessary to install a temporary structure of a large-caliber casing type in the foundation work area in order to prevent an inflow of weak soil or water into the foundation work area 30 or a collapse of the underwater ground. A method of embedding large-caliber casing steel pipes (large-caliber steel pipe pile type) is a representative method of 2 constructing temporary structures. The large-caliber steel pipe pile type is a method of manufacturing integrally large-caliber casing steel pipes with steel materials around a factory or a construction field, 5 carrying the manufactured steel pipes into the construction field and constructing them while sinking them in water. Such a method can reduce field work but has several problems in that it needs large-scale equipment for carrying and lifting the large-sized casing steel pipes and in that 10 stabilization work of the underwater ground must be previously carried out in order to stably settle and install the casing steel pipes in the underwater ground. Moreover, in the case that the underwater ground is developed irregularly, for instance, the bedrock is exposed or the 15 earth layer is distributed very thinly, because the casing steel pipes cannot flexibly cope with the underwater ground, the method cannot prevent a collapse or an inflow of an earth layer while the casing steel pipes excavate the underwater ground. 20 [Disclosure] [Technical Problem] Accordingly, the present invention has been made in an effort to solve the above-mentioned problems occurring in the 25 prior arts, and it is an object of the present invention to provide a temporary structure of a large-caliber casing type and a method of constructing the same, which enables batch installation after prefabrication to thereby reduce field work and can flexibly cope with irregular underwater ground. 30 [Technical Solution] 3 To achieve the above objects, the present invention provides a underwater large-caliber casing structure which is completed by installing sheet piles between steel pipes through a claw connection method and a construction method of 5 a large-caliber casing including the steps of prefabricating steel pipes and sheet piles, installing them in a lump, and embedding and installing center piles and the sheet piles in the ground under water. 10 [Advantageous Effects] The temporary structure of the large-caliber casing type and the method of constructing the same according to the present invention have the following effects. First, the large-caliber casing work can be carried out 15 in the minimized field work because sheet piles are installed after being prefabricated. Accordingly, the present invention can reduce the construction period of time and construction expenses in relation with foundation work of the underwater structure. 20 Second, because the underwater large-caliber casing is constructed in such a manner that the sheet piles and the steel pipes are first installed in an assembled state and H piles are installed inside the steel pipes of the assembled body, there is little possibility to cause a construction 25 error, and as a result, the present invention can enhance the construction quality due to a schemeful construction. Third, because the present invention can install sheet piles while coping with an irregular underwater ground even though the surface of a hard layer (or a rock layer) on the 30 seabed or a riverbed is in a very irregular state, it can prevent a collapse of soil during excavation of the underwater ground inside the casing for laying the foundation.
4 [Description of Drawings] FIGS. 1 and 2 are a plan view and a perspective view of a temporary underwater large-caliber casing structure 5 according to the present invention. FIG. 3 is a detailed diagram showing a connected state of a steel pipe and a sheet pile of the temporary underwater large-caliber casing structure according to the present invention. 10 FIGS. 4 to 7 are flow charts showing a construction method of the temporary underwater large-caliber casing structure according to the present invention. FIGS. 8 to 10 are flow charts showing a process of constructing an underwater structure while applying the 15 construction method of the temporary underwater large-caliber casing structure according to FIGS. 4 to 7, wherein the flow charts respectively show construction sequences of a mono pile for offshore wind and a pier for a bridge. 20 [Best Model The present invention provides a temporary batch installation-type underwater large-caliber casing structure using sheet piles including: steel pipes having a plurality of claw connectors disposed on the outer peripheral surface 25 thereof, the steel pipes being spaced apart from each other at predetermined intervals and installed in the ground under water in such a manner that the claw connectors are opposed to each other; sheet piles having a plurality of claw connectors disposed at end portions thereof, the sheet piles 30 being installed in such a way as to close spaces between the steel pipes and being embedded in the ground under water while engaging with the steel pipes through the claw 5 connectors; a horizontal strut fixed inside or outside the casing to horizontally connect the steel pipes; and center piles respectively inserted into the steel pipes and fixed to the steel pipes while being embedded into the ground under 5 water. The present invention provides a construction method of a temporary batch-installation-type underwater large-caliber casing structure including the steps of: (Sl) assembling steel pipes, sheet piles and a horizontal strut in such a 10 manner that the sheet piles are not located lower than the steel pipes; (S12) carrying the assembled body of the step (Sl) into a construction field and seating the steel pipes on the ground under water; (S13) inserting and driving center piles into the steel pipes so as to embed them into the 15 ground under water; (S14) fixing the center piles to the steel pipes; and (S15) driving the sheet piles so as to embed them into the ground under water. [Mode for Invention] 20 Reference will be now made in detail to the preferred embodiment of the present invention with reference to the attached drawings. FIGS. 1 and 2 are a plan view and a perspective