CN105804090B - A kind of indoor piling wall supporting construction and its construction method - Google Patents

A kind of indoor piling wall supporting construction and its construction method Download PDF

Info

Publication number
CN105804090B
CN105804090B CN201610235951.6A CN201610235951A CN105804090B CN 105804090 B CN105804090 B CN 105804090B CN 201610235951 A CN201610235951 A CN 201610235951A CN 105804090 B CN105804090 B CN 105804090B
Authority
CN
China
Prior art keywords
wall
ground
bored concrete
concrete pile
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610235951.6A
Other languages
Chinese (zh)
Other versions
CN105804090A (en
Inventor
王志龙
周俊
周哲
许蓓
袁林娜
范海飞
施麟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi construction Refco Group Ltd
JIANGXI THE SECOND CONSTRUCTION CO., LTD.
Original Assignee
Jiangxi Construction Refco Group Ltd
JIANGXI SECOND CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Construction Refco Group Ltd, JIANGXI SECOND CONSTRUCTION Co Ltd filed Critical Jiangxi Construction Refco Group Ltd
Priority to CN201610235951.6A priority Critical patent/CN105804090B/en
Publication of CN105804090A publication Critical patent/CN105804090A/en
Application granted granted Critical
Publication of CN105804090B publication Critical patent/CN105804090B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/10Prefabricated parts, e.g. composite sheet piles made of concrete or reinforced concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/10Prefabricated parts, e.g. composite sheet piles made of concrete or reinforced concrete
    • E02D5/12Locking forms; Edge joints; Pile crossings; Branch pieces

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Environmental & Geological Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a kind of indoor piling wall supporting construction, including ground-connecting-wall and bored concrete pile;The both sides of ground-connecting-wall set bored concrete pile respectively;Ground-connecting-wall and bored concrete pile overlap occlusion by being embedded in the built-in fitting of the two edge;The two ends of built-in fitting are horizontal-extending along the outer surface of ground-connecting-wall, and the built-in fitting flange for folding the body normal to be formed with built-in fitting and being parallel to each other;A waterstop member is provided with built-in fitting;Ground-connecting-wall, bored concrete pile and waterstop member formation sealing piling wall;The side being connected outside bored concrete pile with ground-connecting-wall is provided with the tube members that the prepackage live wire being made up of waterproof insulation material is provided with cement sand bed, cement sand bed;Cement sand bed, prefabricated thermal insulation mortar soft board, prefabricated waterproof soft board are disposed with the wall face of the underground space formed between ground-connecting-wall and the bottom of bored concrete pile, displacement transducer is laid between bored concrete pile and the prefabricated thermal insulation mortar soft board and prefabricated thermal insulation mortar soft board of ground-connecting-wall intersection, the electric wire of connection displacement transducer extends to wall top from tube members.

