CN104631810B - High altitude moving hanging basket system and construction method - Google Patents
High altitude moving hanging basket system and construction method Download PDFInfo
- Publication number
- CN104631810B CN104631810B CN201510021729.1A CN201510021729A CN104631810B CN 104631810 B CN104631810 B CN 104631810B CN 201510021729 A CN201510021729 A CN 201510021729A CN 104631810 B CN104631810 B CN 104631810B
- Authority
- CN
- China
- Prior art keywords
- hanging basket
- hawser
- rope
- hanging
- high altitude
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Movable Scaffolding (AREA)
Abstract
The invention discloses a kind of high altitude moving hanging basket system and construction method, belong to the realm of building construction, it is provided that a kind of efficiency of construction improving anti-boatswain chair, reduce the high altitude moving hanging basket system of construction cost. By arranging hawser, and hanging basket is movably hung on hawser by hanging structure, workmen can carry out the construction to anti-boatswain chair in hanging basket, and, in the present invention movement of hanging basket is very convenient, only need to can be realized by corresponding pull rope, integral construction efficiency can be effectively improved, reduce construction cost. It addition, the potential safety hazard of workmen also can be effectively reduced, it is ensured that construction safety. High altitude moving hanging basket system of the present invention, its construction method is simple, is suitable in the heavy constructions such as various stadiums or exhibition center the construction to anti-boatswain chair.
Description
Technical field
The present invention relates to the realm of building construction, particularly relate to the construction method of a kind of high altitude moving hanging basket system and this high altitude moving hanging basket system.
Background technology
Along with the fast development of some heavy constructions such as stadiums or exhibition center in recent years, the span of this type of building is increasing, and easily all more than 50 meters, and its headroom is also higher, generally all more than 20 meters. And the installation of the anti-boatswain chair for this type of building, owing to anti-boatswain chair is typically mounted on the lower section of the main structures such as steel truss, therefore install very inconvenient, it is typically with traditional mode building full hall scaffold at present, owing to the construction location of boatswain chair anti-in this type of heavy construction is higher, therefore the stability requirement of full hall scaffold is just higher, otherwise there is bigger potential safety hazard; And in order to improve the stability of full hall scaffold, the volume of scaffold can only be increased, and can cause accordingly and build scaffold material requested and increase, take excessive ground space, cause claim for eot simultaneously, cost increases; It addition, scaffold is also unfavorable for that scaffold moves, and affects efficiency of construction after increasing.
Summary of the invention
Present invention solves the technical problem that and be to provide a kind of high altitude moving hanging basket system solving the problems referred to above and its construction method, can effectively improve the efficiency of construction of anti-boatswain chair, reduce construction cost.
The technical solution adopted for the present invention to solve the technical problems is: high altitude moving hanging basket system, including hanging basket and building body, steel truss at building body is arranged below at least two hawsers that are parallel to each other and that keep at a certain distance away, and the two ends of every hawser are fixedly connected in the side main body of building body both sides; The two ends of described hanging basket are corresponding with two adjacent hawsers respectively, are respectively arranged with one group of hanging structure at the two ends of hanging basket, and described hanging structure is hung on the hawser of respective side, and can move along hawser; Also include Anterior crossbite rope and rear pull rope; One end of described Anterior crossbite rope is fixed on the front of hanging basket, and the other end is connected with hanging basket;One end of described rear pull rope is fixed on the rear of hanging basket, and the other end is connected with hanging basket.
Further: described often group hanging structure includes the hanger that arranges in the lower end of the hanging basket left and right sides, hangs on same hawser and two the pulley suspension hooks that can move along hawser, two pulley suspension hooks respectively with two hanger one_to_one corresponding; Described often group hanging structure also includes two suspension rods being separately positioned on hanging basket both sides, the two ends of described suspension rod are connected with the hanger of the same side and pulley suspension hook respectively, also include gag lever post, described gag lever post is fixed on hanging basket, and the two ends of gag lever post connect one to one with the suspension rod of both sides respectively.
Further: described often group hanging structure also includes two U-shaped limiting cards; Described gag lever post is across above hanging basket; Two U-shaped limit fasteners are on gag lever post and are arranged on the upper end of breast board of the hanging basket left and right sides.
Further: also including protection network, described protection network is arranged on the surrounding of hanging basket, on protection network, the edge of close hanging basket side connects with the surrounding breast board on hanging basket body.
Further: also include choosing net bar, described in choose net bar and have many, and be arranged on the surrounding of hanging basket; Described one end choosing net bar is connected with hanging basket, and the other end tiltedly stretches out, and chooses on net bar near one end of hanging basket lower than the one end away from hanging basket; Described protection network is arranged on to be chosen on net bar, and supports by choosing net bar.
Further: described pulley suspension hook includes housing, suspension hook, head pulley and auxiliary pulley, described suspension hook is arranged on the lower end of housing, and described head pulley is rotating to be arranged on housing, and the chute of head pulley is buckled in the top of hawser; Described auxiliary pulley is rotating to be arranged on housing, and auxiliary pulley is positioned at the lower section of head pulley, and the chute of auxiliary pulley is buckled in the lower section of hawser; The one end being connected with pulley suspension hook on suspension rod hangs on suspension hook.
Further: both sides corresponding with auxiliary pulley on housing are respectively arranged with chute, in chute, it is provided with slide block moving up and down, on the support end axle of the auxiliary pulley both sides rotating slide block being arranged on respective side respectively; Also including elastic component, one end of described elastic component is connected with the bottom of slide block, and the other end is against the bottom of chute.
Further: also including auxiliary lifting rope, one end of described auxiliary lifting rope is connected with hawser, the lower edge truss that the other end is corresponding with above hawser connects.
The construction method of above-mentioned high altitude moving hanging basket system, comprises the following steps:
A) structure of high altitude moving hanging basket system:
A) after building main body construction completes, below the steel truss of building body, the two ends of every hawser are fixedly connected in the side main body of both sides, hawser are carried out prestressed stretch-draw simultaneously by the equally spaced many hawsers that be arranged in parallel;
B) electric hoist is set on steel truss; By electric hoist, hanging basket is winched to preset height;
C) hanging basket two ends are hung on corresponding hawser respectively through hanging structure, then release the annexation of electric hoist and hanging basket, hawser carry hanging basket;
D) arranging Anterior crossbite rope and rear pull rope, one end of Anterior crossbite rope is fixed on the front of hanging basket, the other end is connected with hanging basket; One end of rear pull rope is fixed on the rear of hanging basket, and the other end is connected with hanging basket;
B) movement of hanging basket: can along hawser direction hanging basket moved forward or after move, corresponding following two mode respectively:
E) reach of hanging basket, unclamps the connection of rear pull rope and hanging basket, then tightens up Anterior crossbite rope, is moved forward by Anterior crossbite wire saws hanging basket; After mobile end, again Anterior crossbite rope and rear pull rope are connected with hanging basket respectively;
F) the rear shifting of hanging basket, unclamps the connection of Anterior crossbite rope and hanging basket, then tightens up rear pull rope, draws hanging basket by rear pull rope and is moved rearwards by;After mobile end, again Anterior crossbite rope and rear pull rope are connected with hanging basket respectively;
C) dismounting of high altitude moving hanging basket system:
G) hanging basket is moved to electric hoist place, and again electric hoist is connected with hanging basket;
H) connection of Anterior crossbite rope and rear pull rope and hanging basket is released;
I) release the connection of hawser and hanging basket, hoist carry hanging basket;
J) by electric hoist, hanging basket is transferred to ground;
K) hawser and electric hoist are removed.
Further: described electric hoist has two, and two electric hoists respectively with two hawser one_to_one corresponding, simultaneously two electric hoists respectively with the two ends one_to_one corresponding of hanging basket; And in step b) or step j), two electric hoist synchronous workings, make hanging basket increase or held stationary in decline process respectively.
The invention has the beneficial effects as follows: overall structure is simple, takies ground space few, and easy construction, safety is high, additionally in work progress, the movement of hanging basket is very convenient, can improve efficiency of construction, shortens the engineering time, saves construction cost.
Accompanying drawing explanation
Fig. 1 is the top view of the present invention;
Fig. 2 is the side view of the present invention;
Fig. 3 is the schematic diagram of the mounting structure of hanging basket;
Fig. 4 is the side view of Fig. 3;
Fig. 5 is the close-up schematic view of sectional view shown in Section A-A in Fig. 4;
Fig. 6 is the schematic three dimensional views of the mounting structure of U-shaped limiting card;
Fig. 7 is the top view of the hanging basket with protection network;
Fig. 8 is the sectional view shown in section B-B in Fig. 7;
Fig. 9 is the front view of pulley suspension hook;
Figure 10 is the side view of pulley suspension hook;
Figure 11 is the enlarged diagram of regional area P in Fig. 9;
Figure is labeled as: hanging basket 1, breast board 11, hawser 2, side main body 31, lower edge truss 32, hanger 41, pulley suspension hook 42, suspension rod 43, gag lever post 44, U-shaped limiting card 45, housing 421, suspension hook 422, head pulley 423, auxiliary pulley 424, chute 425, slide block 426, support end axle 427, elastic component 428, Anterior crossbite rope 51, rear pull rope 52, protection network 6, choose net bar 61, auxiliary lifting rope 7.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the present invention is further described.
As shown in Fig. 1 to Figure 11, for the schematic diagram of the present invention; The present invention adopts the construction in later period of anti-boatswain chair after main structure construction completes suitable in large-scale, long span building body, and anti-boatswain chair needs to be arranged on below steel truss.
High altitude moving hanging basket system of the present invention, including hanging basket 1 and building body, steel truss at building body is arranged below at least two hawsers 2 that are parallel to each other and that keep at a certain distance away, and the two ends of every hawser are fixedly connected in the side main body 31 of building body both sides; The two ends of described hanging basket 1 are corresponding with two adjacent hawsers respectively, are respectively arranged with one group of hanging structure at the two ends of hanging basket, and described hanging structure is hung on the hawser 2 of respective side, and can move along hawser 2; Also include Anterior crossbite rope 51 and rear pull rope 52; One end of described Anterior crossbite rope is fixed on the front of hanging basket, and the other end is connected with hanging basket; One end of described rear pull rope 52 is fixed on the rear of hanging basket, and the other end is connected with hanging basket. Building body of the present invention refers to and is carrying out the agent structure built before the later stage construction to anti-boatswain chair, and it can provide for high altitude moving hanging basket system and support; Meanwhile, anti-boatswain chair needs to be arranged on below steel truss, simultaneously by steel truss support. Side main body 31, according to practical situation, may generally be concrete column or concrete walls, and the two ends of hawser can be anchored on corresponding concrete column or concrete walls.
The effect of hawser 2 is for hanging basket, generally speaking, one hanging basket should at least be hung on adjacent two piece hawser, and, in order to avoid hawser due to after hanging overweight hanging basket tenesmus amount excessive, typically require and hawser is carried out prestressed stretch-draw, as the prestressing force size of stretch-draw, it is necessary to determine according to practical situation. It addition, for the quantity of hawser, can according to the size of actual building body, and the factor such as the spacing of adjacent two hawsers determines. When selecting hawser, requirement of strength to hawser be should also be considered, it is ensured that hawser will not rupture. It is said that in general, the spacing of adjacent hawser is relevant to the length of hanging basket, and the spacing of adjacent hawser less than the length of hanging basket, when being 12 meters such as hanging basket length, should can be set to 10 meters by the spacing of adjacent hawser.
Wherein, the effect of Anterior crossbite rope 51 and rear pull rope 52 is that it is separately fixed at the front and back of hanging basket for moving hanging basket, it is however generally that can be respectively fixed in the building structure of correspondence; It addition, when without moving hanging basket, can Anterior crossbite rope 51 and rear pull rope 52 be tightened up respectively, so limit rocking of hanging basket further also by Anterior crossbite rope 51 and rear pull rope 52.
Hanging basket is movably hung on hawser by hanging structure, facilitate the movement of hanging basket, its hanging structure can adopt following form: often organizes the hanger 41 that hanging structure includes arranging in the lower end of hanging basket 1 left and right sides, hang on same hawser 2 and two the pulley suspension hooks 42 that can move along hawser, two pulley suspension hooks respectively with two hanger one_to_one corresponding; Described often group hanging structure also includes two suspension rods 43 being separately positioned on hanging basket both sides, the two ends of described suspension rod are connected with the hanger of the same side and pulley suspension hook respectively, also include gag lever post 44, described gag lever post is fixed on hanging basket, and the two ends of gag lever post 44 connect one to one with the suspension rod of both sides respectively. It is be relatively fixed state by adopting rear suspension bar and the hanging basket of this kind of hanging structure, therefore, in work progress, the situations such as hanging basket will not twist, compare the situation only with suspension rod or lifting rope, can significantly more efficient reduction hanging basket construction time rocking, improve hanging basket safety. It addition, in above-mentioned barrel structure, described often group hanging structure also can arrange two U-shaped limiting cards 45; By gag lever post 44 across above hanging basket; Simultaneously and it is arranged on the upper end of breast board 11 of the hanging basket left and right sides by two U-shaped limit fasteners on gag lever post, so, can conveniently whole hanging structure be dismantled. And gag lever post also can arrange the collar at its two ends, being attached with corresponding suspension rod by the collar, the dismounting making whole hanging structure is convenient. It addition, hanging basket itself can be spliced mutually by section bar, as adopted rectangular steel tube, channel-section steel etc. to carry out welding or bolt is formed by connecting, so facilitate the adjustment to hanging basket length.
Additionally, consider that the hanging basket in the present invention is when construction, its position is general higher, generally 20 meters both more than, therefore to avoid some article to drop from hanging basket cause security incident, protection network 6 can be set further, and protection network 6 is arranged on the surrounding of hanging basket 1, edge near hanging basket side on protection network 6 is connected with the surrounding breast board 11 on hanging basket. Can be caught by protection network after having article to drop out from imprudence hanging basket; Certainly, may further be provided and choose net bar 61, described in choose net bar 61 and have many, and be arranged on the surrounding of hanging basket 1;Described one end choosing net bar is connected with hanging basket, and the other end tiltedly stretches out, and chooses on net bar near one end of hanging basket lower than the one end away from hanging basket; Described protection network 6 is arranged on to be chosen on net bar, and supports by choosing net bar. The effect choosing net bar mainly improves the enabling capabilities of protection network; It is also convenient for installation and the support of the protection network to some flexibilities simultaneously.
Additionally, in order to improve the matching relationship of pulley suspension hook 42 and hawser 2, improve the safety of construction, avoid the occurrence of de-wheel or the situation of card wheel, pulley jib is hooked into traveling one-step optimization by the present invention, and it includes housing 421, suspension hook 422, head pulley 423 and auxiliary pulley 424, and described suspension hook 422 is arranged on the lower end of housing 421, described head pulley 423 is rotating to be arranged on housing 421, and the chute of head pulley is buckled in the top of hawser 2; Described auxiliary pulley 424 is rotating to be arranged on housing 421, and auxiliary pulley 424 is positioned at the lower section of head pulley 423, and the chute of auxiliary pulley is buckled in the lower section of hawser 2; The one end being connected with pulley suspension hook on suspension rod 43 hangs on suspension hook 422. So, the chute of head pulley 423 and auxiliary pulley 424 it is collectively forming the spacing constraint to hawser, makes hawser be limited in the chute of the two firmly, effectively avoid the occurrence of de-wheel or the situation of card wheel. So that the chute of head pulley 423 and auxiliary pulley 424 adapts to different size of hawser after coordinating, both sides that also can be corresponding with auxiliary pulley 424 on housing 421 further are respectively arranged with chute 425, slide block 426 moving up and down it is provided with, on the support end axle 427 of the described auxiliary pulley 424 both sides rotating slide block 426 being arranged on respective side respectively in chute 425; Also including elastic component 428, one end of described elastic component 428 is connected with the bottom of slide block 426, and the other end is against the bottom of chute 425. So, the relative position relation of auxiliary pulley and head pulley can be adjusted further by elastic component 428, meet and the coordinating of different size of hawser. Spring generally can be adopted as elastic component 428.
Furthermore, it is contemplated that the span of this type of building is generally large, even if after hawser has been carried out prestressed stretch-draw, due to hanging basket when construction plus generally heavier after construction equipment and workmen, therefore, often cause hawser tenesmus amplitude relatively big, cause construction inconvenience. Can falling a little in some auxiliary that arrange again at the interval, middle part of hawser for this, fall a position in auxiliary and arrange auxiliary lifting rope 7, be connected with hawser 2 one end of auxiliary lifting rope 7, the lower edge truss 32 that the other end is corresponding with above hawser connects. And what is called lower edge truss 32, refer to the truss structure in building body, namely part-structure in steel truss, certainly, it is desirable to it can meet corresponding bearing capacity. It addition, during for being provided with auxiliary lifting rope, when needs are from auxiliary lifting rope position moving hanging basket, auxiliary for this place lifting rope first can be removed, the auxiliary lifting rope of re-attached after hanging basket is moved through, and hawser is winched to again setting height.
The construction method of of the present invention high altitude moving hanging basket system is further illustrated below: it comprises the following steps:
A) structure of high altitude moving hanging basket system:
A) after building main body construction completes, below the steel truss of building body, the two ends of every hawser are fixedly connected in the side main body 31 of both sides, hawser are carried out prestressed stretch-draw simultaneously by the equally spaced many hawsers 2 that be arranged in parallel;
B) electric hoist is set on steel truss; By electric hoist, hanging basket is winched to preset height;
C) hanging basket two ends are hung on corresponding hawser respectively through hanging structure, then release the annexation of electric hoist and hanging basket, hawser carry hanging basket;
D) arranging Anterior crossbite rope 51 and rear pull rope 52, one end of Anterior crossbite rope is fixed on the front of hanging basket, the other end is connected with hanging basket; One end of rear pull rope 52 is fixed on the rear of hanging basket, and the other end is connected with hanging basket;
B) movement of hanging basket: can along hawser direction hanging basket moved forward or after move, corresponding following two mode respectively:
E) reach of hanging basket, unclamps the connection of rear pull rope 52 and hanging basket, then tightens up Anterior crossbite rope 51, draw hanging basket by Anterior crossbite rope 51 and move forward; After mobile end, again Anterior crossbite rope 51 and rear pull rope 52 are connected with hanging basket respectively;
F) the rear shifting of hanging basket, unclamps the connection of Anterior crossbite rope 51 and hanging basket, then tightens up rear pull rope 52, draw hanging basket by rear pull rope 52 and be moved rearwards by; After mobile end, again Anterior crossbite rope 51 and rear pull rope 52 are connected with hanging basket respectively;
C) dismounting of high altitude moving hanging basket system:
G) hanging basket is moved to electric hoist place, and again electric hoist is connected with hanging basket;
H) connection of Anterior crossbite rope 51 and rear pull rope 52 and hanging basket is released;
I) release the connection of hawser and hanging basket, hoist carry hanging basket;
J) by electric hoist, hanging basket is transferred to ground;
K) hawser and electric hoist are removed.
Owing to this construction method is to have carried out after building body has been constructed, therefore the structure such as the side main body 31 in building body and steel truss has been constructed.
First, when arranging hawser, the construction desired height according to installing anti-boatswain chair is needed to be configured, and it also requires in conjunction with length of boom, the hanging basket degree of depth, hawser tenesmus amplitude, the many factors such as workmen's height considers, and it is finally required to meet workmen and stands in hanging basket and should conveniently anti-boatswain chair be installed. Further, according to practical situation, auxiliary lifting rope 7 also can be set hawser is carried out auxiliary support, it is to avoid lifting rope transition drops, and causes construction inconvenience.
The effect arranging electric hoist is for promoting hanging basket, certainly, hanging basket should be completed before this, it is then placed within the vacant lot below electric hoist, in order to ensure hanging basket held stationary when raising and lowering, at least two electric hoist is generally set, and two electric hoists respectively with two hawser one_to_one corresponding, simultaneously two electric hoists respectively with the two ends one_to_one corresponding of hanging basket; And require two electric hoist synchronous workings. So-called two electric hoists respectively with two hawser one_to_one corresponding, simultaneously two electric hoists respectively with the two ends one_to_one corresponding of hanging basket, refer to time, after hanging basket is winched to reservation height by electric hoist, it should convenient hanging basket is hung on corresponding hawser by hanging structure.
Claims (9)
1. high altitude moving hanging basket system, including hanging basket (1) and building body, it is characterized in that: the steel truss at building body is arranged below at least two hawsers (2) that are parallel to each other and that keep at a certain distance away, and the two ends of every hawser are fixedly connected in the side main body (31) of building body both sides; The two ends of described hanging basket (1) are corresponding with two adjacent hawsers respectively, one group of hanging structure it is respectively arranged with at the two ends of hanging basket, described hanging structure is hung on the hawser (2) of respective side, and can be mobile along hawser (2); Also include Anterior crossbite rope (51) and rear pull rope (52); One end of described Anterior crossbite rope is fixed on the front of hanging basket, and the other end is connected with hanging basket; The one end at described rear pull rope (52) is fixed on the rear of hanging basket, and the other end is connected with hanging basket;Described often group hanging structure includes the hanger (41) arranged in the lower end of hanging basket (1) left and right sides, hang over two pulley suspension hooks (42) that same hawser (2) is upper and can move along hawser, two pulley suspension hooks respectively with two hanger one_to_one corresponding; Described often group hanging structure also includes two suspension rods (43) being separately positioned on hanging basket both sides, the two ends of described suspension rod are connected with the hanger of the same side and pulley suspension hook respectively, also include gag lever post (44), described gag lever post is fixed on hanging basket, and the two ends of gag lever post (44) connect one to one with the suspension rod of both sides respectively.
2. high altitude moving hanging basket system as claimed in claim 1, it is characterised in that: described often group hanging structure also includes two U-shaped limiting cards (45); Described gag lever post (44) is across above hanging basket; Two U-shaped limit fasteners are on gag lever post and are arranged on the upper end of breast board (11) of the hanging basket left and right sides.
3. high altitude moving hanging basket system as claimed in claim 1 or 2, it is characterized in that: also include protection network (6), described protection network (6) is arranged on the surrounding of hanging basket (1), and the upper edge near hanging basket side of protection network (6) connects with the surrounding breast board (11) on hanging basket.
4. high altitude moving hanging basket system as claimed in claim 3, it is characterised in that: also include choosing net bar (61), described in choose net bar (61) and have many, and be arranged on the surrounding of hanging basket (1); Described one end choosing net bar is connected with hanging basket, and the other end tiltedly stretches out, and chooses on net bar near one end of hanging basket lower than the one end away from hanging basket; Described protection network (6) is arranged on to be chosen on net bar, and supports by choosing net bar.
5. high altitude moving hanging basket system as claimed in claim 1 or 2, it is characterized in that: described pulley suspension hook (42) includes housing (421), suspension hook (422), head pulley (423) and auxiliary pulley (424), described suspension hook (422) is arranged on the lower end of housing (421), described head pulley (423) is rotating to be arranged on housing (421), and the chute of head pulley is buckled in the top of hawser (2); Described auxiliary pulley (424) is rotating to be arranged on housing (421), and auxiliary pulley (424) is positioned at the lower section of head pulley (423), and the chute of auxiliary pulley is buckled in the lower section of hawser (2); The upper one end being connected with pulley suspension hook of suspension rod (43) hangs on suspension hook (422).
6. high altitude moving hanging basket system as claimed in claim 5, it is characterized in that: be respectively arranged with chute (425) in the upper both sides corresponding with auxiliary pulley (424) of housing (421), slide block moving up and down (426) it is provided with, on the support end axle (427) of auxiliary pulley (424) the both sides rotating slide block (426) being arranged on respective side respectively in chute (425); Also including elastic component (428), one end of described elastic component (428) is connected with the bottom of slide block (426), and the other end is against the bottom of chute (425).
7. high altitude moving hanging basket system as claimed in claim 1, it is characterized in that: also include auxiliary lifting rope (7), one end of described auxiliary lifting rope (7) is connected with hawser (2), and the lower edge truss (32) that the other end is corresponding with above hawser connects.
8. the construction method of high altitude moving hanging basket system, is characterised by: the construction method of the high altitude moving hanging basket system according to any one of the claims 1 to 7, comprises the following steps:
A) structure of high altitude moving hanging basket system:
A) after building main body construction completes, the equally spaced many hawsers (2) that be arranged in parallel below the steel truss of building body, the two ends of every hawser are fixedly connected in the side main body (31) of both sides, hawser are carried out prestressed stretch-draw simultaneously;
B) electric hoist is set on steel truss; By electric hoist, hanging basket is winched to preset height;
C) hanging basket two ends are hung on corresponding hawser respectively through hanging structure, then release the annexation of electric hoist and hanging basket, hawser carry hanging basket;
D) arranging Anterior crossbite rope (51) and rear pull rope (52), one end of Anterior crossbite rope is fixed on the front of hanging basket, the other end is connected with hanging basket; One end of rear pull rope (52) is fixed on the rear of hanging basket, and the other end is connected with hanging basket;
B) movement of hanging basket: can along hawser direction hanging basket moved forward or after move, corresponding following two mode respectively:
E) reach of hanging basket, unclamps the connection of rear pull rope (52) and hanging basket, then tightens up Anterior crossbite rope (51), draws hanging basket by Anterior crossbite rope (51) and moves forward; After mobile end, again Anterior crossbite rope (51) and rear pull rope (52) are connected with hanging basket respectively;
F) the rear shifting of hanging basket, unclamps the connection of Anterior crossbite rope (51) and hanging basket, then tightens up rear pull rope (52), draws hanging basket by rear pull rope (52) and is moved rearwards by; After mobile end, again Anterior crossbite rope (51) and rear pull rope (52) are connected with hanging basket respectively;
C) dismounting of high altitude moving hanging basket system:
G) hanging basket is moved to electric hoist place, and again electric hoist is connected with hanging basket;
H) connection of Anterior crossbite rope (51) and rear pull rope (52) and hanging basket is released;
I) release the connection of hawser and hanging basket, hoist carry hanging basket;
J) by electric hoist, hanging basket is transferred to ground;
K) hawser and electric hoist are removed.
9. the construction method of high altitude moving hanging basket system as claimed in claim 8., it is characterised in that: described electric hoist has two, and two electric hoists respectively with two hawser one_to_one corresponding, simultaneously two electric hoists respectively with the two ends one_to_one corresponding of hanging basket; And in step b) or step j), two electric hoist synchronous workings, make hanging basket held stationary in rising or decline process move respectively.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510021729.1A CN104631810B (en) | 2015-01-15 | 2015-01-15 | High altitude moving hanging basket system and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510021729.1A CN104631810B (en) | 2015-01-15 | 2015-01-15 | High altitude moving hanging basket system and construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104631810A CN104631810A (en) | 2015-05-20 |
CN104631810B true CN104631810B (en) | 2016-06-08 |
Family
ID=53211005
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510021729.1A Expired - Fee Related CN104631810B (en) | 2015-01-15 | 2015-01-15 | High altitude moving hanging basket system and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104631810B (en) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105155832B (en) * | 2015-06-17 | 2017-08-25 | 中建钢构有限公司 | A kind of hanging basket equipment and its moving method |
CN107165169B (en) * | 2016-03-07 | 2019-02-12 | 中交一公局第一工程有限公司 | A kind of construction method and spouting plant of the unmanned mobile whitewashing in high-altitude |
CN105715032B (en) * | 2016-04-15 | 2017-09-29 | 中国五冶集团有限公司 | It is a kind of that there is the construction hanging basket for crossing over locomotive function and moving method is crossed over |
CN105986664A (en) * | 2016-07-20 | 2016-10-05 | 中国建筑局(集团)有限公司 | Hanging basket and roof reverse hanging plate operation platform with same |
CN107313360B (en) * | 2017-07-18 | 2022-12-06 | 南昌大学 | Sliding cable type support-free support replacing operation platform |
CN109958219A (en) * | 2019-04-11 | 2019-07-02 | 中国十七冶集团有限公司 | A kind of complex environment roofing truss lower part liner plate suspension cable installation method |
CN111456407A (en) * | 2020-04-15 | 2020-07-28 | 中国化学工程第三建设有限公司 | Method and device for constructing decoration and maintenance process of wall bodies at two ends below beam track by using travelling crane beam |
CN116290721B (en) * | 2023-05-17 | 2023-09-19 | 河北盛威建筑机械有限公司 | Telescopic hanging basket convenient for construction |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2794106B2 (en) * | 1994-10-05 | 1998-09-03 | ドーエイ外装有限会社 | Work gondola |
JPH09169481A (en) * | 1995-12-20 | 1997-06-30 | Hitachi Building Syst Co Ltd | Elevating device for installing elevator |
CN101338582B (en) * | 2008-07-25 | 2011-05-11 | 中铁四局集团有限公司 | Movable hanging basket type construction method for large-span large-breadth suspended ceiling |
CN202767494U (en) * | 2012-09-06 | 2013-03-06 | 安徽富煌钢构股份有限公司 | Hanging basket for high-altitude roof inner plate construction |
CN203701560U (en) * | 2013-12-31 | 2014-07-09 | 森特士兴集团股份有限公司 | Suspension hanging basket for high-altitude roofing inner plate construction |
-
2015
- 2015-01-15 CN CN201510021729.1A patent/CN104631810B/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN104631810A (en) | 2015-05-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104631810B (en) | High altitude moving hanging basket system and construction method | |
CN101476410B (en) | Mounting and demounting method for roof plate formwork support platform of concrete silo | |
CN205934747U (en) | A hang basket that is used for cantilever to pour bridge construction operation with pre -compaction structure | |
CN105621280B (en) | The apparatus and method for mounting and dismounting crane arm | |
CN204311719U (en) | External hanging type scaffold | |
CN102425261B (en) | Large-span multiunit tensile membrane structure and installation construction method thereof | |
CN208899886U (en) | Cantilever frame platform | |
CN101169001A (en) | Quadrangular pyramid sphere net case falsework-free constructing and mounting method and hoisting machine tool | |
CN205777580U (en) | Automatic lifting type discharging platform | |
CN105586832A (en) | Suspension type catwalk surface net mounting system | |
CN205442393U (en) | Posture that falls suspension system | |
CN112523112A (en) | Method for dismantling overhead suspension casting hanging basket | |
CN209308433U (en) | A kind of multi-functional trolley of Cast-in-situ Beam steel reinforcement cage binding installation | |
CN202000647U (en) | Base device for lifting scaffold in elevator shaft | |
CN101723240B (en) | Special fixture for hoisting rectangular section steel column and hoisting method by using same | |
CN214399282U (en) | Steel strand limiting and fixing device | |
CN213326443U (en) | Quick unloading platform | |
CN205591115U (en) | Suspension type catwalk veil installing the system | |
CN105060124B (en) | Intra-frame portal crane system and hoisting use method thereof | |
CN208684255U (en) | A kind of Elements of Space Grid Truss high altitude bulk assembled positioning device | |
CN209307871U (en) | A kind of hanging basket formwork Integral lifting device | |
CN202899720U (en) | Steel pole provided with foot treadles and used for high-tension transmission line iron tower | |
CN220599128U (en) | Assembled fixed suspension mechanism of electric hanging basket | |
CN205741935U (en) | The mounting and positioning device of Wavelike steel webplate | |
CN210216217U (en) | Road traffic signboard |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20180503 Address after: 610000 18 T District, 108 Jing Ye Road, Qingyang District, Chengdu, Sichuan. Patentee after: In the section of Construction Group Co. Ltd. Address before: 610027 1, 19 1, 1 ginkgo Road, Jinniu District, Chengdu, Sichuan. Patentee before: ZHONGYU YUANFA INTERNATIONAL CONSTRUCTION GROUP CO., LTD. |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160608 Termination date: 20180115 |