WO2012157829A1 - Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same - Google Patents
Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same Download PDFInfo
- Publication number
- WO2012157829A1 WO2012157829A1 PCT/KR2011/009993 KR2011009993W WO2012157829A1 WO 2012157829 A1 WO2012157829 A1 WO 2012157829A1 KR 2011009993 W KR2011009993 W KR 2011009993W WO 2012157829 A1 WO2012157829 A1 WO 2012157829A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- steel pipe
- pile
- underwater
- sheet pile
- casing
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/002—Ground foundation measures for protecting the soil or subsoil water, e.g. preventing or counteracting oil pollution
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/02—Restraining of open water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/18—Foundations formed by making use of caissons
Definitions
- the present invention is a large-diameter casing installation for the purpose of preventing the collapse or intrusion of the soil layer when excavating the ground for the foundation construction in the process of building underwater structures such as dams, bridges, offshore wind power in the sea, rivers, etc.
- it is possible to install in detail after pre-assembly, can be installed while reducing the field work, and also can be installed while responding flexibly to irregular underwater ground construction of large-diameter casing type and its preferred construction method It is about.
- Underwater ground foundation works by digging underwater ground and constructing monopile, etc., before the excavation of underwater ground, preventing soft soil or water from entering the foundation construction area or preventing the underwater ground from collapsing.
- the construction method of such a temporary structure is a method of constructing a large-diameter casing steel pipe (large-diameter steel pipe type).
- Large-diameter steel pipe is a method of manufacturing large-diameter casing steel pipe with steel materials around the factory or construction site and then bringing it to the construction site and sinking it in the water.
- This method has the advantage of reducing on-site work, but requires large equipment for transporting and lifting large casing steel pipes, and requires preliminary stabilization work for underwater grounds in order to stably install and install casing steel pipes on underwater grounds.
- the casing steel pipe does not respond flexibly to the underwater soil. It is not easy to prevent the phenomenon, and the problem that the excavation work becomes difficult is likely to occur.
- the present invention was developed to improve the shortcomings of temporary structures by conventional large-diameter casing steel pipes in the foundation construction of underwater structures, which can be installed while pre-assembling to reduce the field work, and also flexible to irregular underwater grounds.
- the present invention provides a large-diameter casing structure that is fixed and installed on the subsurface ground, and the large-diameter casing structure is completed by the structure to install the seat pile between the steel pipes and insert the center pile inside the steel pipes;
- the preferred method of construction provides a large-diameter casing construction method in which the steel pipe and sheet piles are pre-assembled and pre-assembled in a batch.
- the sheet pile can be installed in a pre-assembled state, it is possible to perform underwater large-diameter casing construction with minimal field work. Therefore, it is possible to shorten the construction period and reduce the construction cost in connection with the basic construction of the underwater structure.
- FIGS. 8 to 10 is a construction sequence diagram showing a process of constructing an underwater structure while applying the construction method of the underwater large diameter casing temporary structure according to FIGS. 4 to 7, respectively, for mono-pile and bridge for offshore wind power The construction sequence of the bridge is shown.
- the sheet pile 20 is a sheet-like pile member which is provided with an engaging connector 23 at the end and is engaged while being connected to each other, and is generally the same as a conventional sheet pile used for construction of an earth wall or a temporary barrier. .
- the sheet piles 20 are arranged to be engaged with each other and installed while hitting the ground.
- the seat pile 20 while the seat pile 20 is engaged with the steel pipe 10 through the engagement connection (13, 23) between the steel pipe 10 to form a casing of the closed structure together with the steel pipe 10 to the submarine ground. Is installed.
- the seat piles 20 are coupled to each other while being connected to the steel pipes 10 as well as the seat piles 20 so that the steel pipes 10 are closed by the sheet piles 20.
- the horizontal strut 30 is configured to be fixed while horizontally connecting the steel pipes 10 inside or outside the casing.
- the plurality of steel pipes 10 are reinforced by horizontal struts 30 while being restrained as one.
- the horizontal strut 30 is preferably provided to include an external strut 31 that is continuously installed outside the casing for a stable reinforcement structure.
- the horizontal strut 30 is only fixed to the steel pipe 10, the sheet pile 20 is simply installed in contact.
- the steel pipe 10, the horizontal struts 30, and the sheet pile 20 may be installed in the underwater ground while hitting the sheet pile 20 even when assembled. Meanwhile, the horizontal strut 30 may be provided in parallel in multiple stages.
- the horizontal strut 30 may further be provided with a vertical strut 40 vertically connecting the multiple stage horizontal struts 30.
- the horizontal strut 30 and the vertical strut 40 may adopt an appropriate cross-sectional member in a conventional steel frame member such as an H-beam, a c-channel, an angle, etc. according to the structural design.
- the vertical strut 40 provided with the c channel can be confirmed.
- the center pile 50 is inserted into the steel pipe 10 is a configuration that is fixed to the steel pipe 10 while entering the ground.
- the center pile 50 is installed in the underwater ground together with the seat pile 20 to stably fix the casing temporary structure according to the present invention on the underwater ground.
- the center pile 50 preferably adopts a normal steel frame member such as H-shaped steel, but in FIG. 1, the center pile 50 provided with the H-shaped steel can be confirmed.
- the center pile 50 is fixed to the steel pipe 10, for this purpose it can be used as a coupler.
- the coupler is installed in a fixing method such as wedge type, bolt assembly type, etc., rather than fixing method such as welding.
- the underwater large-diameter casing temporary structure is completed.
- the casing of the closed structure is completed by the engagement coupling of the steel pipe 10 and the seat pile 20 and the stable construction state is maintained by the underwater ground fixing of the center pile 50 and the seat pile 20.
- Underwater large diameter casing construction according to the present invention can be completed in a closed structure of a circular or polygonal.
- FIG. 1 and 2 show a temporary structure of the casing type installed in a closed structure of a polygon.
- the steel pipe 10 is disposed to be located at the edge of the polygonal composition
- the sheet pile 20 is disposed to be located at the side of the polygonal composition to complete the polygonal closed structure.
- the closed structure of the polygon can be easily completed while the horizontal strut 30 is applied to the usual straight steel member as it is.
- FIG. 4 to 7 is a construction procedure for the construction method of the underwater large diameter casing temporary structure according to the present invention, illustrating a method of constructing the underwater large diameter casing temporary structure of Figures 1 and 2. It looks at the construction method of underwater large diameter casing temporary construction according to the present invention.
- the center pile 50 such as H-shaped steel
- the center pile 50 is inserted into the steel pipe 10, and installed in the underwater ground (S13, FIG. 6), and the center pile 50 is fixed to the steel pipe 10 ( Step S14), the seat pile 20 is driven and installed in the underwater ground (Step S15 (Fig. 7).
