CN202767494U - Hanging basket for high-altitude roof inner plate construction - Google Patents

Hanging basket for high-altitude roof inner plate construction Download PDF

Info

Publication number
CN202767494U
CN202767494U CN201220452475.0U CN201220452475U CN202767494U CN 202767494 U CN202767494 U CN 202767494U CN 201220452475 U CN201220452475 U CN 201220452475U CN 202767494 U CN202767494 U CN 202767494U
Authority
CN
China
Prior art keywords
hanging basket
roof
suspension cable
hanging
roof inner
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201220452475.0U
Other languages
Chinese (zh)
Inventor
何焰江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Fuhuang Steel Structure Co Ltd
Original Assignee
Anhui Fuhuang Steel Structure Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Fuhuang Steel Structure Co Ltd filed Critical Anhui Fuhuang Steel Structure Co Ltd
Priority to CN201220452475.0U priority Critical patent/CN202767494U/en
Application granted granted Critical
Publication of CN202767494U publication Critical patent/CN202767494U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses a hanging basket for high-altitude roof inner plate construction. The hanging basket is characterized by comprising a hanging basket suspended cable and a frame-type hanging basket body. Two ends of a steel wire rope are respectively and fixedly connected to roof steel beams at two ends of a main body structure through ring clamps, and the two roof steel beams and the steel wire rope connected between the two beams form the hanging basket suspended cable. A hanging ring is arranged on the periphery of the hanging basket body and hung on the hanging basket suspended cable through a U-shaped clamp which is inverted. The hanging ring can slide along the hanging basket suspended cable. The hanging basket enables construction of inner plates of extra-large steel structure factory building roofs to be fast and safe.

Description

High-altitude roof inner slab construction hanging basket
Technical field
The utility model relates to a kind of steel structural overhead roof inner slab construction hanging basket.
Background technology
In field of steel structure, the super large steel-structure factory building is increasing, and the roof inner slab terrain clearance is also more and more higher, and its roof inner slab difficulty of construction is increasing; Because roof inner slab is on girder steel, below roof purline, traditional ground moving operating platform can not satisfy construction needs and safe handling requirement, has seriously restricted construction speed, has greatly increased construction cost.
Summary of the invention
The utility model is for avoiding the existing weak point of above-mentioned prior art, providing the roof inner slab construction of a kind of high-altitude to use hanging basket, so that the construction of super large steel structural plant roof inner panel is more quick, safety.
The utility model is that the technical solution problem adopts following technical scheme:
The roof inner slab construction of a kind of high-altitude of the utility model is to arrange with the design feature of hanging basket:
One hanging basket suspension cable is that the two ends with wire rope are fixedly connected on the steel roof joist at agent structure two ends by annular snap respectively; Consist of the hanging basket suspension cable with described two ends steel roof joist and the wire rope that is connected to therebetween;
One frame type hanging basket is provided with suspension ring in the periphery of described hanging basket, and described suspension ring are hung on the hanging basket suspension cable by inverted " U " shape card, and can slide at the hanging basket suspension cable.
The roof inner slab construction of the utility model high-altitude also is with the design feature of hanging basket:
Described hanging basket suspension cable be the twice that be arranged in parallel be one group; Described frame type hanging basket is to hang on twice hanging basket suspension cable so that dual-side is parallel.
The hanging basket suspension cable that the four road hanging basket suspension cables that be arranged in parallel between the twice steel roof joist, two frame type hanging baskets are separately positioned on separately can synchronizing moving.
Compared with the prior art, the utility model beneficial effect is embodied in:
The utility model utilizes hanging basket to realize the construction of superelevation roof inner slab, and work progress is efficient, quick; Easy construction, safety, reliability.
Description of drawings
Fig. 1 is the utility model structural representation;
Fig. 2 is the utility model section of structure;
Fig. 3 is the utility model frame type barrel structure schematic diagram;
Number in the figure: 1 hanging basket; 2 wire rope; 3 steel roof joists; 4 roof inner slabs; 5 roofing outside plates; 6 roof purlines; 7 angle steel; 8 round steel; 9 suspension ring.
The specific embodiment
Referring to Fig. 1, Fig. 2 and Fig. 3, the construction of the present embodiment high and medium roof inner slab is set to the structure of hanging basket:
One hanging basket suspension cable is to be that the two ends of the wire rope 2 of 20mm are fixedly connected on the steel roof joist 3 at agent structure two ends by annular snap respectively with diameter, and per 30 meters of wire rope 2 arranges temporary fixed point at middle girder steel; Consist of the hanging basket suspension cables with twice steel roof joist 3 and the wire rope 2 that is connected to therebetween;
One frame type hanging basket is provided with suspension ring 9 in the periphery of hanging basket 1, and suspension ring 9 are hung on the hanging basket suspension cable by inverted " U " shape card, and can slide at the hanging basket suspension cable.In order to reduce friction, can be on wire rope 2 coating butter, play lubricated effect.
In the implementation, the hanging basket suspension cable be the twice that be arranged in parallel be one group; The frame type hanging basket adopts rectangular configuration, hangs on twice hanging basket suspension cable so that its dual-side is parallel.
Because roof inner slab has certain length, therefore, the four road hanging basket suspension cables that can between the twice steel roof joist, be arranged in parallel, two frame type hanging baskets respectively can synchronizing moving at suspension cable separately.
Existing part roof inner slab 4 has been finished installation among Fig. 1 and Fig. 2, and roofing outside plate 5 and roof purline 6 are by the designing requirement construction; The hanging basket of frame type shown in Fig. 31 is take angle steel 7 as framework, at the fixing welding of angle steel 7 round steel 8, and the fixing welding hanging ring 9 on the top of round steel 8.
Bracketplant constructing operation method
After wire rope 2 and frame type hanging basket 1 is all in place, upper three people in each frame type hanging basket, two frame type hanging baskets arranged side by side are one group, according to the distance between the length adjustment of roof inner slab two frame type hanging baskets arranged side by side.Begin to install first roof inner slab from the original position of roof inner slab, install between first roof inner slab, second roof inner slab then is installed; Stand in two personnel's synchronizing moving hanging baskets in the frame type hanging basket mobile forward, mobile method is that hand is grabbed roof purline, and both hands firmly drop backward, slowly the frame type hanging basket are moved forward, finish successively the installation of the 3rd, the 4th roof inner slab;
Because agent structure length is usually very large, wire rope 2 has about 100 ~ 200 meters usually, and per 30 meters of wire rope arranges temporary fixed point at middle girder steel, the like; Wire rope is below girder steel, hanging basket can directly be slided over, after the workman operates wire rope and arrives temporary fixed point, solve the constraint of temporary fixed point, hanging basket is slided in the past, recover subsequently the constraint of temporary fixed point, proceed the roof inner slab construction, until the whole installations of roof inner slab.

Claims (3)

1. hanging basket is used in a high-altitude roof inner slab construction, it is characterized in that arranging:
One hanging basket suspension cable is that the two ends with wire rope (2) are fixedly connected on the steel roof joist (3) at agent structure two ends by annular snap respectively; Consist of the hanging basket suspension cable with described two ends steel roof joists (3) and the wire rope (2) that is connected to therebetween;
One frame type hanging basket is provided with suspension ring (9) in the periphery of described hanging basket (1), and described suspension ring (9) are hung on the hanging basket suspension cable by inverted " U " shape card, and can slide at the hanging basket suspension cable.
2. hanging basket is used in roof inner slab construction in high-altitude according to claim 1, it is characterized in that described hanging basket suspension cable be the twice that be arranged in parallel be one group; Described frame type hanging basket (1) is to hang on twice hanging basket suspension cable so that dual-side is parallel.
3. high-altitude according to claim 1 roof inner slab construction hanging basket, it is characterized in that: the four road hanging basket suspension cables that be arranged in parallel between twice steel roof joist (3), the hanging basket suspension cable that two frame type hanging baskets (1) are separately positioned on separately can synchronizing moving.
CN201220452475.0U 2012-09-06 2012-09-06 Hanging basket for high-altitude roof inner plate construction Expired - Lifetime CN202767494U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201220452475.0U CN202767494U (en) 2012-09-06 2012-09-06 Hanging basket for high-altitude roof inner plate construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201220452475.0U CN202767494U (en) 2012-09-06 2012-09-06 Hanging basket for high-altitude roof inner plate construction

Publications (1)

Publication Number Publication Date
CN202767494U true CN202767494U (en) 2013-03-06

Family

ID=47774077

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201220452475.0U Expired - Lifetime CN202767494U (en) 2012-09-06 2012-09-06 Hanging basket for high-altitude roof inner plate construction

Country Status (1)

Country Link
CN (1) CN202767494U (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104060813A (en) * 2014-07-02 2014-09-24 浙江省二建钢结构有限公司 Construction device and method for large-span steel girder frame connection platform
CN104358393A (en) * 2014-10-24 2015-02-18 中铁航空港建设集团北京有限公司 Horizontal moving platform hung at high altitude
CN104631810A (en) * 2015-01-15 2015-05-20 中誉远发国际建设集团有限公司 High-altitude movable hanging basket system and construction method thereof
CN104963495A (en) * 2015-06-05 2015-10-07 中国十七冶集团有限公司 Suspension hanging basket for installation of roof surface bottom layer color plate
CN105155832A (en) * 2015-06-17 2015-12-16 中建钢构有限公司 Hanging basket device and moving method thereof
CN105715032A (en) * 2016-04-15 2016-06-29 中国五冶集团有限公司 Construction hanging basket with spanning movement function and spanning movement method
CN104060809B (en) * 2014-07-16 2016-07-06 深圳市特艺达装饰设计工程有限公司 A kind of roofing daylighting glass steelframe installs equipment and operation method thereof
CN106115573A (en) * 2016-08-19 2016-11-16 中国化学工程第三建设有限公司 The installation equipment of factory roof coloured silk steel inner panel and installation method
CN108468433A (en) * 2018-04-12 2018-08-31 陈年康 A kind of construction tool of workshop metal Roof inner panel

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104060813A (en) * 2014-07-02 2014-09-24 浙江省二建钢结构有限公司 Construction device and method for large-span steel girder frame connection platform
CN104060813B (en) * 2014-07-02 2016-06-08 浙江省二建钢结构有限公司 The constructing device of large-span steel girder framework connection mode platform and constructional method
CN104060809B (en) * 2014-07-16 2016-07-06 深圳市特艺达装饰设计工程有限公司 A kind of roofing daylighting glass steelframe installs equipment and operation method thereof
CN104358393A (en) * 2014-10-24 2015-02-18 中铁航空港建设集团北京有限公司 Horizontal moving platform hung at high altitude
CN104631810A (en) * 2015-01-15 2015-05-20 中誉远发国际建设集团有限公司 High-altitude movable hanging basket system and construction method thereof
CN104963495A (en) * 2015-06-05 2015-10-07 中国十七冶集团有限公司 Suspension hanging basket for installation of roof surface bottom layer color plate
CN104963495B (en) * 2015-06-05 2017-07-14 中国十七冶集团有限公司 A kind of hanging basket for installing roofing bottom colored steel
CN105155832A (en) * 2015-06-17 2015-12-16 中建钢构有限公司 Hanging basket device and moving method thereof
CN105715032A (en) * 2016-04-15 2016-06-29 中国五冶集团有限公司 Construction hanging basket with spanning movement function and spanning movement method
CN105715032B (en) * 2016-04-15 2017-09-29 中国五冶集团有限公司 It is a kind of that there is the construction hanging basket for crossing over locomotive function and moving method is crossed over
CN106115573A (en) * 2016-08-19 2016-11-16 中国化学工程第三建设有限公司 The installation equipment of factory roof coloured silk steel inner panel and installation method
CN108468433A (en) * 2018-04-12 2018-08-31 陈年康 A kind of construction tool of workshop metal Roof inner panel

Similar Documents

Publication Publication Date Title
CN202767494U (en) Hanging basket for high-altitude roof inner plate construction
CN203701560U (en) Suspension hanging basket for high-altitude roofing inner plate construction
CN202881852U (en) Suspension bridge cable installation system
CN201943007U (en) Constant amplitude frame beam crane capable of being used in combination with movable support frame
CN202012047U (en) Steel strand inclined pulling and buckling system of tower
CN109372243A (en) A kind of hanging basket system for the installation of steel construction metal Roof bottom plate
CN106592962A (en) Large-height-difference long-span stiff-skeleton cladding concrete formwork construction method and apparatus
CN103993745B (en) A kind of conversion beam integral hoisting device for rapid and hanging method thereof
CN103896127A (en) Connecting structure of construction hoist and building climbing formwork frame
CN104153586B (en) A kind of suspension cable hangs the construction method of mounting purlines
CN202379601U (en) Dual annular rail hoisting device for curtain wall
CN205955185U (en) Mould is hung in subway station tread wind channel special use
CN203129580U (en) Formwork system
CN102661035A (en) Tool type wall connecting piece for exterior wall scaffold
CN202658867U (en) Overhanging construction platform
CN105040592B (en) A kind of horizontal drawing cable bridge and its erection method
CN103835369A (en) Extensible high-altitude conjoined steel structure
CN215331383U (en) Hanging basket structure for high-rise building construction
CN202543812U (en) Measure bracket for hanging ceilings on roofs of platform layers of rail traffic elevated station
CN204982628U (en) Horizontal drawing cable bridge
CN103790388B (en) Greatly install improve one's methods across the waft high-altitude of eaves of cantilever roofing steel
CN201952736U (en) Auxiliary pier movable bracket for assisting invariable-amplitude beam erecting crane in erecting steel box girder
CN202299362U (en) Erecting structure for suspension type scaffold of pipe rack
CN103791465B (en) By the method for the hydraulic elevator mounting industrial illumination of plant building light fixture based on driving
CN206256382U (en) It is a kind of to suspend purlin car in midair for the triangle that Wavelike steel webplate is installed

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130306