CN114703831A - Construction method of reinforced concrete cast-in-place pile under complex geological condition - Google Patents

Construction method of reinforced concrete cast-in-place pile under complex geological condition Download PDF

Info

Publication number
CN114703831A
CN114703831A CN202210415128.9A CN202210415128A CN114703831A CN 114703831 A CN114703831 A CN 114703831A CN 202210415128 A CN202210415128 A CN 202210415128A CN 114703831 A CN114703831 A CN 114703831A
Authority
CN
China
Prior art keywords
hole
slurry
reinforced concrete
cleaning
place pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210415128.9A
Other languages
Chinese (zh)
Inventor
籍跃奎
王东亮
卫芷
高晓霞
张俊生
马绥军
关军良
王龙强
莫红霞
杜喜明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shanxi Sijian Group Co Ltd
Original Assignee
China Shanxi Sijian Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shanxi Sijian Group Co Ltd filed Critical China Shanxi Sijian Group Co Ltd
Priority to CN202210415128.9A priority Critical patent/CN114703831A/en
Publication of CN114703831A publication Critical patent/CN114703831A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/385Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/0023Slurry
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Geology (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to the technical field of building construction, in particular to a construction method of a reinforced concrete cast-in-place pile under a complex geological condition, which comprises the following steps: s1, leveling the field and setting out the pile position; s2, forming holes, taking soil, and installing a steel protective cylinder to a position X meters away from the natural terrace; s3, performing slurry wall protection construction; s4, entering rock, pulling out pipes and cleaning holes; s5, placing a reinforcement cage; s6, pouring concrete; and S7, post grouting, and checking and accepting. The invention adopts the construction process of the cast-in-place pile with the steel casing and the mud casing and the bored hole, solves the problems of easy hole collapse and buried drilling of the cast-in-place pile under the complicated geological conditions of the ultra-thick fly ash layer, vibration hole collapse during rock entering, water source shortage, serious water leakage, poor wall protection forming and the like, greatly reduces the cost and the working strength, and improves the construction efficiency.

Description

一种复杂地质条件下钢筋混凝土灌注桩施工方法A construction method of reinforced concrete cast-in-place piles under complex geological conditions

技术领域technical field

本发明涉及建筑施工技术领域,更具体而言,涉及一种复杂地质条件下钢筋混凝土灌注桩施工方法。The invention relates to the technical field of building construction, and more particularly, to a construction method of reinforced concrete cast-in-place piles under complex geological conditions.

背景技术Background technique

针对深山沟谷地段、电厂粉煤灰回填层地质条件,存在工程原地质地貌不平、谷底标高高低不一、岩体强度不一、粉煤灰层回填厚度不均、回填厚度较厚等不利条件,同时粉煤灰层具有颗粒分散不均、结构疏松,易透水、易塌方,充盈系数大等缺点,通过数据对比分析,粉煤灰层在桩身受力中起负磨阻作用,同时粉煤灰内含物质对桩内钢筋有腐蚀作用等。In view of the geological conditions of the deep mountain valleys and the fly ash backfill layer of the power plant, there are unfavorable conditions such as uneven geology and landforms of the original project, different elevations of the valley bottom, different rock mass strength, uneven thickness of the fly ash layer, and thick backfill thickness. At the same time, the fly ash layer has the disadvantages of uneven particle dispersion, loose structure, easy water permeability, easy collapse, and large filling coefficient. Through data comparison and analysis, the fly ash layer plays a negative wear resistance role in the stress of the pile body, while the fly ash layer plays a negative role in the stress of the pile body. The material contained in the ash has a corrosive effect on the steel reinforcement in the pile.

经采用单一施工工艺多次试桩,均无法达到建设单位造价低、工期紧及高质量施工要求。其中采用全钢护筒单一施工工艺,虽能保证桩基质量,但是所需设备要求高,费用多,不经济;采用单一泥浆护壁,易塌孔,失水量大,影响坝体安全,有安全隐患,不能满足施工要求。After many tests of piles using a single construction process, the construction units could not meet the requirements of low cost, tight construction period and high-quality construction. Among them, the single construction process of all-steel casing can ensure the quality of the pile foundation, but the required equipment is high, the cost is high, and it is not economical; the use of a single mud wall is easy to collapse holes, and the water loss is large, which affects the safety of the dam body. Hidden danger, can not meet the construction requirements.

因此,有必要对现有技术进行改进。Therefore, it is necessary to improve the existing technology.

发明内容SUMMARY OF THE INVENTION

为了克服现有技术中存在的不足,提供一种复杂地质条件下钢筋混凝土灌注桩施工方法。In order to overcome the deficiencies in the prior art, a construction method for reinforced concrete cast-in-place piles under complex geological conditions is provided.

为了解决上述技术问题,本发明采用的技术方案为:In order to solve the above-mentioned technical problems, the technical scheme adopted in the present invention is:

一种复杂地质条件下钢筋混凝土灌注桩施工方法,包括:A construction method for reinforced concrete cast-in-place piles under complex geological conditions, comprising:

S1、场地平整、桩位放线;S1. The site is leveled, and the pile position is laid out;

S2、成孔、取土、安装钢护筒至距自然地坪X米处;S2. Make a hole, borrow soil, and install the steel casing to a distance of X meters from the natural floor;

S3、泥浆护壁施工至岩层;S3. The mud retaining wall is constructed to the rock formation;

S4、入岩、拔管、清孔;S4. Rock entry, extubation, and hole cleaning;

S5、安放钢筋笼;S5, place the steel cage;

S6、混凝土浇筑;S6. Concrete pouring;

S7、后注浆、检验验收。S7, post grouting, inspection and acceptance.

进一步的,所述S2中,采用搓管机成孔,调整搓管机位置就位,旋挖机取土,吊放并搓入第一节钢护筒、校对垂直度,使用冲抓斗从钢护筒内取土,边取土边下压钢护筒,当钢护筒高出导墙顶面12-1.5m时,安装第二节钢护筒并继续下压取土直至至距自然地坪Xm处;Further, in the described S2, a pipe rubbing machine is used to form a hole, the position of the pipe rubbing machine is adjusted to be in place, the rotary excavator is used to extract soil, the first section of the steel casing is hoisted and rubbed, the verticality is checked, and a punching bucket is used to remove the soil. Take soil from the steel casing, and press down the steel casing while taking the soil. When the steel casing is 12-1.5m higher than the top surface of the guide wall, install the second section of the steel casing and continue to press the soil down until the distance from the natural Floor Xm;

所述X的数值根据自然地坪标高和挖出的土质确定。The value of X is determined according to the natural floor elevation and the excavated soil quality.

进一步的,取土过程中,保持开挖面超过钢护筒底口的深度≥2.5m。Further, during the borrowing process, keep the depth of the excavation surface exceeding the bottom opening of the steel casing ≥ 2.5m.

进一步的,所述S3包括:Further, the S3 includes:

S31、泥浆制备,首先注入1Y m3自来水,搅拌半小时以后,边搅拌边投放120YKg复合膨润土,膨润土溶解后,均匀地投入0.5YKg羧甲基纤维素,然后依次投入1.5YKg火碱、1Ykg渗水明矾、2Ykg生石灰,Y的数值根据泥浆实际用量确定;S31, mud preparation, first inject 1Y m 3 tap water, after stirring for half an hour, put in 120 YKg of composite bentonite while stirring, after the bentonite is dissolved, evenly put in 0.5YKg carboxymethyl cellulose, then put in 1.5YKg caustic soda, 1Ykg water seepage in turn Alum, 2Ykg quicklime, the value of Y is determined according to the actual amount of mud;

S32、使用旋挖转斗将孔内钻渣依次挖出,至X米处放入化学泥浆直至钻孔完成。S32. Use a rotary digging bucket to dig out the drilling slag in the hole in turn, and put chemical mud at X meters until the drilling is completed.

进一步的,所述入岩包括:使用超深桩完成成孔作业,套管周边局部回填夯实,旋挖机冲抓锤在套管内,注入泥浆,使用旋挖钻斗将孔内钻渣依次挖出,在成孔过程中随时补充泥浆,保证护筒内泥浆水头压力;Further, the rock entry includes: using an ultra-deep pile to complete the hole forming operation, backfilling and compacting the surrounding of the casing, a rotary excavator punching a grab hammer into the casing, injecting mud, and using a rotary drilling bucket to excavate the drilling slag in the hole in turn. During the hole forming process, the mud is replenished at any time to ensure the mud head pressure in the casing;

所述清孔包括:旋挖钻机钻孔达到设计深度时,进行清孔,清孔后沉渣厚度≤50mm,钻至设计标高时使用带有活门的筒形钻清理沉渣,即一次清孔,清孔后提出钻头。The hole cleaning includes: cleaning the hole when the drilling of the rotary drilling rig reaches the design depth, the thickness of the sediment after cleaning the hole is ≤ 50mm, and using a cylindrical drill with a valve to clean the sediment when the hole is drilled to the design elevation, that is, cleaning the hole at one time and cleaning the hole. Lift the drill bit after the hole.

进一步的,钢筋笼制作严格按设计加工,主筋位置用钢筋定位支架控制等分距离,主筋间距允许偏差±10mm;箍筋或螺旋筋螺距允许偏差±20mm;钢筋笼直径允许偏差±10mm;钢筋笼长度允许偏差±50mm;每2m设置一道加劲箍,以加强钢筋笼的强度,钢筋笼的长度由挖孔深度确定;纵向钢筋焊接采用单面搭接焊,搭接长度≥10d;接头相互错开不小于35d,同一截面接头数量≤50%。Further, the rebar cage is manufactured in strict accordance with the design and processing. The position of the main rebar is controlled by the rebar positioning bracket to control the equal distance, the allowable deviation of the main rebar spacing is ±10mm; the allowable deviation of the pitch of stirrups or spiral bars is ±20mm; the allowable deviation of the diameter of the rebar cage is ±10mm; The allowable deviation of length is ±50mm; a stiffening hoop is set every 2m to strengthen the strength of the reinforcement cage, and the length of the reinforcement cage is determined by the depth of the digging hole; the longitudinal reinforcement welding adopts single-sided lap welding, and the lap length is greater than or equal to 10d; the joints are not staggered. Less than 35d, the number of joints in the same section is less than or equal to 50%.

进一步的,混凝土浇筑采用导管灌注,安放导管时,控制导管底部距孔底40cm,调整导管卡盘高度,将导管卡固,导管安放完毕后,检测孔底泥浆和孔底沉渣厚度,若两个条件同时满足要求,可直接灌注混凝土,如果有一项不能满足要求,需进行二次清孔。Further, the concrete is poured with conduit. When placing the conduit, control the bottom of the conduit to be 40cm from the bottom of the hole, adjust the height of the conduit chuck, and clamp the conduit. After the conduit is placed, check the thickness of the mud and sediment at the bottom of the hole. If the conditions meet the requirements at the same time, concrete can be poured directly. If one item cannot meet the requirements, secondary hole cleaning is required.

进一步的,所述二次清孔包括:将泥浆泵的高压管和灌注导管连接密封,开启泥浆泵,进行泥浆循环,当孔底沉渣厚度小于5cm后持续泥浆循环,以置换泥浆降低泥浆比重,当泥浆比重<1.15时,停止清孔,马上进行灌注;Further, the secondary hole cleaning includes: connecting and sealing the high-pressure pipe of the mud pump and the perfusion conduit, turning on the mud pump, and performing mud circulation, and when the thickness of the sediment at the bottom of the hole is less than 5cm, the mud circulation is continued to replace the mud and reduce the specific gravity of the mud. When the specific gravity of the mud is less than 1.15, the hole cleaning is stopped and the perfusion is carried out immediately;

清孔完毕与灌注混凝土的间隔时间不超过45分钟,以防孔内沉渣再次沉淀及钻孔缩颈的发生,浇注混凝土前,孔底500mm以内的泥浆比重应小于1.20。The interval between clearing the hole and pouring concrete should not exceed 45 minutes to prevent the sediment in the hole from re-precipitating and the occurrence of borehole necking. Before pouring concrete, the specific gravity of the mud within 500mm of the bottom of the hole should be less than 1.20.

为了确保桩顶部没有浮浆、杂质,混凝土浇筑至少超出设计桩顶标高500mm。In order to ensure that there is no laitance and impurities on the top of the pile, the concrete should be poured at least 500mm above the designed pile top elevation.

进一步的,后注浆过程中,水泥浆采用32.5MPa矿渣硅酸盐水泥,水灰比0.6,注浆量:桩端2000kg,桩群注浆应先外围后内部,采用A、B两桩轮换注浆。Further, in the post-grouting process, 32.5MPa slag Portland cement is used for the cement slurry, the water-cement ratio is 0.6, and the grouting amount is 2000kg at the pile end. Grouting.

本发明与现有技术相比所具有的有益效果为:Compared with the prior art, the present invention has the following beneficial effects:

1、本发明采用钢护筒+泥浆护壁钻孔灌注桩施工工艺,解决超厚粉煤灰层复杂地质条件灌注桩成桩易塌孔埋钻、入岩时振动塌孔、水源紧缺且水渗漏严重、护壁成型差等难题,极大地降低成本和工作强度、提高施工效率。1. The present invention adopts the construction technology of steel casing + mud wall bored cast-in-situ pile to solve the problems of super-thick fly ash layer and complex geological conditions. Serious leakage, poor wall protection and other problems, greatly reduce the cost and work intensity, and improve construction efficiency.

2、本发明发挥钢护筒和泥浆护壁组合施工工艺综合效果,钢护筒可工厂化生产,定型化安装,可重复周转利用,有效降低充盈系数;泥浆护壁解决了粉煤灰层及粉煤灰与原地层交界处塌方问题,造价低,效率高,成孔质量好,成桩质量优,有利于环境保护。2. The invention exerts the comprehensive effect of the combined construction technology of the steel casing and the mud wall. The steel casing can be produced in a factory, can be installed in a stereotyped manner, can be used repeatedly, and can effectively reduce the filling coefficient; the mud wall can solve the problem of the fly ash layer and the coal The landslide problem at the junction of the ash and the original stratum has low cost, high efficiency, good hole-forming quality, and excellent pile-forming quality, which is beneficial to environmental protection.

3、本发明采用自主研制的泥浆护壁配比,保证成孔质量。3. The present invention adopts the self-developed ratio of mud retaining wall to ensure the quality of hole formation.

附图说明Description of drawings

下面将通过附图对本发明的具体实施方式做进一步的详细说明。The specific embodiments of the present invention will be further described in detail below with reference to the accompanying drawings.

图1为本发明工艺流程图;Fig. 1 is the process flow diagram of the present invention;

图2为本发明后注浆施工工艺流程图;Fig. 2 is the post-grouting construction process flow chart of the present invention;

图3为泥浆护壁成孔剖面图。Figure 3 is a cross-sectional view of the mud retaining wall forming a hole.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

实施例:Example:

一种复杂地质条件下钢筋混凝土灌注桩施工方法,包括:A construction method for reinforced concrete cast-in-place piles under complex geological conditions, comprising:

S1、场地平整、桩位放线;S1. The site is leveled, and the pile position is laid out;

施工前将场地用挖掘机进行场地平整定位放线,预留200厚粉煤灰人工平整,场地平整度≦±10cm,保证桩基机械行驶及就位平稳,对放线和桩垂直度严格把控,现场放线前必须进行场地平整、压实,确保桩基机械行驶及就位平稳、准确。根据建设单位给定的坐标控制点,采用全站仪进行桩位放样及标高测定,并由RTK复测并误差控制在5mm之内。Before construction, use an excavator for site leveling, positioning and laying out, and reserve 200 thick fly ash for manual leveling. The site must be leveled and compacted before the on-site lay-out to ensure that the mechanical driving and positioning of the pile foundation is stable and accurate. According to the coordinate control point given by the construction unit, the total station is used to carry out the stakeout and elevation measurement, and the RTK is re-measured and the error is controlled within 5mm.

S2、成孔、取土、安装钢护筒至距自然地坪X米处;S2. Make a hole, borrow soil, and install the steel casing to a distance of X meters from the natural floor;

根据测量放样的桩点,待履带式起重机配合搓管机粗略就位,再次复测,调整搓管机位置直到精准就位,采用280旋挖机取土,吊放并搓入第一节钢护筒,校对垂直度,压入深度约为2.5m-3.5m,然后用冲抓斗从钢护筒内取土,一边抓土、一边下压钢护筒,保持开挖面超过钢护筒底口深度大于等于2.5m,第一节钢护筒下压至钢护筒高出导墙顶面1.5m时,检测垂直度,如不合格则进行纠偏调整,如合格则安装第二节钢护筒继续下压取土。以此类推,挖至距自然地坪Xm处。According to the measured stake points, after the crawler crane and the pipe rubbing machine are roughly in place, repeat the test again, adjust the position of the pipe rubbing machine until it is accurately in place, use a 280 rotary excavator to extract soil, hoist and rub the first section of steel Protect the tube, check the verticality, press the depth of about 2.5m-3.5m, and then use a punching bucket to extract soil from the steel tube, while grabbing the soil, press the steel tube down, and keep the excavation surface beyond the steel tube. The depth of the bottom opening is greater than or equal to 2.5m. When the first section of the steel casing is pressed down until the steel casing is 1.5m higher than the top surface of the guide wall, check the verticality. The protective tube continues to press down to extract soil. And so on, dig to Xm from the natural floor.

X的数值根据自然地坪标高和挖出的土质确定,经对本实施例所面对地质条件进行分析发现:埋深在35m~40m以上的粉煤灰层夹炉渣,结构疏松、渗水性最强;埋深在40m以下及粉煤灰与原地层交界处塌方严重,但透水性弱,因此,选择X为40,从地面以下至埋深40m范围内采用280钻机及冲抓斗钢护筒跟进成孔施工,可解决粉煤灰易透水、易塌方、充盈系数大及粉煤灰负摩阻和桩身成型不好等质量问题。在40m以下采用400钻机钻岩结合自配泥浆护壁。The value of X is determined according to the natural floor elevation and the excavated soil quality. After analyzing the geological conditions faced by this example, it is found that the slag sandwiched by the fly ash layer with a buried depth of more than 35m to 40m has a loose structure and the strongest water permeability. ; The buried depth is below 40m and the landslide is serious at the junction of the fly ash and the original stratum, but the water permeability is weak. Therefore, choose X to be 40, and use a 280 drilling rig and a punching grab steel casing from below the ground to the buried depth of 40m. The hole-forming construction can solve the quality problems such as fly ash easy to permeate, easy to collapse, large filling coefficient, negative friction of fly ash and poor pile shape. Below 40m, 400 drilling rigs are used to drill rock combined with self-configured mud wall protection.

S3、泥浆护壁施工;S3, mud wall construction;

S31、泥浆的制备:首先注入1*Y m3自来水,搅拌半小时以后,边搅拌边投放120*YKg复合膨润土,膨润土溶解后,均匀地投入0.5*YKg羧甲基纤维素,然后依次投入1.5*YKg火碱、1*Ykg渗水明矾、2*Ykg生石灰,Y的数值根据泥浆实际用量确定。S31. Preparation of mud: firstly inject 1*Y m 3 tap water, and after stirring for half an hour, put in 120*YKg composite bentonite while stirring, after the bentonite is dissolved, evenly put in 0.5*YKg carboxymethyl cellulose, and then put in 1.5*YKg in turn *YKg caustic soda, 1*Ykg seepage alum, 2*Ykg quicklime, the value of Y is determined according to the actual amount of mud.

S32、钻机就位:首先做好场地的平整,使主机左右履带板处于同一水平面上,动力头施工位置朝履带顺直方向布置,调整好机身前后左右的水平。并将钻机桅杆调整至垂直于孔口的水平面,使钻头中心置于护筒内的桩中心位置。S32. The drilling rig is in place: First, level the site so that the left and right crawler shoes of the main machine are on the same horizontal plane, and the construction position of the power head is arranged in the straight direction of the crawler, and the level of the front, rear, left and right of the fuselage is adjusted. Adjust the rig mast to a level perpendicular to the orifice so that the center of the drill bit is at the center of the pile inside the casing.

S33、用旋挖钻斗将孔内钻渣依次挖出,至40m处向桩孔内放入化学泥浆,直到钻孔完成。S33. Use a rotary drilling bucket to excavate the drilling slag in the hole in turn, and put chemical mud into the pile hole at a distance of 40m until the drilling is completed.

S4、入岩、拔管、清孔;S4. Rock entry, extubation, and hole cleaning;

采用桩长L≥50m且长径比L/D≥50的桩,用特制钻杆44×5×19.5完成成孔作业,套管周边局部回填夯实,400旋挖机冲抓锤在套管内,注入足够的泥浆,然后旋挖钻斗将孔内钻渣依次挖出,并在成孔过程中随时补充泥浆,保证护筒内泥浆水头压力,安排装载机将钻斗挖出的钻渣清理到场外。如在钻挖过程中遇到孤石、瓢石或者大体岩体、坚硬岩层时更换金刚钻,随时查看桅杆垂直度,控制桩孔垂直度,直到设计入岩深度。Use piles with pile length L ≥ 50m and length-diameter ratio L/D ≥ 50. Use special drill pipe 44×5×19.5 to complete the hole forming operation. Part of the surrounding of the casing is backfilled and compacted, and the 400 rotary excavator punches the hammer in the casing. Inject enough mud, and then dig out the drilling slag in the hole in turn with the rotary drilling bucket, and replenish the mud at any time during the hole forming process to ensure the head pressure of the mud in the casing. outside. If the diamond drill is replaced when encountering boulders, ladle stones or general rock mass or hard rock formation during the drilling process, check the verticality of the mast at any time, and control the verticality of the pile hole until the designed rock penetration depth.

旋挖钻机钻孔达到设计深度时,应及时清孔,清孔后沉渣不得大于50mm。钻至设计标高时用带有活门的筒形钻清理沉渣,即一次清孔。清孔后提出钻头,进行孔径、孔深、垂直度检测,验收合格后,移走钻机,盖好盖板,进行下道工序施工。When the drilling of the rotary drilling rig reaches the design depth, the hole should be cleaned in time, and the sediment should not be larger than 50mm after cleaning. When drilling to the design level, use a cylindrical drill with a valve to clean up the sediment, that is, clear the hole at one time. After clearing the hole, put out the drill bit, and test the hole diameter, hole depth, and verticality. After the acceptance is qualified, remove the drilling rig, cover the cover plate, and proceed to the next process construction.

S5、安放钢筋笼;S5, place the steel cage;

钢筋笼制作严格按设计加工,主筋位置用钢筋定位支架控制等分距离。主筋间距允许偏差±10mm;箍筋或螺旋筋螺距允许偏差±20mm;钢筋笼直径允许偏差±10mm;钢筋笼长度允许偏差±50mm。加劲箍每2m一道,以加强钢筋笼的强度,钢筋笼的长度由挖孔深度确定;纵向钢筋焊接采用单面搭接焊,搭接长度≥10d。接头相互错开不小于35d,同一截面接头数量≤50%。钢筋笼搬运和吊装时,应防止变形;安放前需再检查孔内的情况,以确定孔内无塌方和沉渣;安放要对准孔位,扶稳、缓慢、顺直,避免碰撞孔壁,严禁墩笼、扭笼。The reinforcement cage is manufactured in strict accordance with the design and processing, and the position of the main reinforcement is controlled by the reinforcement positioning bracket to control the equal distance. The allowable deviation of the spacing of the main bars is ±10mm; the allowable deviation of the pitch of the stirrups or spiral bars is ±20mm; the allowable deviation of the diameter of the steel cage is ±10mm; the allowable deviation of the length of the steel cage is ±50mm. Stiffening hoop is installed every 2m to strengthen the strength of the reinforcement cage. The length of the reinforcement cage is determined by the depth of the digging hole; the longitudinal reinforcement welding adopts single-sided lap welding, and the lap length is greater than or equal to 10d. The joints should be staggered by not less than 35d, and the number of joints in the same section should be less than or equal to 50%. When handling and hoisting, the steel cage should be prevented from being deformed; it is necessary to check the situation in the hole before placing it to make sure that there is no collapse and sediment in the hole; the placement should be aligned with the hole position, stabilized, slow, and straight to avoid collision with the hole wall. It is strictly forbidden to pierce the cage and twist the cage.

S6、混凝土浇筑;S6. Concrete pouring;

钢筋笼安放后进行沉渣厚度测设,满足沉渣厚度不大于5cm后安装混凝土导管,混凝土采用导管灌注,导管内径为300mm,螺丝扣连接。检查导管外观,导管内壁应圆滑、顺直、光洁和无局部凹凸。根据套管顶标高,孔底标高,计算导管所需长度对导管进行试拼,并进行编号。导管采用吊车配合人工安装,导管安放时,人工配合扶稳使位置居钢筋笼中心,然后稳步沉放、防止卡挂钢筋骨架和碰撞孔壁。安装时控制导管底距孔底40cm。导管高度确定后,用吊车调整导管卡盘高度,用卡盘将导管卡住。After the reinforcement cage is placed, the thickness of the sediment is measured and designed. If the thickness of the sediment is not greater than 5cm, the concrete conduit is installed. The concrete is poured with the conduit. The inner diameter of the conduit is 300mm and the turnbuckle connection. Check the appearance of the catheter, the inner wall of the catheter should be smooth, straight, smooth and free of local bumps. According to the elevation of the top of the casing, the elevation of the bottom of the hole, and to calculate the required length of the conduit, try to assemble the conduit and number it. The duct is installed manually by a crane. When the duct is placed, it should be stabilized manually to make the position in the center of the steel cage, and then it is steadily placed to prevent the steel frame from being stuck and colliding with the wall of the hole. When installing, the bottom of the control conduit should be 40cm away from the bottom of the hole. After the height of the conduit is determined, adjust the height of the conduit chuck with a crane, and clamp the conduit with the chuck.

导管安放工序结束后,检测孔底泥浆和孔底沉渣厚度,若两个条件同时满足要求,可直接灌注混凝土。如果有一项不能满足要求,需进行二次清孔。二次清孔时,将泥浆泵的高压管和灌注导管连接密封,开启泥浆泵,进行泥浆循环,当孔底沉渣厚度小于5cm后应再进行一段时间的泥浆循环,以置换泥浆降低泥浆比重,当泥浆比重<1.15时,方可停止清孔,马上进行灌注,清孔完毕与灌注混凝土的间隔时间不超过45分钟,以防孔内沉渣再次沉淀及钻孔缩颈的发生。浇注混凝土前,孔底500mm以内的泥浆比重应小于1.20。After the conduit placement process is completed, the thickness of the mud at the bottom of the hole and the sediment at the bottom of the hole are detected. If the two conditions meet the requirements at the same time, concrete can be poured directly. If there is one item that cannot meet the requirements, a secondary hole cleaning is required. When cleaning the hole for the second time, connect and seal the high-pressure pipe of the mud pump and the pouring pipe, turn on the mud pump, and carry out mud circulation. When the specific gravity of the mud is less than 1.15, the hole cleaning can be stopped, and the pouring shall be carried out immediately. The interval between the completion of the hole cleaning and the pouring of concrete shall not exceed 45 minutes to prevent the sediment in the hole from re-precipitating and the occurrence of borehole necking. Before pouring concrete, the specific gravity of the mud within 500mm of the bottom of the hole should be less than 1.20.

在浇注混凝土前,应进行清孔,要求孔壁、孔底必须清理干净,孔底无浮渣,孔壁无松动。当有地下水而渗水量不大时,则应抽除孔内积水后,用导管法浇注混凝土。导管未端离孔底不宜大于1.5m;混凝土宜采用插入式振捣器振实,每浇注1.5m振捣一次。混凝土应连续浇筑振捣密实,充盈系数大于1。浇筑混凝土至少超出设计桩顶标高500mm,以确保桩顶处没有浮浆、杂质。Before pouring concrete, the hole should be cleaned, and it is required that the hole wall and hole bottom must be cleaned, there is no scum at the bottom of the hole, and the hole wall is not loose. When there is groundwater and the seepage amount is not large, the water in the hole should be removed, and then the concrete should be poured by the conduit method. The distance between the end of the pipe and the bottom of the hole should not be greater than 1.5m; the concrete should be vibrated with a plug-in vibrator, and vibrated once every 1.5m of pouring. Concrete should be continuously poured and compacted, and the filling factor should be greater than 1. Pour concrete at least 500mm above the designed pile top elevation to ensure that there is no floating slurry and impurities at the pile top.

灌桩过程中因跟进式护筒埋设较深,不能整体拔出,影响成桩质量,采用分节拔取,当灌桩混凝土面升至跟进式护筒内时,跟进式全护筒与旋挖钻机动力头驱动套连接,转动跟进式护筒,直到转动,方可进行继续灌桩作业,混凝土面每升6m,旋挖钻机和全护筒再次连接,钻机带动力头驱动套拔取2节跟进式护筒,辅助工使用液泡水准仪测量、调整跟进式护筒的垂直度。如此重复,直至最后全部灌完,拔出全部套管。During the piling process, since the follow-up type casing is deeply buried, it cannot be pulled out as a whole, which affects the quality of the pile, so it is extracted by sections. Connect with the power head driving sleeve of the rotary drilling rig, turn the follow-up casing until it rotates, and then continue the piling operation. The concrete surface is 6m per liter. The rotary drilling rig and the full casing are connected again. The drilling rig has a power head driving sleeve. Take out 2 sections of the follow-up protective tube, and the auxiliary worker uses a bubble level to measure and adjust the verticality of the follow-up protective tube. Repeat this until the final filling is completed, and all the casings are pulled out.

混凝土使用C40 P6商品混凝土,塌落度160~180mm,混凝土浇筑塌落度180mm±20mm,初凝时间不小于45分钟,且不大于2小时,终凝时间不大于6小时,混凝土浇筑时间10m3/30分钟,混凝土浇筑时淹没护筒的高度不得大于3m,混凝土浇筑至拔管高度后即进行拔管,拔管时间控制在1m/6分钟。成孔所产生的渣土采用自卸汽车运至业主指定地点。成桩后,成孔不再循环利用的泥浆采用泥浆车密闭运弃至业主指定地The concrete shall be C40 P6 commercial concrete, with a slump of 160-180mm, a concrete pouring slump of 180mm±20mm, an initial setting time of not less than 45 minutes and not more than 2 hours, a final setting time of not more than 6 hours, and a concrete pouring time of 10m 3 / 30 minutes, the height of the submerged casing shall not be greater than 3m when the concrete is poured, and the extubation shall be carried out after the concrete is poured to the extubation height, and the extubation time shall be controlled at 1m/6 minutes. The muck produced by the hole formation is transported to the place designated by the owner by dump truck. After the pile is formed, the mud that is no longer recycled after the hole is formed shall be transported in a sealed manner by a mud truck to the site designated by the owner.

S7、后注浆、检验验收。S7, post grouting, inspection and acceptance.