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Foundations (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
- Earth Drilling (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The present invention relates to a large-caliber casing installation construction for preventing a collapse or an inflow of an earth layer during excavation of the ground for laying a foundation in the process of building a underwater structure, such as a dam, a bridge, an offshore wind structure under water, such as sea and river. The present invention completes a casing structure by installing a sheet pile between steel pipes and insertingly installing a center piles inside the steel pipes, and as a result, enables batch installation after first assembling the casing structure, and thus, can reduce field work and flexibly respond to irregular grounds underwater during construction.
Description
본 발명은 바다, 하천 등의 수중에 댐, 교량, 해상풍력 등의 수중 구조물을 구축하는 과정에서 기초 시공을 위해 지반을 굴착할 때 토사층의 붕괴 혹은 유입을 막기 위한 목적으로 시공하는 대구경 케이싱 설치 공사에 관한 것으로서, 더욱 상세하게는 선조립한 후 일괄설치가 가능하여 현장작업을 줄이면서 시공할 수 있고 아울러 불규칙한 수중지반에도 유연하게 대응하면서 시공할 수 있는 대구경 케이싱 형태의 가설구조물과 이의 바람직한 시공방법에 관한 것이다.The present invention is a large-diameter casing installation for the purpose of preventing the collapse or intrusion of the soil layer when excavating the ground for the foundation construction in the process of building underwater structures such as dams, bridges, offshore wind power in the sea, rivers, etc. In more detail, it is possible to install in detail after pre-assembly, can be installed while reducing the field work, and also can be installed while responding flexibly to irregular underwater ground construction of large-diameter casing type and its preferred construction method It is about.
바다, 하천 등의 수중에 댐, 교량, 해상풍력 등의 수중 구조물을 안정적으로 구축하기 위해서는 수중지반에 안정적인 기초 시공이 선행되어야 한다. 수중지반의 기초공사는 수중지반을 굴착한 후 모노파일 등을 시공하는 방법으로 진행하는데, 수중지반을 굴착하기에 앞서 기초 공사구역으로 연약 토사 내지 물이 유입되는 것을 막거나 수중지반이 붕괴하는 것을 막기 위한 목적으로 기초 공사구역에 대구경 케이싱 형태의 가설구조물을 설치할 필요가 있다. 이러한 가설구조물의 시공방법은 대구경 케이싱 강관을 근입 시공하는 방식(대구경 강관식)이 대표적이다.In order to stably build underwater structures such as dams, bridges, and offshore wind powers in the sea, rivers, etc., stable foundation construction must be preceded. Underwater ground foundation works by digging underwater ground and constructing monopile, etc., before the excavation of underwater ground, preventing soft soil or water from entering the foundation construction area or preventing the underwater ground from collapsing. For the purpose of preventing, it is necessary to install temporary structures in the form of large diameter casings in the foundation construction area. The construction method of such a temporary structure is a method of constructing a large-diameter casing steel pipe (large-diameter steel pipe type).
대구경 강관식은 공장 내지 시공현장 주변에서 강재로 대구경 케이싱 강관을 일체 제작한 다음 이를 시공현장에 반입하여 수중에 가라앉히면서 시공하는 방식이다. 이 방식은 현장작업을 줄일 수 있는 이점이 있으나, 대형 케이싱 강관의 운반, 양중을 위한 대형장비가 필요하고 케이싱 강관을 수중지반에 안정적으로 정착 설치하기 위해 수중지반의 안정화공사를 사전에 수행해야 하는 단점이 있다. 또한 암반이 노출되어 있거나 토사층이 매우 얇게 분포하는 등 수중지반이 매우 불규칙하게 발달되어 있는 경우에는 케이싱 강관이 수중지반에 유연하게 대응하지 못하기 때문에 케이싱 강관 내부를 굴착할 때 토사층이 붕괴하면서 유입되는 현상을 방지할 수 없어 굴착작업이 곤란해지는 문제가 발생하기 쉽다.Large-diameter steel pipe is a method of manufacturing large-diameter casing steel pipe with steel materials around the factory or construction site and then bringing it to the construction site and sinking it in the water. This method has the advantage of reducing on-site work, but requires large equipment for transporting and lifting large casing steel pipes, and requires preliminary stabilization work for underwater grounds in order to stably install and install casing steel pipes on underwater grounds. There are disadvantages. In addition, when the underwater soil is very irregularly developed, such as the exposed rock or the very thin soil layer, the casing steel pipe does not respond flexibly to the underwater soil. It is not easy to prevent the phenomenon, and the problem that the excavation work becomes difficult is likely to occur.
본 발명은 수중구조물의 기초 공사에서 종래 대구경 케이싱 강관에 의한 가설구조물의 단점을 개선하고자 개발된 것으로, 선조립한 후 일괄설치가 가능하여 현장작업을 줄이면서 설치할 수 있고 아울러 불규칙한 수중지반에도 유연하게 대응하면서 설치할 수 있는 대구경 케이싱 형태의 가설구조물과 이의 바람직한 시공방법을 제공하는데 기술적 과제가 있다.The present invention was developed to improve the shortcomings of temporary structures by conventional large-diameter casing steel pipes in the foundation construction of underwater structures, which can be installed while pre-assembling to reduce the field work, and also flexible to irregular underwater grounds. There is a technical problem to provide a temporary structure of a large diameter casing form and a preferred construction method that can be installed while corresponding.
상기한 기술적 과제를 해결하기 위해 본 발명은, 수중지반에 정착 시공되는 대구경 케이싱 구조물로서 강관 사이에 시트파일을 맞물림 결합방식 설치하고 강관 내부에 센터파일을 삽입 설치하는 구조로 완성되는 대구경 케이싱 구조물과, 이의 바람직한 시공방법으로 강관과 시트파일을 선조립 일괄 설치한 후 센터파일과 시트파일의 근입 시공하는 대구경 케이싱 시공방법을 제공한다.In order to solve the above technical problem, the present invention provides a large-diameter casing structure that is fixed and installed on the subsurface ground, and the large-diameter casing structure is completed by the structure to install the seat pile between the steel pipes and insert the center pile inside the steel pipes; In addition, the preferred method of construction provides a large-diameter casing construction method in which the steel pipe and sheet piles are pre-assembled and pre-assembled in a batch.
본 발명에 따르면 다음과 같은 효과를 기대할 수 있다.According to the present invention, the following effects can be expected.
첫째, 시트파일을 선조립한 상태로 설치할 수 있기 때문에 현장작업을 최소화하면서 수중 대구경 케이싱 공사를 실시할 수 있다. 따라서 수중구조물의 기초 공사와 관련하여 공사기간을 단축하고 공사비를 절감할 수 있다.First, since the sheet pile can be installed in a pre-assembled state, it is possible to perform underwater large-diameter casing construction with minimal field work. Therefore, it is possible to shorten the construction period and reduce the construction cost in connection with the basic construction of the underwater structure.
