CN208899886U - Cantilever frame platform - Google Patents

Cantilever frame platform Download PDF

Info

Publication number
CN208899886U
CN208899886U CN201821254687.1U CN201821254687U CN208899886U CN 208899886 U CN208899886 U CN 208899886U CN 201821254687 U CN201821254687 U CN 201821254687U CN 208899886 U CN208899886 U CN 208899886U
Authority
CN
China
Prior art keywords
cantilever frame
draw piece
drawing device
hoisting hook
hook drawing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821254687.1U
Other languages
Chinese (zh)
Inventor
陈振明
吴曦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Steel Structure Engineering Co Ltd
Original Assignee
China Construction Steel Structure Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Steel Structure Corp Ltd filed Critical China Construction Steel Structure Corp Ltd
Priority to CN201821254687.1U priority Critical patent/CN208899886U/en
Application granted granted Critical
Publication of CN208899886U publication Critical patent/CN208899886U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a kind of cantilever frame platform, is related to the technical field of construction.Cantilever frame platform provided by the utility model includes: building structure main body and truss element;The side of building structure main body is provided with truss installa-tion face along the vertical direction;Truss element includes cantilever frame, removable connector, installation pillar, first hangs draw piece and the first hoisting hook drawing device;One end of cantilever frame is connected to truss installa-tion face by removable connector;The first end of installation pillar is connected to building structure main body, and second end extends to the top of cantilever frame;First first end for hanging draw piece is connected to the second end of installation pillar by the first hoisting hook drawing device, and the first second end for hanging draw piece is connected to cantilever frame;The length of draw piece is hung by the first hoisting hook drawing device, adjustable first.By cantilever frame platform provided by the utility model, alleviate that install working procedure present in cantilever frame in the prior art cumbersome, the technical issues of time-consuming feed consumption.