按设计水灰比搅拌水泥浆→水泥浆经过滤至储浆灌,准备灌浆→将注浆管活接头与桩身压浆管连接→打开排气阀并开泵放气→关闭排气阀压浆,终止标准由压浆量、压力以及地面是否返浆来综合控制:终止压浆时关闭止浆阀静置5—10分钟再拆卸管件,压浆管头用堵头再次堵上。Stir the cement slurry according to the designed water-cement ratio → the cement slurry is filtered to the storage slurry and ready for grouting → connect the grouting pipe joint to the pile grouting pipe → open the exhaust valve and open the pump to release air → close the exhaust valve pressure Slurry, the termination standard is comprehensively controlled by the amount of grouting, pressure and whether the ground returns to grouting: when grouting is terminated, close the stop valve and let it stand for 5-10 minutes before disassembling the pipe fittings, and plug the grouting pipe head again with a plug.

压浆管采用Φ25mm*3mm钢管桩底对称布置2根,长度与钢筋笼长度相配合,采用螺纹箍缠生胶带连接,注浆管丝扣加工不得少于四圈,压浆管用铁丝绑缚于钢筋笼上,随钢筋笼下入孔内,混凝土灌注后压浆管应露出施工作业面不少于30cm,底部伸出钢筋笼50cm。Two grouting pipes are arranged symmetrically at the bottom of Φ25mm*3mm steel pipe piles, the length is matched with the length of the steel cage, and the grouting pipe is connected with raw tape. On the steel cage, the grouting pipe should be exposed at least 30cm from the construction work surface after the concrete is poured into the hole with the steel cage, and 50cm from the bottom of the steel cage.

桩侧桩端后压浆技术参数的确定:Determination of technical parameters of post grouting at pile side and pile end:

水泥浆:采用32.5MPa矿渣硅酸盐水泥,水灰比0.6,注浆量:桩端2000kg。Cement slurry: 32.5MPa slag Portland cement, water-cement ratio 0.6, grouting amount: 2000kg at the pile end.

压力控制:大于等于3MPa,当注浆压力长时间低于正常值或地面出现冒浆或周围桩孔窜浆,应改为间歇注浆,间歇时间宜为30-60分钟,或调低浆液水灰比。Pressure control: greater than or equal to 3MPa, when the grouting pressure is lower than the normal value for a long time or the ground appears grouting or the surrounding pile holes channel grouting, it should be changed to intermittent grouting, the intermittent time should be 30-60 minutes, or the slurry water should be reduced grey ratio.

压浆时间:在混凝土灌注完成后,注浆作业于2d后开始,不宜迟于成桩30d后,注浆作业与成孔作业点的距离不宜小于8—10m。Grouting time: After the concrete is poured, the grouting operation should start after 2 days, and it should not be later than 30 days after the pile is formed. The distance between the grouting operation and the hole forming operation point should not be less than 8-10m.

注浆顺序:对于桩群注浆应先外围后内部,采用A、B两桩轮换注浆。Grouting sequence: For pile group grouting, the outer grouting should be done first and then the interior, and two piles A and B should be alternately grouted.

上面仅对本发明的较佳实施例作了详细说明,但是本发明并不限于上述实施例,在本领域普通技术人员所具备的知识范围内,还可以在不脱离本发明宗旨的前提下作出各种变化,各种变化均应包含在本发明的保护范围之内。Only the preferred embodiments of the present invention have been described in detail above, but the present invention is not limited to the above-mentioned embodiments, and within the scope of knowledge possessed by those of ordinary skill in the art, various aspects can also be made without departing from the purpose of the present invention. Various changes should be included within the protection scope of the present invention.

Claims (10)

1. A construction method of a reinforced concrete cast-in-place pile under a complex geological condition is characterized by comprising the following steps:
s1, leveling the field and setting out the pile position;
s2, forming holes, taking soil, and installing a steel casing to a position X meters away from the natural terrace;
s3, performing slurry wall protection construction;
s4, entering rock, pulling out pipes and cleaning holes;
s5, placing a reinforcement cage;
s6, pouring concrete;
and S7, post grouting, and checking and accepting.
2. The method for constructing the reinforced concrete cast-in-place pile under the complicated geological condition according to claim 1, which is characterized by comprising the following steps of: in the step S2, a pipe rolling machine is adopted to form a hole, the position of the pipe rolling machine is adjusted to be in place, a rotary digging machine is used for taking soil, the first section of steel protective cylinder is hung and rolled in, the verticality is corrected, a punching grab bucket is used for taking soil from the steel protective cylinder, the steel protective cylinder is pressed down while taking soil, when the steel protective cylinder is 12-1.5m higher than the top surface of the guide wall, a second section of steel protective cylinder is installed, and soil is continuously pressed down until the position is Xm away from the natural terrace;
and the numerical value of the X is determined according to the elevation of the natural terrace and the excavated soil quality.
3. The method for constructing the reinforced concrete cast-in-place pile under the complicated geological condition as recited in claim 2, characterized in that: and in the soil taking process, the depth of the excavation surface exceeding the bottom opening of the steel casing is kept to be more than or equal to 2.5 m.
4. The method for constructing the reinforced concrete cast-in-place pile under the complicated geological condition according to claim 1, which is characterized by comprising the following steps of: the S3 includes:
s31, preparing slurry, firstly injecting 1 x Y m3After stirring for half an hour, adding 120 × YKg composite bentonite while stirring, after the bentonite is dissolved, uniformly adding 0.5 × YKg carboxymethyl cellulose, and then sequentially adding 1.5 × YKg caustic soda, 1 × Ykg water-seepage alum and 2 × Ykg quicklime, wherein the value of Y is determined according to the actual dosage of the slurry;
and S32, sequentially digging out drilling residues in the hole by using a rotary digging bucket, and putting chemical slurry into the position of X meters until the drilling is finished.
5. The method for constructing the reinforced concrete cast-in-place pile under the complicated geological condition according to claim 1, which is characterized by comprising the following steps of: the rock entering comprises: using the ultra-deep pile to finish hole forming operation, locally backfilling and tamping the periphery of the sleeve, using a punching and grabbing hammer of a rotary excavator to inject slurry into the sleeve, using a rotary drilling bucket to sequentially dig out drilling slag in holes, replenishing the slurry at any time in the hole forming process, and ensuring the water head pressure of the slurry in the pile casing;
the hole cleaning comprises: and when the drill hole of the rotary drilling rig reaches the designed depth, cleaning the hole, cleaning the sediment with the thickness of less than or equal to 50mm after cleaning the hole, cleaning the sediment by using a cylindrical drill with a valve when the drill hole reaches the designed elevation, and taking out the drill bit after cleaning the hole.
6. The method for constructing the reinforced concrete cast-in-place pile under the complicated geological condition according to claim 1, which is characterized by comprising the following steps of: the steel reinforcement cage is manufactured strictly according to the design, the position of the main reinforcement is controlled by a steel reinforcement positioning bracket to be equally spaced, and the allowable deviation of the space between the main reinforcements is +/-10 mm; the allowable deviation of the screw pitch of the stirrup or the spiral rib is +/-20 mm; the allowable deviation of the diameter of the reinforcement cage is +/-10 mm; the length of the reinforcement cage is allowed to deviate +/-50 mm; arranging a stiffening hoop every 2m to strengthen the strength of the reinforcement cage, wherein the length of the reinforcement cage is determined by the depth of the excavated hole; the longitudinal steel bar welding adopts single-side lap welding, and the lap length is more than or equal to 10 d; the joints are staggered with each other by not less than 35d, and the number of the joints on the same section is not more than 50%.
7. The method for constructing the reinforced concrete cast-in-place pile under the complicated geological condition according to claim 1, which is characterized by comprising the following steps of: the concrete pouring adopts the conduit to pour, when the conduit is placed, the bottom of the conduit is controlled to be 40cm away from the bottom of the hole, the height of the conduit clamping disc is adjusted, the conduit is clamped and fixed, after the conduit is placed, the thickness of slurry at the bottom of the hole and the thickness of sediment at the bottom of the hole are detected, if two conditions meet the requirements at the same time, concrete can be directly poured, and if one condition cannot meet the requirements, secondary hole cleaning is needed.
8. The method for constructing the reinforced concrete cast-in-place pile under the complicated geological condition as recited in claim 7, wherein: the secondary hole cleaning comprises: connecting and sealing a high-pressure pipe of a slurry pump and a pouring guide pipe, starting the slurry pump, circulating slurry, continuously circulating the slurry after the thickness of sediment at the bottom of a hole is less than 5cm so as to replace the slurry and reduce the specific gravity of the slurry, and stopping cleaning the hole when the specific gravity of the slurry is less than 1.15, and immediately pouring;
the time interval between the completion of hole cleaning and concrete pouring does not exceed 45 minutes, so that the occurrence of sediment in the hole re-precipitation and necking of the drilled hole is avoided, and the specific gravity of the slurry within 500mm of the hole bottom is less than 1.20 before the concrete is poured.
9. The method for constructing the reinforced concrete cast-in-place pile under the complicated geological condition according to claim 1, which is characterized by comprising the following steps of: and pouring concrete at least 500mm higher than the designed pile top elevation.
10. The method for constructing the reinforced concrete cast-in-place pile under the complicated geological condition according to claim 1, which is characterized by comprising the following steps of: in the post-grouting process, the cement paste adopts 32.5MPa slag portland cement, the water cement ratio is 0.6, and the grouting amount is as follows: the pile end is 2000kg, the pile group is grouted firstly from the periphery to the inside, and A, B piles are used for alternate grouting.
CN202210415128.9A 2022-04-20 2022-04-20 Construction method of reinforced concrete cast-in-place pile under complex geological condition Pending CN114703831A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210415128.9A CN114703831A (en) 2022-04-20 2022-04-20 Construction method of reinforced concrete cast-in-place pile under complex geological condition

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210415128.9A CN114703831A (en) 2022-04-20 2022-04-20 Construction method of reinforced concrete cast-in-place pile under complex geological condition

Publications (1)

Publication Number Publication Date
CN114703831A true CN114703831A (en) 2022-07-05

Family

ID=82174126

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210415128.9A Pending CN114703831A (en) 2022-04-20 2022-04-20 Construction method of reinforced concrete cast-in-place pile under complex geological condition

Country Status (1)

Country Link
CN (1) CN114703831A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115369860A (en) * 2022-09-30 2022-11-22 中建八局第二建设有限公司 Construction method of super-long isolation pile close to subway
CN115652911A (en) * 2022-10-21 2023-01-31 重庆大学溧阳智慧城市研究院 Method for protecting wall of screw thread soil-sampling cast-in-situ bored pile
CN116479954A (en) * 2023-05-06 2023-07-25 保利长大工程有限公司 A test method for bridge prefabricated tubular piles in complex geological conditions

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101684648A (en) * 2008-09-28 2010-03-31 要明伦 Compound reinforcing method capable of rapidly falling-silt, promoting-seepage, prepressing, reinforcing and blow filling soft clay
CN102086645A (en) * 2009-12-07 2011-06-08 中交第三航务工程勘察设计院有限公司 Socketed pile and construction method thereof
CN102747725A (en) * 2012-07-13 2012-10-24 中铁二十四局集团上海铁建工程有限公司 Bored pile construction method with tiny disturbance
CN103088814A (en) * 2013-02-27 2013-05-08 路桥华祥国际工程有限公司 Rotary drilling rig coordinated with percussion drill hole-forming construction method
CN104120716A (en) * 2013-04-28 2014-10-29 杨哲 Slurry wall protection construction method for bored pile
CN105239563A (en) * 2015-10-27 2016-01-13 贵州开磷建设集团有限公司 Dry-method hole forming filling pile structure for post-grouting matched rotary drilling rig and construction method
CN105649012A (en) * 2015-12-30 2016-06-08 中铁局集团有限公司 Construction method for bored pile of subway station enclosure structure of upper-soft lower-hard ground
CN106087997A (en) * 2016-07-26 2016-11-09 中铁建大桥工程局集团第五工程有限公司 A kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method
CN107524142A (en) * 2017-09-20 2017-12-29 中国二十冶集团有限公司 A kind of holing with slurry wall protection cast-in-place pile construction method
CN109469052A (en) * 2018-09-13 2019-03-15 深圳市蛇口招商港湾工程有限公司 A kind of miscellaneous fill and muddy terrain pile base construction method
CN109488202A (en) * 2018-11-05 2019-03-19 云南建投第三建设有限公司 A kind of gravel rock stratum pile foundation drilling construction engineering method containing gravel-boulder bed
CN110206493A (en) * 2019-07-10 2019-09-06 贵州建工梵净山建筑工程有限公司 A kind of full-sleeve full-rotation construction process for bored pile
CN110924383A (en) * 2019-10-31 2020-03-27 国家电网有限公司 Construction method of pressurized cast-in-place pile based on reinforced fibers and metakaolin
CN111560950A (en) * 2020-04-20 2020-08-21 中铁十二局集团有限公司 Pile hole forming method for cast-in-place pile
CN112852073A (en) * 2021-03-18 2021-05-28 辽宁工程技术大学 Preparation method of argillized gangue curing agent
CN113668527A (en) * 2021-08-04 2021-11-19 深圳宏业基岩土科技股份有限公司 Construction method for inserting long steel pile casing under rotary digging pile construction of deep rockfill silt stratum

Patent Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101684648A (en) * 2008-09-28 2010-03-31 要明伦 Compound reinforcing method capable of rapidly falling-silt, promoting-seepage, prepressing, reinforcing and blow filling soft clay
CN102086645A (en) * 2009-12-07 2011-06-08 中交第三航务工程勘察设计院有限公司 Socketed pile and construction method thereof
CN102747725A (en) * 2012-07-13 2012-10-24 中铁二十四局集团上海铁建工程有限公司 Bored pile construction method with tiny disturbance
CN103088814A (en) * 2013-02-27 2013-05-08 路桥华祥国际工程有限公司 Rotary drilling rig coordinated with percussion drill hole-forming construction method
CN104120716A (en) * 2013-04-28 2014-10-29 杨哲 Slurry wall protection construction method for bored pile
CN105239563A (en) * 2015-10-27 2016-01-13 贵州开磷建设集团有限公司 Dry-method hole forming filling pile structure for post-grouting matched rotary drilling rig and construction method
CN105649012A (en) * 2015-12-30 2016-06-08 中铁局集团有限公司 Construction method for bored pile of subway station enclosure structure of upper-soft lower-hard ground
CN106087997A (en) * 2016-07-26 2016-11-09 中铁建大桥工程局集团第五工程有限公司 A kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method
CN107524142A (en) * 2017-09-20 2017-12-29 中国二十冶集团有限公司 A kind of holing with slurry wall protection cast-in-place pile construction method
CN109469052A (en) * 2018-09-13 2019-03-15 深圳市蛇口招商港湾工程有限公司 A kind of miscellaneous fill and muddy terrain pile base construction method
CN109488202A (en) * 2018-11-05 2019-03-19 云南建投第三建设有限公司 A kind of gravel rock stratum pile foundation drilling construction engineering method containing gravel-boulder bed
CN110206493A (en) * 2019-07-10 2019-09-06 贵州建工梵净山建筑工程有限公司 A kind of full-sleeve full-rotation construction process for bored pile
CN110924383A (en) * 2019-10-31 2020-03-27 国家电网有限公司 Construction method of pressurized cast-in-place pile based on reinforced fibers and metakaolin
WO2021082767A1 (en) * 2019-10-31 2021-05-06 国家电网有限公司 Method for constructing reinforced fiber and metakaolin-based pressurized cast-in-place pile
CN111560950A (en) * 2020-04-20 2020-08-21 中铁十二局集团有限公司 Pile hole forming method for cast-in-place pile
CN112852073A (en) * 2021-03-18 2021-05-28 辽宁工程技术大学 Preparation method of argillized gangue curing agent
CN113668527A (en) * 2021-08-04 2021-11-19 深圳宏业基岩土科技股份有限公司 Construction method for inserting long steel pile casing under rotary digging pile construction of deep rockfill silt stratum

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
武汉地质学院主编: "钻探工艺学", vol. 1, 31 July 1987, 地质出版社, pages: 63 - 66 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115369860A (en) * 2022-09-30 2022-11-22 中建八局第二建设有限公司 Construction method of super-long isolation pile close to subway
CN115652911A (en) * 2022-10-21 2023-01-31 重庆大学溧阳智慧城市研究院 Method for protecting wall of screw thread soil-sampling cast-in-situ bored pile
CN116479954A (en) * 2023-05-06 2023-07-25 保利长大工程有限公司 A test method for bridge prefabricated tubular piles in complex geological conditions

Similar Documents

Publication Publication Date Title
CN106545005B (en) A kind of reinforcing body and reinforcement means of subway tunnel shield end
WO2022096024A1 (en) Construction method for super-long small-diameter hole bored pile
AU2021106928A4 (en) Construction method for excavation of deep pit with triaxial mixing pile waterstop curtains and rotary bored cast-in-place pile supports
CN114703831A (en) Construction method of reinforced concrete cast-in-place pile under complex geological condition
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN108894214A (en) A kind of solution cavity geological environment bored concrete pile and its bore forming method
CN110593254A (en) Construction method of cast-in-situ bored pile in stratum with karst cave in joint zone
CN103015429A (en) Long auger rotary-jet mixing steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN104695458A (en) Construction method of deep stirring and jet grouting compound pile waterproof curtain
CN114622572A (en) Large-scale round foundation pit triaxial mixing pile supporting structure and construction method thereof
CN114016495A (en) Construction method for underground continuous wall system under weak geological conditions in sea reclamation area
CN112609690A (en) Construction method of rotary drilling cast-in-place pile in sea-filling geological complex area
CN114875972A (en) Open-cut top-down foundation pit main structure construction method
CN116446385A (en) A karst non-filled cast-in-situ pile structure and its construction method
CN114737979B (en) Construction method for continuously passing large-diameter water conveying pipeline downwards in shield region
CN115717397A (en) Larsen steel sheet pile and prestressed anchor cable combined supporting construction method
CN110777775A (en) Foundation pit structure and construction method thereof
CN116043824A (en) A rapid construction method of ground connection wall in complex strata with upper soft and lower hard
CN114575355A (en) Soil protection and descent construction method
CN113216215A (en) Deep groove support reverse construction method in complex environment
CN114439024A (en) A kind of steel pipe curtain auxiliary pile foundation hole forming construction technology
CN116122314A (en) Construction method of locking steel pipe pile cofferdam
CN213417870U (en) High rich water loess sand cobble stratum vary voltage tube well structure in
CN115369906A (en) Construction method for beaded karst cave pile foundation in karst development area
CN114411758A (en) A construction technology of multi-axial grouting piles for foundation pit support based on solid waste utilization

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20220705

RJ01 Rejection of invention patent application after publication