CN202881852U - Suspension bridge cable installation system - Google Patents

Suspension bridge cable installation system Download PDF

Info

Publication number
CN202881852U
CN202881852U CN 201220380855 CN201220380855U CN202881852U CN 202881852 U CN202881852 U CN 202881852U CN 201220380855 CN201220380855 CN 201220380855 CN 201220380855 U CN201220380855 U CN 201220380855U CN 202881852 U CN202881852 U CN 202881852U
Authority
CN
China
Prior art keywords
cable
bearing
load
cables
walking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220380855
Other languages
Chinese (zh)
Inventor
杨建国
王瑛
崔建英
张跃平
杨育青
李国涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Juli Sling Co Ltd
Original Assignee
Juli Sling Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Juli Sling Co Ltd filed Critical Juli Sling Co Ltd
Priority to CN 201220380855 priority Critical patent/CN202881852U/en
Application granted granted Critical
Publication of CN202881852U publication Critical patent/CN202881852U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model provides a suspension bridge cable installation system which comprises a main tower, a pier, movable suspended scaffold walking cables, bearing cables, movable suspended scaffolds, a beam anchoring-adjusting device, lifting pulleys and a rack winch. A bearing frame is arranged at the tower top of the main tower, the bearing cables and the movable suspended scaffold walking cables are bridged on the bearing frame, two ends of the movable suspended walking cables and the bearing cables are respectively and fixedly connected at the position of the pier outside the main tower through the beam anchoring-adjusting device, the bearing cables are arranged between two movable suspended scaffold walking cables, a plurality of movable suspended scaffolds are arranged on the two movable suspended scaffold walking cables, the lifting pulleys are suspended on the bearing cables, the bearing cables and the lifting pulleys combine to form a roller rail, the lifting pulleys are connected with the rack winch through steel wire ropes, and the movable suspended scaffolds and the bearing cables form an operation platform of a cable system. The suspension bridge cable installation system has the advantages of being low in engineering cost and convenient to maintain.

Description

The galvanized wire for suspension bridge installation system
Technical field
The utility model belongs to the bridge member field, particularly the cable installation system of suspension bridge.
Background technology
Suspension bridge is a kind of bridge construction form with super large span ability, and its application is very extensive.Funicular system be main in the suspension bridge structure, also be very important primary structure member.
Rope-suspension bridge cable system is installed and generally to be adopted along the main push-towing rope line style, thereunder to set up cat road continuous, that be comprised of " wire rope track cable-distribution beam-expanded metal lath " etc. as constructor's operating platform, and the cat road is special facilities in suspension bridge construction.From main push-towing rope set up, adjust, tight cable, to cord clip, hanger erection and main cable protection, constructor's operation is all carried out at Mao Dao.But there are some defectives in cat road construction technology:
1, complex structure, the composition member is many, repeat usage is low.The load that the cat road bears passes to the wire rope track cable by expanded metal lath, and for making the wire rope producing balanced forces, wire rope track cable anchor point must arrange adjusting device, along long per 4 meters of rope distribution beam will be set.The bridge type of suspension bridge, span, main push-towing rope sample diversified in specifications form cat road member and will redesign, make.
2, erecting process is complicated, operation is many, and required duty cycle is long.Especially self-anchored suspension bridge because the cat road must be finished laggard just can the installation at tower, beam and set up, affects the continuity of structure construction, causes the construction period to increase.
3, the funicular system installation exercise generally carries out at some point, and the constructor need to arrive setting along the walking of cat road.In the installation of large-span suspension bridge funicular system, often operating personnel to arrive setting very tired, have a strong impact on construction efficiency.
4, because the member in composition cat road is many, quantity is large, and recycling rate of waterused is low, cause waste of material, construction costs to improve.
The utility model content
The utility model is intended to overcome the defective of prior art, provide a kind of duration short, construction costs is low, galvanized wire for suspension bridge installation system easy to maintenance.
In order to solve the problems of the technologies described above, the utility model provides following technical scheme:
The galvanized wire for suspension bridge installation system, comprise king-tower, bridge pier, at the king-tower cat head bearing support is installed, it is characterized in that, Hanging Basket walking cable, the load-bearing cable, Hanging Basket, anchoring-adjusting device on the beam, Hoisting tackle and rack winch, added load-bearing cable and the Hanging Basket walking cable of being provided with of bearing support, Hanging Basket walking cable and load-bearing cable two ends are fixedly connected on the outer bridge pier place of king-tower by anchoring-adjusting device on the beam respectively, be provided with the load-bearing cable between the two Hanging Baskets walking cable, hang a plurality of Hanging Baskets on the two Hanging Baskets walking cable, hang Hoisting tackle on the load-bearing cable, load-bearing cable and Hoisting tackle are combined to form roller-way, Hoisting tackle is connected with rack winch by wire rope, and Hanging Basket and load-bearing cable consist of the job platform of cable installation system.
Further, be hung with four groups of Hanging Baskets along Hanging Basket walking cable, each one group of Hanging Basket of two sides of king-tower.
Further, Hoisting tackle is comprised of coaster and the sling and jig that is lifted on the load-bearing cable.
Further, be connected with the all-in-one-piece anchorage on the bridge pier.
Compared with prior art, the utlity model has following beneficial effect:
1, replace continuous cat road can simplify construction installation with local Hanging Basket.
2, the facility that relatively reduces has shortened the erection construction phase.
3, standardized Hanging Basket, Hoisting tackle etc. are equipped with and are beneficial to maintenance, can improve the equipment recycling rate of waterused.
4, raising can reduce construction costs.
Description of drawings
Fig. 1 is the schematic diagram of the utility model galvanized wire for suspension bridge installation system;
Fig. 2 is the layout schematic diagram of the utility model suspension bridge half bridge;
Fig. 3 is the walking cable of the utility model suspension bridge and the schematic cross-section of load-bearing cable;
Fig. 4 is the utility model galvanized wire for suspension bridge installation system work schematic diagram.
The specific embodiment
Below in conjunction with accompanying drawing preferred embodiment of the present utility model is described, should be appreciated that preferred embodiment described herein only is used for description and interpretation the utility model, and be not used in restriction the utility model.
Such as Fig. 1, Fig. 2, Fig. 3, shown in Figure 4, the galvanized wire for suspension bridge installation system, comprise anchoring-adjusting device 3, Hoisting tackle 6 and rack winch 7 on king-tower 9, bridge pier 8, Hanging Basket walking cable 1, load-bearing cable 5, Hanging Basket 4, the beam, two bridge piers 8 are distributed in king-tower 9 both sides, be installed with bearing support 2 at king-tower 9 cats head, bearing support 2 added load-bearing cable 5 and the Hanging Basket walking cables 1 of being provided with, Hanging Basket walking cable 1 all is fixedly connected with bridge pier 8 by anchoring on the beam 3 with load-bearing cable 5 one ends, and Hanging Basket walking cable 1 and load-bearing cable 5 other ends all are movably connected on another bridge pier 8 places by adjusting device.Be provided with load-bearing cable 5 between the two Hanging Baskets walking cable 1, two Hanging Baskets walking cable 1 is provided with 8 Hanging Baskets 4, hang four groups of Hanging Baskets 4 along Hanging Basket walking cable 1, each one group of Hanging Basket 4 of two sides of king-tower 9, Hanging Basket 4 moves along Hanging Basket walking cable 1 and finishes main push-towing rope 12 liftings, Hanging Basket 4 adopts has autonomous, elevating function Hanging Basket, hangs Hoisting tackle 6 on the load-bearing cable 5, and Hoisting tackle 6 is comprised of coaster and the sling and jig that is lifted on the load-bearing cable.Load-bearing cable 5 and Hoisting tackle 6 are combined to form roller-way, and Hoisting tackle 6 is connected with rack winch 7 by wire rope, at main bridge head and the tail two ends a rack winch 7 are set respectively, are used for traction Hoisting tackle 6.Hanging Basket 4 and load-bearing cable 5 consist of the job platform of funicular system.
In addition, also be connected with all-in-one-piece anchorage 10 on the above-mentioned bridge pier 8, Hanging Basket walking cable 1 and load-bearing cable 5 two ends are connected on the anchorage 10.
Utilize above-mentioned galvanized wire for suspension bridge installation system, the main push-towing rope of lifting suspension bridge and other member have the advantages that the construction period is short, easy to maintenance, construction costs is low.
The above only is explanation embodiment of the present utility model; be not limited to the utility model; for a person skilled in the art; all within spirit of the present utility model and principle; any modification of doing, be equal to replacement, improvement etc., all should be included within the protection domain of the present utility model.

Claims (4)

1. galvanized wire for suspension bridge installation system, comprise king-tower, bridge pier, at the king-tower cat head bearing support is installed, it is characterized in that, Hanging Basket walking cable, the load-bearing cable, Hanging Basket, anchoring-adjusting device on the beam, Hoisting tackle and rack winch, added load-bearing cable and the Hanging Basket walking cable of being provided with of bearing support, Hanging Basket walking cable and load-bearing cable two ends are fixedly connected on the outer bridge pier place of king-tower by anchoring-adjusting device on the beam respectively, be provided with the load-bearing cable between the two Hanging Baskets walking cable, hang a plurality of Hanging Baskets on the two Hanging Baskets walking cable, hang Hoisting tackle on the load-bearing cable, load-bearing cable and Hoisting tackle are combined to form roller-way, Hoisting tackle is connected with rack winch by wire rope, and Hanging Basket and load-bearing cable consist of the job platform of funicular system.
2. galvanized wire for suspension bridge installation system according to claim 1 is characterized in that: be hung with four groups of Hanging Baskets along Hanging Basket walking cable, each one group of Hanging Basket of two sides of king-tower.
3. galvanized wire for suspension bridge installation system according to claim 1 is characterized in that: Hoisting tackle is comprised of coaster and the sling and jig that is lifted on the load-bearing cable.
4. galvanized wire for suspension bridge installation system according to claim 1 is characterized in that: be connected with the all-in-one-piece anchorage on the bridge pier.
CN 201220380855 2012-08-02 2012-08-02 Suspension bridge cable installation system Expired - Lifetime CN202881852U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220380855 CN202881852U (en) 2012-08-02 2012-08-02 Suspension bridge cable installation system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220380855 CN202881852U (en) 2012-08-02 2012-08-02 Suspension bridge cable installation system

Publications (1)

Publication Number Publication Date
CN202881852U true CN202881852U (en) 2013-04-17

Family

ID=48073293

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220380855 Expired - Lifetime CN202881852U (en) 2012-08-02 2012-08-02 Suspension bridge cable installation system

Country Status (1)

Country Link
CN (1) CN202881852U (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631329A (en) * 2014-12-30 2015-05-20 中铁大桥局集团有限公司 Method for adjusting overall line shape of continuous catwalk of suspension bridge
CN105369741A (en) * 2015-12-14 2016-03-02 中交一公局第三工程有限公司 Suspension-type movable operation platform for constructing catwalk face net
CN105586832A (en) * 2015-12-15 2016-05-18 中交一公局第三工程有限公司 Suspension type catwalk surface net mounting system
CN105113414B (en) * 2015-09-11 2016-09-21 中铁八局集团桥梁工程有限责任公司 A kind of suspension bridge main rope fast erecting method
CN106087766A (en) * 2016-08-12 2016-11-09 扬州北晟桥梁科技有限公司 New type suspension bridge main push-towing rope and hoist cable integrated construction frock
CN106988220A (en) * 2017-03-13 2017-07-28 中交第四公路工程局有限公司 Tower structure and the method excessively of a kind of continous way suspension bridge cat road head-rope
CN107201724A (en) * 2016-03-19 2017-09-26 湖北建科结构加固有限责任公司 A kind of suspension bridge is without cat pipeline construction method
CN107881923A (en) * 2017-12-19 2018-04-06 中建四局第三建筑工程有限公司 A kind of cable bridge main rope fast erecting method and device
CN109137758A (en) * 2018-11-23 2019-01-04 中交第三航务工程局有限公司 A kind of self-anchored suspension bridge cable construction technology
CN112012101A (en) * 2020-07-06 2020-12-01 深圳市科兰德实业发展有限公司 Suspension bridge main cable maintenance equipment
CN113026528A (en) * 2021-03-10 2021-06-25 浙江中天恒筑钢构有限公司 Method for mounting mountain forest space curve steel structure plank road

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631329B (en) * 2014-12-30 2016-06-29 中铁大桥局集团有限公司 A kind of suspension bridge continuous way cat road integral linear method of adjustment
CN104631329A (en) * 2014-12-30 2015-05-20 中铁大桥局集团有限公司 Method for adjusting overall line shape of continuous catwalk of suspension bridge
CN105113414B (en) * 2015-09-11 2016-09-21 中铁八局集团桥梁工程有限责任公司 A kind of suspension bridge main rope fast erecting method
CN105369741B (en) * 2015-12-14 2017-04-19 中交一公局第三工程有限公司 Suspension-type movable operation platform for constructing catwalk face net
CN105369741A (en) * 2015-12-14 2016-03-02 中交一公局第三工程有限公司 Suspension-type movable operation platform for constructing catwalk face net
CN105586832A (en) * 2015-12-15 2016-05-18 中交一公局第三工程有限公司 Suspension type catwalk surface net mounting system
CN107201724A (en) * 2016-03-19 2017-09-26 湖北建科结构加固有限责任公司 A kind of suspension bridge is without cat pipeline construction method
CN106087766A (en) * 2016-08-12 2016-11-09 扬州北晟桥梁科技有限公司 New type suspension bridge main push-towing rope and hoist cable integrated construction frock
CN106988220A (en) * 2017-03-13 2017-07-28 中交第四公路工程局有限公司 Tower structure and the method excessively of a kind of continous way suspension bridge cat road head-rope
CN107881923A (en) * 2017-12-19 2018-04-06 中建四局第三建筑工程有限公司 A kind of cable bridge main rope fast erecting method and device
CN109137758A (en) * 2018-11-23 2019-01-04 中交第三航务工程局有限公司 A kind of self-anchored suspension bridge cable construction technology
CN112012101A (en) * 2020-07-06 2020-12-01 深圳市科兰德实业发展有限公司 Suspension bridge main cable maintenance equipment
CN113026528A (en) * 2021-03-10 2021-06-25 浙江中天恒筑钢构有限公司 Method for mounting mountain forest space curve steel structure plank road

Similar Documents

Publication Publication Date Title
CN202881852U (en) Suspension bridge cable installation system
CN202090286U (en) Traction system suitable for self-anchored type double cable plane suspension bridge
CN101672102B (en) Steel structural overhead ceiling construction platform
CN201943007U (en) Constant amplitude frame beam crane capable of being used in combination with movable support frame
CN102324712A (en) Method for electrified spanning construction of high-voltage power transmission and transformation line
CN202012047U (en) Steel strand inclined pulling and buckling system of tower
CN104060835A (en) Lifting-sliding construction method for single plane truss
CN208413709U (en) A kind of unit glass curtain wall ring rail Lift-on/Lift-off System
CN103882812A (en) Construction method for midspan main beams of cable-stayed bridge
CN104153586B (en) A kind of suspension cable hangs the construction method of mounting purlines
CN102392419A (en) High and large side-span cast-in-place construction method in conjunction with bracket and counterweight
CN102758404B (en) Front fulcrum hanging basket travelling device of spatial V-shaped cable-stayed bridge
CN204418013U (en) Bridge flange plate is constructed self-propelled cantilever hanging basket
CN101913534B (en) Fixed double-suspending point cantilever track type purlin suspender
CN104452594A (en) Multi-support cable guide method cable replacement device
CN205329550U (en) Suspension bridge catwalk system
CN101787677B (en) Method for erecting girder of suspension bridge by double-hoisting hydraulic NC (numerical control) cable crane
CN206769343U (en) It is a kind of to be used for the travelling bridge that guardrail is constructed that builds a bridge
CN102061681A (en) Fixed dual-hoisting point cantilever track type joist truss installing method
CN201722937U (en) Sliding platform for installation of net rack
CN2871634Y (en) Bridge maintaining equipment
CN201746247U (en) Fixed double hoisting cantilever rail girder hanger
CN202265781U (en) Bridge angle cradle with triangular truss
CN201952736U (en) Auxiliary pier movable bracket for assisting invariable-amplitude beam erecting crane in erecting steel box girder
CN206052545U (en) For the maintenance of across road overline bridge or the hanging mobile platform of application

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130417