CN107700366A - Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method - Google Patents

Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method Download PDF

Info

Publication number
CN107700366A
CN107700366A CN201711160995.8A CN201711160995A CN107700366A CN 107700366 A CN107700366 A CN 107700366A CN 201711160995 A CN201711160995 A CN 201711160995A CN 107700366 A CN107700366 A CN 107700366A
Authority
CN
China
Prior art keywords
steel
girder
trestle
construction
buttress
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711160995.8A
Other languages
Chinese (zh)
Other versions
CN107700366B (en
Inventor
梁之海
杜越
刘俊斌
赵久远
朱山山
严朝锋
王永丽
李东牛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Urban Construction Transportation Development Co ltd
Original Assignee
First Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd filed Critical First Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd
Priority to CN201711160995.8A priority Critical patent/CN107700366B/en
Publication of CN107700366A publication Critical patent/CN107700366A/en
Application granted granted Critical
Publication of CN107700366B publication Critical patent/CN107700366B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/12Portable or sectional bridges
    • E01D15/133Portable or sectional bridges built-up from readily separable standardised sections or elements, e.g. Bailey bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/005Piers, trestles, bearings, expansion joints or parapets specially adapted for portable or sectional bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a kind of deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone and construction method, the trestle includes trestle body and the horizontal operation platform on front side of trestle body;Trestle body includes bottom bracing structure, girder and floorings, bottom bracing structure includes one or more lower anchors in the steel buttress anchor pile on naked rock river bed, girder front support is supported in the supporting table of bank side on steel cofferdam and its rear end, and concrete pumping pipe is placed with floorings;For horizontal operation putting up platform on steel cofferdam and it is connected as one with girder, steel buttress anchor pile includes groined type steel buttress and steel buttress anchor structure;The method comprising the steps of:First, steel buttress anchoring pile driving construction;2nd, main beam supporting;3rd, floorings are mated formation.Reasonable in design, easy construction of the invention and using effect is good, is supported on naked rock river bed using steel buttress anchor pile is firm, girder rear and front end be respectively supported at steel cofferdam with the supporting table of bank side, saving of work and time.

Description

Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method
Technical field
The invention belongs to bridge construction technical field, more particularly, to the deep water high-block bridge degree bridge construction naked rock river of hard stone Bed trestle and construction method.
Background technology
With the development of national economy, China railways bridge cause fast development, China is in Bridge Design theory, construction skill Caught up with terms of art and equipment or close to advanced international standard, large span is over strait, crossing-fiver bridge construction is continuously increased.To depth Water, Gao Dun, Longspan Bridge water in pier carry out in work progress, when riverbed is the naked rock river bed of hard stone, the construction of pier in water Difficulty is bigger, it usually needs sets up trestle.Wherein, " deep water " refers to that the depth of water of bridge foundation is in 5m~more than 6m, " high pier " It is highly more than 30 meters to refer to bridge pier, and " large span " refers to porous across footpath overall length >=100 meter and single hole across footpath >=40 meter.Hard stone is (i.e. Solid rock) refer to fresh complete, particle electrical connection and the rock for having higher mechanical strength, refer generally in saturated-water phase Under compressive ultimate strength be more than 50 kg/cms rock, such as sedimentary rock, igneous rock, metamorphic rock, solid rock tool There are very high mechanical strength and very strong water-resistance.Naked rock river bed refers to the exposed bedrock that riverbed is intectate.
When reality is set up to trestle, because bridge location riverbed is naked rock river bed, rock is hard, and the anchoring of trestle buttress is stack The key of bridge construction technology, and the critical process of trestle construction safety quality control.In deep-water bare solid rock riverbed and Under streamflow regime, pile foundation construction can not be installed with steel pile casting and carry out mud circulation, set up drilling platform difficulty, therefore use tradition Method plugs steel sheet pile construction or is drilled to hole construction method difficulty using normal impact, and the anchoring of trestle buttress is a great problem;If Then needing that chamber type template is installed using pouring underwater concrete parcel steel buttress method, concreting side's amount is bigger, and The bad control of construction quality, steel buttress anchoring effect is poor, and steel buttress stability is difficult in the case of the storehouse flood discharge of flood season Minjiang upper To ensure, and also need to remove concrete using Blasting Excavation method by navigation channel and hydraulic department relevant regulations after the completion of trestle use To original bed face.
The content of the invention
In view of the above-mentioned deficiencies in the prior art, the technical problem to be solved by the present invention is that provide a kind of deep water high pier The span bridge construction naked rock river bed trestle of hard stone, its reasonable in design, easy construction, remove convenient and using effect It is good, it is supported in using steel buttress anchor pile is firm on naked rock river bed, it is collateral with bank that girder rear and front end is respectively supported at steel cofferdam Support on platform, saving of work and time.
In order to solve the above technical problems, the technical solution adopted by the present invention is:A kind of deep water high-block bridge degree bridge construction With the naked rock river bed trestle of hard stone, it is characterised in that:Including the trestle body for pier in water of constructing and positioned at the trestle body The horizontal operation platform of front side, pier is reinforced concrete knoll in the water;The trestle body includes bottom bracing structure, level The girder being set up on the bottom bracing structure and the floorings being layed on girder, the bottom bracing structure include one Or multiple lower anchors, in the steel buttress anchor pile on naked rock river bed, the steel buttress anchor pile is in vertically to laying, Duo Gesuo Steel buttress anchor pile is stated to be supported in from the front to the back below girder;The front support of girder pier in for the water of constructing On steel cofferdam, the rear end of the girder is supported in the supporting table of bank side, and bank side supporting table is the support being erected on riverbank Platform;The length of the girder is not less than the clear distance between bank side supporting table and steel cofferdam, is placed with and is used on the floorings Construct the concrete pumping pipe of pier in the water;The horizontal operation putting up platform is on steel cofferdam, the horizontal operation platform Connected as one with girder;
The steel buttress anchor pile includes groined type steel buttress and the steel anchored to the groined type steel branch pedestal Buttress anchor structure, the stake holes for the steel buttress anchor pile lower anchor is drilled with the naked rock river bed, and the stake holes is in It is not less than 5m to laying and its depth vertically, the groined type steel buttress bottom is located at the middle inside of the stake holes;The steel Buttress anchor structure is by the concrete structure of the concrete form in the injection stake holes, the steel buttress anchor structure Height it is consistent with the depth of the stake holes;The groined type steel buttress includes four root architectures and the vertical steel of size all same Manage, be fastenedly connected between adjacent two vertical steel pipes by horizontal brace rod, the horizontal brace rod is located at steel buttress Above anchor structure;The bottom of the every vertical steel pipe is supported in the stake holes bottom, under the every vertical steel pipe Portion is poured into steel buttress anchor structure.
The above-mentioned deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that:The concrete Length of the pumping line along girder is laid from the front to the back.
The above-mentioned deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that:The bank is collateral The apical side height of support platform is identical with the overhead height of steel cofferdam, and the top surface of the horizontal operation platform is equal with the top surface of floorings Together.
The above-mentioned deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that:The stake holes Aperture is φ 2m~φ 3m.
The above-mentioned deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that:The vertical steel The external diameter of pipe is φ 0.6m~φ 0.65m, and the clear distance between adjacent two vertical steel pipes is 0.4m~0.7m.
The above-mentioned deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that:The groined type The transverse distribution beam that multiple tracks is laid in same level, the transverse distribution beam and the perpendicular cloth of girder are provided with steel buttress If the girder is supported in described in multiple tracks on transverse distribution beam, transverse distribution beam described in multiple tracks is in horizontal layout and along girder Length direction lay from the front to the back.
The above-mentioned deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that:The groined type The quantity that transverse distribution beam is laid on steel buttress is twice, and transverse distribution beam described in twice is respectively front side distribution beam and is located at The rear side distribution beam at the front side distribution beam rear;
Four vertical steel pipes include the front side steel pipe and two two symmetric supports below the front side distribution beam Rear side steel pipe of the symmetric support below the rear side distribution beam, two front side steel pipes and two rear side steel pipes are in pair Claim to lay, two front side steel pipes are symmetrically laid in below the left and right sides of girder, and two rear side steel pipes are symmetrically laid Below the left and right sides of girder;The front side distribution beam is weldingly fixed on two front side steel pipes, the rear side distribution Beam is weldingly fixed on two rear side steel pipes;
