CN104963495A - Suspension hanging basket for installation of roof surface bottom layer color plate - Google Patents

Suspension hanging basket for installation of roof surface bottom layer color plate Download PDF

Info

Publication number
CN104963495A
CN104963495A CN201510306087.XA CN201510306087A CN104963495A CN 104963495 A CN104963495 A CN 104963495A CN 201510306087 A CN201510306087 A CN 201510306087A CN 104963495 A CN104963495 A CN 104963495A
Authority
CN
China
Prior art keywords
hanging basket
wire rope
steel
steel wire
pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510306087.XA
Other languages
Chinese (zh)
Other versions
CN104963495B (en
Inventor
姚成新
梁义
王芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201510306087.XA priority Critical patent/CN104963495B/en
Publication of CN104963495A publication Critical patent/CN104963495A/en
Application granted granted Critical
Publication of CN104963495B publication Critical patent/CN104963495B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention provides a suspension hanging basket for installation of a roof surface bottom layer color plate. The suspension hanging basket comprises a steel beam and a purline, wherein a first steel wire rope and a second steel wire rope are respectively fixed on the steel beam on two ends of the purline; the first steel wire rope is connected with a third steel wire rope via a first lever hoist; the second steel wire rope is connected with the third wire steel rope via a second lever hoist; and the third steel wire rope is connected with the hanging basket via a pulley. The hanging basket can be flexibly placed according to construction side conditions; the hanging basket can be clamped via a self-clamp device, so hanging basket stability can be enhanced; and the hanging basket can be accurately positioned via a hanging hook.