둘째, 시트파일과 강관을 조립체 상태로 먼저 설치하고 그 조립체의 강관 내부에 엄지말뚝을 설치하는 방식으로 수중 대구경 케이싱을 시공하기 때문에 시공오차의 발생 우려가 거의 없으며, 그 결과 설계에 따른 시공으로 시공품질을 향상시킬 수 있다.Second, there is little risk of construction errors because the large-diameter casing is installed by installing the seat pile and the steel pipe in the assembly state first and then installing the thumb pile inside the steel pipe of the assembly. Can improve the quality.
셋째, 해저 혹은 하저에 단단한 층(혹은 암층)의 표면이 매우 불규칙한 상태로 존재하는 경우에도 그 불규칙한 수중지반에 대응하면서 시트파일을 설치할 수 있기 때문에 기초 공사를 위해 케이싱 내부의 수중지반을 굴착할 때에 토사붕괴를 최대한 방지할 수 있다.Third, even when the surface of the rigid layer (or rock layer) is very irregular on the seabed or the bottom, seat piles can be installed while responding to the irregular underwater ground. Therefore, when excavating the underwater ground inside the casing for foundation work, Soil disintegration can be prevented as much as possible.
도 1과 도 2는 본 발명에 따른 수중 대구경 케이싱 가설구조물에 대한 평면도와 사시도이다.1 and 2 are a plan view and a perspective view of the underwater large diameter casing temporary structure according to the present invention.
도 3은 본 발명에 따른 수중 대구경 케이싱 가설구조물에서 강관과 시트파일의 접속상세이다.3 is a connection detail of the steel pipe and the sheet pile in the underwater large diameter casing temporary structure according to the present invention.
도 4 내지 도 7은 본 발명에 따른 수중 대구경 케이싱 가설구조물의 시공방법에 대한 시공순서도이다.4 to 7 is a construction sequence diagram for the construction method of the underwater large diameter casing temporary structure according to the present invention.
도 8 내지 도 10은 도 4 내지 도 7에 따른 수중 대구경 케이싱 가설구조물의 시공방법을 적용하면서 수중구조물을 시공하는 과정을 보여주는 시공순서도로, 각각 해상풍력용 모노파일(mono-pile)과 교량용 교각의 시공순서도이다.8 to 10 is a construction sequence diagram showing a process of constructing an underwater structure while applying the construction method of the underwater large diameter casing temporary structure according to FIGS. 4 to 7, respectively, for mono-pile and bridge for offshore wind power The construction sequence of the bridge is shown.
본 발명에 따른 시트파일을 이용한 일괄설치형 수중 대구경 케이싱 가설구조물은 수중지반에 정착 시공되는 대구경 케이싱 구조물로서, 외주면에 맞물림접속구가 마련된 강관 부재로 복수 개가 맞물림접속구끼리 서로 마주보도록 소정 간격으로 배치되면서 수중바닥에 안착 설치되는 강관; 단부에 맞물림접속구가 마련된 시트파일로, 하나 이상이 상기 강관 사이를 폐합하도록 설치되되, 맞물림접속구를 통해 강관과 맞물림 접속되면서 수중지반까지 근입 설치되는 시트파일; 케이싱 내부 또는 외부에서 상기 강관 사이를 수평 연결하면서 고정 설치되는 수평스트러트; 상기 강관 내부에 삽입되어 수중지반까지 근입되면서 강관에 고정 설치되는 센터파일;을 포함하여 구성되는 것을 특징으로 한다.The batch-mounted underwater large-diameter casing construction using the seat pile according to the present invention is a large-diameter casing structure that is fixed and installed on the underwater ground. A steel pipe seated on the floor; A seat pile provided with an engagement connector at an end thereof, the seat pile being installed to close one or more of the steel pipes, the seat pile being installed into the ground while being connected to the steel pipe through an engagement connector; A horizontal strut fixedly installed while horizontally connecting the steel pipes inside or outside the casing; And a center pile inserted into the steel pipe and fixed to the steel pipe while being inserted into the underwater ground.
본 발명에 따른 수중 대구경 케이싱 가설구조물의 시공방법은 상기한 시트파일을 이용한 일괄설치형 수중 대구경 케이싱 가설구조물을 시공하는 방법으로, 강관,시트파일, 수평스트러트를 조립하되 시트파일이 강관보다 아래로 내려오지 않게 조립하는 제S11단계; 제S11단계의 조립체를 시공현장에 반입하여 강관을 수중바닥에 안착시키는 제S12단계; 강관 내부에 센터파일을 삽입 항타하여 수중지반에 근입 설치하는 제S13단계; 센터파일을 강관에 고정시키는 제S14단계; 시트파일을 항타하여 수중지반에 근입 설치하는 제S15단계;를 포함하여 이루어지는 것을 특징으로 한다.The construction method of the underwater large diameter casing temporary structure according to the present invention is a method of constructing a batch-mounted underwater large diameter casing temporary structure using the above-mentioned sheet pile, while assembling the steel pipe, sheet pile, horizontal strut, the sheet pile is lower than the steel pipe Step S11 to assemble so as not to come; S12 step of bringing the assembly of step S11 into the construction site to seat the steel pipe on the water floor; Inserting and driving the center pile into the steel pipe; S14 step of fixing the center pile to the steel pipe; It characterized in that it comprises a; the step S15 step to install in the underwater ground by hitting the sheet pile.
이하 첨부한 도면 및 바람직한 실시예에 따라 본 발명을 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings and preferred embodiments.
도 1과 도 2는 본 발명에 따른 수중 대구경 케이싱 가설구조물에 대한 평면도와 사시도이다. 수중 대구경 케이싱은 바다, 하천 등의 수중에 댐, 교량, 해상풍력 등의 수중 구조물을 구축하는 과정에서 기초 시공을 위해 지반을 굴착할 때 토사층의 붕괴 혹은 유입을 막기 위한 목적으로 시공하는 가설구조물인데, 본 발명은 수중 대구경 케이싱을 조립구조로서 강관(10), 시트파일(20), 수평스트러트(30), 센터파일(50)을 포함하도록 구성한다는데 특징이 있다.1 and 2 are a plan view and a perspective view of the underwater large diameter casing temporary structure according to the present invention. Underwater large-diameter casing is a temporary structure for the purpose of preventing the collapse or inflow of soil layers when excavating the ground for foundation construction in the process of constructing underwater structures such as dams, bridges, and offshore wind power in the sea, rivers, etc. The present invention is characterized in that the submerged large diameter casing is configured to include a steel pipe 10, a sheet pile 20, a horizontal strut 30, a center pile 50 as an assembly structure.
본 발명에서 강관(10)은 속이 빈 중공형 부재로 외주면에 맞물림접속구(13)가 마련되는 구성인데, 복수 개가 맞물림접속구(13)끼리 서로 마주보도록 소정 간격으로 배치되면서 수중바닥에 안착 설치된다. 이와 같은 강관(10)은 그 내부에 삽입 설치되는 센터파일(50)의 가이드관 역할을 한다.In the present invention, the steel pipe 10 is a hollow hollow member that is provided with an engagement connector 13 on the outer circumferential surface, and a plurality of engagement connectors 13 are disposed at predetermined intervals so as to face each other and installed on the bottom of the water. Such a steel pipe 10 serves as a guide pipe of the center pile 50 inserted into it.