Connected between adjacent two vertical steel pipes by horizontal brace rod fastening described in the multiple tracks from top to bottom laid Connect, the horizontal brace rod is shaped steel rod member and is fixedly connected between vertical steel pipe with welding manner;
Two are provided with described in per pass on transverse distribution beam spacing postive stop baffle, the postive stop baffle are carried out to girder In vertically to laying, two postive stop baffles are symmetrically laid at left and right sides of girder;The overhead height of the postive stop baffle is low In the apical side height of girder.
The above-mentioned deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that:Also include twice Be laid in same level and to carrying out spacing longitudinal spacing part at the top of girder, the longitudinal spacing part in horizontal layout and It is in parallel laying with girder, and the girder top card is loaded between longitudinal spacing part described in twice;
The upper distribution beam being laid in same level is provided with the girder from the front to the back, the upper distribution beam is in water Plain cloth is set and itself and the perpendicular laying of girder;The floorings are paved on described in multiple tracks in upper distribution beam;
Longitudinal spacing part described in twice is respectively positioned on below distribution beam, longitudinal spacing part described in per pass with described in multiple tracks on Distribution beam, which is fastenedly connected, to be integrated;
The girder includes the Bailey beam laid from left to right of multiple tracks, Bailey beam described in multiple tracks in vertically to lay and its It is in parallel laying;It is fastenedly connected and is integrated by longitudinal connection structure between Bailey beam described in adjacent twice, the longitudinal direction connects Binding structure is the truss frame for connecting being spliced by multiple tracks connecting rod;
The floorings are horizontal steel plate, and guard rail is provided with above the left and right sides of the floorings.
Meanwhile the invention also discloses a kind of method and step is simple, reasonable in design and easy construction, construction quality are easy to protect The deep water high-block bridge degree bridge construction of the card naked rock river bed trestle construction method of hard stone, it is characterised in that this method include with Lower step:
Step 1: steel buttress anchors pile driving construction:Each steel buttress anchor pile of institute's construction bridge is constructed respectively, until Complete the work progress of all steel buttress anchor piles;The construction method all same of all steel buttress anchor piles;
To when steel buttress anchor pile is constructed any one described, process is as follows:
Step 101, drilling:Current institute's construction steel buttress anchor pile is from top to bottom drilled through on naked rock river bed using rig The stake holes;
Step 102, the lifting of groined type steel buttress:By the groined type steel buttress that shaping is pre-machined lift and transfer to Described in step 101 in stake holes, the groined type steel buttress bottom is set to be located at the middle inside of the stake holes, and make the well word The bottom of the every vertical steel pipe is supported in the stake holes bottom in shape steel buttress;
Step 103, anchoring:To concrete perfusion in stake holes described in step 101, after institute's concrete perfusion solidification, obtain Obtain the steel buttress anchor structure of construction molding;
Step 2: main beam supporting:It is ready to use in after the completion of the steel cofferdam construction of pier in the water of constructing, by institute's construction bridge Main beam supporting constructed in step 1 completion steel buttress anchor pile on, and by the front support of girder on steel cofferdam and will be main The rear end of beam is supported in the supporting table of bank side;
Step 3: floorings are mated formation:Mat formation described in step 2 on girder floorings;
In step 2 middle girder erection process, horizontal operation platform is synchronized and set up, and by girder and horizontal operation Platform, which is fastenedly connected, to be integrated.
The above method, it is characterized in that:When being drilled in step 101, bored using the drilling platform for floating on the water surface Hole;The construction passage for the steel buttress anchor pile of constructing is provided with the drilling platform, the rig is all-hydraulic impact Clean-out machine and its be installed on the drilling platform;
When the lifting of groined type steel buttress is carried out in step 102, the groined type steel buttress is lifted and transferred using crane barge In to the stake holes;
In step 103 into the stake holes during concrete perfusion, it is irrigated using the crane barge.
The present invention has advantages below compared with prior art:
1st, steel buttress anchor pile is reasonable in design, using single pile single-column form, using the single pile groined type steel of major diameter Buttress, its combining structure rigidity is big, and resistance flood impact capacity is strong, easy for construction, and groined type steel buttress bottom anchor jail Lean on, easy construction.The construction quality of steel buttress anchor pile is easily controlled, and steel buttress anchoring effect is good, trestle resistance flood impact Ability is strong, securely and reliably.
2nd, using floating platform as drilling platform, convenient disassembly, without setting up drilling platform in addition, it is easy for construction flexibly, Platform can be facilitated to move, it is securely and reliably, cost-effective.Drilling platform is simple in construction, and raft includes 2 parallel and independent cloth If platform body, while rig installation is met, significantly saved the dosage of steel, and it is difficult to greatly reduce construction Degree;Drilled tunnel is arranged between 2 platform bodies, during drilling construction, will not be produced eccentric force, is advantageous to the steady of raft Determining raft includes 2 platform bodies that are parallel and independently laying, and the clear distance between 2 platform bodies is not less than 2.5m, While meeting rig installation, the dosage of steel is significantly saved, and difficulty of construction greatly reduces.Also, 2 flat Connected between playscript with stage directions body by crossbeam, the intensity and toughness of crossbeam is larger, adds the impact resistance of platform body, ensures platform The stability and globality of body.Meanwhile the drilled tunnel for rig construction is provided between drilling frame and crossbeam, Without opening up drilled tunnel on raft again, while the drilled tunnel is arranged between 2 platform bodies, drilling construction When, eccentric force will not be produced, is advantageous to the stabilization of raft;And the setting of bearing beam is the weight for undertaking rig, Dynamic load caused by the gravity of rig and operation is entered into row buffering, if directly rig is arranged on buoyancy tank, Buoyancy tank can be deformed, influence the bearing capacity of buoyancy tank.Thus, stake position bore position can effectively be ensured using the drilling platform.
3rd, riverbed is the exposed riverbed of solid rock, and stake holes aperture will not cave in, it is not necessary to install steel pile casting.
4th, construction method is simple, easy construction and using effect are good, using all-hydraulic percussion reverse circulation drill drilling construction, Using gas lift method borehole cleaning, solid rock will not collapse hole, it is not necessary to the measure such as steel pile casting, mud off and mud circulation cleaning quarrel, clearly Hole effect is good, and easy for construction, speed is soon, environmental protection is good and saves cost.Trestle is easily removed after completion, after the completion of engineering construction, Steel buttress need to only be cut off from riverbed face position and removed when trestle is removed, meet that navigation channel and flood control require, it is convenient to remove.
5th, practical value is high and popularizing application prospect is extensive, and versatility is good, can be commonly used to naked rock river bed trestle steel buttress In anchoring, construction safety is reliable, and easy for construction, speed is fast, saves construction cost.Used steel buttress anchor pile rigidity is big, Flood fighting water slug ability is strong, easy for construction, saves construction cost, is particularly useful for the only cylindricality formula steel buttress construction of simple trestle.
In summary, reasonable in design, easy construction of the invention, dismounting are conveniently and using effect is good, using steel buttress Anchor pile is firm to be supported on naked rock river bed, and girder rear and front end is respectively supported at steel cofferdam and in the supporting table of bank side, saving of labor saves When.
Below by drawings and examples, technical scheme is described in further detail.
Brief description of the drawings
Fig. 1 is the vertical bridge of the hard naked rock river bed trestle of stone of the present invention to structural representation.
Fig. 2 is the direction across bridge structural representation of the hard naked rock river bed trestle of stone of the present invention.
Fig. 3 is the method flow block diagram when present invention constructs to the naked rock river bed trestle of hard stone.
Fig. 4 uses the structural representation of drilling platform for the present invention.
Description of reference numerals:
1-girder;3-floorings;
4-naked rock river bed;5-steel buttress anchor pile;5-1-steel buttress anchor structure;
5-2-vertical steel pipe;5-3-horizontal brace rod;5-4-transverse distribution beam;
6-postive stop baffle;7-guard rail;8-go up distribution beam;
9-longitudinal spacing part;10-bank side supporting table;11-steel cofferdam;
12-concrete pumping pipe;13-horizontal operation platform;13-1-platform body;
13-2-crossbeam;13-3-bearing beam;13-4-anchor ingot.
Embodiment
A kind of naked rock river bed trestle of hard stone of deep water high-block bridge degree bridge construction as shown in Figure 1 and Figure 2, including for Construct the trestle body of pier and the horizontal operation platform 13 on front side of the trestle body in water, pier mixes for reinforcing bar in the water Solidifying knoll;The trestle body includes the girder 1 and laying of bottom bracing structure, level frame on the bottom bracing structure In the floorings 3 on girder 1, the bottom bracing structure includes one or more lower anchors in the steel branch on naked rock river bed 4 Pier anchor pile 5, the steel buttress anchor pile are in be supported in girder from the front to the back to laying, multiple steel buttress anchor piles vertically 1 lower section;The steel cofferdam 11 of the front support of the girder 1 pier in for the water of constructing, the rear end support of the girder 1 In in bank side supporting table 10, bank side supporting table 10 is the support platform being erected on riverbank;The length of the girder 1 is not small Clear distance between bank side supporting table 10 and steel cofferdam 11, be placed with the floorings 3 in the water of constructing pier it is mixed Coagulate native pumping line 12;The horizontal operation platform 13 is erected on steel cofferdam 11, and the horizontal operation platform 13 is connected with girder 1 It is integrated;
The steel buttress anchor pile 5 includes groined type steel buttress and the steel anchored to the groined type steel branch pedestal Buttress anchor structure 5-1, the stake holes for the steel buttress anchor pile lower anchor, the stake are drilled with the naked rock river bed 4 In 5m is not less than to laying and its depth vertically, the groined type steel buttress bottom is located at the middle inside of the stake holes in hole;Institute It is by the concrete structure of the concrete form in the injection stake holes, the steel buttress to state steel buttress anchor structure 5-1 Anchor structure 5-1 height is consistent with the depth of the stake holes;The groined type steel buttress includes four root architectures and size is homogeneous It is fastenedly connected between same vertical steel pipe 5-2, adjacent two vertical steel pipe 5-2 by horizontal brace rod 5-3, the water Flushconnection bar 5-3 is located above steel buttress anchor structure 5-1;Every vertical steel pipe 5-2 bottom is supported in the stake Bottom hole portion, every vertical steel pipe 5-2 bottom are poured into steel buttress anchor structure 5-1.
In the present embodiment, length of the concrete pumping pipe 12 along girder 1 is laid from the front to the back.
Also, the concrete pumping pipe 12 is in horizontal layout.Thus, can length that is easy, effectively meeting pier in the water Apart from concrete conveyance demand.
In the present embodiment, the apical side height of bank side supporting table 10 is identical with the overhead height of steel cofferdam 11, the water The top surface of flat workbench 13 and the top surface flush of floorings 3.
Thus, the top surface of horizontal operation platform 13 and the top surface of floorings 3, thus can largely simplify pier in water Work progress.Also, while 13 overall stability of workbench is improved the standard, the position of steel cofferdam 11 can be carried out effective It is spacing.
Wherein, the horizontal operation platform 13 is the workbench for pier in the water of constructing;The front end of girder 1 with Horizontal operation platform 13 connects as one.
During practice of construction, the aperture of the stake holes is φ 2m~φ 3m.The external diameter of the vertical steel pipe 5-2 be φ 0.6m~ Clear distance between φ 0.65m, adjacent two vertical steel pipe 5-2 is 0.4m~0.7m.Thus, can be right according to specific needs Clear distance difference between the aperture of the stake holes, the external diameter of the vertical steel pipe 5-2 and adjacent two vertical steel pipe 5-2 Adjust accordingly.
In the present embodiment, the transverse distribution beam that multiple tracks is laid in same level is provided with the groined type steel buttress 5-4, the transverse distribution beam 5-4 and 1 perpendicular laying of girder, the girder 1 are supported in transverse distribution beam 5-4 described in multiple tracks On, transverse distribution beam 5-4 described in multiple tracks is from the front to the back laid in horizontal layout and along the length direction of girder 1.
The quantity that transverse distribution beam 5-4 is laid on the groined type steel buttress is twice, transverse distribution beam described in twice 5-4 is respectively front side distribution beam and the rear side distribution beam positioned at the front side distribution beam rear.
Four vertical steel pipe 5-2 include the front side steel pipe and two two symmetric supports below the front side distribution beam Rear side steel pipe of the root symmetric support below the rear side distribution beam, two front side steel pipes are in two rear side steel pipes Symmetrical to lay, two front side steel pipes are symmetrically laid in below the left and right sides of girder 1, two symmetrical cloth of rear side steel pipe Below the left and right sides of girder 1;The front side distribution beam is weldingly fixed on two front side steel pipes, the rear side point It is weldingly fixed on beam on two rear side steel pipes.
Pass through horizontal brace rod 5-3 described in the multiple tracks from top to bottom laid between adjacent two vertical steel pipe 5-2 It is fastenedly connected, the horizontal brace rod 5-3 is shaped steel rod member and is fixedly connected between vertical steel pipe 5-2 with welding manner.
Two are provided with transverse distribution beam 5-4 described in per pass spacing postive stop baffle 6, the limit are carried out to girder 1 Position baffle plate 6 is in vertically to laying, and two postive stop baffles 6 are symmetrically laid in the left and right sides of girder 1;The postive stop baffle 6 Overhead height is less than the apical side height of girder 1.
Meanwhile the deep water high-block bridge degree bridge construction of the present invention naked rock river bed trestle of hard stone, in addition to twice It is laid in same level and spacing longitudinal spacing part 9 is carried out to the top of girder 1, the longitudinal spacing part 9 is in horizontal cloth And if it is in parallel laying with girder 1, the top card of girder 1 is loaded between longitudinal spacing part 9 described in twice.
In the present embodiment, the upper distribution beam 8 being laid in same level, institute are provided with the girder 1 from the front to the back It is in horizontal layout and itself and 1 perpendicular laying of girder to state distribution beam 8;The floorings 3 are paved on upper distribution beam 8 described in multiple tracks On.
Longitudinal spacing part 9 described in twice is respectively positioned on the lower section of distribution beam 8, longitudinal spacing part 9 described in per pass with multiple tracks institute State distribution beam 8 and be fastenedly connected and be integrated.
In the present embodiment, the girder 1 includes the Bailey beam that multiple tracks is laid from left to right, and Bailey beam described in multiple tracks is in perpendicular Directly to lay and its be in parallel laying;It is fastenedly connected between Bailey beam described in adjacent twice by longitudinal connection structure as one Body, the longitudinal connection structure are the truss frame for connecting being spliced by multiple tracks connecting rod.
In the present embodiment, the floorings 3 are horizontal steel plate, are provided with above the left and right sides of the floorings 3 anti- Guardrail 7.
In the present embodiment, pier is located on naked rock river bed in the water and it is located at Minjiang Shuikou Reservoir Tail, Fujian at bridge location River face is open, and bridge zone section is IV grade of navigation channel, and in the case of the not flood discharge of downstream, flow velocity is 0.5m/s or so at bridge location, flood discharge When design current velocity 3.3m/s, design and construction water level+62.5m, meet design water level 67m within 2 years one;Riverbed is intectate, exposed base Rock, riverbed are severely-weathered, weak weathered granite.
Consider navigation condition, the hydrology, geology and the construction cost in the Min River, the hard naked rock river bed trestle of stone of the present invention is adopted With simple trestle scheme, set up from riverbank to water Zhong Dun directions, and the naked rock river bed trestle of hard stone is in water the steel cofferdam of pier Upstream side, the installation and personnel for meeting concrete pump pipe 12 are passed through, and construction material and equipment use water transportation Ship Transportation.
In the present embodiment, the quantity of the steel buttress anchor pile 5 is two.
, can according to specific needs during practice of construction, the cloth of quantity and each steel buttress anchor pile 5 to steel buttress anchor pile 5 If position adjusts accordingly respectively.
In the present embodiment, the aperture of the stake holes is φ 2.5m and its depth is 6m.It is vertical in the groined type steel buttress Steel pipe 5-2 is external diameter φ 0.63m steel pipe, and horizontal brace rod 5-3 is I-steel, and four vertical steel pipe 5-2 are connected using I-steel Connect to form entirety, groined type steel buttress is anchored using steel buttress anchor structure 5-1 (drill-pouring structure), effective anchorage depth is 6m, strength grade of concrete used in steel buttress anchor structure 5-1 are C30.
The transverse distribution beam 5-4 is spliced by twice I-steel, transverse distribution beam 5-4 and the groined type steel buttress Between weld triangle bearing diagonal, on transverse distribution beam 5-4 install Bailey beam use deck type as trestle main bearing beam, trestle Structure, Bailey beam use three row's single layer structures, and I-steel is laid as bridge floor transverse distribution according to spacing 50cm on Bailey beam top Beam (i.e. upper distribution beam 8), in bridge floor transverse distribution beam laying depth 6mm steel plates as floorings 3, the width 2.5m of floorings 3, Bridge floor guardrail (i.e. guard rail 7) is highly 1.2m, and railing is using 75 × 75 × 8mm of ∠ angle steel as railing montant.Trestle region For prohibited area, navigation mark setting is carried out.
In addition, also needing to set measure of water diversion, " V " font point water plate specifically is set along water surface side in groined type steel buttress, Avoid floating object from accumulating, increase steel buttress impact resistance.
As shown in figure 3, when being constructed to the naked rock river bed trestle of hard stone, comprise the following steps:
Step 1: steel buttress anchors pile driving construction:Each steel buttress anchor pile 5 of institute's construction bridge is constructed respectively, directly To the work progress for completing all steel buttress anchor piles 5;The construction method all same of all steel buttress anchor piles 5;
To when steel buttress anchor pile 5 is constructed any one described, process is as follows:
Step 101, drilling:Current institute's construction steel buttress anchor pile is from top to bottom drilled through on naked rock river bed 4 using rig The stake holes;
Step 102, the lifting of groined type steel buttress:By the groined type steel buttress that shaping is pre-machined lift and transfer to Described in step 101 in stake holes, the groined type steel buttress bottom is set to be located at the middle inside of the stake holes, and make the well word Every vertical steel pipe 5-2 bottom is supported in the stake holes bottom in shape steel buttress;
Step 103, anchoring:To concrete perfusion in stake holes described in step 101, after institute's concrete perfusion solidification, obtain Obtain the steel buttress anchor structure 5-1 of construction molding;
Step 2: main beam supporting:It is ready to use in after the completion of the construction of steel cofferdam 11 of pier in the water of constructing, by institute's construction bridge Girder 1 be set up on the steel buttress anchor pile 5 for completion of being constructed in step 1, and by the front support of girder 1 in steel cofferdam 11 Above and by the rear end of girder 1 it is supported in bank side supporting table 10;
Step 3: floorings are mated formation:Mat formation described in step 2 on girder 1 floorings 3.
In step 2 middle girder erection process, horizontal operation platform 12 is synchronized and set up, and by girder 1 and horizontal work Make platform 12 and be fastenedly connected to be integrated.
In the present embodiment, when being drilled in step 101, drilled using the drilling platform for floating on the water surface;It is described The construction passage for the steel buttress anchor pile of constructing is provided with drilling platform, the rig bores for all-hydraulic percussion reverse circulation Machine and its be installed on the drilling platform.
When the lifting of groined type steel buttress is carried out in step 102, the groined type steel buttress is lifted and transferred using crane barge In to the stake holes;
In step 103 into the stake holes during concrete perfusion, it is irrigated using the crane barge.
The all-hydraulic percussion reverse circulation drill is the all-hydraulic percussion reverse circulation drill of YCJF-25 types, clear using gas lift method Be cut simultaneously concrete perfusion, forms concrete clear water structure (i.e. steel buttress anchor structure 5-1).The steel buttress anchor structure 5-1 Valid bonding length be not less than 5m, the heavy quarrel thickness in bottom meets drilled pile construction code requirement;By groined type steel branch before perfusion In pier insertion stake holes, it is ensured that the anchoring of groined type steel buttress is firm;Afterwards, pouring underwater concrete, filling concrete to riverbed face, Strength grade of concrete is C30, then the groined type steel buttress anchoring is completed, and obtains the steel buttress anchor pile 5 of construction molding.By It is the exposed riverbed of solid rock in riverbed, need not install steel pile casting, mud off and mud using the steel buttress anchor pile 5 follows The ring measure such as quarrel clearly, groined type steel buttress need to only be cut off from riverbed face position when trestle is removed, the anchor of steel buttress anchor pile 5 Gu safe and reliable, easy for construction, speed is soon, environmental protection is good and saves cost.
After the completion for the treatment of that all steel buttress anchor piles 5 are constructed, transverse distribution beam 5-4 is installed on each steel buttress anchor pile 5, Bailey beam is installed on transverse distribution beam 5-4 again.When reality is installed to transverse distribution beam 5-4 and the Bailey beam, use Crane barge coordinates installation.Bailey beam transportation by driving after harbour is assembled into pack is installed at bridge location, and Bailey beam support uses 90cm type branch Frame, after the completion of Bailey beam assembly, all lower boom direction across bridge are integral using I-steel connection, and lower boom and I-steel Between using U-bolt connect, increase horizontal stability.Bailey beam top is transversely mounted distribution beam 8, spacing 1.0m, Ran Houpu If 6mm steel plates, finally install guard rail.Due at left and right sides of load-bearing distribution beam and trestle beam-ends head sets spacing measure (i.e. postive stop baffle 6 and longitudinal spacing part 9), the stability of trestle can be effectively increased.
When steel buttress anchoring pile driving construction is carried out in step 1, constructed according to construction process for bored pile, sink quarrel thickness not More than 5cm.Institute's concrete perfusion intensity completes the work progress of steel buttress anchor pile 5 after reaching design strength 70% in step 103.
The drilling platform is assembled and boring procedure in, drilling platform is always because being under flowing water state and pile foundation construction shakes In dynamic state, stake holes position need to be detected at any time, the position of the drilling platform is adjusted using windlass, it is ensured that stake holes position is accurate.
As shown in figure 4, in the present embodiment, the drilling platform includes drilling frame, the floating for the drilling frame installation is put down Platform and the anchoring mechanism for fixing the raft, the raft include the platform body 13-1 of 2 parallel layings, Clear distance between 2 platform body 13-1 is not less than 2.5m, and 2 platform body 13-1 are connected by crossbeam 13-2, The length of the crossbeam 13-2 is more than 2.5m, and the quantity of the crossbeam 13-2 is 2, and 2 crossbeam 13-2 are separately positioned on The front and rear of the platform body 13-1,2 crossbeam 13-2 with the perpendicular layings of platform body 13-1, institute The drilled tunnel being provided between drilling frame and the crossbeam 13-2 for the drilling machine construction is stated, the drilling frame is in including multiple The bearing beam 13-3 equidistantly laid, multiple bearing beam 13-3 are parallel to each other, each bearing beam 13-3 both ends respectively with institute Platform body 13-1 connections are stated, each bearing beam 13-3 length is 12m~16m, the platform body 13-1, crossbeam 13-2 and bearing beam 13-3 are laid on same plane, and each platform body 13-1 is by multiple buoyancy tanks along single laying Assembled, multiple buoyancy tanks are laid in same level, and the width of each buoyancy tank is 5m~8m;The anchorage machine Structure includes multiple anchor ingots 4.
During actual use, the raft includes the platform body 13-1 of 2 parallel layings, 2 platform bodies Clear distance between 13-1 is not less than 2.5m, has significantly saved the dosage of steel, and difficulty of construction greatly reduces.
During actual use, the clear distance between 2 platform body 13-1 is not less than 2.5m, and the width of each buoyancy tank Spend for 5m~8m, disclosure satisfy that the size requirement of rig.
In the present embodiment, the weight of the drilling machine master is 19t, the weight 8t of tup, the size of rig plane for it is long × Width=7.76m × 2.8m, the stroke of the buoyancy tank upper ram are controlled in 0.3~0.4m.
During actual use, the connector such as screw rod, connecting rod is attached between 2 platform body 13-1, is preferably Crossbeam 13-2 connections, because the platform body 13-1 is not when the rig carries out operation, be subject to for dead load, when When the rig carries out bore operation, caused dynamic loading can be impacted, therefore to increase the platform body 13-1 Impact resistance, first have to ensure platform body 13-1 stability and globality, and crossbeam 13-2 intensity and toughness is larger, It is effectively increased the globality of the platform body 13-1.
During actual use, the length of the crossbeam 13-2 is more than 2.5m, and preferable crossbeam 13-2 length is 2 institutes The clear distance sum between platform body 13-1 and 2 platform body 13-1 is stated, adds crossbeam 13-2 and 2 platforms Body 13-1 connection fixing.
During actual use, the setting of the bearing beam 13-3 is the weight for undertaking the rig, by the drilling Dynamic load caused by the gravity of equipment and operation enters row buffering, if the rig directly is arranged on into the buoyancy tank On, it can be deformed the buoyancy tank, influence the bearing capacity of the buoyancy tank.
During actual use, each platform body 13-1 is assembled by multiple buoyancy tanks along single laying, preferably Each platform body 13-1 it is assembled along the buoyancy tank longitudinally laid by 2, and the size of each buoyancy tank is: Length × width × height=9m × 2.7m × 1.65m.
During actual use, the quantity of the anchoring mechanism is 4 groups, and 4 anchor slabs 5 are fixed on the 4 of the raft Individual angle point.
In the present embodiment, the crossbeam 13-2 and platform body 13-1 is welded.
During actual use, the crossbeam 13-2 and platform body 13-1 by bolt or can be welded to connect, preferably To be welded to connect, because caused dynamic loading can make bolt produce loosening in the rig operation process, influence described The reliability connected between crossbeam 13-2 and platform body 13-1, so as to influence the globality of the floating box type drilling platform and stably Property.
In the present embodiment, the crossbeam 13-2 and the bearing beam 13-3 are i shaped steel.
During actual use, in order to meet that floating box type drilling platform described in the requirement of strength and stiffness is I36b I-steel.
In the present embodiment, multiple bearing beam 13-3's is centrally disposed in 2 platform body 13-1 middles, described in reduction Raft produces eccentric force, influences the stability of the raft.
In the present embodiment, the anchor ingot 4 is laid in vertical, and the lower end of the anchor ingot 4 is fixed on basement rock, the anchor ingot 4 Upper end and the platform body 13-1 anchor.
It is described above, only it is presently preferred embodiments of the present invention, not the present invention is imposed any restrictions, it is every according to the present invention Any simple modification, change and the equivalent structure change that technical spirit is made to above example, still fall within skill of the present invention In the protection domain of art scheme.

Claims (10)

  1. A kind of 1. deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone, it is characterised in that:Including for water of constructing The trestle body of middle pier and the horizontal operation platform (13) on front side of the trestle body, pier is armored concrete in the water Pier;The trestle body includes bottom bracing structure, the girder (1) that level frame is located on the bottom bracing structure and is layed in Floorings (3) on girder (1), the bottom bracing structure include one or more lower anchors on naked rock river bed (4) Steel buttress anchor pile (5), the steel buttress anchor pile are in be supported from the front to the back to laying, multiple steel buttress anchor piles vertically Below girder (1);The steel cofferdam (11) of front support pier in for the water of constructing of the girder (1), the master The rear end of beam (1) is supported in bank side supporting table (10), and bank side supporting table (10) is the support platform being erected on riverbank; The length of the girder (1) is not less than the clear distance between bank side supporting table (10) and steel cofferdam (11), is put on the floorings (3) It is equipped with the concrete pumping pipe (12) for pier in the water of constructing;The horizontal operation platform (13) is erected on steel cofferdam (11) On, the horizontal operation platform (13) connects as one with girder (1);
    The steel buttress anchor pile (5) includes groined type steel buttress and the steel branch anchored to the groined type steel branch pedestal Pier anchor structure (5-1), the stake holes for the steel buttress anchor pile lower anchor is drilled with the naked rock river bed (4), it is described For stake holes in 5m is not less than to laying and its depth vertically, the groined type steel buttress bottom is located at the middle inside of the stake holes; The steel buttress anchor structure (5-1) is by the concrete structure of the concrete form in the injection stake holes, the steel The height of buttress anchor structure (5-1) is consistent with the depth of the stake holes;The groined type steel buttress includes four root architectures and chi The vertical steel pipe (5-2) of very little all same is tight by horizontal brace rod (5-3) between adjacent two vertical steel pipes (5-2) It is solidly connected, the horizontal brace rod (5-3) is located above steel buttress anchor structure (5-1);Every vertical steel pipe (5-2) Bottom is supported in the stake holes bottom, and the bottom of the every vertical steel pipe (5-2) is poured into steel buttress anchor structure (5- 1) in.
  2. 2. according to the naked rock river bed trestle of hard stone of the deep water high-block bridge degree bridge construction described in claim 1, it is characterised in that: Length of the concrete pumping pipe (12) along girder (1) is laid from the front to the back.
  3. 3. according to the naked rock river bed trestle of hard stone of the deep water high-block bridge degree bridge construction described in claim 1 or 2, its feature exists In:The apical side height of bank side supporting table (10) is identical with the overhead height of steel cofferdam (11), the horizontal operation platform (13) the top surface flush of top surface and floorings (3).
  4. 4. according to the naked rock river bed trestle of hard stone of the deep water high-block bridge degree bridge construction described in claim 1 or 2, its feature exists In:The aperture of the stake holes is φ 2m~φ 3m.
  5. 5. according to the naked rock river bed trestle of hard stone of the deep water high-block bridge degree bridge construction described in claim 1 or 2, its feature exists In:The external diameter of the vertical steel pipe (5-2) is φ 0.6m~φ 0.65m, net between adjacent two vertical steel pipes (5-2) Away from for 0.4m~0.7m.
  6. 6. according to the naked rock river bed trestle of hard stone of the deep water high-block bridge degree bridge construction described in claim 1 or 2, its feature exists In:The transverse distribution beam (5-4) that multiple tracks is laid in same level, the transverse direction point are provided with the groined type steel buttress With beam (5-4) and girder (1) perpendicular laying, the girder (1) is supported in described in multiple tracks on transverse distribution beam (5-4), multiple tracks The transverse distribution beam (5-4) is from the front to the back laid in horizontal layout and along the length direction of girder (1).
  7. 7. according to the naked rock river bed trestle of hard stone of the deep water high-block bridge degree bridge construction described in claim 6, it is characterised in that: The quantity that transverse distribution beam (5-4) is laid on the groined type steel buttress is twice, transverse distribution beam (5-4) described in twice point Wei not front side distribution beam and the rear side distribution beam positioned at the front side distribution beam rear;
    Four vertical steel pipes (5-2) include the front side steel pipe and two two symmetric supports below the front side distribution beam Rear side steel pipe of the symmetric support below the rear side distribution beam, two front side steel pipes and two rear side steel pipes are in pair Claim to lay, two front side steel pipes are symmetrically laid in below the left and right sides of girder (1), two symmetrical cloth of rear side steel pipe Below the left and right sides of girder (1);The front side distribution beam is weldingly fixed on two front side steel pipes, the rear side Distribution beam is weldingly fixed on two rear side steel pipes;
    Pass through horizontal brace rod (5-3) described in the multiple tracks from top to bottom laid between adjacent two vertical steel pipes (5-2) It is fastenedly connected, the horizontal brace rod (5-3) is shaped steel rod member and fixes company between vertical steel pipe (5-2) with welding manner Connect;
    Two are provided with described in per pass on transverse distribution beam (5-4) spacing postive stop baffle (6) is carried out to girder (1), it is described Postive stop baffle (6) is in vertically to laying, and two postive stop baffles (6) are symmetrically laid at left and right sides of girder (1);It is described spacing The overhead height of baffle plate (6) is less than the apical side height of girder (1).
  8. 8. according to the naked rock river bed trestle of hard stone of the deep water high-block bridge degree bridge construction described in claim 1 or 2, its feature exists In:Also include twice to be laid in same level and to carrying out spacing longitudinal spacing part (9) at the top of girder (1), it is described vertical To locating part (9) in horizontal layout and its with girder (1) be in parallel laying, girder (1) top card is loaded on vertical described in twice To between locating part (9);
    The upper distribution beam (8) being laid in same level, the upper distribution beam are provided with the girder (1) from the front to the back (8) it is in horizontal layout and itself and girder (1) perpendicular laying;The floorings (3) are paved on upper distribution beam (8) described in multiple tracks On;
    Longitudinal spacing part (9) described in twice is respectively positioned on below distribution beam (8), and longitudinal spacing part (9) described in per pass is and multiple tracks The upper distribution beam (8), which is fastenedly connected, to be integrated;
    The girder (1) includes the Bailey beam laid from left to right of multiple tracks, Bailey beam described in multiple tracks in vertically to lay and its It is in parallel laying;It is fastenedly connected and is integrated by longitudinal connection structure between Bailey beam described in adjacent twice, the longitudinal direction connects Binding structure is the truss frame for connecting being spliced by multiple tracks connecting rod;
    The floorings (3) are horizontal steel plate, and guard rail (7) is provided with above the left and right sides of the floorings (3).
  9. A kind of 9. method constructed to trestle as claimed in claim 1, it is characterised in that this method comprises the following steps:
    Step 1: steel buttress anchors pile driving construction:Each steel buttress anchor pile (5) of institute's construction bridge is constructed respectively, until Complete the work progress of all steel buttress anchor piles (5);The construction method all same of all steel buttress anchor piles (5);
    To when steel buttress anchor pile is constructed any one described, process is as follows:
    Step 101, drilling:Current institute's construction steel buttress anchor pile is from top to bottom drilled through on naked rock river bed (4) using rig The stake holes;
    Step 102, the lifting of groined type steel buttress:The groined type steel buttress that shaping is pre-machined is lifted and transferred to step Described in 101 in stake holes, the groined type steel buttress bottom is set to be located at the middle inside of the stake holes, and make the groined type steel The bottom of the every vertical steel pipe (5-2) is supported in the stake holes bottom in buttress;
    Step 103, anchoring:To concrete perfusion in stake holes described in step 101, after institute's concrete perfusion solidification, applied The steel buttress anchor structure (5-1) of work shaping;
    Step 2: main beam supporting:It is ready to use in after the completion of steel cofferdam (11) construction of pier in the water of constructing, by institute's construction bridge Girder (1) is set up on the steel buttress anchor pile (5) for completion of being constructed in step 1, and the front support of girder (1) is enclosed in steel It is supported on weir (11) and by the rear end of girder (1) in bank side supporting table (10);
    Step 3: floorings are mated formation:Mat formation on the girder described in step 2 (1) floorings (3);
    In step 2 middle girder erection process, horizontal operation platform (12) is synchronized and set up, and by girder (1) and horizontal work Make platform (12) and be fastenedly connected to be integrated.
  10. 10. in accordance with the method for claim 9, it is characterised in that:When being drilled in step 101, using floating on the water surface Drilling platform drilled;The construction passage for the steel buttress anchor pile of constructing is provided with the drilling platform, it is described Rig be all-hydraulic percussion reverse circulation drill and its be installed on the drilling platform;
    When the lifting of groined type steel buttress is carried out in step 102, the groined type steel buttress is lifted and transferred to institute using crane barge State in stake holes;
    In step 103 into the stake holes during concrete perfusion, it is irrigated using the crane barge.
CN201711160995.8A 2017-11-20 2017-11-20 Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method Active CN107700366B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711160995.8A CN107700366B (en) 2017-11-20 2017-11-20 Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711160995.8A CN107700366B (en) 2017-11-20 2017-11-20 Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method

Publications (2)

Publication Number Publication Date
CN107700366A true CN107700366A (en) 2018-02-16
CN107700366B CN107700366B (en) 2019-08-27

Family

ID=61180616

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711160995.8A Active CN107700366B (en) 2017-11-20 2017-11-20 Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method

Country Status (1)

Country Link
CN (1) CN107700366B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056534A (en) * 2018-07-19 2018-12-21 中铁大桥局第九工程有限公司 A kind of movable type bored pile construction platform and method
CN109322241A (en) * 2018-11-08 2019-02-12 中建五局土木工程有限公司 Trestle work structure and construction method
CN110552294A (en) * 2019-09-29 2019-12-10 中国建筑第八工程局有限公司 Bridge girder erection machine reverse beam erection construction platform and construction method thereof
CN112681135A (en) * 2020-12-14 2021-04-20 中铁二十局集团第三工程有限公司 Construction method of n-shaped sea-crossing temporary steel trestle
CN112779850A (en) * 2020-12-31 2021-05-11 浙大城市学院 Granular material cargo transporting trestle platform for river-crossing tunnel navigation sealing cofferdam construction and construction method
CN112857305A (en) * 2019-11-28 2021-05-28 湖南五新模板有限公司 Landing stage of detectable deformation state
CN115450126A (en) * 2022-09-30 2022-12-09 中铁二十局集团第一工程有限公司 Bridge supporting structure and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1900424A (en) * 2005-07-21 2007-01-24 郑州市华中建筑机械有限公司 Half span type down guide frame bridging machine and its beam building method
CN102953341A (en) * 2012-12-13 2013-03-06 中铁上海工程局有限公司 Overhead trestle structure built on non-covering steep bare rocks in deep rapids
CN102979039A (en) * 2012-12-13 2013-03-20 中铁上海工程局第二工程有限公司 Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN207452738U (en) * 2017-11-20 2018-06-05 中铁二十局集团第一工程有限公司 The deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1900424A (en) * 2005-07-21 2007-01-24 郑州市华中建筑机械有限公司 Half span type down guide frame bridging machine and its beam building method
CN102953341A (en) * 2012-12-13 2013-03-06 中铁上海工程局有限公司 Overhead trestle structure built on non-covering steep bare rocks in deep rapids
CN102979039A (en) * 2012-12-13 2013-03-20 中铁上海工程局第二工程有限公司 Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN207452738U (en) * 2017-11-20 2018-06-05 中铁二十局集团第一工程有限公司 The deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
徐小祥: "深水裸露坡岩大型高低刃脚双壁钢围堰设计与施工", 《铁道建筑》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056534A (en) * 2018-07-19 2018-12-21 中铁大桥局第九工程有限公司 A kind of movable type bored pile construction platform and method
CN109322241A (en) * 2018-11-08 2019-02-12 中建五局土木工程有限公司 Trestle work structure and construction method
CN110552294A (en) * 2019-09-29 2019-12-10 中国建筑第八工程局有限公司 Bridge girder erection machine reverse beam erection construction platform and construction method thereof
CN112857305A (en) * 2019-11-28 2021-05-28 湖南五新模板有限公司 Landing stage of detectable deformation state
CN112681135A (en) * 2020-12-14 2021-04-20 中铁二十局集团第三工程有限公司 Construction method of n-shaped sea-crossing temporary steel trestle
CN112681135B (en) * 2020-12-14 2022-10-11 中铁二十局集团第三工程有限公司 Construction method of n-shaped sea-crossing temporary steel trestle
CN112779850A (en) * 2020-12-31 2021-05-11 浙大城市学院 Granular material cargo transporting trestle platform for river-crossing tunnel navigation sealing cofferdam construction and construction method
CN115450126A (en) * 2022-09-30 2022-12-09 中铁二十局集团第一工程有限公司 Bridge supporting structure and construction method

Also Published As

Publication number Publication date
CN107700366B (en) 2019-08-27

Similar Documents

Publication Publication Date Title
CN107700366B (en) Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method
CN105386408B (en) Deep-water bridge pile foundation construction method
CN101666081B (en) Abrupt slope bare rock drilling platform and technology in huge reservoir
CN102953341B (en) A kind of high-order trestle work structure be arranged in deep water torrent intectate steep bare rock
CN102352632B (en) Anchor rod sheet pile combined structure and method for reinforcing high filling body on one side of slope
CN102720140B (en) Large-span prestress concrete continuous beam deepwater pier construction process
CN108103939B (en) Combined reinforcement mode and construction process for construction of oblique-section steel trestle
CN102979039B (en) Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN106049281A (en) Deep-water construction method of bridge at water pebble soil and argillaceous sandstone areas and auxiliary working platform
CN101538833B (en) Vertical subsection double-wall steel cofferdam water stopping construction method
CN103741657A (en) Construction method of large multifunctional over-water construction platform
CN108005094B (en) Pier and pier top beam section construction method in naked rock river bed water
CN203049443U (en) High level trestle structure arranged on steep bare rock of deepwater torrent unsheathed layer
CN207452738U (en) The deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone
CN110042843A (en) A kind of large deep foundation pit construction method of complex condition
CN201502056U (en) Bare rock drilling platform for steep slope of deep reservoir area
CN106498957A (en) Steel sheet pile cofferdam construction platform and integral construction method
CN112195779A (en) Multifunctional trestle construction method suitable for thick pebble layer
CN100473787C (en) Connecting structure for use in piled anchor supporting system and construction method thereof
CN107489106A (en) A kind of rocky bed subaqueous bearing platform construction method
CN208280155U (en) A kind of steel trestle infrastructure structure for resisting the impact of flood discharge torrent speed
CN208201658U (en) A kind of steel trestle rapid construction device
CN110029653B (en) Method for treating steel pipe pile foundation of riprap seabed foundation
CN107841952B (en) Attached type high-altitude assembly support and construction method for side-span cast-in-place section of rigid frame continuous beam
CN108035372B (en) A method of steel lifted trunk is hung using drilling platform gooseneck

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 215151 No. 10, Datong Road, high tech Zone, Suzhou, Jiangsu

Patentee after: China Railway Construction Urban Construction Transportation Development Co.,Ltd.

Country or region after: China

Address before: Engineering technology management center of the first Engineering Co., Ltd. of China Railway 20th bureau group, No.10 Datong Road, high tech Zone, Suzhou City, Jiangsu Province

Patentee before: NO.1 ENGINEERING CORPORATION LIMITED OF CR20G

Country or region before: China

CP03 Change of name, title or address