CN110485430A - A kind of interlocking pile combines foundation pit supporting method with ground-connecting-wall - Google Patents
A kind of interlocking pile combines foundation pit supporting method with ground-connecting-wall Download PDFInfo
- Publication number
- CN110485430A CN110485430A CN201910669401.9A CN201910669401A CN110485430A CN 110485430 A CN110485430 A CN 110485430A CN 201910669401 A CN201910669401 A CN 201910669401A CN 110485430 A CN110485430 A CN 110485430A
- Authority
- CN
- China
- Prior art keywords
- wall
- ground
- interlocking pile
- concrete
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/18—Bulkheads or similar walls made solely of concrete in situ
- E02D5/187—Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/36—Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Foundations (AREA)
Abstract
本发明属于基坑支护技术领域,涉及一种咬合桩与地连墙联合基坑支护方法,咬合桩素桩与咬合桩硂桩咬合形成咬合桩体;咬合桩与外墙结构相连形成平整墙面;在地连墙与咬合桩上部分别浇筑冠梁;第一道支撑为钢筋混凝土支撑,与冠梁上的预留钢筋相连,根据基坑形状及受力特点使用钢筋混凝土角撑、钢筋混凝土对撑、钢筋混凝土斜撑;在地连墙和外墙结构上按设计标高安装围檩;第二、三道支撑为双拼结构的钢支撑,钢支撑与围檩相连,将咬合桩与地连墙相结合,充分利用两者的优点,又能克服两者的缺点,防水效果好,施工灵活,抗渗能力强,具有广泛的应用前景和良好的经济效应。
The invention belongs to the technical field of foundation pit support, and relates to a foundation pit support method combined with an occlusal pile and a ground wall. Wall surface; crown beams are poured on the ground connection wall and the upper part of the occlusal piles respectively; the first support is reinforced concrete support, which is connected with the reserved steel bars on the crown beams. Concrete opposite braces and reinforced concrete diagonal braces; purlins are installed on the ground connection wall and outer wall structure according to the design elevation; the second and third supports are steel supports of a double structure, and the steel supports are connected to the purlins, and the occlusal piles and purlins are connected to each other. The combination of ground and wall can make full use of the advantages of both, and can overcome the shortcomings of both. It has good waterproof effect, flexible construction, strong impermeability, and has wide application prospects and good economic effects.
Description
技术领域:Technical field:
本发明属于基坑支护技术领域,具体涉及一种咬合桩与地连墙联合基坑支护方法。The invention belongs to the technical field of foundation pit support, and in particular relates to a combined foundation pit support method of occlusal piles and ground connecting walls.
背景技术:Background technique:
随着我国经济水平的提高,交通压力越来越大,深基坑工程随之兴起。由于地铁基坑深度大且周围建筑物多,水文地质条件复杂,对基坑支护的安全要求也越来越高。With the improvement of my country's economic level, traffic pressure is increasing, and deep foundation pit projects are emerging. Due to the large depth of the subway foundation pit, many surrounding buildings, and complex hydrogeological conditions, the safety requirements for foundation pit support are getting higher and higher.
目前常用的深基坑支护形式有地下连续墙、咬合桩,不仅支护形式存在差异,其优点缺点也各不相同。地下连续墙是基础工程在地面上采用一种挖槽机械,沿着深开挖工程的周边轴线,在泥浆护壁条件下开槽,在槽内吊放钢筋笼,然后灌筑水下混凝土筑成一个单元槽段,逐段进行施工,在地下筑成一道连续的钢筋混凝土墙壁,作为截水、防渗、承重、挡水结构,地下连续墙施工时速度快、振动小,噪音低,较适合在城市施工。地连墙墙体刚度大,基坑开挖后可承载能力强,稳定性高。墙体本身防渗性能好,适用于地下水位高,水头压力大的基坑工程;咬合桩是相邻混凝土排桩间部分圆周咬合,并于咬合桩硂桩内吊入钢筋笼,形成具有良好防渗作用的整体连续防水、挡土围护结构,咬合桩配筋率较低,降低支护结构的配筋率。咬合桩柱间不存在施工冷缝夹杂泥土,整体性强,抗渗能力强。咬合桩施工时灵活,可以依需要转折,更适合施工一些平面多变的基坑支护。At present, the commonly used deep foundation pit support forms include underground diaphragm wall and occlusal piles. Not only are there differences in support forms, but also their advantages and disadvantages are also different. The underground diaphragm wall is a foundation project that adopts a trenching machine on the ground. Along the peripheral axis of the deep excavation project, trenches are made under the condition of mud retaining walls, steel cages are hung in the trenches, and then underwater concrete is poured to form an underground diaphragm wall. The unit tank section is constructed section by section, and a continuous reinforced concrete wall is built underground as a water interception, seepage prevention, load-bearing, and water retaining structure. The construction speed of the underground diaphragm wall is fast, the vibration is small, and the noise is low. city construction. The ground connection wall has high rigidity, strong bearing capacity and high stability after excavation of the foundation pit. The wall itself has good anti-seepage performance, and is suitable for foundation pit engineering with high groundwater level and high water head pressure; the occlusal pile is part of the circumferential occlusion between adjacent concrete rows, and is hoisted into the steel cage in the occlusal pile. The overall continuous waterproof and soil retaining enclosure structure with anti-seepage effect, the reinforcement ratio of the occlusal pile is low, and the reinforcement ratio of the support structure is reduced. There is no construction cold joint mixed with soil between the occlusal piles, which has strong integrity and strong anti-seepage ability. The construction of occlusal piles is flexible and can be turned as needed, which is more suitable for the construction of foundation pit support with variable planes.
在基坑支护工程中,咬合桩与地连墙联合基坑支护结构可以充分利用两者的优点,又能克服两者的缺点,具有广泛的应用前景和良好的经济效应。因此,设计一种合理、可靠的咬合桩与地连墙联合基坑支护方法迫在眉睫。In foundation pit support engineering, the joint foundation pit support structure of occlusal pile and ground connection wall can make full use of the advantages of both, and can overcome the shortcomings of both, so it has wide application prospects and good economic effects. Therefore, it is imminent to design a reasonable and reliable foundation pit support method combined with occlusal piles and ground-connected walls.
发明内容:Invention content:
本发明的目的在于克服现有技术存在的缺点,设计提供一种咬合桩与地连墙联合基坑支护方法,增强支护结构的稳定性与安全性。The purpose of the present invention is to overcome the shortcomings of the prior art, to design and provide a combined foundation pit supporting method of occlusal piles and ground connecting walls, and to enhance the stability and safety of the supporting structure.
为了实现上述目的,本发明通过咬合桩与地连墙联合支护结构实现,具体过程为:In order to achieve the above object, the present invention is realized through the combined support structure of the occlusal pile and the ground connection wall, and the specific process is as follows:
步骤1:进行咬合桩的施工,注意与地连墙相邻的咬合桩为素桩,以便于地连墙与相邻咬合桩素桩咬合,放线定位后,钻机就位,取土成孔直至设计孔底标高,荤桩应在成孔检查合格后吊放钢筋笼,后浇筑混凝土拔管成桩。Step 1: Carry out the construction of occlusal piles. Note that the occlusal piles adjacent to the ground connection wall are plain piles, so that the ground connection wall and the adjacent occlusal piles are occluded. Up to the design hole bottom elevation, the piles should be hoisted with reinforcement cages after the hole inspection is qualified, and then concrete should be poured to form piles.
步骤2:进行地连墙的施工,地连墙的放线定位导墙施工,制备泥浆,成槽后,吊放钢筋笼浇筑混凝土,形成地连墙;Step 2: Carry out the construction of the ground connection wall, set out the line of the ground connection wall to locate the guide wall construction, prepare the mud, and after the groove is formed, hang the reinforcement cage and pour the concrete to form the ground connection wall;
步骤3:进行地连墙与咬合桩接缝处的施工,地连墙成槽时,靠近咬合桩素桩一侧采用旋挖钻扩大成槽墙体宽度至少200mm,确保浇筑混凝土时,混凝土能绕流过槽钢背面;采用旋挖钻钻除部分接缝处咬合桩素桩,使地连墙与相邻咬合桩素桩至少有300mm咬合,对咬合桩素桩刷壁后,吊放钢筋笼,浇筑混凝土;Step 3: Carry out the construction of the joint between the ground connection wall and the occlusal pile. When the ground connection wall is grooved, use a rotary drill to expand the width of the groove wall at least 200mm on the side close to the occlusal pile plain pile to ensure that the concrete can be poured. Flow around the back of the channel steel; use a rotary drill to remove some of the seam piles at the joints, so that the ground connection wall and the adjacent seam piles have at least 300mm of seaming, and after the wall of the seam piles are brushed, hang the steel bars cage, pouring concrete;
步骤4:在咬合桩素桩桩顶与地连墙墙顶进行冠梁施工,先定位放线,再绑扎钢筋,然后支护模板,浇筑混凝土形成钢筋混凝土冠梁,并预留与钢筋混凝土撑连接的钢筋,地连墙与咬合桩素桩相连处的冠梁应浇筑成一体;Step 4: Carry out crown and beam construction on the top of the occlusal pile plain pile and the top of the ground connection wall. The connected steel bars, the crown beam at the connection between the ground connection wall and the occlusal pile should be poured into one piece;
步骤5:在冠梁施工时,施工第一道钢筋混凝土支撑,施作垫层,钢筋焊接、绑扎、安装,模板安装及加固,浇筑混凝土,拆模后养护混凝土,待支撑强度达到75%时,继续向下挖土;Step 5: During the construction of the crown beam, construct the first reinforced concrete support, apply the cushion, weld, bind, install the steel bars, install and reinforce the formwork, pour concrete, remove the formwork and then maintain the concrete until the support strength reaches 75% , continue to dig down;
步骤6:进行桩墙结合施工,在咬合桩已施工部位采用锚固钢筋挂网喷射混凝土形成网喷混凝土层,厚度不小于100mm,再在网喷混凝土层上做砂浆找平层,厚度不小于20mm,然后在找平层上做防水层,最后喷射混凝土层形成侧墙;Step 6: Carry out pile-wall combined construction, use anchoring steel bar hanging net sprayed concrete to form a sprayed concrete layer at the construction site of the occlusal pile, the thickness is not less than 100mm, and then make a mortar leveling layer on the sprayed concrete layer, the thickness is not less than 20mm, Then make a waterproof layer on the leveling layer, and finally spray the concrete layer to form the side wall;
步骤7:按设计标高安装围檩,在围檩上安装三角形支架、用两根直径20mm的YG2型胀管螺栓紧固三角形支架,围檩与侧墙之间的空隙用C30细石混凝土充填;吊装钢围檩紧贴墙身,再安装YG2胀管螺栓,斜撑处的钢围檩应预埋防滑移件;Step 7: Install the purlin according to the design elevation, install the triangular bracket on the purlin, fasten the triangular bracket with two YG2 expansion tube bolts with a diameter of 20mm, and fill the gap between the purlin and the side wall with C30 fine stone concrete; Lift the steel purlins close to the wall, and then install YG2 expansion bolts. The steel purlins at the diagonal braces should be embedded with anti-slip parts;
步骤8:钢支撑整体拼接吊装采用10t龙门吊安装,钢支撑安装就位后,每榀支撑用两台100t台液压千斤顶在钢管支撑活动端预加分级施加轴力,并进行锁定,加设楔形块后,拆下千斤顶完成钢支撑的安装;Step 8: The overall splicing and hoisting of the steel support is installed by a 10t gantry crane. After the steel support is installed in place, two 100t hydraulic jacks are used for each support to pre-apply the axial force on the movable end of the steel support and lock it, and add a wedge After the block is removed, the jack is removed to complete the installation of the steel support;
步骤9:继续开挖后应先撑后挖,及时架设第三道钢支撑;测量定位,锚固三角形支架,安装围檩、钢支撑,施加预应力,加设楔形块后,拆下千斤顶完成钢支撑的安装。Step 9: After continuing to excavate, support first and then dig, erect the third steel support in time; measure and position, anchor the triangular support, install purlins and steel supports, apply prestress, and after adding wedge blocks, remove the jack to complete the steel support. Support installation.
