CN103898910A - Method for anchoring trestle steel pipe piles on seabed rock bare landform - Google Patents

Method for anchoring trestle steel pipe piles on seabed rock bare landform Download PDF

Info

Publication number
CN103898910A
CN103898910A CN201410083929.5A CN201410083929A CN103898910A CN 103898910 A CN103898910 A CN 103898910A CN 201410083929 A CN201410083929 A CN 201410083929A CN 103898910 A CN103898910 A CN 103898910A
Authority
CN
China
Prior art keywords
steel pipe
pipe pile
landforms
exposed
trestle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410083929.5A
Other languages
Chinese (zh)
Inventor
乔光
李新强
杨小雷
刘开来
赵春亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Engineering Co Ltd
CCCC Third Harbor Engineering Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
CCCC Third Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd, CCCC Third Harbor Engineering Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN201410083929.5A priority Critical patent/CN103898910A/en
Publication of CN103898910A publication Critical patent/CN103898910A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a method for anchoring trestle steel pipe piles on a seabed rock bare landform. The method includes the following steps that first, a steel pipe pile assisting platform is manufactured and steel pipe piles are preliminarily erected; second, concrete is poured in steel pipes underwater; third, holes are drilled in the concrete in the steel pipes, and the concrete is drilled through till a preset depth below the bed rock face is reached; fourth, anchor rods are placed in the drilled holes, and mortar is pressed in the drilled holes. The method for anchoring trestle steel pipe piles on the seabed rock bare landform solves the problem that steel pipe piles cannot be driven in the seabed rock bare landform through traditional hammering or vibration, achieves stable connection between the steel pipe piles and rock and has the advantages of being easy to operate, little in material consumption, stable, reliable and high in economic benefit.

Description

Trestle steel pipe pile anchoring process on the exposed landforms of marine rock
Technical field
The present invention relates to trestle steel pipe pile anchoring process on the exposed landforms of a kind of marine rock.
Background technology
In prior art, the construction of sea berth steel pipe pile, according to seabottom geology condition difference, construction method is different, for there being covering layer area generally to adopt pile driving barge pile driving method by hammer, or vibrosinking, for the exposed landforms of marine rock, the general clump of piles that adopts in area is stable among a small circle, the mode that steel pipe pile is directly sitting on basement rock or adopts bored pile to be combined with steel pipe pile, but there is no more ripe construction method for the area that the exposed landforms scope of rock larger area especially scar discrepancy in elevation big rise and fall and trestle circuit are grown.
Summary of the invention
The object of this invention is to provide trestle steel pipe pile anchoring process on the exposed landforms of a kind of marine rock.
The technical scheme that the present invention adopted is for achieving the above object: trestle steel pipe pile anchoring process on the exposed landforms of a kind of marine rock, comprises the following steps:
A, make steel pipe pile assistance platform and tentatively prop up vertical steel pipe pile;
B, carry out underwater concreting in steel pipe;
C, steel pipe inner concrete is holed, drill concrete until reach the following desired depth of bedrock surface;
D, boring in transfer anchor pole and be pressed into mortar.
In described steps A, steel pipe pile assistance platform can carry out leveling by telescopic supporting leg.
Described telescopic supporting leg is that big steel pipe overlaps little steel tubular structure.
In described steps A, steel pipe pile assistance platform plane is equilateral triangle.
In described step B, in steel pipe, underwater concreting adopts vertical duct method.
Long and the stake inner concrete height of the pre-test of holing in described step C steel pipe pile stake, determines drilling depth.
After drilling concrete, continue to creep into until reach design anchorage depth.
In described step D, by anchor pole and Grouting Pipe colligation, the hole of holding successfully in advance through anchor pole top with rope, transfers along sleeve pipe, transfers after at the bottom of hole and starts slip casting.
Trestle steel pipe pile anchoring process on the exposed landforms of a kind of marine rock of the present invention, solve the problem that steel pipe pile cannot adopt traditional hammering or vibration to squeeze on the exposed landforms of marine rock, having realized steel pipe pile is connected with the firm of rock, have simple to operate, material consumption is few, the feature reliable and stable, economic benefit is high.
Brief description of the drawings
Fig. 1 is the vertical schematic diagram of the steel pipe pile positioning support of trestle steel pipe pile anchoring process on the exposed landforms of a kind of marine rock of the present invention.
Fig. 2 is the steel pipe pile Zhi Lihou bottom sand pocket pile schematic diagram of trestle steel pipe pile anchoring process on the exposed landforms of a kind of marine rock of the present invention.
Fig. 3 is the anchor rod anchored schematic diagram of trestle steel pipe pile anchoring process on the exposed landforms of a kind of marine rock of the present invention.
Fig. 4 is the Grouting Pipe of trestle steel pipe pile anchoring process and the relative position schematic diagram of anchor pole on the exposed landforms of a kind of marine rock of the present invention.
In figure: 1, auxiliary positioning platform; 2, link; 3, steel pipe pile; 4, sand pocket; 5, interim fulcrum; 6, concrete; 7, scar; 8, mortar; 9, anchor pole; 10, Grouting Pipe.
Detailed description of the invention
As shown in Figures 1 to 4, trestle steel pipe pile anchoring process on the exposed landforms of marine rock, comprise the following steps: A, make steel pipe pile assistance platform and tentatively prop up vertical steel pipe pile, at sea Zhi Liding position steel pipe pile need to complete by auxiliary positioning platform, auxiliary positioning platform 1 can carry out the landforms that leveling rises and falls to be suitable for seabed height, leveling realizes by telescopic supporting leg, supporting leg is the structure that big steel pipe overlaps little steel pipe, little steel pipe can freely jump in big steel pipe, after 1 leveling of auxiliary positioning platform, spacer pin on little steel pipe is stuck on the clamp of big steel pipe, thereby limit jumping of little steel pipe, keep auxiliary positioning platform level, after the leveling of assistance platform coarse positioning, refute the loop wheel machine steel pipe pile of slinging and position Zhi Li side, after having located and other propped up the steel pipe pile having stood and carried out lateral, levelling auxiliary positioning platform plane is equilateral triangle, internal lining pipe and outer tube length are determined according to construction area depth of water situation, while needing to ensure climax, tripod is in the time of minimum scar, top top bracing still can surface, between top bracing, completely spread as operation platform with steel plate, railing is established on two limits of triangle, another limit need be set up link 2 and do not established railing, on outer tube top, mouth is opened vertical two symmetrical notches downwards, draw hole baffle plate two two meters long of notch two side welds, open 0.08 meter of circular hole of diameter at mouthful downward 2.5 meters of, inner tube top, auxiliary positioning platform erection adopts jack to realize, auxiliary positioning platform is transferred by just refuting loop wheel machine, GPS auxiliary positioning, and between interim fulcrum 5, distance is less than link 2 length, locating platform is relative with interim fulcrum 5 without railing one side, loop wheel machine decoupling device after position meets the demands, manually pull steel pipe pile both sides jack leveling locating platform, locating platform level has been blocked gear shaft