CN102953341A - Overhead trestle structure built on non-covering steep bare rocks in deep rapids - Google Patents
Overhead trestle structure built on non-covering steep bare rocks in deep rapids Download PDFInfo
- Publication number
- CN102953341A CN102953341A CN2012105361505A CN201210536150A CN102953341A CN 102953341 A CN102953341 A CN 102953341A CN 2012105361505 A CN2012105361505 A CN 2012105361505A CN 201210536150 A CN201210536150 A CN 201210536150A CN 102953341 A CN102953341 A CN 102953341A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- trestle
- pipe pile
- rock
- precipitous
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Foundations (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210536150.5A CN102953341B (en) | 2012-12-13 | 2012-12-13 | A kind of high-order trestle work structure be arranged in deep water torrent intectate steep bare rock |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210536150.5A CN102953341B (en) | 2012-12-13 | 2012-12-13 | A kind of high-order trestle work structure be arranged in deep water torrent intectate steep bare rock |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102953341A true CN102953341A (en) | 2013-03-06 |
CN102953341B CN102953341B (en) | 2015-10-21 |
Family
ID=47762684
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210536150.5A Active CN102953341B (en) | 2012-12-13 | 2012-12-13 | A kind of high-order trestle work structure be arranged in deep water torrent intectate steep bare rock |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102953341B (en) |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103306202A (en) * | 2013-06-14 | 2013-09-18 | 中铁大桥局集团第二工程有限公司 | Steel panel used in fabricated Bailey truss in matching manner |
CN103898910A (en) * | 2014-03-10 | 2014-07-02 | 中交一航局第三工程有限公司 | Method for anchoring trestle steel pipe piles on seabed rock bare landform |
CN104047222A (en) * | 2013-03-14 | 2014-09-17 | 上海市政工程设计研究总院(集团)有限公司 | Bridge structure near mountain and by river and construction method of bridge |
CN104929044A (en) * | 2014-04-04 | 2015-09-23 | 重庆建工桥梁工程有限责任公司 | Construction method for offshore steel trestle |
CN104922825A (en) * | 2015-06-15 | 2015-09-23 | 徐州工程学院 | Quick laying cart for earthquake rescue emergency access |
CN107386285A (en) * | 2017-08-03 | 2017-11-24 | 中铁六局集团有限公司 | A kind of novel steel tube pile foundation rock borehole anchorage method |
CN107574813A (en) * | 2017-08-09 | 2018-01-12 | 贵州正业工程技术投资有限公司 | The device and construction method of Soil-rock combined ground are passed through in a kind of karst area |
CN107700366A (en) * | 2017-11-20 | 2018-02-16 | 中铁二十局集团第工程有限公司 | Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method |
CN108547276A (en) * | 2018-05-28 | 2018-09-18 | 宁波交通工程建设集团有限公司 | It is waterborne to fill sand steel tube pile embeded in rock workbench and its construction method |
CN108625365A (en) * | 2018-06-20 | 2018-10-09 | 湖南建工交通建设有限公司 | Improve prestress and cultivation stake composite structure and the construction method of steel trestle antidumping |
CN108660909A (en) * | 2018-07-24 | 2018-10-16 | 东北大学 | A kind of prefabricated steel and concrete combination beam trestle and construction method |
CN110409281A (en) * | 2019-08-12 | 2019-11-05 | 中交隧道工程局有限公司 | A kind of deep water drift net steel trestle |
CN110847047A (en) * | 2019-11-21 | 2020-02-28 | 中交第二航务工程局有限公司 | Open sea bare rock trestle construction method |
CN111364492A (en) * | 2020-03-11 | 2020-07-03 | 中国建筑第六工程局有限公司 | Deep-water shallow-covering-layer steel pipe anchoring construction device and method |
CN114855588A (en) * | 2022-04-14 | 2022-08-05 | 中建铁路投资建设集团有限公司 | Temporary construction transfer platform ramp trestle combination |
CN114960651A (en) * | 2022-04-29 | 2022-08-30 | 中国铁建港航局集团有限公司 | Bored concrete pile drilling platform and construction method thereof |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS54156312A (en) * | 1978-05-31 | 1979-12-10 | Kahee Shimomura | Underwater polystyle foundation provided with multilayer footing |
US20050084338A1 (en) * | 2003-10-15 | 2005-04-21 | Fmc Technologies, Inc. | Mudmat foundation for subsea equipment |
CN101078211A (en) * | 2007-04-23 | 2007-11-28 | 中铁大桥局集团第二工程有限公司 | Underwater anchorage system auxiliary wooden stool structure platform and construction method thereof |
KR20100005830A (en) * | 2008-07-08 | 2010-01-18 | 고려대학교 산학협력단 | Development of a set bridge post connector using unit filled concrete with internally confined hollow and a method for construction |
CN101666081A (en) * | 2009-09-23 | 2010-03-10 | 中交二公局第六工程有限公司 | Abrupt slope bare rock drilling platform and technology in huge reservoir |
CN102619206A (en) * | 2012-04-06 | 2012-08-01 | 中铁二十二局集团第三工程有限公司 | Foundation platform structure of bare rock and karst pile in deep water |
-
2012
- 2012-12-13 CN CN201210536150.5A patent/CN102953341B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS54156312A (en) * | 1978-05-31 | 1979-12-10 | Kahee Shimomura | Underwater polystyle foundation provided with multilayer footing |
US20050084338A1 (en) * | 2003-10-15 | 2005-04-21 | Fmc Technologies, Inc. | Mudmat foundation for subsea equipment |
CN101078211A (en) * | 2007-04-23 | 2007-11-28 | 中铁大桥局集团第二工程有限公司 | Underwater anchorage system auxiliary wooden stool structure platform and construction method thereof |
KR20100005830A (en) * | 2008-07-08 | 2010-01-18 | 고려대학교 산학협력단 | Development of a set bridge post connector using unit filled concrete with internally confined hollow and a method for construction |
CN101666081A (en) * | 2009-09-23 | 2010-03-10 | 中交二公局第六工程有限公司 | Abrupt slope bare rock drilling platform and technology in huge reservoir |
CN102619206A (en) * | 2012-04-06 | 2012-08-01 | 中铁二十二局集团第三工程有限公司 | Foundation platform structure of bare rock and karst pile in deep water |
Non-Patent Citations (1)
Title |
---|
罗根传: "钻孔平台(栈桥)钢管及桩基钢护筒底部固结方案", 《西部交通科技》 * |
Cited By (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104047222A (en) * | 2013-03-14 | 2014-09-17 | 上海市政工程设计研究总院(集团)有限公司 | Bridge structure near mountain and by river and construction method of bridge |
CN103306202A (en) * | 2013-06-14 | 2013-09-18 | 中铁大桥局集团第二工程有限公司 | Steel panel used in fabricated Bailey truss in matching manner |
CN103306202B (en) * | 2013-06-14 | 2015-04-29 | 中铁大桥局集团第二工程有限公司 | Steel panel used in fabricated Bailey truss in matching manner |
CN103898910A (en) * | 2014-03-10 | 2014-07-02 | 中交一航局第三工程有限公司 | Method for anchoring trestle steel pipe piles on seabed rock bare landform |
CN104929044A (en) * | 2014-04-04 | 2015-09-23 | 重庆建工桥梁工程有限责任公司 | Construction method for offshore steel trestle |
CN104922825A (en) * | 2015-06-15 | 2015-09-23 | 徐州工程学院 | Quick laying cart for earthquake rescue emergency access |
CN104922825B (en) * | 2015-06-15 | 2018-02-06 | 齐鲁工业大学 | Earthquake rescue emergency access quickly lays car |
CN107386285A (en) * | 2017-08-03 | 2017-11-24 | 中铁六局集团有限公司 | A kind of novel steel tube pile foundation rock borehole anchorage method |
CN107574813A (en) * | 2017-08-09 | 2018-01-12 | 贵州正业工程技术投资有限公司 | The device and construction method of Soil-rock combined ground are passed through in a kind of karst area |
CN107700366A (en) * | 2017-11-20 | 2018-02-16 | 中铁二十局集团第工程有限公司 | Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method |
CN108547276A (en) * | 2018-05-28 | 2018-09-18 | 宁波交通工程建设集团有限公司 | It is waterborne to fill sand steel tube pile embeded in rock workbench and its construction method |
CN108547276B (en) * | 2018-05-28 | 2023-11-28 | 宁波交通工程建设集团有限公司 | Water sand-filled rock-socketed steel pipe pile working platform and construction method thereof |
CN108625365A (en) * | 2018-06-20 | 2018-10-09 | 湖南建工交通建设有限公司 | Improve prestress and cultivation stake composite structure and the construction method of steel trestle antidumping |
CN108660909A (en) * | 2018-07-24 | 2018-10-16 | 东北大学 | A kind of prefabricated steel and concrete combination beam trestle and construction method |
CN110409281A (en) * | 2019-08-12 | 2019-11-05 | 中交隧道工程局有限公司 | A kind of deep water drift net steel trestle |
CN110409281B (en) * | 2019-08-12 | 2024-03-15 | 中交隧道工程局有限公司 | Deepwater bare rock steel trestle |
CN110847047A (en) * | 2019-11-21 | 2020-02-28 | 中交第二航务工程局有限公司 | Open sea bare rock trestle construction method |
CN110847047B (en) * | 2019-11-21 | 2021-11-26 | 中交二航局第一工程有限公司 | Open sea bare rock trestle construction method |
CN111364492A (en) * | 2020-03-11 | 2020-07-03 | 中国建筑第六工程局有限公司 | Deep-water shallow-covering-layer steel pipe anchoring construction device and method |
CN114855588A (en) * | 2022-04-14 | 2022-08-05 | 中建铁路投资建设集团有限公司 | Temporary construction transfer platform ramp trestle combination |
CN114960651A (en) * | 2022-04-29 | 2022-08-30 | 中国铁建港航局集团有限公司 | Bored concrete pile drilling platform and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN102953341B (en) | 2015-10-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102953341B (en) | A kind of high-order trestle work structure be arranged in deep water torrent intectate steep bare rock | |
CN102979039B (en) | Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream | |
CN104612162B (en) | A kind of Deep Foundation Pit of Metro Stations excavation construction method | |
CN105386408B (en) | Deep-water bridge pile foundation construction method | |
CN102979069A (en) | Bored pile platform construction method on covering-free steep bare rock in deepwater and rapid stream | |
CN102953362B (en) | A kind of drilled pile platform be arranged in deep water torrent intectate steep bare rock | |
CN101864773B (en) | Deep foundation pit support process | |
CN102966111B (en) | A kind of steel pipe pile anchoring construction method in deep water torrent intectate steep bare rock | |
CN101666081B (en) | Abrupt slope bare rock drilling platform and technology in huge reservoir | |
CN203049443U (en) | High level trestle structure arranged on steep bare rock of deepwater torrent unsheathed layer | |
CN107700366B (en) | Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method | |
CN109780325A (en) | A kind of water factory's water intaking tunnel submarine pipeline installation method | |
CN105040715A (en) | Method for building bridge construction cofferdam through steel sheet piles | |
CN107503362A (en) | A kind of compound antiskid piling wall retaining structure and construction method suitable for reservoir stability | |
CN102561371A (en) | Steel caisson enclosure structure at island-tunnel combination part | |
CN109797749A (en) | Underwater foundation pit construction device and construction method | |
CN104164881A (en) | Piling wall overlapping cantilever foundation pit support construction method and structure | |
CN113174958A (en) | Construction method for foundation pit of adjacent road under poor ground condition | |
CN104912065A (en) | Underwater anchor pile construction method | |
CN109610473A (en) | A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration | |
CN106758759B (en) | A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed | |
CN201502056U (en) | Bare rock drilling platform for steep slope of deep reservoir area | |
CN207452738U (en) | The deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone | |
CN201459749U (en) | Stable structure for construction platform of deep water steel pipe pile | |
CN202989949U (en) | Steel casing fixing structure on steep bare rock without covering layer in deep water and rapids |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C53 | Correction of patent of invention or patent application | ||
CB02 | Change of applicant information |
Address after: 200436 Shanghai, Zhabei District, West Lane Road, Lane Lane, central Times Square, building 9, floor 2, layer 299 Applicant after: Shanghai Civil Engineering Co., Ltd. of Crec Applicant after: CRECSHANGHAI CIVIL ENGINEERING GROUP NO.2 ENGINEERING CO., LTD. Address before: 200436 Shanghai, Zhabei District, West Lane Road, Lane Lane, central Times Square, building 9, floor 2, layer 299 Applicant before: Shanghai Civil Engineering Co., Ltd. of CREC Applicant before: No.2 Engineering Company, Shanghai Civil Engineering Co., Ltd. of CREC |
|
COR | Change of bibliographic data |
Free format text: CORRECT: APPLICANT; FROM: SHANGHAI CIVIL ENGINEERING CO., LTD. OF CREC TO: SHANGHAI CIVIL ENGINEERING CO., LTD. OF CREC |
|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 200436, 9 floor, building 2, Times Square, central Times Square, Lane 299, Shanghai Road, Zhabei District Co-patentee after: China Railway Shanghai Engineering Bureau Group Municipal Environmental Protection Engineering Co.,Ltd. Patentee after: SHANGHAI CIVIL ENGINEERING Co.,Ltd. OF CREC Address before: 200436, 9 floor, building 2, Times Square, central Times Square, Lane 299, Shanghai Road, Zhabei District Co-patentee before: NO 2 ENGINEERING Co.,Ltd. SHANGHAI CIVIL ENGINEERING CO LTD OF CREC Patentee before: SHANGHAI CIVIL ENGINEERING Co.,Ltd. OF CREC |
|