Description

A kind of indoor piling wall supporting construction and its construction method
Technical field
The present invention relates to building field, and in particular to a kind of piling wall combination supporting construction and its construction method.
Background technology
With expanding economy, land resource more tends to be nervous.The depth of excavation of foundation pit is also increasingly deeper in architectural engineering, The depth of many buildings is more than 15 meters, and this is higher for the requirement of foundation pit supporting construction.Excavated under the conditions of soil layer During underground thing one foundation ditch of construction space, its side wall is very easy to collapse into hole, it is necessary to which construction temperature pier structure is used to Retaining support, can just ensure the safety of foundation ditch and underground thing construction safety and the existing building of foundation ditch surrounding.
However, the supporting construction of correlation technique is when occurring the emergencies such as earthquake or in support construction process In, displacement or trickle inclination for supporting construction can not be monitored in time to be perceived, the risk that there is harm main building.
The content of the invention
There is provided it is an object of the invention to avoid above-mentioned weak point of the prior art.
The purpose of the present invention is achieved through the following technical solutions:
There is provided a kind of indoor piling wall supporting construction, it is characterised in that:Including several ground-connecting-walls and several bored concrete piles;It is described Ground-connecting-wall is formed using paddling process, churning method or press injecting method;The both sides of each ground-connecting-wall are respectively arranged with bored concrete pile, Each ground-connecting-wall connects to form piling wall supporting construction by the bored concrete pile;The ground-connecting-wall and bored concrete pile are by being embedded in The built-in fitting overlap joint occlusion of the two edge;Outer surface of the two ends of the built-in fitting along the ground-connecting-wall is horizontal-extending, and rolls over The folded body normal formed with the built-in fitting and the built-in fitting flange being parallel to each other;A sealing structure is provided with the built-in fitting Part;The ground-connecting-wall, bored concrete pile and waterstop member formation sealing piling wall;The appearance for the side that the bored concrete pile is connected with ground-connecting-wall Face is provided with the pipe that the prepackage live wire being made up of waterproof insulation material is provided with one layer of cement sand bed, cement sand bed Part;The high 1500mm underground space is formed between the bottom of the ground-connecting-wall and bored concrete pile, is applied on the wall face in the space Covering on one layer of cement sand bed, cement sand bed is brushed with to be enclosed with prefabricated thermal insulation mortar soft board, prefabricated thermal insulation mortar soft board Covered with prefabricated waterproof soft board, wherein, the prefabricated thermal insulation mortar soft board and prefabricated thermal insulation mortar of bored concrete pile and ground-connecting-wall intersection Displacement transducer is laid between soft board, the electric wire of connection displacement transducer is default from ground-connecting-wall after being coated with waterproof material Tube members extend to the wall top of ground-connecting-wall.
Preferably, the adjacent bored concrete pile 2 is respectively arranged with an annular construction member, and the annular construction member crosses ground-connecting-wall, Preset in the annular construction member and be equipped with bearing element, cement mortar, any bearing element are filled with the annular construction member On be provided with one be used for keep annular construction member cement mortar stream annular space centralizer, the bored concrete pile and ground-connecting-wall it Between be additionally provided with elastic sealing element for sealing the annular construction member.
Preferably, the anchoring piece extended along ground-connecting-wall direction is also associated with the built-in fitting;Untill the waterstop member Water steel plate, its centre position by being fixedly welded on the built-in fitting.
Preferably, the steel plate for sealing water is 5 × 50 steel plate for sealing water;The anchoring piece includes anchor bar and high polymer material The component being made;The anchoring piece is symmetrically welded in the both sides of the waterstop member;The length of the main body of the built-in fitting and ground Even the thickness of wall is adapted, and the length of the built-in fitting flange is more than or equal to 20mm.
Preferably, the supporting construction can according to site condition, geological conditions and construction requirement, can shape become broken line type And/or turning type.
Preferably, ground-connecting-wall thickness is 700mm~900mm;A length of 5000mm~the 7000mm of ground-connecting-wall wall.
Preferably, the ground-connecting-wall thickness is 800mm;The a length of 6000mm of ground-connecting-wall wall;Pile diameter be more than etc. In ground-connecting-wall thickness+400mm.
Preferably, ground-connecting-wall is more than or equal to 200mm with the length for being engaged section of bored concrete pile;The adjacent ground-connecting-wall and perfusion Adjoining diameter=1/2 pile diameter-ground-connecting-wall and bored concrete pile between the occlusion section of stake are engaged section.
Preferably, the wall top of the ground-connecting-wall and the stake top absolute altitude of bored concrete pile are consistent.
A kind of construction method of indoor piling wall supporting construction, it is characterised in that comprise the following steps:
(1) preparation of construction, smooth construction site;(2) the construction line-putting:According to job site, construction Survey Control point is laid And bench mark, periphery axis is carried out to be accurately positioned setting-out;(3) filling pile construction:Drilled by the operating type of bored concrete pile, design Bottom absolute altitude, forms the stake holes for irrigating the bored concrete pile, bored concrete pile is squeezed into stake holes;(4) bored concrete pile is conserved:Allow its intensity Value reaches 75% design load;(5) construction of ground-connecting-wall is carried out between two adjacent bored concrete piles;(6) treat that wall and bored concrete pile reach To predetermined value, the tube members of prepackage live wire are inserted in ground-connecting-wall and bored concrete pile junction;(7) on underground space exterior wall and successively Place cement sand bed, prefabricated thermal insulation mortar soft board, displacement transducer and prefabricated waterproof soft board.
