CN107700366B - Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method - Google Patents

Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method Download PDF

Info

Publication number
CN107700366B
CN107700366B CN201711160995.8A CN201711160995A CN107700366B CN 107700366 B CN107700366 B CN 107700366B CN 201711160995 A CN201711160995 A CN 201711160995A CN 107700366 B CN107700366 B CN 107700366B
Authority
CN
China
Prior art keywords
steel
girder
trestle
buttress
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711160995.8A
Other languages
Chinese (zh)
Other versions
CN107700366A (en
Inventor
梁之海
杜越
刘俊斌
赵久远
朱山山
严朝锋
王永丽
李东牛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd filed Critical First Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd
Priority to CN201711160995.8A priority Critical patent/CN107700366B/en
Publication of CN107700366A publication Critical patent/CN107700366A/en
Application granted granted Critical
Publication of CN107700366B publication Critical patent/CN107700366B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/12Portable or sectional bridges
    • E01D15/133Portable or sectional bridges built-up from readily separable standardised sections or elements, e.g. Bailey bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/005Piers, trestles, bearings, expansion joints or parapets specially adapted for portable or sectional bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Abstract

It includes trestle ontology and the horizontal operation platform on front side of trestle ontology that the invention discloses a kind of deep water high-block bridge degree bridge constructions with the naked rock river bed trestle of hard stone and construction method, the trestle;Trestle ontology includes bottom bracing structure, girder and floorings, bottom bracing structure includes one or more lower anchors in the steel buttress anchor pile on naked rock river bed, girder front support is supported in the supporting table of bank side on steel cofferdam and its rear end, and concrete pumping pipe is placed on floorings;For horizontal operation putting up platform on steel cofferdam and it is connected as one with girder, steel buttress anchor pile includes groined type steel buttress and steel buttress anchor structure;The method comprising the steps of: one, steel buttress anchors pile driving construction;Two, main beam supporting;Three, floorings are mated formation.Structure of the invention designs reasonable, easy construction and using effect is good, is supported on naked rock river bed using steel buttress anchor pile is firm, girder rear and front end is respectively supported in steel cofferdam and bank side supporting table, saving of work and time.

Description

Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method
Technical field
The invention belongs to bridge construction technical fields, more particularly, to the deep water high-block bridge degree bridge construction naked rock river of hard stone Bed trestle and construction method.
Background technique
With the development of national economy, China railways bridge cause is grown rapidly, and China is in Bridge Design theory, construction skill Art and equipment aspect are being caught up with or close to advanced international standard, large span is over strait, crossing-fiver bridge construction is continuously increased.To depth Water, Gao Dun, Longspan Bridge water in pier carry out in work progress, when riverbed is the naked rock river bed of hard stone, the construction of pier in water Difficulty is bigger, it usually needs sets up trestle.Wherein, " deep water " refers to the depth of water of bridge foundation in 5m~6m or more, and " high pier " is Refer to that bridge pier height is 30 meters or more, " large span " refers to porous across footpath overall length >=100 meter and single hole across footpath >=40 meter.Hard stone is (i.e. Solid rock) refer to fresh complete, particle electrical connection and the rock for having higher mechanical strength, refer generally in saturated-water phase Under compressive ultimate strength be greater than the rocks of 50 kg/cms, such as sedimentary rock, igneous rock, metamorphic rock, solid rock tool There are very high mechanical strength and very strong water-resistance.Naked rock river bed refers to that riverbed is the exposed bedrock of intectate.
When reality sets up trestle, since bridge location riverbed is naked rock river bed, rock is hard, and the anchoring of trestle buttress is stack The critical process of key and trestle construction safety the quality control of bridge construction technology.In deep-water bare solid rock riverbed and Under streamflow regime, pile foundation construction steel pile casting can not be installed and carry out mud circulation, set up drilling platform difficulty, therefore use tradition Method plugs steel sheet pile construction or is drilled to hole construction method difficulty using normal impact, and the anchoring of trestle buttress is a great problem;If Then needing to install chamber type template using pouring underwater concrete package steel buttress method, concreting side's amount is bigger, and The bad control of construction quality, steel buttress anchoring effect is poor, and in the library flood discharge of flood season Minjiang upper, steel buttress stability is difficult It also needs to remove concrete using Blasting Excavation method by navigation channel and hydraulic department relevant regulations to guarantee, and after the completion of trestle use To original bed face.
Summary of the invention
In view of the above-mentioned deficiencies in the prior art, the technical problem to be solved by the present invention is that providing a kind of high pier of deep water The span bridge construction naked rock river bed trestle of hard stone, reasonable in design, easy construction remove convenient and using effect It is good, it is supported on naked rock river bed using steel buttress anchor pile is firm, it is collateral with bank that girder rear and front end is respectively supported at steel cofferdam It supports on platform, saving of work and time.
In order to solve the above technical problems, the technical solution adopted by the present invention is that: a kind of deep water high-block bridge degree bridge construction With the naked rock river bed trestle of hard stone, it is characterised in that: including the trestle ontology for pier in water of constructing and be located at the trestle ontology The horizontal operation platform of front side, pier is reinforced concrete knoll in the water;The trestle ontology includes bottom bracing structure, level The girder being set up on the bottom bracing structure and the floorings being layed on girder, the bottom bracing structure include one Or multiple lower anchors, in the steel buttress anchor pile on naked rock river bed, the steel buttress anchor pile is arranged vertically, Duo Gesuo Steel buttress anchor pile is stated to be supported in from the front to the back below girder;The front support of girder pier in for the water of constructing On steel cofferdam, the rear end of the girder is supported in the supporting table of bank side, and bank side supporting table is the support being erected on riverbank Platform;The length of the girder is not less than the clear distance between bank side supporting table and steel cofferdam, is placed with and is used on the floorings It constructs the concrete pumping pipe of pier in the water;The horizontal operation putting up platform is on steel cofferdam, the horizontal operation platform It is connected as one with girder;
The steel buttress anchor pile includes groined type steel buttress and the steel that is anchored to the groined type steel branch pedestal Buttress anchor structure, the stake holes for the steel buttress anchor pile lower anchor is drilled on the naked rock river bed, and the stake holes is in Vertically to lay and its depth be not less than 5m, the groined type steel buttress lower part is located at the middle inside of the stake holes;The steel Buttress anchor structure is the concrete structure of the concrete form by injecting in the stake holes, the steel buttress anchor structure Height it is consistent with the depth of the stake holes;The groined type steel buttress includes four structure snd size vertical steels all the same It manages, is fastenedly connected by horizontal brace rod between adjacent two vertical steel pipes, the horizontal brace rod is located at steel buttress Above anchor structure;The bottom end of the every vertical steel pipe is supported in the stake holes bottom, under the every vertical steel pipe Portion is poured into steel buttress anchor structure.
The above-mentioned deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that: the concrete Pumping line is laid from the front to the back along the length of girder.
The above-mentioned deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that: the bank is collateral The apical side height for supportting platform is identical as the overhead height of steel cofferdam, and the top surface of the horizontal operation platform is equal with the top surface of floorings Together.
The above-mentioned deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that: the stake holes Aperture is φ 2m~φ 3m.
The above-mentioned deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that: the vertical steel The outer diameter of pipe is φ 0.6m~φ 0.65m, and the clear distance between adjacent two vertical steel pipes is 0.4m~0.7m.
The above-mentioned deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that: the groined type The transverse distribution beam that multiple tracks is laid in same level, the transverse distribution beam and the perpendicular cloth of girder are provided on steel buttress If the girder is supported on transverse distribution beam described in multiple tracks, transverse distribution Liang Juncheng horizontal layout described in multiple tracks and along girder Length direction lay from the front to the back.
The above-mentioned deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that: the groined type The quantity of laid transverse distribution beam is twice on steel buttress, and transverse distribution beam described in twice is respectively front side distribution beam and is located at The rear side distribution beam at front side distribution beam rear;
Four vertical steel pipes include front side steel pipe and two piece of two symmetric supports below the front side distribution beam Rear side steel pipe of the symmetric support below the rear side distribution beam, two front side steel pipes and two rear side steel pipes are in pair Claim to lay, two front side steel pipes are symmetrically laid in below the left and right sides of girder, and two rear side steel pipes are symmetrically laid Below the left and right sides of girder;The front side distribution beam is weldingly fixed on two front side steel pipes, the rear side distribution Beam is weldingly fixed on two rear side steel pipes;