Description

Cantilever frame platform
Technical field
The utility model relates to the technical fields of construction, more particularly, to a kind of cantilever frame platform.
Background technique
Skyscraper is often designed with outer cantilevered structure in the middle and upper part high level position of its main structure.Megastore, shadow Depending on the heavy constructions extensive utilizations such as theater, stadiums, the conference and exhibition center and airport station large span space knot to come in every shape Structure system, to realize moulding abundant;It is the pith of large-span space structure system across cantilever design greatly.Outer cantilevered structure Primary structure form across cantilever design greatly has steel construction, steel-concrete combined structure and prestressed reinforced concrete construction.Outer overhanging Structure and the cantilever frame of steel construction is usually relied on across cantilever design greatly to realize, to meet wanting for structure stress and actual use It asks.Cantilever frame has the characteristics that span is big and moulding is complicated, and stability and safety are the key that design and construction, overhanging The installation of truss is to build outer cantilevered structure and the greatly important ring across cantilever design.
The installation of cantilever frame, which generally requires, in the prior art builds temporary support, is divided using lifting equipment Section lifting, supports using woods will support frame and fixes the free end of cantilever frame, then carries out butt welding to cantilever frame And connect its attached rod piece.
The construction of building of temporary support needs to put into lot of materials, mechanical equipment and manpower, and construction cost is higher, construction Duration is longer;The stability of temporary support is poor, there is the risk point compared with polydispersion.In addition, being installed in cantilever frame Afterwards, temporary support needs to remove, and demolishing process easily causes interference to ground construction work;In addition, temporary support needs to consume Take a large amount of disposable materials, cause to waste, increase construction cost, does not meet economic and environment-friendly construction theory.
In conclusion that there are working procedures is cumbersome for installation cantilever frame in the prior art, the technical issues of time-consuming feed consumption.
The information disclosed in the background technology section is intended only to deepen the reason to the general background technology of the utility model Solution, and it is known to those skilled in the art existing to be not construed as recognizing or imply that the information is constituted in any form Technology.
Utility model content
The purpose of this utility model is to provide a kind of cantilever frame platforms, install cantilever frame in the prior art to alleviate The technical issues of existing working procedure is cumbersome, time-consuming feed consumption.
Cantilever frame platform provided by the utility model includes: building structure main body and truss element;Building structure main body Side be provided with truss installa-tion face along the vertical direction;Truss element includes cantilever frame, removable connector, installation branch Column, first hang draw piece and the first hoisting hook drawing device;One end of cantilever frame is connected to truss installa-tion by removable connector Face;The first end of installation pillar is connected to building structure main body, and second end extends to the top of cantilever frame;First hangs draw piece First end is connected to the second end of installation pillar by the first hoisting hook drawing device, and the first second end for hanging draw piece is connected to overhanging Truss;The length of draw piece is hung by the first hoisting hook drawing device, adjustable first.
Further, truss element further includes second hanging draw piece and the second hoisting hook drawing device, and second hangs the first of draw piece End is connected to the second end of installation pillar by the second hoisting hook drawing device, and the second second end for hanging draw piece is connected to building structure Main body;First, which hangs draw piece and second, hangs draw piece positioned at the two sides of installation pillar;By the second hoisting hook drawing device, it is adjusted second Hang the length of draw piece.
Further, truss element further includes that third hangs draw piece and third hoisting hook drawing device;Third hangs the first of draw piece End is connected to the second end of installation pillar by third hoisting hook drawing device, and the second end that third hangs draw piece is connected to overhanging purlin Frame;By third hoisting hook drawing device, adjustable third hangs the length of draw piece;And the second end that third hangs draw piece is located at first The second end of draw piece is hung close to the side of building structure main body.
Further, the first hoisting hook drawing device and the second hoisting hook drawing device include bottle gouard moved by hands.
Further, the first end for installing pillar is connected with muti-piece pillar stiffener, muti-piece pillar stiffener with building Main structure body connection, and along the circumferentially distributed of installation pillar.
Further, truss element further includes the first cable wind rope and the second cable wind rope, the first cable wind rope and the second cable wind rope Equal one end is connected to building structure main body, and the other end is connected to cantilever frame;First cable wind rope and the second cable wind rope are located at The two sides of the vertical plane of cantilever frame.
Further, the first cable wind rope and the second cable wind rope are located at same level.
Further, cantilever frame platform provided by the utility model includes more truss structure units, and more truss structure units exist It is spaced apart on truss installa-tion face along level aspect, and is provided with support connector between adjacent two truss structures unit.
Further, support connector includes more connecting rods, and the both ends of more connecting rods are connected to adjacent two Pin Cantilever frame.
Further, removable connector includes connecting plate, and connecting plate is fixedly connected on truss installa-tion face, cantilever frame Lapping ends are in connecting plate.
Cantilever frame platform provided by the utility model, is related to the technical field of construction.It is provided by the utility model Cantilever frame platform includes: building structure main body and truss element;The side of building structure main body is provided with along the vertical direction Truss installa-tion face;Truss element includes cantilever frame, removable connector, installation pillar, first hangs draw piece and the first hoisting hook Drawing device;One end of cantilever frame is connected to truss installa-tion face by removable connector;The first end of installation pillar is connected to Building structure main body, second end extend to the top of cantilever frame;First first end for hanging draw piece is loaded by the first hoisting hook The second end for being connected to installation pillar is set, the first second end for hanging draw piece is connected to cantilever frame;It is loaded by the first hoisting hook It sets, adjustable first hangs the length of draw piece.Using cantilever frame platform provided by the utility model come installation cantilever frame, One end of cantilever frame is connected to building structure main body by removable connector;By installation pillar, first hang draw piece and Cantilever frame is carried out suspension tension by the first hoisting hook drawing device.Cantilever frame is temporarily fixed on building in this way, being achieved that Main structure body, convenient for will be welded and fixed between cantilever frame and building structure main body in finishing operations, and in overhanging purlin The node that frame is segmented position carries out weld job and connects attached rod piece.
Installation pillar in cantilever frame platform provided by the utility model, first hang draw piece and the first hoisting hook drawing device Installation process it is simple, be easy to dismount, can be recycled for multiple times, reduce disposable material consuming.Compared to existing There is the temporary support that cantilever frame is used to support in technology, occupied area is small, and difficulty of construction is small, is more applicable for more than the convolution Implement the lesser construction site in ground.
Therefore, by cantilever frame platform provided by the utility model, installation cantilever frame institute in the prior art is alleviated The technical issues of existing working procedure is cumbersome, time-consuming feed consumption.
To enable the above objects, features, and advantages of the utility model to be clearer and more comprehensible, be cited below particularly the utility model compared with Good embodiment, and cooperate appended attached drawing, it is described below in detail.
Detailed description of the invention
It, below will be right in order to illustrate more clearly of specific embodiment of the present invention or technical solution in the prior art Specific embodiment or attached drawing needed to be used in the description of the prior art are briefly described, it should be apparent that, it is described below In attached drawing be that some embodiments of the utility model are not paying creativeness for those of ordinary skill in the art Under the premise of labour, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is the side view of the first embodiment of cantilever frame platform provided by the embodiment of the utility model;
Fig. 2 is the partial enlarged view in Fig. 1 at A;
Fig. 3 is the top view of the first embodiment of cantilever frame platform provided by the embodiment of the utility model;
Fig. 4 is the top view of second of embodiment of cantilever frame platform provided by the embodiment of the utility model.
Icon: 011- building structure main body;012- cantilever frame;02- installs pillar;031- first hangs draw piece;032- Two hang draw piece;033- third hangs draw piece;041- the first hoisting hook drawing device;042- the second hoisting hook drawing device;043- third rises Drawing device is hung again;The first cable wind rope of 051-;The second cable wind rope of 052-;06- connecting plate;07- connecting rod.
Specific embodiment
The technical solution of the utility model is clearly and completely described below in conjunction with attached drawing, it is clear that described Embodiment is the utility model a part of the embodiment, instead of all the embodiments.Based on the embodiments of the present invention, originally Field those of ordinary skill every other embodiment obtained without making creative work belongs to practical Novel protected range.
It is in the description of the present invention, it should be noted that term " center ", "upper", "lower", "left", "right", " perpendicular Directly ", the orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" is to be based on the orientation or positional relationship shown in the drawings, and is only For ease of description the utility model and simplify description, rather than the device or element of indication or suggestion meaning must have it is specific Orientation, be constructed and operated in a specific orientation, therefore should not be understood as limiting the present invention.In addition, term " the One ", " second ", " third " are used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " is pacified Dress ", " connected ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integrally Connection;It can be mechanical connection, be also possible to be electrically connected;Can be directly connected, can also indirectly connected through an intermediary, It can be the connection inside two elements.For the ordinary skill in the art, above-mentioned art can be understood with concrete condition The concrete meaning of language in the present invention.
Cantilever frame platform provided by the embodiment of the utility model includes: building structure main body 011 and truss element;Building The side of main structure body 011 is provided with truss installa-tion face along the vertical direction;Truss element includes cantilever frame 012, detachable Connector, installation pillar 02, first hang draw piece 031 and the first hoisting hook drawing device 041;One end of cantilever frame 012 passes through can Dismantling connection part is connected to truss installa-tion face;The first end of installation pillar 02 is connected to building structure main body 011, and second end extends To the top of cantilever frame 012;First first end for hanging draw piece 031 is connected to installation branch by the first hoisting hook drawing device 041 The second end of column 02, the first second end for hanging draw piece 031 are connected to cantilever frame 012;By the first hoisting hook drawing device 041, Adjustable first hangs the length of draw piece 031.
Specifically, led to using cantilever frame platform provided by the embodiment of the utility model come installation cantilever frame 012 It crosses removable connector and one end of cantilever frame 012 is connected to building structure main body 011;It is hung by installation pillar 02, first Cantilever frame 012 is carried out suspension tension by draw piece 031 and the first hoisting hook drawing device 041.In this way, being achieved that cantilever frame 012 is temporarily fixed on building structure main body 011, convenient in finishing operations, by cantilever frame 012 and building structure main body 011 it Between be welded and fixed, and carry out weld job in the node that cantilever frame 012 is segmented position and connect attached rod piece.
Installation pillar 02 in cantilever frame platform provided by the embodiment of the utility model, first hang draw piece 031 and first The installation process of hoisting hook drawing device 041 is simple, is easy to dismount, and can be recycled for multiple times, and disposable material is reduced Material expends.The temporary support of cantilever frame 012 is used to support in compared with the prior art, occupied area is small, and difficulty of construction is small, It is more applicable for implementing in the lesser construction site of the room for maneuver.
Specifically, in the assembled moulding bed of ground setting truss, assembled cantilever frame 012 is welded;And in cantilever frame 012 Upper welding lifting lug hangs draw piece 031 for lifting and connecting first.
Specifically, installation pillar 02 extends along the vertical direction, and top is provided with for connecting with the first hoisting hook drawing device 041 The lifting lug connect.One end of first hoisting hook drawing device 041 is connect with installation pillar 02, and draw piece 031 is hung in other end connection first First end.
By the first hoisting hook drawing device 041, the first length for hanging draw piece 031 is adjusted, makes first to hang the tension of draw piece 031.
In some embodiments, first draw piece 031 is hung using wirerope.
In some embodiments, first draw piece 031 is hung using pull rod, pull rod passes through wirerope and the first hoisting hook drawing device 041 connection.
In some embodiments, building structure main body 011 is steel construction, and installation pillar 02 is welded in building structure main body On 011.
In some embodiments, building structure main body 011 is concrete structure;When building structure main body 011 is constructed, if Built-in fitting is set, for connecting installation pillar 02.
As another embodiment, cantilever frame 012 can be replaced cantilever frame section.Cantilever frame section is connected to and is built In building structure main body 011, then continue to splice cantilever frame far from one end of building structure main body 011 in the cantilever frame section Section.
Further, truss element further includes second hanging draw piece 032 and the second hoisting hook drawing device 042, and second hangs draw piece 032 first end is connected to the second end of installation pillar 02 by the second hoisting hook drawing device 042, and second hangs the of draw piece 032 Two ends are connected to building structure main body 011;First, which hangs draw piece 031 and second, hangs draw piece 032 positioned at the two sides of installation pillar 02;It is logical The second hoisting hook drawing device 042 is crossed, adjustable second hangs the length of draw piece 032.
Specifically, Fig. 1 is please referred to, the top of installation pillar 02 is oppositely arranged that there are two lifting lugs, is respectively used to connection first Hoisting hook drawing device 041 and the second hoisting hook drawing device 042.It is provided with lifting lug in building structure main body 011, which is located at peace Fill side of the pillar 02 far from truss installa-tion face.
First, which hangs draw piece 031 and second, hangs draw piece 032 respectively from the two sides of installation pillar 02 to the installation application drawing of pillar 02 Power can make the structure for installing pillar 02 more stable.
Further, truss element further includes that third hangs draw piece 033 and third hoisting hook drawing device 043;Third hangs draw piece 033 first end is connected to the second end of installation pillar 02 by third hoisting hook drawing device 043, and third hangs the of draw piece 033 Two ends are connected to cantilever frame 012;By third hoisting hook drawing device 043, adjustable third hangs the length of draw piece 033;And The second end that third hangs draw piece 033 is located at first and hangs the second end of draw piece 031 close to the side of building structure main body 011.
Specifically, first draw piece 031 is hung and third hangs draw piece 033 and the stress of cantilever frame 012 can be made more to disperse, thus Improve the stability of structure.
It is completed between cantilever frame 012 and building structure main body 011 after being welded to connect, third hangs draw piece 033 and third rises Hanging drawing device 043 again can disassemble respectively, carry out circulation and be used for multiple times.
Further, the first hoisting hook drawing device 041, the second hoisting hook drawing device 042 and third hoisting hook drawing device 043 It is all made of bottle gouard moved by hands.
Specifically, it first hangs draw piece 031, second hang draw piece 032 and third hangs draw piece 033 one end is connected to a hand respectively Dynamic cucurbit, convenient for manually hanging draw piece 031 by bottle gouard moved by hands respectively to first, second hanging draw piece 032 and third hangs draw piece 033 length is adjusted, and makes to install pillar 02 and the stress of cantilever frame 012 is more balanced.
In some embodiments, second draw piece 032 is hung and third hangs draw piece 033 and is all made of wirerope.
Further, the first end for installing pillar 02 is connected with muti-piece pillar stiffener, muti-piece pillar stiffener with build Building structure main body 011 connects, and along the circumferentially distributed of installation pillar 02.
Specifically, the two sides of pillar stiffener are welded to connect with installation pillar 02 and building structure main body 011 respectively, favorably It connect with building structure main body 011 stronger in making to install pillar 02, improves the intensity for installing pillar 02.
Further, truss element further includes the first cable wind rope 051 and the second cable wind rope 052, the first cable wind rope 051 and The equal one end of two cable wind rope 052 is connected to building structure main body 011, and the other end is connected to cantilever frame 012;First cable wind rope 051 The two sides of the vertical plane of cantilever frame 012 are located at the second cable wind rope 052.
Specifically, referring to figure 3., the first cable wind rope 051 and the second cable wind rope 052 are horizontally extending, and position In the same horizontal plane.In this way, being conducive to the active force and the second cable wind rope 052 that make the first cable wind rope 051 to cantilever frame 012 To the resultant force of the active force of cantilever frame 012 along the length direction of cantilever frame 012.
First cable wind rope 051 and the second cable wind rope 052 apply pulling force to opposite two sides respectively to cantilever frame 012, can Keep the position at the overhanging end of cantilever frame 012 more stable.By the length and the second cable wind rope that adjust the first cable wind rope 051 052 length, can the position at overhanging end to cantilever frame 012 be adjusted.
Further, referring to figure 4., cantilever frame platform provided by the embodiment of the utility model includes more truss structure lists Member, more truss structure units are spaced apart in terms of the level on truss installa-tion face, and are arranged between adjacent two truss structures unit There is support connector.
Specifically, more truss structure units can successively be built in one direction or more truss structure units are synchronized and built.
Support connector includes more connecting rods 07, and more connecting rods 07 distinguish the overhanging in one end and a truss structure unit Truss 012 connects, and the other end is connect with cantilever frame 012 in adjacent another truss structure unit.Support connector can make more Pin The whole structure of truss element composition is more firm.
In some embodiments, it is welded to connect between connecting rod 07 and cantilever frame 012.
Further, removable connector includes connecting plate 06, and connecting plate 06 is fixedly connected on truss installa-tion face, overhangs purlin The lapping ends of frame 012 are in connecting plate 06.
Specifically, referring to figure 2., connecting plate 06 is bolted to connection in building structure main body 011.Cantilever frame 012 lapping ends connecting with truss installa-tion face are in connecting plate 06;Connecting plate 06 applies upward support to cantilever frame 012 Power.After cantilever frame 012 and building structure main body 011 are completed to be welded to connect, connecting plate 06 can be removed;Connecting plate 06 can follow Ring uses.
Using cantilever frame platform provided by the embodiment of the utility model, the step of installation method of cantilever frame 012, is wrapped It includes: installation pillar 02 is connected in building structure main body 011;By the lifting of cantilever frame 012 to the purlin of building structure main body 011 One end of cantilever frame 012 and truss installa-tion face are attached, cantilever frame 012 by frame mounting surface using removable connector Positioned at the lower section on the top of installation pillar 02;The first end that first hangs draw piece 031 is connected by the first hoisting hook drawing device 041 In the top of installation pillar 02, the first second end for hanging draw piece 031 is connected to cantilever frame 012;It is loaded by the first hoisting hook The length that draw piece 031 is hung in 041 adjustment first is set, to adjust the overhanging end absolute altitude of cantilever frame 012;To cantilever frame 012 with build It is welded to connect between building structure main body 011;It removes first and hangs draw piece 031 and the first hoisting hook drawing device 041.
Specifically, cantilever frame 012 can be completed welding assembly on ground;Cantilever frame section can also be connected to building knot In structure main body 011, connect paragraph by paragraph.
In some embodiments, it installs between pillar 02 and building structure main body 011 and also to hang draw piece 032 and the by second Two hoisting hook drawing devices 042 connection, to provide the stability of installation pillar 02.
In some embodiments, cantilever frame 012 is also tied by the first cable wind rope 051 and the second cable wind rope 052 with building Structure main body 011 connects, and the first cable wind rope 051 and the second cable wind rope 052 are located at the two sides of cantilever frame 012, so as to overhang The stability of 012 horizontal position of truss.
It is completed between cantilever frame 012 and building structure main body 011 after being welded to connect, draw piece 031, second can be hung by first Hang draw piece 032, the first hoisting hook drawing device 041, the second hoisting hook drawing device 042, the first cable wind rope 051 and the second cable wind rope 052 can disassemble respectively, be used for multiple times.
Further, the step of draw piece 031 and the first hoisting hook drawing device 041 are hung in dismounting first includes: that unloading first is hung The pulling force of draw piece 031;And during unloading, deformation monitoring is carried out to cantilever frame 012.
Specifically, by the first hoisting hook drawing device 041, the first length elongation for hanging draw piece 031 can be made, gradually with gradually The pulling force of draw piece 031 is hung in unloading first.During the pulling force for hanging draw piece 031 to first unloads, to cantilever frame 012 Deformation monitoring, the self-strength to observe cantilever frame 012 and the bonding strength between building structure main body 011 are carried out, from And reinforcement of weld can be carried out in time to intensity node not up to standard.
Specifically, using cantilever frame platform provided by the embodiment of the utility model, the installation method of cantilever frame 012 Step includes:
Step 1, the assembled moulding bed of ground setting cantilever frame 012, completes the welding of cantilever frame 012 or cantilever truss section It is assembled.
Step 2, the section form and size of installation pillar 02 are determined by calculating, pillar is welded in the bottom of installation pillar 02 Stiffener, and be welded to connect in building structure main body 011.
Step 3, cantilever frame 012 is hoisted to the truss installa-tion face of building structure main body 011 using lifting equipment, and is led to Removable connector is crossed to be fixed temporarily.
Step 4, installation pillar 02 is outer connect directed through bottle gouard moved by hands and wirerope with cantilever frame 012.Pillar is installed It is connect directed through bottle gouard moved by hands and wirerope with building structure main body 011 in 02.Wirerope is tensed by bottle gouard moved by hands;
Horizontal symmetrical drawing sets the first cable wind rope 051 and the second cable wind rope 052.
Step 5, steel wire tensioning degree is adjusted by bottle gouard moved by hands, and then adjusts the mark at the overhanging end of cantilever frame 012 It is high;The horizontal position at the overhanging end of cantilever frame 012 is adjusted by the first cable wind rope 051 and the second cable wind rope 052.
Step 6, after cantilever frame 012 is adjusted in place, the weld job of connecting node is completed.
Step 7, connection support connector between adjacent two Pin cantilever frame 012 or cantilever frame section, forms stable sky Between structural unit.
Step 8, after cantilever frame 012 forms stable space structure unit, the stretching force of wirerope is slowly unloaded.
Finally, it should be noted that all the embodiments in this specification are described in a progressive manner, each embodiment What is stressed is all differences from other embodiments, and same and similar part cross-reference is between each embodiment It can;The above various embodiments is only to illustrate the technical solution of the utility model, rather than its limitations;Although referring to aforementioned each implementation The utility model is described in detail in example, those skilled in the art should understand that: it still can be to aforementioned Technical solution documented by each embodiment is modified, or equivalent substitution of some or all of the technical features; In the absence of conflict, the features in the embodiments and the embodiments of the present application can be combined with each other.And these modifications, replacement Or combination, the scope of the technical solutions of the embodiments of the utility model that it does not separate the essence of the corresponding technical solution.

Claims (10)

1. a kind of cantilever frame platform characterized by comprising building structure main body and truss element;The building structure master The side of body is provided with truss installa-tion face along the vertical direction;The truss element includes cantilever frame, removable connector, peace Dress pillar, first hang draw piece and the first hoisting hook drawing device;
One end of the cantilever frame is connected to the truss installa-tion face by the removable connector;
The first end of the installation pillar is connected to the building structure main body, and second end extends to the upper of the cantilever frame Side;
Described first first end for hanging draw piece is connected to the second end of the installation pillar by the first hoisting hook drawing device, Described first second end for hanging draw piece is connected to the cantilever frame;By the first hoisting hook drawing device, it is adjusted first Hang the length of draw piece.
2. cantilever frame platform according to claim 1, which is characterized in that the truss element further includes second hanging draw piece With the second hoisting hook drawing device, the described second first end for hanging draw piece is connected to the peace by the second hoisting hook drawing device The second end of pillar is filled, the described second second end for hanging draw piece is connected to the building structure main body;Described first hang draw piece and Described second hangs the two sides that draw piece is located at the installation pillar;
The length of draw piece is hung by the second hoisting hook drawing device, adjustable second.
3. cantilever frame platform according to claim 2, which is characterized in that the truss element further includes that third hangs draw piece With third hoisting hook drawing device;
The first end that the third hangs draw piece is connected to the second end of the installation pillar by the third hoisting hook drawing device, The second end that the third hangs draw piece is connected to the cantilever frame;By the third hoisting hook drawing device, third is adjusted Hang the length of draw piece;And the second end that the third hangs draw piece is located at described first and hangs the second end of draw piece close to the building The side of main structure body.
4. cantilever frame platform according to claim 3, which is characterized in that the first hoisting hook drawing device, described Two hoisting hook drawing devices and third hoisting hook drawing device include bottle gouard moved by hands.
5. cantilever frame platform according to claim 1, which is characterized in that the first end of the installation pillar is connected with more Block pillar stiffener, pillar stiffener described in muti-piece are connect with the building structure main body, and along the week of the installation pillar To distribution.
6. cantilever frame platform according to claim 1-5, which is characterized in that the truss element further includes One cable wind rope and the second cable wind rope, first cable wind rope and described equal one end of second cable wind rope are connected to the building structure master Body, the other end are connected to the cantilever frame;
First cable wind rope and second cable wind rope are located at the two sides of the vertical plane of the cantilever frame.
7. cantilever frame platform according to claim 6, which is characterized in that first cable wind rope and second guy Rope is located at same level.
8. cantilever frame platform according to claim 6, which is characterized in that the cantilever frame platform includes described in more Pin Truss element, truss element described in more Pin on the truss installa-tion face along level in terms of be spaced apart, and adjacent two Pin institute It states and is provided with support connector between truss element.
9. cantilever frame platform according to claim 8, which is characterized in that the support connector includes more connections Bar, the both ends of the more connecting rods are connected to cantilever frame described in adjacent two Pin.
10. cantilever frame platform according to claim 1, which is characterized in that the removable connector includes connecting plate, The connecting plate is fixedly connected on the truss installa-tion face, and the lapping ends of the cantilever frame are in the connecting plate.
CN201821254687.1U 2018-08-03 2018-08-03 Cantilever frame platform Active CN208899886U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821254687.1U CN208899886U (en) 2018-08-03 2018-08-03 Cantilever frame platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821254687.1U CN208899886U (en) 2018-08-03 2018-08-03 Cantilever frame platform

Publications (1)

Publication Number Publication Date
CN208899886U true CN208899886U (en) 2019-05-24

Family

ID=66568755

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821254687.1U Active CN208899886U (en) 2018-08-03 2018-08-03 Cantilever frame platform

Country Status (1)

Country Link
CN (1) CN208899886U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756254A (en) * 2018-08-03 2018-11-06 中建钢构有限公司 The installation method of cantilever frame platform and cantilever frame
CN110725551A (en) * 2019-07-31 2020-01-24 中冶(上海)钢结构科技有限公司 Method for mounting high-altitude large cantilever steel beam without diagonal draw bar
CN111395777A (en) * 2020-04-24 2020-07-10 五冶集团上海有限公司 Construction method of mounting cantilever platform of preheating tower
CN114991106A (en) * 2022-07-01 2022-09-02 湖北海洋工程装备研究院有限公司 Platform floats outward

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756254A (en) * 2018-08-03 2018-11-06 中建钢构有限公司 The installation method of cantilever frame platform and cantilever frame
CN110725551A (en) * 2019-07-31 2020-01-24 中冶(上海)钢结构科技有限公司 Method for mounting high-altitude large cantilever steel beam without diagonal draw bar
CN111395777A (en) * 2020-04-24 2020-07-10 五冶集团上海有限公司 Construction method of mounting cantilever platform of preheating tower
CN114991106A (en) * 2022-07-01 2022-09-02 湖北海洋工程装备研究院有限公司 Platform floats outward
CN114991106B (en) * 2022-07-01 2024-01-16 湖北海洋工程装备研究院有限公司 Outward floating platform

Similar Documents

Publication Publication Date Title
CN208899886U (en) Cantilever frame platform
CN208430687U (en) Self-anchored type suspended-cable structure support construction and system
CN102359302B (en) Extra-high voltage large-span iron tower assembling method
CN104746883B (en) A kind of arcuate space truss lifts construction method of installation with three machines
CN104234200B (en) A kind of suspen-shell structure rope leverage is by ring lifting installation method
CN102936962A (en) Construction method of slanting cantilever steel structure supported by temporary steel frame
CN108612187A (en) A kind of welding ball grid assembling and construction method
CN109138454A (en) A kind of installation method of super high-rise building outline border bandy truss
CN206692235U (en) A kind of steel structure dome lifts by crane erecting device
CN105804400A (en) Hoisting construction method of curved truss
CN102108748B (en) Quadrilateral endless rope chord supporting structure and construction process
CN105040591B (en) A kind of positioner of Wavelike steel webplate and its localization method
CN101503908A (en) Construction method for spacing suspension cable structural template support platform
CN108894496A (en) A kind of over-the-counter construction method of Large-span Truss String Structure beam
CN109826082B (en) Construction method for installing decorative structure in multi-tower combined space of cable-stayed bridge
CN108842954A (en) A kind of huge different section Honeycomb Beam structural system construction method of installation of aerofoil profile roofing
CN109231023A (en) The installation method of high pedestal jib crane boom system
CN208534069U (en) The assembled support device of steel bar truss floor support plate composite floor system
CN108756254A (en) The installation method of cantilever frame platform and cantilever frame
CN203559570U (en) Operating platform for steel pipe support frame overhung on surrounding columns
CN215166467U (en) Be suitable for under steel construction of segmentation promotion construction to hang piping lane
CN104085832A (en) Flexible component lifting device and lifting method thereof
CN210288878U (en) Precast concrete Y type roof beam subassembly
CN208685464U (en) A kind of bridge pier column template
CN110219416B (en) Precast concrete Y-shaped beam assembly and construction method thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 3801, 38 / F, Zhongjian science and engineering building, No. 3331, Weilan Coast Community Center Road, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee after: China Construction Engineering Group Co.,Ltd.

Address before: 518000 Guangdong city of Shenzhen province Nanshan District Guangdong streets Center Road No. 3331 steel built in 27 storey building room 2701

Patentee before: China Construction Steel Structure Corp.,Ltd.

CP03 Change of name, title or address
TR01 Transfer of patent right

Effective date of registration: 20210301

Address after: No.1908, Zhongtian Meijing building, No.2009, Pingshan Avenue, Liulian community, Pingshan street, Pingshan District, Shenzhen, Guangdong 518000

Patentee after: China Construction Steel Engineering Co.,Ltd.

Address before: 3801, 38 / F, China Construction Science and engineering building, No. 3331, Weilan Coast Community Central Road, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province