CN203701560U - Suspension hanging basket for high-altitude roofing inner plate construction - Google Patents

Suspension hanging basket for high-altitude roofing inner plate construction Download PDF

Info

Publication number
CN203701560U
CN203701560U CN201320892703.0U CN201320892703U CN203701560U CN 203701560 U CN203701560 U CN 203701560U CN 201320892703 U CN201320892703 U CN 201320892703U CN 203701560 U CN203701560 U CN 203701560U
Authority
CN
China
Prior art keywords
hanging basket
altitude
suspension cable
roof
suspension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320892703.0U
Other languages
Chinese (zh)
Inventor
刘爱森
陈文�
魏忠国
郑锦泉
王乾锁
李彦希
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Center International Group Co Ltd
Original Assignee
Center International Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Center International Group Co Ltd filed Critical Center International Group Co Ltd
Priority to CN201320892703.0U priority Critical patent/CN203701560U/en
Application granted granted Critical
Publication of CN203701560U publication Critical patent/CN203701560U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a suspension hanging basket for high-altitude roofing inner plate construction, which comprises a frame-type hanging basket (1) hung under the high-altitude roofing inner plate and a hanging basket suspension cable (2), wherein, two ends of the hanging basket suspension cable (2) are fixed to a roofing steel beam (3) on two ends of a main body structure; a suspension ring apparatus (4) is set on the hanging basket (1); the hanging basket (1) is hung to the hanging basket suspension cable (2) through the suspension ring apparatus (4); the hanging basket (1) is set along the width direction of the high-altitude roofing (5), and the length and size is less than or equal to the length and size of the roofing steel beam (3). According to the utility model, the hanging basket is set in normal state, multi groups of workers can be carried for construction, therefore construction efficiency is obviously improved.