본 발명에서 시트파일(20)은 단부에 맞물림접속구(23)가 마련되어 상호 간 맞물림 접속하면서 결합하는 시트 형태의 파일 부재로, 일반적으로 흙막이벽이나 가물막이 시공에 이용되는 통상의 시트파일과 동일하다. 다시 말해 시트파일(20) 한 장씩 서로 맞물리게 배치하고 지중에 때려 박으면서 설치하는 부재이다. 다만 본 발명에서는 시트파일(20)이 강관(10)과 함께 폐쇄구조의 케이싱을 형성하도록 강관(10) 사이에서 맞물림접속구(13, 23)를 통해 강관(10)과 맞물림 접속되면서 수중지반까지 근입 설치된다. 시트파일(20)에 의해 강관(10) 사이가 폐합되도록 시트파일(20) 상호 간은 물론 강관(10)과도 맞물림 접속하면서 결합 설치되는 것이다.In the present invention, the sheet pile 20 is a sheet-like pile member which is provided with an engaging connector 23 at the end and is engaged while being connected to each other, and is generally the same as a conventional sheet pile used for construction of an earth wall or a temporary barrier. . In other words, the sheet piles 20 are arranged to be engaged with each other and installed while hitting the ground. However, in the present invention, while the seat pile 20 is engaged with the steel pipe 10 through the engagement connection (13, 23) between the steel pipe 10 to form a casing of the closed structure together with the steel pipe 10 to the submarine ground. Is installed. The seat piles 20 are coupled to each other while being connected to the steel pipes 10 as well as the seat piles 20 so that the steel pipes 10 are closed by the sheet piles 20.
본 발명에서 수평스트러트(30)는 케이싱 내부 또는 외부에서 강관(10) 사이를 수평 연결하면서 고정 설치되는 구성이다. 수평스트러트(30)에 의해 복수 개의 강관(10)은 하나로 구속되면서 보강된다. 안정적인 보강구조를 위해 수평스트러트(30)는 케이싱 외부에서 연속하게 설치되는 외부스트러트(31)를 포함하도록 마련하는 것이 바람직하다. 수평스트러트(30)는 강관(10)에만 고정될 뿐이며, 시트파일(20)에는 단순히 접촉 설치된다. 그래야 강관(10), 수평스트러트(30), 시트파일(20)이 서로 조립된 상태에서도 시트파일(20)을 타격하면서 수중지반에 근입 설치할 수 있다. 한편 수평스트러트(30)는 다단으로 평행하게 마련될 수 있으며, 이 경우 다단의 수평스트러트(30)를 수직 연결하는 수직스트러트(40)를 더 마련할 수도 있다. 수평스트러트(30)와 수직스트러트(40)는 구조설계에 따라 H형강, ㄷ채널, 앵글 등 통상의 철골부재에서 적절한 단면의 부재를 채택하면 되는데, 도 1에서는 H형강으로 마련된 외부스트러트(31)와 ㄷ채널로 마련된 수직스트러트(40)를 확인할 수 있다.In the present invention, the horizontal strut 30 is configured to be fixed while horizontally connecting the steel pipes 10 inside or outside the casing. The plurality of steel pipes 10 are reinforced by horizontal struts 30 while being restrained as one. The horizontal strut 30 is preferably provided to include an external strut 31 that is continuously installed outside the casing for a stable reinforcement structure. The horizontal strut 30 is only fixed to the steel pipe 10, the sheet pile 20 is simply installed in contact. Thus, the steel pipe 10, the horizontal struts 30, and the sheet pile 20 may be installed in the underwater ground while hitting the sheet pile 20 even when assembled. Meanwhile, the horizontal strut 30 may be provided in parallel in multiple stages. In this case, the horizontal strut 30 may further be provided with a vertical strut 40 vertically connecting the multiple stage horizontal struts 30. The horizontal strut 30 and the vertical strut 40 may adopt an appropriate cross-sectional member in a conventional steel frame member such as an H-beam, a c-channel, an angle, etc. according to the structural design. And the vertical strut 40 provided with the c channel can be confirmed.
본 발명에서 센터파일(50)은 강관(10) 내부에 삽입되어 수중지반까지 근입되면서 강관(10)에 고정 설치되는 구성이다. 센터파일(50)은 시트파일(20)과 함께 수중지반에 근입 설치되어 본 발명에 따른 케이싱 가설구조물을 수중지반에 안정적으로 정착시키는 구성이 된다. 다만 센터파일(50)은 일종의 엄지말뚝이 되므로 가능하다면 시트파일(20)보다 깊은 심도로 근입 설치하는 것이 바람직하다. 센터파일(50)은 H형강 등 통상의 철골부재를 적절히 채택하면 바람직한데, 도 1에서는 H형강으로 마련된 센터파일(50)을 확인할 수 있다. 한편 센터파일(50)은 강관(10)에 고정 설치되는데, 이를 위해 커플러를 적절하게 이용할 수 있다. 다만 본 발명에 따른 수중 대구경 케이싱이 곧 철거되는 가설구조물이라는 것을 감안한다면 커플러는 용접 등의 고정방법보다는 탈착이 용이한 쐐기식, 볼트조립식 등의 고정방법으로 설치되는 구조가 바람직하다.In the present invention, the center pile 50 is inserted into the steel pipe 10 is a configuration that is fixed to the steel pipe 10 while entering the ground. The center pile 50 is installed in the underwater ground together with the seat pile 20 to stably fix the casing temporary structure according to the present invention on the underwater ground. However, since the center pile 50 becomes a kind of thumb pile, it is preferable to install the root pile at a deeper depth than the seat pile 20 if possible. The center pile 50 preferably adopts a normal steel frame member such as H-shaped steel, but in FIG. 1, the center pile 50 provided with the H-shaped steel can be confirmed. On the other hand, the center pile 50 is fixed to the steel pipe 10, for this purpose it can be used as a coupler. However, considering that the underwater large diameter casing according to the present invention is a temporary structure to be immediately dismantled, it is preferable that the coupler is installed in a fixing method such as wedge type, bolt assembly type, etc., rather than fixing method such as welding.
상기와 같은 구성에 의해 수중 대구경 케이싱 가설구조물이 완성된다. 강관(10)과 시트파일(20)의 맞물림 결합으로 폐쇄구조의 케이싱이 완성되고 센터파일(50)과 시트파일(20)의 수중지반 정착으로 안정적인 구축상태가 유지되는 것이다. 본 발명에 따른 수중 대구경 케이싱 가설구조물은 원형 또는 다각형의 폐쇄구조로 완성될 수 있다.By such a configuration, the underwater large-diameter casing temporary structure is completed. The casing of the closed structure is completed by the engagement coupling of the steel pipe 10 and the seat pile 20 and the stable construction state is maintained by the underwater ground fixing of the center pile 50 and the seat pile 20. Underwater large diameter casing construction according to the present invention can be completed in a closed structure of a circular or polygonal.