Description

A kind of hanging basket installing roofing bottom colored steel
Technical field
The present invention relates to a kind of hanging basket, particularly a kind of hanging basket installing roofing bottom colored steel, belongs to technical field of building construction.
Background technology
Steel-structure factory building is due to attractive in appearance, durable, that cost is low, the construction period is short advantage, being more and more widely used in engineering construction, in order to reduce the temperature in factory building, increasing the aesthetic property in factory building, the roofing of factory building is often designed to double-deck colored steel, centre is heat-preservation cotton, spreads one deck color steel and be exposed above roof purline, and opposing wind rain shines, one deck colored steel is inhaled below roof purline, hold heat-preservation cotton, can play purposes attractive in appearance, middle heat-preservation cotton plays insulation effect again; Carried out furred ceiling just as to factory building, roofing steel truss is covered by bottom colored steel, and indoor at factory building, a purlin be can't see from the bottom up by whole factory building, succinct, elegant in appearance.
The installation of the bottom colored steel below roof purline is comparatively complicated and dangerous, and normal construction method is built a framework construction exactly, setting up to roofing, providing an operating platform installation roofing bottom colored steel colored steel to constructor by frame by there being facility floor.One method sets up overall shelf, roofing bottom colored steel is installed at constructor station on the top of the shelf, construct in this way, although the efficiency of installing the period is high, but its shortcoming is taken, tears shelf open costly, affect the construction of next procedure, need to coordinate mutually with multiple working procedure, the cycle of whole construction works is long; Another kind method sets up moveable shelf, one piece of bottom colored steel is installed, a mobile shelf, installing bottom layer colored steel and these two operations of mobile shelf ceaselessly overlapping, until the installation of bottom colored steel, constructor is upper and lower continually, safety does not ensure, although this method saves the circulation material of large quantities of shelfs and takes, tears expense open, inefficiency, also produce interference with other operation, the construction period is long.Sometimes due to the obstruction of above ground structure, cannot shelf be moved, directly have influence on completing of whole engineering.
Summary of the invention
The technical problem to be solved in the present invention overcomes existing defect, provides a kind of hanging basket installing roofing bottom colored steel, not only convenient mobile; And the height of hanging basket can be controlled, effectively can solve the problem in background technology.
In order to solve the problems of the technologies described above, the invention provides following technical scheme:
A kind of hanging basket installing roofing bottom colored steel of the present invention, comprise girder steel and be arranged on the wingceltis bar on girder steel, the girder steel at described wingceltis bar two ends is fixed with the first wire rope and the second wire rope respectively, described first wire rope connects the 3rd wire rope by the first lever hoist, described second wire rope connects the 3rd wire rope by the second lever hoist, and described 3rd wire rope connects hanging basket by moveable roller.
As a preferred technical solution of the present invention, the 3rd wire rope of described hanging basket both sides is provided with adjustment suspension hook.
As a preferred technical solution of the present invention, described 3rd wire rope and pulley are 3-5 and described pulley side is provided with from gripping mechanism.
As a preferred technical solution of the present invention, described hanging basket forms by bottom bar and by the guard rail rod that diagonal brace connects, and described bottom bar is provided with sheer pole, and described sheer pole is equipped with plank; Described guard rail rod is provided with cross tube.
The beneficial effect that compared with prior art the present invention reaches is: a kind of hanging basket installing roofing bottom colored steel, according to the needs of job site, can regulate the position of hanging basket flexibly, and by from gripping mechanism clamping, to strengthen the stability of hanging basket; And can by the accurate polarization of adjustment suspension hook raising to hanging basket.
Accompanying drawing explanation
Accompanying drawing is used to provide a further understanding of the present invention, and forms a part for manual, together with embodiments of the present invention for explaining the present invention, is not construed as limiting the invention.
In the accompanying drawings:
Fig. 1 is overall structure schematic diagram of the present invention;
Fig. 2 is barrel structure schematic diagram of the present invention;
Number in the figure: 1, wingceltis bar; 2, girder steel; 3, the first wire rope; 4, the second wire rope; 5, the first Lever Blocks; 6, the second lever hoist; 7, hanging basket; 8, pulley; 9, from gripping mechanism; 10, suspension hook is adjusted; 11, guard rail rod; 12, cross tube; 13, bottom bar; 14, sheer pole; 15, plank; 16, diagonal brace; 17, the 3rd wire rope.
Detailed description of the invention
Below in conjunction with accompanying drawing, the preferred embodiments of the present invention are described, should be appreciated that preferred embodiment described herein is only for instruction and explanation of the present invention, is not intended to limit the present invention.
Embodiment: as shown in Figure 1, a kind of hanging basket installing roofing bottom colored steel of the present invention, comprise girder steel 2 and be arranged on the wingceltis bar 1 on girder steel 2, the girder steel 2 at described wingceltis bar 1 two ends is fixed with respectively the first wire rope 3 and the second wire rope 4, described first wire rope 3 connects the 3rd wire rope 17 by the first lever hoist 5, described second wire rope 4 connects the 3rd wire rope 17 by the second lever hoist 6, and described 3rd wire rope 17 is flexibly connected hanging basket 7 by pulley 8.
Further, the 3rd wire rope 17 of described hanging basket 7 both sides is provided with adjustment suspension hook 10.The degree of disturbance of the 3rd wire rope 17 self can be effectively reduced by adjustment suspension hook 10.Described 3rd wire rope 17 and pulley 8 are 3-5 and described pulley 8 side is provided with from gripping mechanism 9.Hanging basket 7 is installed multiple pulley 8, and by the 3rd wire rope 17 through pulley 8.
Described hanging basket 7 forms by bottom bar 13 and by the guard rail rod 11 that diagonal brace 16 connects, and described bottom bar 13 is provided with sheer pole 14, and described sheer pole 14 is equipped with plank 15; Described guard rail rod 11 is provided with cross tube 12.Hanging basket 7 surrounding arranges guard rail rod 11, ensures the safety of construction worker.
The present invention is flexibly connected hanging basket 7 by many wire rope, by two lever hoists, hanging basket 7 is raised to suitable height, and by clamping hanging basket from gripping mechanism 9, is then reduced the degree of disturbance of wire rope by adjustment suspension hook 10.
A kind of hanging basket installing roofing bottom colored steel of the present invention, according to the needs of job site, can regulate the position of hanging basket 7 flexibly, and by clamping from gripping mechanism 9, to strengthen the stability of hanging basket 7; And accurate polarization to hanging basket 7 can be improved by adjustment suspension hook 10.
Last it is noted that the foregoing is only the preferred embodiments of the present invention, be not limited to the present invention, although with reference to previous embodiment to invention has been detailed description, for a person skilled in the art, it still can be modified to the technical scheme described in foregoing embodiments, or carries out equivalent replacement to wherein portion of techniques feature.Within the spirit and principles in the present invention all, any amendment done, equivalent replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (4)