Pass through the fastening of horizontal brace rod described in the multiple tracks from top to bottom laid between adjacent two vertical steel pipes to connect It connects, the horizontal brace rod is fashioned iron rod piece and is fixedly connected between vertical steel pipe with welding manner;
The postive stop baffle that girder is limited there are two being respectively provided on transverse distribution beam described in per pass, the postive stop baffle It is arranged vertically, two postive stop baffles are symmetrically laid at left and right sides of girder;The overhead height of the postive stop baffle is low In the apical side height of girder.
The above-mentioned deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that: further include twice Be laid in same level and to the longitudinal spacing part limited at the top of girder, the longitudinal spacing part in horizontal layout and It is laid with girder in parallel, and the girder top card is loaded between longitudinal spacing part described in twice;
The upper distribution beam being laid in same level is provided on the girder from the front to the back, the upper distribution beam is in water Plain cloth is set and itself and the perpendicular laying of girder;The floorings are paved in upper distribution beam described in multiple tracks;
Longitudinal spacing part described in twice is respectively positioned below distribution beam, longitudinal spacing part described in per pass with described in multiple tracks on Distribution beam, which is fastenedly connected, to be integrated;
The girder includes the Bailey beam that multiple tracks is laid from left to right, and Bailey beam described in multiple tracks is arranged vertically and it Laid in parallel;It is fastenedly connected and is integrated by longitudinal connection structure between Bailey beam described in adjacent twice, the longitudinal direction connects Binding structure is the truss frame for connecting being spliced by multiple tracks connecting rod;
The floorings are horizontal steel plate, are provided with protective fence above the left and right sides of the floorings.
Meanwhile a kind of the invention also discloses method and steps simple, design is rationally and easy construction, construction quality are easy to protect The deep water high-block bridge degree bridge construction of the card naked rock river bed trestle construction method of hard stone, which is characterized in that this method include with Lower step:
Step 1: steel buttress anchors pile driving construction: it constructs respectively to each steel buttress anchor pile of institute's construction bridge, until Complete the work progress of all steel buttress anchor piles;The construction method of all steel buttress anchor piles is all the same;
When constructing any one described steel buttress anchor pile, process is as follows:
Step 101, drilling: current institute's construction steel buttress anchor pile is from top to bottom drilled through on naked rock river bed using drilling machine The stake holes;
Step 102, groined type steel buttress lifting: will be pre-machined the molding groined type steel buttress lift and transfer to In stake holes described in step 101, the groined type steel buttress lower part is set to be located at the middle inside of the stake holes, and make the well word The bottom end of the every vertical steel pipe is supported in the stake holes bottom in shape steel buttress;
Step 103, anchoring: the concrete perfusion into stake holes described in step 101 obtains after the solidification of institute's concrete perfusion Obtain the steel buttress anchor structure of construction molding;
Step 2: main beam supporting: being ready to use in after the completion of the steel cofferdam construction of pier in the water of constructing, by institute's construction bridge Main beam supporting construct in step 1 completion steel buttress anchor pile on, and by the front support of girder on steel cofferdam and leading The rear end of beam is supported in the supporting table of bank side;
Step 3: floorings are mated formation: floorings of mating formation on the girder described in step 2;
In step 2 middle girder erection process, horizontal operation platform is synchronized and is set up, and by girder and horizontal operation Platform, which is fastenedly connected, to be integrated.
The above method, it is characterized in that: being bored when being drilled in step 101 using the drilling platform for floating on the water surface Hole;The construction channel for the steel buttress anchor pile of constructing is provided on the drilling platform, the drilling machine is all-hydraulic impact Clean-out machine and its be installed on the drilling platform;
When carrying out the lifting of groined type steel buttress in step 102, the groined type steel buttress is lifted and transferred using crane barge In to the stake holes;
In step 103 into the stake holes when concrete perfusion, it is irrigated using the crane barge.
Compared with the prior art, the present invention has the following advantages:
1, steel buttress anchor pile is reasonable in design, using single pile single-column form, using the single pile groined type steel of major diameter Buttress, a combination thereof rigidity of structure is big, and resistance flood impact capacity is strong, easy for construction, and groined type steel buttress bottom anchor jail It leans on, easy construction.The construction quality of steel buttress anchor pile is easy to control, and steel buttress anchoring effect is good, and trestle resists flood impact Ability is strong, securely and reliably.
2, convenient for disassembly and assembly using floating platform as drilling platform, without in addition setting up drilling platform, it is easy for construction flexibly, Platform can be facilitated mobile, securely and reliably, save the cost.Drilling platform structure is simple, and raft includes 2 parallel and independent cloth If platform body substantially saved the dosage of steel while meeting drilling device installation, and it is difficult to greatly reduce construction Degree;Drilled tunnel is arranged between 2 platform bodies, when drilling construction, will not generate eccentric force, be conducive to the steady of raft Determining raft includes 2 platform bodies that are parallel and independently laying, and the clear distance between 2 platform bodies is not less than 2.5m, While meeting drilling device installation, the dosage of steel is substantially saved, and difficulty of construction greatly reduces.Also, 2 flat It is connected between playscript with stage directions body by crossbeam, the intensity and toughness of crossbeam is larger, increases the impact resistance of platform body, guarantees platform The stability and globality of ontology.Meanwhile the drilled tunnel for drilling device construction is provided between drilling frame and crossbeam, It no longer needs to open up drilled tunnel on raft, while the drilled tunnel is arranged between 2 platform bodies, drilling construction When, eccentric force will not be generated, the stabilization of raft is conducive to;And the setting of bearing beam is the weight for undertaking drilling device, The dynamic load generated when by the gravity of drilling device and operation buffers, if directly drilling device is arranged on buoyancy tank, Buoyancy tank can be made to be deformed, influence the bearing capacity of buoyancy tank.Thus, stake position bore position can effectively be ensured using the drilling platform.
3, riverbed is the exposed riverbed of solid rock, and stake holes aperture will not collapse, and does not need installation steel pile casting.
4, construction method is simple, easy construction and using effect are good, using all-hydraulic percussion reverse circulation drill drilling construction, Using gas lift method borehole cleaning, solid rock will not collapse hole, do not need the measures such as steel pile casting, mud off and mud circulation cleaning quarrel, clearly Hole effect is good, and easy for construction, speed is fastly, environmental protection is good and saves cost.Trestle is easy to remove after completion, after the completion of engineering construction, Steel buttress need to only be cut off from riverbed face position and be removed when trestle is removed, met navigation channel and flood control requires, it is convenient to remove.
5, practical value is high and popularization and application foreground is extensive, and versatility is good, can be commonly used to naked rock river bed trestle steel buttress In anchoring, construction safety is reliable, and easy for construction, speed is fast, saves construction cost.Used steel buttress anchor pile rigidity is big, Flood fighting water slug ability is strong, easy for construction, saves construction cost, is particularly useful for the only cylindricality formula steel buttress construction of simple trestle.
In conclusion structure of the invention design is reasonable, easy construction, dismounting is convenient and using effect is good, using steel buttress Anchor pile is firm to be supported on naked rock river bed, and girder rear and front end is respectively supported in steel cofferdam and bank side supporting table, and saving of labor saves When.
Below by drawings and examples, technical scheme of the present invention will be described in further detail.
Detailed description of the invention
Fig. 1 is the vertical bridge of the hard naked rock river bed trestle of stone of the present invention to structural schematic diagram.
Fig. 2 is the direction across bridge structural schematic diagram of the naked rock river bed trestle of the hard stone of the present invention.
Fig. 3 is the method flow block diagram when present invention constructs to hard stone naked rock river bed trestle.
Fig. 4 for the used drilling platform of the present invention structural schematic diagram.
Description of symbols:
1-girder;3-floorings;
4-naked rock river beds;5-steel buttress anchor piles;5-1-steel buttress anchor structure;
5-2-vertical steel pipe;5-3-horizontal brace rod;5-4-transverse distribution beam;
6-postive stop baffles;7-protective fences;8-upper distribution beams;
9-longitudinal spacing parts;10-bank side supporting tables;11-steel cofferdams;
12-concrete pumping pipes;13-horizontal operation platforms;13-1-platform body;
13-2-crossbeam;13-3-bearing beam;13-4-anchor ingot.
Specific embodiment
A kind of deep water high-block bridge degree bridge construction as shown in Figure 1 and Figure 2 naked rock river bed trestle of hard stone, including be used for It constructs the trestle ontology of pier and the horizontal operation platform 13 on front side of the trestle ontology in water, pier is mixed for reinforcing bar in the water Solidifying knoll;The trestle ontology includes the girder 1 and laying of bottom bracing structure, level frame on the bottom bracing structure In the floorings 3 on girder 1, the bottom bracing structure includes one or more lower anchors in the steel branch on naked rock river bed 4 Pier anchor pile 5, the steel buttress anchor pile are arranged vertically, and multiple steel buttress anchor piles are supported in girder from the front to the back 1 lower section;The steel cofferdam 11 of the front support of the girder 1 pier in for the water of constructing, the rear end support of the girder 1 In in bank side supporting table 10, bank side supporting table 10 is the support platform being erected on riverbank;The length of the girder 1 is not small Clear distance between bank side supporting table 10 and steel cofferdam 11, be placed on the floorings 3 in the water of constructing pier it is mixed Solidifying soil pumping line 12;The horizontal operation platform 13 is erected on steel cofferdam 11, and the horizontal operation platform 13 is connect with girder 1 It is integrated;
The steel buttress anchor pile 5 includes groined type steel buttress and the steel anchored to the groined type steel branch pedestal Buttress anchor structure 5-1 is drilled with the stake holes for the steel buttress anchor pile lower anchor, the stake on the naked rock river bed 4 Hole is arranged vertically and its depth is not less than 5m, and the groined type steel buttress lower part is located at the middle inside of the stake holes;Institute State the concrete structure that steel buttress anchor structure 5-1 is the concrete form by injecting in the stake holes, the steel buttress The height of anchor structure 5-1 is consistent with the depth of the stake holes;The groined type steel buttress includes that four structure snd size are homogeneous It is fastenedly connected by horizontal brace rod 5-3 between same vertical steel pipe 5-2, adjacent two vertical steel pipe 5-2, the water Flushconnection bar 5-3 is located above steel buttress anchor structure 5-1;The bottom end of the every vertical steel pipe 5-2 is supported in the stake Hole bottom, the lower part of the every vertical steel pipe 5-2 are poured into steel buttress anchor structure 5-1.
In the present embodiment, the concrete pumping pipe 12 is laid from the front to the back along the length of girder 1.
Also, the concrete pumping pipe 12 is in horizontal layout.Thus, it can length that is easy, effectively meeting pier in the water Apart from concrete conveyance demand.
In the present embodiment, the apical side height of bank side supporting table 10 is identical as the overhead height of steel cofferdam 11, the water The top surface of flat workbench 13 and the top surface flush of floorings 3.
Thus, the top surface of horizontal operation platform 13 and the top surface of floorings 3, thus can largely simplify pier in water Work progress.Also, while improving the standard 13 overall stability of workbench, the position of steel cofferdam 11 can be carried out effective Limit.
Wherein, the horizontal operation platform 13 is the workbench for pier in the water of constructing;1 front end of girder with Horizontal operation platform 13 is connected as one.
When practice of construction, the aperture of the stake holes is φ 2m~φ 3m.The outer diameter of the vertical steel pipe 5-2 be φ 0.6m~ Clear distance between φ 0.65m, adjacent two vertical steel pipe 5-2 is 0.4m~0.7m.Thus, it is according to specific needs, right The aperture of the stake holes, the vertical steel pipe 5-2 outer diameter and adjacent two vertical steel pipe 5-2 between clear distance difference It adjusts accordingly.
In the present embodiment, the transverse distribution beam that multiple tracks is laid in same level is provided on the groined type steel buttress 5-4, the transverse distribution beam 5-4 and the perpendicular laying of girder 1, the girder 1 are supported in transverse distribution beam 5-4 described in multiple tracks On, transverse distribution beam 5-4 described in multiple tracks is in horizontal layout and lays from the front to the back along the length direction of girder 1.
The quantity of laid transverse distribution beam 5-4 is twice, transverse distribution beam described in twice on the groined type steel buttress 5-4 is respectively front side distribution beam and the rear side distribution beam positioned at front side distribution beam rear.
Four vertical steel pipe 5-2 include front side steel pipe and two of two symmetric supports below the front side distribution beam Rear side steel pipe of the root symmetric support below the rear side distribution beam, two front side steel pipes are in two rear side steel pipes Symmetrical to lay, two front side steel pipes are symmetrically laid in below the left and right sides of girder 1, two symmetrical cloth of rear side steel pipe Below the left and right sides of girder 1;The front side distribution beam is weldingly fixed on two front side steel pipes, the rear side point It is weldingly fixed on two rear side steel pipes with beam.
Pass through horizontal brace rod 5-3 described in the multiple tracks from top to bottom laid between adjacent two vertical steel pipe 5-2 It is fastenedly connected, the horizontal brace rod 5-3 is fashioned iron rod piece and is fixedly connected between vertical steel pipe 5-2 with welding manner.
