CN104631810A - High-altitude movable hanging basket system and construction method thereof - Google Patents

High-altitude movable hanging basket system and construction method thereof Download PDF

Info

Publication number
CN104631810A
CN104631810A CN201510021729.1A CN201510021729A CN104631810A CN 104631810 A CN104631810 A CN 104631810A CN 201510021729 A CN201510021729 A CN 201510021729A CN 104631810 A CN104631810 A CN 104631810A
Authority
CN
China
Prior art keywords
hanging basket
hawser
rope
hanging
pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510021729.1A
Other languages
Chinese (zh)
Other versions
CN104631810B (en
Inventor
温江
罗挺
罗京
王谷雨
王云贵
杨元伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
In the section of Construction Group Co. Ltd.
Original Assignee
ZHONGYU YUANFA INTERNATIONAL CONSTRUCTION GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHONGYU YUANFA INTERNATIONAL CONSTRUCTION GROUP Co Ltd filed Critical ZHONGYU YUANFA INTERNATIONAL CONSTRUCTION GROUP Co Ltd
Priority to CN201510021729.1A priority Critical patent/CN104631810B/en
Publication of CN104631810A publication Critical patent/CN104631810A/en
Application granted granted Critical
Publication of CN104631810B publication Critical patent/CN104631810B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The invention discloses a high-altitude movable hanging basket system and a construction method thereof and belongs to the field of construction. By the adoption of the system, reverse hanging plate construction efficiency is improved, and construction cost is reduced. By arranging a mooring rope and hanging a hanging basket through a hanging structure movably on the mooring rope, a constructor can conduct reserve hanging plate construction in the hanging basket. Furthermore, the hanging basket can be moved conveniently through a corresponding hauling cable, overall construction efficiency can be effectively improved, and construction cost can be reduced. Besides, potential safety hazards can be effectively reduced for the constructor, and construction safety is ensured. According to the system, the construction method is simple, and the system is suitable for construction of reverse hanging plates in large buildings such as stadiums and exhibition buildings.

