The utility model content
The purpose of this utility model be solve that the excavation slope top displacement that the soft clay area excavation pit in the urban district exists is excessive, the problem a little less than the soil nailing shingle nail support force, the support technology that provides a kind of adding to have sleeper and soil nailing to combine, strengthening the globality of foundation pit supporting construction, with the excavation of the soft soil layer foundation ditch that is applicable to the urban district.
The purpose of this utility model is achieved through the following technical solutions:
Foundation ditch with sleeper and plate brad supporting is included in the hole body that digs out on the ground, surrounded by the side slope body, the side slope body be vertically arranged with sleeper, the side slope body laterally squeezed into soil nailing.
Described sleeper is a drilled pressure filling pile, and this drilled pressure filling pile is to drop into rubble in the reinforcing cage to be pressed into the cement paste formation again, and its underpart enters the bottom 2.0~4.0m of hole body, and pile spacing is 1.2~2.0m, and row of piles is apart from being 1.0~1.5m, and the stake footpath is 350~450mm; Reinforcing cage comprises that 8 indented barss are main muscle, and every 2m disposes reinforcing rib one on the length direction, and main muscle is provided with spiral stirrup outward, and helix pitch is 20cm; The top of sleeper is provided with Guan Liang.
The body of rod of described soil nailing adopts steel pipe, and is divided into three sections; Front end 1/3rd and middle part three/part are fixedly connected with screw-thread steel respectively as hangnail, and front end three/part is drilled with the slip casting eye; Hangnail is a screw arrangement.
Described side slope surface is provided with the steel concrete surface layer, and this surface layer comprises steel mesh reinforcement and pea gravel concreten; Soil nailing and steel concrete surface layer connection are provided with the horizontal reinforcing rib of waling and elongated layout.
Described Guan Liang ties up weldering with the soil nailing end on top and is connected.
The crossing angle of described soil nailing and horizontal plane is 10~15 °.
The composite support structure that the utility model adopts above-mentioned sleeper to combine with soil nailing has been expanded the range of application of soil nailing structure greatly, especially in the application of soft clay area; Plate brad supporting belongs to the mechanism of initiatively reinforcing, and can improve the undisturbed soil intensity of foundation ditch greatly, increases the rigidity of the compound soil body, has retrained the distortion of slope soil, has significantly improved the resistance to overturning of side slope; The effect of sleeper is the soil lateral that reduces in the construction stage excavation, supports sprayed mortar surface layer weight, improves the resistance to overturning of plate brad supporting system.
As seen, adopt the utility model of said structure, compared with prior art, can solve the problem a little less than, the soil nailing shingle nail support force excessive, be applicable to the supporting of the soft soil layer institute excavation pit in the urban district in the excavation slope top displacement that the soft clay area excavation pit in urban district exists.
The specific embodiment
Below in conjunction with specific embodiments and the drawings the utility model is further described.
As shown in Figure 1, comprise the hole body that is surrounded by the side slope body at the foundation ditch of the soft clay area in urban district excavation, vertically the arranging of side slope is provided with sleeper 1, laterally arranges and squeezed into soil nailing 2, and the top of sleeper 1 is provided with hat beam 3.
As shown in Figure 2, the angle of intersection 7 of soil nailing 2 and horizontal plane is between 10~15 °, and sleeper 1 is that concrete inserts section 6 with the lower end of soil nailing 2 composite support structural panels; Side slope surface is provided with the sprayed mortar surface layer, and the pea gravel concreten that sprays match ratio and be C20 is as breast boards, and top is sprayed mortar surface layer 4 when putting slope section plate brad supporting, and thickness is 50mm; Sprayed mortar surface layer 5 when the bottom is a vertical section sleeper-soil nailing composite support, thickness is 80mm.The sprayed mortar surface layer all adopts pea gravel concreten, and intensity is C20, and cement is the 32.5R Composite portland cement.The reinforced concrete slab structure that above-mentioned two parts surface layer all is made up of sprayed mortar and steel mesh reinforcement.The surfacing steel bar net adopts reinforcing bar binding to form.
Sleeper is a drilled pressure filling pile, and this drilled pressure filling pile is to drop into rubble in the reinforcing cage to be pressed into the cement paste formation again, according to designing requirement, its underpart enters the bottom 2.0~4.0m of hole body, pile spacing is 1.2~2.0m, and row of piles is apart from being 1.0~1.5m, and the stake footpath is 350~450mm; Reinforcing cage comprises that 8 indented barss are main muscle, and every 2m disposes reinforcing rib one on the length direction, and main muscle is provided with spiral stirrup outward, and helix pitch is 20cm; The top of sleeper is provided with Guan Liang.
As shown in Figure 5, are furnished with 6 reinforcing bars in the hat beam 3.
As shown in Figure 6, hat beam 3 is tied up to weld with soil nailing 2 and is connected.
As Fig. 7, shown in Figure 8, the body of rod of soil nailing 1 adopts steel pipe 10, and is divided into three sections; Front end 1/3rd and middle part three/part are fixedly connected with screw-thread steel respectively as hangnail 8, and front end three/part is drilled with the slip casting eye; Hangnail 8 is a screw arrangement.
As shown in Figure 8, the steel pipe 10 of soil nailing 1 stretches into the horizontal reinforcing rib 12 of anchor pole that the interior end of steel concrete surface layer is fixedly connected with anchor pole waling 13 and elongated layout, and its fixedly connected mode can be welding.
The job practices of present embodiment and concrete parameter are as follows:
1, sleeper
(1) parameter: basic parameter was provided with as follows when drilled pressure filling pile was used for pattern foundation pit supporting structure: stake long according to each foundation ditch section cutting depth difference and difference, it determines that principle is that stake end enters 2.0~4.0m at the bottom of the foundation ditch, pile spacing is 1.2~2.0m, can arrange more and put, row of piles is apart from being 1.0~1.5m, and the design stake is 350~450mm directly; The pile body structure: pile body disposes 8 on Φ 16 indented barss symmetrically and evenly, and every 1m disposes φ 6.5 reinforcing ribs one as main muscle, and main muscle is provided with φ 6.5 spiral stirrups outward, and helix pitch is 20cm, and thickness of protection tier is 20mm; The stake top is provided with 350 (or 450) * 300mm contact and connects with Guan Liang, to guarantee the mass action of drilled pressure filling pile in pattern foundation pit supporting structure.
(2), the construction equipment of sleeper
The CK15-A rig; Mortar pump; Mortar mixer.
(3), the construction technology process of sleeper
The construction technology process of sleeper is as follows:
Discharge hole → draw hole → be lowered to sleeve pipe → put into reinforcing cage and Grouting Pipe → insert gravel → slip casting → excavation hat beam foundation trench, and colligation hat beam steel → build C15 concrete → drilled pressure filling pile maintenance → soil excavation
1) discharge hole:
According to Shop Drawing Design Document IT Application and each drilled pressure filling pile stake position of on-the-spot actual measuring.
2) draw the hole: perforate plan-position error is no more than ± 5cm.
3) reinforcing cage is made: because stake is longer, and reinforcing cage segmentation place welding quality particular importance, main muscle joint should stagger mutually, and guaranteeing that same cross section spigot number is no more than 50%, two joint spacing of main muscle sum should be greater than 50cm, and weldering elongation degree should satisfy code requirement;
4) pore-forming, be lowered to Grouting Pipe, fill out gravel: hole depth by project management department according to the base pit engineering plan and on-the-spotly actually determine.Adopt CK15-A rig pore-forming during construction, behind the pore-forming, put into reinforcing cage, be lowered to Grouting Pipe, insert 0~4cm cobble.
5) slip casing by pressure: injecting paste material adopts the neat slurry of 32.5R Composite portland cement preparation, slurry water gray scale 0.5: 1, grouting pressure is 1MPa~2MPa, extremely next pile is poured into after returning out underflow in the stake top, treat that slurries are after sinking a period of time, previous stake of pouring into is recharged, and this process should be carried out repeatedly, till no longer sinking to slurries.
6) the contact beam is made: the stake top is provided with 350 (or 450) * 300mm contact beam and connects, to guarantee the mass action of drilled pressure filling pile in pattern foundation pit supporting structure; After slip casing by pressure is finished, manually dig and make contact beam groove, and manually cut a top laitance, pile body and second layer anchor pole are welded to connect, will anchor into about pile body 10cm in the beam body, assembling reinforcement, thickness of concrete cover is 2.5cm, formwork is built the C20 concrete.
7) drilled pressure filling pile maintenance: drilled pressure filling pile pile body palpus maintenance 7 days, treat that its intensity reaches design strength 60% and carries out soil excavation with the top.
2, soil nailing
(1) parameter of soil nailing
Soil nailing is divided into soil nailing body and surface layer.
The soil nailing body: the used slurries of soil nailing slip casting are neat slurry, and the slurry water/binder ratio is 0.5: 1, and pressure is 1~2Mpa; Soil nailing length and soil nailing spacing can be adjusted in right amount according to the actual geological condition in scene.By designing requirement, rod body material adopts Φ 48 steel pipes, and the body of rod is divided into three sections, and front end 1/3 part welding 50mm@2000mm screw-thread steel is as hangnail, and brill slip casting eye, and middle part 1/3 part welding 50mm@2000mm screw-thread steel does not bore the slip casting eye as hangnail; Afterbody 1/3 does not weld screw-thread steel.Hangnail takes spiral way to arrange.The body of rod surperficial straight do not have the slight crack that influences body of rod quality, and the internal request of the body of rod is unimpeded.