도 1과 도 2는 다각형의 폐쇄구조로 설치한 케이싱 형태의 가설구조물을 보여준다. 보는 바와 같이 강관(10)을 다각형 구도의 모서리에 위치하도록 배치하고, 시트파일(20)을 다각형 구도의 변에 위치하도록 배치하여 다각형의 폐쇄구조로 완성하고 있다. 다각형의 폐쇄구조는 수평스트러트(30)를 통상의 직선 철골부재를 그대로 적용하면서 쉽게 완성할 수 있다. 1 and 2 show a temporary structure of the casing type installed in a closed structure of a polygon. As shown, the steel pipe 10 is disposed to be located at the edge of the polygonal composition, and the sheet pile 20 is disposed to be located at the side of the polygonal composition to complete the polygonal closed structure. The closed structure of the polygon can be easily completed while the horizontal strut 30 is applied to the usual straight steel member as it is.
나아가 도 1과 도 2에서는 수평스트러트(30)를 내·외부스트러트(31, 32)로 마련하여 케이싱 내·외부 각각에서 서로 이격하면서 평행하게 설치하고, 내·외부스트러트(31, 32) 사이에 시트파일(20)을 접촉시키면서 설치하고 있다. 이와 같은 수평스트러트(30)의 설치 구조는 내·외부스트러트(31, 32)에 의한 안정적인 보강구조를 확보하는 한편 시트파일(20)을 근입 설치하는 과정에서 시트파일(20)의 수직도를 유지하는데 유리하다.Furthermore, in FIGS. 1 and 2, horizontal struts 30 are provided as inner and outer struts 31 and 32 and are installed in parallel while being spaced apart from each other inside and outside the casing, and between inner and outer struts 31 and 32. The sheet pile 20 is provided in contact with each other. The installation structure of the horizontal struts 30 secures a stable reinforcement structure by the internal and external struts 31 and 32, and maintains the verticality of the sheet piles 20 during the installation of the sheet piles 20. It is advantageous to.
도 3은 본 발명에 따른 수중 대구경 케이싱 가설구조물에서 강관(10)과 시트파일(20)의 접속상세를 보여준다. 도 3에서는 종래의 강관을 적절히 변형하여 강관(10)로 마련하고 있는데, 구체적으로 강관본체(11); 강관본체(11) 외주면에 용접 접합된 날개시트(12); 날개시트(12) 단부가 절곡되어 형성된 맞물림접속구(13);로 구성하고 있다. 다시 말해 시트파일(20)을 절반으로 나누어 강관본체(11)의 양쪽에 접합하는 것으로 맞물림접속구(13)가 마련된 강관(10)을 완성한 것이다. 이러한 강관(10)은 간편하게 시트파일(20)의 맞물림 접속하면서 결합 설치된다. 3 shows the connection details of the steel pipe 10 and the seat pile 20 in the underwater large diameter casing temporary structure according to the present invention. In FIG. 3, a conventional steel pipe is appropriately modified to be provided as a steel pipe 10, specifically, a steel pipe main body 11; Wing sheet 12 welded to the outer peripheral surface of the steel pipe body (11); And an engagement connector 13 formed by bending an end portion of the wing sheet 12. In other words, by dividing the sheet pile 20 in half and joining both sides of the steel pipe main body 11, the steel pipe 10 provided with the engagement connector 13 is completed. These steel pipes 10 are simply installed while being engaged with the seat pile 20.
도 4 내지 도 7은 본 발명에 따른 수중 대구경 케이싱 가설구조물의 시공방법에 대한 시공순서도로, 도 1과 도 2의 수중 대구경 케이싱 가설구조물이 시공되는 방법을 예시한다. 이를 통해 본 발명에 따른 수중 대구경 케이싱 가설구조물의 시공방법을 살펴본다.4 to 7 is a construction procedure for the construction method of the underwater large diameter casing temporary structure according to the present invention, illustrating a method of constructing the underwater large diameter casing temporary structure of Figures 1 and 2. It looks at the construction method of underwater large diameter casing temporary construction according to the present invention.
먼저 강관(10), 시트파일(20), 수평스트러트(30)를 조립하며, 수직스트러트(40)를 더 설치하는 경우에는 수직스트러트(40)도 조립한다(제S11단계, 도 4). 시트파일(20)은 강관(10)과 동일하거나 강관(10)보다 긴 길이로 준비하고 강관(10)보다는 아래로 내려오지 않게 조립하는 것이 바람직한데, 이는 시트파일(20)에 방해받지 않으면서 강관(10)을 수중바닥에 안정적으로 안착 설치하기 위함이다.First, the steel pipe 10, the sheet pile 20, the horizontal struts 30 are assembled, and when the vertical struts 40 are further installed, the vertical struts 40 are also assembled (S11, FIG. 4). Sheet pile 20 is preferably the same as the steel pipe 10 or longer length than the steel pipe 10 and preferably assembled so as not to descend below the steel pipe 10, which is not disturbed by the sheet pile 20 This is to install the steel pipe (10) on the bottom of the stable installation.
다음으로 제S11단계에서 조립한 조립체를 시공현장에 반입하여 강관(10)을 수중바닥에 안착 설치한다(S12단계, 도 5). 크레인으로 양중하면서 설치하며, 안착 설치한 후에는 조립체가 움직이지 않도록 붙잡아 둔다.Next, the assembly assembled in step S11 is carried into the construction site, and the steel pipe 10 is seated and installed on the underwater floor (step S12, FIG. 5). It is installed while lifting with a crane, and after installation, it is held by the assembly so that it does not move.
다음으로 강관(10) 내부에 H형강 등의 센터파일(50)을 삽입 항타하여 수중지반에 근입 설치하고(제S13단계, 도 6), 센터파일(50)을 강관(10)에 고정시키고(제S14단계), 시트파일(20)을 항타하여 수중지반에 근입 설치한다(제S15단계(도 7). 크레인, 해머 등을 적절히 이용하면서 진행하도록 한다. Next, the center pile 50, such as H-shaped steel, is inserted into the steel pipe 10, and installed in the underwater ground (S13, FIG. 6), and the center pile 50 is fixed to the steel pipe 10 ( Step S14), the seat pile 20 is driven and installed in the underwater ground (Step S15 (Fig. 7).
이로써 수중 대구경 케이싱 가설구조물 시공이 완성된다. 시공현장에서는 미리 조립한 조립체의 배치작업과, 센터파일(50)의 삽입 항타작업, 시트파일(20)의 항타작업을 실시하기만 하면 되기 때문에 현장작업량을 줄이면서 신속하게 공사를 수행할 수 있다.This completes the construction of underwater large diameter casing temporary structure. In the construction site, it is only necessary to carry out the arrangement work of the pre-assembled assembly, the insert driving of the center pile 50 and the driving of the seat pile 20, so that the construction work can be performed quickly while reducing the amount of field work. .
도 8 내지 도 10은 도 4 내지 도 7에 따른 수중 대구경 케이싱 가설구조물의 시공방법을 적용하면서 수중구조물을 시공하는 과정을 보여주는 시공순서도로, 해상풍력용 모노파일(mono-pile)과 교량용 교각의 시공순서도이다.8 to 10 is a construction flowchart showing a process of constructing an underwater structure while applying the construction method of the underwater large diameter casing temporary structure according to FIGS. 4 to 7, a mono-pile for offshore wind power and a bridge for bridges The construction sequence is shown.
도 8과 도 9는 모노파일(MP)의 시공순서를 보여준다. 먼저 시공 위치에 수중 대구경 케이싱 가설구조물을 시공하며(도 8), 시공방법은 앞에서 살펴본 도 4 내지 도 7에서와 같다. 이어 굴착장치를 케이싱 가설구조물 내부에 삽입하고 잭업 바지(jackup barge)의 상단에 고정한 후 굴착 베이스머신과 굴착장치를 연결하여 케이싱 가설구조물 내부를 굴착한다(도 9(a)). 이때 역순환 방식으로 케이싱 가설구조물 내부에 굴착용수를 공급하는 한편 Drill Pipe 내부를 통하여 굴착용수 및 암편을 배출할 수 있다. 다음으로 모노파일(MP)을 굴착공 내부에 관입 설치하고(도 9(b)), 모노파일과 굴착공 사이를 콘크리트, 몰탈, 각종 충전재 등으로 그라우팅(G)한 후(도 9(c)), 케이싱 가설구조물을 철거한다(도 9(d)). 철거는 설치방법과 반대로 실시하면 된다. 다시 말해 먼저 시트파일(20)을 수중지반에서 인발하고, 이어 센터파일(50)의 고정상태를 풀어 수중지반에서 인발한 후 강관(10)에서 인출하여 제거하고, 다음으로 강관(10), 시트파일(20), 수평스트러트(30)가 조립된 상태의 조립체를 양중하여 운반하는 것이다. 이로써 모노파일 같은 수중구조물의 시공이 완성된다. 8 and 9 show the construction sequence of the monopile (MP). First, construct a large underwater casing temporary construction at the construction location (Fig. 8), the construction method is the same as in Figures 4 to 7 discussed above. Then, the excavation device is inserted into the casing temporary structure, and fixed to the top of the jackup barge (jackup barge), and then the excavating device is connected to the excavating base machine to excavate the casing temporary structure (FIG. 9 (a)). At this time, the excavating water and the rock piece can be discharged through the drill pipe while supplying the excavating water inside the casing temporary structure in a reverse circulation method. Next, the monofilament (MP) is inserted into the excavation hole (Fig. 9 (b)), and then grouted (G) between the monofilament and the excavation hole with concrete, mortar, and various fillers (Fig. 9 (c)). ), The casing temporary structure is removed (FIG. 9 (d)). Dismantling can be done in the reverse way of installation. In other words, the sheet pile 20 is first drawn out of the underwater ground, and then the center pile 50 is released and drawn out of the underwater ground and then drawn out of the steel pipe 10 and then removed, and then the steel pipe 10 and the sheet. The pile 20 and the horizontal strut 30 are conveyed by lifting the assembly in an assembled state. This completes the construction of underwater structures such as monopile.
도 10은 수중 교각의 시공순서를 보여준다. 수중 교각의 시공을 위해서는 먼저 도 8과 같이 시공 위치에 먼저 시공 위치에 수중 대구경 케이싱 가설구조물을 시공한다. 이어 양수펌프 등을 이용하여 케이싱 가설구조물 내부에 양수작업을 실시하고(도 10(a)), 케이싱 가설구조물 내부에 수중지반이 드러나면 수중지반에 교각 기초(P1)와 교각 본체(P2)를 시공한다(도 10(b)(c)). 다음으로 케이싱 가설구조물 내부에 물을 투입한 후(도 10(d)), 케이싱 가설구조물을 철거한다(도 10(e)). 이때 가설구조물의 철거는 앞에서 살펴본 모노파일 시공과정에서와 동일하다. 이로써 교량의 교각 등과 같은 수중구조물의 시공이 완성된다. 10 shows the construction sequence of the underwater piers. For the construction of underwater piers, first, construct a large underwater diameter casing construction at the construction location as shown in FIG. Subsequently, the pumping work is carried out inside the casing temporary structure using a pumping pump (FIG. 10 (a)), and when the underwater ground is exposed inside the casing temporary structure, the piers foundation (P1) and the pier body (P2) are constructed on the underwater ground. (FIG. 10 (b) (c)). Next, after the water is put into the casing temporary structure (Fig. 10 (d)), the casing temporary structure is removed (Fig. 10 (e)). At this time, the dismantling of the temporary structure is the same as in the monofiling process. This completes the construction of underwater structures such as bridge piers.
이상에서 본 발명은 구체적인 실시예를 참조하여 상세히 설명되었으나, 실시예는 본 발명을 예시하기 위한 것일 뿐이므로, 본 발명의 기술적 사상을 벗어나지 않는 범위 내에서 치환, 부가 및 변형된 실시 형태들 역시 아래에 첨부한 특허청구범위에 의하여 정하여지는 본 발명의 보호범위에 속한다고 할 것이다.The present invention has been described in detail above with reference to specific embodiments, but the embodiments are only for illustrating the present invention, and thus the embodiments substituted, added, and modified within the scope without departing from the spirit of the present invention are also described below. It will be said to belong to the protection scope of the present invention as defined by the claims appended hereto.
Claims (6)
- 수중지반에 정착 시공되는 대구경 케이싱 구조물로서,As a large diameter casing structure fixed in the underwater ground,외주면에 맞물림접속구(13)가 마련된 강관 부재로, 복수 개가 맞물림접속구(13)끼리 서로 마주보도록 소정 간격으로 배치되면서 수중바닥에 안착 설치되는 강관(10);A steel pipe member provided with an engaging connector 13 on an outer circumferential surface thereof, the plurality of engaging pipes 13 being disposed at predetermined intervals so as to face each other, the steel pipe 10 being installed on the bottom of the water;단부에 맞물림접속구(23)가 마련된 시트파일(20)로, 하나 이상이 상기 강관(10) 사이를 폐합하도록 설치되되, 맞물림접속구(13, 23)를 통해 강관(10)과 맞물림 접속되면서 수중지반까지 근입 설치되는 시트파일(20);The seat pile 20 is provided with an engaging connector 23 at the end, one or more are installed to close between the steel pipe 10, while being engaged and connected to the steel pipe 10 through the engaging connector (13, 23) Seat pile 20 is installed until the root;케이싱 내부 또는 외부에서 상기 강관(10) 사이를 수평 연결하면서 고정 설치되는 수평스트러트(30);A horizontal strut 30 fixedly installed while horizontally connecting the steel pipes 10 inside or outside the casing;상기 강관(10) 내부에 삽입되어 수중지반까지 근입되면서 강관(10)에 고정 설치되는 센터파일(50);A center pile 50 inserted into the steel pipe 10 and fixed to the steel pipe 10 while being inserted into the underwater ground;을 포함하여 구성되는 것을 특징으로 하는 시트파일을 이용한 일괄설치형 수중 대구경 케이싱 가설구조물.Bulk installation type underwater large diameter casing temporary structure using a sheet pile, characterized in that comprising a.
- 제1항에서,In claim 1,상기 수평스트러트(30)는, The horizontal strut 30,케이싱 외부에 위치하도록 설치되는 외부스트러트(31);와 케이싱 내부에 위치하도록 설치되는 내부스트러트(32);를 포함하여 구성되되 내·외부스트러트(31, 32)가 서로 이격하면서 평행하게 배치되도록 설치되며,An outer strut 31 installed to be located outside the casing; and an inner strut 32 installed to be positioned inside the casing; wherein the inner and outer struts 31 and 32 are spaced apart from each other and arranged in parallel. ,상기 시트파일(20)은, 내·외부스트러트(31, 32)에 접촉하게 설치되는 것을 특징으로 하는 시트파일을 이용한 일괄설치형 수중 대구경 케이싱 가설구조물.The sheet pile (20) is installed in bulk contact type underwater large diameter casing construction using a sheet pile, characterized in that installed in contact with the inner and outer struts (31, 32).
- 제1항 또는 제2항에서,The method of claim 1 or 2,상기 강관(10)은, 강관본체(11); 강관본체(11) 외주면에 용접 접합된 날개시트(12); 날개시트(12) 단부가 절곡되어 형성된 맞물림접속구(13);를 포함하여 구성된 것임을 특징으로 하는 시트파일을 이용한 일괄설치형 수중 대구경 케이싱 가설구조물.The steel pipe 10, the steel pipe body 11; Wing sheet 12 welded to the outer peripheral surface of the steel pipe body (11); Batch-mounted underwater large-diameter casing temporary structure using a sheet pile, characterized in that it comprises a;
- 제1항 또는 제2항에서,The method of claim 1 or 2,상기 강관(10)은, 다각형 구도의 모서리에 위치하도록 배치되고,The steel pipe 10 is disposed to be located at the corner of the polygonal composition,상기 시트파일(20)은, 강관(10) 상호 간을 연결하면서 다각형 구도의 변에 위치하도록 배치되고,The sheet pile 20 is disposed so as to be located on the sides of the polygonal composition while connecting the steel pipes 10,상기 수평스트러트(30)는, 강관(10)의 외곽으로 둘러 감으면서 다각형 구도로 설치되는 외부스트러트(31)를 포함하여 구성된 것임을 특징으로 하는 시트파일을 이용한 일괄설치형 수중 대구경 케이싱 가설구조물.The horizontal strut 30 is a batch installation type underwater large-diameter casing temporary structure using a sheet pile, characterized in that configured to include an outer strut 31 is installed as a polygonal composition while surrounding the outside of the steel pipe (10).
- 제1항 또는 제2항에서,The method of claim 1 or 2,상기 센터파일(50)은, H형강인 것을 특징으로 하는 시트파일을 이용한 일괄설치형 수중 대구경 케이싱 가설구조물.The center pile 50 is a batch installation type underwater large diameter casing temporary structure using a sheet pile, characterized in that the H-shaped steel.
- 제1항 또는 제2항에 따른 시트파일을 이용한 일괄설치형 수중 대구경 케이싱 가설구조물을 시공하는 방법으로,A method of constructing a batch-mounted underwater large-diameter casing temporary structure using a sheet pile according to claim 1 or 2,강관(10), 시트파일(20), 수평스트러트(30)를 조립하되, 시트파일(20)이 강관(10)보다 아래로 내려오지 않게 조립하는 제S11단계;S11 step of assembling the steel pipe 10, the sheet pile 20, the horizontal struts 30, the sheet pile 20 is not lowered than the steel pipe 10;제S11단계의 조립체를 시공현장에 반입하여 강관(10)을 수중바닥에 안착시키는 제S12단계;Step S12 of bringing the assembly of step S11 into the construction site to seat the steel pipe 10 on the underwater floor;강관(10) 내부에 센터파일(50)을 삽입 항타하여 수중지반에 근입 설치하는 제S13단계;Inserting and driving the center pile 50 into the steel pipe 10;센터파일(50)을 강관(10)에 고정시키는 제S14단계;Step S14 of fixing the center pile 50 to the steel pipe 10;시트파일(20)을 항타하여 수중지반에 근입 설치하는 제S15단계;A step S15 of driving the seat pile 20 in the ground;를 포함하여 이루어지는 것을 특징으로 하는 수중 대구경 케이싱 가설구조물의 시공방법.Construction method of underwater large diameter casing temporary construction comprising a.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP11865671.9A EP2708658A1 (en) | 2011-05-13 | 2011-12-22 | Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same |
AU2011368478A AU2011368478B2 (en) | 2011-05-13 | 2011-12-22 | Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2011-0045103 | 2011-05-13 | ||
KR1020110045103A KR101106219B1 (en) | 2011-05-13 | 2011-05-13 | Sheetpile type large-diameter casing for underwater structure and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2012157829A1 true WO2012157829A1 (en) | 2012-11-22 |
Family
ID=45614347
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/KR2011/009993 WO2012157829A1 (en) | 2011-05-13 | 2011-12-22 | Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same |
Country Status (4)
Country | Link |
---|---|
EP (1) | EP2708658A1 (en) |
KR (1) | KR101106219B1 (en) |
AU (1) | AU2011368478B2 (en) |
WO (1) | WO2012157829A1 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110485305A (en) * | 2019-08-27 | 2019-11-22 | 中铁大桥局集团有限公司 | Steel pile casting Anti-fall platform and its construction method for water Bridge foundation construction |
CN113431071B (en) * | 2021-05-24 | 2022-05-13 | 徐州中矿岩土技术股份有限公司 | Rescue pipe and emergency rescue pipe fitting for dam piping accident and using method thereof |
CN114960890A (en) * | 2022-04-15 | 2022-08-30 | 中国港湾工程有限责任公司 | Construction method of offshore water outlet |
CN115369858A (en) * | 2022-07-29 | 2022-11-22 | 中国化学工程第六建设有限公司 | Construction process of concrete filled steel tubular column |
CN117166462A (en) * | 2023-09-08 | 2023-12-05 | 湖北省工业建筑集团有限公司 | Rotary drilling pile foundation construction device and method for hard rock combined stratum |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102016972B1 (en) * | 2017-01-13 | 2019-09-03 | 권혁빈 | Construction Method of Underwater Civil Engineering Structure Foundation |
CN109356166B (en) * | 2018-11-06 | 2023-12-29 | 福建卓越建设工程开发有限公司 | Steel pipe pile-Larson steel sheet pile bending direct combined driving combined supporting system and construction method |
KR102205948B1 (en) | 2018-11-16 | 2021-01-21 | 한국건설기술연구원 | Method for connecting very large diameter mono-pile into rock using small and middle diameter pin pile |
KR20200134761A (en) | 2019-05-23 | 2020-12-02 | 양필규 | The workstation mounted on top of file form |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20060102837A (en) * | 2005-03-25 | 2006-09-28 | 재현토건(주) | Cofferdam construction method using the large caliber steel pipe for the structures constructed over the water |
KR100884289B1 (en) * | 2008-06-23 | 2009-02-17 | 가원이엔씨 주식회사 | Composite type steel temporary construction and construction method thereof |
KR20090037114A (en) * | 2007-10-11 | 2009-04-15 | 현대건설주식회사 | Cofferdam, its construction method using sheet file and wale and construction method for underwater structure using the cofferdam |