Description

High altitude moving hanging basket system and construction method
Technical field
The present invention relates to the realm of building construction, particularly relate to the construction method of a kind of high altitude moving hanging basket system and this high altitude moving hanging basket system.
Background technology
Along with the fast development of some heavy constructions such as stadiums or exhibition hall in recent years, the span of this type of building is increasing, and easily all more than 50 meters, and its headroom is also higher, generally all more than 20 meters.And the installation of anti-boatswain chair for this type of building, because anti-boatswain chair is arranged on the below of the main structures such as steel truss usually, therefore install very inconvenient, normally adopt traditional mode of building full hall scaffold at present, because the construction location of boatswain chair anti-in this type of heavy construction is higher, therefore just higher to the stability requirement of full hall scaffold, otherwise there is larger potential safety hazard; And in order to improve the stability of full hall scaffold, the volume of scaffold can only be increased, the material requested that scaffolds erecting can be caused accordingly to increase, take excessive ground space, cause claim for eot simultaneously, cost increases; In addition, scaffold is also unfavorable for that scaffold moves, and affects efficiency of construction after increasing.
Summary of the invention
The technical problem that the present invention solves is to provide a kind of high altitude moving hanging basket system of solving the problem and its construction method, effectively can improve the efficiency of construction of anti-boatswain chair, reduces construction cost.
The technical solution adopted for the present invention to solve the technical problems is: high altitude moving hanging basket system, comprise hanging basket and building body, below the steel truss of building body, be provided with at least two parallel to each other and hawsers kept at a certain distance away, the two ends of every root hawser are fixedly connected in the side main body of building body both sides; The two ends of described hanging basket are corresponding with adjacent two hawsers respectively, and be respectively arranged with one group of hanging structure at the two ends of hanging basket, described hanging structure is hung on the hawser of respective side, and can move along hawser; Also comprise Anterior crossbite rope and rear pull rope; One end of described Anterior crossbite rope is fixed on the front of hanging basket, and the other end is connected with hanging basket; One end of described rear pull rope is fixed on the rear of hanging basket, and the other end is connected with hanging basket.
Further: the described hanger often organized lower end that hanging structure is included in the hanging basket left and right sides and arrange, to hang on same hawser and can along two of a hawser movement pulley suspension hook, two pulley suspension hooks respectively with two hanger one_to_one corresponding; Described hanging structure of often organizing also comprises two suspension rods being separately positioned on hanging basket both sides, the two ends of described suspension rod are connected with the hanger of the same side and pulley suspension hook respectively, also comprise gag lever post, described gag lever post is fixed on hanging basket, and the two ends of gag lever post connect one to one with the suspension rod of both sides respectively.
Further: described hanging structure of often organizing also comprises two U-shaped limiting cards; Described gag lever post is across above hanging basket; Two U-shaped limit fasteners are on gag lever post and be arranged on the upper end of the breast board of the hanging basket left and right sides.
Further: also comprise protective screening, described protective screening is arranged on the surrounding of hanging basket, and protective screening connects with the surrounding breast board on hanging basket body near the edge of hanging basket side.
Further: also comprise and choose net bar, described in choose net bar and have many, and be arranged on the surrounding of hanging basket; Described one end of choosing net bar is connected with hanging basket, the oblique extension of the other end, and to choose on net bar near one end of hanging basket lower than the one end away from hanging basket; Described protective screening is arranged on to be chosen on net bar, and supports by choosing net bar.
Further: described pulley suspension hook comprises housing, suspension hook, head pulley and auxiliary pulley, and described suspension hook is arranged on the lower end of housing, described head pulley is rotating to be arranged on housing, and the chute of head pulley is buckled in the top of hawser; Described auxiliary pulley is rotating to be arranged on housing, and auxiliary pulley is positioned at the below of head pulley, and the chute of auxiliary pulley is buckled in the below of hawser; One end that suspension rod is connected with pulley suspension hook hangs on suspension hook.
Further: both sides corresponding with auxiliary pulley on housing are respectively arranged with chute, be provided with slide block moving up and down in chute, the support end axle of auxiliary pulley both sides is rotating to be respectively arranged on the slide block of respective side; Also comprise elastic component, one end of described elastic component is connected with the bottom of slide block, and the other end is against the bottom of chute.
Further: also comprise auxiliary lifting rope, one end of described auxiliary lifting rope is connected with hawser, and the lower edge truss that the other end is corresponding with above hawser connects.
The construction method of above-mentioned high altitude moving hanging basket system, comprises the following steps:
A) structure of high altitude moving hanging basket system:
