CN110344394A - A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method - Google Patents

A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method Download PDF

Info

Publication number
CN110344394A
CN110344394A CN201910547691.XA CN201910547691A CN110344394A CN 110344394 A CN110344394 A CN 110344394A CN 201910547691 A CN201910547691 A CN 201910547691A CN 110344394 A CN110344394 A CN 110344394A
Authority
CN
China
Prior art keywords
steel plate
slip casting
foundation
existing
reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910547691.XA
Other languages
Chinese (zh)
Inventor
宗朝阳
韩毓殷
周小亮
陈鹏
潘传宇
雷波
周旋
李淋淋
周坤
黄兴昌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Railway Investment Construction Group Co Ltd
Original Assignee
China State Railway Investment Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China State Railway Investment Construction Group Co Ltd filed Critical China State Railway Investment Construction Group Co Ltd
Priority to CN201910547691.XA priority Critical patent/CN110344394A/en
Publication of CN110344394A publication Critical patent/CN110344394A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本发明公开了一种深基坑周边浅埋构筑物基础加固结构及施工方法,包括抗倾覆板、注浆钢管、固定钢板,所述抗倾覆板由钢筋骨架和浇筑于既有基础四周的混凝土组成,注浆钢管沿既有基础四周梅花形布置并通过固定钢板进行固定后与抗倾覆板钢筋骨架连接在一起,其施工步骤为施工准备→注浆孔钻设→压浆→基坑开挖→钢筋骨架绑扎及固定钢板焊接→混凝土浇筑及养护,通过在既有基础四周打设注浆钢管注浆加固地基,随后将注浆钢管通过加固钢板固定于抗倾覆板主筋上,最后浇筑抗倾覆板混凝土,形成一个“桩承台”,可有效的解决既有基础处理时间长、加固效果不明显等问题,保证了扩大既有基础承载力及其稳定性,同时具有施工速度快、经济效益好等特点。

The invention discloses a foundation reinforcement structure and a construction method of a shallow buried structure around a deep foundation pit, comprising an anti-overturning plate, a grouted steel pipe, and a fixed steel plate. The anti-overturning plate is composed of a steel bar skeleton and concrete poured around the existing foundation , grouting steel pipes are arranged in a plum blossom shape around the existing foundation and are fixed by fixed steel plates and then connected with the steel skeleton of the anti-overturning plate. The construction steps are construction preparation → grouting hole drilling → grouting → foundation pit excavation → Reinforcement skeleton binding and fixed steel plate welding→concrete pouring and maintenance, the foundation is strengthened by laying grouted steel pipes around the existing foundation, and then the grouted steel pipes are fixed on the main reinforcement of the anti-overturning slab through the reinforcement steel plate, and finally the anti-overturning slab is poured Concrete forms a "pile cap", which can effectively solve the problems of long treatment time and inconspicuous reinforcement effect of the existing foundation, ensure the expansion of the bearing capacity and stability of the existing foundation, and at the same time have fast construction speed and good economic benefits Features.

Description

一种深基坑周边浅埋构筑物基础加固结构及施工方法A foundation reinforcement structure and construction method for shallow buried structures around deep foundation pits

技术领域technical field

本发明属于建筑工程地基基础加固施工技术领域,具体涉及一种深基坑周边浅埋构筑物基础加固结构,主要应用于深基坑周边浅埋构筑物基础加固,保证既有浅埋构筑物安全,同时还涉及深基坑周边浅埋构筑物基础加固结构的施工方法。The invention belongs to the technical field of construction engineering foundation reinforcement construction, and in particular relates to a foundation reinforcement structure for shallow-buried structures around deep foundation pits, which is mainly used for foundation reinforcement of shallow-buried structures around deep foundation pits to ensure the safety of existing shallow-buried structures and at the same time The invention relates to a construction method for reinforcing the foundation of shallow buried structures around deep foundation pits.

背景技术Background technique

随着城市化的发展,工程建设场地周边环境越来越复杂,深基坑开挖过程中不可避免的会对既有地层产生扰动,从而引起基坑变形及基坑周边土体位移,对周边建筑物安全造成影响,特别是基坑周边重要构建筑物,其对地基稳定性要求极为严苛,如不采取措施对其进行加固,基坑施工过程中一旦发生基坑变形超过允许范围,极易导致构筑物出现沉降或倾覆,造成极为恶劣的社会影响及不可挽回的经济损失。With the development of urbanization, the surrounding environment of the engineering construction site is becoming more and more complex. During the excavation of deep foundation pits, it is inevitable that the existing stratum will be disturbed, which will cause deformation of the foundation pit and displacement of the soil around the foundation pit. The safety of buildings is affected, especially the important structures around the foundation pit, which have extremely strict requirements on the stability of the foundation. If no measures are taken to reinforce it, once the deformation of the foundation pit exceeds the allowable range during the construction of the foundation pit, it will be very serious. It is easy to cause the structure to sink or overturn, causing extremely bad social impact and irreparable economic loss.

对于深基坑周边的构筑物,一般采取迁改或注浆加固来降低施工风险:采用迁改方式时,需进行层层报批、既有构筑物拆除、新建构筑物施工等程序,流程较长且不可控,工期延误风险较大;采用注浆加固方式时,只能对构筑物周边土体进行加固,无法对构筑物基础下方土体进行有效加固,加固效果不明显。因此,为降低深基坑周边构筑物在开挖过程中的安全风险,研究和掌握切可行的深基坑周边构筑物浅埋基础加固技术尤为重要。For structures around deep foundation pits, relocation or grouting reinforcement is generally adopted to reduce construction risks: when relocation is adopted, procedures such as approval layer by layer, demolition of existing structures, and construction of new structures are required, and the process is long and uncontrollable , the risk of delay in the construction period is greater; when the grouting reinforcement method is used, only the soil around the structure can be reinforced, and the soil below the foundation of the structure cannot be effectively reinforced, and the reinforcement effect is not obvious. Therefore, in order to reduce the safety risk of structures around deep foundation pits during the excavation process, it is particularly important to study and master feasible shallow-buried foundation reinforcement technologies for structures around deep foundation pits.

发明内容Contents of the invention

本发明的第一个目的在于提供一种结构简单、施工方便、对既有浅基础构筑物影响小,加固效果好的深基坑周边浅埋构筑物基础加固结构。The first object of the present invention is to provide a foundation reinforcement structure for shallow buried structures around deep foundation pits with simple structure, convenient construction, little impact on existing shallow foundation structures, and good reinforcement effect.

本发明的第一个目的通过以下的技术措施来实现:一种深基坑周边浅埋构筑物基础加固结构,包括沿既有基础外沿向外依次设置的固定钢板、注浆钢管以及抗倾覆板,所述抗倾覆板包括钢筋骨架及浇筑于既有基础四周的混凝土,所述固定钢板呈方形设置于既有基础外部并位于浇筑的混凝土内,所述固定钢板上设有根据注浆钢管布置位置预留孔洞,所述注浆钢管沿既有基础四周环向布置,布置数量不少于2环,相邻2环注浆钢管呈梅花形交错布置,同一环注浆钢管尾端穿过固定钢板预留孔洞与固定钢板焊接固定在一起。The first object of the present invention is achieved through the following technical measures: a foundation reinforcement structure for shallow buried structures around deep foundation pits, including fixed steel plates, grouted steel pipes and anti-overturning plates arranged in sequence along the outer edge of the existing foundation , the anti-overturning plate includes a steel skeleton and concrete poured around the existing foundation. Holes are reserved in the position, the grouted steel pipes are arranged circumferentially along the existing foundation, and the number of layouts is not less than 2 rings. The holes reserved in the steel plate are welded and fixed together with the fixed steel plate.

作为改进,所述钢筋骨架为双层钢筋网,所述钢筋骨架与既有基础采用植筋的方式进行连接。As an improvement, the steel frame is a double-layer steel mesh, and the steel frame is connected to the existing foundation by planting bars.

作为改进,所述注浆钢管前端设有的锥头,尾端设有止浆段,中间部分设有等距间隔设置的溢浆孔。As an improvement, the front end of the grouting steel pipe is provided with a cone head, the tail end is provided with a grout stop section, and the middle part is provided with grout overflow holes arranged at equidistant intervals.

作为改进,所述锥头的度不小于10cm,所述止浆段的长度不小于1.5m,所述溢浆孔的间距为15cm,所述溢浆孔呈梅花形布置且孔径为10~16mm。As an improvement, the thickness of the cone head is not less than 10cm, the length of the slurry stop section is not less than 1.5m, the distance between the overflow holes is 15cm, and the overflow holes are arranged in a quincunx shape with a diameter of 10-16mm .

作为改进,所述固定钢板将注浆钢管连接成一整体,并与钢筋骨架焊接固定牢固,所述固定钢板包括第一层固定钢板、第二层固定钢板,所述第一层固定钢板、第二层固定钢板分别位于钢筋骨架的上方及下方。As an improvement, the fixed steel plate connects the grouted steel pipes into a whole, and is welded and fixed firmly with the steel skeleton. The fixed steel plate includes a first fixed steel plate and a second fixed steel plate. The first fixed steel plate, the second fixed steel plate Layer-fixed steel plates are respectively located above and below the reinforcement skeleton.

作为改进,所述固定钢板由1cm钢板制作而成,所述固定钢板宽度为注浆钢管直径的3倍。As an improvement, the fixed steel plate is made of a 1 cm steel plate, and the width of the fixed steel plate is three times the diameter of the grouted steel pipe.

作为改进,所述固定钢板沿既有基础向外设置有两个。As an improvement, two fixed steel plates are arranged outwards along the existing foundation.

作为改进,其施工方法,其特征包含以下步骤:As an improvement, its construction method is characterized by the following steps:

步骤一:施工准备Step 1: Construction preparation

组织现场调查,对拟加固既有基础周边管线情况进行全方位摸排,探明地下管线位置;进行场地平整及人、机、材准备。Organize on-site investigations, conduct an all-round survey of the surrounding pipelines of the existing foundation to be reinforced, find out the location of underground pipelines; carry out site leveling and preparation of manpower, machinery and materials.

步骤二:注浆孔钻设Step 2: Drilling the grouting hole

基础加固范围为3~5倍既有基础宽度,注浆孔沿既有基础四周双排梅花形布置,孔距1.3m×1.3m,内排注浆孔距既有基础外侧间距不小于1m;注浆孔直径比注浆钢管直径大5~10mm,孔深按照10m与进入岩层不小于2m双控,注浆钢管顶标高与所加固的构筑物既有基础顶面标高相同,注浆孔孔位纵横误差不得超过±50mm,垂直度允许误差不应超过3‰,清孔后沉渣厚度不大于50mm。The scope of foundation reinforcement is 3 to 5 times the width of the existing foundation. The grouting holes are arranged in double rows along the perimeter of the existing foundation in a plum blossom shape, with a hole spacing of 1.3m×1.3m, and the distance between the inner row of grouting holes and the outer side of the existing foundation is not less than 1m; The diameter of the grouting hole is 5-10mm larger than the diameter of the grouting steel pipe, and the hole depth is double-controlled by 10m and entering the rock formation not less than 2m. The top elevation of the grouting steel pipe is the same as that of the existing foundation top surface of the reinforced structure. The vertical and horizontal error shall not exceed ±50mm, the allowable error of verticality shall not exceed 3‰, and the thickness of the sediment after cleaning the hole shall not exceed 50mm.

步骤三:压浆Step 3: Grouting

注浆钢管1注浆采用M30水泥浆液,水灰比一般为0.5~1(按注浆试验进行确定),并掺入适量缓凝剂,水泥采用P.O.42.5普通硅酸盐水泥,拌和水采用饮用水;采用压浆泵进行压浆,压浆结束时用浓浆封孔,控制灌浆压力在0.2~0.5MPa左右。Grouting steel pipe 1 uses M30 cement slurry for grouting, the water-cement ratio is generally 0.5-1 (determined according to the grouting test), and an appropriate amount of retarder is added. The cement is P.O.42.5 ordinary Portland cement, and the mixing water is drinking water. Water; the grouting pump is used for grouting, and the hole is sealed with thick grout at the end of grouting, and the grouting pressure is controlled at about 0.2-0.5MPa.

步骤四:基坑开挖Step 4: Excavation of foundation pit

采用挖掘机对需加固的构筑物既有基础周边土方进行开挖,开挖坡度1:1.5,开挖深度0.5~1.0m,基坑开挖线301附近10cm土体采用人工清底,靠近基础50cm范围内采用人工开挖,开挖时需注意加强对注浆钢管的保护,避免造成注浆钢管折断、破损。Use an excavator to excavate the earth around the existing foundation of the structure that needs to be reinforced. The excavation slope is 1:1.5, and the excavation depth is 0.5-1.0m. Manual excavation is adopted within the scope, and attention should be paid to strengthening the protection of the grouted steel pipe during excavation to avoid breaking and damage to the grouted steel pipe.

步骤五:钢筋骨架绑扎及固定钢板焊接Step 5: Binding of reinforcement skeleton and welding of fixed steel plate

对构筑物既有基础表面凿面轻锤、凿毛,并清理干净既有基础表面的松散颗粒及浮渣尘土,根据钢筋骨架的位置在既有基础上打设植筋孔;将第一层固定钢板穿入注浆钢管并焊接固定,开始钢筋骨架绑扎,钢筋骨架绑扎完成后穿入第二层固定钢板,将并将固定钢板与钢筋骨架接触部位进行双面满焊连接。Lightly hammer and chisel the surface of the existing foundation of the structure, and clean up the loose particles and scum and dust on the surface of the existing foundation, and set reinforcement holes on the existing foundation according to the position of the steel skeleton; fix the first layer The steel plate is penetrated into the grouted steel pipe and welded and fixed, and the steel frame binding is started. After the steel frame binding is completed, the second layer of fixed steel plate is penetrated, and the contact part of the fixed steel plate and the steel frame is connected by double-sided full welding.

步骤六:混凝土浇筑及养护Step 6: Concrete pouring and maintenance

根据抗倾覆板尺寸进行模板安装并在既有基础于抗倾覆板接触位置涂刷界面剂进行处理,随后进行抗倾覆板混凝土浇筑;混凝土浇筑后,在常温条件下12h内应覆盖浇水养护,浇水次数以保持混凝土湿润为宜,养护时间不少于七昼夜。Install the formwork according to the size of the anti-overturning slab and apply an interface agent on the existing foundation at the contact position of the anti-overturning slab for treatment, and then pour the anti-overturning slab concrete; after the concrete is poured, it should be covered and cured within 12 hours under normal temperature conditions. The frequency of watering is appropriate to keep the concrete moist, and the curing time is not less than seven days and nights.

与现有技术相比,本发明具有如下优点:Compared with prior art, the present invention has following advantage:

(1)通过注浆钢管注浆加固现有地基,同时注浆钢管与抗倾覆板整体形成了一个“桩承台”,有效的增加了既有基础的承载力及稳定性,加固效果好。(1) The existing foundation is reinforced by grouting steel pipes. At the same time, the grouting steel pipes and the anti-overturning plate form a "pile cap" as a whole, which effectively increases the bearing capacity and stability of the existing foundation, and the reinforcement effect is good.

(2)本发明施工工艺较简单,可避免既有构筑物迁改所带来的相关问题,施工速度快、效率高。(2) The construction process of the present invention is relatively simple, which can avoid related problems caused by the relocation and modification of existing structures, and has high construction speed and high efficiency.

(3)本发明对基坑周边构筑物基础进行原地加固,投入的机械、材料等资源较少,与构筑物迁改相比,无需拆除及新建,施工费用降低明显,经济效益良好。(3) The present invention reinforces the foundation of the structures around the foundation pit in situ, and requires less resources such as machinery and materials. Compared with the relocation of structures, it does not need to be demolished and newly built, the construction cost is significantly reduced, and the economic benefits are good.

附图说明Description of drawings

图1是本发明一种深基坑周边浅埋构筑物基础加固结构及施工方法的注浆钢管示意图。Fig. 1 is a schematic diagram of a grouted steel pipe for the foundation reinforcement structure and construction method of a shallow buried structure around a deep foundation pit according to the present invention.

图2是本发明一种深基坑周边浅埋构筑物基础加固结构及施工方法的注浆钢管平面布置示意图。Fig. 2 is a schematic plan layout diagram of a grouted steel pipe for the foundation reinforcement structure and construction method of a shallow buried structure around a deep foundation pit according to the present invention.

图3是本发明一种深基坑周边浅埋构筑物基础加固结构及施工方法的基坑开挖剖面示意图。Fig. 3 is a schematic diagram of a excavation section of a foundation pit excavation of a shallow buried structure foundation reinforcement structure and construction method around a deep foundation pit according to the present invention.

图4是本发明一种深基坑周边浅埋构筑物基础加固结构及施工方法的钢筋骨架与固定钢板连接平面示意图。Fig. 4 is a schematic diagram of the connection plane between the steel skeleton and the fixed steel plate of a foundation reinforcement structure and construction method of a shallow buried structure around a deep foundation pit according to the present invention.

图5是本发明一种深基坑周边浅埋构筑物基础加固结构及施工方法的钢筋骨架与固定钢板连接剖面示意图。Fig. 5 is a schematic cross-sectional view of the connection between the steel skeleton and the fixed steel plate of a foundation reinforcement structure and construction method of a shallow buried structure around a deep foundation pit according to the present invention.

图6是本发明一种深基坑周边浅埋构筑物基础加固结构及施工方法的加固整体剖面示意图。Fig. 6 is a schematic cross-sectional view of a reinforcement structure and a construction method for a shallow buried structure around a deep foundation pit according to the present invention.

附图标记:1、注浆钢管,101、锥头,102、止浆段,103、溢浆孔,2、固定钢板,201、第一层固定钢板,202、第二层固定钢板,3、抗倾覆板,301、基坑开挖线,302、钢筋骨架,4、既有基础。Reference signs: 1, grouting steel pipe, 101, cone head, 102, slurry stop section, 103, overflow hole, 2, fixed steel plate, 201, first layer of fixed steel plate, 202, second layer of fixed steel plate, 3, Anti-overturning board, 301, foundation pit excavation line, 302, steel skeleton, 4, existing foundation.

具体实施方式Detailed ways

为了更好的理解本发明的技术方案,下面结合实施例附图对本发明进一步详细说明。应当理解,此处所描述的具体实施例仅用以解释本发明,并不用于限定本发明。In order to better understand the technical solution of the present invention, the present invention will be further described in detail below in conjunction with the accompanying drawings of the embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.

一种深基坑周边浅埋构筑物基础加固结构,其特征在于:包括沿既有基础4外沿向外依次设置的固定钢板2、注浆钢管1以及抗倾覆板3,所述抗倾覆板3包括钢筋骨架302及浇筑于既有基础4四周的混凝土,所述固定钢板2呈方形设置于既有基础4外部并位于浇筑的混凝土内,所述固定钢板2上设有根据注浆钢管1布置位置预留孔洞,所述注浆钢管(1)沿既有基础(4)四周环向布置,布置数量不少于2环,相邻2环注浆钢管(1)呈梅花形交错布置,同一环注浆钢管(1)尾端穿过固定钢板(2)预留孔洞与固定钢板(2)焊接固定在一起。A foundation reinforcement structure for shallow buried structures around deep foundation pits, characterized in that it includes fixed steel plates 2, grouted steel pipes 1, and anti-overturning plates 3 arranged in sequence along the outer edge of the existing foundation 4, and the anti-overturning plates 3 Including the steel skeleton 302 and the concrete poured around the existing foundation 4, the fixed steel plate 2 is arranged outside the existing foundation 4 in a square shape and is located in the poured concrete, and the fixed steel plate 2 is arranged according to the arrangement of the grouted steel pipe 1. Holes are reserved in the position, the grouting steel pipes (1) are arranged circumferentially along the existing foundation (4), and the number of layouts is not less than 2 rings. The tail end of the ring grouting steel pipe (1) passes through the reserved hole of the fixed steel plate (2) and is welded and fixed together with the fixed steel plate (2).

作为本实施例较佳实施方式的是,所述钢筋骨架302为双层钢筋网,所述钢筋骨架302与既有基础4采用植筋的方式进行连接。As a preferred implementation manner of this embodiment, the reinforcement frame 302 is a double-layer reinforcement mesh, and the reinforcement frame 302 is connected to the existing foundation 4 by planting bars.

作为本实施例较佳实施方式的是,所述注浆钢管1前端设有的锥头101,尾端设有止浆段102,中间部分设有等距间隔设置的溢浆孔103。As a preferred implementation of this embodiment, the grouting steel pipe 1 is provided with a conical head 101 at the front end, a grout stop section 102 at the rear end, and grout overflow holes 103 arranged at equal intervals in the middle part.

作为本实施例较佳实施方式的是,所述锥头101的度不小于10cm,所述止浆段102的长度不小于1.5m,所述溢浆孔103的间距为15cm,所述溢浆孔103呈梅花形布置且孔径为10~16mm。As a preferred implementation mode of this embodiment, the degree of the cone head 101 is not less than 10cm, the length of the slurry stop section 102 is not less than 1.5m, the distance between the slurry overflow holes 103 is 15cm, and the slurry overflow The holes 103 are arranged in a quincunx shape with a diameter of 10-16 mm.

作为本实施例较佳实施方式的是,所述固定钢板2将注浆钢管1连接成一整体,并与钢筋骨架302焊接固定牢固,所述固定钢板2包括第一层固定钢板201、第二层固定钢板202,所述第一层固定钢板201、第二层固定钢板202分别位于钢筋骨架302的上方及下方。As a preferred implementation of this embodiment, the fixed steel plate 2 connects the grouted steel pipe 1 as a whole, and is welded and fixed firmly with the reinforcement frame 302. The fixed steel plate 2 includes a first layer of fixed steel plate 201, a second layer of The fixed steel plates 202, the first layer of fixed steel plates 201 and the second layer of fixed steel plates 202 are respectively located above and below the reinforcement frame 302.

作为本实施例较佳实施方式的是,所述固定钢板2由1cm钢板制作而成,所述固定钢板2宽度约为注浆钢管1直径的3倍。As a preferred implementation of this embodiment, the fixed steel plate 2 is made of a 1 cm steel plate, and the width of the fixed steel plate 2 is about three times the diameter of the grouted steel pipe 1 .

一种深基坑周边浅埋构筑物基础加固结构施工方法,其特征包含以下步骤:A construction method for reinforcing the foundation of a shallow buried structure around a deep foundation pit, characterized by comprising the following steps:

步骤一:施工准备Step 1: Construction preparation

组织现场调查,对拟加固既有基础4周边管线情况进行全方位摸排,探明地下管线位置;进行场地平整及人、机、材准备。Organize on-site investigations, conduct an all-round survey of the surrounding pipelines of the existing foundation 4 to be reinforced, find out the location of underground pipelines; carry out site leveling and preparation of manpower, machinery and materials.

步骤二:注浆孔钻设Step 2: Drilling the grouting hole

基础加固范围为3~5倍既有基础4宽度,注浆孔沿既有基础4四周双排梅花形布置,孔距1.3m×1.3m,内排注浆孔距既有基础4外侧间距不小于1m;注浆孔直径比注浆钢管1直径大5~10mm,孔深按照10m与进入岩层不小于2m双控,注浆钢管1顶标高与所加固的构筑物既有基础4顶面标高相同,注浆孔孔位纵横误差不得超过±50mm,垂直度允许误差不应超过3‰,清孔后沉渣厚度不大于50mm。The scope of foundation reinforcement is 3 to 5 times the width of the existing foundation 4. The grouting holes are arranged in double rows along the perimeter of the existing foundation 4 in a quincunx shape. The distance between the holes is 1.3m×1.3m. Less than 1m; the diameter of the grouting hole is 5-10mm larger than the diameter of the grouting steel pipe 1, and the hole depth is double-controlled according to 10m and the entry rock formation is not less than 2m. The elevation of the top of the grouting steel pipe 1 is the same as that of the existing foundation 4 of the reinforced structure , The vertical and horizontal error of the grouting hole position shall not exceed ±50mm, the allowable error of the verticality shall not exceed 3‰, and the thickness of the sediment after cleaning the hole shall not exceed 50mm.

步骤三:压浆Step 3: Grouting

注浆钢管1注浆采用M30水泥浆液,水灰比一般为0.5~1(按注浆试验进行确定),并掺入适量缓凝剂,水泥采用P.O.42.5普通硅酸盐水泥,拌和水采用饮用水;采用压浆泵进行压浆,压浆结束时用浓浆封孔,控制灌浆压力在0.2~0.5MPa左右。Grouting steel pipe 1 uses M30 cement slurry for grouting, the water-cement ratio is generally 0.5-1 (determined according to the grouting test), and an appropriate amount of retarder is added. The cement is P.O.42.5 ordinary Portland cement, and the mixing water is drinking water. Water; the grouting pump is used for grouting, and the hole is sealed with thick grout at the end of grouting, and the grouting pressure is controlled at about 0.2-0.5MPa.

步骤四:基坑开挖Step 4: Excavation of foundation pit

采用挖掘机对需加固的构筑物既有基础4周边土方进行开挖,开挖坡度1:1.5,开挖深度0.5~1.0m,基坑开挖线301附近10cm土体采用人工清底,靠近基础50cm范围内采用人工开挖,开挖时需注意加强对注浆钢管1的保护,避免造成注浆钢管1折断、破损。Use an excavator to excavate the earth around the existing foundation 4 of the structure to be reinforced. The excavation slope is 1:1.5, and the excavation depth is 0.5-1.0m. Manual excavation is adopted within a range of 50 cm. During excavation, attention should be paid to strengthening the protection of the grouted steel pipe 1 to avoid breaking and damage to the grouted steel pipe 1.

步骤五:钢筋骨架302绑扎及固定钢板2焊接Step 5: Binding of reinforcement frame 302 and welding of fixed steel plate 2

对构筑物既有基础4表面凿面轻锤、凿毛,并清理干净既有基础4表面的松散颗粒及浮渣尘土,根据钢筋骨架1的位置在既有基础4上打设植筋孔;将第一层固定钢板201穿入注浆钢管并焊接固定,开始钢筋骨架302绑扎,钢筋骨架302绑扎完成后穿入第二层固定钢板202,将并将固定钢板2与钢筋骨架302接触部位进行双面满焊连接。Lightly hammer and chisel the surface of the existing foundation 4 of the structure, and clean up the loose particles and scum and dust on the surface of the existing foundation 4, and set reinforcement holes on the existing foundation 4 according to the position of the steel skeleton 1; The first layer of fixed steel plate 201 is penetrated into the grouted steel pipe and welded and fixed, and the reinforcement frame 302 is bound. Full face solder connection.

步骤六:混凝土浇筑及养护Step 6: Concrete pouring and maintenance

根据抗倾覆板3尺寸进行模板安装并在既有基础4于抗倾覆板3接触位置涂刷界面剂进行处理,随后进行抗倾覆板3混凝土浇筑;混凝土浇筑后,在常温条件下12h内应覆盖浇水养护,浇水次数以保持混凝土湿润为宜,养护时间不少于七昼夜。Install the formwork according to the size of the anti-overturning slab 3 and apply an interface agent on the contact position of the existing foundation 4 to the anti-overturning slab 3 for treatment, and then pour the concrete for the anti-overturning slab 3; after the concrete is poured, it should be covered and poured within 12 hours under normal temperature conditions For water curing, the frequency of watering should be to keep the concrete moist, and the curing time should not be less than seven days and nights.

本发明的上述实施例仅仅是为清楚地说明本发明所作的举例,而并非是对本发明的实施方式的限定,对于所属领域的普通技术人员来说,在上述说明的基础上还可以做出其它不同形式的变化或变动,这里无法对所有的实施方式予以穷举,凡是属于本发明的技术方案所引伸出的显而易见的变化或变动仍处于本发明的保护范围之列。The above-mentioned embodiments of the present invention are only examples for clearly illustrating the present invention, rather than limiting the implementation of the present invention. For those of ordinary skill in the art, on the basis of the above description, other Variations or changes in different forms cannot be exhaustively listed here, and any obvious changes or changes derived from the technical solutions of the present invention are still within the scope of protection of the present invention.

Claims (7)

1. a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction, it is characterised in that: including along existing basic (4) outer to Fixation steel plate (2), slip casting steel pipe (1) and the antidumping plate (3) set gradually outside, the antidumping plate (3) includes reinforcing bar It frame (302) and pours in the concrete of existing basic (4) surrounding, the fixation steel plate (2), which is square, is set to existing basic (4) Outside is simultaneously located in the concrete poured, and the fixation steel plate (2) is equipped with according to slip casting steel pipe (1) position preformed hole Hole, the slip casting steel pipe (1) is circumferentially disposed along existing basic (4) surrounding, and arrangement quantity is no less than 2 rings, adjacent 2 ring slip casting steel pipe It (1) is in quincunx interlaced arrangement, same ring slip casting steel pipe (1) tail end passes through fixation steel plate (2) reserving hole and fixation steel plate (2) It is welded and fixed together.
2. a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction according to claim 1, it is characterised in that: described Framework of steel reinforcement (302) is double layer bar, and the framework of steel reinforcement (302) is connected by the way of bar planting with existing basic (4) It connects.
3. a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction according to claim 1, it is characterised in that: described The conehead (101) that slip casting steel pipe (1) front end is equipped with, tail end are equipped with only slurry section (102), and middle section is equipped with equidistant interval setting Extravasating hole (103).
4. a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction according to claim 3, it is characterised in that: described The degree of conehead (101) is not less than 10cm, and the length of only slurry section (102) is not less than 1.5m, the spacing of the extravasating hole (103) For 15cm, the extravasating hole (103) is 10~16mm in quincuncial arrangement and aperture.
5. a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction according to claim 1, it is characterised in that: described Fixation steel plate (2) is integral by slip casting steel pipe (1) connection, and is welded and fixed securely with framework of steel reinforcement (302), the fixed steel Plate (2) includes first layer fixation steel plate (201), second layer fixation steel plate (202), the first layer fixation steel plate (201), second Layer fixation steel plate (202) is located at the over and under of framework of steel reinforcement (302).
6. a kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction according to claim 5, it is characterised in that: described Fixation steel plate (2) is made by 1cm steel plate, and fixation steel plate (2) width is 3 times of 1 diameter of slip casting steel pipe.
7. a kind of construction method of above-mentioned surrounding deep foundation pit shallow embedding structure base ruggedized construction, feature comprise the steps of:
Step 1: preparation of construction
Field investigation is organized, basic (4) periphery line conditions progress existing to quasi- reinforcing is comprehensive to sound out the people in a given scope one by one in order to break a criminal case, and verifies underground utilities position It sets;Carry out levelling of the land and people, machine, material preparation.
Step 2: injected hole is drilled with
Strengthening of foundation range is 3~5 times of existing basic (4) width, and injected hole is along the double quincunx cloth of existing basic (4) surrounding It sets, pitch-row 1.3m × 1.3m, interior row's injected hole is not less than 1m away from spacing on the outside of existing basic (4);Slip casting bore dia is than slip casting steel Manage the big 5~10mm of (1) diameter, hole depth according to 10m and enter rock stratum be not less than 2m dual control, slip casting steel pipe (1) top mark height with it is added Solid existing basic (4) top surface absolute altitude of structures it is identical, error must not exceed ± 50mm to injected hole hole location in length and breadth, and verticality allows Error is not to be exceeded 3 ‰, and sediment thickness is not more than 50mm after borehole cleaning.
Step 3: mud jacking
(1) slip casting of slip casting steel pipe uses M30 cement grout, and the ratio of mud is generally 0.5~1 (being determined by grouting test), and Appropriate retarder is mixed, cement uses P.O.42.5 ordinary portland cement, and mixing water uses drinking water;It is carried out using mudjack Mud jacking uses underflow sealing of hole at the end of mud jacking, and controlled grouting pressure is in 0.2~0.5MPa or so.
Step 4: excavation of foundation pit
It is excavated using excavator basic (4) periphery cubic metre of earth existing to the structures that need to be reinforced, excavates gradient 1:1.5, excavate 0.5~1.0m of depth, nearby the 10cm soil body is used within the scope of the 50cm of basis excavation of foundation pit line (301) using artificial clear bottom Hand excavation, when excavation, should be noted the protection reinforced to slip casting steel pipe 1, avoid slip casting steel pipe 1 and fracture, is damaged.
Step 5: framework of steel reinforcement (302) binding and fixation steel plate (2) welding
It is existing to structures basis (4) surface chisel face gently hammer, dabbing, and clean out it is existing basis (4) surface discrete particles And dross dust, bar planting hole is set on existing basic (4) according to the position of framework of steel reinforcement (1);By first layer fixation steel plate (201) it penetrates slip casting steel pipe and is welded and fixed, start framework of steel reinforcement (302) binding, penetrated after the completion of framework of steel reinforcement (302) binding Fixation steel plate (2) will and be carried out two-sided be fully welded with framework of steel reinforcement (302) contact site and connect by second layer fixation steel plate (202).
Step 6: concreting and maintenance
Template installation is carried out and in existing basic (4) in antidumping plate (3) contact position brushing circle according to antidumping plate (3) size Face agent is handled, and antidumping plate (3) concreting is then carried out;After concreting, it should be covered in 12h under normal temperature conditions Lid water seasoning, for irrigation times to keep concrete is wet to be advisable, curing time is no less than sennight.
CN201910547691.XA 2019-06-24 2019-06-24 A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method Pending CN110344394A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910547691.XA CN110344394A (en) 2019-06-24 2019-06-24 A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910547691.XA CN110344394A (en) 2019-06-24 2019-06-24 A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method

Publications (1)

Publication Number Publication Date
CN110344394A true CN110344394A (en) 2019-10-18

Family

ID=68182838

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910547691.XA Pending CN110344394A (en) 2019-06-24 2019-06-24 A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method

Country Status (1)

Country Link
CN (1) CN110344394A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110761288A (en) * 2019-10-30 2020-02-07 中国铁建重工集团股份有限公司 Concrete pouring method for deep foundation pit
CN114232598A (en) * 2021-11-23 2022-03-25 广州市市政工程机械施工有限公司 Grouting isolation wall for protecting existing building/structure foundation
CN116263050A (en) * 2022-09-16 2023-06-16 中建八局发展建设有限公司 A Supporting Method for Confined Space with Complicated Geological Conditions
CN116752590A (en) * 2023-06-21 2023-09-15 中建交通建设集团有限公司 Enlarged reinforcement structure and reinforcement method of platform
CN116791694A (en) * 2023-07-19 2023-09-22 中铁隧道局集团建设有限公司 Construction method for tunneling existing bridge pile foundation

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201567574U (en) * 2010-01-07 2010-09-01 贵州省交通规划勘察设计研究院 Slope Reinforcement and Fixing Structure of Prestressed Anchor Pier
CN106499413A (en) * 2016-11-19 2017-03-15 中铁十二局集团有限公司 A kind of Shallow-buried section tunnel stratum consolidation construction method
CN108914927A (en) * 2018-07-30 2018-11-30 中铁二十三局集团有限公司 The miniature steel pipe pile reinforced construction method of existing line base insuring highway' slope
CN109208627A (en) * 2018-09-11 2019-01-15 中建五局土木工程有限公司 Structure and its construction method are protected in high-rise structures strengthening of foundation
CN210827422U (en) * 2019-06-24 2020-06-23 中建铁路投资建设集团有限公司 Peripheral shallow structure foundation reinforced structure that buries of deep basal pit

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201567574U (en) * 2010-01-07 2010-09-01 贵州省交通规划勘察设计研究院 Slope Reinforcement and Fixing Structure of Prestressed Anchor Pier
CN106499413A (en) * 2016-11-19 2017-03-15 中铁十二局集团有限公司 A kind of Shallow-buried section tunnel stratum consolidation construction method
CN108914927A (en) * 2018-07-30 2018-11-30 中铁二十三局集团有限公司 The miniature steel pipe pile reinforced construction method of existing line base insuring highway' slope
CN109208627A (en) * 2018-09-11 2019-01-15 中建五局土木工程有限公司 Structure and its construction method are protected in high-rise structures strengthening of foundation
CN210827422U (en) * 2019-06-24 2020-06-23 中建铁路投资建设集团有限公司 Peripheral shallow structure foundation reinforced structure that buries of deep basal pit

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110761288A (en) * 2019-10-30 2020-02-07 中国铁建重工集团股份有限公司 Concrete pouring method for deep foundation pit
CN110761288B (en) * 2019-10-30 2021-09-10 中国铁建重工集团股份有限公司 Concrete pouring method for deep foundation pit
CN114232598A (en) * 2021-11-23 2022-03-25 广州市市政工程机械施工有限公司 Grouting isolation wall for protecting existing building/structure foundation
CN116263050A (en) * 2022-09-16 2023-06-16 中建八局发展建设有限公司 A Supporting Method for Confined Space with Complicated Geological Conditions
CN116752590A (en) * 2023-06-21 2023-09-15 中建交通建设集团有限公司 Enlarged reinforcement structure and reinforcement method of platform
CN116791694A (en) * 2023-07-19 2023-09-22 中铁隧道局集团建设有限公司 Construction method for tunneling existing bridge pile foundation

Similar Documents

Publication Publication Date Title
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN106958256B (en) A caisson construction technology with layered pouring and multiple subsidence
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN106499413B (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
CN108442382A (en) It crosses the pressure line in-situ conservation of deep basal pit and goes along with sb. to guard him soil-baffling structure and construction method
CN105804089B (en) Locally increase deep support system and its construction method after a kind of former deep foundation pit construction
CN105756091B (en) A Construction Method of Subway Station Foundation Pit Controlling the Deformation of Adjacent Buildings
CN103321246B (en) Construction Method of Foundation Pit Using Underground Diaphragm Wall
CN207003499U (en) A kind of anti-floating lifting device of underground tunnel upper excavation of foundation pit
CN207892653U (en) Decompression hydrophobic structure suitable for Weathering-residual soil layer fissure zone
CN104099946B (en) Inspection-pit between a kind of Novel top pipeline section
CN105464074B (en) High polymer grouting protective structure of manual digging pile and its construction method
CN108797641A (en) A kind of structure and its construction method of Underground Subway Station construction period full station sealing
CN104196014A (en) Combined rock-embedded anchor cable slide-resistant pile where round steel is implanted and construction method thereof
CN110158630A (en) A kind of deep covering layer area large-span arch bridge annular ground continuous wall base
CN109706952A (en) Large-scale well-sinking construction method
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN206736963U (en) Ditch millet section high water level district lid tunnel stagnant water structure
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN104264683A (en) Concave ultra-deep foundation pit zoned supporting method for three-side surrounded cultural protection building
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN219158994U (en) A foundation pit support structure for ultra-deep and large-diameter circular pipe-jacking wells in deep soft soil areas
CN105386610A (en) Protective construction method for natural-foundation ancient architectures at top of asymmetric deep foundation pit
CN112144559A (en) Well construction method in high water-rich loess sandy gravel stratum transformer tube well
CN114575355B (en) Soil protection construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191018