The beneficial effect of embodiment provided by the present invention:
(1) a kind of indoor piling wall supporting construction that embodiments of the invention are provided, itself and the ground-connecting-wall in correlation technique Supporting construction is compared, and stack pile plane stiffness improves more than 18%;In addition, stake, wall node are rationally, easy construction, it is ensured that ground Connection wall joint quality, effectively eliminates the common quality defect of ground-connecting-wall joint.
(2) embodiments of the invention additionally provide a kind of construction technology for being applied to the present invention, because bored concrete pile connects with ground Wall has ripe construction technology, therefore present invention construction is simple, using first construction stake, ground-connecting-wall of constructing afterwards, ground-connecting-wall construction nothing Need to be job-hoped construction, can continuously be constructed.
(3) due to being provided with displacement transducer, therefore, when stake and/or wall occur slight mobile, displacement transducer can be by To mobile terminal the real-time monitoring to piling wall supporting construction can be achieved, to prevent the generation of potential danger in information transmission.
(4) due to being provided with the bearing element of dual reinforcing function, and bearing member in the bored concrete pile and ground-connecting-wall of the present invention It is provided with centralizer on part, centralizer can ensure that the cement mortar filling gap in the annular construction member where bearing element, therefore, Piling wall supporting construction is not only strengthened, being smoothed out for construction is more ensure that.
(5) cost of bored concrete pile of the present invention is lower than ground-connecting-wall, and piling wall combination support construction total cost is relatively low, can be a large amount of The cost that uses manpower and material resources sparingly, can be widely popularized applicable.
Brief description of the drawings
Invention is described further using accompanying drawing, but the embodiment in accompanying drawing does not constitute any limitation of the invention, For one of ordinary skill in the art, on the premise of not paying creative work, it can also be obtained according to the following drawings Its accompanying drawing.
Fig. 1 is a kind of plan for indoor piling wall supporting construction that embodiments of the invention are provided.
Fig. 2 is a kind of elevation for indoor piling wall supporting construction that embodiments of the invention are provided.
Fig. 3 is the bored concrete pile and ground-connecting-wall occlusion section for a kind of indoor piling wall supporting construction that embodiments of the invention are provided And the enlarged drawing of built-in fitting.
Fig. 4 is a kind of broken line type layout drawing for indoor piling wall supporting construction that embodiments of the invention are provided.
Fig. 5 is a kind of turning type layout drawing for indoor piling wall supporting construction that embodiments of the invention are provided.
Fig. 6 is a kind of annular construction member schematic diagram for indoor piling wall supporting construction that embodiments of the invention are provided.
Fig. 7 is a kind of bearing element schematic diagram for indoor piling wall supporting construction that embodiments of the invention are provided.
Wherein:Wherein:1- ground-connecting-walls, 2- bored concrete piles, 3- built-in fittings, 4- waterstop members, 5- anchoring pieces, 6- built-in fitting methods Orchid, 7- walls top, 8- stake tops, 9- displacement transducers, 10- tube members, 11- cement sand beds, 12- prefabricated thermal insulation mortar soft boards, 13- Prefabricated waterproof soft board, 14a, 14b- bearing element, 15- centralizers, 16- cement mortar, 17- annular construction members, B- ground-connecting-wall thickness, L- ground-connecting-wall length, D- pile diameters, d- piling walls occlusion section diameter, D1- adjoining diameter, HWall- ground-connecting-wall height, HStake- perfusion Pile length.
Embodiment
The invention will be further described with the following Examples.
A kind of indoor piling wall supporting construction that embodiments of the invention are provided, including several ground-connecting-walls 1 and several perfusions Stake 2.Ground-connecting-wall 1 is formed using paddling process, churning method or press injecting method.The both sides of each ground-connecting-wall 1 are respectively arranged with perfusion Stake 2, each ground-connecting-wall 1 forms piling wall supporting construction by the connection of bored concrete pile 2;Ground-connecting-wall 1 and bored concrete pile 2 are by being embedded in the two The overlap joint occlusion of built-in fitting 3 of edge;Outer surface of the two ends of built-in fitting 3 along ground-connecting-wall 1 is horizontal-extending, and fold to be formed with advance The body normal of embedded part 3 and the built-in fitting flange 6 being parallel to each other;A waterstop member 4 is provided with built-in fitting 3;Ground-connecting-wall 1, filling Note stake 2 and the formation sealing piling wall of waterstop member 4;The side that the outside of bored concrete pile 2 is connected with ground-connecting-wall 1 is provided with one layer of cement mortar The tube members 10 for the prepackage live wire being made up of waterproof insulation material are provided with layer 11, cement sand bed 11;Ground-connecting-wall 1 and filling The high 1500mm underground space is formed between the bottom for noting stake 2, one layer of cement sand bed 11 is painted with the wall face in space, Covering is enclosed with prefabricated thermal insulation mortar soft board 12, prefabricated thermal insulation mortar soft board 12 covered with prefabricated waterproof on cement sand bed 11 Soft board 13, wherein, the prefabricated thermal insulation mortar soft board 12 and prefabricated thermal insulation mortar soft board 12 of bored concrete pile 2 and the intersection of ground-connecting-wall 1 it Between be laid with displacement transducer 9, the electric wire of connection displacement transducer 9 coated with waterproof material after from ground-connecting-wall 1 default pipe Component 10 extends to the wall top 7 of ground-connecting-wall 1.
