CN107542108B - A reverse construction method of a building basement structure - Google Patents

A reverse construction method of a building basement structure Download PDF

Info

Publication number
CN107542108B
CN107542108B CN201611198350.9A CN201611198350A CN107542108B CN 107542108 B CN107542108 B CN 107542108B CN 201611198350 A CN201611198350 A CN 201611198350A CN 107542108 B CN107542108 B CN 107542108B
Authority
CN
China
Prior art keywords
basement
construction
floor
excavation
negative
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201611198350.9A
Other languages
Chinese (zh)
Other versions
CN107542108A (en
Inventor
王立军
祝浩
周新科
廖俊侨
雷勇军
沈俊川
祁永平
龙平
廖斌
陈焕旭
刘昆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Jianye Engineering Group Co Ltd
Original Assignee
Shenzhen Jianye Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Jianye Engineering Group Co Ltd filed Critical Shenzhen Jianye Engineering Group Co Ltd
Priority to CN201611198350.9A priority Critical patent/CN107542108B/en
Publication of CN107542108A publication Critical patent/CN107542108A/en
Application granted granted Critical
Publication of CN107542108B publication Critical patent/CN107542108B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

一种建筑物地下室结构的逆向施工方法,解决基坑周围地面沉陷、道路、建筑、地下管线变形错位和基坑开挖后续施工的困难的问题,该工法采用在先期成型的桩柱孔内浇筑地下结构桩柱子后,在进行地下结构部分逆作施工的方法实现,该施工方法由以下步骤实现:1地面上进行地下室结构的桩柱孔施工,桩柱孔分成地下室空间尺寸以下的桩孔部分和穿越地下室空间尺寸的柱孔部分。2.桩子混凝土浇筑。3.柱子混凝土浇筑。4.地下室负一层结构土方挖掘清除。5.地下室负一层外墙混凝土结构施工。6.地下室负一层土方挖掘清除结构施工。7.地下室负二层土方挖掘清除施工。8.地下室负二层的横梁、楼板结构施工。有益效果是,施工方法简单、效率高、成本低。

A reverse construction method for the basement structure of a building, which solves the problems of ground subsidence around the foundation pit, deformation and dislocation of roads, buildings, and underground pipelines, and difficulties in subsequent construction of foundation pit excavation. The construction method adopts pouring in the pile holes formed in advance After the underground structure is piled, the method of reverse construction of the underground structure is realized. The construction method is realized by the following steps: 1. The pile hole construction of the basement structure is carried out on the ground, and the pile hole is divided into pile holes below the size of the basement space. and the portion of the column hole that crosses the size of the basement space. 2. Pile concrete pouring. 3. Concrete pouring of columns. 4. Excavation and removal of earthwork for the negative first floor structure of the basement. 5. Concrete structure construction of the outer wall of the negative floor of the basement. 6. Earthwork excavation and clearing structure construction on the negative floor of the basement. 7. Excavation and removal of earth on the negative second floor of the basement. 8. Construction of beams and floor slabs on the negative second floor of the basement. The beneficial effect is that the construction method is simple, high in efficiency and low in cost.

Description

一种建筑物地下室结构的逆向施工方法A reverse construction method of a building basement structure

一种建筑物地下室结构的逆向施工方法A reverse construction method of a building basement structure

技术领域technical field

本发明涉及一种建筑施工方法,特别是一种建筑物地下室结构的逆向施工方法。The invention relates to a building construction method, in particular to a reverse construction method for a basement structure of a building.

背景技术Background technique

自改革开放以来,国内城市建设规模不断扩大,建筑物密度和高度也随之加大,深、大型基坑随建筑物密度和高度的增加已被普遍采用。现有技术是采用先挖掘基坑在施工的办法,但随着开挖深度的不断增加,降水形成的降落漏斗影响区域范围也不断扩大,对基坑周围既有建筑物的影响也越来越大,现有技术造成基坑周围地面沉陷、道路、建筑、地下管线变形错位和基坑开挖后续施工的困难。Since the reform and opening up, the scale of domestic urban construction has continued to expand, and the density and height of buildings have also increased. Deep and large foundation pits have been widely used as the density and height of buildings increase. The existing technology adopts the method of excavating the foundation pit first, but with the continuous increase of the excavation depth, the influence area of the falling funnel formed by precipitation is also expanding, and the impact on the existing buildings around the foundation pit is also increasing. The existing technology has caused ground subsidence around the foundation pit, deformation and dislocation of roads, buildings, and underground pipelines, and difficulties in subsequent construction of foundation pit excavation.

发明目的purpose of invention

为解决上述基坑周围地面沉陷、道路、建筑、地下管线变形错位和基坑开挖后续施工的困难的问题,本发明公开一种建筑物地下室结构的逆向施工方法,针对工程周边建筑物密集,地下管线复杂的地区,在地下结构部分采用逆作综合施工,取得较好效果。In order to solve the above-mentioned problems of ground subsidence around the foundation pit, deformation and dislocation of roads, buildings, and underground pipelines, and difficulties in subsequent construction of foundation pit excavation, the present invention discloses a reverse construction method for the basement structure of a building. In areas with complex underground pipelines, comprehensive reverse construction is used in the underground structure, and better results are achieved.

本发明实现发明目的采用的方法是:The method that the present invention realizes the purpose of the invention adopts is:

一种建筑物地下室结构的逆向施工方法,该工法采用在先期成型的桩柱孔内浇筑地下结构桩柱子后,再进行地下结构部分逆作施工的方法实现,该施工方法由以下步骤实现:A reverse construction method for a basement structure of a building. The construction method is realized by pouring underground structure piles in previously formed pile holes, and then carrying out partial reverse construction of the underground structure. The construction method is realized by the following steps:

步骤1.地面上进行地下室结构的桩柱孔施工,并对形成的桩柱孔进行护壁处理,桩柱孔施工中,桩柱孔分成地下室空间尺寸以下的桩孔部分和穿越地下室空间尺寸的柱孔部分,对于穿越地下室空间尺寸的柱孔部分的孔径尺寸大于柱子轮廓尺寸0.8-1.2米的柱子施工空间。Step 1. Carry out the pile hole construction of the basement structure on the ground, and carry out wall protection treatment on the formed pile hole. During the pile hole construction, the pile hole is divided into the pile hole part below the size of the basement space and the column passing through the size of the basement space. For the hole part, the hole diameter of the column hole part passing through the basement space size is larger than the column outline size of 0.8-1.2 meters in the column construction space.

步骤2.桩子混凝土浇筑:将桩子钢筋笼安装就位在桩孔部分孔内,复线无误后浇筑桩芯混凝土,桩子混凝土浇筑至柱子插筋锚固端底标高处,待柱插筋绑扎安装后二次灌注桩子混凝土至设计标高;Step 2. Pile concrete pouring: install the pile reinforcement cage in place in the pile hole, pour the pile core concrete after the double line is correct, and pour the pile concrete to the bottom elevation of the anchoring end of the column inserting reinforcement. After the column inserting reinforcement is bound and installed, two Secondary pouring of pile concrete to the design elevation;

步骤3.柱子混凝土浇筑:Step 3. Column Concreting:

捆扎柱子钢筋,在柱孔部分的柱孔内进行柱箍筋的绑扎,柱子钢筋绑扎安装时,按照地下楼层标高及设计位置安装固定地下室外墙水平预埋筋及柱子箍抗剪预埋筋;Bind the column reinforcement, and bind the column stirrup in the column hole of the column hole. When the column reinforcement is bound and installed, install and fix the horizontal pre-embedded reinforcement of the basement exterior wall and the shear pre-embedded reinforcement of the column hoop according to the elevation of the underground floor and the design position;

安装固定柱子模板,柱子模板的安装固定,按模板设计要求在柱孔部分的柱孔内自下而上进行;Install and fix the column formwork, the installation and fixation of the column formwork shall be carried out from bottom to top in the column hole of the column hole part according to the design requirements of the formwork;

在安装固定的柱子模板内浇筑柱子混凝土至柱子设计标高;Pour column concrete in the installed and fixed column formwork to the column design level;

步骤4.地下室负一层结构土方挖掘清除;Step 4. Earthwork excavation and removal of the negative first floor structure of the basement;

桩子混凝土和柱子混凝土浇筑完成后,采用机械和人工结合方式对地下室负一层结构土方挖掘清除,挖掘清除后对负一层的柱子模板进行拆除施工。After the pouring of pile concrete and column concrete is completed, the earthwork of the basement negative floor structure is excavated and cleared by mechanical and manual methods, and the column formwork of the negative floor is removed after excavation and removal.

步骤5.地下室负一层外墙混凝土结构施工;Step 5. Construction of the concrete structure of the exterior wall of the negative floor of the basement;

在地下室负一层结构土方挖掘清除过程中应及时插入外墙施工,每次施工高度应视周边土体情况现场按设计规范确定,外墙水平钢筋采用单面搭接焊的方法与柱子施工时预留筋焊接,上节挡墙施工时,应预留竖筋与下节竖筋连接,设置水平止水钢板或防水凹槽;In the excavation and removal process of the basement negative floor structure, the external wall construction should be inserted in time. The height of each construction should be determined on site according to the surrounding soil conditions and according to the design specifications. Reserve ribs for welding. When constructing the upper section of the retaining wall, reserve vertical ribs to connect with the lower section vertical ribs, and set horizontal water-stop steel plates or waterproof grooves;

步骤6.地下室结构施工;Step 6. basement structure construction;

地下室负一层土方挖掘清除完成后,根据基底土质情况浇筑混凝土垫层,垫层厚度应满足刚度要求,防止地下室负一层顶板模板下沉,垫层标高应与地下室负二层楼板底标高一致,横梁、楼板结构模板支撑立杆底部应加设垫板,防止垫层局部不均匀沉降,进行地下室负一层横梁、楼板结构混凝土浇筑;After the excavation and removal of the earthwork on the negative floor of the basement is completed, pour a concrete cushion according to the soil quality of the basement. The thickness of the cushion should meet the rigidity requirements to prevent the roof formwork of the negative first floor of the basement from sinking. , the bottom of beams and floor structure formwork support poles should be equipped with a backing plate to prevent local uneven settlement of the cushion layer, and concrete pouring of beams and floor slab structures on the negative floor of the basement;

步骤7.地下室负二层土方挖掘清除施工;Step 7. Excavation and removal of earth on the negative second floor of the basement;

待地下室负一层横梁、楼板结构混凝土达到规范要求的拆模强度后,拆除支撑架体,进行地下二层土方挖掘清除,地下二层土方挖掘清除均为暗挖,采用分层开挖土方,每层厚度小于1米,开挖土方的基坑边与外墙边距离不小于2米,边坡坡度应根据土质情况,满足自然放坡的坡度要求,地下室负二层土方挖掘清除完成后,根据基底土质情况浇筑负二层混凝土垫层;After the beam and floor structure concrete of the negative first floor of the basement reach the formwork removal strength required by the code, the supporting frame is removed, and the earthwork excavation and removal of the second underground floor is carried out. The thickness of each layer is less than 1 meter, and the distance between the side of the excavated foundation pit and the side of the outer wall is not less than 2 meters. The slope of the side slope should meet the slope requirements of natural grading according to the soil quality. Pouring the negative second floor concrete cushion according to the soil quality of the base;

步骤8.地下室负二层的横梁、楼板结构施工;Step 8. Construction of beams and floor slab structures on the negative second floor of the basement;

在地下室负二层混凝土垫层上进行地下室负二层结构横梁、楼板施工,由于地下室柱子先行施工,而地下各层横梁、楼板随土体开挖进展自上而下逐层浇筑,通过柱上预留抗剪钢筋及环梁与柱子之间的摩擦力承受地下室楼板活荷载及自重,地下室每层的横梁、楼板结构混凝土浇筑应同步施工。Construction of beams and slabs on the second floor of the basement is carried out on the concrete cushion of the second floor of the basement. Since the pillars in the basement are constructed first, the beams and floors of each underground floor are poured layer by layer from top to bottom as the soil excavation progresses. The shear reinforcement and the friction between the ring beam and the column are reserved to bear the live load and self-weight of the basement floor, and the concrete pouring of the beam and floor structure of each floor of the basement should be constructed simultaneously.

本发明的有益效果是,施工方法简单、效率高、成本低,可别是解决基坑周围地面沉陷、道路、建筑、地下管线变形错位和基坑开挖后续施工的困难等技术问题。本施工工法主要适用于工程桩为挖孔桩的地质地段、邻近建筑物及周围环境对沉降变形敏感、施工工期紧张、施工场地狭窄、周围建筑密度大的大型地下结构工程。The beneficial effect of the present invention is that the construction method is simple, high in efficiency and low in cost, and can solve technical problems such as ground subsidence around the foundation pit, deformation and dislocation of roads, buildings, and underground pipelines, and difficulties in subsequent construction of foundation pit excavation. This construction method is mainly applicable to large-scale underground structural projects where the engineering piles are excavated piles, the adjacent buildings and the surrounding environment are sensitive to settlement deformation, the construction period is tight, the construction site is narrow, and the surrounding building density is high.

下面结合附图对本发明进行详细说明。The present invention will be described in detail below in conjunction with the accompanying drawings.

附图1为本发明施工工艺流程图。Accompanying drawing 1 is construction process flowchart of the present invention.

具体实施方式:Detailed ways:

本发明施工的工艺原理为:本发明多层地下室的施工方法是一种“封闭式”施工方法。其工艺原理是在地基土方上开挖桩柱孔施工,桩柱孔施工中,桩柱孔分成地下室空间尺寸以下的桩孔部分和穿越地下室空间尺寸的柱孔部分,对于穿越地下室空间尺寸的柱孔部分的孔径尺寸大于柱子轮廓尺寸0.8-1.2米的柱子施工空间,桩芯混凝土浇筑后在桩孔内实施地下结构的柱子,柱子施工过程中需预留梁抗剪钢筋及墙的水平钢筋。然后进行负一层土方开挖,开挖过程中逆作浇筑挡墙对边坡进行支护。再浇筑首层横梁、楼板结构,利用其作为地下结构的水平支撑。按此方法自上而下逐层完成地下结构施工,直至结构封底。The technological principle of the construction of the present invention is: the construction method of the multi-storey basement of the present invention is a kind of " closed " construction method. The principle of the technology is to excavate the pile hole construction on the foundation soil. During the pile hole construction, the pile hole is divided into the pile hole part below the basement space size and the column hole part passing through the basement space size. For the column passing through the basement space size The aperture size of the hole part is 0.8-1.2 meters larger than the column outline size. After the pile core concrete is poured, the underground structure column is implemented in the pile hole. During the column construction process, the shear reinforcement of the beam and the horizontal reinforcement of the wall need to be reserved. Then excavate the negative layer of earthwork, during which the retaining wall is poured upside down to support the slope. Then pour the beam and floor structure of the first floor, and use it as the horizontal support of the underground structure. According to this method, the construction of the underground structure is completed layer by layer from top to bottom until the bottom of the structure is sealed.

该施工方法由以下步骤实现:This construction method is realized by the following steps:

步骤1.地面上进行地下室结构的桩柱孔施工,并对形成的桩柱孔进行护壁处理,桩柱孔施工中,桩柱孔分成地下室空间尺寸以下的桩孔部分和穿越地下室空间尺寸的柱孔部分,对于穿越地下室空间尺寸的柱孔部分的孔径尺寸大于柱子轮廓尺寸0.8-1.2米的柱子施工空间。Step 1. Carry out the pile hole construction of the basement structure on the ground, and carry out wall protection treatment on the formed pile hole. During the pile hole construction, the pile hole is divided into the pile hole part below the size of the basement space and the column passing through the size of the basement space. For the hole part, the hole diameter of the column hole part passing through the basement space size is larger than the column outline size of 0.8-1.2 meters in the column construction space.

桩柱孔施工严格按照相关规章、规范施工外,施工采用的技术措施为:In addition to the construction of pile holes in strict accordance with relevant regulations and specifications, the technical measures adopted for construction are as follows:

桩柱孔施工中,钢筋混凝土护壁,穿越地下室空间尺寸的柱孔部分的孔径尺寸大于柱子轮廓尺寸0.8-1.2米,扩大直径的尺寸应能满足柱子施工作业,最佳取800~1000mm为益,扩大桩孔的底标高低于柱子底插筋的底端30~50mm。In the construction of pile holes, the reinforced concrete retaining wall, the hole size of the column hole part passing through the basement space size is 0.8-1.2 meters larger than the outline size of the column, and the enlarged diameter size should be able to meet the column construction work, and the best choice is 800-1000mm. The bottom elevation of the enlarged pile hole is 30-50mm lower than the bottom end of the column bottom insertion bar.

在流沙情况较轻时,缩短这一循环的开挖深度至0.5m,以减少挖层孔壁的暴露时间,及时进行护壁混凝土灌注,当桩柱孔壁塌落,有泥沙流入而不能形成桩柱孔时,可用纺织袋逐渐堆堵,形成桩柱孔的外壁,并控制保证内壁满足设计要求。When the quicksand situation is relatively light, shorten the excavation depth of this cycle to 0.5m to reduce the exposure time of the hole wall of the excavation layer, and timely pour concrete into the retaining wall. When the hole wall of the pile collapses, there will be silt flowing in and no For the pile holes, textile bags can be gradually piled up to form the outer wall of the pile hole, and the inner wall can be controlled to meet the design requirements.

在流砂较严重时,用下钢套筒的方法,钢套筒与护壁用的钢模相似,以孔外径为直径,可分成4~6段圆弧,再加上适当的肋条,相互用螺栓或钢筋环扣连接,在开挖0.5m左右,即可分片将套筒装入,深入孔底不少于0.2m,插入上部混凝土护壁外侧部小于0.5m,装后即支模浇注护壁混凝土,若放入套筒后流砂仍上涌,可采取突出挖出后即用混凝土封闭孔底的方法,待混凝土凝结后,将孔心部位的混凝土清凿形成桩柱孔。When the quicksand is serious, use the method of lowering the steel sleeve. The steel sleeve is similar to the steel mold used for the wall. The outer diameter of the hole is used as the diameter, and can be divided into 4 to 6 sections of arcs, plus appropriate ribs. Bolt or steel ring buckle connection, after about 0.5m of excavation, the sleeve can be installed in pieces, penetrated into the bottom of the hole not less than 0.2m, inserted into the outer part of the upper concrete retaining wall less than 0.5m, and cast the retaining wall after installation For concrete, if the quicksand still rises after being put into the sleeve, the method of sealing the bottom of the hole with concrete can be adopted after the protrusion is dug out. After the concrete is set, the concrete at the center of the hole is cleared to form a pile hole.

步骤2.桩子混凝土浇筑:将桩子钢筋笼安装就位在桩孔部分孔内,复线无误后浇筑桩芯混凝土,桩子混凝土浇筑至柱子插筋锚固端底标高处,待柱插筋绑扎安装后二次灌注桩子混凝土至设计标高。Step 2. Pile concrete pouring: install the pile reinforcement cage in place in the pile hole, pour the pile core concrete after the double line is correct, and pour the pile concrete to the bottom elevation of the anchoring end of the column inserting reinforcement. After the column inserting reinforcement is bound and installed, two Concrete the piles for the second time to the design elevation.

桩子混凝土浇筑:Pile Concreting:

桩子钢筋笼制作好后采用塔吊或吊车安装就位,复线无误后浇筑桩芯混凝土,桩子混凝土浇筑至柱插筋锚固端底标高处,待柱子插筋绑扎安装后二次灌注桩子混凝土至设计标高。After the pile reinforcement cage is made, install it in place with a tower crane or a crane. After the double line is correct, pour the pile core concrete. The pile concrete is poured to the height of the anchor end and bottom of the column insertion reinforcement. After the column insertion reinforcement is bound and installed, the pile concrete is poured twice to the design elevation. .

步骤3.柱子混凝土浇筑:Step 3. Column Concreting:

捆扎柱子钢筋,在柱孔部分的柱孔内进行柱箍筋的绑扎,柱子钢筋绑扎安装时,按照地下楼层标高及设计位置安装固定地下室外墙水平预埋筋及柱子箍抗剪预埋筋。Bundle the column reinforcement, and bind the column stirrup in the column hole of the column hole. When the column reinforcement is bound and installed, install and fix the horizontal pre-embedded reinforcement of the basement exterior wall and the shear pre-embedded reinforcement of the column hoop according to the elevation of the underground floor and the design position.

安装固定柱子模板,柱子模板的安装固定,按模板设计要求在柱孔部分的柱孔内自下而上进行;Install and fix the column formwork, the installation and fixation of the column formwork shall be carried out from bottom to top in the column hole of the column hole part according to the design requirements of the formwork;

在安装固定的柱子模板内浇筑柱子混凝土至柱子设计标高。Pour column concrete in the installed and fixed column formwork to the column design level.

桩孔内地下室结构柱子混凝土浇注Concrete pouring of basement structural columns inside pile holes

将轴线侧放于桩井圈上,并做好油漆标记;再将轴线落于桩子顶混凝土上,在桩子顶混凝土上放柱子出插筋位置,绑扎柱插筋,钢管架定位;采用汽车泵浇筑柱插筋混凝土,混凝土浇筑至设计基顶标高。Put the axis on the side of the pile well circle, and make a paint mark; then drop the axis on the concrete on the top of the pile, place the column on the concrete on the top of the pile to insert the reinforcement, bind the column and insert the reinforcement, and position the steel pipe frame; use the car pump Pour the concrete with column inserts, and pour the concrete to the design elevation of the foundation top.