The postive stop baffle 6 that girder 1 is limited there are two being respectively provided on transverse distribution beam 5-4 described in per pass, the limit Position baffle 6 is arranged vertically, and two postive stop baffles 6 are symmetrically laid in 1 left and right sides of girder;The postive stop baffle 6 Overhead height is lower than the apical side height of girder 1.
Meanwhile the deep water high-block bridge degree bridge construction of the present invention naked rock river bed trestle of hard stone, it further include twice It is laid in same level and to the longitudinal spacing part 9 limited at the top of girder 1, the longitudinal spacing part 9 is in horizontal cloth And if it is laid in parallel with girder 1,1 top card of girder is loaded between longitudinal spacing part 9 described in twice.
In the present embodiment, the upper distribution beam 8 being laid in same level, institute are provided on the girder 1 from the front to the back Distribution beam 8 is stated in horizontal layout and itself and the perpendicular laying of girder 1;The floorings 3 are paved on upper distribution beam 8 described in multiple tracks On.
Longitudinal spacing part 9 described in twice is respectively positioned on the lower section of distribution beam 8, longitudinal spacing part 9 described in per pass with multiple tracks institute It states distribution beam 8 and is fastenedly connected and be integrated.
In the present embodiment, the girder 1 includes the Bailey beam that multiple tracks is laid from left to right, and Bailey beam described in multiple tracks is in perpendicular Straight Xiang Bushe and its be in parallel laying;Being fastenedly connected between Bailey beam described in adjacent twice by longitudinal connection structure is one Body, the longitudinal connection structure are the truss frame for connecting being spliced by multiple tracks connecting rod.
In the present embodiment, the floorings 3 are horizontal steel plate, are provided with above the left and right sides of the floorings 3 anti- Guardrail 7.
In the present embodiment, pier is located on naked rock river bed in the water and it is located at Minjiang Shuikou Reservoir Tail, Fujian at bridge location River face is open, and bridge zone section is IV grade of navigation channel, and in downstream in the case where not flood discharge, flow velocity is 0.5m/s or so, flood discharge at bridge location When design current velocity 3.3m/s, design and construct water level+62.5m, 2 years one chance design water level 67m;Riverbed is intectate, exposed base Rock, riverbed are severely-weathered, weak weathered granite.
Consider that navigation condition, the hydrology, geology and the construction cost in the Min River, the heavily fortified point naked rock river bed trestle of stone of the present invention are adopted It with simple trestle scheme, is set up from riverbank Xiang Shuizhong pier direction, and the hard naked rock river bed trestle of stone is in water the steel cofferdam of pier Upstream side, installation and the personnel for meeting concrete pump pipe 12 are current, and construction material and equipment use water transportation Ship Transportation.
In the present embodiment, the quantity of the steel buttress anchor pile 5 is two.
When practice of construction, according to specific needs, the cloth of quantity and each steel buttress anchor pile 5 to steel buttress anchor pile 5 If position adjusts accordingly respectively.
In the present embodiment, the aperture of the stake holes is φ 2.5m and its depth is 6m.It is vertical in the groined type steel buttress Steel pipe 5-2 is the steel pipe of outer diameter φ 0.63m, and horizontal brace rod 5-3 is I-steel, and four vertical steel pipe 5-2 are connected using I-steel It connects to form entirety, groined type steel buttress is anchored using steel buttress anchor structure 5-1 (drill-pouring structure), effective anchorage depth is Strength grade of concrete used in 6m, steel buttress anchor structure 5-1 is C30.
The transverse distribution beam 5-4 is spliced by twice I-steel, transverse distribution beam 5-4 and the groined type steel buttress Between weld triangle bearing diagonal, Bailey beam is installed on transverse distribution beam 5-4 and is used as trestle main bearing beam, trestle is using deck type Structure, Bailey beam use three row's single layer structures, are laid with I-steel as bridge floor transverse distribution according to spacing 50cm on Bailey beam top Beam (i.e. upper distribution beam 8), in bridge floor transverse distribution beam laying depth 6mm steel plate as floorings 3, the width 2.5m of floorings 3, Bridge floor guardrail (i.e. protective fence 7) is highly 1.2m, and railing is using 75 × 75 × 8mm of ∠ angle steel as railing vertical bar.Trestle region For prohibited area, navigation mark setting is carried out.
In addition, also needing setting measure of water diversion, " V " font point water plate specifically is set along water surface side in groined type steel buttress, It avoids floating material from accumulating, increases steel buttress impact resistance.
As shown in figure 3, when constructing to the naked rock river bed trestle of hard stone, comprising the following steps:
Step 1: steel buttress anchors pile driving construction: constructing respectively to each steel buttress anchor pile 5 of institute's construction bridge, directly To the work progress for completing all steel buttress anchor piles 5;The construction method of all steel buttress anchor piles 5 is all the same;
When constructing any one described steel buttress anchor pile 5, process is as follows:
Step 101, drilling: current institute's construction steel buttress anchor pile is from top to bottom drilled through on naked rock river bed 4 using drilling machine The stake holes;
Step 102, groined type steel buttress lifting: will be pre-machined the molding groined type steel buttress lift and transfer to In stake holes described in step 101, the groined type steel buttress lower part is set to be located at the middle inside of the stake holes, and make the well word The bottom end of the every vertical steel pipe 5-2 is supported in the stake holes bottom in shape steel buttress;
Step 103, anchoring: the concrete perfusion into stake holes described in step 101 obtains after the solidification of institute's concrete perfusion Obtain the steel buttress anchor structure 5-1 of construction molding;
Step 2: main beam supporting: being ready to use in after the completion of the construction of steel cofferdam 11 of pier in the water of constructing, by institute's construction bridge Girder 1 be set up on the steel buttress anchor pile 5 for completion of constructing in step 1, and by the front support of girder 1 in steel cofferdam 11 Above and by the rear end of girder 1 it is supported in bank side supporting table 10;
Step 3: floorings are mated formation: floorings 3 of mating formation on the girder 1 described in step 2.
In step 2 middle girder erection process, horizontal operation platform 12 is synchronized and is set up, and by girder 1 and horizontal work Make platform 12 and be fastenedly connected to be integrated.
In the present embodiment, when being drilled in step 101, drilled using the drilling platform for floating on the water surface;It is described The construction channel for the steel buttress anchor pile of constructing is provided on drilling platform, the drilling machine is all-hydraulic percussion reverse circulation brill Machine and its be installed on the drilling platform.
When carrying out the lifting of groined type steel buttress in step 102, the groined type steel buttress is lifted and transferred using crane barge In to the stake holes;
In step 103 into the stake holes when concrete perfusion, it is irrigated using the crane barge.
The all-hydraulic percussion reverse circulation drill is the all-hydraulic percussion reverse circulation drill of YCJF-25 type, clear using gas lift method Be cut simultaneously concrete perfusion, is formed concrete clear water structure (i.e. steel buttress anchor structure 5-1).The steel buttress anchor structure 5-1 Valid bonding length be not less than 5m, the heavy quarrel thickness in bottom meets drilled pile construction code requirement;By groined type steel branch before perfusion Pier is inserted into stake holes, it is ensured that the anchoring of groined type steel buttress is secured;Later, pouring underwater concrete, filling concrete to riverbed face, Strength grade of concrete is C30, then the groined type steel buttress anchoring is completed, and obtains the steel buttress anchor pile 5 of construction molding.By It is the exposed riverbed of solid rock in riverbed, installation steel pile casting, mud off and mud is not needed using the steel buttress anchor pile 5 and followed Ring such as is cut clearly at the measures, only need to cut off groined type steel buttress from riverbed face position when trestle is removed, 5 anchor of steel buttress anchor pile Gu safe and reliable, easy for construction, speed is fastly, environmental protection is good and saves cost.
After the completion of all steel buttress anchor piles 5 are constructed, transverse distribution beam 5-4 is installed on each steel buttress anchor pile 5, Bailey beam is installed on transverse distribution beam 5-4 again.When reality installs transverse distribution beam 5-4 and the Bailey beam, use Crane barge is coupled.Bailey beam transportation by driving after harbour is assembled into pack is installed at bridge location, and Bailey beam bracket uses 90cm type branch Frame, after the completion of Bailey beam is assembled, all lower boom direction across bridge are integral using I-steel connection, and lower boom and I-steel Between using U-bolt connect, increase horizontal stability.Bailey beam top is transversely mounted distribution beam 8, then spacing 1.0m is spread If 6mm steel plate, finally installs guard rail.Due at left and right sides of load-bearing distribution beam and trestle beam-ends head be arranged limit measure (i.e. postive stop baffle 6 and longitudinal spacing part 9), can effectively increase the stability of trestle.
It when carrying out steel buttress anchoring pile driving construction in step 1, constructs according to construction process for bored pile, sinks quarrel thickness not Greater than 5cm.Institute's concrete perfusion intensity completes 5 work progress of steel buttress anchor pile after reaching design strength 70% in step 103.
The drilling platform is assembled and boring procedure in, drilling platform is always because under flowing water state and pile foundation construction shakes In dynamic state, stake holes position need to be detected at any time, the position of the drilling platform is adjusted using windlass, it is ensured that stake holes position is accurate.
As shown in figure 4, in the present embodiment, the drilling platform include drill frame, for the drilling frame installation floating it is flat Platform and anchoring mechanism for fixing the raft, the raft includes 2 platform body 13-1 laid in parallel, Clear distance between 2 platform body 13-1 is not less than 2.5m, and 2 platform body 13-1 are connected by crossbeam 13-2, The length of the crossbeam 13-2 is greater than 2.5m, and the quantity of the crossbeam 13-2 is 2, and 2 crossbeam 13-2 are separately positioned on The front and rear of the platform body 13-1,2 crossbeam 13-2 with the perpendicular laying of platform body 13-1, institute The drilled tunnel being provided between drilling frame and the crossbeam 13-2 for the drilling machine construction is stated, the drilling frame, which includes multiple, is in The bearing beam 13-3 equidistantly laid, multiple bearing beam 13-3 are parallel to each other, the both ends of each bearing beam 13-3 respectively with institute Platform body 13-1 connection is stated, the length of each bearing beam 13-3 is 12m~16m, the platform body 13-1, crossbeam 13-2 and bearing beam 13-3 are laid on same plane, and each platform body 13-1 is by multiple buoyancy tanks along single laying Assembled, multiple buoyancy tanks are laid in same level, and the width of each buoyancy tank is 5m~8m;The anchorage machine Structure includes multiple anchor ingots 4.
In actual use, the raft includes 2 platform body 13-1 laid in parallel, 2 platform bodies Clear distance between 13-1 is not less than 2.5m, has substantially saved the dosage of steel, and difficulty of construction greatly reduces.
In actual use, the clear distance between 2 platform body 13-1 is not less than 2.5m, and the width of each buoyancy tank Degree is 5m~8m, can satisfy the size requirement of drilling machine.
In the present embodiment, the weight of the drilling machine main engine is 19t, the weight 8t of tup, the size of drilling machine plane be it is long × The stroke of width=7.76m × 2.8m, the buoyancy tank upper ram is controlled in 0.3~0.4m.
In actual use, the connectors such as screw rod, connecting rod are attached between 2 platform body 13-1, preferably Crossbeam 13-2 connection is subject to be dead load since the platform body 13-1 is not when the drilling device carries out operation, when When the drilling device carries out bore operation, the dynamic loading that impact generates will receive, therefore to increase the platform body 13-1 Impact resistance, first have to the stability and globality that guarantee platform body 13-1, and the intensity and toughness of crossbeam 13-2 is larger, It is effectively increased the globality of the platform body 13-1.
In actual use, the length of the crossbeam 13-2 is greater than 2.5m, and the length of the preferred crossbeam 13-2 is 2 institutes The sum of the clear distance between platform body 13-1 and 2 platform body 13-1 is stated, crossbeam 13-2 and 2 platforms are increased The connection fixing of ontology 13-1.
In actual use, the setting of the bearing beam 13-3 is the weight for undertaking the drilling device, by the drilling The dynamic load generated when the gravity of equipment and operation is buffered, if directly the drilling device is arranged in the buoyancy tank On, the buoyancy tank can be made to be deformed, influence the bearing capacity of the buoyancy tank.
In actual use, each platform body 13-1 is assembled by multiple buoyancy tanks along single laying, preferably Each of the buoyancy tank laid along longitudinal direction by 2 of the platform body 13-1 it is assembled, and the size of each buoyancy tank are as follows: Length × width × height=9m × 2.7m × 1.65m.
In actual use, the quantity of the anchoring mechanism is 4 groups, and 4 anchor slabs 5 are fixed on the 4 of the raft A angle point.
In the present embodiment, the crossbeam 13-2 and the platform body 13-1 are welded.
In actual use, the crossbeam 13-2 and platform body 13-1 can be by bolt or welded connectings, preferably To be welded to connect, because the dynamic loading generated in the drilling device operation process can make bolt generate loosening, influence described The reliability connected between crossbeam 13-2 and platform body 13-1, to influence the globality and stabilization of the floating box type drilling platform Property.
In the present embodiment, the crossbeam 13-2 and the bearing beam 13-3 are i shaped steel.
It in actual use, is I36b I-steel to meet floating box type drilling platform described in the requirement of strength and stiffness.
In the present embodiment, multiple bearing beam 13-3's is centrally disposed in 2 middles platform body 13-1, described in reduction Raft generates eccentric force, influences the stability of the raft.
In the present embodiment, the anchor ingot 4 is laid in vertical, and the lower end of the anchor ingot 4 is fixed on basement rock, the anchor ingot 4 Upper end and the platform body 13-1 anchor.
The above is only presently preferred embodiments of the present invention, is not intended to limit the invention in any way, it is all according to the present invention Technical spirit any simple modification to the above embodiments, change and equivalent structural changes, still fall within skill of the present invention In the protection scope of art scheme.

