CN113216215A - Deep groove support reverse construction method in complex environment - Google Patents

Deep groove support reverse construction method in complex environment Download PDF

Info

Publication number
CN113216215A
CN113216215A CN202110606691.XA CN202110606691A CN113216215A CN 113216215 A CN113216215 A CN 113216215A CN 202110606691 A CN202110606691 A CN 202110606691A CN 113216215 A CN113216215 A CN 113216215A
Authority
CN
China
Prior art keywords
deep trench
construction
deep
complex environment
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110606691.XA
Other languages
Chinese (zh)
Inventor
李建新
董党
马勇举
来延龙
冯学良
曹武志
刘蔚萌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 11 Co Ltd
Original Assignee
Sinohydro Bureau 11 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 11 Co Ltd filed Critical Sinohydro Bureau 11 Co Ltd
Priority to CN202110606691.XA priority Critical patent/CN113216215A/en
Publication of CN113216215A publication Critical patent/CN113216215A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00—Excavations; Bordering of excavations; Making embankments
    • E02D17/06—Foundation trenches ditches or narrow shafts
    • E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • E02D17/083—Shoring struts
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00—Handling building or like materials for hydraulic engineering or foundations
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00—Excavations; Bordering of excavations; Making embankments
    • E02D17/06—Foundation trenches ditches or narrow shafts
    • E02D17/12—Back-filling of foundation trenches or ditches

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

本发明公开了一种复杂环境下深沟槽支护逆作施工方法,包括以下步骤:首先测量放线,确定管道轴线及结构边线;然后根据地质情况及工作条件,并在深沟槽周围布置高压旋喷桩;旋喷桩施工完成后在深沟槽开设截水沟,随后在沟槽四周设立防护栏杆;对深沟槽的上层土方进行开挖,并对开挖后的深沟槽上部施作混凝土支护结构;待上层混凝土支护结构施作完成并达到强度要求后,再对深沟槽的下层土方进行开挖和支护作业,重复上道工序直至施工到深沟槽底部;当施工到深沟槽底部后,对深沟槽的底部进行底板浇筑;底板浇筑完成后,进行管道安装,随后对深沟槽进行回填。该方法采用逆作法对深沟槽进行由上至下的分层支护,支护效果好。

Figure 202110606691

The invention discloses a construction method for deep trench support reverse working in complex environment, which comprises the following steps: firstly measuring and setting out lines, determining the pipeline axis and structural edge; then according to geological conditions and working conditions, arranging around the deep trench High-pressure rotary jetting piles; after the construction of rotary jetting piles is completed, a water intercepting ditch is opened in the deep trench, and then protective railings are set up around the trench; the upper soil of the deep trench is excavated, and the upper part of the deep trench is excavated. Construction of concrete supporting structure; after the construction of the upper concrete supporting structure is completed and the strength requirements are met, the lower earthwork of the deep trench is excavated and supported, and the previous procedure is repeated until the construction reaches the bottom of the deep trench; After the construction reaches the bottom of the deep trench, the bottom of the deep trench is poured; after the bottom is poured, the pipeline is installed, and then the deep trench is backfilled. This method adopts the reverse method to carry out layered support from top to bottom for deep trenches, and the support effect is good.

Figure 202110606691

Description

Deep groove support reverse construction method in complex environment
Technical Field
The invention relates to the technical field of engineering construction, in particular to a deep groove support reverse construction method in a complex environment.
Background
The deep groove supporting technology is widely applied in China, and large deformation and uneven settlement are often caused due to the diversity and complexity of geological conditions of various projects, the inaccuracy of complex pipelines and geological prospecting data of municipal projects and the like. The mixed layer of the sludge layer and the sand layer often generates quicksand and collapse, and the water seepage amount under the substrate is large; the saturated soil body is seriously liquefied in the process of road surface crushing and steel sheet pile construction, and the safety and normal use of buildings (structures), underground pipelines and other municipal facilities close to the periphery of a foundation pit are influenced. The engineering progress is severely restricted, and certain potential safety hazards are caused. The conventional support type adopted in the complex geological environment can not meet the deformation stability requirement of the structure.
Disclosure of Invention
In order to solve the technical problem, the invention provides a deep groove support reverse construction method in a complex environment.
The technical scheme for solving the technical problems is as follows: a deep groove support reverse construction method in a complex environment comprises the following steps:
s1: and (4) measuring and setting out, namely firstly establishing a coordinate control network, wherein the precision is in accordance with the requirement. Plane control: and (4) determining the axis of the pipeline according to a construction drawing strictly, and then putting out the pile site of the jet grouting pile and the excavation line of the foundation trench. Elevation control: in the elevation control of the vertical section of the pipe trench in construction, the base is adopted to arrange high-program control piles, the distance between the piles is controlled to be 10m, and the elevation is marked on the upper part of the pile.
S2, arranging high-pressure jet grouting piles around the deep grooves according to geological conditions and working conditions;
s3, forming a water intercepting ditch in the deep ditch after the construction of the jet grouting pile is finished; subsequently, guard rails are arranged around the grooves.
S4: excavating the upper earthwork of the deep groove, and applying a concrete supporting structure on the upper part of the excavated deep groove;
s5: after the upper concrete supporting structure is completely constructed and meets the strength requirement, excavating and supporting the lower earthwork of the deep groove, and repeating S2 until the construction is carried out to the bottom of the deep groove;
s6: after the deep groove is constructed to the bottom of the deep groove, pouring a bottom plate at the bottom of the deep groove;
s7: and after the bottom plate is poured, the pipeline is installed, and the deep groove is backfilled.
Furthermore, when the upper part of the deep groove is excavated, most earthwork of the deep groove is excavated by machinery, then the well wall is trimmed by a manual small appliance, when the lower part of the deep groove is excavated, a manual pneumatic tool is used for chiseling, and the residue soil is hoisted out of the deep groove by mechanical hoisting.
And further, immediately binding steel bars for each layer of excavation, assembling and reinforcing the steel bars through a steel die after the steel bars are bound and installed, reserving a pouring gate, pouring concrete into the pouring gate, plugging the reserved gate after the concrete is poured to a position above the reserved pouring gate, removing the template until the concrete meets the strength requirement, and excavating the earthwork of the second layer in the deep groove.
Furthermore, when the steel bars are installed, the section steel bars are reserved on the upper layer well body, and the lower section steel bars of the upper layer well body are welded with the steel bars of the lower layer well body.
Furthermore, when the earthwork is excavated, the excavation depth of the earthwork does not exceed the pouring depth of the earthwork.
Furthermore, the concrete supporting structure is provided with expansion joints with the width of 2cm-3cm every 9m-10 m.
Further, before the bottom plate is poured in the step S6, whether the bearing capacity reaches a design value is detected, and when the bearing capacity does not meet the design value, coarse sand gravel with the thickness of 500mm and the thickness of 1:1 is adopted for replacement and filling, and then concrete is poured.
The invention has the following beneficial effects: according to the deep groove support reverse construction method in the complex environment, the deep groove is layered and supported from top to bottom by adopting a reverse construction method, so that the lateral movement and surrounding ground surface settlement of the enclosure structure can be effectively controlled aiming at the complex geological environment, the uplift deformation resistance of a pit bottom can be increased, and the influence on surrounding buildings is small; meanwhile, the layered detection is realized through the layered construction of the reverse construction method, and then the manual detection and excavation are assisted, so that the accurate detection can be realized for complex underground pipelines and pipelines with deeper depth, the construction safety can be ensured to a greater extent, the damage to the pipelines in the construction is avoided, in addition, the deep trench excavation is assisted by grouting reinforcement and anti-seepage measures, the construction safety is effectively ensured, and the supporting effect is improved.
Drawings
FIG. 1 is a flow chart of the construction of the present invention;
fig. 2 is a schematic view of the layered excavation in the present invention.
Detailed Description
The principles and features of this invention are described below in conjunction with the following drawings, which are set forth by way of illustration only and are not intended to limit the scope of the invention.
As shown in fig. 1 to 2, a deep groove support reverse construction method in a complex environment comprises the following steps:
s1: and (4) measuring and setting out, namely firstly establishing a coordinate control network, wherein the precision is in accordance with the requirement. Plane control: and (4) determining the axis of the pipeline according to a construction drawing strictly, and then putting out the pile site of the jet grouting pile and the excavation line of the foundation trench. Elevation control: in the elevation control of the vertical section of the pipe trench in construction, the base is adopted to arrange high-program control piles, the distance between the piles is controlled to be 10m, and the elevation is marked on the upper part of the pile.
And S2, determining the geological condition and the working condition of the construction position, and arranging high-pressure jet grouting piles around the deep groove. The high-pressure jet grouting pile is used as a water stop pile, the pile diameter of the high-pressure jet grouting pile is 500mm, and the lap joint is 150 mm. The rotary jet grouting pile is constructed by adopting a single-pipe method, the cement strength is 42.5, the water cement ratio of cement paste is 1.0, the overlap length of the sectional lifting of the jet pipe is not less than 100mm, the pile position deviation is not more than 50mm, and the diameter of a formed hole and the length of the pile are not less than the design values. The requirement of the high-pressure rotary jet grouting pile on the grouting pressure reaches 20MPa, the lifting speed is 20cm/min, and the vertical deviation is not more than 1.0 percent.
S3: the deep trench is provided with a 30 cm-30 cm intercepting drain. Adopting common MU15 concrete, M10 cement mortar for masonry, adopting C15 concrete as a cushion layer, and preventing surface water from flowing into the groove; protective railings are arranged around the groove, the railings are fixed on the embedded iron plate, the height of each railing is 1.2m, and each vertical rod is arranged at every 1.5 m. The upright rods are made of phi 48-3.2 steel pipes, the handrails are made of phi 48 steel pipes, the middle parts of the handrails are provided with three horizontal connecting rods, and the materials are formed by welding phi 48 steel pipes and the upright rods. Priming with red lead anti-rust paint, and brushing finish paint. The guardrail must be strong, reliable, ensure personnel's safety.
And S4, excavating the upper earthwork of the deep groove, and constructing a concrete supporting structure on the upper part of the excavated deep groove. When the excavation is carried out, the excavation of the upper-layer earthwork part is carried out by adopting manual auxiliary mechanical operation, most earthwork of the deep groove is firstly excavated by using a machine, then the well wall is maintained by manually holding a small-sized tool, and the disturbance to the soil surface of the supporting structure rock is reduced as much as possible. In the work progress, according to concrete geological conditions and operating condition, the reasonable arrangement supports temporarily, guarantees the stability of soil layer, avoids causing the soil property to collapse and induces the incident. When the earthwork is excavated, the excavation depth of the earthwork is not more than the pouring depth of the earthwork, so that the earth pressure balance is kept, and the soil body collapse is prevented.
S5: and after the upper concrete supporting structure is constructed and meets the strength requirement, excavating and supporting the lower earthwork of the deep groove, and repeating S4 until the construction is carried out to the bottom of the deep groove. And the lower rock part is excavated by adopting a manual pneumatic tool, lifted to the wellhead surface by mechanical hoisting, and loaded to a slag yard. The excavation construction of the working well is reasonably carried out in cooperation with the reinforced concrete construction of the well wall, and the excavation of the lower soil body is carried out after the strength of the upper concrete meets the requirement.
S6: and pouring the wall body to the designed depth, wherein the bearing capacity of the bearing layer of the bottom plate reaches 100KPa of the design or replacing and filling coarse sand and gravels with the thickness of 500mm being 1:1, and meeting the bearing capacity requirement, so that the bottom plate C30 concrete can be poured.
When concrete supporting construction is carried out, steel bar binding is carried out immediately every layer of excavation, after steel bar binding installation is completed, steel dies are used for splicing and reinforcing and reserving a pouring gate, then concrete is poured into the pouring gate, after the concrete is poured to the position above the reserved pouring gate, the reserved gate is sealed, the template is removed until the concrete meets the strength requirement, and then the second layer of earthwork excavation in the deep groove is carried out. When the steel bars are installed, the section steel bars are reserved on the upper well body, the lower section steel bars of the upper well body are welded with the steel bars of the lower well body, and interval welding is adopted to ensure that the number of the welding joints of the same section is not more than 50%.
The concrete supporting structure is provided with expansion joints with the width of 2cm-3cm every 9m-10m, two sides are excavated simultaneously during the construction of the retaining wall without overexcavation, the front section of the concrete supporting structure is excavated by 4.5m, and the rear end of the concrete supporting structure is excavated by 4.5m after the construction. The stability of the soil body and the change of the underground water level need to be enhanced and observed in the construction process.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (7)

1.一种复杂环境下深沟槽支护逆作施工方法,其特征在于,包括以下步骤:1. a deep trench support reverse construction method under a complex environment, is characterized in that, comprises the following steps: S1:测量放线,首先建立坐标控制网,精度符合设计要求;平面控制:严格按施工图先定出管道轴线,再放出旋喷桩桩位点及基槽的开挖线;高程控制:施工中管沟纵断面的高程控制,采用基底设置高程控制桩,控制桩间距为10m,在桩上部标注高程;S1: Measure and lay out the line, first establish a coordinate control network, and the accuracy meets the design requirements; plane control: first determine the axis of the pipeline in strict accordance with the construction drawing, and then release the excavation line of the pile position and foundation groove; elevation control: construction For the elevation control of the longitudinal section of the middle pipe trench, the base is used to set up elevation control piles, the spacing between the control piles is 10m, and the elevation is marked on the top of the piles; S2:根据地质情况及工作条件,并在深沟槽周围布置高压旋喷桩;S2: According to the geological conditions and working conditions, high-pressure jetting piles are arranged around the deep trenches; S3:旋喷桩施工完成后在深沟槽开设截水沟;随后在沟槽四周设立防护栏杆;S3: after the construction of the rotary jet pile is completed, a water intercepting ditch is set up in the deep groove; subsequently, a protective railing is set up around the groove; S4:对深沟槽的上层土方进行开挖,并对开挖后的深沟槽上部施作混凝土支护结构;S4: excavate the upper soil of the deep trench, and apply a concrete support structure to the upper part of the deep trench after excavation; S5:待上层混凝土支护结构施作完成并达到强度要求后,再对深沟槽的下层土方进行开挖和支护作业,重复S2直至施工到深沟槽底部;S5: After the construction of the upper concrete supporting structure is completed and the strength requirements are met, the lower earthwork of the deep trench is excavated and supported, and S2 is repeated until the construction reaches the bottom of the deep trench; S6:当施工到深沟槽底部后,对深沟槽的底部进行底板浇筑;S6: After the construction reaches the bottom of the deep trench, the bottom of the deep trench is poured; S7:底板浇筑完成后,进行管道安装,随后对深沟槽进行回填。S7: After the base plate is poured, pipe installation, followed by backfilling of deep trenches. 2.根据权利要求1所述的复杂环境下深沟槽支护逆作施工方法,其特征在于,对深沟槽上部进行开挖作业时,首先采用机械挖除深沟槽的大部土方,再通过人工持小型器具修整井壁,对深沟槽下部进行开挖时,采用人工手持风动工具凿除,并通过机械吊运将渣土吊出深沟槽。2. The construction method for deep trench support reverse work under complex environment according to claim 1, is characterized in that, when excavating the upper part of the deep trench, firstly adopt mechanical excavation to remove most of the earthwork of the deep trench, Then, the well wall is trimmed by hand with small tools. When excavating the lower part of the deep groove, manual hand-held pneumatic tools are used to chisel away, and the slag is lifted out of the deep groove by mechanical hoisting. 3.根据权利要求2所述的复杂环境下深沟槽支护逆作施工方法,其特征在于,每开挖一层立即进行钢筋绑扎,当钢筋绑扎安装完成后通过钢模拼装加固并预留浇注口,随后向浇注口内浇筑混凝土,当混凝土浇筑到预留浇注口以上后,将预留口封堵,直至混凝土达到强度要求后拆除模板,再进行深沟槽内第二层土方开挖。3. The deep trench support reverse working construction method under complex environment according to claim 2, is characterized in that, every excavation layer immediately carries out steel bar binding, when the steel bar binding is installed, it is reinforced by steel mold assembly and reserved. The pouring gate is then poured into the pouring gate. When the concrete is poured above the reserved pouring gate, the reserved opening is blocked until the concrete reaches the strength requirements, and the formwork is removed, and then the second layer of earthwork in the deep trench is excavated. 4.根据权利要求3所述的复杂环境下深沟槽支护逆作施工方法,其特征在于,进行钢筋安装时,在上层井体预留下节段钢筋,且上层井体的下节段钢筋与下层井体的钢筋焊接。4. The construction method for deep trench support reverse operation under complex environment according to claim 3, is characterized in that, when the reinforcement is installed, lower section reinforcement bars are reserved in the upper layer well body, and the lower segment of the upper layer well body is The steel bars are welded with the steel bars of the lower well body. 5.根据权利要求1至3任一项所述的复杂环境下深沟槽支护逆作施工方法,其特征在于,对土方进行开挖时,土方的开挖深度不超过土方的浇筑深度。5. The construction method for deep trench support in complex environment according to any one of claims 1 to 3, wherein when excavating the earthwork, the excavation depth of the earthwork does not exceed the pouring depth of the earthwork. 6.根据权利要求3所述的复杂环境下深沟槽支护逆作施工方法,其特征在于,混凝土支护结构每隔9m-10m设置2cm-3cm宽的伸缩缝。6 . The reverse construction method for deep trench support under complex environment according to claim 3 , wherein the concrete support structure is provided with expansion joints with a width of 2 cm to 3 cm every 9 m to 10 m. 7 . 7.根据权利要求5所述的复杂环境下深沟槽支护逆作施工方法,其特征在于,步骤S6中对底板进行浇筑前,检测承载力是否达到设计值,若不满足则采取500mm厚1:1粗砂碎石换填,随后再浇筑混凝土。7. The construction method for deep trench support reverse operation under complex environment according to claim 5, is characterized in that, before the bottom plate is poured in step S6, check whether the bearing capacity reaches the design value, if not satisfied, take 500mm thick 1:1 coarse sand and gravel replacement, followed by concrete pouring.
CN202110606691.XA 2021-05-31 2021-05-31 Deep groove support reverse construction method in complex environment Pending CN113216215A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110606691.XA CN113216215A (en) 2021-05-31 2021-05-31 Deep groove support reverse construction method in complex environment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110606691.XA CN113216215A (en) 2021-05-31 2021-05-31 Deep groove support reverse construction method in complex environment

Publications (1)

Publication Number Publication Date
CN113216215A true CN113216215A (en) 2021-08-06

Family

ID=77082082

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110606691.XA Pending CN113216215A (en) 2021-05-31 2021-05-31 Deep groove support reverse construction method in complex environment

Country Status (1)

Country Link
CN (1) CN113216215A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113944201A (en) * 2021-09-28 2022-01-18 中国港湾工程有限责任公司 Construction method for detecting underwater pipeline by using V-shaped exploration groove
CN116446407A (en) * 2023-05-15 2023-07-18 中国十七冶集团有限公司 Deep trench excavation construction method for river close to existing structure
CN119412066A (en) * 2024-09-02 2025-02-11 中建五局土木工程有限公司 Inverted well excavation construction method based on vertical mobile support of formwork support system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2093090A (en) * 1981-01-29 1982-08-25 Nishimatsu Constr Co Ltd Method and apparatus for making a deep trench
CN101550699A (en) * 2009-04-24 2009-10-07 浙江勤业建工集团有限公司 Construction method for large-diameter pipe protection around deep pit
CN109577337A (en) * 2017-09-29 2019-04-05 中国石油天然气股份有限公司 Construction Method of Deep Foundation Pit of Drainage Pipeline
CN110306616A (en) * 2019-08-02 2019-10-08 中交上海航道局有限公司 A kind of construction method of sewage conduct
CN110593264A (en) * 2019-08-01 2019-12-20 中建五局土木工程有限公司 Excavation construction method for underground pipeline in-situ protection long and narrow deep foundation pit
CN212027274U (en) * 2020-04-16 2020-11-27 中国建筑第二工程局有限公司 Shapping tool type anti-smashing shed for operation in groove of personnel
CN112064751A (en) * 2020-08-08 2020-12-11 上海静安市政工程有限公司 Deep groove construction method for drainage pipeline

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2093090A (en) * 1981-01-29 1982-08-25 Nishimatsu Constr Co Ltd Method and apparatus for making a deep trench
CN101550699A (en) * 2009-04-24 2009-10-07 浙江勤业建工集团有限公司 Construction method for large-diameter pipe protection around deep pit
CN109577337A (en) * 2017-09-29 2019-04-05 中国石油天然气股份有限公司 Construction Method of Deep Foundation Pit of Drainage Pipeline
CN110593264A (en) * 2019-08-01 2019-12-20 中建五局土木工程有限公司 Excavation construction method for underground pipeline in-situ protection long and narrow deep foundation pit
CN110306616A (en) * 2019-08-02 2019-10-08 中交上海航道局有限公司 A kind of construction method of sewage conduct
CN212027274U (en) * 2020-04-16 2020-11-27 中国建筑第二工程局有限公司 Shapping tool type anti-smashing shed for operation in groove of personnel
CN112064751A (en) * 2020-08-08 2020-12-11 上海静安市政工程有限公司 Deep groove construction method for drainage pipeline

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
崔泽英: "结合恒山路防洪渠施工谈高压旋喷桩在排水工程深沟槽作业中的应用", 《太原城市职业技术学院学报》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113944201A (en) * 2021-09-28 2022-01-18 中国港湾工程有限责任公司 Construction method for detecting underwater pipeline by using V-shaped exploration groove
CN116446407A (en) * 2023-05-15 2023-07-18 中国十七冶集团有限公司 Deep trench excavation construction method for river close to existing structure
CN119412066A (en) * 2024-09-02 2025-02-11 中建五局土木工程有限公司 Inverted well excavation construction method based on vertical mobile support of formwork support system
CN119412066B (en) * 2024-09-02 2025-10-10 中建五局土木工程有限公司 Inverted well excavation construction method based on vertical mobile support of formwork support system

Similar Documents

Publication Publication Date Title
CN108914931B (en) An assembled vertical shield ring foundation pile and construction method
CN106499413B (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN101215834A (en) Construction Method of Outrigger Type Diaphragm Wall
CN108442382A (en) It crosses the pressure line in-situ conservation of deep basal pit and goes along with sb. to guard him soil-baffling structure and construction method
CN104563146A (en) Construction method for open caisson engineering of fixed and direct burial type rainwater and sewage pumping station
CN110700280B (en) A diversion device and construction method for foundation pit support construction in narrow areas
CN115977102B (en) Combined construction structure and construction method of upper foundation pit and lower tunnel in saturated soft loess stratum
CN116591148B (en) Construction method of underground continuous wall system
CN110258582B (en) Inclined support foundation pit supporting structure based on steel pipe pile and Lassen steel plate and construction method
CN114703831A (en) Construction method of reinforced concrete cast-in-place pile under complex geological condition
CN115710912A (en) Narrow roadway foundation pit supporting process
CN113431097A (en) Protection structure of shallow foundation building next to deep foundation pit engineering and construction method
CN114622572A (en) Large-scale round foundation pit triaxial mixing pile supporting structure and construction method thereof
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN106065628B (en) Based on the major diameter running water pipe security protection construction method faced forever with reference to theory
CN112064751A (en) Deep groove construction method for drainage pipeline
CN114837213A (en) Tower crane foundation structure and construction method thereof
CN114232602A (en) Underground continuous pile construction process
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN103790148A (en) Combined treatment construction method for collapsible loess foundation
CN207878451U (en) A kind of device using hole rising pouring slurry ground-connecting-wall control influence of foundation excavation
CN111733827A (en) Construction method of deep foundation pit protection in the complex environment of adjacent high-speed railways under silt geology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210806