柱子主筋与插筋采用直螺纹连接,先搭设钢管灯笼架,作柱子钢筋定位,保证钢筋的平面位置及垂直度。钢筋工在柱子孔内进行柱箍筋的绑扎。由于孔内操作空间有限,柱子箍筋只能从上部套住柱子主筋,用绳子系好,滑入下部,从下往上绑扎柱箍筋。柱子钢筋绑扎安装时,按照地下楼层标高及设计位置安装固定地下室外墙水平预埋筋及柱子箍抗剪预埋筋。The main reinforcement of the column and the insertion reinforcement are connected by straight threads. First, a steel pipe lantern frame is erected to position the reinforcement of the column to ensure the plane position and verticality of the reinforcement. Rebar workers bind the column stirrups in the column holes. Due to the limited operating space in the hole, the column hoops can only cover the main bars of the column from the upper part, tie them with ropes, slide them into the lower part, and bind the column hoops from bottom to top. When the column reinforcement is bound and installed, install and fix the horizontal pre-embedded reinforcement of the basement exterior wall and the shear pre-embedded reinforcement of the column hoop according to the elevation of the underground floor and the design position.

柱子模板制作安装。在制作模板以前绘制出详细的模板拼装图和制作大样图用来指导模板的制作和安装工作。模板制作完毕后,采用吊车或塔吊将模板吊入孔内就位。柱子模板采用钢管柱箍+顶托加固。根据柱子大小及高度计算出钢管柱箍的间距,一般为400-1000mm;顶托数量按柱子截面宽度设置,顶托后用钢管支撑于桩混凝土护壁上。柱箍安装应按模板设计要求自下而上进行,在已浇混凝土桩上200mm开始设置。柱子模板安装完毕后,应全面复核模板的垂直度,对角线长差,截面尺寸等项目,支撑必须牢固,预埋件、预留件、预留孔洞严禁漏设,必须准确、稳固。Post formwork fabrication and installation. Before making the template, draw a detailed template assembly diagram and make a large sample diagram to guide the production and installation of the template. After the formwork is finished, use a crane or a tower crane to hoist the formwork into the hole and put it in place. The column formwork is reinforced with steel pipe column hoops and jacking brackets. According to the size and height of the column, the spacing of the steel pipe hoops is calculated, which is generally 400-1000mm; the number of jacking is set according to the section width of the column, and the steel pipe is used to support the concrete retaining wall of the pile after jacking. The column hoop installation should be carried out from bottom to top according to the design requirements of the formwork, starting at 200mm on the poured concrete pile. After the column formwork is installed, the verticality of the formwork, the length difference of the diagonal line, the cross-sectional size and other items should be comprehensively reviewed. The support must be firm. Embedded parts, reserved parts, and reserved holes are strictly prohibited to be missed, and must be accurate and stable.

柱子混凝土浇筑。浇筑前应对模板浇水湿润,柱模板的清扫口应在清除杂物及积水后再封闭。柱子混凝土浇筑严禁爆模,在浇筑时应安排木工守模,如出现情况及时处理。如果柱子高度大于2米,混凝土浇筑应采用串筒或导管。Concreting of columns. The formwork should be watered and moistened before pouring, and the cleaning opening of the column formwork should be closed after removing debris and accumulated water. It is strictly forbidden to explode the formwork in the concrete pouring of the column. Carpenters should be arranged to guard the formwork during the pouring, and if there is a situation, it should be dealt with in time. If the height of the column is greater than 2 meters, the concrete pouring should use string tubes or conduits.

步骤4.地下室负一层结构土方挖掘清除;Step 4. Earthwork excavation and removal of the negative first floor structure of the basement;

桩子混凝土和柱子混凝土浇筑完成后,采用机械和人工结合方式对地下室负一层结构土方挖掘清除,挖掘清除后对负一层的柱子模板进行拆除施工。After the pouring of pile concrete and column concrete is completed, the earthwork of the basement negative floor structure is excavated and cleared by mechanical and manual methods, and the column formwork of the negative floor is removed after excavation and removal.

此层土方为敞开式挖掘清除,采用挖掘机进行挖掘清除,自卸汽车运场外弃土场。雨天施工时及软弱地基的土方运输道路,应铺筑片石,必要时铺垫厚钢板,以保证土方正常运输。临时道路具体走向根据现场实际情况确定,宽度应满足土方运输的要求。土方挖掘清除至设计标高以上300mm时停止挖掘,采用人工开挖至设计标高。边坡坡度应根据土质情况,满足自然放坡的坡度要求。This layer of soil is excavated and cleared openly, using excavators to excavate and clear, dump trucks to the spoil yard outside the yard. For construction in rainy days and earth transportation roads with weak foundations, gravel should be paved, and thick steel plates should be laid if necessary to ensure normal transportation of earth. The specific direction of the temporary road is determined according to the actual situation on site, and the width should meet the requirements of earthwork transportation. Excavation shall be stopped when the earthwork excavation is cleared to 300mm above the design elevation, and manual excavation shall be adopted to the design elevation. The slope of the side slope shall meet the slope requirements of natural grading according to the soil quality.

原施工桩柱孔时浇筑的钢筋混凝土护壁,在土方开挖时采用凿岩机凿除,利用废旧模板对柱子进行包裹保护,防止护壁破除过程中对柱子造成损伤。The reinforced concrete wall that was poured during the original construction of the pile hole was removed by a rock drill during the earthwork excavation, and the column was wrapped and protected with waste formwork to prevent damage to the column during the removal of the wall.

在土方挖掘清除过程中应及时插入外墙施工,每次施工高度应视周边土体情况现场确定(一般为1.5m一段)。外墙水平钢筋采用单面搭接焊的方法与原柱子施工时预留筋焊接。外墙模板为单面支撑体系。脚手架支撑,模板安装支撑牢固,不得有松动、跑模、下沉等现象。应保证挡土墙设计形状、尺寸及位置准确,并便于拆卸。从第二节挡墙开始,模板应支设斜口便于混凝土浇筑,混凝土浇筑至模板斜口上方,高出挡墙顶10-20cm,保证混凝土浇筑质量。待拆除模板后,人工凿除斜口混凝土。During the excavation and removal of earthwork, the external wall construction should be inserted in time, and the height of each construction should be determined on site according to the surrounding soil conditions (generally a section of 1.5m). The horizontal reinforcement of the outer wall is welded with the reinforcement reserved during the construction of the original column by the method of single-side lap welding. The exterior wall formwork is a single-sided support system. Scaffold support, formwork installation and support are firm, and there must be no looseness, run-out, sinking, etc. It shall be ensured that the designed shape, size and position of the retaining wall are accurate and easy to disassemble. Starting from the second section of the retaining wall, the formwork should be supported with a bevel to facilitate concrete pouring, and the concrete should be poured above the bevel of the formwork, 10-20cm higher than the top of the retaining wall, to ensure the quality of concrete pouring. After the formwork is removed, the beveled concrete is manually chiseled.

上节挡墙施工时,应预留竖筋与下节竖筋连接,设置水平止水钢板或防水凹槽。挡墙施工完毕后,若有渗水现象,可在渗水部位钻孔设置排水孔及排水管疏导渗水。During the construction of the upper section of the retaining wall, the vertical bars should be reserved to connect with the lower section's vertical bars, and horizontal water-stop steel plates or waterproof grooves should be set. After the construction of the retaining wall is completed, if there is water seepage, drain holes and drain pipes can be drilled at the seepage parts to guide the seepage.

步骤5.地下室负一层外墙混凝土结构施工;Step 5. Construction of the concrete structure of the exterior wall of the negative floor of the basement;

在地下室负一层结构土方挖掘清除过程中应及时插入外墙施工,每次施工高度应视周边土体情况现场按设计规范确定,外墙水平钢筋采用单面搭接焊的方法与柱子施工时预留筋焊接,上节挡墙施工时,应预留竖筋与下节竖筋连接,设置水平止水钢板或防水凹槽。In the excavation and removal process of the basement negative floor structure, the external wall construction should be inserted in time. The height of each construction should be determined on site according to the surrounding soil conditions and according to the design specifications. Reserve ribs for welding. When constructing the upper retaining wall, reserve vertical ribs to connect with the lower vertical ribs, and set horizontal water-stop steel plates or waterproof grooves.

步骤6.地下室结构施工;Step 6. basement structure construction;

地下室负一层土方挖掘清除完成后,根据基底土质情况浇筑混凝土垫层,垫层厚度应满足刚度要求,防止地下室负一层顶板模板下沉,垫层标高应与地下室负二层楼板底标高一致,横梁、楼板结构模板支撑立杆底部应加设垫板,防止垫层局部不均匀沉降,进行地下室负一层横梁、楼板结构混凝土浇筑;After the excavation and removal of the earthwork on the negative floor of the basement is completed, pour a concrete cushion according to the soil quality of the basement. The thickness of the cushion should meet the rigidity requirements to prevent the roof formwork of the negative first floor of the basement from sinking. , the bottom of beams and floor structure formwork support poles should be equipped with a backing plate to prevent local uneven settlement of the cushion layer, and concrete pouring of beams and floor slab structures on the negative floor of the basement;

步骤7.地下室负二层土方挖掘清除施工;Step 7. Excavation and removal of earth on the negative second floor of the basement;

待地下室负一层横梁、楼板结构混凝土达到规范要求的拆模强度后,拆除支撑架体,进行地下二层土方挖掘清除,地下二层土方挖掘清除均为暗挖,采用分层开挖土方,每层厚度小于1米,开挖土方的基坑边与外墙边距离不小于2米,边坡坡度应根据土质情况,满足自然放坡的坡度要求,地下室负二层土方挖掘清除完成后,根据基底土质情况浇筑负二层混凝土垫层。After the beam and floor structure concrete of the negative first floor of the basement reach the formwork removal strength required by the code, the supporting frame is removed, and the earthwork excavation and removal of the second underground floor is carried out. The thickness of each layer is less than 1 meter, and the distance between the side of the excavated foundation pit and the side of the outer wall is not less than 2 meters. The slope of the side slope should meet the slope requirements of natural grading according to the soil quality. According to the condition of the base soil, the concrete cushion of the negative second floor is poured.

待地面首层梁板结构混凝土达到规范要求的拆模强度后,拆除支撑架体,进行地下负二层土方挖掘清除,此层及以下楼层土方均为暗挖。采用分层挖掘清除土方,每层厚度小于1米,挖掘清除土方的基坑边与外墙边距离不小于2米,边坡坡度应根据土质情况,满足自然放坡的坡度要求。挖掘机应视楼层高度、结构柱子跨度、布局以及土质情况选择长臂挖掘机,履带抓斗铲机垂直运输出土。出土顺序应从出土口向建筑物中间区域延伸,然后再向四周扩大。临时道路应根据土质情况进行硬化处理。After the concrete of the beam-slab structure on the first floor on the ground reaches the formwork removal strength required by the code, the supporting frame is removed, and the earthwork of the negative second floor underground is excavated and cleared. The excavation shall be carried out in layers, and the thickness of each layer shall be less than 1 meter. The distance between the edge of the foundation pit and the edge of the outer wall shall not be less than 2 meters. The slope shall meet the slope requirements of natural grading according to the soil quality. The excavator should choose a long-arm excavator according to the height of the floor, the span of the structural columns, the layout and the soil quality, and the crawler grab shovel should be transported vertically for excavation. The excavation sequence should extend from the excavation opening to the middle area of the building, and then expand to the surrounding area. Temporary roads should be hardened according to soil conditions.

挖掘清除前在每根柱子阳角粘贴反光警示带,并对驾驶员进行详细的安全技术交底,严禁在施工过程中碰到结构柱子、横梁和楼板。Before excavation and removal, paste reflective warning tapes on the positive corners of each pillar, and provide detailed safety technical disclosure to the driver. It is strictly forbidden to touch structural pillars, beams and floors during the construction process.

步骤8.地下室负二层的横梁、楼板结构施工;Step 8. Construction of beams and floor slab structures on the negative second floor of the basement;

在地下室负二层混凝土垫层上进行地下室负二层结构横梁、楼板施工,由于地下室柱子先行施工,而地下各层横梁、楼板随土体开挖进展自上而下逐层浇筑,通过柱上预留抗剪钢筋及环梁与柱子之间的摩擦力承受地下室楼板活荷载及自重,地下室每层的横梁、楼板结构混凝土浇筑应同步施工。Construction of beams and slabs on the second floor of the basement is carried out on the concrete cushion of the second floor of the basement. Since the pillars in the basement are constructed first, the beams and floors of each underground floor are poured layer by layer from top to bottom as the soil excavation progresses. The shear reinforcement and the friction between the ring beam and the column are reserved to bear the live load and self-weight of the basement floor, and the concrete pouring of the beam and floor structure of each floor of the basement should be constructed simultaneously.

地下结构梁柱节点处理Treatment of Beam-column Joints of Underground Structures

土方挖掘清除到楼板底标高后,视土体情况对基底进行硬化处理,然后进行地下结构梁板施工。由于地下室柱子先行施工,而地下各层梁板随土体开挖进展自上而下逐层浇筑,因此梁柱节点的处理为地下结构的重点控制项目。After the earthwork is excavated and cleared to the bottom elevation of the floor, the base is hardened according to the soil condition, and then the underground structural beam and slab construction is carried out. Since the basement columns are constructed first, and the beams and slabs of each underground layer are poured layer by layer from top to bottom with the progress of soil excavation, the treatment of beam-column joints is a key control item of the underground structure.

通过柱上预留抗剪钢筋(或植筋)及横梁与柱子之间的摩擦力承受地下室楼板活荷载及自重。即在地下室楼板的横梁高范围内设置环梁柱箍,其截面尺寸与配筋应经设计验算后确定,柱箍的高度最好与地下室主梁的高度一致。地下室主梁钢筋锚入柱箍内,锚固长度应符合相关规范、图集的要求。柱箍的钢筋、模板制安,混凝土浇筑应与地下室的梁板结构同步施工。The live load and self-weight of the basement floor are borne by the reserved shear reinforcement (or planted reinforcement) on the column and the friction between the beam and the column. That is, ring beam column hoops are set within the beam height range of the basement floor, and the cross-sectional size and reinforcement should be determined after design checks. The height of the column hoops should preferably be consistent with the height of the basement main beam. The steel bars of the main girder in the basement are anchored into the column hoop, and the anchorage length should meet the requirements of relevant specifications and atlases. The steel bars and formwork for column hoops and concrete pouring shall be constructed simultaneously with the beam and slab structure of the basement.

施工前需先将柱子表面凿毛,选用高频率低振动机械进行凿毛,凿毛作业时要把混凝土的旧面彻底凿掉,露出新混凝土层,凿毛作业时不应伤害到建筑物的结构。Before construction, the surface of the column needs to be chiseled first, and high-frequency and low-vibration machines are used for chiseling. When chiseling, the old surface of the concrete should be completely chiseled off to expose the new concrete layer. The chiseling operation should not damage the structure of the building. structure.

柱箍主筋及要筋采用两个“门”字箍单面搭接焊。地下室主梁钢筋端头必须伸到柱边,并弯锚15d,板钢筋锚入至梁内。柱箍处的钢筋较密,浇筑混凝土时采用小直径振捣棒振捣,防止漏棒,避免造成混凝土质量缺陷。地下室梁柱节点处理见图。The main reinforcement and the main reinforcement of the column hoop adopt two single-sided lap welding of the "door" hoop. The end of the steel bar of the main beam in the basement must extend to the edge of the column and be bent and anchored for 15d, and the steel bar of the plate is anchored into the beam. The steel bars at the column hoops are relatively dense, and small-diameter vibrating rods are used to vibrate when pouring concrete to prevent leaking rods and avoid concrete quality defects. The treatment of beam-column joints in the basement is shown in the figure.

本发明实施例中,重复步骤6、7和步骤8,实现地下室多层施工。In the embodiment of the present invention, steps 6, 7 and 8 are repeated to realize multi-layer construction in the basement.

本发明在施工中,涉及的抗浮底板与锚杆施工In the construction of the present invention, the anti-floating bottom plate and anchor rod construction involved

如地下室底板标高低于地下水位,则底板就需要考虑抗浮的要求。可采用结构梁板抗浮,也可采用抗浮底板+抗浮锚杆的形式,无论采用哪种形式均需经设计验算后,确定具体的施工方案。结构横梁、楼板施工与基础梁板基本相同;抗浮锚杆+抗浮底板施工需要注意一下几点:If the elevation of the basement floor is lower than the groundwater level, the floor needs to consider the requirements of anti-floating. Structural beams and slabs can be used to resist buoyancy, or the form of anti-floating bottom plate + anti-floating anchor rods can be used. No matter which form is adopted, the specific construction plan must be determined after design check and calculation. The construction of structural beams and floor slabs is basically the same as that of foundation beams and slabs; the following points need to be paid attention to in the construction of anti-floating anchor + anti-floating floor:

(1)在整个施工过程中均应采用水泵或其他降水措施对基础进行降水,使地下水保持低于抗浮底板1-1.5m为最佳。(1) Water pumps or other dewatering measures should be used to dewater the foundation throughout the construction process, so that the groundwater is kept 1-1.5m lower than the anti-floating floor.

(2)锚杆锚固段应使锚筋位于锚孔中部,处并确保水泥砂浆保护层厚度大于25mm。(2) The anchorage section of the anchor rod should make the anchor bar located in the middle of the anchor hole, and ensure that the thickness of the cement mortar protective layer is greater than 25mm.

(3)锚杆全面施工前应作试验锚杆以确定锚杆长度。试验应根据不同的土层情况、锚杆长度及设计抗拔力要求确定试验组数。每一种情况的组数至少取1组,每组锚杆数不得少于3根;试验完成后应形成试验报告作为设计人员确定本场地锚杆长度之依据。(3) Before the full construction of the anchor bolt, the anchor bolt should be tested to determine the length of the anchor bolt. The number of test groups should be determined according to different soil layer conditions, bolt length and design pull-out resistance requirements. The number of groups in each case should be at least 1 group, and the number of anchor rods in each group should not be less than 3; after the test is completed, a test report should be formed as the basis for the designer to determine the length of the anchor rods on the site.

(4)桩柱孔进入中等风化岩层达到设计深度后应及时清孔,插入锚筋和灌浆,特别是锚固段要采取措施清除岩渣,遇孔内裂隙不能封堵,应让砂浆充填密实,保证砂浆与岩壁间充分粘结。为使锚固段内水泥砂浆填密实,灌浆管要插入孔底,自最低部分开始灌注,以排除孔内余水。(4) After the pile hole enters the medium weathered rock stratum and reaches the design depth, the hole should be cleaned in time, and the anchor reinforcement and grouting should be inserted. In particular, measures should be taken to remove the rock slag at the anchorage section, and the cracks in the hole cannot be sealed. Ensure sufficient bonding between the mortar and the rock wall. In order to make the cement mortar in the anchorage section compact, the grouting pipe should be inserted into the bottom of the hole and poured from the lowest part to remove the remaining water in the hole.

(5) 锚杆在土层段如遇土层塌孔或淤泥、流砂时,应带护壁套管跟管钻进。(5) If the anchor bolt encounters a hole in the soil layer or silt or quicksand in the soil layer, it should be drilled with the wall casing and the pipe.

(6)锚孔灌浆时应根据现场施工情况作适当调整,以避免因压力过大而恶化岩体裂隙。(6) When grouting anchor holes, appropriate adjustments should be made according to the site construction conditions to avoid deterioration of rock mass cracks due to excessive pressure.

(7)施工时应采取措施保证锚杆锚入中风化岩体内长度。当达到钻孔深度时,取出较完整岩芯,必须经地勘单位鉴定达到中风化标准,方能作为锚固段始端。当遇到破碎状岩体时,其锚杆的锚固长度应根据现场的具体情况由地勘、设计人员另定。(7) Measures should be taken during construction to ensure the length of the bolt anchored into the weathered rock body. When the drilling depth is reached, a relatively complete rock core must be taken out, and it must be identified by the geological survey unit to meet the moderate weathering standard before it can be used as the beginning of the anchorage section. When a broken rock mass is encountered, the anchorage length of the bolt should be determined separately by the geological survey and design personnel according to the specific conditions on site.

待抗浮锚杆施工完毕后施工抗浮底板,抗浮底板厚度由设计确定。抗浮锚杆上端锚入抗浮底板内,形成整体。The anti-floating bottom plate shall be constructed after the construction of the anti-floating anchor rods is completed, and the thickness of the anti-floating bottom plate shall be determined by the design. The upper end of the anti-floating anchor rod is anchored into the anti-floating bottom plate to form a whole.

监控监测Monitoring

在本发明方法施工中,应进行监测,监测从地下室开始施工起至地下室完工后三个月。包括临近建筑物的倾斜度、倾斜方向、倾斜速率以及地面裂缝的位置、走向、长度、宽度、变化程度进行监测。During the construction of the method of the present invention, monitoring should be carried out, and the monitoring starts from the construction of the basement to three months after the completion of the basement. Including the inclination, inclination direction, inclination rate of adjacent buildings, and the location, direction, length, width, and degree of change of ground cracks for monitoring.

实施过程中还应对地下水位进行监测。通过孔内设置水位管,采用水位计等方法进行测量。地下水位监测精度不宜低于10mm。The groundwater level should also be monitored during implementation. The water level pipe is set through the hole, and the water level gauge and other methods are used for measurement. The accuracy of groundwater level monitoring should not be lower than 10mm.

加强现场巡视与监测,对监测的数据进行统计、整理、分析,及时将分析结果上报,如出现监测数据超出相应规范的情况,应立即预警、停止现场作业,并上报相关部门商讨处理方案。Strengthen on-site inspections and monitoring, collect statistics, collate, and analyze the monitored data, and report the analysis results in a timely manner. If the monitoring data exceeds the corresponding specifications, an early warning should be issued, the on-site operation should be stopped, and the relevant departments should be reported to discuss the solution.

本发明工程实例1Engineering example 1 of the present invention

宝能世纪城项目东区酒店及办公楼工程Baoneng Century City project east area hotel and office building project

宝能世纪城项目东区酒店及办公楼工程位于江西省赣州市赣江源大道与瑞金路交界处。本工程结构体系为型钢砼柱框筒结构;层数为地上四十三层,地下三层,建筑结构总高度为182.05m。建筑使用功能:酒店、办公及配套。地上总建筑面积66035.91㎡,建筑基底面积1862.33㎡,主楼为43层办公楼及酒店,层高3.9~6.55m,总高182.05m,地下室3层,高15.2m,框架结构。地处于商业闹市区,周边居民楼较多,施工场地狭小。该工程2016年1月开工,2018年7月竣工。The hotel and office building project in the east area of the Baoneng Century City project is located at the junction of Ganjiangyuan Avenue and Ruijin Road, Ganzhou City, Jiangxi Province. The structural system of this project is a steel concrete column frame tube structure; the number of floors is 43 floors above ground and 3 floors underground, and the total height of the building structure is 182.05m. Building use function: hotel, office and supporting facilities. The total construction area on the ground is 66035.91㎡, the building base area is 1862.33㎡, the main building is a 43-story office building and hotel, with a floor height of 3.9~6.55m, a total height of 182.05m, a basement with 3 floors, a height of 15.2m, and a frame structure. Located in a commercial downtown area, there are many residential buildings around, and the construction site is small. The project started in January 2016 and was completed in July 2018.

本工程由于地址条件及周边环境因素影响,-2、-3层采用逆作法施工。根据逆作法施工需要,-2、-3层柱子一次性浇筑至-1层梁底,-2层梁板结构需后浇筑施工。均采用本工法施工,取得了良好的经济效益和社会效益。Due to the influence of address conditions and surrounding environmental factors in this project, -2 and -3 floors are constructed using the reverse method. According to the construction needs of the reverse method, the columns on the -2 and -3 floors are poured to the bottom of the beams on the -1 floor at one time, and the beam-slab structure on the -2 floor needs to be poured later. All adopt this method of construction, and have achieved good economic and social benefits.

本发明工程实例2Engineering example 2 of the present invention

佛山宝能金融大厦工程Foshan Baoneng Financial Building Project

佛山宝能金融大厦工程位于广东省佛山市佛山新城岭南大道与富华路交口东北角。本工程地下3层,地上31层,149.5m,总建筑面积81959.34㎡,其中地下19791.72㎡,地上62167.62㎡。工程为框架-核心筒结构,于2014年9月开工,2017年7月竣工。本工程由于周边环境限制,-2、-3层按逆作法施工,施工中节约了工程造价,增大了逆作法地下室的有效使用面积,取得了良好的经济效益和社会效益。The Foshan Baoneng Financial Building Project is located at the northeast corner of the intersection of Lingnan Avenue and Fuhua Road, Foshan Xincheng, Foshan City, Guangdong Province. This project has 3 floors underground, 31 floors above ground, 149.5m, and a total construction area of 81959.34㎡, including 19791.72㎡ underground and 62167.62㎡ above ground. The project is a frame-core tube structure, which started in September 2014 and was completed in July 2017. Due to the limitation of the surrounding environment, the -2 and -3 floors are constructed by the reverse method, which saves the construction cost, increases the effective use area of the basement by the reverse method, and achieves good economic and social benefits.

本工法不仅保证了施工进度,也取得了非常大的经济效益,利润达20%。同时通过工程质量最终验收检验,均达到设计及规范要求,合格率达100%,表明本工法在逆作法施工中有着广泛的应用前景。This construction method not only guarantees the construction progress, but also achieves very large economic benefits, with a profit of 20%. At the same time, it passed the final acceptance inspection of project quality, and all met the design and specification requirements, with a pass rate of 100%, indicating that this construction method has broad application prospects in reverse construction.

Claims (2)

1. a kind of reverse construction method of building basement structure, which, which uses, pours ground in earlier molding pile hole After flowering structure pile, then the method for carrying out underground structure part adverse construction method is realized, it is characterised in that: the construction method by with Lower step is realized:
The pile hole construction of basement structure is carried out on step 1. ground, and retaining wall processing, pile are carried out to the pile hole of formation In the construction of hole, pile hole is divided into basement space size stake holes part below and passes through the post holes portion of basement space size Point, the pillar for being greater than 0.8-1.2 meters of pillar overall size for passing through the aperture size of post holes part of basement space size Construction space;
Step 2. stake concreting: stake steel reinforcement cage is fitted in place in stake holes partial hole, the errorless after-pouring stake of multiple line Core concrete, at stake concreting to pillar joint bar anchored end bottom absolute altitude, the secondary pouring stake after the binding installation of column joint bar Sub- concrete is to designed elevation;
Step 3. pillar concreting:
Pillar reinforcing bar is tied up, the binding of column tie-bar is carried out in the post holes of post holes part, when the binding of pillar reinforcing bar is installed, according to ground Lower floor absolute altitude and design position install the horizontal embedded ribs of fixed underground room exterior wall and pillar hoop shearing resistance embedded ribs;
Fixed post template is installed, the installation of post template is fixed, by stencil design requirements in the post holes of post holes part under oneself And upper progress;
Pillar concrete is poured to pillar designed elevation in the fixed post template of installation;
Step 4. basement negative one layer structure excavation of earthwork is removed;
After the completion of stake concrete and pillar concreting, using mechanical and artificial combination to basement negative one layer structure Excavation of earthwork is removed, and is excavated and is carried out Demolition Construction to the post template of negative one layer after removing;
Step 5. basement negative one layer exterior wall concrete structure construction;
It should be inserted into external wall construction in time in basement negative one layer structure excavation of earthwork reset procedure, each construction height should regard week Side soil body situation scene is determined that exterior wall horizontal reinforcement is reserved when constructing using the method and pillar of single-selded lap joint by design specification Muscle welding, when upper section Retaining wall, should reserve vertical bar and connect with lower section vertical bar, horizontal steel plate for sealing water or waterproof groove is arranged;
Step 6. basement structure construction;
After the completion of basement negative one layer excavation of earthwork is removed, according to substrate soil property situation casting concrete bed course, cushion thickness is answered Meet rigidity requirement, prevents basement negative one layer roof plate template from sinking, bed course absolute altitude should be with the minus two floors board bottom absolute altitude of basement Unanimously, crossbeam, floor construction shuttering supporting bottom of upright rod should add backing plate, prevent bed course part differential settlement, carry out underground Room negative one floor crossbeam, floor construction concreting;
Construction is removed in the minus two layers of excavation of earthwork of step 7. basement;
After basement negative one layer crossbeam, floor construction concrete reach the strength of mould stripping of code requirement, supporting frame is removed, into The excavation of earthwork of two layers of row underground is removed, and the excavation of earthwork removing of two layers of underground is tunneling, using the stage excavation earthwork, every thickness degree Less than 1 meter, the foundation pit side of earth excavation and exterior wall back gauge are not less than 2 meters, and grade of side slope should meet nature according to soil property situation The slope requirement of slope pours minus two layers of coagulation according to substrate soil property situation after the completion of the minus two layers of excavation of earthwork of basement is removed Soil padding;
Minus two layers of the crossbeam of step 8. basement, floor construction construction;
The negative two-layer structure crossbeam of basement, floor slab construction are carried out on the minus two layer concretes bed course of basement, due to basement column Sub construction in advance, and each layer crossbeam in underground, floor successively pour from top to bottom with soil excavation progress, by reserving shearing resistance on column Frictional force between reinforcing bar and ring beam and pillar bears basement floor live load and self weight, crossbeam, the floor of every layer of basement Structural concrete, which pours, answers synchronous construction.
2. a kind of reverse construction method of building basement structure according to claim 1, it is characterised in that: repeat to walk Rapid 7 and step 8, realize the construction of basement multilayer.
CN201611198350.9A 2016-12-22 2016-12-22 A reverse construction method of a building basement structure Expired - Fee Related CN107542108B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611198350.9A CN107542108B (en) 2016-12-22 2016-12-22 A reverse construction method of a building basement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611198350.9A CN107542108B (en) 2016-12-22 2016-12-22 A reverse construction method of a building basement structure