view of a temporary underwater large-caliber casing structure 25 according to the present invention. The underwater large caliber casing is a temporary structure for preventing a collapse or an inflow of an earth layer during excavation of the ground for laying a foundation in the process of building an underwater structure, such as a dam, a bridge, and an 30 offshore wind structure under water, such as sea and river. The underwater large-caliber casing assembling structure 6 includes steel pipes 10, sheet piles 20, a horizontal strut 30, and center piles 50. The steel pipe 10 is an empty hollow member and has a claw connector 13 disposed on the outer peripheral surface 5 thereof. A plurality of the steel pipes 10 are arranged at predetermined intervals and are seated on the bottom under water in such a manner that the claw connectors 13 are opposed to each other. Such steel pipes 10 serve as a guide pipe of the center piles 50 respectively inserted and mounted 10 inside the steel pipes. The sheet piles 20 are sheet type pile members which respectively have claw connectors 23 disposed at ends thereof so as to be joined to each other through a claw connection, and are generally the same as typical sheet piles used for 15 retaining walls or cofferdams. In other words, the sheet piles 20 are arranged in mutual claw connection one by one and are installed under the ground while being driven into the ground. The sheet piles 20 are embedded and installed to the underwater ground while being engaged and connected with 20 the steel pipes 10 through the claw connectors 13 and 23 between the steel pipes 10 so as to form a casing of a closed structure together with the steel pipes 10. The sheet piles 20 are joined one another in engagement with one another and with the steel pipes 10 so as to close 25 spaces between the steel pipes 10 by the sheet piles 20. The horizontal strut 30 is fixedly mounted while horizontally connecting the steel pipes 10 inside or outside the casing. A plurality of the steel pipes 10 are restricted and reinforced into one body by the horizontal strut 30. For 30 a stable reinforcing structure, it is preferable that the horizontal strut 30 includes an outer strut 31 which is continuously mounted from the outside of the casing. The 7 horizontal strut 30 is fixed only to the steel pipes 10 and simply gets in contact with the sheet piles 20, such that the sheet piles 20 can be embedded and installed in the underwater ground while being driven even in a state where 5 the steel pipes 10, the horizontal strut 30 and the sheet piles 20 are assembled together. In the meantime, the horizontal strut 30 may be disposed parallel to each other in multistage, and in this instance, vertical strut 40 may be additionally disposed for vertically connecting the 10 multistage horizontal strut 30. The horizontal strut 30 and the vertical strut 40 may be adopted from general steel members having a proper cross section, such as H-shaped steels, E-shaped channels, angles, and others, according to structural designs, and FIG. 1 illustrates the outer strut 31 15 having the H-shaped steel and the vertical strut 40 having the E-shaped channel. The center pile 50 is inserted into the steel pipe 10 and fixed to the steel pipe 10 while being embedded to the underwater ground. The center piles 50 are embedded and 20 mounted in the underwater ground together with the sheet piles 20 and serve to stably settle the temporary casing structure to the underwater ground. It is possible that the center piles 50 are embedded deeper than the sheet piles 20 if possible because the center piles 50 are H beams. 25 Preferably, the center piles 50 are properly adopted from general steel members, such as H-shaped steels, and FIG. 1 illustrates the center piles 50 having the H-shaped steels. Meanwhile, the center piles 50 are fixed to the steel pipes 10, and for this, couplers may be used properly. Considering 30 that the underwater large-caliber casing according to the present invention is the temporary structure which will be demolished before long, it is preferable that the couplers 8 are mounted by a wedge type fixing method or a bolt fastening method so as to be easily attached and detached rather than the welding method. Through the above structure, the temporary underwater 5 large-caliber casing structure is finished. The casing of the closed structure is completed through the claw connection of the steel pipes 10 and the sheet piles 20, and the temporary structure can keep a stable construction state through settlement of the center piles 50 and the sheet piles 10 20 in the underwater ground. The temporary underwater large caliber casing structure according to the present invention may have a circular closed structure or a polygonal closed structure. FIGS. 1 and 2 show a temporary casing structure of the 15 polygonal closed structure. As shown in the drawings, the steel pipes 10 are arranged in such a way as to be located at edges of a polygon and the sheet piles 20 are arranged in such a way as to be located as sides of the polygon to thereby complete the polygonal closed structure. The 20 polygonal closed structure can be easily completed when general straight steel members are applied as the horizontal struts 30 as they are. Furthermore, in FIGS. 1 and 2, the horizontal strut 30 has inner and outer struts 31 and 32 which are spaced apart 25 from each other and respectively mounted in parallel with each other inside and outside the casing, and the sheet piles 20 are contactingly mounted between the inner and outer struts 31 and 32. Such an installation structure of the horizontal strut 30 is favorable in securing a stable 30 reinforcing structure by the inner and outer struts 31 and 32 and keeping perpendicularity of the sheet piles 20 during the process of embedding and installing the sheet piles 20.
9 FIG. 3 is a detailed diagram showing a connected state of a steel pipe and a sheet pile of the temporary underwater large-caliber casing structure according to the present invention. In FIG. 3, the steel pipes 10 are formed by 5 properly transforming conventional steel pipes. Concretely, the steel pipe 10 includes: a steel pipe body 11; a wing sheet 12 welded on the outer peripheral surface of the steel pipe body 11; and a claw connector 13 formed by an end portion of the wing sheet 12 curved. In other words, the 10 sheet pile 20 is divided in half and joined to both sides of the steel pipe body 11, such that the steel pipe 10 having the claw connector 13 is completed. The steel pipe 10 is simply joined during the claw connection of the sheet pile 20. FIGS. 4 to 7 are flow charts showing a construction 15 method of the temporary underwater large-caliber casing structure according to the present invention, and illustrate the method of constructing the temporary underwater large caliber casing structure of FIGS. 1 and 2. Now, the construction method of the temporary underwater large-caliber 20 casing structure according to the present invention will be described. First, the steel pipes 10, the sheet piles 20 and the horizontal strut 30 are assembled, and the vertical struts 40 may be further assembled in the case that the vertical struts 25 40 are installed (Sl, See FIG. 4) . The sheet piles 20 are equal to or longer than the steel pipes 10, and preferably, are not located lower than the steel pipes 10. The reason is not to be interfered by the sheet piles 20 and to stably install the steel pipes 10 in the ground under water. 30 Next, the assembled body assembled in the step Sl is carried into a construction field, and the steel pipes 10 are seated and installed in the ground under water (S12, See FIG.
10 5). The steel pipes 10 are installed while being lifted by a crane, and the assembled body is held not to be moved after the installation. Next, the center piles 50 of the H-shaped steels are 5 inserted and driven into the steel pipes 10 so as to be embedded in the ground under water (S13, See FIG. 6) . After that, the center piles 50 are fixed in the steel pipes 10 (S14), and the sheet piles 20 are driven to be embedded and installed in the ground under water (S15, See FIG. 7). In 10 this instance, a crane, a hammer, or others may be used properly. Through the above steps, the temporary large-caliber casing structure is completely constructed. Because arrangement of the previously assembled body, insertion and 15 driving of the center piles 50, and driving of the sheet piles 20 are just carried out in the construction field, the present invention can reduce a work amount in the construction field and allow rapid construction work. FIGS. 8 to 10 are flow charts showing a process of 20 constructing an underwater structure while applying the construction method of the temporary underwater large-caliber casing structure according to FIGS. 4 to 7, wherein the flow charts respectively show construction sequences of a mono pile for offshore wind and a pier for a bridge. 25 FIGS. 8 and 9 illustrate a construction sequence of the mono-pile (MP) . First, the temporary underwater large caliber casing structure is constructed in a construction position (See FIG> 8), and the construction method is the same as FIGS. 4 to 7. A drilling rig is inserted into the 30 temporary casing structure and fixed to the top of a jackup barge, and then, a drilling base machine and the drilling rig are connected with each other so as to drill the inside of 11 the temporary casing structure (See FIG. 9(a)). In this instance, drilling water is supplied to the inside of the temporary casing structure in a reverse cycle, and then, drilling water and rock fragments are discharged out through 5 a drill pipe. Next, the mono-pile (MP) is inserted and installed inside an excavation hole (FIG. 9(b)), various grouting materials, such as concrete, mortar, or other filling materials, fill between the mono-pile and the excavation hole (FIG. 9(c)), and then, the temporary casing 10 structure is removed (FIG. 9(d)). The removal work is carried out in reverse. In other words, first, the sheet piles 20 are drawn out from the ground under water, the fixed state of the center piles 50 is released to draw out the center piles 50 from the ground under water and remove the 15 center piles 50 from the steel pipes 10, and then, the assembled body of the steel pipes 10, the sheet piles 20 and the horizontal strut 30 is lifted and carried. Through the above process, the underwater structure like the mono-pile can be constructed completely. 20 FIG. 10 illustrates a construction sequence of a pier under water. In order to construct the underwater pier, as shown in FIG. 8, first, the temporary underwater large caliber casing structure is constructed at the construction position. Next, water is supplied to the inside of the 25 temporary casing structure by a water lift pump (FIG. 10(a)), and then, when the underwater ground is exposed inside the temporary casing structure, a foundation of the pier (P1) and a pier body (P2) are constructed in the ground under water (FIGS. 19(b) and (c)). Next, after water is supplied to the 30 inside the temporary casing structure (FIG. 10(d)), the temporary casing structure is removed (FIG. 10 (e)) . In this instance, the removal of the temporary structure is the same 12 as the construction process of the mono-pile described above. Through the above process, the underwater structure such as the pier of the bridge is constructed completely. As described above, while the present invention has been 5 particularly shown and described with reference to the example embodiments thereof, it will be understood by those of ordinary skill in the art that the above embodiments of the present invention are all exemplified and various changes, modifications and equivalents may be made therein without 10 departing from the scope of the present invention. Therefore, it would be understood that the technical and protective scope of the present invention shall be defined by the technical idea as defined by the following claims.
AU2011368478A 2011-05-13 2011-12-22 Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same Ceased AU2011368478B2 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
KR1020110045103A KR101106219B1 (en) 2011-05-13 2011-05-13 Sheetpile type large-diameter casing for underwater structure and construction method thereof
KR10-2011-0045103 2011-05-13
PCT/KR2011/009993 WO2012157829A1 (en) 2011-05-13 2011-12-22 Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same