Description

A kind of high-altitude roof inner slab construction hanging basket
Technical field
The utility model relates to steel work technical field, more particularly, relates to a kind of high-altitude roof inner slab construction hanging basket.
Background technology
In field of steel structure, super large steel-structure factory building is increasing, and roof inner slab terrain clearance is also more and more higher, and its roof inner slab difficulty of construction is increasing; Because roof inner slab is on girder steel, below roof purline, traditional ground moving operating platform can not meet construction needs and safe handling requirement, has seriously restricted construction speed, has greatly increased construction cost.
A kind of high-altitude roof inner slab construction hanging basket is disclosed in Chinese patent literature CN202767494U, it is characterized in that arranging: a hanging basket suspension cable, be that the two ends of wire rope are fixedly connected on the steel roof joist at agent structure two ends by annular snap respectively, form hanging basket suspension cable with twice steel roof joist and the wire rope being connected to therebetween; One frame type hanging basket, is provided with suspension ring in the periphery of hanging basket, and suspension ring are hung on hanging basket suspension cable by inverted " U " shape card, and can on hanging basket suspension cable, slide.The construction that the utility model can make super large steel structural plant roof inner panel is more quick, safety.
Realize in process of the present utility model, inventor finds that prior art at least exists following problem:
1, the hanging basket in above-mentioned document only can hold a people or two people, in whole work progress, need multiple such hanging baskets, personnel only can carry out constructing operation in certain area, and the harmony between the constructor on adjacent two hanging baskets is poor, therefore can affect construction speed and efficiency of construction.
2, because its volume is little, the stability of personnel in the time of work high above the ground is poor, once hanging basket goes wrong, can seriously jeopardize constructor's life security.
Utility model content
In order to solve the problem of prior art, improve constructor's safety and efficiency of construction, the utility model provides a kind of high-altitude roof inner slab construction hanging basket.
Described technical scheme is as follows:
A kind of high-altitude roof inner slab construction hanging basket, comprise the frame type hanging basket and the one group of hanging basket suspension cable that are arranged at roof inner slab below, high-altitude, the two ends of described hanging basket suspension cable are fixed on the steel roof joist at agent structure two ends, described hanging basket is provided with hoisting ring device, described hanging basket hangs on described hanging basket suspension cable by hoisting ring device, described hanging basket is along the width setting of high-altitude roofing, and its length dimension is less than or equal to the length dimension of described steel roof joist.
Described hanging basket suspension cable is provided with many, and each described hanging basket suspension cable is parallel interval setting, and the two ends of described hanging basket suspension cable are individually fixed on the steel roof joist that is positioned at agent structure two ends.
The middle part of each described hanging basket suspension cable is respectively equipped with the suspension lifting rope for supporting each described hanging basket suspension cable, and the other end of described suspension lifting rope is fixedly connected with the steel roof joist being positioned in agent structure of its top.
Along being also provided with the lifeline for hanging construction safety band on the whole length direction of described hanging basket, the two ends of described lifeline are mounted slidably in being positioned on roofing tie-rod roof inner slab below and near described steel roof joist two ends of described high-altitude.
The middle part of described lifeline is mounted slidably in being positioned on the roofing tie-rod of below, roof inner slab middle part, described high-altitude.
The U-shaped frame construction that described hanging basket is formed by steel-pipe welding, its bottom is provided with hanging basket plate.
Described hoisting ring device comprises the suspension ring that are placed on described hanging basket suspension cable and the steel wire pocket rope being connected with described suspension ring, described steel wire pocket rope arranges along the bottom of described hanging basket, its two ends are stretched out along the both sides of described hanging basket and are fastened with the steel pipe of described hanging basket upper end, and the two ends of described steel wire pocket rope are fixedly connected with described suspension ring respectively.
On described hanging basket, be also provided with the drive unit for driving described hanging basket to move along described hanging basket suspension cable.
Described drive unit is Chain block, and its length direction along described hanging basket at least arranges one, and one end of described Chain block is connected with described hanging basket, and its other end is fixed on the steel roof joist of described agent structure one end by hanging lifting rope.
The beneficial effect that the technical scheme that the utility model provides is brought is:
(1) the utility model is set to elongatedly by hanging basket, and constructor can walk up and down in hanging basket, and convenient construction can be realized the synchronous propelling construction of whole roofing, and efficiency of construction is high.
(2) by the whole length direction of hanging basket, lifeline being set, lifeline adopts and separates setting with hanging basket, and in construction, constructor hangs over safety belt in lifeline, and in the time that hanging basket goes wrong, lifeline can ensure constructor's safety.
(3) hanging basket uses steel wire pocket rope to be connected with suspension ring, and steel wire pocket rope is connected with the upper end steel pipe of hanging basket, while steel wire pocket rope employing from bottom by hanging basket pocket one enclose, can play like this dual fail-safe effect, can effectively prevent hanging basket to drop.
Accompanying drawing explanation
In order to be illustrated more clearly in the technical scheme in the utility model embodiment, below the accompanying drawing of required use during embodiment is described is briefly described, apparently, accompanying drawing in the following describes is only embodiment more of the present utility model, for those of ordinary skills, do not paying under the prerequisite of creative work, can also obtain according to these accompanying drawings other accompanying drawing.
Fig. 1 is high-altitude provided by the utility model roofing overall structure schematic diagram;
Fig. 2 is the schematic cross-section shown in Fig. 1;
Fig. 3 is the barrel structure schematic diagram in Fig. 1;
Fig. 4 is the hanging basket cross section structure schematic diagram shown in Fig. 3.
In figure:
1-hanging basket, 11-steel pipe, 12-hanging basket plate; 2-hanging basket suspension cable; 3-steel roof joist; 4-hoisting ring device, 41-suspension ring, 42-steel wire pocket rope; 5-high-altitude roofing; 6-Chain block; 7-hangs lifting rope; 8-lifeline; 9-roofing tie-rod; 10-roofing outside plate; 20-roof inner slab; 30-agent structure.
The specific embodiment
For making the purpose of this utility model, technical scheme and advantage clearer, below in conjunction with accompanying drawing, the utility model embodiment is described in further detail.
The utility model provides a kind of high-altitude roof inner slab construction hanging basket, and as depicted in figs. 1 and 2, high-altitude roofing 5 is wherein made up of roof inner slab 20, roofing outside plate 10, agent structure 30, steel roof joist 3 of being connected with agent structure 30 etc.; Hanging basket comprises the frame type hanging basket 1 and the one group of hanging basket suspension cable 2 that are arranged at roof inner slab below, high-altitude, on the parallel steel roof joist 3 that is fixed on agent structure two ends in two ends of hanging basket suspension cable 2, hanging basket 1 is provided with hoisting ring device 4, hanging basket 1 hangs on hanging basket suspension cable 2 by hoisting ring device 4, hanging basket 1 is along the width setting of high-altitude roofing 5, and its length dimension is less than or equal to the length dimension of steel roof joist 3.Hanging basket 1 in Fig. 1 is along the whole width setting of high-altitude roofing.The parallel interval on the whole width of agent structure of hanging basket suspension cable 2 is wherein provided with many, the two ends of every hanging basket suspension cable 2 are all crossed in the length of whole high-altitude roofing 5, simultaneously in order not make the sag of hanging basket suspension cable 2 excessive, can be provided for suspending in midair at the middle part of high-altitude roofing the suspension lifting rope 7 of hanging basket suspension cable 2, also can hanging basket suspension cable 2 be suspended in midair interval piecemeal, avoid hanging basket suspension cable excessive sag.
For the ease of driving hanging basket 1, hanging basket 1 can be moved forward along hanging basket suspension cable 2, on hanging basket 1, be also provided with the drive unit for driving described hanging basket 1 to move along hanging basket suspension cable 2.The drive unit here can be selected Chain block 6, also can select other drive unit, as pull mode.Chain block 6 wherein at least arranges one along the length direction of hanging basket 1, and one end of Chain block 6 is connected with hanging basket 1, and its other end is fixed on the steel roof joist 3 of agent structure 30 one end by hanging lifting rope 7.
In order to guarantee constructor's construction safety, along being also provided with the lifeline 8 for hanging construction safety band on the whole length direction of hanging basket 1, the two ends of lifeline 8 are mounted slidably in being positioned on high-altitude roofing 5 roofing tie-rod 9 inner panel below and near steel roof joist 3 two ends.Lifeline 8 is the wire rope that are connected on roof truss tie-rod, and wire rope does not contact with hanging basket, in the time that people constructs on hanging basket, safety belt is hung in lifeline 8, and the problem if hanging basket occurs dropping etc., people can be hung in lifeline by safety belt, is unlikely to fall.
For the larger steel roof joist 3 of span, avoid the sag at lifeline 8 middle parts excessive, the middle part of lifeline 8 can be mounted slidably in being positioned on the roofing tie-rod 9 of high-altitude roofing 5 inner panel 20 belows, middle part.
As shown in Figure 3 and Figure 4, hanging basket 1 is wherein welded the U-shaped frame construction forming by steel pipe 11, and its bottom is provided with hanging basket plate 12.
Hoisting ring device 4 shown in Fig. 4 comprises the suspension ring 41 that are placed on hanging basket suspension cable 2 and the steel wire pocket rope 42 being connected with suspension ring 41, steel wire pocket rope 42 pockets are placed in the bottom of hanging basket 1, the two ends of steel wire pocket rope 42 are stretched out along the both sides of hanging basket 1 and are fastened with the steel pipe 11 of hanging basket 1 upper end, and the two ends of steel wire pocket rope 42 are fixedly connected with suspension ring 41 respectively.Hanging basket uses steel wire pocket rope 42 to be connected with suspension ring 41, and steel wire pocket rope 42 is connected with the steel pipe 11 of hanging basket 1, while steel wire pocket rope 42 from bottom by hanging basket 1 pocket one enclose, can play like this dual fail-safe effect, effectively prevent hanging basket 1 to drop.
The utility model is applicable to the higher and irregular project of facility floor of factory building eaves height, can multi-span, organize people more and construct simultaneously, and construction efficiency is significantly improved.
Above-mentioned the utility model embodiment sequence number, just to describing, does not represent the quality of embodiment.
The foregoing is only preferred embodiment of the present utility model, not in order to limit the utility model, all within spirit of the present utility model and principle, any modification of doing, be equal to replacement, improvement etc., within all should being included in protection domain of the present utility model.