Publications (2)

Publication Number Publication Date
CN107542108A CN107542108A (en) 2018-01-05
CN107542108B true CN107542108B (en) 2019-11-22

Family

ID=60966805

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611198350.9A Expired - Fee Related CN107542108B (en) 2016-12-22 2016-12-22 A reverse construction method of a building basement structure

Country Status (1)

Country Link
CN (1) CN107542108B (en)

Families Citing this family (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108560728B (en) * 2018-02-12 2019-11-01 杨春 Loose tool pouring type integral top lifting construction method
CN108203994A (en) * 2018-03-14 2018-06-26 中建四局第建筑工程有限公司 Along the method for subinverse construction technology on a kind of basement
CN109629894A (en) * 2018-12-13 2019-04-16 徐州华阳饲料有限公司 A kind of method of construction of discharging dust guard
CN109778906A (en) * 2019-01-31 2019-05-21 重庆科技学院 Construction method of underground small storage room
CN110439002A (en) * 2019-07-18 2019-11-12 中国建筑第四工程局有限公司 A kind of interim horizontal structure of inner support is used as the method for permanent structure beam slab
CN111456323A (en) * 2020-04-20 2020-07-28 上海建工二建集团有限公司 Structural Column, Basement Structural Column and Construction Method of Early-stage Construction Structure
CN111764578B (en) * 2020-07-07 2022-04-12 中建一局集团建设发展有限公司 Reverse construction pile column structure and construction method thereof
CN111998839B (en) * 2020-07-10 2021-06-15 北京城建集团有限责任公司 Support column positioning and verticality detection system based on reverse construction method
CN111877399A (en) * 2020-07-28 2020-11-03 南通隆嘉机械科技有限公司 Construction method for rapid channel sinking culvert construction by reverse operation
CN111851584A (en) * 2020-07-31 2020-10-30 山东建筑大学 Construction Method of Reinforced Concrete Frame Structure Column Foundation Enclosure Beam in Reverse Construction
CN111779027A (en) * 2020-08-18 2020-10-16 北京中岩智泊科技有限公司 Construction method for constructing underground garage through cover-excavation top-down construction
CN112482437B (en) * 2020-10-15 2022-06-24 上海建工二建集团有限公司 Integrated vertical supporting system for reverse construction pile and construction method thereof
CN112538981A (en) * 2020-11-26 2021-03-23 上海建工四建集团有限公司 Old building basement obstacle removing and new building pile foundation synchronous construction method
CN115404911B (en) * 2022-09-13 2024-09-13 南通大学 Reverse construction method of underground structure
CN118774441B (en) * 2024-07-29 2026-02-06 上海宝冶集团有限公司 Method for metallurgical technical improvement of factory building steel column penetrating multilayer floor slab under condition of wet soft foundation

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1279319A (en) * 1999-06-29 2001-01-10 陈星� Full-reverse construction technology for basement
JP2006083610A (en) * 2004-09-16 2006-03-30 Shimizu Corp Reverse strike method
CN101117805A (en) * 2007-08-22 2008-02-06 浙江大学 A method of multi-purpose semi-upside down method for one pile in underground engineering

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1279319A (en) * 1999-06-29 2001-01-10 陈星� Full-reverse construction technology for basement
JP2006083610A (en) * 2004-09-16 2006-03-30 Shimizu Corp Reverse strike method
CN101117805A (en) * 2007-08-22 2008-02-06 浙江大学 A method of multi-purpose semi-upside down method for one pile in underground engineering

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
厦门世侨中心地下室钢结构逆作法施工技术;唐香君 等;《施工技术》;20140710;第43卷(第13期);133-136页 *

Also Published As

Publication number Publication date
CN107542108A (en) 2018-01-05

Similar Documents

Publication Publication Date Title
CN107542108B (en) A reverse construction method of a building basement structure
CN100473790C (en) Tower crane foundation for construction and manufacturing method thereof
CN106958256A (en) A kind of placement layer by layer, the open caisson construction technique repeatedly sunk
CN101215834A (en) Construction Method of Outrigger Type Diaphragm Wall
CN103343544A (en) Construction method for large-scale open caisson
CN110117959B (en) Construction method for foundation pit support near river
CN113235601A (en) Deep foundation pit construction risk control structure and method for collapsible loess adjacent building
Paul et al. Comparative study of construction technologies for underground metro stations in India
CN110439590A (en) tunnel construction method
CN115897600A (en) A construction method for a new foundation pit adjacent to the deep foundation pit adjacent area of an existing subway station
CN106760620A (en) A kind of utilization open caisson increases the construction method for building the underground space under existing building
CN109706952A (en) Large-scale well-sinking construction method
CN105714769A (en) Construction method for anti-sliding cast-in-place pile
CN119412105A (en) A construction method for protecting intersecting shield sections
CN106065628B (en) Based on the major diameter running water pipe security protection construction method faced forever with reference to theory
CN114232602A (en) Underground continuous pile construction process
CN113898007B (en) Semi-inverse construction method for long-span corridor structure along street
CN113846695B (en) Reverse construction method basement construction method
CN115404885A (en) Gradual retaining construction method suitable for multi-step high and steep slopes
CN119754359A (en) A foundation structure replacement construction method for a shield tunnel passing through a pile foundation of an upper building
CN215906845U (en) Large-span vestibule mounting structure in foundation pit
CN111827705A (en) Method for expanding well barrel-shaped underground garage in existing underground garage
CN215211056U (en) Assembled multilayer inner supporting structure
CN116591205A (en) Method for quick construction of sump pit in foundation pit of subway entrance and exit in water-rich sand layer
CN116427416A (en) Construction method of deep foundation pit for seaside circulating water pump house

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191122