CN205934718U - Movable hanging basket device for bridge construction - Google Patents
Movable hanging basket device for bridge construction Download PDFInfo
- Publication number
- CN205934718U CN205934718U CN201620865054.9U CN201620865054U CN205934718U CN 205934718 U CN205934718 U CN 205934718U CN 201620865054 U CN201620865054 U CN 201620865054U CN 205934718 U CN205934718 U CN 205934718U
- Authority
- CN
- China
- Prior art keywords
- support bar
- bridge
- fixedly connected
- bridge floor
- basket device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 18
- 230000004888 barrier function Effects 0.000 claims description 4
- 238000012423 maintenance Methods 0.000 abstract description 4
- 238000005516 engineering process Methods 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Landscapes
- Movable Scaffolding (AREA)
Abstract
The utility model provides a movable hanging basket device for bridge construction; the device comprises a track assembly, a supporting seat, a balancing weight, a working platform and a supporting frame; the counterweight block is placed on the supporting seat, one end of the supporting frame is fixedly connected with the supporting seat, the other end of the supporting frame extends towards the lower part of the outer side of the bridge deck, the other end of the supporting frame is horizontally and fixedly connected with the working platform, and the working platform extends into the lower side of the bottom of the bridge deck; the rail assembly comprises a plurality of sliding rails and a plurality of sliding blocks, the sliding rails are laid at the edge of the bridge floor, the sliding blocks are installed at the bottom of the supporting seat, and the sliding blocks are matched with the sliding rails respectively. The workman can stand and work on work platform, maintains or the maintenance operation bottom the bridge floor to control the supporting seat and remove along guide rail assembly's slide rail direction, and then drive work platform moving as a whole, make whole hanging flower basket device can continuous movement, compare hanging flower basket device among the prior art, improved workman's operation environment, promoted work efficiency, practiced thrift a large amount of construction period.
Description
Technical field
This utility model is related to a kind of nacelle device, particularly to a kind of bridge construction movable hanging basket device.
Background technology
When bridge construction or maintenance, need often to be constructed or upkeep operation in the bridge floor bottom of bridge, at present, tradition
Working hanging basket carries rope, and can only be fixed on a position construction, need reorientate when continuous construction, extremely not
Just, a large amount of construction periods are affected;And there are a large amount of potential safety hazards in operating personnel.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of easy to use, bridge construction that can continuously construct
Use movable hanging basket device.
For solving above-mentioned technical problem, this utility model provides a kind of bridge construction movable hanging basket device;
Including rail assembly, support base, balancing weight, work platformses and bracing frame;
Balancing weight is placed on support base, and bracing frame one end is fixedly connected with support base, and the bracing frame other end is to outside bridge floor
Side lower part extends, and the bracing frame other end is fixedly connected with work platformses level, and work platformses stretch on the downside of bridge floor bottom;
Rail assembly includes some slide rails and some slide blocks, and described slide rail is laid on bridge floor marginal position, described slide rail
Trend consistent with the length direction of bridge, some slide blocks are arranged on support base bottom, and some slide blocks are joined with some slide rails respectively
Close.
After such structure, workman may stand in and works on work platformses, and bridge floor bottom is keeped in repair or maintenance
Operation, and manipulate support base along the slide rail direction movement of guide assembly, and then drive work platformses to move integrally, make entirely to hang
Basket device can be with continuous moving, middle nacelle device compared to existing technology, improves the working environment of workman, improves work effect
Rate, has saved a large amount of construction periods.
For clearer understanding technology contents of the present utility model, below by this bridge construction movable hanging basket device
It is referred to as this nacelle device.
The bracing frame of this nacelle device includes some vertical first support bars, the second support bar of some levels and some
The 3rd vertical support bar, first support bar, second support bar and the 3rd support bar are one-to-one relationship;
Described first support bar lower end is fixedly connected with support base, described second support bar one end with corresponding first
Strut is fixedly connected, and the described second support bar other end is stretched out outside bridge floor and is fixedly connected with corresponding 3rd support bar,
The level height of the 3rd described support bar lower end is less than level height and described 3rd support bar lower end and the work of bridge floor bottom
Make platform side to fix, work platformses opposite side stretches on the downside of bridge floor bottom.
After such structure, the structure of bracing frame is more reasonable, reduces the impact to whole nacelle device for the bracing frame,
Avoid security incident.
Second support bar one end of this nacelle device is fixedly connected with the middle part of corresponding first support bar, described first
It is provided with flower basket bolt between strut upper end and corresponding 3rd support bar;After such structure, it is possible to reduce the second support
The stress and deformation of bar, increases the stability of bracing frame.
The work platformses of this nacelle device are formed around safety barrier and safety net;After such structure, increase this
The safety of nacelle device, prevents workman from falling from work platformses.
Brief description
Fig. 1 is the use state figure of this nacelle device.
Fig. 2 is the axonometric chart of Fig. 1.
Specific embodiment
As shown in Fig. 1 is to 2
This nacelle device includes rail assembly, 2, three pieces of balancing weights 3 of support base, work platformses 5 and bracing frame.
Rail assembly includes two slide rails 11 and eight slide blocks 12, and two slide rails 11 are laid on bridge floor 6 marginal position, every
The trend of slide rail 11 is consistent with the length direction of bridge, and eight slide blocks 12 are separately mounted to support base 2 bottom, and each slide block
12 are placed on support base 2 with corresponding slide rail 11 slide fit, three pieces of balancing weights 3.
Bracing frame includes four vertical second support bars 42 of 41, four levels of first support bar and four vertical
Three support bars 43, first support bar 41, second support bar 42 and the 3rd support bar 43 are one-to-one relationship, first support bar
41st, second support bar 42 and the 3rd support bar 43 are also all steel structure truss structure;
Four first support bar 41 lower ends are bolted with support base 2 right part, and bracing piece 46 is passed through on support base 2 right side
Bolt is fixed and first support bar 41 upper end between.
It is welded and fixed by two connecting rods 44 between four first support bar 41 upper ends, every second support bar 42 left end
It is bolted with the middle part of corresponding first support bar 41, second support bar 42 right-hand member stretches out outside bridge floor 6, every second
Strut 42 right-hand member is welded and fixed with corresponding 3rd support bar 43 upper end, every first support bar 41 upper end with corresponding 3rd
Between strut 43 upper end also by flower basket bolt 45 hinged it is ensured that connecting the two stable connection, the 3rd support bar 43 lower end is downward
Side extends, and the level height of the 3rd support bar 43 lower end is less than the level height of bridge floor 6 bottom.
Work platformses 5 are a steel structure platform, the right side of work platformses 5 respectively with four the 3rd support bar 43 lower weld
Fixing, work platformses 5 left part stretches on the downside of bridge floor 6 bottom, and exists between work platformses 5 and bridge floor 6 bottom and necessarily supply work
The space of people's work, work platformses 5 are formed around safety barrier 51 and airtight safety net (not shown), safety barrier 51
And safety net is airtight ensure that workmen's safety.
During use, workman may stand in and works on work platformses 5, and bridge floor 6 bottom is keeped in repair or maintenance work, and
Manipulate support base 2 to move along slide rail 11 direction of guide assembly, and then drive work platformses 5 to move integrally, make whole hanging basket dress
Putting can be with continuous moving, and middle nacelle device compared to existing technology improves the working environment of workman, improves work efficiency, section
About a large amount of construction periods.
It is additionally provided with special ladder 7, workman is easy to climb up and down, extremely convenient.
Above-described is only a kind of embodiment of the present utility model it is noted that ordinary skill for this area
For personnel, on the premise of without departing from this utility model principle, some modifications and improvement can also be made, these also should be regarded as
Belong to protection domain of the present utility model.
Claims (4)
1. a kind of bridge construction movable hanging basket device, it is characterized by:
Including rail assembly, support base, balancing weight, work platformses and bracing frame;
Balancing weight is placed on support base, and bracing frame one end is fixedly connected with support base, under the bracing frame other end is to outside bridge floor
Portion extends, and the bracing frame other end is fixedly connected with work platformses level, and work platformses stretch on the downside of bridge floor bottom;
Rail assembly includes some slide rails and some slide blocks, and described slide rail is laid on bridge floor marginal position, the walking of described slide rail
To consistent with the length direction of bridge, some slide blocks are arranged on support base bottom, and some slide blocks are coordinated with some slide rails respectively.
2. bridge construction according to claim 1 movable hanging basket device, is characterized in that:
Described bracing frame includes some vertical first support bars, the second support bar of some levels and some vertical 3rd
Support bar, first support bar, second support bar and the 3rd support bar are one-to-one relationship;
Described first support bar lower end is fixedly connected with support base, described second support bar one end and corresponding first support bar
It is fixedly connected, the described second support bar other end is stretched out outside bridge floor and is fixedly connected with corresponding 3rd support bar, described
The level height of the 3rd support bar lower end be less than the level height of bridge floor bottom and described 3rd support bar bottom is flat with work
Platform side is fixed, and work platformses opposite side stretches on the downside of bridge floor bottom.
3. bridge construction according to claim 2 movable hanging basket device, is characterized in that:
Described second support bar one end is fixedly connected with the middle part of corresponding first support bar, described first support bar upper end with
It is provided with flower basket bolt between corresponding 3rd support bar.
4. bridge construction according to claim 1 movable hanging basket device, is characterized in that:
Described work platformses are formed around safety barrier and safety net.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620865054.9U CN205934718U (en) | 2016-08-10 | 2016-08-10 | Movable hanging basket device for bridge construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620865054.9U CN205934718U (en) | 2016-08-10 | 2016-08-10 | Movable hanging basket device for bridge construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205934718U true CN205934718U (en) | 2017-02-08 |
Family
ID=57922454
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620865054.9U Expired - Fee Related CN205934718U (en) | 2016-08-10 | 2016-08-10 | Movable hanging basket device for bridge construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205934718U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108373126A (en) * | 2018-01-29 | 2018-08-07 | 陈细妹 | A kind of road and bridge construction tool fast lifting equipment |
CN113089477A (en) * | 2021-04-06 | 2021-07-09 | 四川川交路桥有限责任公司 | Hanging basket suspension system |
CN113502758A (en) * | 2021-08-31 | 2021-10-15 | 河南城建学院 | Hanging basket hanging device for bridge construction |
CN114481862A (en) * | 2022-01-06 | 2022-05-13 | 中国五冶集团有限公司 | Movable truss device and construction process |
-
2016
- 2016-08-10 CN CN201620865054.9U patent/CN205934718U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108373126A (en) * | 2018-01-29 | 2018-08-07 | 陈细妹 | A kind of road and bridge construction tool fast lifting equipment |
CN113089477A (en) * | 2021-04-06 | 2021-07-09 | 四川川交路桥有限责任公司 | Hanging basket suspension system |
CN113502758A (en) * | 2021-08-31 | 2021-10-15 | 河南城建学院 | Hanging basket hanging device for bridge construction |
CN114481862A (en) * | 2022-01-06 | 2022-05-13 | 中国五冶集团有限公司 | Movable truss device and construction process |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205934718U (en) | Movable hanging basket device for bridge construction | |
CN100590277C (en) | Overhead bridge type suspension scaffold | |
CN203175023U (en) | Counter weight type cantilever hanging basket device | |
CN206768611U (en) | Bridge pier hanging basket mounting operation platform | |
CN109826411A (en) | A kind of climbing frame and its operation method for building | |
CN204310644U (en) | A kind of single suspension centre cage guide installation and maintenance hanging basket | |
CN211257766U (en) | Movable operating platform with anti-overturning supporting legs | |
CN103011031A (en) | Stand column type 360-degree rotary oil tank maintenance platform | |
CN207958995U (en) | A kind of totally-enclosed flap seat of Hanging Basket convenient for adjusting installation | |
CN205604084U (en) | Hanging flower basket device of prefabricated little case roof beam construction usefulness | |
CN205777428U (en) | Elevator is from climbing platforms | |
CN210529487U (en) | Bridge and box-shaped bridge inspection device with flange plates | |
CN104278830A (en) | Integrated combined scaffold | |
CN210795684U (en) | Novel movable lifting platform | |
CN207862788U (en) | It is a kind of to be connected to the outstanding stretch-draw jack hanging apparatus filled on Hanging Basket | |
CN214713878U (en) | Tower crane cat ladder structure | |
CN104847101B (en) | Operation platform for decoration work on long cantilever positions of roofs with steel structures | |
CN204103309U (en) | A kind of composite type inspection platform | |
CN205693609U (en) | Ground photovoltaic bracket and photovoltaic module hanger bracket device are installed | |
CN204803771U (en) | High pier bridge disease of highway inspection punishment facility | |
CN106401157A (en) | Movable operation platform and high-altitude construction method | |
CN205529939U (en) | Bridge testing and maintenance platform of rope type | |
CN208305021U (en) | Cantilever type multilayer hanging cage for continuously welding ultrahigh and overlong welding seams | |
CN203394008U (en) | Suspension type hanging bracket used on plane truss | |
CN207812982U (en) | A kind of inner wall of oil tank construction hanging basket |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170208 Termination date: 20170810 |
|
CF01 | Termination of patent right due to non-payment of annual fee |