CN106087997A - A kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method - Google Patents

A kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method Download PDF

Info

Publication number
CN106087997A
CN106087997A CN201610597380.0A CN201610597380A CN106087997A CN 106087997 A CN106087997 A CN 106087997A CN 201610597380 A CN201610597380 A CN 201610597380A CN 106087997 A CN106087997 A CN 106087997A
Authority
CN
China
Prior art keywords
hole
drilling
mud
depth
casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610597380.0A
Other languages
Chinese (zh)
Inventor
苏春生
梁朋刚
何十美
汤振亚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Bridge Engineering Bureau Group Co Ltd, Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority to CN201610597380.0A priority Critical patent/CN106087997A/en
Publication of CN106087997A publication Critical patent/CN106087997A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/35Foundations formed in frozen ground, e.g. in permafrost soil

Abstract

The invention discloses a kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method, comprise the following steps: (1) first carries out place leveling before construction, operation area is carried out foreign material cleaning and arranges place;(2) bury casing, and prepare slurry coat method or the retaining wall clay of abundance;(3) check measurement baseline and basic point, measure mark fixed pile and elevation;(4) rig is carried out in place fixing;(5) use impact to bore drilling and forming hole, and in hole, irrigate mud or clay retaining wall;(6) control impact brill enters the rock degree of depth, and the boring got out carries out the judgement of whole hole;(7) clear hole is drawn slag and measures whole bore dia and the degree of depth;(8) make steel reinforcement cage and install in whole hole;(9) in whole hole, installation carries out the conduit of secondary pile hole cleaning;(10) concrete perfusion carry out inspection of pile foundation.The be drilled to hole wall of the present invention is solid, stable;Simple in equipment is not limited by place, it is possible to increase substantially drilling efficiency, saves construction cost.

Description

A kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method
Technical field
The present invention relates to bored pile construction field, specifically refer to a kind of high latitude, high and cold Permafrost Area drilled pile Construction.
Background technology
Bored concrete pile system refers to pass through the means such as machine drilling, steel pipe soil compaction or manpower excavation at engineering site in foundation soil Forming stake holes, and within it place steel reinforcement cage, concrete perfusion and the stake made, different according to forming hole method, bored concrete pile again may be used It is divided into several classes such as driven cast-in-place pile, cast-in-situ bored pile and digging hole filling pile.Cast-in-situ bored pile is to define by pile making method classification A kind of pile-type.And frozen soil refers to below zero degrees celsius, and the various rocks containing ice and soil, it is the most sensitive to temperature, Containing abundant ground ice.Therefore, frozen soil has rheological characteristic, and its long-term strength is far below instantaneous strength feature.Just due to these Feature, is necessary for facing two at permafrost region build engineering structure big dangerous: frost heave and thaw collapse.The most existing high in high latitude The pile foundation construction scheme that cold area carries out the works such as railway, highway is few, and not can solve frozen soil layer easily because of temperature Degree changes and causes collapse hole and the impaired problem of pile foundation;And when running into the complex area, high and cold mountain area of geological layering also There is no a kind of efficient drilled pile construction engineering method of irrigating to carry out pile foundation construction.
Summary of the invention
It is an object of the invention to provide one can be at high latitude Cold And Frozen-soil Regions efficient drilling, effectively prevents frozen soil pair The high latitude of pile foundation destruction, high and cold Permafrost Area drilled pile construction engineering method.
The present invention is achieved through the following technical solutions: a kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method, bag Include following steps:
(1) before construction, first carry out place leveling, operation area is carried out foreign material cleaning and arranges place;
(2) bury casing, and prepare slurry coat method or the retaining wall clay of abundance;
(3) check measurement baseline and basic point, measure mark fixed pile and elevation;
(4) rig is carried out in place fixing;
(5) use impact to bore drilling and forming hole, and in hole, irrigate mud or clay retaining wall;
(6) control impact brill enters the rock degree of depth, and the boring got out carries out the judgement of whole hole;
(7) clear hole is drawn slag and measures whole bore dia and the degree of depth;
(8) make steel reinforcement cage and install in whole hole;
(9) in whole hole, installation carries out the conduit of secondary pile hole cleaning;
(10) concrete perfusion carry out inspection of pile foundation.
At high latitude extremely frigid zones, during freezing soil, forming water translocation, the most not only the moisture of origin-location is frozen into Ice, and under the effect of penetration, moisture will never freeze district and migrate to freezing front, and build-up ice at freezing front, make soil Frost heave the most violent.And when moisture freezes in foundation soil, produce the gluing connection of ice so that soil is connected closely with ground, Form the frost heave of works.Under natural endowment, due to the difference of foundation soil soil condition, moisture condition, freezing condition etc., bridge The frost heave discontinuity of beam pile foundation, and ever-frozen ground causes pile foundation impaired seriously for pile foundation frost heave is uneven just, Thus cause bridge collapse.Then corresponding safeguard procedures should just be carried out when drilled pile construction so that pile foundation to occur after avoiding The problem damaged, prevents structural destruction and causes the generation of major accident.And from the point of view of for pile foundation, around stake, soil freezes Knot power provides bearing capacity to pile foundation, say, that the water translocation frost-heave force formed that freezes should be avoided uneven, to be avoided because of The situation of the pile foundation shakiness that the void ratio of the dissipation of frozen soil thaw collapse resulting hole gap water and excretion, the soil body reduces and causes.
And the construction of the present invention mainly by impact brill creep into engineering method, described impact creep into engineering method have with Lower construction characteristic: simple in equipment, applied widely, easy to operate, hole wall is more solid, stable, and collapse hole is few, is not executed Ground, workshop limits, noiseless and vibration effect etc.;Be applicable to loess, cohesive soil, silty clay, artificial miscellaneous fill, hard soil layer, Sand gravel layer containing boulder, erratic boulder layer, rock stratum, be therefore widely adopted.And in the geologic structure of high and cold high latitude area Complexity, the problem that frozen soil to be tackled brings, also to use difference when drilled grout hole running into different geological conditions Countermeasure creep into.
Above-mentioned construction is in Bridge Pile Foundation Construction for many years, particularly on high latitude, high and cold ever-frozen ground ground District's drilled pile construction empirically, is formed after summary and induction step by step, is specifically designed for and high latitude extremely frigid zones ever-frozen ground ground The pile foundation construction of the works such as railway under the multiple geological condition in district, highway, it is also possible to for the preferable non-Frozen Ground Area of geology Pile foundation construction.Concrete principle, for utilizing impact drilled as holes, then bored concrete pile system, is suspended impact in midair with impact drill or hoist engine and is bored Head (also known as block stamp) repeated stock up and down, by hard soil or crushing rock formation pore-forming, part disintegrating slag or mud are clamp-oned in hole wall, big portion It is divided into body refuse, draws out pore-forming with naughty slag cylinder, then Reperfu-sion concrete pile.
To better implement the present invention, further, in described step (2), the mount scheme burying casing is as follows:
(3.1) make casing, described casing use 5mm thickness steel plate make and internal diameter than stake footpath big 30 ~ 40cm, casing is suitable for reading It is welded with suspension ring;
(3.2) casing utilizes rotary drilling rig rotate press-in soil face buried depth to permafrost haorizon (the general degree of depth is 1.5 ~ 3m) and make to protect Cylinder top exceeds working water level (or level of ground water) 1.5 ~ 2.0m;In conjunction with frozen soil all the year round and on-the-spot actual address situation, casing buries It is deep to permafrost haorizon to prevent the unstable soil layer temperature influence thawing above permafrost haorizon from causing the phenomenons such as collapse hole.And in order to keep Head, then by mud overfall working water level to be exceeded 1.5 ~ 2.0m top 0.3m above ground level on casing top;
(3.3) backfill the clay of 0.5 ~ 1.0m thickness with surrounding and tamp bottom casing.By by bottom casing and surrounding Clay compacting with avoid unsettled bottom casing thus cause the hole that collapses, leak and the problem such as spillage.
Further, in described step (5), the arrangement and method for construction that drilling and forming hole is bored in impact is as follows:
(5.1) first loosening steel wire rope, each slack rope length is in the range of 5 ~ 8cm, at hard soil layer each slack rope 3 ~ 5cm;First put Pine steel wire rope is to prevent the phenomenon of " fan the air hammer " from occurring, it is to avoid rig, drilling cramp and steel wire rope are by excessive unexpected load And suffer damage and drilling cramp beat;And slack rope amount is too much, then can reduce stroke, reduce rate of penetration, cause the steel promoting burr-drill Cord produces and rocks, the deviation casing center, plumb position of steel wire rope, produces inclined hole, makes steel wire rope tangle generation thing time serious Therefore.
(5.2) use circulating mud pump toward being in the milk in hole and keeping water level in borehole to exceed level of ground water 1.5 ~ 2.0m;
(5.3) jump bit pin is used to creep into.
Further, the counte-rplan using jump bit to creep into of described step (5.3) use following proposal one to scheme Seven any one:
Scheme one: if there being water in hole, just direct plunges into clay and by impact cone with 50cm little stroke repeated stock pulping;
Scheme two: by high liquid limit clay, containing sand low limit clay layer time, use relative density be 1.1 ~ 1.2 mud also With stroke percussion drilling in 75cm;
Scheme three: by less sticky, containing the sandy soil layer that gravel is many time, use relative density be the mud of 1.25 ~ 1.5 and use Tubular, hollow draws slag drill bit with 50 ~ 70cm medium and small stroke percussion drilling;
Scheme four: when by layer of sand, gravel layer, uses relative density to be the mud of 1.25 ~ 1.5 and draw slag drill bit with hollow With stroke percussion drilling in 75cm;
Scheme five: when running into the loose sand of drift sand phenomenon or thicker, should put into clay and grain in the ratio of 1:0.5 in hole The footpath slabstone less than 15cm, and with cross solid-cone drill bit, with the little stroke repeated stock of 50cm;
Scheme six: when by the soil layer of hard closely knit boulder bed or basement rock etc, using relative density is the mud of 1.3 ~ 1.5 And with cross solid-cone drill bit with the high-stroke percussion drilling of 100cm;
Scheme seven: when by frozen soil layer, use relative density be the mud of 1.25 ~ 1.5 and with hollow slag drill bit of drawing with 75cm Middle stroke percussion drilling.
Further, to draw the embodiment of slag as follows the clear hole in described step (7):
(7.1) within when normally creeping into every eight hours, slag is at least drawn once;
(7.2) when creeping into closely knit hard soil layer, the purest drilling depth carries out drawing slag less than 5 ~ 10cm;Soft creeping into During layer, the purest drilling depth carries out drawing slag less than 15 ~ 30cm;
(7.3) slag is the most once drawn before entering frozen soil layer.
Further, the rig fixing process in place in described step (4), including drilled pile ground location control and The three-dimensional position of drilled pile controls, and it is first to check survey data and demarcate drilled pile position that described ground location controls;Institute The three-dimensional position stating drilled pile controls to be to maintain rig level, firm and 3 points (overhead traveling crane, rotating disk, a casing center) vertical line, and Verify with horizon rule and plummet and check.
Further, described step (5) carries out middle inspection, institute during using impact to bore drilling and forming hole in real time State middle inspection to include that gaging hole is deep, survey mud balance, survey rig speed and the record of geological information.
Further, the slurry coat method prepared in step (2) selects plasticity index to be not less than 15, particle diameter 0.1mm and content It is not more than the cohesive soil of 6%.And the mud of different relative density should be prepared for different soil.
Further, the method entering the rock degree of depth controlling impact brill of described step (6) is, according to engineering site reconnaissance report Accuse strongly weathered sand-rock position absolute altitude and casing end face absolute altitude, calculate the degree of depth of strong-weathered rock end face, and using this degree of depth as control point, and Estimation frozen soil layer to formation depth, progress when determining boring.
Further, described step (6) carries out criterion that whole hole judges as, stake end entrance to the boring got out During middle weathered rock formation 1 ~ 2m, rig is beated more violent than when entering rock, and drilling depth is not accelerated even to slow down, and is just borehole bottom location.
The present invention compared with prior art, has the following advantages and beneficial effect:
(1) the be drilled to hole wall of the present invention is solid, stable, reduces the collapse hole probability caused because of temperature damage frozen soil layer;
(2) present invention is not limited by place, reduces special geological surrounding Xia Zhu island quantities;
(3) present device simple structure, it is simple to transport is marched into the arena and transition;
(4) present invention obtains more stable whole hole by using different reply boring schemes for Different Strata structure Structure, it is also possible to increase substantially drilling efficiency, saves construction cost.
Accompanying drawing explanation
By the detailed description non-limiting example made with reference to the following drawings of reading, other features of the present invention, Purpose and advantage will become apparent:
Fig. 1 is the construction flow chart of the present invention.
Detailed description of the invention
Below in conjunction with embodiment, the present invention is described in further detail, but embodiments of the present invention is not limited to this, Without departing from the idea case in the present invention described above, according to ordinary skill knowledge and customary means, make various replacing Change and change, all should be included within the scope of the invention.
Embodiment:
Present embodiment discloses a kind of Permafrost Area high-order, high and cold drilled pile construction engineering method, as it is shown in figure 1, be mainly The Frost heave of frozen soil caused by water translocation in high latitude extremely frigid zones frozen soil is overcome to damage the problem of pile foundation, not only by many Kind of arrangement and method for construction prevent aperture from subsiding and pile foundation unbalance stress and destroyed situation occurs, and when boring construction by impact Carry out creeping into ensure efficiency of construction for different geological stratifications by kinds of schemes so that hole wall is solid stable.Described construction work Method specific embodiments is as follows:
1, preparation of construction:
First, preparation of construction to be carried out before construction, the place of construction area is flattened, removes foreign material, rig position Tamp, simultaneously to construction water, mud pit position, power supply, sandstone stock ground, mixer position, steel bar meter place, execute Work sidewalk does unified arrangement, it is important to note that transport unimpeded, and beneficially parallel-cross operation, waste water, useless slurry, the discharge of waste residue Meet environmental requirement, accomplish civilized construction.
Then surveying and locating, makes the stake position of basic each stake.Surveying and locating follows " by the principle of entirety to local ", stake position During setting-out, the tolerance in length and breadth of stake≤± 5cm, the most accurately measurement baseline and basic point, demarcation drilled pile position and elevation, and Before and after Zhuan, left and right is respectively provided with fender pile for detecting center and the absolute altitude of stake at any time at the 2m of center, and measures the center of stake holes Position deviation cannot be greater than 5mm.Bit central and casing centre deviation cannot be greater than 5cm.
Boring Ground arrangement is as far as possible to fill out for digging, to reduce the thermal agitation that the excavation to original place table causes.Under rig substructure Engine radiating part additionally arranges polystyrene foam plastics thermal insulation board, to reduce impact thermally equilibrated on ground.
2, casing is buried underground:
Casing have correcting burr-drill, control stake position, isolation surface water seepage, prevent aperture from caving in, raise hole in hydrostatic head and solid Determine steel reinforcement cage effect.Casing uses thick 5mm steel plate to make, internal diameter should than stake footpath big 30 ~ 40cm, in conjunction with this engineering frozen soil all the year round and On-the-spot actual geological condition, casing buried depth to permafrost haorizon (general 1.5m ~ 3m) is subject to preventing the unstable soil layer above permafrost haorizon Temperature affects thawing and causes the phenomenons such as collapse hole.For keeping head, the mud overfall working water level to be exceeded on casing top (or ground Lower water level) 1.5 ~ 2.0m top 0.3m above ground level.Unsettled for avoiding at the bottom of casing, cause the hole that collapses, leak, spillage, at the bottom of casing and Surrounding should backfill the clay of 0.5 ~ 1.0m thickness and tamp, and the deviation of casing plan-position should not surpass 5cm.Casing center time embedding Axis aligns Zhuan Wei center, and its deviation is not preferably greater than 20cm.
And ought once run into geologic condition complex in the case of, it should use double steel cylinders bury underground, encircle for protection outward In cylinder diameter bigger (bigger 65cm than stake diameter) and first embedment ground, and before embedment, on the casing of outer ring, wrap water proof cloth And coat Colophonium to prevent casing to be corroded, after then waiting until drilling via formations, embedment scribbles the inner ring casing of Colophonium again, and two It is filled with one layer of clay in seasonally thaw layer in the middle of layer casing, thus ensure that the tangent coordinate system of frozen soil layer upper soil horizon will not Pile foundation is damaged.
Then starting to arrange mud circulating system after having buried casing, described mud circulating system includes mud pit, precipitation Pond and draining waste discharge sizing device etc., mud pit and sedimentation tank excavation require a length of 6.0m, wide 4.0m, high 2.0m.After having excavated Middle fluting 50 × 20cm, slope ratio requires 1:0.75, and sets up the anti-of mud pit and sedimentation tank in pool side 40cm ~ 50cm position Guard rail rod, railing scaffolding height requires 1.5m, front rail spacing 50cm, vertical vertical pole's span 80cm, and gos deep into ground 30cm; Using right-angle coupler to connect between transverse and longitudinal rod member, pull bar uses red and white paint locker to brush every 20cm after having set up, Make it eye-catching effectively, and wrapping up the Dense mesh screen that a circle is double-deck about, use and tie up between tied silk and railing firmly by heavy Pond, shallow lake can adjust the relative density of mud, and mud should select plasticity index to be not less than 15, and particle diameter 0.1mm content is not more than 6% Cohesive soil.Different soil layer specific gravity of muds can be selected by following data;Cohesive soil and lam can pulping, mud on the spot The relative density 1.1 ~ 1.2 of slurry;Silt and sand, the relative density of mud crosses 1.25 ~ 1.5;Sandy gravel and drifting sand layer, mud Relative density 1.3 ~ 1.5.
3, rig is in place fixing:
Buried casing, after preparing enough slurry coat method clay, rig is in place, must keep when rig is in place smooth firm, do not tilt And displacement, and certain fixation is taked to prevent in drilling process displacement and rock.When rig is in place, should take measures to ensure Drilling tool center and casing center superposition, it is not more than 2cm partially.Support mast, be directed at stake holes center, it is ensured that rig was being constructed In journey steadily, not run-off the straight, displacement.The plumb line of the crown sheave leading edge of percussive drill drilling cramp should be directed at stake holes center, partially Difference cannot be greater than 10mm.
Drilling cramp is boring and the support of concrete perfusion, will install smooth firm, safety, and have certain rigidity, In boring or when other operates, it is not likely to produce displacement and rocks.It is suitable to select according to engineering geological data and design data Rig kind, model, and coordinate the drill bit being suitable for.In boring procedure, necessary center, align piles position, pore-forming center, gadder must Palpus held stationary, is not subjected to displacement, tilts and depression;When installing in place, detailed measurements rear base sleeper pads and stoppers, top Fixing steadily with cable wind rope, and running check in boring procedure, to ensure that turntable surface level, borer frame are vertical, and then really Perpendicularity and the pore size of protecting pile body are uniform.
4, impact brill drilling and forming hole:
When constructing with percussive drill, steel wire rope quantity of margin should be controlled, typically at soft soil horizon each slack rope 5 ~ 8cm, at closely knit heavily fortified point Hard stratum every time can slack rope 3 ~ 5cm.Slack rope amount is very few, is formed " fan the air hammer ", makes rig, drilling cramp and steel wire rope by excessive meaning External load, subjects to damage, and drilling cramp is beated, extremely unstable;Slack rope amount is too much, then can reduce stroke, reduces rate of penetration, Cause the steel wire rope promoting burr-drill to produce to rock, the deviation casing center, plumb position of steel wire rope, produce inclined hole, time serious, make steel Cord is tangled and is had an accident.
In drilling process, circulating mud pump is used to keep water level in borehole to exceed level of ground water (korneforos water level) 1.5 ~ 2.0m mud Slurry conduit gradually to sink at the bottom of hole with drilling footage, is beneficial to boring mud and floats, accelerates rate of penetration.
And be directed to different rock-layers and taked different counte-rplan as follows:
(1), when starting to creep into, mud should first be irrigated in hole.Depending on the indexs such as specific gravity of mud are according to soil layer situation, such as hole In have water, clay can be direct plungeed into, by impact cone with 0.5m little stroke repeated stock pulping.Below casing footing in the range of 2 ~ 4m Belong to riverbed surface, use the mud of density 1.3 ~ 1.5, little stroke repeated stock, make solid not the collapsing of hole wall not leak.This hole section one As do not draw slag.
(2) when by high liquid limit clay, sandy clay of low liquid limit layer, use the mud of density 1.1 ~ 1.2,75cm rushes Journey percussion drilling.
(3) when creep into less sticky, containing the sandy soil layer that gravel is many time, should protect with the mud that relative density is 1.25 ~ 1.5 Wall, draws slag drill bit with tubular, hollow, 50 ~ 70cm medium and small stroke percussion drilling.
(4) when creeping in layer of sand, gravel layer, hole wall wild effect often occurs, generally use hollow slag of drawing to bore Head, creeps into the moderate stroke of 75cm, and the mud using relative density to be 1.25 ~ 1.5 carries out retaining wall.
(5) when meeting the loose sand of drift sand phenomenon or thicker, clay and grain should be put in hole in the ratio of 1:0.5 The footpath slabstone less than 15cm, and with cross solid-cone (drill bit), with the little stroke repeated stock of 50cm, make clay, slabstone squeeze Entering hole wall, this process can be repeated, and makes every effort to hole wall stable.
(6) at the soil layer by hard closely knit boulder bed or basement rock (strong weathered granite and middle weathered granite) etc Time, it being full of the mud suspension boring mud of 1.3 ~ 1.5 in remaining hole, preferential selection has the cross solid-cone of greater impact power, adopts With the high-stroke percussion drilling of 100cm.
(7) when by frozen soil layer all the year round, for preventing hole wall wild effect, generally employing is hollow draws slag drill bit, Creeping into the moderate stroke of 75cm, the mud using relative density to be 1.25 ~ 1.5 carries out retaining wall.When entering frozen soil layer all the year round, Should ensure that boring and the seriality of perfusion, prevent freezing layer and receive disturbance generation collapse hole phenomenon.In continuous drilling process, because freezing The existence of layer, should not cause collapse hole phenomenon, can suitably turn mud balance down, reduces and draws slag number of times, shortens the pore-forming time.According to Ancient Lip river railway 640 is with the pore-forming experience of stake and summary, if construction continuously is bored in impact, frozen soil layer serves the effect of retaining wall.
5, enter rock severity control and whole hole judge:
According to Engineering Geology Investigation report strongly weathered sand-rock position absolute altitude and casing end face absolute altitude, calculate the deep of strong-weathered rock end face Degree, and using this degree of depth as control point, and estimate frozen soil layer to formation depth, progress when determining boring.When burr-drill contact is severely-weathered During scar, power and rate of penetration suffered by burr-drill are substantially different from soil layer, and now rig is beated acutely, and (especially drilling cramp rear end is jumped Move and become apparent from), drilling depth substantially slows down, and this is into rock signal.At this moment should shut down measured hole bed rock face elevation, this elevation is exactly strong The upper limit height value of weathered layer, and perform elevation and initial time record.Rock is taken with this depth point drilling depth 20 ~ 30cm again that is as the criterion Sample, and with geologic report or examination piling generally acknowledge rock field mark standard conscientiously contrast confirmation.Owing to mud recycles, its In be inevitably mixed with the rock originally got out, but the ratio being consistent with fresh core typically must not be less than 30% by right The discriminating of lithology confirms, then can calculate strong-weathered rock layer thickness.
The thickness one of strongly weathered sand-rock is confirmed, and namely stake holes has passed through weathered rock formation during strong-weathered rock enters.Should stop Elevation at the bottom of machine measured hole, and compare with the middle weathered granite upper limit elevation of geological mapping Preliminary Analysis For Data, with hole In bed rock bits samples met, decomposed rock standard is main, then elevation at the bottom of this hole is the initial elevation of middle weathered layer in-rock segment.
Whole hole criterion is that during stake end enters, weathered rock formation 1 ~ 2m is when determining whole hole, if having arrived hole termination depth, bores Machine is beated more violent than when entering rock, and drilling depth is not accelerated, and even slows down;Bore sample and rock sample when entering rock compares, whole hole In rock sample, middle decayed rock percentage composition must be significantly larger than into percentage ratio during rock.By creeping into continuously and to landwaste sample The discriminating of product, just can measure the in-rock segment degree of depth.
In the decision process of whole hole the most ready, increase mud balance, determine whether rapidly pore-forming, prevent because of the time Cross the thawing of long frozen soil layer and cause the phenomenons such as collapse hole shrinkage cavity.
6, draw slag and examine hole:
In the perforate stage, for making boring mud clamp-on hole wall, slag can be drawn after creeping into 4 ~ 5m again.Normally creeping into per tour (eight hours is one Class) at least should draw slag once;Typically creep into less than the purest brill of 5 ~ 10cm broken ground closely knit hard soil layer is the purest When entering less than 15 ~ 30cm, should carry out drawing slag.Or draw slag once during every drilling depth 0.5m ~ 1.0m, draw 4 ~ 5 every time, or draw to mud Interior slag inclusion substantially reduces, without coarse granule, relative density recover normal till.Mud should be added in time in hole to safeguard after drawing slag Head height.Throw in clay pulping voluntarily, once can not put into too much, with free sticky cone, card cone.One is carried out before entering frozen soil layer Secondary drawing slag, once enter frozen soil layer, should reduce as far as possible draw slag number of times, fast drilling is until by frozen soil layer, reducing freezing successively The disturbance of soil layer.Carry out at once after determining whole hole examining hole, determine the diameter in hole, the degree of depth.
7, fabrication of reinforcing cage is installed:
Steel reinforcement cage requires to make according to design in the processing place of bridge location, and rainy day, snow sky, strong wind weather and ambient temperature are less than zero When lower 20 DEG C, must not outdoor weld job.Reinforcing bar uses HPB300/HRB400 model, reinforcing bar upper and lower side and each 2.5m in middle part Four Ф 16 reinforcing bar earrings it are symmetrical arranged, it is ensured that protective layer thickness in same cross section.Framework of steel reinforcement lay after end face and bottom surface Vertical error cannot be greater than 5cm.Raw material is welded as flash butt welding, and horizontal reinforcement welding point is manual electric arc welding, vertical steel Muscle welding point is electroslag pressure welding.Described reinforcing bar all uses in floor manufacture hole and installs, Steel Reinforcing Bar Material to being welded into whole long dispensing, Limit, hole transported to by the material welded, and is grouped by the main muscle specification in stirrup lattice and stacks.And stake top mark is high, socket length is strictly by design Figure requirement, length of reinforcing cage is by the actual grade times protective layer thickness that subtracts 2.90cm is first set up on the limit, hole of molding high when installing in hole Shelf, every limit transfers the whole long spiral welded, and the every limit of minor face transfers 2, every limit, long limit transfer 3 in place fixed as stirrup Position muscle, boundling reinforcing bar weld seam to be staggered, spot welding or side be bundled into bundle, and spacer bar is put into rear upper end crotch and is welded on support body and opens Stirrup put into by beginning crane, and is welded on spacer bar by stirrup according to design, from bottom to top molding stirrup net.Use after muscle molding Main muscle put into by 25 tons of cranes.The main muscle of stake is in place divides bundle lifting by the natural classification specification of stirrup, and ties up once every 2m, prevents It is at random.Main muscle is transferred and is completed at the bottom of stake, and lower five groups of bar benders are evenly distributed in stake holes, and the main muscle separately hung in, by spacing And colligation temporarily fixing some, the most from bottom to top pointwise colligation sizing.
8, cement injection:
Using underwater gliders method poured pile base concrete, concrete uses early strength concrete under low temperature at blending station collection Middle stirring, workability to get well, and the slump controls at 18 ~ 20cm, uses concrete tank to be transported to scene.In filling concrete process In, it is ensured that the seriality poured, must not interrupt, shorten the time interval removing conduit as far as possible.For guaranteeing stake top quality, stake top Add filling 0.5 ~ 1m height.Perfusion scene must carry out Site Detection to air content, the slump and three indexs of bleeding rate, confirms to close Can use after lattice.After filling concrete completes, stake jacking row must be covered heat storing and heat preserving.
9, inspection of pile foundation:
After pile body concrete reaches design strength, cut pile crown, carry out small strain Non-Destructive Testing.Concrete quality is had a question Time, core boring sampling inspection, drilling core checking is generally large due to the design load of big straight cast-in-situ bored pile, has perhaps by static force pile testing method How difficulty, so conventional geological drilling rig core boring sampling along its length on pile body, by the observation of core sample and test are determined The quality of stake.
New thermal balance generates:
The pile foundation construction process change thermal balance of ground, the various heats produced in work progress make the ground temperature at pile foundation drastically become Change, cause foundation soil certain limit around to heat up and melt.For forming new thermal equilibrium state, Permafrost Area cast-in-situ bored pile After concreting, must can carry out the construction of cushion cap above section after the heat exchanging process in a stage.
Performance analysis:
Use percussive drill drilling construction, exciting flexible, reduce and take up an area place, effectively protect the life in forest land, Daxinganling District State environment.Efficiency of construction is high simultaneously, little to frozen soil layer disturbance after reasonable arrangement construction, it is ensured that hole quality, achieves good Social benefit and economic benefit.
Embodiment 2:
The present embodiment is on the basis of above-described embodiment, limits further, if constructed in the winter time, it should to arrangement and method for construction Carry out some to improve.
Along with the reduction of temperature, the frost zone above frozen soil layer starts to freeze until earth's surface all the year round.Now bury one underground Joint 1.5m casing, it is ensured that mud overfall can start the impact drilling construction higher than working water level.Hollow drawing is used during construction Slag drill bit, creeps into the moderate stroke of 75cm, and the mud using relative density to be 1.25 ~ 1.5 carries out retaining wall, it is ensured that the company of construction Continuous property, prevent water, mud freeze cause the phenomenons such as bit freezing.In work progress, mud balance can suitably be turned down.In this hole when Mud had both played retaining wall effect, serves again thermal insulation function, protects frozen soil layer, substantially reduced the thing such as collapse hole, shrinkage cavity Therefore the probability occurred.
Drilled pile concrete uses early strength concrete under low temperature, determines that concrete is adopted by thermodynamic metering and economic analysis Use regenerative process maintenance.Pour to designed elevation super filling about 1m concrete, prevent coagulation at temperature too low impact design stake top Soil intensity.For preventing soil layer temperature influence around pile foundation from producing change, in time to backfilling non-frost heave material in hole, play guarantor Fender pile base concrete and function of heat insulation.Other parts of the present embodiment are same as the previously described embodiments, repeat no more.
Embodiment 3:
The present embodiment is on the basis of above-described embodiment, limits further, and the present embodiment is by the construction of the present invention Applying in the biggest bridge construction engineering, whole engineering is built together and is set 4 grand bridges, two bridges, pile foundation 640, 10053 linear meter(lin.m.)s, all use impact drilled as holes construction, terminate in August, 2010 pile foundation construction from August, 2009 separately work, warp Small strain detects all I, II class stakes, and wherein I class stake 590, reaches 92%, and pile quality is excellent.Other portions of the present embodiment Divide same as the previously described embodiments, repeat no more.
The above, be only presently preferred embodiments of the present invention, and the present invention not does any pro forma restriction, every depends on Any simple modification of being made above example according to the technical spirit of the present invention, equivalent variations, each fall within the protection of the present invention Within the scope of.

Claims (10)

1. a high latitude, high and cold Permafrost Area drilled pile construction engineering method, it is characterised in that: comprise the following steps:
(1) before construction, first carry out place leveling, operation area is carried out foreign material cleaning and arranges place;
(2) bury casing, and prepare slurry coat method or the retaining wall clay of abundance;
(3) check measurement baseline and basic point, measure mark fixed pile and elevation;
(4) rig is carried out in place fixing;
(5) use impact to bore drilling and forming hole, and in hole, irrigate mud or clay retaining wall;
(6) control impact brill enters the rock degree of depth, and the boring got out carries out the judgement of whole hole;
(7) clear hole is drawn slag and measures whole bore dia and the degree of depth;
(8) make steel reinforcement cage and install in whole hole;
(9) in whole hole, installation carries out the conduit of secondary pile hole cleaning;
(10) concrete perfusion carry out inspection of pile foundation.
The high latitude of one the most according to claim 1, high and cold Permafrost Area drilled pile construction engineering method, it is characterised in that: In described step (2), the mount scheme burying casing is as follows:
(3.1) make casing, described casing use 5mm thickness steel plate make and internal diameter than stake footpath big 30 ~ 40cm, casing is suitable for reading It is welded with suspension ring;
(3.2) casing utilizes rotary drilling rig rotate press-in soil face buried depth to permafrost haorizon, and makes casing top exceed construction water Position 1.5 ~ 2.0m;
(3.3) backfill the clay of 0.5 ~ 1.0m thickness with surrounding and tamp bottom casing.
The high latitude of one the most according to claim 1, high and cold Permafrost Area drilled pile construction engineering method, it is characterised in that: In described step (5), the arrangement and method for construction that drilling and forming hole is bored in impact is as follows:
(5.1) first loosening steel wire rope, each slack rope length is in the range of 5 ~ 8cm, at hard soil layer each slack rope 3 ~ 5cm;
(5.2) use circulating mud pump toward being in the milk in hole and keeping water level in borehole to exceed level of ground water 1.5 ~ 2.0m;
(5.3) jump bit pin is used to creep into.
The high latitude of one the most according to claim 3, high and cold Permafrost Area drilled pile construction engineering method, it is characterised in that: The counte-rplan crept into of jump bit that use of described step (5.3) use any one of following proposal one to scheme seven:
Scheme one: if there being water in hole, just direct plunges into clay and by impact cone with 50cm little stroke repeated stock pulping;
Scheme two: by high liquid limit clay, containing sand low limit clay layer time, use relative density be 1.1 ~ 1.2 mud also With stroke percussion drilling in 75cm;
Scheme three: by less sticky, containing the sandy soil layer that gravel is many time, use relative density be the mud of 1.25 ~ 1.5 and use Tubular, hollow draws slag drill bit with 50 ~ 70cm medium and small stroke percussion drilling;
Scheme four: when by layer of sand, gravel layer, uses relative density to be the mud of 1.25 ~ 1.5 and draw slag drill bit with hollow With stroke percussion drilling in 75cm;
Scheme five: when running into the loose sand of drift sand phenomenon or thicker, should put into clay and grain in the ratio of 1:0.5 in hole The footpath slabstone less than 15cm, and with cross solid-cone drill bit, with the little stroke repeated stock of 50cm;
Scheme six: when by the soil layer of hard closely knit boulder bed or basement rock etc, using relative density is the mud of 1.3 ~ 1.5 And with cross solid-cone drill bit with the high-stroke percussion drilling of 100cm;
Scheme seven: when by frozen soil layer, use relative density be the mud of 1.25 ~ 1.5 and with hollow slag drill bit of drawing with 75cm Middle stroke percussion drilling.
The high latitude of one the most according to claim 1, high and cold Permafrost Area drilled pile construction engineering method, it is characterised in that: The embodiment that slag is drawn in clear hole in described step (7) is as follows:
(7.1) within when normally creeping into every eight hours, slag is at least drawn once;
(7.2) when creeping into closely knit hard soil layer, the purest drilling depth carries out drawing slag less than 5 ~ 10cm;Soft creeping into During layer, the purest drilling depth carries out drawing slag less than 15 ~ 30cm;
(7.3) slag is the most once drawn before entering frozen soil layer.
6., according to the high latitude of one described in any one of claim 1 ~ 5, high and cold Permafrost Area drilled pile construction engineering method, it is special Levy and be: the rig fixing process in place in described step (4), including the ground location control of drilled pile and standing of drilled pile Body position controls, and it is first to check survey data and demarcate drilled pile position that described ground location controls;Described drilled pile Three-dimensional position controls to be to maintain rig level, firm and three one vertical lines, and checks with horizon rule and plummet verification.
7., according to the high latitude of one described in any one of claim 1 ~ 5, high and cold Permafrost Area drilled pile construction engineering method, it is special Levy and be: described step (5) carries out middle inspection, described middle inspection during using impact to bore drilling and forming hole in real time Deep including gaging hole, survey mud balance, survey rig speed and the record of geological information.
8., according to the high latitude of one described in any one of claim 1 ~ 5, high and cold Permafrost Area drilled pile construction engineering method, it is special Levy and be: the slurry coat method prepared in described step (2) selects plasticity index to be not less than 15, particle diameter 0.1mm and content no more than The cohesive soil of 6%.
9., according to the high latitude of one described in any one of claim 1 ~ 5, high and cold Permafrost Area drilled pile construction engineering method, it is special Levy and be: the method entering the rock degree of depth controlling impact brill of described step (6) is to report strong-weathered rock according to engineering site reconnaissance Layer position absolute altitude and casing end face absolute altitude, calculate the degree of depth of strong-weathered rock end face, and using this degree of depth as control point, and estimate frozen soil layer To formation depth, progress when determining boring.
10. according to the high latitude of one described in any one of claim 1 ~ 5, high and cold Permafrost Area drilled pile construction engineering method, its It is characterised by: described step (6) carries out criterion that whole hole judges as, decomposed rock in the entrance of stake end to the boring got out During layer 1 ~ 2m, rig is beated more violent than when entering rock, and drilling depth is not accelerated even to slow down, and is just borehole bottom location.
CN201610597380.0A 2016-07-26 2016-07-26 A kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method Pending CN106087997A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610597380.0A CN106087997A (en) 2016-07-26 2016-07-26 A kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610597380.0A CN106087997A (en) 2016-07-26 2016-07-26 A kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method

Publications (1)

Publication Number Publication Date
CN106087997A true CN106087997A (en) 2016-11-09

Family

ID=57448896

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610597380.0A Pending CN106087997A (en) 2016-07-26 2016-07-26 A kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method

Country Status (1)

Country Link
CN (1) CN106087997A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107905728A (en) * 2017-11-15 2018-04-13 中国水利水电第十六工程局有限公司 Rockfill area drilling construction method
CN107965290A (en) * 2017-11-13 2018-04-27 云南建投第十建设有限公司 Gravelly soil leak Rotating fields section stake holes processing method
CN108301403A (en) * 2018-01-04 2018-07-20 中国建筑第八工程局有限公司 Subway drilling cast-in-place pile construction method
CN109577341A (en) * 2018-11-08 2019-04-05 中交二航局成都城市建设工程有限公司 The anti-collapse construction method of rich water ovum erratic boulder soil body burning into sand stratum foundation pit major diameter fender post
CN111021949A (en) * 2019-10-28 2020-04-17 中国一冶集团有限公司 Drilling method for improving impact drilling on sand layer and mud rock layer
CN112577546A (en) * 2020-12-11 2021-03-30 杭州长杰科技有限公司 Multifunctional pile machine construction recorder
CN114075950A (en) * 2020-08-21 2022-02-22 中国石油化工股份有限公司 Horizontal well development method for natural gas hydrate
CN114703831A (en) * 2022-04-20 2022-07-05 山西四建集团有限公司 Construction method of reinforced concrete cast-in-place pile under complex geological condition
CN115075770A (en) * 2022-07-11 2022-09-20 青海九零六工程勘察设计院有限责任公司 Drilling construction process for high and cold complex stratum

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2295608C2 (en) * 2005-02-07 2007-03-20 Роберт Мияссарович Хафизов Method for pile driving in permafrost ground (variants)
CN103088814A (en) * 2013-02-27 2013-05-08 路桥华祥国际工程有限公司 Rotary drilling rig coordinated with percussion drill hole-forming construction method
CN103469789A (en) * 2013-09-30 2013-12-25 中铁二十局集团有限公司 Karst-area underwater bridge pier drilled pile construction method
CN104612134A (en) * 2014-12-16 2015-05-13 中铁建大桥工程局集团第五工程有限公司 Cast-in place pile post-grouting construction method for pouring construction
CN105714772A (en) * 2016-02-22 2016-06-29 北龙建设集团有限公司 Re-drilling concrete wall protecting method for hole formation of rock-socketed pile in karst region

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2295608C2 (en) * 2005-02-07 2007-03-20 Роберт Мияссарович Хафизов Method for pile driving in permafrost ground (variants)
CN103088814A (en) * 2013-02-27 2013-05-08 路桥华祥国际工程有限公司 Rotary drilling rig coordinated with percussion drill hole-forming construction method
CN103469789A (en) * 2013-09-30 2013-12-25 中铁二十局集团有限公司 Karst-area underwater bridge pier drilled pile construction method
CN104612134A (en) * 2014-12-16 2015-05-13 中铁建大桥工程局集团第五工程有限公司 Cast-in place pile post-grouting construction method for pouring construction
CN105714772A (en) * 2016-02-22 2016-06-29 北龙建设集团有限公司 Re-drilling concrete wall protecting method for hole formation of rock-socketed pile in karst region

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
孙晓羽: "《基础工程》", 31 July 2015 *
惠向兵: "哈大铁路客专钻孔桩旋挖钻机施工及钻头研究", 《中国优秀硕士学位论文全文数据库工程科技Ⅱ辑》 *
肖华: "高原冻土区桥梁下部结构施工", 《西藏科技》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107965290A (en) * 2017-11-13 2018-04-27 云南建投第十建设有限公司 Gravelly soil leak Rotating fields section stake holes processing method
CN107905728A (en) * 2017-11-15 2018-04-13 中国水利水电第十六工程局有限公司 Rockfill area drilling construction method
CN107905728B (en) * 2017-11-15 2020-01-14 中国水利水电第十六工程局有限公司 Rock-fill area drilling construction method
CN108301403A (en) * 2018-01-04 2018-07-20 中国建筑第八工程局有限公司 Subway drilling cast-in-place pile construction method
CN109577341A (en) * 2018-11-08 2019-04-05 中交二航局成都城市建设工程有限公司 The anti-collapse construction method of rich water ovum erratic boulder soil body burning into sand stratum foundation pit major diameter fender post
CN111021949A (en) * 2019-10-28 2020-04-17 中国一冶集团有限公司 Drilling method for improving impact drilling on sand layer and mud rock layer
CN114075950A (en) * 2020-08-21 2022-02-22 中国石油化工股份有限公司 Horizontal well development method for natural gas hydrate
CN114075950B (en) * 2020-08-21 2024-04-09 中国石油化工股份有限公司 Horizontal well development method of natural gas hydrate
CN112577546A (en) * 2020-12-11 2021-03-30 杭州长杰科技有限公司 Multifunctional pile machine construction recorder
CN114703831A (en) * 2022-04-20 2022-07-05 山西四建集团有限公司 Construction method of reinforced concrete cast-in-place pile under complex geological condition
CN115075770A (en) * 2022-07-11 2022-09-20 青海九零六工程勘察设计院有限责任公司 Drilling construction process for high and cold complex stratum
CN115075770B (en) * 2022-07-11 2024-04-09 青海九零六工程勘察设计院有限责任公司 Drilling construction process for high and cold complex stratum

Similar Documents

Publication Publication Date Title
CN106087997A (en) A kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method
CN107938676B (en) Pile foundation construction method for penetrating through full-filling karst cave
CN110424381A (en) A kind of process for rotary digging drilling hole stake
CN107524138B (en) Construction method of ultra-deep foundation pit underground diaphragm wall
CN103088814A (en) Rotary drilling rig coordinated with percussion drill hole-forming construction method
CN102251777A (en) Large-scale karst cavity treatment method for karst tunnel
CN102953341A (en) Overhead trestle structure built on non-covering steep bare rocks in deep rapids
CN108149678A (en) A kind of loess retaining wall does the construction method of operation pore-creating filling pile
CN102979039B (en) Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN105275381A (en) Drilling construction method for water-rich cobble stratum by utilizing impact drill
CN109488202A (en) A kind of gravel rock stratum pile foundation drilling construction engineering method containing gravel-boulder bed
CN109083182A (en) Collapsible loess super long large diameter pile foundation churning driven dry method construction method
CN109778869A (en) Foundation ditch construction method
CN106320333A (en) Row type water cast-in-place pile device and construction method
CN106436788A (en) Foundation reinforcement and inclination correction method for friction piles of high-rise building
CN113174961B (en) Foundation pit slope supporting method
CN110952586A (en) Construction process for bearing platform below expressway
CN203049443U (en) High level trestle structure arranged on steep bare rock of deepwater torrent unsheathed layer
CN106988305A (en) A kind of pile-column pier construction method of underground integrated molding
CN211312224U (en) Steel casing positioning tool for bridge drilled pile based on existing pavement transformation
CN114232607A (en) Frozen soil section drilled pile construction process
CN109944244A (en) A kind of anti-float anchor rod and its construction method
CN206143760U (en) Ally oneself with formula of arranging bored concrete pile device on water
CN112281873A (en) Construction method of anchoring pile
CN107675700A (en) The construction method of diaphram wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161109