Preferably, adjacent bored concrete pile 2 is respectively arranged with an annular construction member 17, the annular construction member 17 crosses ground-connecting-wall 1, preset in the annular construction member 17 and be equipped with bearing element 14a, 14b is filled with cement mortar 16, any axle in annular construction member 17 Hold and a centralizer 15 for being used to keep the annular space of annular construction member cement mortar stream, perfusion are provided with element 14a, 14b The elastic sealing element for sealing annular construction member 17 is additionally provided between stake 2 and ground-connecting-wall 1.In addition, in bearing element 14a, 14b Cement mortar 16 is also filled with, by the cement mortar 16 of bearing element 14a, 14b part, ground-connecting-wall 1 and superstructure can be transmitted Power and torque between wall.
Preferably, being also associated with the anchoring piece 5 extended along ground-connecting-wall direction on built-in fitting 3;Waterstop member 4 is water-stopping steel Plate, its centre position by being fixedly welded on built-in fitting 3.
Preferably, steel plate for sealing water is 5 × 50 steel plate for sealing water;Anchoring piece 5 includes anchor bar and high polymer material is made Component;Anchoring piece 5 is symmetrically welded in the both sides of waterstop member 4;The length of the main body of built-in fitting 3 is mutually fitted with the thickness of ground-connecting-wall Should, the length of built-in fitting flange 6 is more than or equal to 20mm.
Preferably, supporting construction can according to site condition, geological conditions and construction requirement, can shape become broken line type And/or turning type.
Preferably, ground-connecting-wall thickness B is 700mm~900mm;The long L of ground-connecting-wall wall is 5000mm~7000mm.
Preferably, ground-connecting-wall thickness B is 800mm;The long L of ground-connecting-wall wall is 6000mm;Pile diameter D is more than or equal to ground Connect wall thickness B+400mm.
Preferably, ground-connecting-wall is more than or equal to 200mm with the length for being engaged section d of bored concrete pile;Adjacent ground-connecting-wall and perfusion Adjoining diameter D between the occlusion section of stake1=1/2 pile diameter D- ground-connecting-walls are engaged section d with bored concrete pile.
Preferably, the wall top 7 of ground-connecting-wall 1 is consistent with the absolute altitude of stake top 8 of bored concrete pile 2.
A kind of construction method of indoor piling wall supporting construction, comprises the following steps:(1) preparation of construction, smooth construction site; (2) the construction line-putting:According to job site, construction Survey Control point and bench mark are laid, periphery axis be accurately positioned to put Sample;(3) filling pile construction:Drilled by the operating type of bored concrete pile, design bottom absolute altitude, form the stake for irrigating the bored concrete pile Hole, bored concrete pile is squeezed into stake holes;(4) bored concrete pile is conserved:Its intensity level is allowed to reach 75% design load;(5) in two adjacent fillings The construction of ground-connecting-wall is carried out between note stake;(6) treat that wall and bored concrete pile reach predetermined value, in ground-connecting-wall and bored concrete pile connection disposal Enter to pre-install the tube members of live wire;(7) on underground space exterior wall and be sequentially placed cement sand bed, prefabricated thermal insulation mortar soft board, Displacement transducer and prefabricated waterproof soft board.
A kind of indoor piling wall supporting construction that embodiments of the invention are provided, itself and the ground-connecting-wall supporting in correlation technique Structure is compared, and stack pile plane stiffness improves more than 18%;In addition, stake, wall node are rationally, easy construction, it is ensured that ground is connected Wall joint quality, effectively eliminates the common quality defect of ground-connecting-wall joint.Embodiments of the invention additionally provide one kind and are applied to The construction technology of the present invention, due to the construction technology of bored concrete pile and ground-connecting-wall with maturation, therefore present invention construction is simple, using elder generation Construction stake, ground-connecting-wall of constructing afterwards, ground-connecting-wall construction can continuously construct without job-hopping construction.Further, since being provided with displacement biography Sensor, therefore, when stake and/or wall occur slight mobile, displacement transducer can transfer information to mobile terminal, achievable pair The real-time monitoring of piling wall supporting construction, to prevent the generation of potential danger.Due to being set in the bored concrete pile and ground-connecting-wall of the present invention There is the bearing element of dual reinforcing function, and centralizer is provided with bearing element, centralizer can ensure that where bearing element Cement mortar filling gap in annular construction member, therefore, not only strengthens piling wall supporting construction, more ensure that the smooth of construction Carry out.The cost of bored concrete pile of the present invention is lower than ground-connecting-wall, and piling wall combination support construction total cost is relatively low, substantial amounts of can save Manpower and materials cost, can be widely popularized applicable.
Finally it should be noted that the above embodiments are merely illustrative of the technical solutions of the present invention, rather than to present invention guarantor The limitation of scope is protected, although being explained with reference to preferred embodiment to the present invention, one of ordinary skill in the art should Work as understanding, technical scheme can be modified or equivalent substitution, without departing from the reality of technical solution of the present invention Matter and scope.