Publications (2)

Publication Number Publication Date
AU2011368478A1 AU2011368478A1 (en) 2013-03-28
AU2011368478B2 true AU2011368478B2 (en) 2014-10-02

Family

ID=45614347

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2011368478A Ceased AU2011368478B2 (en) 2011-05-13 2011-12-22 Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same

Country Status (4)

Country Link
EP (1) EP2708658A1 (en)
KR (1) KR101106219B1 (en)
AU (1) AU2011368478B2 (en)
WO (1) WO2012157829A1 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102016972B1 (en) * 2017-01-13 2019-09-03 권혁빈 Construction Method of Underwater Civil Engineering Structure Foundation
CN109356166B (en) * 2018-11-06 2023-12-29 福建卓越建设工程开发有限公司 Steel pipe pile-Larson steel sheet pile bending direct combined driving combined supporting system and construction method
KR102205948B1 (en) 2018-11-16 2021-01-21 한국건설기술연구원 Method for connecting very large diameter mono-pile into rock using small and middle diameter pin pile
KR20200134761A (en) 2019-05-23 2020-12-02 양필규 The workstation mounted on top of file form
CN110485305A (en) * 2019-08-27 2019-11-22 中铁大桥局集团有限公司 Steel pile casting Anti-fall platform and its construction method for water Bridge foundation construction
CN113431071B (en) * 2021-05-24 2022-05-13 徐州中矿岩土技术股份有限公司 Rescue pipe and emergency rescue pipe fitting for dam piping accident and using method thereof
CN115369858B (en) * 2022-07-29 2023-12-12 中国化学工程第六建设有限公司 Construction process of concrete filled steel tubular column