Claims (8)

1. a kind of deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that: including for water of constructing The trestle ontology of middle pier and the horizontal operation platform (13) on front side of the trestle ontology, pier is armored concrete in the water Pier;The trestle ontology include bottom bracing structure, level frame be set to the bottom bracing structure on girder (1) and be layed in Floorings (3) on girder (1), the bottom bracing structure include one or more lower anchors on naked rock river bed (4) Steel buttress anchor pile (5), the steel buttress anchor pile are arranged vertically, and multiple steel buttress anchor piles support from the front to the back Below girder (1);The steel cofferdam (11) of the front support of the girder (1) pier in for the water of constructing, the master The rear end of beam (1) is supported in bank side supporting table (10), and bank side supporting table (10) is the support platform being erected on riverbank; The length of the girder (1) is not less than the clear distance between bank side supporting table (10) and steel cofferdam (11), puts on the floorings (3) It is equipped with the concrete pumping pipe (12) for pier in the water of constructing;The horizontal operation platform (13) is erected on steel cofferdam (11) On, the horizontal operation platform (13) is connected as one with girder (1);
The steel buttress anchor pile (5) includes groined type steel buttress and the steel branch that is anchored to the groined type steel branch pedestal Pier anchor structure (5-1) is drilled with the stake holes for the steel buttress anchor pile lower anchor on the naked rock river bed (4), described Stake holes is arranged vertically and its depth is not less than 5m, and the groined type steel buttress lower part is located at the middle inside of the stake holes; The steel buttress anchor structure (5-1) is the concrete structure of the concrete form by injecting in the stake holes, the steel The height of buttress anchor structure (5-1) is consistent with the depth of the stake holes;The groined type steel buttress includes four root knot structures and ruler Very little vertical steel pipe (5-2) all the same is tight by horizontal brace rod (5-3) between adjacent two vertical steel pipes (5-2) It is solidly connected, the horizontal brace rod (5-3) is located above steel buttress anchor structure (5-1);Every vertical steel pipe (5-2) Bottom end is supported in the stake holes bottom, and the lower part of the every vertical steel pipe (5-2) is poured into steel buttress anchor structure (5- 1) in;
The apical side height of bank side supporting table (10) is identical as the overhead height of steel cofferdam (11), the horizontal operation platform (13) the top surface flush of top surface and floorings (3);
The transverse distribution beam (5-4) that multiple tracks is laid in same level, the transverse direction are provided on the groined type steel buttress Distribution beam (5-4) and girder (1) perpendicular laying, the girder (1) is supported on transverse distribution beam (5-4) described in multiple tracks, more Transverse distribution beam (5-4) described in road is from the front to the back laid in horizontal layout and along the length direction of girder (1).
2. the deep water high-block bridge degree bridge construction described in accordance with the claim 1 naked rock river bed trestle of hard stone, it is characterised in that: The concrete pumping pipe (12) is laid from the front to the back along the length of girder (1).
3. the deep water high-block bridge degree bridge construction according to claim 1 or 2 naked rock river bed trestle of hard stone, feature exist In: the aperture of the stake holes is φ 2m~φ 3m.
4. the deep water high-block bridge degree bridge construction according to claim 1 or 2 naked rock river bed trestle of hard stone, feature exist In: the outer diameter of the vertical steel pipe (5-2) is φ 0.6m~φ 0.65m, net between adjacent two vertical steel pipes (5-2) Away from for 0.4m~0.7m.
5. the deep water high-block bridge degree bridge construction described in accordance with the claim 1 naked rock river bed trestle of hard stone, it is characterised in that: The quantity of laid transverse distribution beam (5-4) is twice, transverse distribution beam (5-4) described in twice point on the groined type steel buttress It Wei not front side distribution beam and the rear side distribution beam positioned at front side distribution beam rear;
Four vertical steel pipes (5-2) include front side steel pipe and two piece of two symmetric supports below the front side distribution beam Rear side steel pipe of the symmetric support below the rear side distribution beam, two front side steel pipes and two rear side steel pipes are in pair Claim to lay, two front side steel pipes are symmetrically laid in below the left and right sides of girder (1), two symmetrical cloth of rear side steel pipe Below the left and right sides of girder (1);The front side distribution beam is weldingly fixed on two front side steel pipes, the rear side Distribution beam is weldingly fixed on two rear side steel pipes;
Pass through horizontal brace rod (5-3) described in the multiple tracks from top to bottom laid between adjacent two vertical steel pipes (5-2) It is fastenedly connected, the horizontal brace rod (5-3) is fashioned iron rod piece and connects between vertical steel pipe (5-2) with welding manner is fixed It connects;
It is respectively provided on transverse distribution beam (5-4) described in per pass there are two the postive stop baffle (6) limited to girder (1), it is described Postive stop baffle (6) is arranged vertically, and two postive stop baffles (6) are symmetrically laid at left and right sides of girder (1);The limit The overhead height of baffle (6) is lower than the apical side height of girder (1).
6. the deep water high-block bridge degree bridge construction according to claim 1 or 2 naked rock river bed trestle of hard stone, feature exist In: it further include that twice are laid in same level and to the longitudinal spacing part (9) limited at the top of girder (1), it is described vertical To locating part (9) in horizontal layout and its lay in parallel with girder (1), girder (1) top card is loaded on vertical described in twice To between locating part (9);
The upper distribution beam (8) being laid in same level, the upper distribution beam are provided on the girder (1) from the front to the back (8) in horizontal layout and itself and girder (1) perpendicular laying;The floorings (3) are paved on distribution beam (8) upper described in multiple tracks On;
Longitudinal spacing part (9) described in twice is respectively positioned below distribution beam (8), and longitudinal spacing part (9) described in per pass is and multiple tracks The upper distribution beam (8), which is fastenedly connected, to be integrated;
The girder (1) includes the Bailey beam that multiple tracks is laid from left to right, and Bailey beam described in multiple tracks is arranged vertically and it Laid in parallel;It is fastenedly connected and is integrated by longitudinal connection structure between Bailey beam described in adjacent twice, the longitudinal direction connects Binding structure is the truss frame for connecting being spliced by multiple tracks connecting rod;
The floorings (3) are horizontal steel plate, are provided with protective fence (7) above the left and right sides of the floorings (3).
7. a kind of method constructed to trestle as described in claim 1, which is characterized in that method includes the following steps:
Step 1: steel buttress anchors pile driving construction: it constructs respectively to each steel buttress anchor pile (5) of institute's construction bridge, until Complete the work progress of all steel buttress anchor piles (5);The construction method of all steel buttress anchor piles (5) is all the same;
When constructing any one described steel buttress anchor pile, process is as follows:
Step 101, drilling: current institute's construction steel buttress anchor pile is from top to bottom drilled through on naked rock river bed (4) using drilling machine The stake holes;
Step 102, the lifting of groined type steel buttress: the molding groined type steel buttress will be pre-machined and lift and transfer to step In stake holes described in 101, the groined type steel buttress lower part is set to be located at the middle inside of the stake holes, and make the groined type steel The bottom end of the every vertical steel pipe (5-2) is supported in the stake holes bottom in buttress;
Step 103, anchoring: the concrete perfusion into stake holes described in step 101 is applied after the solidification of institute's concrete perfusion The molding steel buttress anchor structure (5-1) of work;
Step 2: main beam supporting: being ready to use in after the completion of steel cofferdam (11) construction of pier in the water of constructing, by institute's construction bridge Girder (1) is set up on the steel buttress anchor pile (5) for completion of constructing in step 1, and the front support of girder (1) is enclosed in steel It is supported in bank side supporting table (10) on weir (11) and by the rear end of girder (1);
Step 3: floorings are mated formation: mating formation on the girder described in step 2 (1) floorings (3);
In step 2 middle girder erection process, horizontal operation platform (12) is synchronized and is set up, and by girder (1) and horizontal work Make platform (12) and be fastenedly connected to be integrated.
8. according to the method for claim 7, it is characterised in that: when being drilled in step 101, using floating on the water surface Drilling platform drills;The construction channel for the steel buttress anchor pile of constructing, the brill are provided on the drilling platform Machine be all-hydraulic percussion reverse circulation drill and its be installed on the drilling platform;
When carrying out the lifting of groined type steel buttress in step 102, the groined type steel buttress is lifted using crane barge and is transferred to institute It states in stake holes;
In step 103 into the stake holes when concrete perfusion, it is irrigated using the crane barge.
CN201711160995.8A 2017-11-20 2017-11-20 Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method Active CN107700366B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711160995.8A CN107700366B (en) 2017-11-20 2017-11-20 Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711160995.8A CN107700366B (en) 2017-11-20 2017-11-20 Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method

Publications (2)

Publication Number Publication Date
CN107700366A CN107700366A (en) 2018-02-16
CN107700366B true CN107700366B (en) 2019-08-27

Family

ID=61180616

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711160995.8A Active CN107700366B (en) 2017-11-20 2017-11-20 Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method

Country Status (1)

Country Link
CN (1) CN107700366B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056534B (en) * 2018-07-19 2021-07-20 中铁大桥局第九工程有限公司 Movable cast-in-situ bored pile construction platform and method
CN109322241A (en) * 2018-11-08 2019-02-12 中建五局土木工程有限公司 Trestle work structure and construction method
CN110552294A (en) * 2019-09-29 2019-12-10 中国建筑第八工程局有限公司 Bridge girder erection machine reverse beam erection construction platform and construction method thereof
CN112857305A (en) * 2019-11-28 2021-05-28 湖南五新模板有限公司 Landing stage of detectable deformation state
CN112681135B (en) * 2020-12-14 2022-10-11 中铁二十局集团第三工程有限公司 Construction method of n-shaped sea-crossing temporary steel trestle
CN112779850B (en) * 2020-12-31 2022-06-28 浙大城市学院 Granular material cargo transporting trestle platform for river-crossing tunnel navigation sealing cofferdam construction and construction method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100415995C (en) * 2005-07-21 2008-09-03 郑州市华中建筑机械有限公司 Half span type down guide frame bridging machine and its beam building method
CN102953341B (en) * 2012-12-13 2015-10-21 中铁上海工程局集团有限公司 A kind of high-order trestle work structure be arranged in deep water torrent intectate steep bare rock
CN102979039B (en) * 2012-12-13 2014-12-03 中铁上海工程局集团第二工程有限公司 Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN207452738U (en) * 2017-11-20 2018-06-05 中铁二十局集团第一工程有限公司 The deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone

Also Published As

Publication number Publication date
CN107700366A (en) 2018-02-16

Similar Documents

Publication Publication Date Title
CN107700366B (en) Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method
CN105386408B (en) Deep-water bridge pile foundation construction method
CN102953341B (en) A kind of high-order trestle work structure be arranged in deep water torrent intectate steep bare rock
CN101666081B (en) Abrupt slope bare rock drilling platform and technology in huge reservoir
CN102352632B (en) Anchor rod sheet pile combined structure and method for reinforcing high filling body on one side of slope
CN103741657B (en) The construction method of large-sized multifunction waterborne traffic accident
CN102720140B (en) Large-span prestress concrete continuous beam deepwater pier construction process
CN108005094B (en) Pier and pier top beam section construction method in naked rock river bed water
CN102979039B (en) Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN106049281A (en) Deep-water construction method of bridge at water pebble soil and argillaceous sandstone areas and auxiliary working platform
CN101538833B (en) Vertical subsection double-wall steel cofferdam water stopping construction method
CN108103939A (en) Oblique section steel trestle construction composite reinforcement mode and construction technology
CN105350526B (en) Method for setting up steel platform
CN207452738U (en) The deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone
CN102268871A (en) Construction method of turnover platform for underwater pile foundation of bridge
CN203049443U (en) High level trestle structure arranged on steep bare rock of deepwater torrent unsheathed layer
CN108708284B (en) A kind of steel trestle construction method for resisting flood discharge bed scour
CN211312224U (en) Steel casing positioning tool for bridge drilled pile based on existing pavement transformation
CN203654196U (en) Guide apparatus for large and multifunctional over-water construction platform
CN110042843A (en) A kind of large deep foundation pit construction method of complex condition
CN201502056U (en) Bare rock drilling platform for steep slope of deep reservoir area
CN100473787C (en) Connecting structure for use in piled anchor supporting system and construction method thereof
CN110029653B (en) Method for treating steel pipe pile foundation of riprap seabed foundation
CN208280155U (en) A kind of steel trestle infrastructure structure for resisting the impact of flood discharge torrent speed
CN208201658U (en) A kind of steel trestle rapid construction device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant