CN215331383U - Hanging basket structure for high-rise building construction - Google Patents
Hanging basket structure for high-rise building construction Download PDFInfo
- Publication number
- CN215331383U CN215331383U CN202121212893.8U CN202121212893U CN215331383U CN 215331383 U CN215331383 U CN 215331383U CN 202121212893 U CN202121212893 U CN 202121212893U CN 215331383 U CN215331383 U CN 215331383U
- Authority
- CN
- China
- Prior art keywords
- hanging basket
- lifting
- basket
- rise building
- building construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000009435 building construction Methods 0.000 title claims abstract description 29
- 230000005540 biological transmission Effects 0.000 claims abstract description 38
- 230000000694 effects Effects 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 24
- 238000000034 method Methods 0.000 abstract description 15
- 229910000831 Steel Inorganic materials 0.000 description 7
- 239000010959 steel Substances 0.000 description 7
- 230000001681 protective effect Effects 0.000 description 6
- 229910000746 Structural steel Inorganic materials 0.000 description 3
- 230000003014 reinforcing effect Effects 0.000 description 3
- 238000005299 abrasion Methods 0.000 description 1
- 230000001174 ascending effect Effects 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 238000004321 preservation Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model relates to the technical field of building instruments, in particular to a hanging basket structure for high-rise building construction, which comprises a fixing clamp for clamping a floor slab, wherein a lifting frame is arranged on the fixing clamp, a hanging basket for lifting is arranged on the lifting frame, a guide rail is arranged on the fixing clamp, a screw rod transmission mechanism is movably arranged on the guide rail, and the screw rod transmission mechanism is in transmission connection with the lifting frame and drives the hanging basket to move along the length direction of the guide rail by driving the lifting frame. The hanging basket structure for high-rise building construction can conveniently adjust the horizontal position of the hanging basket, thereby omitting the disassembly process of the hanging basket in the use process, improving the flexibility of equipment use and improving the construction efficiency.
Description
Technical Field
The utility model relates to the technical field of building instruments, in particular to a hanging basket structure for high-rise building construction.
Background
After the development of production and consumption of cities in the world reaches a certain degree, no effort is made to increase the number of layers of urban buildings. Practice proves that the high-rise building can bring obvious social and economic benefits. Firstly, the high-rise building can shorten the connection distance between departments by utilizing vertical and horizontal traffic in the building, so that the population is concentrated, and the efficiency is improved; secondly, the high-rise building can greatly reduce the land used by the large-area building and save land resources; in addition, the high-rise building can also reduce municipal construction investment and shorten the construction period. The construction of high-rise buildings has been well established, and people around the world have built a lot of high-rise buildings before the industrial revolution, such as the light tower of the stone structure of the great mountain harbour in Egypt and 280 years before the Ministry is 100m high; china is built in 523 years of Songyue Temple in Henan Deng-Chang county at a height of 40 m. The hanging basket is a novel high-altitude operation device which can replace a traditional scaffold, reduce labor intensity, improve working efficiency and be repeatedly used. At present, the use of the construction hanging basket gradually becomes a trend, and the construction hanging basket is widely accepted in high-altitude operations such as outer wall construction, curtain wall installation, heat preservation construction, outer wall maintenance and cleaning of high-rise multi-storey buildings and the like. Meanwhile, the method can be used for the operation of large-scale tank bodies, bridges, dams and other projects. The product can avoid scaffold. The construction cost is greatly reduced, the construction cost is only 28 percent of that of the traditional scaffold, and the working efficiency is greatly improved. The hanging basket is flexible to operate, easy to shift, convenient, practical, safe and reliable. The hanging basket for the construction of the existing high-rise building has the main defects that: the horizontal position of the hanging basket can not be adjusted after the support is fixed by the existing hanging basket for high-rise building construction.
SUMMERY OF THE UTILITY MODEL
The utility model provides a hanging basket structure for high-rise building construction, which can conveniently adjust the horizontal position of the hanging basket, thereby omitting the disassembly process of the hanging basket in the use process, improving the flexibility of equipment use and improving the construction efficiency.
The utility model provides a hanging basket structure for high-rise building construction, which comprises a fixing clamp for clamping a floor slab, wherein a lifting frame is arranged on the fixing clamp, a hanging basket for lifting is arranged on the lifting frame, a guide rail is arranged on the fixing clamp, a screw rod transmission mechanism is movably arranged on the guide rail, and the screw rod transmission mechanism is in transmission connection with the lifting frame and drives the hanging basket to move along the length direction of the guide rail by driving the lifting frame.
According to the hanging basket structure for high-rise building construction, the guide rail is provided with the sliding groove which extends in a straight line, the screw rod transmission mechanism comprises the sliding block, the screw rod motor and the screw rod which is in transmission connection with the screw rod motor and extends along the length direction of the sliding groove, the lifting frame is fixed on the sliding block, and the sliding block is in threaded connection with the screw rod, is in sliding fit in the sliding groove and can slide along the length direction of the sliding groove.
According to the hanging basket structure for high-rise building construction, the protective steel wire extending along the length direction of the sliding groove is fixed on the fixing clamp, the protective ring is arranged on the sliding block, and the sliding block is movably connected to the protective steel wire in series through the protective ring.
According to the hanging basket structure for high-rise building construction, the lifting frame is provided with the elastic reset mechanism, and the elastic reset mechanism is downwards and elastically connected to the hanging basket.
According to the hanging basket structure for high-rise building construction, the elastic reset mechanism comprises a plurality of balance rollers, balance ropes and springs, the springs are arranged in the balance rollers, the lower ends of the balance ropes are synchronously and fixedly connected to the hanging basket from the two opposite sides of the hanging basket respectively, and the upper ends of the balance ropes are elastically connected to the springs in the balance rollers.
According to the hanging basket structure for high-rise building construction, provided by the utility model, the lower end of each balance rope is respectively fixed with a plurality of branch lines, and each branch line is respectively downwards fixedly connected to the hanging basket.
According to the hanging basket structure for high-rise building construction, the lifting frame is provided with the lifting motor, the lifting roller and the connecting plate, the lifting motor drives the lifting roller to rotate, the lifting rope is wound on the lifting roller, the lifting rope is downwards fixedly connected to the connecting plate, and the connecting plate is respectively connected to two opposite sides of the hanging basket through the lifting ropes arranged at two opposite ends.
According to the hanging basket structure for high-rise building construction, the lifting frame is provided with the top plate for supporting the lifting motor, the top plate is provided with the through hole, and the lifting rope penetrates through the through hole downwards and is in clearance fit with the through hole.
According to the hanging basket structure for high-rise building construction, the lifting frame is further provided with a vertically extending support column and a transversely extending electric telescopic rod, the screw rod transmission mechanism is in transmission connection with the support column and can drive the support column to move along the length direction of the guide rail, and the extending direction of the electric telescopic rod is staggered with the length direction of the guide rail and drives the hanging basket to move through the extension and retraction of the electric telescopic rod.
According to the hanging basket structure for high-rise building construction, a hanging basket door is arranged on the hanging basket and is positioned on one side close to the fixing clamp.
The utility model provides a hanging basket structure for high-rise building construction, which is characterized in that a guide rail is additionally arranged on a fixing clamp, a lead screw transmission mechanism is movably arranged on the guide rail, then the lead screw transmission mechanism is in transmission connection with a lifting frame, so that the lead screw transmission mechanism can drive the lifting frame to move, and a hanging basket for lifting is arranged on the lifting frame, so that the hanging basket can be driven to move along the length direction of the guide rail by driving the lifting frame to move by using the lead screw transmission mechanism, the hanging basket is controlled by the lead screw transmission mechanism and can move along the guide rail direction, the horizontal position of the hanging basket can be movably adjusted, namely, the hanging basket on the lifting frame and the hanging basket on the lifting frame can be driven to transversely move together by controlling the lead screw transmission mechanism in the construction operation process, so that the horizontal position of the hanging basket can be conveniently adjusted, the hanging basket does not need to be disassembled for adjusting the horizontal position of the hanging basket, so that the disassembling process of the hanging basket in the using process is omitted, the using flexibility of the equipment is improved, and the construction efficiency is improved.
Drawings
In order to more clearly illustrate the technical solutions of the present invention or the prior art, the drawings needed to be used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings based on these drawings without creative efforts.
FIG. 1 is a perspective view of the overall construction of the present invention;
FIG. 2 is a perspective view of the overall construction of the present invention;
FIG. 3 is a schematic view of a partial structure of the present invention;
FIG. 4 is a schematic view of a partial structure of the present invention;
FIG. 5 is a perspective view of the overall construction of the present invention;
FIG. 6 is a perspective view of the overall construction of the present invention;
FIG. 7 is a partial schematic view of the present invention;
FIG. 8 is a perspective view of the overall construction of the present invention;
FIG. 9 is a perspective view of the overall construction of the present invention;
FIG. 10 is a perspective view of the overall construction of the present invention;
fig. 11 is a perspective view of the overall structure of the present invention.
100-a fixing clip; 200-a lifting frame; 300-hanging basket; 400-a guide rail; 500-a screw drive mechanism; 600-an elastic reset mechanism; 1-a chute; 2-a slide block; 3-a screw motor; 4-a screw rod; 5-protective steel wires; 6-a guard ring; 7-a balance roll; 8-a balancing rope; 9-a spring; 10-a bifurcation line; 11-a lifting motor; 12-a lifting roller; 13-connector tiles; 14-a lifting rope; 15-a top plate; 16-a via hole; 17-a support column; 18-an electric telescopic rod; 19-basket door; 20-bolt; 21-angle iron; 22-reinforcing plate.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention clearer, the technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings, and it is obvious that the described embodiments are some, but not all embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The hanging basket structure for high-rise building construction of the present invention is described below with reference to fig. 1, and includes a fixing clip 100 for clamping a floor slab, a lifting frame 200 is installed on the fixing clip 100, a hanging basket 300 for lifting is installed on the lifting frame 200, a guide rail 400 is formed on the fixing clip 100, a screw rod transmission mechanism 500 is movably installed on the guide rail 400, the screw rod transmission mechanism 500 is in transmission connection with the lifting frame 200, and the screw rod transmission mechanism 500 drives the hanging basket 300 to move along the length direction of the guide rail 400 by driving the lifting frame 200.
In this embodiment, the guide rail 400 is additionally arranged on the fixing clip 100, the screw rod transmission mechanism 500 is movably arranged on the guide rail 400, then the screw rod transmission mechanism 500 is in transmission connection with the lifting frame 200, so that the screw rod transmission mechanism 500 can drive the lifting frame 200 to move, and as the lifting frame 200 is provided with the hanging basket 300 for lifting, the lifting frame 200 driven by the screw rod transmission mechanism 500 can be driven to move along the length direction of the guide rail 400, so that the hanging basket 300 is controlled by the screw rod transmission mechanism 500 and can move along the guide rail 400, and the horizontal position of the hanging basket 300 can be movably adjusted, that is, in the construction process, as long as the screw rod transmission mechanism 500 is controlled to move, the lifting frame 200 and the hanging basket 300 on the lifting frame 200 can be driven to move transversely together, so that the horizontal position of the hanging basket 300 can be conveniently adjusted, the hanging basket does not need to be disassembled for adjusting the horizontal position of the hanging basket 300, so that the disassembling process of the hanging basket in the using process is omitted, the using flexibility of the equipment is improved, and the construction efficiency is improved.
Specifically, as shown in fig. 2 to 3, a sliding chute 1 extending in a straight line is formed on the guide rail 400, the lead screw transmission mechanism 500 includes a sliding block 2, a lead screw motor 3 and a lead screw 4, the lead screw 4 is in transmission connection with the lead screw motor 3, the lead screw 4 extends along the length direction of the sliding chute 1, the lifting frame 200 is fixed on the sliding block 2, the sliding block 2 is in threaded connection with the lead screw 4 through an internal screw hole (not marked in the figure), and meanwhile, the sliding block 2 is in sliding fit in the sliding chute 1 and can slide along the length direction of the sliding chute 1. Because the slider 2 is restricted in the spout 1, so as to drive the lead screw 4 to rotate by starting the lead screw motor 3, can utilize the lead screw transmission mode to drive the slider 2 to move linearly in the spout 1 along the length direction of the spout 1, because the lifting frame 200 is fixed on the slider 2, the lifting frame 200 and the hanging basket 300 on the lifting frame 200 can also move along with the slider 2, so that the hanging basket 300 can realize the movable adjustment in the horizontal direction, in use, as long as the forward and reverse rotation of the lead screw motor 3 are controlled, the slider 2 can be controlled to move back and forth, thereby the hanging basket 300 can also move and adjust in the horizontal direction along with the same, and the operation is flexible and simple.
Specifically, the sliding groove 1 is a strip-shaped through hole penetrating through the fixing clip 100, the sliding block 2 is an i-shaped sliding block, and grooves on two sides of the sliding block 2 are respectively clamped on two sides of the sliding groove 1 in a matched manner, so that the sliding block 2 can be limited in the sliding groove 1 and can only move along the length direction of the sliding groove 1.
Further, as shown in fig. 4, a protection steel wire 5 extending along the length direction of the sliding chute 1 is fixed on the fixing clip 100, a protection ring 6 is arranged on the sliding block 2, and the sliding block 2 is movably connected in series to the protection steel wire 5 through the protection ring 6. When the sliding block 2 is disconnected from the sliding groove 1 in the running process of the equipment, the protective steel wire 5 pulls the lifting frame 200 and the hanging basket 300 through the protective ring 6, so that the casualty rate in the accident occurrence can be reduced, and the safety accident can be prevented.
Further, as shown in fig. 5, the lifting frame 200 is provided with an elastic return mechanism 600, and the elastic return mechanism 600 is elastically connected to the hanging basket 300 downwards. The elasticity canceling release mechanical system 600 elasticity resets the pulling force and can provide ascending pulling force, can help reducing the pulling force that comes from the hanging flower basket 300 that the crane 200 received, effectively improves the whole load carrying capacity of equipment, and when the lifting rope between hanging flower basket 300 and the crane 200 broke off, elasticity canceling release mechanical system 600 can hold hanging flower basket 300, helps avoiding incident's emergence.
Specifically, as shown in fig. 6 to 7, the elastic return mechanism 600 includes two balance rollers 7, balance ropes 8 and springs 9, the springs 9 are installed in the balance rollers 7, the lower ends of the balance ropes 8 are synchronously and fixedly connected to the basket 300 from the left and right sides of the basket 300, respectively, and the upper ends of the balance ropes 8 are elastically connected to the springs 9 in the balance rollers 7, respectively. Therefore, the two opposite sides of the hanging basket 300 synchronously receive upward elastic reset pulling force, the stability of the whole hanging basket 300 can be improved, the whole load capacity of the equipment is further improved, and when the lifting rope between the hanging basket 300 and the lifting frame 200 is broken, the balancing ropes 8 on the two sides can also pull the hanging basket 300 to avoid safety accidents.
More specifically, as shown in fig. 8, three branch lines 10 are respectively fixed to the lower ends of the balancing cords 8 at both sides, and the three branch lines 10 are respectively fixedly connected to the basket 300 downward. Three diverged lines 10 that the balanced rope 8 lower extreme branched are fixed connection hanging flower basket 300, this structure can be effectively with elasticity reset pulling force balanced distribution in hanging flower basket 300, help avoiding hanging flower basket 300 to rock to the connection with hanging flower basket 300 is also more firm, and factor of safety is higher.
Further, as shown in fig. 9, the crane 200 is provided with a lifting motor 11, a lifting roller 12 and a connecting plate 13, the lifting motor 11 drives the lifting roller 12 to rotate, a lifting rope 14 is wound on the lifting roller 12, the lifting rope 14 is fixedly connected to the connecting plate 13 downward, and the connecting plate 13 is connected to the left and right sides of the gondola 300 by arranging lifting ropes at opposite ends. The structure aims at connecting the lifting rope to the left side and the right side of the hanging basket by utilizing the connecting plates 13, so that the phenomenon that the lifting rope influences the work of workers due to the fact that the lifting rope is connected with the hanging basket in a straight downward mode is avoided, and the obstruction of the inner space of the hanging basket 300 to the workers is reduced to the maximum extent; on the other hand, the use of the engagement plates 13 to connect the lifting ropes to the left and right sides of the basket helps to improve the stability of the entire basket 300 and to prevent the basket 300 from shaking.
Further, as shown in fig. 9, the lifting frame 200 is provided with a top plate 15 for supporting the lifting motor 11, the top plate 15 is provided with a through hole 16, the lifting rope 14 downwardly penetrates through the through hole 16 and is in clearance fit with the through hole 16, that is, the aperture size of the through hole 16 is larger than the diameter of the lifting rope 14, so that the phenomenon that the lifting rope 14 and the lifting frame are excessively rubbed in the lifting process to cause abrasion can be effectively avoided, and the service life of the lifting frame is further influenced.
Further, as shown in fig. 10 to 11, the lifting frame 200 is further provided with a vertically extending support column 17 and a horizontally extending electric telescopic rod 18, the screw rod transmission mechanism 500 is in transmission connection with the support column 17 and can drive the support column 17 to move along the length direction of the guide rail 400, specifically, in this embodiment, the support column 17 is fixedly installed on the slider 2, the support column 17 can be driven to move along the length direction of the guide rail 400 by the movement of the slider 2, and the extending direction of the electric telescopic rod 18 is staggered with the length direction of the guide rail 400, in this embodiment, the extending direction of the electric telescopic rod 18 is perpendicular to the length direction of the guide rail 400, so that the basket 300 can be driven to move along the direction perpendicular to the guide rail 400 by the extension and retraction of the electric telescopic rod 18, thereby further increasing the horizontal moving direction of the basket 300, and thus also conveniently adjusting the horizontal position of the basket 300, the hanging basket does not need to be disassembled for adjusting the horizontal position of the hanging basket 300, so that the disassembling process of the hanging basket in the using process is omitted, the using flexibility of the equipment is improved, and the construction efficiency is improved.
Further, as shown in fig. 10, the basket 300 is provided with the basket door 19, the basket door 19 is positioned at a side close to the fixing clip 100, and the worker can conveniently drop the basket 300 through the basket door 19, which helps to improve the safety factor of the worker using the basket.
Specifically, as shown in fig. 10 to 11, in the present embodiment, a plurality of screw holes (not shown) are formed on the fixing clip 100, each screw hole is fittingly installed with a bolt 20, the number of the screw holes and the bolts 20 is adapted to the length of the fixing clip 100, after the floor slab of the floor is clamped by the fixing clip 100, the fixing clip 100 is locked on the floor slab by the bolts 20, and the whole crane and the basket are fixed.
Alternatively, as shown in fig. 9, an angle iron 21 is fixedly connected to an included angle between the supporting column 17 and the electric telescopic rod 18, the angle iron 21 can improve the stability between the supporting column 17 and the electric telescopic rod 18, and reinforcing plates 22 are respectively connected to two sides of a contact end of the top plate 15 and the electric telescopic rod 18, the reinforcing plates 23 are triangular plates, and the reinforcing plates 23 can increase the contact area between the top plate 15 and the electric telescopic rod 18, so that the connection between the two parts is firmer, and the stability of the device and the safety factor of workers are improved.
Optionally, both lift cords 14 and counterbalance cords 8 are steel cords.
Finally, it should be noted that: the above examples are only intended to illustrate the technical solution of the present invention, but not to limit it; although the present invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; and such modifications or substitutions do not depart from the spirit and scope of the corresponding technical solutions of the embodiments of the present invention.
Claims (10)
1. The utility model provides a hanging flower basket structure that high-rise building construction was used, is including fixation clamp (100) that are used for pressing from both sides tight floor, be provided with crane (200) on fixation clamp (100), be provided with hanging flower basket (300) that are used for going up and down on crane (200), a serial communication port, be provided with guide rail (400) on fixation clamp (100), the activity is provided with lead screw drive mechanism (500) on guide rail (400), lead screw drive mechanism (500) transmission connect in crane (200) and through driving crane (200) are ordered about hanging flower basket (300) along the length direction of guide rail (400) removes.
2. The hanging basket structure for high-rise building construction according to claim 1, wherein a sliding groove (1) extending in a straight line is formed on the guide rail (400), the screw transmission mechanism (500) comprises a sliding block (2), a screw motor (3) and a screw (4) connected to the screw motor (3) in a transmission manner and extending along the length direction of the sliding groove (1), the lifting frame (200) is fixed on the sliding block (2), and the sliding block (2) is connected to the screw (4) in a threaded manner, is in sliding fit with the sliding groove (1) and can slide along the length direction of the sliding groove (1).
3. The hanging basket structure for high-rise building construction according to claim 2, wherein a protection wire (5) extending along the length direction of the chute (1) is fixed on the fixing clip (100), a protection ring (6) is arranged on the sliding block (2), and the sliding block (2) is movably connected in series to the protection wire (5) through the protection ring (6).
4. The basket structure for high-rise building construction according to claim 1, wherein the lifting frame (200) is provided with an elastic restoring mechanism (600), and the elastic restoring mechanism (600) is elastically connected to the basket (300) downwards.
5. The hanging basket structure for high-rise building construction according to claim 4, wherein the elastic reset mechanism (600) comprises a plurality of balance rollers (7), balance ropes (8) and springs (9), the springs (9) are arranged in the balance rollers (7), the lower ends of the balance ropes (8) are synchronously and fixedly connected to the hanging basket (300) from two opposite sides of the hanging basket (300), respectively, and the upper ends of the balance ropes (8) are elastically connected to the springs (9) in the balance rollers (7).
6. The basket structure for high-rise building construction according to claim 5, wherein a plurality of branch lines (10) are fixed to the lower ends of the balance ropes (8), respectively, and each branch line (10) is fixedly connected to the basket (300) downward.
7. The gondola structure for high-rise building construction as claimed in claim 1, wherein the crane (200) is provided with a lifting motor (11), a lifting roller (12) and a joint plate (13), the lifting motor (11) drives the lifting roller (12) to rotate, a lifting rope (14) is wound on the lifting roller (12), the lifting rope (14) is fixedly connected to the joint plate (13) downward, and the joint plate (13) is connected to opposite sides of the gondola (300) by arranging lifting ropes at opposite ends thereof, respectively.
8. The hanging basket structure for high-rise building construction according to claim 7, wherein the lifting frame (200) is provided with a top plate (15) for supporting the lifting motor (11), the top plate (15) is provided with a through hole (16), and the lifting rope (14) penetrates through the through hole (16) downwards and is in clearance fit with the through hole (16).
9. The hanging basket structure for high-rise building construction according to claim 1, wherein the lifting frame (200) is further provided with a vertically extending supporting column (17) and a transversely extending electric telescopic rod (18), the screw rod transmission mechanism (500) is in transmission connection with the supporting column (17) and can drive the supporting column (17) to move along the length direction of the guide rail (400), and the extension direction of the electric telescopic rod (18) is staggered with the length direction of the guide rail (400) and drives the hanging basket (300) to move through the extension and retraction of the electric telescopic rod (18).
10. The basket structure for high-rise building construction according to claim 1, wherein a basket door (19) is provided on the basket (300), the basket door (19) being located at a side close to the fixing clip (100).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121212893.8U CN215331383U (en) | 2021-06-01 | 2021-06-01 | Hanging basket structure for high-rise building construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121212893.8U CN215331383U (en) | 2021-06-01 | 2021-06-01 | Hanging basket structure for high-rise building construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN215331383U true CN215331383U (en) | 2021-12-28 |
Family
ID=79549989
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202121212893.8U Active CN215331383U (en) | 2021-06-01 | 2021-06-01 | Hanging basket structure for high-rise building construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN215331383U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115012635A (en) * | 2022-07-01 | 2022-09-06 | 亚都建设集团有限公司 | Hanging flower basket installation protection mounting structure |
-
2021
- 2021-06-01 CN CN202121212893.8U patent/CN215331383U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115012635A (en) * | 2022-07-01 | 2022-09-06 | 亚都建设集团有限公司 | Hanging flower basket installation protection mounting structure |
CN115012635B (en) * | 2022-07-01 | 2024-05-28 | 亚都建设集团有限公司 | Hanging basket installation protection mounting structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202767494U (en) | Hanging basket for high-altitude roof inner plate construction | |
CN201987468U (en) | Counterweight type high-rise window cleaning machine | |
CN111335614B (en) | Hanging basket device for building construction and using method thereof | |
CN215331383U (en) | Hanging basket structure for high-rise building construction | |
CN110004834A (en) | A kind of automatic climbing platform for hanging cable construction | |
CN209494204U (en) | Suspension type steel ladder | |
CN217028004U (en) | Annular hanging basket suspension device for curtain wall construction of super high-rise building | |
CN213416063U (en) | Overhead hanging basket for steel reinforcement framework | |
CN203334695U (en) | Curtain wall glass installation and suspending system | |
CN220376298U (en) | Hanging basket lifting device | |
CN201099575Y (en) | Hanging basket rotatable material lifting equipment | |
CN116062626A (en) | Curtain wall hoisting equipment and hoisting method for crown part of super high-rise building tower | |
CN216360648U (en) | Hanging basket for bridge construction | |
CN214942249U (en) | Novel indoor wall construction device | |
CN204138213U (en) | Track gun carriage is used in a kind of cell cube curtain wall lifting | |
CN208934392U (en) | Construction mould bases | |
CN209799408U (en) | rail-mounted vertical transportation mechanism for unit plate | |
CN208219414U (en) | Bridge construction hanging basket | |
CN202138937U (en) | Electric hanging basket | |
CN207108183U (en) | A kind of elevator overcoat pulley leading truck jacking system | |
CN110748140A (en) | Track beam hanging basket special for stepped curtain wall | |
CN201459602U (en) | Equipment for bridge construction | |
CN217840830U (en) | Hang rail installation work platform | |
CN215558540U (en) | Movable hanging basket | |
CN112112413A (en) | Self-locking type hanging basket heavy hammer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |