CN201567574U - Prestressed anchorage anchor pier slope reinforcing and fixing structure - Google Patents

Prestressed anchorage anchor pier slope reinforcing and fixing structure Download PDF

Info

Publication number
CN201567574U
CN201567574U CN2010203002398U CN201020300239U CN201567574U CN 201567574 U CN201567574 U CN 201567574U CN 2010203002398 U CN2010203002398 U CN 2010203002398U CN 201020300239 U CN201020300239 U CN 201020300239U CN 201567574 U CN201567574 U CN 201567574U
Authority
CN
China
Prior art keywords
anchor pier
anchor
floral tube
pier
prestressed anchorage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2010203002398U
Other languages
Chinese (zh)
Inventor
谭捍华
罗强
许湘华
贾龙
凌桂香
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Transportation Planning Survey and Design Academe Co Ltd
Original Assignee
GUIZHOU COMMUNICATION PLANNING AND PROSPECTING DESIGN ACADEMY
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUIZHOU COMMUNICATION PLANNING AND PROSPECTING DESIGN ACADEMY filed Critical GUIZHOU COMMUNICATION PLANNING AND PROSPECTING DESIGN ACADEMY
Priority to CN2010203002398U priority Critical patent/CN201567574U/en
Application granted granted Critical
Publication of CN201567574U publication Critical patent/CN201567574U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a prestressed anchorage anchor pier slope reinforcing and fixing structure, which comprises an anchor pier (1) connected with an anchor cable (4), and is characterized in that: a grouting perforated pipe (2) is arranged below the anchor pier (1), and the exposed part of the perforated pipe (2) is inserted in the anchor pier (1) and is fixedly connected with reinforcing steel bars of the anchor pier (1); and the anchor pier (1) and the perforated pipe (2) are fixed by concrete pouring. The grouting perforated pipe is inserted in the foundation below the prestressed anchorage anchor pier, the properties of rock-soil mass of the anchor pier foundation can be improved by pressure grouting, and the perforated pipe is inserted in the rock-soil mass, thereby greatly improving the bearing capacity of the foundation rock-soil mass. In the process of calculation of the prestressed anchorage anchor pier design, when the same prestressing force is designed, the size of the cross section of the prestressed anchorage anchor pier can be improved because the bearing capacity of the foundation improves, thereby reducing the consumption of prestressed anchorage anchor pier reinforced concrete, and saving construction time limit and investment.