Claims (9)

1. a kind of indoor piling wall supporting construction, it is characterised in that:Including ground-connecting-wall (1) and bored concrete pile (2);The ground-connecting-wall (1) Both sides be respectively arranged with bored concrete pile (2), the ground-connecting-wall (1) forms piling wall supporting construction by bored concrete pile (2) connection;It is described Ground-connecting-wall (1) and bored concrete pile (2) overlap occlusion by being embedded in the built-in fitting (3) of the two edge;The two of the built-in fitting (3) End is horizontal-extending along the outer surface of the ground-connecting-wall (1), and folds the body normal to be formed with the built-in fitting (3) and mutually put down Capable built-in fitting flange (6);A waterstop member (4) is provided with the built-in fitting (3);The ground-connecting-wall (1), bored concrete pile (2) With waterstop member (4) formation sealing piling wall;
The outer surface for the side that the bored concrete pile (2) is connected with ground-connecting-wall (1) is provided with cement sand bed (11), cement sand bed (11) tube members (10) for the prepackage live wire being made up of waterproof insulation material are provided with;The ground-connecting-wall (1) and bored concrete pile Bottom between form the high 1500mm underground space, one layer of cement sand bed is painted with the wall face in the space (11), covering is enclosed with prefabricated thermal insulation mortar soft board (12), prefabricated thermal insulation mortar soft board (12) overlying on cement sand bed (11) Be stamped prefabricated waterproof soft board (13), wherein, the prefabricated thermal insulation mortar soft board (12) of bored concrete pile (2) and ground-connecting-wall (1) intersection and Displacement transducer (9), the electric wire waterproof material of connection displacement transducer (9) are laid between prefabricated thermal insulation mortar soft board (12) Default tube members (10) extend to the wall top (7) of ground-connecting-wall (1) from ground-connecting-wall (1) after cladding;
The adjacent bored concrete pile (2) is respectively arranged with an annular construction member (17), and the annular construction member (17) crosses ground-connecting-wall (1), preset in the annular construction member (17) and be equipped with bearing element (14a, 14b), cement is filled with the annular construction member (17) A ring for being used to keep annular construction member cement mortar stream is provided with mortar (16), any bearing element (14a, 14b) The centralizer (15) in shape space, is additionally provided between the bored concrete pile (2) and ground-connecting-wall (1) for sealing the annular construction member (17) elastic sealing element.
2. a kind of indoor piling wall supporting construction according to claim 1, it is characterised in that also connect on the built-in fitting (3) The anchoring piece (5) extended along ground-connecting-wall direction is connected to, the waterstop member (4) is steel plate for sealing water, and it is by being fixedly welded on State the centre position of built-in fitting (3).
3. a kind of indoor piling wall supporting construction according to claim 2, it is characterised in that the steel plate for sealing water is 5 × 50 Steel plate for sealing water;The anchoring piece (5) includes the component that anchor bar and high polymer material are made;Anchoring piece (5) balanced welding It is connected to the both sides of the waterstop member (4);The length of the main body of the built-in fitting (3) and the thickness of ground-connecting-wall are adapted, described The length of built-in fitting flange (6) is more than or equal to 20mm.
4. a kind of indoor piling wall supporting construction according to claim 1, it is characterised in that the supporting construction is according to place Condition, geological conditions and construction requirement, can shape become broken line type and/or turning type.
5. a kind of indoor piling wall supporting construction according to claim 1, it is characterised in that ground-connecting-wall thickness (B) is 700mm ~900mm;Ground-connecting-wall wall length (L) is 5000mm~7000mm.
6. a kind of indoor piling wall supporting construction according to claim 5, it is characterised in that the ground-connecting-wall thickness (B) be 800mm;The ground-connecting-wall wall length (L) is 6000mm;Pile diameter (D) is more than or equal to ground-connecting-wall thickness (B)+400mm.
7. a kind of indoor piling wall supporting construction according to claim 1, it is characterised in that ground-connecting-wall is engaged with bored concrete pile The length of section (d) is more than or equal to 200mm;Adjoining diameter (the D being engaged between section of the adjacent ground-connecting-wall and bored concrete pile1)=l/ 2 pile diameters (D)-ground-connecting-wall is engaged section (d) with bored concrete pile.
8. a kind of indoor piling wall supporting construction according to claim 1, it is characterised in that the wall top of the ground-connecting-wall (1) (7) it is consistent with stake top (8) absolute altitude of bored concrete pile (2).
9. the construction method for the supporting construction described in claim 1, it is characterised in that comprise the following steps:
(1) preparation of construction, smooth construction site;(2) the construction line-putting:According to job site, construction Survey Control point and water are laid On schedule, periphery axis is carried out being accurately positioned setting-out;(3) filling pile construction:Drilled by the operating type of bored concrete pile, design bottom mark Height, forms the stake holes for irrigating the bored concrete pile, bored concrete pile is squeezed into stake holes;(4) bored concrete pile is conserved:Its intensity level is allowed to reach To 75% design load;(5) construction of ground-connecting-wall is carried out between two adjacent bored concrete piles;(6) treat that wall and bored concrete pile reach pre- Definite value, the tube members of prepackage live wire are inserted in ground-connecting-wall and bored concrete pile junction;(7) on underground space exterior wall and it is sequentially placed Cement sand bed, prefabricated thermal insulation mortar soft board, displacement transducer and prefabricated waterproof soft board.
CN201610235951.6A 2016-04-15 2016-04-15 A kind of indoor piling wall supporting construction and its construction method Active CN105804090B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610235951.6A CN105804090B (en) 2016-04-15 2016-04-15 A kind of indoor piling wall supporting construction and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610235951.6A CN105804090B (en) 2016-04-15 2016-04-15 A kind of indoor piling wall supporting construction and its construction method