A) after building main body construction completes, below the steel truss of building body, the two ends of every root hawser are fixedly connected in the side main body of both sides, carry out prestressed stretch-draw simultaneously to hawser by the equally spaced many hawsers that be arranged in parallel;
B) electric hoist is set on steel truss; By electric hoist, hanging basket is winched to preset height;
C) hanging basket two ends are hung on corresponding hawser respectively by hanging structure, then remove the annexation of electric hoist and hanging basket, carry hanging basket by hawser;
D) arrange Anterior crossbite rope and rear pull rope, one end of Anterior crossbite rope is fixed on the front of hanging basket, the other end is connected with hanging basket; One end of rear pull rope is fixed on the rear of hanging basket, the other end is connected with hanging basket;
B) movement of hanging basket: can along hawser direction hanging basket moved forward or after move, corresponding following two kinds of modes respectively:
E) reach of hanging basket, unclamps the connection of rear pull rope and hanging basket, then tightens up Anterior crossbite rope, is moved forward by Anterior crossbite wire saws hanging basket; After mobile end, again Anterior crossbite rope is connected with hanging basket respectively with rear pull rope;
F) move after hanging basket, unclamp the connection of Anterior crossbite rope and hanging basket, then tighten up rear pull rope, moved backward by rear pull rope traction hanging basket; After mobile end, again Anterior crossbite rope is connected with hanging basket respectively with rear pull rope;
C) dismounting of high altitude moving hanging basket system:
G) hanging basket is moved to electric hoist place, and again electric hoist is connected with hanging basket;
H) connection of Anterior crossbite rope and rear pull rope and hanging basket is removed;
I) remove the connection of hawser and hanging basket, carry hanging basket by hoist;
J) by electric hoist, hanging basket is transferred to ground;
K) hawser and electric hoist is removed.
Further: described electric hoist has two, and two electric hoists respectively with two hawser one_to_one corresponding, simultaneously two electric hoists respectively with the two ends one_to_one corresponding of hanging basket; And in step b) or step j) in, two electric hoist synchronous workings, make hanging basket held stationary in rising or decline process respectively.
The invention has the beneficial effects as follows: overall structure is simple, takies ground space few, and easy construction, safety is high, very convenient to the movement of hanging basket in work progress in addition, can improve efficiency of construction, shortens the engineering time, saves construction cost.
Accompanying drawing explanation
Fig. 1 is top view of the present invention;
Fig. 2 is lateral view of the present invention;
Fig. 3 is the schematic diagram of the mounting structure of hanging basket;
Fig. 4 is the lateral view of Fig. 3;
Fig. 5 is the close-up schematic view of sectional view shown in A-A cross section in Fig. 4;
Fig. 6 is the schematic three dimensional views of the mounting structure of U-shaped limiting card;
Fig. 7 is the top view of the hanging basket with protective screening;
Fig. 8 is the sectional view shown in B-B cross section in Fig. 7;
Fig. 9 is the front view of pulley suspension hook;
Figure 10 is the lateral view of pulley suspension hook;
Figure 11 is the enlarged diagram of regional area P in Fig. 9;
Be labeled as in figure: hanging basket 1, breast board 11, hawser 2, side main body 31, lower edge truss 32, hanger 41, pulley suspension hook 42, suspension rod 43, gag lever post 44, U-shaped limiting card 45, housing 421, suspension hook 422, head pulley 423, auxiliary pulley 424, chute 425, slide block 426, support end axle 427, elastic component 428, Anterior crossbite rope 51, rear pull rope 52, protective screening 6, choose net bar 61, auxiliary lifting rope 7.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the present invention is further described.
As shown in Fig. 1 to Figure 11, it is schematic diagram of the present invention; The present invention is applicable to large-scale, long span building body and adopts in the construction in later period of anti-boatswain chair after main structure construction completes, and anti-boatswain chair needs to be arranged on below steel truss.
High altitude moving hanging basket system of the present invention, comprise hanging basket 1 and building body, below the steel truss of building body, be provided with at least two parallel to each other and hawsers 2 kept at a certain distance away, the two ends of every root hawser are fixedly connected in the side main body 31 of building body both sides; The two ends of described hanging basket 1 are corresponding with adjacent two hawsers respectively, and be respectively arranged with one group of hanging structure at the two ends of hanging basket, described hanging structure is hung on the hawser 2 of respective side, and can move along hawser 2; Also comprise Anterior crossbite rope 51 and rear pull rope 52; One end of described Anterior crossbite rope is fixed on the front of hanging basket, and the other end is connected with hanging basket; One end of described rear pull rope 52 is fixed on the rear of hanging basket, and the other end is connected with hanging basket.Building body of the present invention refer to carry out the later stage to the construction of anti-boatswain chair before the agent structure of having built, it can be high altitude moving hanging basket system and provides support; Meanwhile, anti-boatswain chair needs to be arranged on below steel truss, simultaneously by steel truss support.Side main body 31, according to actual conditions, generally can be concrete column or concrete wall, and the two ends of hawser can be anchored on corresponding concrete column or concrete wall.
The effect of hawser 2 is for hanging basket, generally speaking, a hanging basket should at least be hung on two adjacent hawsers, and, in order to avoid hawser because tenesmus amount after hanging overweight hanging basket is excessive, usually need to carry out prestressed stretch-draw to hawser, as the prestressing force size of stretch-draw, need to determine according to actual conditions.In addition, for the quantity of hawser, can according to the size of actual building body, and the factor such as the spacing of adjacent two hawsers determines.When selecting hawser, also should consider the requirement of strength to hawser, guaranteeing that hawser can not rupture.Generally speaking, the spacing of adjacent hawser is relevant to the length of hanging basket, and the spacing of adjacent hawser should be less than the length of hanging basket, as hanging basket length be 12 meters time, the spacing of adjacent hawser can be set to 10 meters.
Wherein, the effect of Anterior crossbite rope 51 and rear pull rope 52 is for moving hanging basket, and it is separately fixed at front and the rear of hanging basket, generally speaking can be respectively fixed in corresponding building structure; In addition, when without the need to moving hanging basket, respectively Anterior crossbite rope 51 and rear pull rope 52 can be tightened up, so also limit rocking of hanging basket further by Anterior crossbite rope 51 and rear pull rope 52.
Hanging basket is movably hung on hawser by hanging structure, facilitate the movement of hanging basket, its hanging structure can adopt following form: often organize the hanger 41 that hanging structure is included in the lower end setting of hanging basket 1 left and right sides, to hang on same hawser 2 and can along two of a hawser movement pulley suspension hook 42, two pulley suspension hooks respectively with two hanger one_to_one corresponding; Described hanging structure of often organizing also comprises two suspension rods 43 being separately positioned on hanging basket both sides, the two ends of described suspension rod are connected with the hanger of the same side and pulley suspension hook respectively, also comprise gag lever post 44, described gag lever post is fixed on hanging basket, and the two ends of gag lever post 44 connect one to one with the suspension rod of both sides respectively.By adopting the rear suspension bar of this kind of hanging structure and hanging basket to be relative stationary state, therefore, in work progress, the situations such as hanging basket can not twist, compare the situation only adopting suspension rod or lifting rope, more can effectively reducing hanging basket rocking when constructing, improving the safety of hanging basket.In addition, in above-mentioned barrel structure, described hanging structure of often organizing also can arrange two U-shaped limiting cards 45; By gag lever post 44 across above hanging basket; Simultaneously on gag lever post, be arranged on the upper end of the breast board 11 of the hanging basket left and right sides by two U-shaped limit fasteners, like this, can conveniently dismantle whole hanging structure.And gag lever post also can arrange the collar at its two ends, be connected with corresponding suspension rod by the collar, make the dismounting of whole hanging structure convenient.In addition, hanging basket itself can be spliced mutually by section bar, carries out welding or bolt is formed by connecting as adopted rectangular steel tube, channel-section steel etc., facilitates the adjustment to hanging basket length like this.
In addition, consider that hanging basket in the present invention is when constructing, its position is general higher, usually 20 meters both more than, therefore drop in order to avoid some article from hanging basket and cause security incident, can protective screening 6 be set further, and protective screening 6 is arranged on the surrounding of hanging basket 1, connect on protective screening 6 with the surrounding breast board 11 on hanging basket near the edge of hanging basket side.Can be caught by protective screening after having article to drop out because of carelessness from hanging basket; Certainly, also can arrange further and choose net bar 61, described in choose net bar 61 and have many, and be arranged on the surrounding of hanging basket 1; Described one end of choosing net bar is connected with hanging basket, the oblique extension of the other end, and to choose on net bar near one end of hanging basket lower than the one end away from hanging basket; Described protective screening 6 is arranged on to be chosen on net bar, and supports by choosing net bar.The effect of choosing net bar mainly improves the enabling capabilities of protective screening; Also the convenient installation to the protective screening of some flexibilities and support simultaneously.
In addition, in order to improve the matching relationship of pulley suspension hook 42 and hawser 2, improve the safety of construction, avoid the situation occurring de-wheel or card wheel, the present invention optimizes further to pulley suspension hook, and it comprises housing 421, suspension hook 422, head pulley 423 and auxiliary pulley 424, and described suspension hook 422 is arranged on the lower end of housing 421, described head pulley 423 is rotating to be arranged on housing 421, and the chute of head pulley is buckled in the top of hawser 2; Described auxiliary pulley 424 is rotating to be arranged on housing 421, and auxiliary pulley 424 is positioned at the below of head pulley 423, and the chute of auxiliary pulley is buckled in the below of hawser 2; One end that suspension rod 43 is connected with pulley suspension hook hangs on suspension hook 422.Like this, jointly form the spacing constraint to hawser by the chute of head pulley 423 and auxiliary pulley 424, hawser is limited in the chute of the two firmly, effectively avoid the situation occurring de-wheel or card wheel.The hawser of different size can be adapted to after coordinating with the chute of auxiliary pulley 424 to make head pulley 423, both sides that also can be corresponding with auxiliary pulley 424 on housing 421 are further respectively arranged with chute 425, in chute 425, be provided with slide block 426 moving up and down, the support end axle 427 of described auxiliary pulley 424 both sides is rotating to be respectively arranged on the slide block 426 of respective side; Also comprise elastic component 428, one end of described elastic component 428 is connected with the bottom of slide block 426, and the other end is against the bottom of chute 425.Like this, the relative position relation of auxiliary pulley and head pulley can be adjusted further by elastic component 428, meet the cooperation from the hawser of different size.Generally spring can be adopted as elastic component 428.
In addition, consider that this type of span of building is general comparatively large, even if after having carried out prestressed stretch-draw to hawser, due to hanging basket construct time add construction equipment and constructor after usually heavier, therefore, often cause hawser to drop amplitude comparatively greatly, cause construction inconvenience.For this reason can some be set again assist a little at the interval, middle part of hawser, assisting a position to arrange auxiliary lifting rope 7, be connected one end of auxiliary lifting rope 7 with hawser 2, the lower edge truss 32 that the other end is corresponding with above hawser connects.And so-called lower edge truss 32, refer to the trussed construction in building body, namely part-structure in steel truss, certainly, require that it can meet corresponding bearing capacity.In addition, for when being provided with auxiliary lifting rope, when needs are from auxiliary lifting rope position moving hanging basket, auxiliary for this place lifting rope first can being removed, treat that hanging basket reconnects auxiliary lifting rope after moving again, and hawser is winched to setting height again.
Further illustrate the construction method of high altitude moving hanging basket system of the present invention below: it comprises the following steps:
A) structure of high altitude moving hanging basket system:
A) after building main body construction completes, below the steel truss of building body, the two ends of every root hawser are fixedly connected in the side main body 31 of both sides, carry out prestressed stretch-draw simultaneously to hawser by the equally spaced many hawsers 2 that be arranged in parallel;
B) electric hoist is set on steel truss; By electric hoist, hanging basket is winched to preset height;
C) hanging basket two ends are hung on corresponding hawser respectively by hanging structure, then remove the annexation of electric hoist and hanging basket, carry hanging basket by hawser;
D) arrange Anterior crossbite rope 51 and rear pull rope 52, one end of Anterior crossbite rope is fixed on the front of hanging basket, the other end is connected with hanging basket; One end of rear pull rope 52 is fixed on the rear of hanging basket, the other end is connected with hanging basket;
B) movement of hanging basket: can along hawser direction hanging basket moved forward or after move, corresponding following two kinds of modes respectively:
E) reach of hanging basket, unclamps rear pull rope 52 and the connection of hanging basket, then tightens up Anterior crossbite rope 51, draw hanging basket move forward by Anterior crossbite rope 51; After mobile end, again Anterior crossbite rope 51 is connected with hanging basket respectively with rear pull rope 52;
F) move after hanging basket, unclamp Anterior crossbite rope 51 and the connection of hanging basket, then tighten up rear pull rope 52, draw hanging basket by rear pull rope 52 and move backward; After mobile end, again Anterior crossbite rope 51 is connected with hanging basket respectively with rear pull rope 52;
C) dismounting of high altitude moving hanging basket system:
G) hanging basket is moved to electric hoist place, and again electric hoist is connected with hanging basket;
H) connection of Anterior crossbite rope 51 and rear pull rope 52 and hanging basket is removed;
I) remove the connection of hawser and hanging basket, carry hanging basket by hoist;
J) by electric hoist, hanging basket is transferred to ground;
K) hawser and electric hoist is removed.
Because this construction method has been carried out after building body has been constructed, the structures such as the side main body 31 therefore in building body and steel truss have been constructed.
First, when arranging hawser, the construction desired height according to installing anti-boatswain chair is needed to arrange, and need in conjunction with length of boom, the hanging basket degree of depth, hawser tenesmus amplitude, the many factors such as constructor's height consider, and it is finally required to meet constructor and stands in hanging basket and should conveniently install anti-boatswain chair.Further, according to actual conditions, auxiliary lifting rope 7 pairs of hawsers also can be set and carry out supplemental support, avoid lifting rope transition to drop, and cause construction inconvenience.
The effect arranging electric hoist is for promoting hanging basket, certainly, hanging basket should be assembled before this, then be placed on the vacant lot below electric hoist, in order to ensure hanging basket held stationary when rising and decline, general setting at least two electric hoists, and two electric hoists respectively with two hawser one_to_one corresponding, simultaneously two electric hoists respectively with the two ends one_to_one corresponding of hanging basket; And require two electric hoist synchronous workings.So-called two electric hoists respectively with two hawser one_to_one corresponding, simultaneously two electric hoists respectively with the two ends one_to_one corresponding of hanging basket, refer to time, after hanging basket to winch to and subscribes height by electric hoist, should conveniently hanging basket be hung on corresponding hawser by hanging structure.

Claims (10)

1. high altitude moving hanging basket system, comprise hanging basket (1) and building body, it is characterized in that: below the steel truss of building body, be provided with at least two parallel to each other and hawsers kept at a certain distance away (2), the two ends of every root hawser are fixedly connected in the side main body (31) of building body both sides; The two ends of described hanging basket (1) are corresponding with adjacent two hawsers respectively, one group of hanging structure is respectively arranged with at the two ends of hanging basket, described hanging structure is hung on the hawser (2) of respective side, and can be mobile along hawser (2); Also comprise Anterior crossbite rope (51) and rear pull rope (52); One end of described Anterior crossbite rope is fixed on the front of hanging basket, and the other end is connected with hanging basket; The one end at described rear pull rope (52) is fixed on the rear of hanging basket, and the other end is connected with hanging basket.
2. high altitude moving hanging basket system as claimed in claim 1, it is characterized in that: the hanger (41) that the lower end that described often group hanging structure is included in hanging basket (1) left and right sides is arranged, hang over same hawser (2) upper and can along two of a hawser movement pulley suspension hook (42), two pulley suspension hooks respectively with two hanger one_to_one corresponding; Described hanging structure of often organizing also comprises two suspension rods (43) being separately positioned on hanging basket both sides, the two ends of described suspension rod are connected with the hanger of the same side and pulley suspension hook respectively, also comprise gag lever post (44), described gag lever post is fixed on hanging basket, and the two ends of gag lever post (44) connect one to one with the suspension rod of both sides respectively.
3. high altitude moving hanging basket system as claimed in claim 2, is characterized in that: described hanging structure of often organizing also comprises two U-shaped limiting cards (45); Described gag lever post (44) is across above hanging basket; Two U-shaped limit fasteners are on gag lever post and be arranged on the upper end of the breast board (11) of the hanging basket left and right sides.
4. the high altitude moving hanging basket system as described in claim 1,2 or 3, it is characterized in that: also comprise protective screening (6), described protective screening (6) is arranged on the surrounding of hanging basket (1), and protective screening (6) is upper to connect with the surrounding breast board (11) on hanging basket near the edge of hanging basket side.
5. high altitude moving hanging basket system as claimed in claim 4, is characterized in that: also comprise and choose net bar (61), described in choose net bar (61) and have many, and be arranged on the surrounding of hanging basket (1); Described one end of choosing net bar is connected with hanging basket, the oblique extension of the other end, and to choose on net bar near one end of hanging basket lower than the one end away from hanging basket; Described protective screening (6) is arranged on to be chosen on net bar, and supports by choosing net bar.
6. high altitude moving hanging basket system as claimed in claim 2 or claim 3, it is characterized in that: described pulley suspension hook (42) comprises housing (421), suspension hook (422), head pulley (423) and auxiliary pulley (424), described suspension hook (422) is arranged on the lower end of housing (421), described head pulley (423) is rotating to be arranged on housing (421), and the chute of head pulley is buckled in the top of hawser (2); Described auxiliary pulley (424) is rotating to be arranged on housing (421), and auxiliary pulley (424) is positioned at the below of head pulley (423), and the chute of auxiliary pulley is buckled in the below of hawser (2); The upper one end be connected with pulley suspension hook of suspension rod (43) hangs on suspension hook (422).
7. high altitude moving hanging basket system as claimed in claim 6, it is characterized in that: be respectively arranged with chute (425) in the upper both sides corresponding with auxiliary pulley (424) of housing (421), in chute (425), be provided with slide block moving up and down (426), the support end axle (427) of auxiliary pulley (424) both sides is rotating to be respectively arranged on the slide block (426) of respective side; Also comprise elastic component (428), one end of described elastic component (428) is connected with the bottom of slide block (426), and the other end is against the bottom of chute (425).
8. high altitude moving hanging basket system as claimed in claim 1, it is characterized in that: also comprise auxiliary lifting rope (7), one end of described auxiliary lifting rope (7) is connected with hawser (2), and the lower edge truss (32) that the other end is corresponding with above hawser connects.
9. the construction method of high altitude moving hanging basket system, is characterised in that: the construction method of the high altitude moving hanging basket system according to any one of the claims 1 to 8, comprises the following steps:
A) structure of high altitude moving hanging basket system:
A) after building main body construction completes, the equally spaced many hawsers (2) that be arranged in parallel below the steel truss of building body, the two ends of every root hawser are fixedly connected in the side main body (31) of both sides, prestressed stretch-draw are carried out to hawser simultaneously;
B) electric hoist is set on steel truss; By electric hoist, hanging basket is winched to preset height;
C) hanging basket two ends are hung on corresponding hawser respectively by hanging structure, then remove the annexation of electric hoist and hanging basket, carry hanging basket by hawser;
D) arrange Anterior crossbite rope (51) and rear pull rope (52), one end of Anterior crossbite rope is fixed on the front of hanging basket, the other end is connected with hanging basket; One end of rear pull rope (52) is fixed on the rear of hanging basket, the other end is connected with hanging basket;
B) movement of hanging basket: can along hawser direction hanging basket moved forward or after move, corresponding following two kinds of modes respectively:
E) reach of hanging basket, unclamps rear pull rope (52) and the connection of hanging basket, then tightens up Anterior crossbite rope (51), is moved forward by Anterior crossbite rope (51) traction hanging basket; After mobile end, again Anterior crossbite rope (51) is connected with hanging basket respectively with rear pull rope (52);
F) move after hanging basket, unclamp Anterior crossbite rope (51) and the connection of hanging basket, then tighten up rear pull rope (52), moved backward by rear pull rope (52) traction hanging basket; After mobile end, again Anterior crossbite rope (51) is connected with hanging basket respectively with rear pull rope (52);
C) dismounting of high altitude moving hanging basket system:
G) hanging basket is moved to electric hoist place, and again electric hoist is connected with hanging basket;
H) connection of Anterior crossbite rope (51) and rear pull rope (52) and hanging basket is removed;
I) remove the connection of hawser and hanging basket, carry hanging basket by hoist;
J) by electric hoist, hanging basket is transferred to ground;
K) hawser and electric hoist is removed.
10. the construction method of high altitude moving hanging basket system as claimed in claim 9, is characterized in that: described electric hoist has two, and two electric hoists respectively with two hawser one_to_one corresponding, simultaneously two electric hoists respectively with the two ends one_to_one corresponding of hanging basket; And in step b) or step j) in, two electric hoist synchronous workings, make hanging basket held stationary in rising or decline process move respectively.
CN201510021729.1A 2015-01-15 2015-01-15 High altitude moving hanging basket system and construction method Expired - Fee Related CN104631810B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510021729.1A CN104631810B (en) 2015-01-15 2015-01-15 High altitude moving hanging basket system and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510021729.1A CN104631810B (en) 2015-01-15 2015-01-15 High altitude moving hanging basket system and construction method

Publications (2)

Publication Number Publication Date
CN104631810A true CN104631810A (en) 2015-05-20
CN104631810B CN104631810B (en) 2016-06-08

Family

ID=53211005

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510021729.1A Expired - Fee Related CN104631810B (en) 2015-01-15 2015-01-15 High altitude moving hanging basket system and construction method

Country Status (1)

Country Link
CN (1) CN104631810B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105155832A (en) * 2015-06-17 2015-12-16 中建钢构有限公司 Hanging basket device and moving method thereof
CN105715032A (en) * 2016-04-15 2016-06-29 中国五冶集团有限公司 Construction hanging basket with spanning movement function and spanning movement method
CN105986664A (en) * 2016-07-20 2016-10-05 中国建筑局(集团)有限公司 Hanging basket and roof reverse-hanging plate work platform including same
CN107165169A (en) * 2016-03-07 2017-09-15 中交公局第工程有限公司 The construction method and spouting plant of a kind of unmanned mobile whitewashing in high-altitude
CN107313360A (en) * 2017-07-18 2017-11-03 南昌大学 Overhead cable formula is without support bearing replacement operating platform
CN109958219A (en) * 2019-04-11 2019-07-02 中国十七冶集团有限公司 A kind of complex environment roofing truss lower part liner plate suspension cable installation method
CN111456407A (en) * 2020-04-15 2020-07-28 中国化学工程第三建设有限公司 Method and device for constructing decoration and maintenance process of wall bodies at two ends below beam track by using travelling crane beam
CN116290721A (en) * 2023-05-17 2023-06-23 河北盛威建筑机械有限公司 Telescopic hanging basket convenient for construction

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08105199A (en) * 1994-10-05 1996-04-23 De-A Gaisou Kk Swinging scaffold
JPH09169481A (en) * 1995-12-20 1997-06-30 Hitachi Building Syst Co Ltd Elevating device for installing elevator
CN101338582A (en) * 2008-07-25 2009-01-07 中铁四局集团有限公司 Nacelle-moving construction method for wide span and big area suspended ceiling
CN202767494U (en) * 2012-09-06 2013-03-06 安徽富煌钢构股份有限公司 Hanging basket for high-altitude roof inner plate construction
CN203701560U (en) * 2013-12-31 2014-07-09 森特士兴集团股份有限公司 Suspension hanging basket for high-altitude roofing inner plate construction

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08105199A (en) * 1994-10-05 1996-04-23 De-A Gaisou Kk Swinging scaffold
JPH09169481A (en) * 1995-12-20 1997-06-30 Hitachi Building Syst Co Ltd Elevating device for installing elevator
CN101338582A (en) * 2008-07-25 2009-01-07 中铁四局集团有限公司 Nacelle-moving construction method for wide span and big area suspended ceiling
CN202767494U (en) * 2012-09-06 2013-03-06 安徽富煌钢构股份有限公司 Hanging basket for high-altitude roof inner plate construction
CN203701560U (en) * 2013-12-31 2014-07-09 森特士兴集团股份有限公司 Suspension hanging basket for high-altitude roofing inner plate construction

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105155832A (en) * 2015-06-17 2015-12-16 中建钢构有限公司 Hanging basket device and moving method thereof
CN107165169A (en) * 2016-03-07 2017-09-15 中交公局第工程有限公司 The construction method and spouting plant of a kind of unmanned mobile whitewashing in high-altitude
CN107165169B (en) * 2016-03-07 2019-02-12 中交一公局第一工程有限公司 A kind of construction method and spouting plant of the unmanned mobile whitewashing in high-altitude
CN105715032A (en) * 2016-04-15 2016-06-29 中国五冶集团有限公司 Construction hanging basket with spanning movement function and spanning movement method
CN105715032B (en) * 2016-04-15 2017-09-29 中国五冶集团有限公司 It is a kind of that there is the construction hanging basket for crossing over locomotive function and moving method is crossed over
CN105986664A (en) * 2016-07-20 2016-10-05 中国建筑局(集团)有限公司 Hanging basket and roof reverse-hanging plate work platform including same
CN107313360A (en) * 2017-07-18 2017-11-03 南昌大学 Overhead cable formula is without support bearing replacement operating platform
CN107313360B (en) * 2017-07-18 2022-12-06 南昌大学 Sliding cable type support-free support replacing operation platform
CN109958219A (en) * 2019-04-11 2019-07-02 中国十七冶集团有限公司 A kind of complex environment roofing truss lower part liner plate suspension cable installation method
CN111456407A (en) * 2020-04-15 2020-07-28 中国化学工程第三建设有限公司 Method and device for constructing decoration and maintenance process of wall bodies at two ends below beam track by using travelling crane beam
CN116290721A (en) * 2023-05-17 2023-06-23 河北盛威建筑机械有限公司 Telescopic hanging basket convenient for construction
CN116290721B (en) * 2023-05-17 2023-09-19 河北盛威建筑机械有限公司 Telescopic hanging basket convenient for construction

Also Published As

Publication number Publication date
CN104631810B (en) 2016-06-08

Similar Documents

Publication Publication Date Title
CN104631810B (en) High altitude moving hanging basket system and construction method
CN202202558U (en) Girder-riding weight basket hanging mechanism arranged on high-rise roof frame girder
CN101476410B (en) Mounting and demounting method for roof plate formwork support platform of concrete silo
CN101736893B (en) Overhanging type scaffold supporting system
CN102108786B (en) Overall lifting construction method of ultra-large type building member and device thereof
CN205934747U (en) A hang basket that is used for cantilever to pour bridge construction operation with pre -compaction structure
CN105621280B (en) The apparatus and method for mounting and dismounting crane arm
CN201598820U (en) Single point suspension external hanging bracket
CN205777580U (en) A kind of automatic lifting discharging platform
CN106988299B (en) The pay-off method of assembled steel reinforced cage descending frame and steel reinforcement cage
CN102425261A (en) Large-span multiunit tensile membrane structure and installation construction method thereof
CN201362953Y (en) Construction platform for pouring concrete silo roof
CN203113793U (en) Large formwork installation system of oblique structure
CN203284126U (en) Simple composite gantry high-altitude weight hoisting device
CN205527435U (en) Installation and device of dismantling jib loading boom
CN2701971Y (en) Dual-purpose tripod for building construction and decoration
CN203200719U (en) Hanging type slope pouring template device
CN216512520U (en) Lifting system suitable for small space
CN202000647U (en) Base device for lifting scaffold in elevator shaft
CN105060124B (en) Intra-frame portal crane system and hoisting use method thereof
CN205034948U (en) Rack formula hanging beam device
CN202899720U (en) Steel pole provided with foot treadles and used for high-tension transmission line iron tower
CN209723570U (en) Steel column docking installation operation platform
CN209307871U (en) A kind of hanging basket formwork Integral lifting device
CN105155832A (en) Hanging basket device and moving method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180503

Address after: 610000 18 T District, 108 Jing Ye Road, Qingyang District, Chengdu, Sichuan.

Patentee after: In the section of Construction Group Co. Ltd.

Address before: 610027 1, 19 1, 1 ginkgo Road, Jinniu District, Chengdu, Sichuan.

Patentee before: ZHONGYU YUANFA INTERNATIONAL CONSTRUCTION GROUP CO., LTD.