Description

Domatic reinforcing of prestress anchoraging anchor pier and fixed structure
Technical field
The utility model relates to domatic reinforcing of a kind of prestress anchoraging anchor pier and fixed structure, belongs to domatic fixing, reinforcing technique field.
Background technology
Prestress anchoraging is numerous industries such as water conservancy, railway, mine, highway and city-building be used for coming down effective means of regulation, slope reinforcement, deep foundation pit support, structure overturning or slip resistance analysis, underground engineering wall rock reinforcing, abutment reinforcing etc.According to the difference of primary structure member, can be divided into anchor pole and anchor cable, in the prestress anchoraging engineering, main application is anchor cable at present.
Prestress anchorage cable mainly is made of anchoring section, free section and fastener head three parts, and fastener head is made up of outer anchor structure thing, billet and ground tackle.Anchor pier is a kind of of outer anchor structure thing, adopts reinforced concrete structure, and prestress anchorage cable (as shown in Figure 2) is set in the middle of anchor pier.
When on loose geotechnical body side slope, carrying out the large-tonnage prestressed anchor reinforcement, domatic geotechnical body bearing capacity deficiency, apply in the prestressing force process or after applying prestressing force, can cause that being reinforced geotechnical body produces bigger creep and plastic strain, anchor pier on domatic can produce sinking, cause loss of prestress, cause anchoring engineering to lose efficacy; A little less than the loose geotechnical body side slope scouring-resistance ability, under the long-term souring of rainwater, can cause anchor pier to come to nothing, cause anchoring engineering to lose efficacy.Be the requirement of satisfying the geotechnical body bearing capacity by the floor space of the anchor pier that increases at present, by advancing the domatic anchor pier that prevents and come to nothing anchor pier being embedding.Yet the increase of sectional dimension can cause construction costs to increase, and long-term slope wash meeting progressively makes the anchor pier bottom surface expose, and comes to nothing, and embedding anchor pier can not guarantee the long-time stability of anchoring engineering.
Summary of the invention
The purpose of this utility model is: domatic reinforcing of a kind of prestress anchoraging anchor pier and fixed structure are provided, satisfying under the prerequisite of identical anchoring effect, adopt the anchor pier of reduced size also can realize effectively fixing, satisfy the requirement of side slope surface bearing capacity, thereby save engineering cost.
The utility model is to constitute like this: comprise anchor pier, anchor pier connects anchor cable, under anchor pier grouting tube is set, and the exposed parts of floral tube inserts in the anchor pier, fixedlys connected with the reinforcing bar of anchor pier, and anchor pier and floral tube are fixed by concreting.
Above-mentioned domatic reinforcing of prestress anchoraging anchor pier and fixed structure, described floral tube front end is taper, is provided with the spillage hole on floral tube, the not boring that leaves at least 20 centimetres at the floral tube afterbody ends the slurry section, injects cement mortar or cement paste in floral tube.
Above-mentioned domatic reinforcing of prestress anchoraging anchor pier and fixed structure, floral tube is arranged under the anchor pier, and the spacing of floral tube is 50cm~80cm in the longitudinal direction; The spacing of floral tube is 20cm~30cm on width.
The present invention inserts grouting tube in the ground below the prestress anchoraging anchor pier, by slip casing by pressure, improved the character of anchor pier ground geotechnical body, and floral tube insertion geotechnical body, plays the pile foundation effect, thereby has improved the bearing capacity of ground geotechnical body greatly.When carrying out prestress anchoraging anchor pier designing and calculating, design same prestressing force, because of bearing capacity of foundation soil improves, can reduce prestress anchoraging anchor pier sectional dimension, thereby reduce the consumption of prestress anchoraging anchor pier steel concrete, both saved the duration, also saved investment.The floral tube exposed parts effectively is connected with the prestress anchoraging anchor pier, floral tube and prestress anchoraging anchor pier are fused form the outer anchor structure thing of prestress anchoraging jointly, because the most of people's geotechnical body of inserting of floral tube, can realize prestress anchoraging anchor pier effectively fixing on side slope surface, thereby reduce the size of prestress anchoraging anchor pier, reduce the consumption of steel concrete, reduce investment outlay.Compare with prior art, it is little that the present invention has an anchor pier volume, in the shortening cycle, saves advantages such as engineering cost.Be applicable to cohesive soil, sand, sand ovum (gravel) stone layer, residual clinosol, completely decomposed rock and strong-weathered rock side slope, the middle weathering soft rock of easy-weathering, dead-soft rock also can adopt.
Description of drawings
Accompanying drawing 1 is a structural representation of the present utility model;
Accompanying drawing 2 is the vertical view of the utility model anchor pier;
Accompanying drawing 3 is the structural representation of the utility model floral tube.
The specific embodiment
Embodiment of the present utility model: make anchor pier 1 domatic 3, anchor pier 1 connects prestress anchorage cable 4, during making, earlier 1 time grouting tube 2 is set at anchor pier, the exposed parts of floral tube 2 is inserted in the anchor pier 1, fixedly connected, anchor pier 1 and floral tube 2 are fixed together by concreting with the reinforcing bar of anchor pier 1, concrete reaches after the intensity and then to anchor pier 1 and carries out the stretch-draw and the anchoring of anchor cable 4, and anchoring process gets final product according to existing construction technology.
Floral tube 2 front ends that adopt are taper, make spillage hole 6 on floral tube 2, and the not boring that leaves at least 20 centimetres at floral tube 2 afterbodys ends slurry section 5, ends slurry section 5 and inserts in the anchor pier 1, and 2 mouth of pipe places are provided with iron hoop 7 at floral tube, inject cement mortar or cement paste in floral tube 2.Floral tube 2 general vertical domatic 3 inserts geotechnical body 1.5m~5.0m, adopts boring or adopts vibratory drilling method that floral tube 2 is inserted in the slope ground body.In floral tube 2, inject cement mortar or cement paste, water/binder ratio w/c=0.5~1.0.Also can adopt cement water glass biliquid slurry.Grouting pressure is not less than 0.2MPa, is generally 0.2MPa~1.0MPa, can determine according to the type of slope ground body.
According to the shape size of domatic 3 angles of inclination and anchor pier 1, floral tube 2 be arranged on anchor pier 1 around, the spacing of floral tube 2 is 50cm~80cm in the longitudinal direction; The spacing of floral tube 2 is 20cm~30cm on width, and effect is better.