本发明所述咬合桩与地连墙联合支护结构的主体结构包括地连墙、咬合桩素桩、冠梁、钢筋混凝土支撑、钢支撑、外墙结构、围檩和咬合桩硂桩;根据不同的工程地质条件、技术要求,选择地连墙或咬合桩作为主体支护结构,咬合桩素桩与咬合桩硂桩咬合形成咬合桩体;在地连墙与咬合桩接缝处,与地连墙相邻的咬合桩为咬合桩素桩,两者咬合相连;咬合桩与外墙结构相连,形成平整墙面;在地连墙与咬合桩上部分别浇筑冠梁;第一道支撑为钢筋混凝土支撑,与冠梁上的预留钢筋相连,根据基坑形状及受力特点使用钢筋混凝土角撑、钢筋混凝土对撑、钢筋混凝土斜撑;在地连墙和外墙结构上按设计标高安装围檩;第二、三道支撑为双拼结构的钢支撑,钢支撑与围檩相连,根据基坑形状及受力特点使用钢支撑角撑、钢支撑对撑、钢支撑斜撑并采取加固措施。The main structure of the joint support structure of the occlusal pile and the ground wall includes the ground wall, the occlusal pile plain pile, the crown beam, the reinforced concrete support, the steel support, the outer wall structure, the surrounding purlin and the occlusal pile; Different engineering geological conditions and technical requirements, choose ground connection wall or occlusal pile as the main support structure. The occlusal piles adjacent to the connecting wall are occlusal piles, and the two are occluded and connected; the occlusal piles are connected with the outer wall structure to form a flat wall surface; crown beams are poured on the ground connection wall and the upper part of the occlusal piles; the first support is steel bars Concrete support, connected with the reserved steel bars on the crown beam, use reinforced concrete corner braces, reinforced concrete opposite braces, and reinforced concrete diagonal braces according to the shape and force characteristics of the foundation pit; install them on the ground connection wall and outer wall structure according to the design elevation Purlins; the second and third supports are steel supports with a double structure, and the steel supports are connected to the purlins. According to the shape and force characteristics of the foundation pit, steel support angle braces, steel support opposite braces, and steel support diagonal braces are used for reinforcement. measure.
本发明所述地下连续墙的具体尺寸根据具体工程与咬合桩的尺寸确定,一般地下连续墙幅宽不大于6m,埋深为10m至50m,厚度为0.5m至1.2m,小于相邻咬合桩素桩直径至少200mm,便于两者咬合紧密;咬合桩素桩的直径和埋深应根据具体工程确定,直径不小于1000mm,至少用C25超缓凝混凝土浇筑,与相邻桩桩间咬合不小于300mm;咬合桩硂桩的直径和埋深根据具体工程确定,直径不小于1000mm,至少用C45水下混凝混凝土浇筑,与相邻桩桩间咬合不小于300mm;冠梁的尺寸为1200×1000mm、1500×1000mm,至少用C45混凝土浇筑;钢筋混凝土支撑的类型、长度、横截面积根据基坑尺寸及具体荷载确定为800×1000mm,至少用C45混凝土浇筑。The specific size of the underground diaphragm wall according to the present invention is determined according to the specific project and the size of the occlusal piles. Generally, the width of the underground diaphragm wall is not more than 6m, the buried depth is 10m to 50m, and the thickness is 0.5m to 1.2m, which is less than that of the adjacent occlusal piles. The diameter of the plain pile should be at least 200mm, which is convenient for the two to occlude tightly; the diameter and buried depth of the occlusal pile should be determined according to the specific project, and the diameter should not be less than 1000mm. 300mm; the diameter and buried depth of the occlusal pile shall be determined according to the specific project, the diameter shall not be less than 1000mm, and at least C45 underwater concrete shall be poured, and the interlocking between adjacent piles shall not be less than 300mm; the size of the crown beam shall be 1200×1000mm , 1500×1000mm, at least poured with C45 concrete; the type, length, and cross-sectional area of the reinforced concrete support are determined to be 800×1000mm according to the size of the foundation pit and the specific load, and poured with at least C45 concrete.
本发明所述外墙结构包括网喷混凝土层、砂浆找平层、施工防水层、侧墙,在咬合桩内侧锚固钢筋上挂网喷射混凝土形成网喷混凝土层,厚度不小于80mm,网喷混凝土层的外侧为厚度不小于20mm的砂浆找平层,砂浆找平层外侧施工防水层,在防水层外侧浇筑侧墙,厚度不小于20mm。The exterior wall structure of the present invention includes a sprayed concrete layer, a mortar leveling layer, a construction waterproof layer, and a side wall. The sprayed concrete layer is formed by hanging the sprayed concrete on the anchoring steel bars inside the occlusal piles, the thickness of which is not less than 80 mm, and the sprayed concrete layer. The outer side of the mortar leveling layer is a mortar leveling layer with a thickness of not less than 20mm, and a waterproof layer is constructed outside the mortar leveling layer, and a side wall is poured outside the waterproof layer with a thickness of not less than 20mm.
本发明所述围檩采用组合双拼工字钢,一般采用Q235B钢,围檩架设在三角形支架上,三角形支架采用直径20mm的YG2型胀管螺栓与地连墙相连,连接长度不小于280mm,在设置斜撑的围檩内侧墙体内预埋防滑件,用于增强围檩的抗滑移能力,防滑件由钢板和钢筋焊接而成,钢板的厚度不小于20mm,钢筋为带肋钢筋,直径不小于20mm。The purlins of the present invention are made of combined double I-beams, usually Q235B steel, and the purlins are erected on triangular supports, and the triangular supports are connected to the ground connection wall by YG2 expansion tube bolts with a diameter of 20mm, and the connection length is not less than 280mm. Anti-slip parts are pre-embedded in the inner wall of the purlin with diagonal braces to enhance the anti-slip ability of the purlin. The anti-slip parts are welded by steel plates and steel bars. The thickness of the steel plates is not less than 20mm, and the steel bars are ribbed steel bars. The diameter is not less than 20mm.
