CN105804090A - Indoor piling wall support structure and construction method therefor - Google Patents
Indoor piling wall support structure and construction method therefor Download PDFInfo
- Publication number
- CN105804090A CN105804090A CN201610235951.6A CN201610235951A CN105804090A CN 105804090 A CN105804090 A CN 105804090A CN 201610235951 A CN201610235951 A CN 201610235951A CN 105804090 A CN105804090 A CN 105804090A
- Authority
- CN
- China
- Prior art keywords
- wall
- ground
- bored concrete
- concrete pile
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims description 109
- 239000004570 mortar (masonry) Substances 0.000 claims abstract description 18
- 238000006073 displacement reaction Methods 0.000 claims abstract description 17
- 239000011083 cement mortar Substances 0.000 claims abstract description 14
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 12
- 238000007789 sealing Methods 0.000 claims description 18
- 239000004568 cement Substances 0.000 claims description 16
- 238000009413 insulation Methods 0.000 claims description 16
- 239000004576 sand Substances 0.000 claims description 16
- 238000004873 anchoring Methods 0.000 claims description 10
- 229910000831 Steel Inorganic materials 0.000 claims description 9
- 239000010959 steel Substances 0.000 claims description 9
- 239000000463 material Substances 0.000 claims description 8
- 238000013461 design Methods 0.000 claims description 6
- 230000015572 biosynthetic process Effects 0.000 claims description 3
- 238000005253 cladding Methods 0.000 claims description 3
- 239000012774 insulation material Substances 0.000 claims description 3
- 238000012423 maintenance Methods 0.000 claims description 3
- 238000002360 preparation method Methods 0.000 claims description 3
- 239000011810 insulating material Substances 0.000 abstract 1
- 238000000034 method Methods 0.000 description 10
- 238000005516 engineering process Methods 0.000 description 5
- 230000007547 defect Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000009977 dual effect Effects 0.000 description 2
- 230000035800 maturation Effects 0.000 description 2
- 238000012544 monitoring process Methods 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 238000012546 transfer Methods 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/10—Prefabricated parts, e.g. composite sheet piles made of concrete or reinforced concrete
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/10—Prefabricated parts, e.g. composite sheet piles made of concrete or reinforced concrete
- E02D5/12—Locking forms; Edge joints; Pile crossings; Branch pieces
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Composite Materials (AREA)
- Environmental & Geological Engineering (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610235951.6A CN105804090B (en) | 2016-04-15 | 2016-04-15 | A kind of indoor piling wall supporting construction and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610235951.6A CN105804090B (en) | 2016-04-15 | 2016-04-15 | A kind of indoor piling wall supporting construction and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105804090A true CN105804090A (en) | 2016-07-27 |
CN105804090B CN105804090B (en) | 2017-10-27 |
Family
ID=56459305
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610235951.6A Active CN105804090B (en) | 2016-04-15 | 2016-04-15 | A kind of indoor piling wall supporting construction and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105804090B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110258576A (en) * | 2019-05-28 | 2019-09-20 | 安徽省公路桥梁工程有限公司 | The construction method of foundation pit enclosure support system |
CN110284506A (en) * | 2019-05-22 | 2019-09-27 | 上海港城建筑安装工程有限公司 | A kind of foundation pit enclosure method for the expansion construction that deep basal pit is cheated to shallow foundation |
CN110485431A (en) * | 2019-07-24 | 2019-11-22 | 青岛理工大学 | A kind of interlocking pile combines foundation pit supporting construction with ground-connecting-wall |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0813495A (en) * | 1994-06-29 | 1996-01-16 | Maeda Corp | Earth retaining wall and method thereof |
CN101435198A (en) * | 2008-12-23 | 2009-05-20 | 中铁二院工程集团有限责任公司 | Deep pit support reinforcing anti-seepage water stop composite structure |
CN103669402A (en) * | 2013-12-25 | 2014-03-26 | 华东建筑设计研究院有限公司 | Pile and wall integrated structure combining outer wall of basement body and guard pile |
CN103790185A (en) * | 2014-01-29 | 2014-05-14 | 中国航空规划建设发展有限公司 | Shock insulation groove enclosure wall for deep foundation shock insulation structure and constructing method of shock insulation groove enclosure wall |
CN203821412U (en) * | 2014-04-17 | 2014-09-10 | 广东省基础工程公司 | Supporting structure with scattered row piles and continuous walls |
CN104818728A (en) * | 2015-04-08 | 2015-08-05 | 山东大学 | Permanent supporting system with basement floor and supporting piles capable of working together |
-
2016
- 2016-04-15 CN CN201610235951.6A patent/CN105804090B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0813495A (en) * | 1994-06-29 | 1996-01-16 | Maeda Corp | Earth retaining wall and method thereof |
CN101435198A (en) * | 2008-12-23 | 2009-05-20 | 中铁二院工程集团有限责任公司 | Deep pit support reinforcing anti-seepage water stop composite structure |