Surface layer: the reinforced concrete slab structure pattern that surface layer adopts sprayed mortar and steel mesh reinforcement to form.Lay steel mesh reinforcement between the soil nailing body of rod, and on steel mesh reinforcement, press the main muscle of putting 2 vertical long 60cm of being as anchor pole waling 13, elongated horizontal bar is as horizontal reinforcing rib of anchor pole 12 and steel pipe 10 welding as the body of rod, thereafter the pea gravel concreten that sprays match ratio and be C20 is as breast boards, top put slope section plate brad supporting the time sprayed mortar surface thickness 50mm, sprayed mortar surface thickness 80mm during the vertical section sleeper of bottom-plate brad supporting.Sprayed mortar adopts pea gravel concreten, and intensity is C20, and cement is the 32.5R Composite portland cement.The surfacing steel bar net adopts φ 8@150 * 150~250 * 250 reinforcing bar bindings to form.Soil nailing end and reinforcing rib adopt and are welded to connect.
(2) construction equipment of soil nailing
QC-150 type Pneumatic immpacting roof-bolter; Pneumatic mortar machine; Air compressor machine; The sprayed mortar machine; Electric welding machine cutting machine etc.
(3) construction technology process of soil nailing
The soil nailing job practices: adopting QC-150 type Pneumatic immpacting roof-bolter is the welded tube of φ 48mm with diameter, impacts and squeezes in the stratum, forms soil nailing after the slip casting.
The soil nailing construction technology process is as follows:
1) construction survey
A. excavation line is measured: finished by civil engineering unit.
B. the soil nailing position is measured: marked with red paint by full-time survey crew along smooth sprayed mortar face, measure error must not surpass 5cm.
2) soil nailing construction
A. the body of rod is made: make according to the base pit engineering plan, and the body of rod is divided into three sections, front end 1/3 part welding 50mm@2000 screw-thread steel is as hangnail; And boring the slip casting eye, middle part 1/3 part welding 50mm@2000 screw-thread steel does not bore the slip casting eye as hangnail; Afterbody 1/3 does not weld hangnail, and hangnail takes spiral way to arrange.The selection of the body of rod requires the surface straight, does not have the slight crack that influences body of rod quality, and the internal request of the body of rod is unimpeded.
B. the body of rod is laid: the body of rod is laid and is adopted QC-150 type Pneumatic immpacting to squeeze in the stratum, forms soil nailing after the slip casting.
Squeeze into method.Require the soil nailing position in the construction in design attitude 5cm scope, it is 10~15 degree that soil nailing is put into soil body back rake angle.
3) welding
A. the welding between the body of rod: should guarantee during welding that bonding area adheres to specification, and guarantee that body of rod inside is unimpeded.
B. soil nailing and metal host muscle welding: the control weld strength, should avoid rosin joint and the not enough problem of bonding area in the welding emphatically.
4) construction of shotcrete
A. foundation pit walls should clean out loosened soil before the construction of shotcrete, for guaranteeing that panel closely is connected with mini pile, should clean out loosened soil in the mini pile position, exposes pile concrete, cheats wall simultaneously and keeps straight.
B. the artificial spice in concrete mix report carrying out scene that provide according to Nanchong City quality monitoring station of concrete batching, spice is even.
C. sprayed mortar thickness is 5~8cm, and 28 days planted agents after having sprayed are carried out in accordance with regulations maintenance.For guaranteeing sprayed mortar thickness, the foundation ditch work plane is provided with sprayed mortar thickness sign every 1m, can adopt small wooden or bar dowel, length is about about 15cm, and an end inserts in the wall earth of hole, and an end exposes the outer 8cm of hole wall, during construction of shotcrete, set sign is covered.For guaranteeing the sprayed mortar protective layer thickness, reinforced mesh should adopt reinforced mesh gravel pebbles or other fritter shape material cushion to rise about 3cm after laying and finishing.
5) mud jacking
A. the slurry water gray scale is 0.5, and mud jacking pressure is about 1.5MPa.
B. every soil nailing mud jacking amount is not less than 50kg (can determine optimum mud jacking amount according to actual conditions less than the bolt grouting amount scene of 6m to length).
C. slurries should stir, and with stirring with usefulness, need to use up before slurries reach initial set.
D. the soil nailing mortar depositing construction should be shared supporting at this soil nailing and partly sprays and carry out after coagulation construction is finished 1 day, and performs the mud jacking construction note.
6) shoveling forms foundation ditch
The shoveling time should avoid damaging completed dado structure during shoveling after mud jacking finishes 12 hours.