Claims (1)

1. a high-altitude roof inner slab construction hanging basket, comprise the frame type hanging basket (1) and the one group of hanging basket suspension cable (2) that are arranged at roof inner slab below, high-altitude, the two ends of described hanging basket suspension cable (2) are fixed on the steel roof joist (3) at agent structure (30) two ends, described hanging basket (1) is provided with hoisting ring device (4), described hanging basket (1) hangs on described hanging basket suspension cable (2) by hoisting ring device (4), it is characterized in that, described hanging basket (1) is along the width setting of high-altitude roofing (5), its length dimension is less than or equal to the length dimension of described steel roof joist (3).
2. roof inner slab construction hanging basket in high-altitude according to claim 1, it is characterized in that, described hanging basket suspension cable (2) is provided with many, each described hanging basket suspension cable (2) is parallel interval setting, and the two ends of described hanging basket suspension cable (2) are individually fixed on the steel roof joist (3) that is positioned at agent structure (30) two ends.
3. roof inner slab construction hanging basket in high-altitude according to claim 2, it is characterized in that, the middle part of each described hanging basket suspension cable (2) is respectively equipped with the suspension lifting rope (7) for supporting each described hanging basket suspension cable, and the other end of described suspension lifting rope (7) is fixedly connected with the steel roof joist (3) being positioned in agent structure (30) of its top.
4. roof inner slab construction hanging basket in high-altitude according to claim 1 and 2, it is characterized in that, along the lifeline (8) being also provided with on the whole length direction of described hanging basket (1) for hanging construction safety band, the two ends of described lifeline (8) are mounted slidably in being positioned on roofing tie-rods (9) described high-altitude roofing (5) inner panel below and near described steel roof joist (3) two ends.
5. roof inner slab construction hanging basket in high-altitude according to claim 4, is characterized in that, the middle part of described lifeline (8) is mounted slidably in being positioned on the roofing tie-rod (9) of below, described high-altitude roofing (5) inner panel middle part.
6. roof inner slab construction hanging basket in high-altitude according to claim 1, is characterized in that, described hanging basket (1) is welded the U-shaped frame construction forming by steel pipe (11), and its bottom is provided with hanging basket plate (12).
7. roof inner slab construction hanging basket in high-altitude according to claim 6, it is characterized in that, described hoisting ring device (4) comprises the suspension ring (41) that are placed on described hanging basket suspension cable (2) and the steel wire pocket rope (42) being connected with described suspension ring (41), described steel wire pocket rope (42) arranges along the bottom of described hanging basket (1), its two ends are stretched out along the both sides of described hanging basket (1) and are fastened with the steel pipe (11) of described hanging basket (1) upper end, and the two ends of described steel wire pocket rope (42) are fixedly connected with described suspension ring (41) respectively.
8. roof inner slab construction hanging basket in high-altitude according to claim 1, is characterized in that, is also provided with for driving described hanging basket (1) along the mobile drive unit of described hanging basket suspension cable (2) on described hanging basket (1).
9. roof inner slab construction hanging basket in high-altitude according to claim 8, it is characterized in that, described drive unit is Chain block (6), its length direction along described hanging basket (1) at least arranges one, one end of described Chain block (6) is connected with described hanging basket (1), and its other end is fixed on the steel roof joist (3) of described agent structure one end by hanging lifting rope (7).
CN201320892703.0U 2013-12-31 2013-12-31 Suspension hanging basket for high-altitude roofing inner plate construction Expired - Lifetime CN203701560U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320892703.0U CN203701560U (en) 2013-12-31 2013-12-31 Suspension hanging basket for high-altitude roofing inner plate construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320892703.0U CN203701560U (en) 2013-12-31 2013-12-31 Suspension hanging basket for high-altitude roofing inner plate construction

Publications (1)

Publication Number Publication Date
CN203701560U true CN203701560U (en) 2014-07-09

Family

ID=51052016

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320892703.0U Expired - Lifetime CN203701560U (en) 2013-12-31 2013-12-31 Suspension hanging basket for high-altitude roofing inner plate construction

Country Status (1)

Country Link
CN (1) CN203701560U (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104358393A (en) * 2014-10-24 2015-02-18 中铁航空港建设集团北京有限公司 Horizontal moving platform hung at high altitude
CN104631810A (en) * 2015-01-15 2015-05-20 中誉远发国际建设集团有限公司 High-altitude movable hanging basket system and construction method thereof
CN104963495A (en) * 2015-06-05 2015-10-07 中国十七冶集团有限公司 Suspension hanging basket for installation of roof surface bottom layer color plate
CN105155832A (en) * 2015-06-17 2015-12-16 中建钢构有限公司 Hanging basket device and moving method thereof
CN105369741A (en) * 2015-12-14 2016-03-02 中交一公局第三工程有限公司 Suspension-type movable operation platform for constructing catwalk face net
CN108190808A (en) * 2018-02-13 2018-06-22 黑龙江省建筑安装集团有限公司 The anti-furred ceiling high-altitude slide apparatus of color steel and anti-ceiling construction engineering method
CN108468433A (en) * 2018-04-12 2018-08-31 陈年康 A kind of construction tool of workshop metal Roof inner panel
CN108755965A (en) * 2018-06-21 2018-11-06 浙江大学 One kind is greatly across suspension cable-tied arch structural system and building structure
CN109083395A (en) * 2018-08-14 2018-12-25 浙江中南建设集团钢结构有限公司 A kind of Excitations for Long Span Suspension operating platform and its erection method
CN109958219A (en) * 2019-04-11 2019-07-02 中国十七冶集团有限公司 A kind of complex environment roofing truss lower part liner plate suspension cable installation method

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104358393A (en) * 2014-10-24 2015-02-18 中铁航空港建设集团北京有限公司 Horizontal moving platform hung at high altitude
CN104631810A (en) * 2015-01-15 2015-05-20 中誉远发国际建设集团有限公司 High-altitude movable hanging basket system and construction method thereof
CN104963495B (en) * 2015-06-05 2017-07-14 中国十七冶集团有限公司 A kind of hanging basket for installing roofing bottom colored steel
CN104963495A (en) * 2015-06-05 2015-10-07 中国十七冶集团有限公司 Suspension hanging basket for installation of roof surface bottom layer color plate
CN105155832A (en) * 2015-06-17 2015-12-16 中建钢构有限公司 Hanging basket device and moving method thereof
CN105369741B (en) * 2015-12-14 2017-04-19 中交一公局第三工程有限公司 Suspension-type movable operation platform for constructing catwalk face net
CN105369741A (en) * 2015-12-14 2016-03-02 中交一公局第三工程有限公司 Suspension-type movable operation platform for constructing catwalk face net
CN108190808A (en) * 2018-02-13 2018-06-22 黑龙江省建筑安装集团有限公司 The anti-furred ceiling high-altitude slide apparatus of color steel and anti-ceiling construction engineering method
CN108190808B (en) * 2018-02-13 2024-04-12 黑龙江省建筑安装集团有限公司 Color steel plate anti-suspended ceiling high-altitude sliding device and anti-suspended ceiling construction method
CN108468433A (en) * 2018-04-12 2018-08-31 陈年康 A kind of construction tool of workshop metal Roof inner panel
CN108755965A (en) * 2018-06-21 2018-11-06 浙江大学 One kind is greatly across suspension cable-tied arch structural system and building structure
CN109083395A (en) * 2018-08-14 2018-12-25 浙江中南建设集团钢结构有限公司 A kind of Excitations for Long Span Suspension operating platform and its erection method
CN109083395B (en) * 2018-08-14 2024-05-10 浙江中南绿建科技集团有限公司 Large-span suspension cable operation platform and erecting method thereof
CN109958219A (en) * 2019-04-11 2019-07-02 中国十七冶集团有限公司 A kind of complex environment roofing truss lower part liner plate suspension cable installation method

Similar Documents

Publication Publication Date Title
CN203701560U (en) Suspension hanging basket for high-altitude roofing inner plate construction
CN202767494U (en) Hanging basket for high-altitude roof inner plate construction
CN107178035B (en) Bridge side high altitude operation Electronic control stage apparatus
CN204751997U (en) Planer -type cantilever crane device
CN206486233U (en) A kind of installing engineering Special elevator
CN204391605U (en) A kind of helicopter live line working plug-in type hanging basket
CN204689430U (en) To Construction of Silo movable hoisting device
CN205934718U (en) Travelling cradle device is used in bridge construction
CN203755638U (en) Suspending slippage type high-altitude inverted oblique plane operation hanging basket
CN211622534U (en) Movable cantilever operation platform
CN103274310A (en) Self-lifting type cableway transporting device
CN205932925U (en) Electric precipitation removes anode plate hoist device
CN210856930U (en) Maintenance system of cable-stay bridge inverted Y-shaped tower column
CN205472340U (en) People's passageway on instrument formula tower crane
CN205011219U (en) Assembly type structure precast shear wall's multi -purpose hoist and mount balance beam
CN204111203U (en) A kind of connection structure of passing through formula double trolley
CN103643790B (en) It is applicable to the self-crawling type operating platform of colossal column
CN211006334U (en) Maintenance equipment for inner side surface of inverted Y-shaped tower column of three-way movable cable-stayed bridge
CN203879021U (en) Automatic ascending and descending type modular transferring platform
CN203559573U (en) Foldable suspension of suspended platform
CN202170231U (en) Mobile pulling bar
CN201686458U (en) Movable operating platform used for quickly processing welding seam at end opening of steel box girder
CN207959894U (en) A kind of architectural engineering operation platform
CN205777594U (en) A kind of roofing large-span steel girder steel construction twin beams purlin car
CN203271161U (en) Super-high-rise building construction hoist

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20140709