CN103669402A (en) * | 2013-12-25 | 2014-03-26 | 华东建筑设计研究院有限公司 | Pile and wall integrated structure combining outer wall of basement body and guard pile |
CN103790185A (en) * | 2014-01-29 | 2014-05-14 | 中国航空规划建设发展有限公司 | Shock insulation groove enclosure wall for deep foundation shock insulation structure and constructing method of shock insulation groove enclosure wall |
CN203821412U (en) * | 2014-04-17 | 2014-09-10 | 广东省基础工程公司 | Supporting structure with scattered row piles and continuous walls |
CN104818728A (en) * | 2015-04-08 | 2015-08-05 | 山东大学 | Permanent supporting system with basement floor and supporting piles capable of working together |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110284506A (en) * | 2019-05-22 | 2019-09-27 | 上海港城建筑安装工程有限公司 | A kind of foundation pit enclosure method for the expansion construction that deep basal pit is cheated to shallow foundation |
CN110258576A (en) * | 2019-05-28 | 2019-09-20 | 安徽省公路桥梁工程有限公司 | The construction method of foundation pit enclosure support system |
CN110258576B (en) * | 2019-05-28 | 2021-04-09 | 安徽省公路桥梁工程有限公司 | Construction method of foundation pit enclosure support system |
CN110485431A (en) * | 2019-07-24 | 2019-11-22 | 青岛理工大学 | A kind of interlocking pile combines foundation pit supporting construction with ground-connecting-wall |
Also Published As
Publication number | Publication date |
---|---|
CN105804090B (en) | 2017-10-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103572755B (en) | Prestressed concrete prefabricated pile | |
CN205742213U (en) | Foundation pit supporting construction | |
CN106013052A (en) | Steel sheet pile and open caisson combined underground garage and construction method thereof | |
CN107012871B (en) | A kind of suspension type goes along with sb. to guard him the deep reversed construction method for greatly enhancing foundation pit fabricated construction | |
CN110485430A (en) | A kind of interlocking pile combines foundation pit supporting method with ground-connecting-wall | |
CN110158649A (en) | The construction method of Adjacent Underground Pipeline when a kind of caisson sinking construction | |
CN103321246A (en) | Underground diaphragm wall based foundation pit construction method | |
CN201538975U (en) | Seepage-proofing joint of underground continuous wall | |
CN101575859B (en) | Anti-seepage joint of underground continuous walls and construction method thereof | |
KR20090114863A (en) | Parallelly connected iron tube and construction method for underground structure using the same | |
CN105649094B (en) | A kind of deep water foundation bearing platform construction three wall steel cofferdams and its construction method | |
CN105804090A (en) | Indoor piling wall support structure and construction method therefor | |
CN105862875A (en) | Support structure and construction method thereof | |
CN108118689B (en) | Prefabricated underground diaphragm wall capable of being partially recycled, lifting appliance and construction method | |
CN203559419U (en) | Prestressed concrete precast pile | |
CN108221954B (en) | Easy-to-detach prefabricated underground diaphragm wall, lifting appliance and construction method | |
CN108221955B (en) | Prefabricated underground diaphragm wall capable of being recycled integrally, lifting appliance and construction method | |
CN110344418A (en) | The structure and its construction technology of support system in a kind of deep basal pit | |
CN105442528B (en) | Cement grouting sheet pile with sealing ring | |
CN106088762A (en) | The prefabricated assembled circular underground granary of a kind of insertion slot type encased steel plate | |
RU2465401C1 (en) | Method to erect underground structures by "wall in soil" method and wall in soil erected by this method | |
CN106088764B (en) | A kind of stepped prefabricated assembled circular underground granary of encased steel plate | |
CN213978923U (en) | Pre-buried formula underground continuous wall connects and flows processing apparatus | |
CN216515734U (en) | Box culvert structure for underneath passing existing railway engineering | |
CN202007407U (en) | Deep foundation pit supporting system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C41 | Transfer of patent application or patent right or utility model | ||
CB03 | Change of inventor or designer information |
Inventor after: Wang Zhilong Inventor before: Xiao Rui |
|
COR | Change of bibliographic data | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20170117 Address after: 330001 Jianshe Road, Jiangxi, No. 173, Applicant after: JIANGXI THE SECOND CONSTRUCTION CO., LTD. Address before: Zhenhai District 315202 Zhejiang city of Ningbo Province Rong Luo Road No. 372 Applicant before: Xiao Rui |
|
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Wang Zhilong Inventor after: Zhou Jun Inventor after: Zhou Zhe Inventor after: Xu Bei Inventor after: Yuan Linna Inventor after: Fan Haifei Inventor after: Shi Lin Inventor before: Wang Zhilong |
|
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20170920 Address after: 330001 Jianshe Road, Jiangxi, No. 173, Applicant after: JIANGXI THE SECOND CONSTRUCTION CO., LTD. Applicant after: Jiangxi construction Refco Group Ltd Address before: 330001 Jianshe Road, Jiangxi, No. 173, Applicant before: JIANGXI THE SECOND CONSTRUCTION CO., LTD. |
|
GR01 | Patent grant | ||
GR01 | Patent grant |