本发明所述钢支撑的长度、直径、壁厚应根据基坑尺寸及具体荷载确定,根据基坑形状采用钢支撑角撑、钢支撑对撑、钢支撑斜撑,钢支撑的紧固构件为将直径20mm的第一圆钢吊钩、第二圆钢吊钩分别与钢支撑、YG2胀管螺栓间焊接,第一圆钢吊钩、第二圆钢吊钩均由光圆钢筋弯曲成U型,长度不小于50mm,YG2胀管螺栓埋设在围檩上方800mm处,圆钢吊钩与YG2胀管螺栓之间用直径20mm的圆钢S型连接件和紧固螺丝连接,钢支撑为斜撑时,在钢支撑与围檩之间焊接剪力块,剪力块的尺寸与材料符合具体工程要求。The length, diameter, and wall thickness of the steel support in the present invention should be determined according to the size of the foundation pit and the specific load. According to the shape of the foundation pit, steel support angle braces, steel support opposite braces, and steel support diagonal braces are used. The fastening members of the steel support are Weld the first round steel hook and the second round steel hook with a diameter of 20mm to the steel support and YG2 expansion tube bolts respectively. The first round steel hook and the second round steel hook are bent into a U Type, the length is not less than 50mm, YG2 expansion tube bolts are buried 800mm above the purlin, the round steel hook and YG2 expansion tube bolts are connected by round steel S-shaped connectors with a diameter of 20mm and fastening screws, and the steel support is oblique When supporting, the shear block is welded between the steel support and the purlin, and the size and material of the shear block meet the specific engineering requirements.
本发明与现有技术相比,将咬合桩与地连墙相结合,充分利用两者的优点,又能克服两者的缺点,防水效果好,施工灵活,抗渗能力强,具有广泛的应用前景和良好的经济效应。Compared with the prior art, the present invention combines the occlusal pile and the ground connection wall, makes full use of the advantages of the two, and overcomes the shortcomings of the two, has good waterproof effect, flexible construction, strong anti-seepage ability, and has a wide range of applications Prospects and good economic effects.
附图说明:Description of the drawings:
图1为本发明所述咬合桩与地下连续墙连接平面图。Fig. 1 is a plan view of the connection between the occlusal pile and the underground diaphragm wall according to the present invention.
图2为本发明所述咬合桩内侧成墙平面图。Fig. 2 is a plan view of the inner wall of the occlusal pile according to the present invention.
图3为本发明所述咬合桩与地下连续墙联合支护结构的内支撑立面图。Fig. 3 is an internal support elevation view of the combined support structure of the occlusal pile and the underground diaphragm wall according to the present invention.
图4为本发明所述咬合桩与地下连续墙第一道钢筋混凝土支撑平面图。Fig. 4 is a plan view of the first reinforced concrete support of the occlusal pile and the underground diaphragm wall according to the present invention.
图5为本发明所述咬合桩与地下连续墙第二、三道双拼钢筋支撑平面图。Fig. 5 is a plan view of the occlusal pile and the second and third double reinforcement bars of the underground diaphragm wall according to the present invention.
图6为本发明所述双拼钢支撑、围檩和墙体连接立面图。Fig. 6 is an elevational view of the connection between the double steel support, the purlin and the wall according to the present invention.
图7为本发明所述双拼钢支撑、围檩和墙体连接平面图。Fig. 7 is a plan view of the connection between the double steel support, the purlin and the wall according to the present invention.
图8为本发明所述双拼钢斜撑、围檩和墙体连接立面图。Fig. 8 is an elevational view of the connection between the double steel diagonal bracing, the purlin and the wall according to the present invention.
图9为本发明所述双拼钢斜撑、围檩和墙体连接平面图。Fig. 9 is a plan view of the connection between the double steel diagonal brace, the purlin and the wall according to the present invention.
图10为本发明所述预埋防滑件详图。Fig. 10 is a detailed view of the embedded anti-slip part of the present invention.
具体实施方式:Detailed ways:
下面通过具体实例并结合附图对本发明做进一步详细说明。但不应将此理解为本发明上述主题的范围仅限于以下的实例,凡基于本发明内容所实现的技术均属于本发明的范围。The present invention will be described in further detail below through specific examples and in conjunction with the accompanying drawings. However, it should not be understood that the scope of the above-mentioned themes of the present invention is limited to the following examples, and all technologies realized based on the contents of the present invention belong to the scope of the present invention.
实施例1:Example 1:
本实施例所述咬合桩与地连墙联合支护结构的主体结构包括地连墙1、咬合桩素桩2、冠梁3、钢筋混凝土支撑4、钢支撑5、外墙结构6、围檩7和咬合桩硂桩8;根据不同的工程地质条件、技术要求,选择地连墙1或咬合桩作为主体支护结构,咬合桩素桩2与咬合桩硂桩8咬合形成咬合桩体;在地连墙1与咬合桩接缝处,与地连墙1相邻的咬合桩为咬合桩素桩2,两者咬合相连;咬合桩与外墙结构6相连,形成平整墙面;在地连墙1与咬合桩上部分别浇筑冠梁3;第一道支撑为钢筋混凝土支撑4,与冠梁3上的预留钢筋相连,根据基坑形状及受力特点使用钢筋混凝土角撑、钢筋混凝土对撑、钢筋混凝土斜撑;在地连墙1和外墙结构6上按设计标高安装围檩7;第二、三道支撑为双拼结构的钢支撑5,钢支撑5与围檩7相连,根据基坑形状及受力特点使用钢支撑角撑、钢支撑对撑、钢支撑斜撑并采取加固措施。The main structure of the combined support structure of the occlusal pile and the ground wall in this embodiment includes the ground wall 1, the occlusal pile plain pile 2, the crown beam 3, the reinforced concrete support 4, the steel support 5, the outer wall structure 6, and the surrounding purlin. 7 and the occlusal pile 8; according to different engineering geological conditions and technical requirements, the ground connection wall 1 or the occlusal pile is selected as the main support structure, and the occlusal pile 2 and the occlusal pile 8 are occluded to form an occlusal pile body; At the joint between the ground connection wall 1 and the occlusal pile, the occlusal pile adjacent to the ground connection wall 1 is the occlusal pile plain pile 2, and the two are occluded and connected; the occlusal pile is connected with the outer wall structure 6 to form a flat wall surface; The crown beam 3 is poured on the wall 1 and the upper part of the occlusal pile respectively; the first support is a reinforced concrete support 4, which is connected with the reserved steel bars on the crown beam 3, and reinforced concrete corner braces and reinforced concrete pairs are used according to the shape and force characteristics of the foundation pit. Braces, reinforced concrete diagonal braces; the purlins 7 are installed on the ground connection wall 1 and the outer wall structure 6 according to the design elevation; the second and third supports are steel supports 5 with a double structure, and the steel supports 5 are connected with the purlins 7. According to the shape and stress characteristics of the foundation pit, use steel support angle braces, steel support counter braces, steel support diagonal braces and take reinforcement measures.
本实施例所述地下连续墙1的具体尺寸根据具体工程与咬合桩的尺寸确定,一般地下连续墙幅宽不大于6m,埋深为10m至50m,厚度为0.5m至1.2m,小于相邻咬合桩素桩2直径至少200mm,便于两者咬合紧密;咬合桩素桩2的直径和埋深应根据具体工程确定,直径不小于1000mm,至少用C25超缓凝混凝土浇筑,与相邻桩桩间咬合不小于300mm;咬合桩硂桩8的直径和埋深根据具体工程确定,直径不小于1000mm,至少用C45水下混凝混凝土浇筑,与相邻桩桩间咬合不小于300mm;冠梁3的尺寸为1200×1000mm、1500×1000mm,至少用C45混凝土浇筑;钢筋混凝土支撑4的类型、长度、横截面积根据基坑尺寸及具体荷载确定为800×1000mm,至少用C45混凝土浇筑。The specific size of the underground diaphragm wall 1 described in this embodiment is determined according to the specific project and the size of the occlusal pile. Generally, the width of the underground diaphragm wall is not more than 6m, the buried depth is 10m to 50m, and the thickness is 0.5m to 1.2m, which is less than the adjacent wall. The diameter of the plain pile 2 of the occlusal pile is at least 200mm, which is convenient for the two to occlude tightly; the diameter and depth of the occlusal pile 2 should be determined according to the specific project, and the diameter should not be less than 1000mm. The interocclusion of the interlocking pile is not less than 300mm; the diameter and buried depth of the interlocking piles and piles 8 are determined according to the specific project, the diameter is not less than 1000mm, and at least C45 underwater concrete is poured, and the interocclusion between the adjacent piles is not less than 300mm; the crown beam 3 The dimensions are 1200×1000mm, 1500×1000mm, at least poured with C45 concrete; the type, length, and cross-sectional area of the reinforced concrete support 4 are determined to be 800×1000mm according to the size of the foundation pit and the specific load, and poured with at least C45 concrete.
本实施例所述外墙结构6包括网喷混凝土层9、砂浆找平层10、施工防水层11、侧墙12,在咬合桩内侧锚固钢筋13上挂网喷射混凝土形成网喷混凝土层9,厚度不小于80mm,网喷混凝土层9的外侧为厚度不小于20mm的砂浆找平层10,砂浆找平层10外侧施工防水层11,在防水层11外侧浇筑侧墙12,厚度不小于20mm。The exterior wall structure 6 described in this embodiment includes a net shotcrete layer 9, a mortar leveling layer 10, a construction waterproof layer 11, and a side wall 12, and the net shotcrete layer 9 is formed by hanging the net shotcrete on the anchoring steel bar 13 inside the occlusal pile, and the thickness Not less than 80mm, the outside of the sprayed concrete layer 9 is a mortar leveling layer 10 with a thickness of not less than 20mm, and a waterproof layer 11 is constructed outside the mortar leveling layer 10, and a side wall 12 is poured outside the waterproof layer 11, and the thickness is not less than 20mm.
本实施例所述围檩7采用组合双拼工字钢,一般采用Q235B钢,围檩7架设在三角形支架23上,三角形支架23采用直径20mm的YG2型胀管螺栓19与地连墙1相连,连接长度不小于280mm,在设置斜撑的围檩7内侧墙体内预埋防滑件24,用于增强围檩7的抗滑移能力,防滑件24由钢板29和钢筋30焊接而成,钢板29的厚度不小于20mm,钢筋30为带肋钢筋,直径不小于20mm。The purlin 7 in this embodiment adopts combined double I-beams, usually Q235B steel, and the purlin 7 is erected on the triangular support 23, and the triangular support 23 is connected to the ground connection wall 1 by YG2 expansion tube bolts 19 with a diameter of 20mm. , the connection length is not less than 280mm, anti-slip parts 24 are pre-embedded in the inner wall of the purlin 7 provided with diagonal braces to enhance the anti-slip ability of the purlin 7, and the anti-slip parts 24 are welded by steel plates 29 and steel bars 30, The thickness of the steel plate 29 is not less than 20 mm, and the steel bar 30 is a ribbed steel bar with a diameter of not less than 20 mm.
本实施例所述钢支撑5的长度、直径、壁厚应根据基坑尺寸及具体荷载确定,根据基坑形状采用钢支撑角撑、钢支撑对撑、钢支撑斜撑,钢支撑5的紧固构件为将直径20mm的第一圆钢吊钩21、第二圆钢吊钩22分别与钢支撑5、YG2胀管螺栓18间焊接,第一圆钢吊钩21、第二圆钢吊钩22均由光圆钢筋弯曲成U型,长度不小于50mm,YG2胀管螺栓18埋设在围檩7上方800mm处,圆钢吊钩21、22与YG2胀管螺栓18之间用直径20mm的圆钢S型连接件26、27和紧固螺丝28连接,钢支撑5为斜撑时,在钢支撑5与围檩7之间焊接剪力块25,剪力块25的尺寸与材料符合具体工程要求。The length, diameter, and wall thickness of the steel support 5 described in this embodiment should be determined according to the size of the foundation pit and the specific load. The solid component is to weld the first round steel hook 21 and the second round steel hook 22 with a diameter of 20mm to the steel support 5 and the YG2 expansion tube bolt 18 respectively, and the first round steel hook 21 and the second round steel hook 22 are all bent into a U-shape by smooth round steel bars, and the length is not less than 50mm. YG2 expansion tube bolts 18 are buried 800mm above the purlin 7, and a circle with a diameter of 20mm is used between the round steel hooks 21, 22 and YG2 expansion tube bolts 18. Steel S-shaped connectors 26, 27 are connected with fastening screws 28. When the steel support 5 is a diagonal brace, a shear block 25 is welded between the steel support 5 and the purlin 7. The size and material of the shear block 25 conform to the specific project Require.
实施例2:Example 2:
本实施例将实施例1所述支护结构用于某地铁站咬合桩与地下连续墙联合支护中,所述咬合桩与地连墙联合支护主体结构包括地下连续墙1,墙厚800mm,幅宽6.0m,埋深26m,用C45水下混凝土浇筑,地连墙1之间采用H型钢连接;咬合桩素桩2,直径1000mm,与邻桩咬合300mm,埋深26m,用C25超缓凝混凝土浇筑;咬合桩混凝土桩8,直径1000mm,与邻桩咬合300mm,埋深26m,采用C45水下混凝土浇筑;冠梁3,地连墙1的冠梁3尺寸为1200×1000mm,咬合桩的冠梁3尺寸为1500×1000mm;混凝土支撑4,混凝土支撑作为第一道支撑,尺寸为800×1000mm,采用C45混凝土浇筑而成;钢支撑5采用双拼钢支撑,双拼钢支撑采用Φ609mm、壁厚t=16mm钢管;围檩7采用双拼I56c组合工字钢,钢材材料均采用Q235B钢。In this embodiment, the support structure described in Example 1 is used in the combined support of the occlusal pile and the underground diaphragm wall in a certain subway station. The main structure of the joint support of the occlusal pile and the ground connection wall includes an underground diaphragm wall 1 with a wall thickness of 800 mm. , with a width of 6.0m and a buried depth of 26m. It is poured with C45 underwater concrete. The ground connection wall 1 is connected by H-shaped steel. Slow-setting concrete pouring; occlusal pile concrete pile 8, diameter 1000mm, occlusal with adjacent piles 300mm, buried depth 26m, using C45 underwater concrete pouring; crown beam 3, crown beam 3 of ground connection wall 1 with a size of 1200×1000mm, occlusal The size of the crown beam 3 of the pile is 1500×1000mm; the concrete support 4, the concrete support is used as the first support, the size is 800×1000mm, and it is made of C45 concrete; the steel support 5 adopts double steel support, and the double steel support adopts Φ609mm, wall thickness t=16mm steel pipe; purlin 7 is made of double I56c combined I-beam, and the steel material is Q235B steel.
本实施例的具体实施方法为:The concrete implementation method of this embodiment is:
步骤1:采用Φ1000@700mm套管咬合桩,进行咬合桩的施工时,与地连墙1相邻的咬合桩为素桩2,放线定位后,钻机就位,取土成孔直至设计孔底标高,如为咬合桩硂桩在成孔检查合格后吊放钢筋笼,后浇筑混凝土拔管成桩;Step 1: Use Φ1000@700mm casing occlusal piles. When constructing occlusal piles, the occlusal piles adjacent to the ground connection wall 1 are plain piles 2. After setting the line and positioning, the drilling rig is in place, and soil is taken to form holes until the designed holes Bottom elevation, if it is an occlusal pile, the steel cage shall be hoisted after the hole-forming inspection is qualified, and then the concrete shall be poured and the pipe shall be pulled out to form a pile;
步骤2:根据设计要求及导墙确定地连墙1位置,成槽机进行开挖作业,本实施例采用徐工480型液压抓斗成槽机成槽,成槽时采用泥浆护壁,直至深度与相邻咬合桩埋深相同,再进行槽孔验收;Step 2: According to the design requirements and the guide wall, determine the position of ground connection wall 1, and excavate the groove machine. In this embodiment, XCMG 480 hydraulic grab groove machine is used to form grooves. When forming grooves, mud protection walls are used until the depth is equal to Adjacent occlusal piles have the same burial depth, and then the slot hole acceptance is carried out;
步骤3:进行地连墙1与咬合桩素桩2接缝处的施工,地连墙1成槽时,靠近咬合桩素桩2一侧采用旋挖钻扩大成槽墙体宽度200mm,确保浇筑混凝土时,混凝土能绕流过槽钢背面;采用旋挖钻钻除部分接缝处咬合桩素桩2,使地连墙1与相邻咬合桩素桩2咬合300mm,对咬合桩素桩2刷壁后,吊放钢筋笼,浇筑混凝土;Step 3: Carry out the construction of the joint between the ground connection wall 1 and the occlusal pile plain pile 2. When the ground connection wall 1 forms a groove, the side close to the occlusal pile plain pile 2 is expanded into a groove wall with a width of 200 mm to ensure pouring When concrete is used, the concrete can flow around the back of the channel steel; use a rotary drill to drill out some of the seam piles 2, so that the ground wall 1 and the adjacent seam pile 2 are occluded by 300mm, and the seam pile 2 is occluded. After painting the walls, hang the reinforcement cage and pour concrete;
步骤4:在咬合桩2桩顶与地连墙1墙顶进行冠梁3施工,先定位放线,再绑扎钢筋,然后支护模板,浇筑混凝土形成钢筋混凝土冠梁3,并预留与钢筋混凝土撑4连接的钢筋,地连墙1与咬合桩素桩2相连处的冠梁3应浇筑成一体;Step 4: Carry out crown beam 3 construction on the top of the occlusal pile 2 and the top of the ground connection wall 1, first position and set out the wires, then tie the steel bars, then support the formwork, pour concrete to form a reinforced concrete crown beam 3, and reserve The steel bars connected by the concrete support 4 and the crown beam 3 at the connection between the ground connection wall 1 and the occlusal pile plain pile 2 should be poured into one;
步骤5:在冠梁3施工的时候,施工第一道钢筋混凝土支撑4,施作垫层,钢筋焊接、绑扎、安装,模板安装及加固,浇筑混凝土,拆模后养护混凝土,待支撑强度达到75%时,继续向下挖土,基坑转角处采用2000mm×2000mm×300mm的混凝土板撑,其余使用钢筋混凝土对撑和钢筋混凝土斜撑;Step 5: During the construction of the crown beam 3, construct the first reinforced concrete support 4, apply the cushion layer, weld, bind, install the steel bars, install and reinforce the formwork, pour concrete, and maintain the concrete after the formwork is removed until the support strength reaches 75%, continue to dig down, use 2000mm×2000mm×300mm concrete slab braces at the corners of the foundation pit, and use reinforced concrete opposite braces and reinforced concrete diagonal braces for the rest;
步骤6:在咬合桩已施工部位采用锚固钢筋13挂网喷射混凝土形成网喷混凝土层9,厚度100mm,后在网喷混凝土层9上做砂浆找平层10,厚度20mm,再在找平层10上做防水层11,最后喷射混凝土层12,厚度100mm形成侧墙6;Step 6: Use anchoring steel bars 13 to hang the sprayed concrete on the construction site of the occlusal pile to form a sprayed concrete layer 9 with a thickness of 100 mm, and then make a mortar leveling layer 10 on the sprayed concrete layer 9 with a thickness of 20 mm, and then place it on the leveling layer 10 Make the waterproof layer 11, and finally spray the concrete layer 12 with a thickness of 100mm to form the side wall 6;
步骤7:按设计标高安装围檩7,在围檩7上安装三角形支架23、用两根直径20mm的YG2型胀管螺栓19紧固三角形支架23,围檩7与侧墙12之间的空隙用C30细石混凝土充填;吊装钢围檩7紧贴墙身,再安装YG2胀管螺栓18,斜撑处的钢围檩7应预埋防滑移件24;Step 7: Install the purlin 7 according to the design elevation, install the triangular bracket 23 on the purlin 7, fasten the triangular bracket 23 with two YG2 expansion tube bolts 19 with a diameter of 20mm, and the gap between the purlin 7 and the side wall 12 Fill with C30 fine stone concrete; hoist the steel purlin 7 close to the wall, and then install YG2 expansion tube bolts 18, and the steel purlin 7 at the diagonal brace should embed anti-slip parts 24;
步骤8:钢支撑5整体拼接吊装采用10t龙门吊安装,钢支撑5安装就位后,每榀支撑用2台100t台液压千斤顶在钢管支撑活动端预加分级施加轴力,并进行锁定,加设楔形块25后,拆下千斤顶完成钢支撑5的安装;在基坑转角处采用双拼I56c型钢角撑,其余采用双拼钢支撑对撑和双拼钢支撑斜撑。Step 8: The overall splicing and hoisting of the steel support 5 is installed by a 10t gantry crane. After the steel support 5 is installed in place, two 100t hydraulic jacks are used for each support to apply axial force in pre-graded and graded at the movable end of the steel pipe support, and lock it. After the wedge-shaped block 25 is set, the jack is removed to complete the installation of the steel support 5; at the corner of the foundation pit, a double-piece I56c steel corner brace is used, and the rest are double-piece steel support braces and double-piece steel support diagonal braces.
步骤9:继续开挖后应先撑后挖,及时架设第三道钢支撑5,测量定位,锚固三角形支架23,安装围檩7、钢支撑5,施加预应力,加设楔形块后,拆下千斤顶完成钢支撑的安装。Step 9: After continuing the excavation, brace first and then dig, erect the third steel support 5 in time, measure and position, anchor the triangular support 23, install purlin 7 and steel support 5, apply prestress, add wedge blocks, dismantle Lower the jack to complete the installation of the steel support.
Claims (6)
Priority Applications (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910669401.9A CN110485430A (en) | 2019-07-24 | 2019-07-24 | A kind of interlocking pile combines foundation pit supporting method with ground-connecting-wall |
| PCT/CN2020/103603 WO2021013200A1 (en) | 2019-07-24 | 2020-07-22 | Secant pile and retaining wall combined foundation pit supporting structure and method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910669401.9A CN110485430A (en) | 2019-07-24 | 2019-07-24 | A kind of interlocking pile combines foundation pit supporting method with ground-connecting-wall |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN110485430A true CN110485430A (en) | 2019-11-22 |
Family
ID=68548086
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201910669401.9A Pending CN110485430A (en) | 2019-07-24 | 2019-07-24 | A kind of interlocking pile combines foundation pit supporting method with ground-connecting-wall |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN110485430A (en) |
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110952985A (en) * | 2019-11-28 | 2020-04-03 | 苏州中车建设工程有限公司 | Sliding type vertical shaft annular steel support assembly and construction method |
| WO2021013200A1 (en) * | 2019-07-24 | 2021-01-28 | 青岛理工大学 | Secant pile and retaining wall combined foundation pit supporting structure and method |
| CN112962667A (en) * | 2021-02-08 | 2021-06-15 | 中国建筑第八工程局有限公司 | Outer wall structure of sinking yard and construction method thereof |
| CN114197488A (en) * | 2021-12-29 | 2022-03-18 | 中铁大桥勘测设计院集团有限公司 | Foundation ditch double row pile supporting construction |
| CN114790746A (en) * | 2022-05-07 | 2022-07-26 | 中建八局轨道交通建设有限公司 | Welding-free underground diaphragm wall anchoring part and foundation pit inner support mounting method |
| CN115075252A (en) * | 2021-03-10 | 2022-09-20 | 中交二航局成都城市建设工程有限公司 | Leakage-proof device at joint of auxiliary enclosure structure and construction method thereof |
| CN115110543A (en) * | 2022-08-01 | 2022-09-27 | 四川路桥华东建设有限责任公司 | Strip foundation multi-arc multi-arch interlock pile foundation pit supporting structure and supporting method |
| CN115538458A (en) * | 2022-10-26 | 2022-12-30 | 北京市政路桥股份有限公司 | A combined soil retaining and water-stop structure in deep silt and fine sand stratum and its construction method |
| CN116084429A (en) * | 2022-12-31 | 2023-05-09 | 中建一局集团建设发展有限公司 | Stress-retaining type permanent-facing combined continuous pile wall supporting structure and construction method |
| CN116163313A (en) * | 2022-11-23 | 2023-05-26 | 北方工业大学 | Connection structure and construction method of foundation pit steel support and enclosure structure |
| CN116971364A (en) * | 2023-07-27 | 2023-10-31 | 上海市基础工程集团有限公司 | Construction method of joint connection between underground diaphragm wall and bite pile in deep foundation pit project |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106120828A (en) * | 2016-06-23 | 2016-11-16 | 程华清 | A kind of Sandwich biscuit type curtain water stop construction method of diaphragm wall |
| CN208023589U (en) * | 2017-12-08 | 2018-10-30 | 中冶天工集团天津有限公司 | A support type waterproof curtain |
| KR20180124795A (en) * | 2018-08-22 | 2018-11-21 | 박강호 | An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same |
| CN109208637A (en) * | 2018-08-08 | 2019-01-15 | 北京建工土木工程有限公司 | Increase the construction method of open-cut station newly on the basis of existing tunnel |
| CN208717918U (en) * | 2018-09-04 | 2019-04-09 | 龙喜安 | The enclosure structure of foundation pit of subway station of high-voltage line or overpass is worn under a kind of |
| CN109630127A (en) * | 2018-11-22 | 2019-04-16 | 中铁隧道集团二处有限公司 | A kind of construction method of rich water soft stratum ultra-deep shield vertical shaft |
-
2019
- 2019-07-24 CN CN201910669401.9A patent/CN110485430A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106120828A (en) * | 2016-06-23 | 2016-11-16 | 程华清 | A kind of Sandwich biscuit type curtain water stop construction method of diaphragm wall |
| CN208023589U (en) * | 2017-12-08 | 2018-10-30 | 中冶天工集团天津有限公司 | A support type waterproof curtain |
| CN109208637A (en) * | 2018-08-08 | 2019-01-15 | 北京建工土木工程有限公司 | Increase the construction method of open-cut station newly on the basis of existing tunnel |
| KR20180124795A (en) * | 2018-08-22 | 2018-11-21 | 박강호 | An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same |
| CN208717918U (en) * | 2018-09-04 | 2019-04-09 | 龙喜安 | The enclosure structure of foundation pit of subway station of high-voltage line or overpass is worn under a kind of |
| CN109630127A (en) * | 2018-11-22 | 2019-04-16 | 中铁隧道集团二处有限公司 | A kind of construction method of rich water soft stratum ultra-deep shield vertical shaft |
Cited By (15)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2021013200A1 (en) * | 2019-07-24 | 2021-01-28 | 青岛理工大学 | Secant pile and retaining wall combined foundation pit supporting structure and method |
| CN110952985A (en) * | 2019-11-28 | 2020-04-03 | 苏州中车建设工程有限公司 | Sliding type vertical shaft annular steel support assembly and construction method |
| CN110952985B (en) * | 2019-11-28 | 2021-10-26 | 苏州中车建设工程有限公司 | Sliding type vertical shaft annular steel support assembly and construction method |
| CN112962667A (en) * | 2021-02-08 | 2021-06-15 | 中国建筑第八工程局有限公司 | Outer wall structure of sinking yard and construction method thereof |
| CN115075252A (en) * | 2021-03-10 | 2022-09-20 | 中交二航局成都城市建设工程有限公司 | Leakage-proof device at joint of auxiliary enclosure structure and construction method thereof |
| CN115075252B (en) * | 2021-03-10 | 2024-07-23 | 中交二航局(成都)建设工程有限公司 | Construction method of anti-leakage device at joint of auxiliary enclosure structure |
| CN114197488A (en) * | 2021-12-29 | 2022-03-18 | 中铁大桥勘测设计院集团有限公司 | Foundation ditch double row pile supporting construction |
| CN114790746A (en) * | 2022-05-07 | 2022-07-26 | 中建八局轨道交通建设有限公司 | Welding-free underground diaphragm wall anchoring part and foundation pit inner support mounting method |
| CN115110543A (en) * | 2022-08-01 | 2022-09-27 | 四川路桥华东建设有限责任公司 | Strip foundation multi-arc multi-arch interlock pile foundation pit supporting structure and supporting method |
| CN115538458A (en) * | 2022-10-26 | 2022-12-30 | 北京市政路桥股份有限公司 | A combined soil retaining and water-stop structure in deep silt and fine sand stratum and its construction method |
| CN115538458B (en) * | 2022-10-26 | 2025-12-02 | 北京市政路桥股份有限公司 | A combined retaining and water-stopping structure and construction method for deep silty sand strata |
| CN116163313A (en) * | 2022-11-23 | 2023-05-26 | 北方工业大学 | Connection structure and construction method of foundation pit steel support and enclosure structure |
| CN116163313B (en) * | 2022-11-23 | 2024-02-23 | 北方工业大学 | Connection structure of foundation pit section steel support and enclosure structure and construction method |
| CN116084429A (en) * | 2022-12-31 | 2023-05-09 | 中建一局集团建设发展有限公司 | Stress-retaining type permanent-facing combined continuous pile wall supporting structure and construction method |
| CN116971364A (en) * | 2023-07-27 | 2023-10-31 | 上海市基础工程集团有限公司 | Construction method of joint connection between underground diaphragm wall and bite pile in deep foundation pit project |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110485430A (en) | A kind of interlocking pile combines foundation pit supporting method with ground-connecting-wall | |
| CN106958256B (en) | A caisson construction technology with layered pouring and multiple subsidence | |
| CN104264688B (en) | Manually digging hole non-uniform pile support construction process | |
| CN205742213U (en) | Foundation pit supporting construction | |
| WO2021013200A1 (en) | Secant pile and retaining wall combined foundation pit supporting structure and method | |
| CN110485431A (en) | A kind of interlocking pile combines foundation pit supporting construction with ground-connecting-wall | |
| CN101538833B (en) | Vertical subsection double-wall steel cofferdam water stopping construction method | |
| CN103321246B (en) | Construction Method of Foundation Pit Using Underground Diaphragm Wall | |
| CN102995659B (en) | Method for constructing from central area to periphery of ultra-large type underground engineering | |
| CN104018518A (en) | Prefabricated underground diaphragm wall and method for constructing outer basement wall and floor slabs | |
| CN112160324A (en) | Construction method for deep foundation pit support | |
| CN111119198A (en) | A reinforced structure that is used for SMW worker method stake to strut system | |
| CN204000925U (en) | Prefabricated diaphragm wall | |
| CN102286982A (en) | Deep foundation pit precast building enclosure for constructing in low environment | |
| CN111395331B (en) | A kind of artificially dug rectangular cross-section anchor pile assembled wall protection and its construction technology | |
| CN104005414A (en) | Method for constructing large-diameter reinforced concrete cast-in-place pile supporting stand column | |
| CN211171994U (en) | Occlusive pile and diaphragm wall combined foundation pit supporting structure | |
| CN116537819A (en) | Half reverse construction method for primary support of urban mountain tunnel by ultra-large span and small clear distance cover excavation method | |
| CN108118689B (en) | Partially recyclable prefabricated underground diaphragm wall, spreader and construction method | |
| CN211368349U (en) | Steel trestle end of steel pipe pile | |
| CN119435012A (en) | A method for concealed excavation of a three-layer six-hole subway station | |
| CN210263075U (en) | A rear grouting inner anchor and outer water stop support system for grid-type pipe piles | |
| CN108221954B (en) | An easily disassembled prefabricated underground diaphragm wall, spreader and construction method | |
| CN108221955B (en) | Prefabricated underground diaphragm wall capable of being recycled integrally, lifting appliance and construction method | |
| CN113266019B (en) | A construction method of steel pipe support system for foundation pit |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191122 |