Claims (3)

1. domatic reinforcing of prestress anchoraging anchor pier and fixed structure, comprise anchor pier (1), anchor pier (1) connects anchor cable (4), it is characterized in that: grouting tube (2) is set under anchor pier (1), the exposed parts of floral tube (2) inserts in the anchor pier (1), fixedly connected with the reinforcing bar of anchor pier (1), anchor pier (1) is fixed by concreting with floral tube (2).
2. domatic reinforcing of prestress anchoraging anchor pier according to claim 1 and fixed structure, it is characterized in that: described floral tube (2) front end is taper, on floral tube (2), be provided with spillage hole (6), the not boring that leaves at least 20 centimetres at floral tube (2) afterbody ends slurry section (5), injects cement mortar or cement paste in floral tube (2).
3. domatic reinforcing of prestress anchoraging anchor pier according to claim 1 and fixed structure is characterized in that: floral tube (2) is arranged under the anchor pier (1), and the spacing of floral tube (2) is 50cm~80cm in the longitudinal direction; The spacing of floral tube on width (2) is 20cm~30cm.
CN2010203002398U 2010-01-07 2010-01-07 Prestressed anchorage anchor pier slope reinforcing and fixing structure Expired - Lifetime CN201567574U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010203002398U CN201567574U (en) 2010-01-07 2010-01-07 Prestressed anchorage anchor pier slope reinforcing and fixing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010203002398U CN201567574U (en) 2010-01-07 2010-01-07 Prestressed anchorage anchor pier slope reinforcing and fixing structure

Publications (1)

Publication Number Publication Date
CN201567574U true CN201567574U (en) 2010-09-01

Family

ID=42659858

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010203002398U Expired - Lifetime CN201567574U (en) 2010-01-07 2010-01-07 Prestressed anchorage anchor pier slope reinforcing and fixing structure

Country Status (1)

Country Link
CN (1) CN201567574U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056754A (en) * 2018-09-06 2018-12-21 沙洲职业工学院 A kind of spraying type micro combination stake of landslide-proofing
CN110344394A (en) * 2019-06-24 2019-10-18 中建铁路投资建设集团有限公司 A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056754A (en) * 2018-09-06 2018-12-21 沙洲职业工学院 A kind of spraying type micro combination stake of landslide-proofing
CN110344394A (en) * 2019-06-24 2019-10-18 中建铁路投资建设集团有限公司 A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method

Similar Documents

Publication Publication Date Title
CN111021376A (en) Three-dimensional frame pile body structure for deep landslide treatment and construction process thereof
CN101544022B (en) Preparation method for preformed hole fender pile
CN103015414A (en) Precast concrete post grouting pile and grouting process
CN201395794Y (en) Foundation ditch with concealed columns and soil-nailing support
CN201605588U (en) Structure for reinforcing and fixing slope surface of prestress anchoring frame beam
CN213173336U (en) Novel prefabricated assembled anticollision wall
CN103410144B (en) Prestressed reinforcement piles set into rock and construction method
CN101718098A (en) Micro-pile combined dug composite foundation and construction method thereof
CN111101526A (en) Vertical excavation supporting system based on miniature steel pipe piles for red clay foundation pit
CN201605587U (en) Structure for reinforcing and fixing slope surface of prestress anchoring frame plate
CN201567574U (en) Prestressed anchorage anchor pier slope reinforcing and fixing structure
CN204139191U (en) A kind of pile-raft foundation structure
CN102912928B (en) Structural member for restraining grouting anchoring connection by using two ends of steel bar and connection method
CN200943205Y (en) Anchor bar assembly for earth anchor bar construction
CN202882164U (en) Member for restraining grouting anchor connection by using two ends of reinforcing steel bar
CN202194130U (en) Composite prestressed uplift pile with enlarged head
CN102121248A (en) Method for reinforcing and fixing sloping surface of prestressed anchorage element
CN108643215B (en) Construction method of anchor pier type foundation after rotary spraying and pressing into variable cross section
CN202787275U (en) Tubular soil nailing wall of novel pneumatic impact anchor
CN202672161U (en) Cement-soil mixing drum sheet-pile united slope structure with soil nails
CN213952209U (en) PSB finish rolling screw-thread steel pipe pile prestressing force anti-floating pile structure
CN201908311U (en) Reinforcing and fixing structure for slope surface of prestressed anchorage ground beam
CN210239717U (en) Strong anchor grouting supporting structure for controlling red shale tunnel
CN203129131U (en) Cement-soil mixing pile for foundation reinforcement
CN208363089U (en) The steel strand reinforced structure of Pulling-Resistant Anchor Rod in a kind of stake

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GUIZHOU TRANSPORTATION PLANNING SURVEY + DESIGN AC

Free format text: FORMER OWNER: GUIZHOU COMMUNICATION PLANNING AND PROSPECTING DESIGN ACADEMY

Effective date: 20130830

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20130830

Address after: 550001 No. 107 East Zhongshan Road, Guizhou, Guiyang

Patentee after: Guizhou Transportation Planning Survey & Design Academe Co., Ltd.

Address before: 550001 No. 69 East Zhongshan Road, Guizhou, Guiyang

Patentee before: Guizhou Communication Planning and Prospecting Design Academy

CX01 Expiry of patent term

Granted publication date: 20100901

CX01 Expiry of patent term