Publications (2)

Publication Number Publication Date
CN105804090A CN105804090A (en) 2016-07-27
CN105804090B true CN105804090B (en) 2017-10-27

Family

ID=56459305

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610235951.6A Active CN105804090B (en) 2016-04-15 2016-04-15 A kind of indoor piling wall supporting construction and its construction method

Country Status (1)

Country Link
CN (1) CN105804090B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110284506A (en) * 2019-05-22 2019-09-27 上海港城建筑安装工程有限公司 A kind of foundation pit enclosure method for the expansion construction that deep basal pit is cheated to shallow foundation
CN110258576B (en) * 2019-05-28 2021-04-09 安徽省公路桥梁工程有限公司 Construction method of foundation pit enclosure support system
CN110485431A (en) * 2019-07-24 2019-11-22 青岛理工大学 A kind of interlocking pile combines foundation pit supporting construction with ground-connecting-wall

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101435198A (en) * 2008-12-23 2009-05-20 中铁二院工程集团有限责任公司 Deep pit support reinforcing anti-seepage water stop composite structure
CN103669402A (en) * 2013-12-25 2014-03-26 华东建筑设计研究院有限公司 Pile and wall integrated structure combining outer wall of basement body and guard pile
CN103790185A (en) * 2014-01-29 2014-05-14 中国航空规划建设发展有限公司 Shock insulation groove enclosure wall for deep foundation shock insulation structure and constructing method of shock insulation groove enclosure wall
CN203821412U (en) * 2014-04-17 2014-09-10 广东省基础工程公司 Supporting structure with scattered row piles and continuous walls
CN104818728A (en) * 2015-04-08 2015-08-05 山东大学 Permanent supporting system with basement floor and supporting piles capable of working together