KR20090042677A (en) * | 2007-10-26 | 2009-04-30 | 삼성물산 주식회사 | Separate type template and costruction method for cofferdam using the same |
KR20090089832A (en) * | 2009-07-31 | 2009-08-24 | 현대엔지니어링 주식회사 | Nature friendly polygon cell type coffering method for harbor, river and dam construction |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4231194B2 (en) | 2000-09-06 | 2009-02-25 | 新日本製鐵株式会社 | Revetment structure |
-
2011
- 2011-05-13 KR KR1020110045103A patent/KR101106219B1/en not_active IP Right Cessation
- 2011-12-22 EP EP11865671.9A patent/EP2708658A1/en not_active Withdrawn
- 2011-12-22 AU AU2011368478A patent/AU2011368478B2/en not_active Ceased
- 2011-12-22 WO PCT/KR2011/009993 patent/WO2012157829A1/en active Application Filing
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20060102837A (en) * | 2005-03-25 | 2006-09-28 | 재현토건(주) | Cofferdam construction method using the large caliber steel pipe for the structures constructed over the water |
KR20090037114A (en) * | 2007-10-11 | 2009-04-15 | 현대건설주식회사 | Cofferdam, its construction method using sheet file and wale and construction method for underwater structure using the cofferdam |
KR20090042677A (en) * | 2007-10-26 | 2009-04-30 | 삼성물산 주식회사 | Separate type template and costruction method for cofferdam using the same |
KR100884289B1 (en) * | 2008-06-23 | 2009-02-17 | 가원이엔씨 주식회사 | Composite type steel temporary construction and construction method thereof |
KR20090089832A (en) * | 2009-07-31 | 2009-08-24 | 현대엔지니어링 주식회사 | Nature friendly polygon cell type coffering method for harbor, river and dam construction |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110485305A (en) * | 2019-08-27 | 2019-11-22 | 中铁大桥局集团有限公司 | Steel pile casting Anti-fall platform and its construction method for water Bridge foundation construction |
CN113431071B (en) * | 2021-05-24 | 2022-05-13 | 徐州中矿岩土技术股份有限公司 | Rescue pipe and emergency rescue pipe fitting for dam piping accident and using method thereof |
CN114960890A (en) * | 2022-04-15 | 2022-08-30 | 中国港湾工程有限责任公司 | Construction method of offshore water outlet |
CN115369858A (en) * | 2022-07-29 | 2022-11-22 | 中国化学工程第六建设有限公司 | Construction process of concrete filled steel tubular column |
CN115369858B (en) * | 2022-07-29 | 2023-12-12 | 中国化学工程第六建设有限公司 | Construction process of concrete filled steel tubular column |
CN117166462A (en) * | 2023-09-08 | 2023-12-05 | 湖北省工业建筑集团有限公司 | Rotary drilling pile foundation construction device and method for hard rock combined stratum |
CN117166462B (en) * | 2023-09-08 | 2024-05-07 | 湖北省工业建筑集团有限公司 | Rotary drilling pile foundation construction device and method for hard rock combined stratum |
Also Published As
Publication number | Publication date |
---|---|
EP2708658A1 (en) | 2014-03-19 |
KR101106219B1 (en) | 2012-01-19 |
AU2011368478B2 (en) | 2014-10-02 |
AU2011368478A1 (en) | 2013-03-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2012157829A1 (en) | Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same | |
CN109630127B (en) | Construction method of ultra-deep shield vertical shaft for water-rich weak stratum | |
CN106013052B (en) | The construction method of steel sheet pile and open caisson Combined type underground garage parking | |
CN110499772B (en) | Construction method of rock riverbed double-layer steel sheet pile cofferdam | |
PH12014502301B1 (en) | Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method | |
US20060179730A1 (en) | Wall structural member and method for constructing a wall structure | |
CN108677926A (en) | Coercion underground continuous wall and its construction method | |
CN111851543A (en) | Long and narrow deep foundation pit construction cofferdam structure and use method thereof | |
WO2020032453A1 (en) | Multi-wall construction supporting piles used in construction of ports, rivers, dams, and concrete buildings that can prevent inflow of soil and water, and multi-wall construction method using same supporting piles | |
JP2007211408A (en) | Seismic strengthening construction method for existing concrete bridge pier | |
JP3905776B2 (en) | Revetment structure | |
JP6760529B1 (en) | How to build a waterproof wall and a waterproof wall | |
CN211773796U (en) | Be applied to cofferdam structure of pier construction | |
CN105804090A (en) | Indoor piling wall support structure and construction method therefor | |
CN114960715A (en) | Underground engineering surge treatment device and control method | |
CN107237331B (en) | Foundation pit construction method using water pressure support | |
CN113404055B (en) | Inter-pile soil-retaining and water-stopping curtain structure and construction method thereof | |
WO2024063292A1 (en) | Method for constructing water-expandable waterstop for preventing slurry wall water leakage and structure for constructing same | |
WO2010104235A1 (en) | Excavation method of underground plaza and submarine plaza using steel casing retaining wall | |
CN115262533B (en) | Joint-free underground diaphragm wall and construction method thereof | |
CN217758709U (en) | Larsen steel sheet pile supporting construction | |
CN115748773A (en) | Construction method of bridge main pier foundation double-layer steel sheet pile ground connection wall combined cofferdam | |
CN219410886U (en) | Light combined upright post structure for water area foundation pit engineering | |
CN217811059U (en) | Combined temporary foundation pit supporting structure | |
CN113863355B (en) | Waterproof construction method for large-volume bearing platform in water |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 11865671 Country of ref document: EP Kind code of ref document: A1 |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2011865671 Country of ref document: EP |
|
ENP | Entry into the national phase |
Ref document number: 2011368478 Country of ref document: AU Date of ref document: 20111222 Kind code of ref document: A |
|
NENP | Non-entry into the national phase |
Ref country code: DE |