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060102837A (en) * 2005-03-25 2006-09-28 재현토건(주) Cofferdam construction method using the large caliber steel pipe for the structures constructed over the water
KR100884289B1 (en) * 2008-06-23 2009-02-17 가원이엔씨 주식회사 Composite type steel temporary construction and construction method thereof
KR20090037114A (en) * 2007-10-11 2009-04-15 현대건설주식회사 Cofferdam, its construction method using sheet file and wale and construction method for underwater structure using the cofferdam
KR20090042677A (en) * 2007-10-26 2009-04-30 삼성물산 주식회사 Separate type template and costruction method for cofferdam using the same
KR20090089832A (en) * 2009-07-31 2009-08-24 현대엔지니어링 주식회사 Nature friendly polygon cell type coffering method for harbor, river and dam construction

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4231194B2 (en) 2000-09-06 2009-02-25 新日本製鐵株式会社 Revetment structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060102837A (en) * 2005-03-25 2006-09-28 재현토건(주) Cofferdam construction method using the large caliber steel pipe for the structures constructed over the water
KR20090037114A (en) * 2007-10-11 2009-04-15 현대건설주식회사 Cofferdam, its construction method using sheet file and wale and construction method for underwater structure using the cofferdam
KR20090042677A (en) * 2007-10-26 2009-04-30 삼성물산 주식회사 Separate type template and costruction method for cofferdam using the same
KR100884289B1 (en) * 2008-06-23 2009-02-17 가원이엔씨 주식회사 Composite type steel temporary construction and construction method thereof
KR20090089832A (en) * 2009-07-31 2009-08-24 현대엔지니어링 주식회사 Nature friendly polygon cell type coffering method for harbor, river and dam construction

Also Published As

Publication number Publication date
WO2012157829A1 (en) 2012-11-22
AU2011368478A1 (en) 2013-03-28
KR101106219B1 (en) 2012-01-19
EP2708658A1 (en) 2014-03-19

Similar Documents

Publication Publication Date Title
AU2011368478B2 (en) Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same
US9567720B2 (en) Offshore platform for a marine environment
CN106013052B (en) The construction method of steel sheet pile and open caisson Combined type underground garage parking
JP6762800B2 (en) Reinforcement method and structure of existing pile foundation
JP5057223B2 (en) Temporary wall construction method using steel segments
KR102011321B1 (en) Construction method of foundation using rectangular pipe and its foundation
KR100722665B1 (en) Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same
KR100927186B1 (en) Method of constructing cantilevered continuous wallsfor retaining earth and cutting off water
CN110359476B (en) Construction method of construction platform for mounting steel sheet pile cofferdam inner support and bored pile steel casing
KR101211811B1 (en) Cast in concrete pile With precast type Caisson
JP2012117209A (en) Caisson method and equipment for caisson method
JP5986429B2 (en) Caisson and manufacturing method thereof
KR101051978B1 (en) Basement structure construction method using PC member
JP6760529B1 (en) How to build a waterproof wall and a waterproof wall
CN211773796U (en) Be applied to cofferdam structure of pier construction
JP6477565B2 (en) Reinforcing structure and reinforcing method of existing steel sheet pile wall
CN212200387U (en) Diaphragm wall foundation steel guide wall structure in deep water soft silt area
CN113356247B (en) Large deep foundation protection lock catch steel pipe pile cofferdam structure and construction method thereof
CN211873023U (en) Foundation pit supporting device
JP7275844B2 (en) WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE
JP4475116B2 (en) Vertical shaft structure and its construction method
CN111119200A (en) Foundation pit supporting device
CN111206594A (en) Foundation pit supporting construction method
JP4749858B2 (en) Method for enhancing bearing capacity in extension or reconstruction of superstructures of existing buildings
JP6800365B1 (en) How to reinforce the existing caisson foundation

Legal Events

Date Code Title Description
MK25 Application lapsed reg. 22.2i(2) - failure to pay acceptance fee
NB Applications allowed - extensions of time section 223(2)

Free format text: THE TIME IN WHICH TO PAY THE ACCEPTANCE FEE HAS BEEN EXTENDED TO 02 MAR 2015 .

FGA Letters patent sealed or granted (standard patent)