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0813495A (en) * 1994-06-29 1996-01-16 Maeda Corp Earth retaining wall and method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101435198A (en) * 2008-12-23 2009-05-20 中铁二院工程集团有限责任公司 Deep pit support reinforcing anti-seepage water stop composite structure
CN103669402A (en) * 2013-12-25 2014-03-26 华东建筑设计研究院有限公司 Pile and wall integrated structure combining outer wall of basement body and guard pile
CN103790185A (en) * 2014-01-29 2014-05-14 中国航空规划建设发展有限公司 Shock insulation groove enclosure wall for deep foundation shock insulation structure and constructing method of shock insulation groove enclosure wall
CN203821412U (en) * 2014-04-17 2014-09-10 广东省基础工程公司 Supporting structure with scattered row piles and continuous walls
CN104818728A (en) * 2015-04-08 2015-08-05 山东大学 Permanent supporting system with basement floor and supporting piles capable of working together

Also Published As

Publication number Publication date
CN105804090A (en) 2016-07-27

Similar Documents

Publication Publication Date Title
CN103572755B (en) Prestressed concrete prefabricated pile
CN109323049B (en) Sleeve type water pipe applied to crossing bridge and installation and construction method thereof
CN103205964B (en) Cast-in-place pile construction method using steel pipe column splicing piles
CN206928305U (en) A kind of rigid passive area buttress type supporting construction
CN206916753U (en) A kind of water sealing structure of diaphram wall and its seam crossing
CN105804090B (en) A kind of indoor piling wall supporting construction and its construction method
CN209636826U (en) Rich water sand and gravel stratum foundation pit water sealing structure
CN201538975U (en) Seepage-proofing joint of underground continuous wall
CN101575859B (en) Anti-seepage joint of underground continuous walls and construction method thereof
CN108118689B (en) Prefabricated underground diaphragm wall capable of being partially recycled, lifting appliance and construction method
CN105862875A (en) Support structure and construction method thereof
CN102220764B (en) Construction method of deep foundation pit bracing system
CN204825922U (en) Interlock stake envelope
CN203559419U (en) Prestressed concrete precast pile
CN108221954B (en) Easy-to-detach prefabricated underground diaphragm wall, lifting appliance and construction method
CN212508306U (en) Underground shaft assembling and supporting structure
CN205591210U (en) Formula cast member and construction assembly are spliced to underground
CN104652420A (en) Sinking pipe soil withdrawing and cast-in-place rectangular supporting pile diaphragm wall and construction method thereof
CN206495218U (en) Foundation pit supporting construction
CN106088762A (en) The prefabricated assembled circular underground granary of a kind of insertion slot type encased steel plate
CN206722402U (en) Waterproofing for basement moulding wall formwork erecting structure
CN106149729A (en) A kind of building foundation pit quaternity circular section interlocking pile supporting construction
CN204780965U (en) Complicated geology and existing system construction structures that struts of environment access subway
CN216515734U (en) Box culvert structure for underneath passing existing railway engineering
CN202007407U (en) Deep foundation pit supporting system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Wang Zhilong

Inventor before: Xiao Rui

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20170117

Address after: 330001 Jianshe Road, Jiangxi, No. 173,

Applicant after: JIANGXI THE SECOND CONSTRUCTION CO., LTD.

Address before: Zhenhai District 315202 Zhejiang city of Ningbo Province Rong Luo Road No. 372

Applicant before: Xiao Rui

CB03 Change of inventor or designer information

Inventor after: Wang Zhilong

Inventor after: Zhou Jun

Inventor after: Zhou Zhe

Inventor after: Xu Bei

Inventor after: Yuan Linna

Inventor after: Fan Haifei

Inventor after: Shi Lin

Inventor before: Wang Zhilong

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20170920

Address after: 330001 Jianshe Road, Jiangxi, No. 173,

Applicant after: JIANGXI THE SECOND CONSTRUCTION CO., LTD.

Applicant after: Jiangxi construction Refco Group Ltd