later, after locating platform leveling is complete, between locating platform and square refuting, set up springboard, facilitate personnel upper and lower, emit the position of steel pipe pile 3 in link 2 both sides, weld temporary guide structure with angle steel, according to leading truck position, transfer steel pipe pile 3, diver checks at the bottom of snag whether situation is solid naked rock, if any covering layer or cannot need use vibrating hammer pile sinking by estimate of situation, until can not sink, steel pipe, 3 and link 2 between spot welding be connected temporarily, after two steel pipe piles are in place, carry out lateral and bridging welding, steel pipe pile top adds interim lateral provides fulcrum for next circulation of link, for reducing to greatest extent the impact of tidewater, the on-the-spot shortening connect hours, employing tender is manned, springboard people from station set up with the operations simultaneously of many electric welding machines in steel pipe pile side, be required to be every steel pipe pile for bonding campshed is stable and add two Splaylegs supports, Splayleg supports with ground need keep 60 degree left and right angles, diver coordinates the support of the searching Eight characters to stablize fulcrum under water under water, between each row's steel pipe pile and upper row's steel pipe pile, carry out interim vertical company, make to connect between pier and pier entirety and set up the condition that provides for drilling platform, lateral and support complete after, remove link and interim being connected between fulcrum and tripod, carry out the construction of next row, now no longer need interim fulcrum, link can be placed on one and arrange on the stake top bracing having stood, staking out arrives after some, need carry out concrete leveling to scar at the bottom of stake and around, levelling scope outward flange is piled up sand pocket 4, build underwater concrete and need ensure that stake position surrounding concrete toe is positioned on reverse slope, scar is sand more at ordinary times, 4 keep 50cm distance with steel pipe pile 3, highly exceed steel pipe pile 30-40cm, scar inclination need add sand pocket input amount when larger, increase sand pocket wall thick, while preventing concreting, wash upside down sand pocket wall, B, carry out underwater concreting in steel pipe, steel pipe pile Zhi Li completes and does after interim lateral, diver checks the gap situation that steel pipe pile bottom contacts with scar, as gap more adopts sand pocket 4 pile around steel pipe pile 3, after steel pipe bottom check processing completes, adopt mix ship that tremie placing underwater concrete is installed in steel pipe pile, pouring underwater concrete adopts vertical duct method, control conduit and be less than 0.5m apart from the distance at the bottom of stake, go out catheter length according to the calculation of the length of bored pile, before being installed, funnel checks distortion and ring wear situation, and ensure that inside pipe wall is smooth straight, the mortar adhering to is cleaned out, concrete 6 adopts mixer ship to stir, C30 is discrete concrete not, the strict concrete mix of controlling in whipping process, loop wheel machine hangs funnel and conduit is placed on the leakage of steel pipe pile top, mix ship pumped concrete 6 enters funnel, after reaching calculating side's amount, the auxiliary hook of loop wheel machine is extracted funnel piston fast, concrete 6 entirety fall into water, measure stake inner concrete height, do not meet after requirement for height, calculating demanding party of institute amount continues to build, until stake inner concrete height meets 2m requirement, C, steel pipe inner concrete is holed, drill concrete until reach the following desired depth of bedrock surface 7, the concrete of building in steel pipe reaches after requirement of strength, lay interim drilling platform at steel pipe pile top, and adopt geological drilling rig to hole to pipe inner concrete, after drilling concrete, continue to creep into until reach design anchorage depth, long and the stake inner concrete height of boring pre-test stake, determine drilling depth, while being greater than 2.5m as the stake inner concrete degree of depth while creeping into, need transfer 168mm sleeve pipe every slag, as the stake inner concrete degree of depth is less than 2.5m without transferring sleeve pipe, in drilling process, observe drilling depth and return slag situation, meet not the situations such as drilling depth and return slag be abnormal, need stop after brill ascertains the reason to continue again to creep into, judge according to run of steel and return slag material whether drilling rod enters rock, ensure into the rock degree of depth, D, in boring, transfer anchor pole and be pressed into mortar, after boring, rig elevator is mentioned anchor pole 9 hand-holes, remove anchor pole snap ring anchor pole freely falling body at the bottom of hole, anchor pole 9 is made bottom by Q345 angle steel and is opened wedge-shaped opening in order to mud jacking, after anchor pole is transferred, mud jacking will be carried out at the bottom of Grouting Pipe patchhole, sand 8 is pressed into by pneumatic mortar machine, along with preventing pipe laying, slurry face rising hoisting grouting pipe 10 crosses dark insufficient pressure, mud jacking finishes mud jacking after reaching predetermined party amount, hole depth reaches after requirement, drilling rod is proposed, by anchor pole 9 and Grouting Pipe 10 iron wire colligation, colligation does not need sacrifices consisting of an ox, a sheep and a pig Grouting Pipe not come off, with transferring along sleeve pipe in the hole that rope is held successfully in advance through anchor pole top, transfer to shove pump after at the bottom of hole and start slip casting, mortar quality is the key of this technique, must be in strict accordance with match ratio mixing, for preventing jam of grouting pipe, fine sand must sieve, fine sand consumption adopts platform balance metering, Admixture consumption adopts graduated cylinder metering, Grouting Pipe and sleeve pipe are proposed after slip casting is complete immediately, in case at the bottom of brush pump water injection hole.

Claims (8)

1. a trestle steel pipe pile anchoring process on the exposed landforms of marine rock, is characterized in that, comprises the following steps:
A, make steel pipe pile assistance platform and tentatively prop up vertical steel pipe pile;
B, carry out underwater concreting in steel pipe;
C, steel pipe inner concrete is holed, drill concrete until reach the following desired depth of bedrock surface;
D, boring in transfer anchor pole and be pressed into mortar.
2. trestle steel pipe pile anchoring process on the exposed landforms of a kind of marine rock according to claim 1, is characterized in that: in described steps A, steel pipe pile assistance platform can carry out leveling by telescopic supporting leg.
3. trestle steel pipe pile anchoring process on the exposed landforms of a kind of marine rock according to claim 2, is characterized in that: described telescopic supporting leg is that big steel pipe overlaps little steel tubular structure.
4. trestle steel pipe pile anchoring process on the exposed landforms of a kind of marine rock according to claim 1, is characterized in that: in described steps A, steel pipe pile assistance platform plane is equilateral triangle.
5. trestle steel pipe pile anchoring process on the exposed landforms of a kind of marine rock according to claim 1, is characterized in that: in described step B, in steel pipe, underwater concreting adopts vertical duct method.
6. trestle steel pipe pile anchoring process on the exposed landforms of a kind of marine rock according to claim 1, is characterized in that: the long and stake inner concrete height of the pre-test of holing in described step C steel pipe pile stake, determine drilling depth.
7. trestle steel pipe pile anchoring process on the exposed landforms of a kind of marine rock according to claim 6, is characterized in that: after drilling concrete, continue to creep into until reach design anchorage depth.
8. trestle steel pipe pile anchoring process on the exposed landforms of a kind of marine rock according to claim 1, it is characterized in that: in described step D by anchor pole and Grouting Pipe colligation, the hole of holding successfully in advance through anchor pole top with rope, transfers along sleeve pipe, transfers after at the bottom of hole and starts slip casting.
CN201410083929.5A 2014-03-10 2014-03-10 Method for anchoring trestle steel pipe piles on seabed rock bare landform Pending CN103898910A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410083929.5A CN103898910A (en) 2014-03-10 2014-03-10 Method for anchoring trestle steel pipe piles on seabed rock bare landform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410083929.5A CN103898910A (en) 2014-03-10 2014-03-10 Method for anchoring trestle steel pipe piles on seabed rock bare landform

Publications (1)

Publication Number Publication Date
CN103898910A true CN103898910A (en) 2014-07-02

Family

ID=50990463

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410083929.5A Pending CN103898910A (en) 2014-03-10 2014-03-10 Method for anchoring trestle steel pipe piles on seabed rock bare landform

Country Status (1)

Country Link
CN (1) CN103898910A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105239573A (en) * 2015-10-28 2016-01-13 浙江省交通工程建设集团有限公司第二分公司 Rock anchoring construction method for implanted pipe of structural steel trestle
CN107386285A (en) * 2017-08-03 2017-11-24 中铁六局集团有限公司 A kind of novel steel tube pile foundation rock borehole anchorage method
CN108625386A (en) * 2018-07-24 2018-10-09 中铁七局集团第二工程有限公司 A kind of Conveyor belt steel pipe spliced pile and construction method
CN110847047A (en) * 2019-11-21 2020-02-28 中交第二航务工程局有限公司 Open sea bare rock trestle construction method
CN115404897A (en) * 2022-10-08 2022-11-29 中国电建集团成都勘测设计研究院有限公司 Construction method of marine composite foundation
CN116043906A (en) * 2022-12-07 2023-05-02 保利长大工程有限公司 Anchoring construction method for steel pipe pile in underwater bare rock area

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100712191B1 (en) * 2005-12-29 2007-04-27 한국해양연구원 File penetration device and method using pile anchor and winch
CN102953362A (en) * 2012-12-13 2013-03-06 中铁上海工程局有限公司 Bored pile platform built on non-covering steep bare rocks in deep rapids
CN102953341A (en) * 2012-12-13 2013-03-06 中铁上海工程局有限公司 Overhead trestle structure built on non-covering steep bare rocks in deep rapids
CN102966111A (en) * 2012-12-13 2013-03-13 中铁上海工程局第二工程有限公司 Construction method for anchoring steel pipe pile on steep bare rock without covering layer in deep water and rapids
CN203049443U (en) * 2012-12-14 2013-07-10 中铁上海工程局有限公司 High level trestle structure arranged on steep bare rock of deepwater torrent unsheathed layer

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100712191B1 (en) * 2005-12-29 2007-04-27 한국해양연구원 File penetration device and method using pile anchor and winch
CN102953362A (en) * 2012-12-13 2013-03-06 中铁上海工程局有限公司 Bored pile platform built on non-covering steep bare rocks in deep rapids
CN102953341A (en) * 2012-12-13 2013-03-06 中铁上海工程局有限公司 Overhead trestle structure built on non-covering steep bare rocks in deep rapids
CN102966111A (en) * 2012-12-13 2013-03-13 中铁上海工程局第二工程有限公司 Construction method for anchoring steel pipe pile on steep bare rock without covering layer in deep water and rapids
CN203049443U (en) * 2012-12-14 2013-07-10 中铁上海工程局有限公司 High level trestle structure arranged on steep bare rock of deepwater torrent unsheathed layer

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王春利等: "大面积裸岩及浅覆盖层海域栈桥施工关键技术", 《建材发展导向(下)》, no. 3, 30 June 2013 (2013-06-30), pages 280 - 281 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105239573A (en) * 2015-10-28 2016-01-13 浙江省交通工程建设集团有限公司第二分公司 Rock anchoring construction method for implanted pipe of structural steel trestle
CN107386285A (en) * 2017-08-03 2017-11-24 中铁六局集团有限公司 A kind of novel steel tube pile foundation rock borehole anchorage method
CN108625386A (en) * 2018-07-24 2018-10-09 中铁七局集团第二工程有限公司 A kind of Conveyor belt steel pipe spliced pile and construction method
CN110847047A (en) * 2019-11-21 2020-02-28 中交第二航务工程局有限公司 Open sea bare rock trestle construction method
CN110847047B (en) * 2019-11-21 2021-11-26 中交二航局第一工程有限公司 Open sea bare rock trestle construction method
CN115404897A (en) * 2022-10-08 2022-11-29 中国电建集团成都勘测设计研究院有限公司 Construction method of marine composite foundation
CN116043906A (en) * 2022-12-07 2023-05-02 保利长大工程有限公司 Anchoring construction method for steel pipe pile in underwater bare rock area

Similar Documents

Publication Publication Date Title
CN105569560B (en) A full set of tubular type long auger stake machine and the method for utilizing the ram machine construction
CN103898910A (en) Method for anchoring trestle steel pipe piles on seabed rock bare landform
CN102979039B (en) Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN102720186B (en) Underwater once pouring method for variable cross-section bored cast-in-place pile
CN103924585B (en) The construction method of wind-powered electricity generation socketed pile
CN104631438B (en) Long auger guncreting uplift pile construction method
CN109024651B (en) Steel pipe concrete mixed pile foundation and construction method
CN102535529A (en) Construction method of self-balancing method pile foundation bearing capacity test device
CN110924307A (en) Trestle construction method for bare rock geology
CN102953341A (en) Overhead trestle structure built on non-covering steep bare rocks in deep rapids
CN205369231U (en) Steel -pipe pile is filled in drilling
CN109630015A (en) A kind of friction pile mechanical hole building method
CN102979069A (en) Bored pile platform construction method on covering-free steep bare rock in deepwater and rapid stream
CN104018518A (en) Prefabricated underground diaphragm wall and method for constructing outer basement wall and floor slabs
CN108277819B (en) A kind of retaining wall structure
CN108547293A (en) A kind of embedding rock single pile plantation construction technology
CN113981961B (en) Ship-type pile planting method for deepwater bare rock
CN104314076B (en) A kind of soft foundation recoverable prestressed anchor Cable Structure and construction method
CN115306408A (en) Safe launching and receiving method for jacking pipe under high water pressure condition
CN203049443U (en) High level trestle structure arranged on steep bare rock of deepwater torrent unsheathed layer
CN104711975B (en) Construction technology for long spiral cast-in-situ bored pile
CN106758759A (en) A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
CN208472799U (en) The cast-in-place pond fender post float Structure of phreatic high
CN106480876A (en) A kind of inclined hole steel pipe piles set into rock construction
CN115897549A (en) Underwater shallow-earthing weak stratum pipe jacking anti-floating construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140702