1. one kind the hanging basket of roofing bottom colored steel is installed, it is characterized in that, comprise girder steel (2) and be arranged on the wingceltis bar (1) on girder steel (2), the girder steel (2) at described wingceltis bar (1) two ends is fixed with the first wire rope (3) and the second wire rope (4) respectively, described first wire rope (3) connects the 3rd wire rope (17) by the first lever hoist (5), described second wire rope (4) connects the 3rd wire rope (17) by the second lever hoist (6), described 3rd wire rope (17) is flexibly connected hanging basket (7) by pulley (8).
2. a kind of hanging basket installing roofing bottom colored steel according to claim 1, is characterized in that, the 3rd wire rope (17) of described hanging basket (7) both sides is provided with adjustment suspension hook (10).
3. a kind of hanging basket installing roofing bottom colored steel according to claim 2, it is characterized in that, described 3rd wire rope (17) and pulley (8) for 3-5 and described pulley (8) side be provided with from gripping mechanism (9).
4. a kind of hanging basket installing roofing bottom colored steel according to claim 2, it is characterized in that, described hanging basket (7) forms by bottom bar (13) and by the guard rail rod (11) that diagonal brace (16) connects, described bottom bar (13) is provided with sheer pole (14), described sheer pole (14) is equipped with plank (15); Described guard rail rod (11) is provided with cross tube (12).
CN201510306087.XA 2015-06-05 2015-06-05 A kind of hanging basket for installing roofing bottom colored steel Active CN104963495B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510306087.XA CN104963495B (en) 2015-06-05 2015-06-05 A kind of hanging basket for installing roofing bottom colored steel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510306087.XA CN104963495B (en) 2015-06-05 2015-06-05 A kind of hanging basket for installing roofing bottom colored steel

Publications (2)

Publication Number Publication Date
CN104963495A true CN104963495A (en) 2015-10-07
CN104963495B CN104963495B (en) 2017-07-14

Family

ID=54217560

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510306087.XA Active CN104963495B (en) 2015-06-05 2015-06-05 A kind of hanging basket for installing roofing bottom colored steel

Country Status (1)

Country Link
CN (1) CN104963495B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106115573A (en) * 2016-08-19 2016-11-16 中国化学工程第三建设有限公司 The installation equipment of factory roof coloured silk steel inner panel and installation method
CN106812295A (en) * 2017-02-09 2017-06-09 成都启立辰智科技有限公司 A kind of construction hanging basket
CN106836109A (en) * 2017-03-14 2017-06-13 辽宁华三建设工程技术有限公司 A kind of hanging building foot guard repairing treatment suspension platform device
CN109958219A (en) * 2019-04-11 2019-07-02 中国十七冶集团有限公司 A kind of complex environment roofing truss lower part liner plate suspension cable installation method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10104247C1 (en) * 2001-01-31 2002-07-25 Asg Aluminium Systeme Gmbh Traversing installation, used for working on building facades, comprises an endless drive element with a specified minimum value of its total wrap angle on the traction disks
CN101892736A (en) * 2010-08-10 2010-11-24 中建三局东方装饰设计工程有限公司 High altitude moving hanging basket construction method
CN102433985A (en) * 2011-10-15 2012-05-02 于学恭 Quick construction hanging bracket for outer wall of large storage tank
CN202767494U (en) * 2012-09-06 2013-03-06 安徽富煌钢构股份有限公司 Hanging basket for high-altitude roof inner plate construction
EP2677095A2 (en) * 2012-06-21 2013-12-25 GESTA Gesellschaft für Stahlrohrgerüste mit beschränkter Haftung Access system for overhanging or convex curved walls
CN203530851U (en) * 2013-10-16 2014-04-09 中国十七冶集团有限公司 Basket device for combined basket working vehicle
CN203701560U (en) * 2013-12-31 2014-07-09 森特士兴集团股份有限公司 Suspension hanging basket for high-altitude roofing inner plate construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10104247C1 (en) * 2001-01-31 2002-07-25 Asg Aluminium Systeme Gmbh Traversing installation, used for working on building facades, comprises an endless drive element with a specified minimum value of its total wrap angle on the traction disks
CN101892736A (en) * 2010-08-10 2010-11-24 中建三局东方装饰设计工程有限公司 High altitude moving hanging basket construction method
CN102433985A (en) * 2011-10-15 2012-05-02 于学恭 Quick construction hanging bracket for outer wall of large storage tank
EP2677095A2 (en) * 2012-06-21 2013-12-25 GESTA Gesellschaft für Stahlrohrgerüste mit beschränkter Haftung Access system for overhanging or convex curved walls
CN202767494U (en) * 2012-09-06 2013-03-06 安徽富煌钢构股份有限公司 Hanging basket for high-altitude roof inner plate construction
CN203530851U (en) * 2013-10-16 2014-04-09 中国十七冶集团有限公司 Basket device for combined basket working vehicle
CN203701560U (en) * 2013-12-31 2014-07-09 森特士兴集团股份有限公司 Suspension hanging basket for high-altitude roofing inner plate construction

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106115573A (en) * 2016-08-19 2016-11-16 中国化学工程第三建设有限公司 The installation equipment of factory roof coloured silk steel inner panel and installation method
CN106812295A (en) * 2017-02-09 2017-06-09 成都启立辰智科技有限公司 A kind of construction hanging basket
CN106836109A (en) * 2017-03-14 2017-06-13 辽宁华三建设工程技术有限公司 A kind of hanging building foot guard repairing treatment suspension platform device
CN106836109B (en) * 2017-03-14 2022-07-05 辽宁华三建设工程技术有限公司 Suspended platform device for protecting, repairing and processing bottom of suspended building
CN109958219A (en) * 2019-04-11 2019-07-02 中国十七冶集团有限公司 A kind of complex environment roofing truss lower part liner plate suspension cable installation method

Also Published As

Publication number Publication date
CN104963495B (en) 2017-07-14

Similar Documents

Publication Publication Date Title
CN105604334B (en) A kind of rapid constructing method for large span steel truss integral installation
CN106013419B (en) Long-span Cantilever abnormity transfinites structural steel corridor construction engineering method
CN103711323B (en) Utilize the anti-ceiling board construction method of portable tubular truss stage+module roofing
CN106065661A (en) Large span unsettled steel corridor construction engineering method
CN105484502B (en) A kind of industrial premises steel structural roof purlin and support bar combined installation method
CN105822072A (en) Hoisting construction structure and method for air corridor ceiling
CN105625645B (en) Suspension type steel structure lighting skylight construction method
CN104963495A (en) Suspension hanging basket for installation of roof surface bottom layer color plate
CN102979313A (en) High-altitude lifting construction method for overweight steel truss of transferring layer
CN104763109A (en) Quick construction method for pressed bottom tile of large-span steel structure factory building roof
CN202626841U (en) Concrete device for wrapping main arch by hanging method
CN102691269A (en) Movable hanging basket with main arch and concrete outside
CN103912128B (en) The construction method of high-altitude disjunctor steel truss
CN106013453B (en) Long-span Cantilever transfinites structure construction engineering method
CN206233851U (en) Walking type wall color steel plate hanging ladder for installation
CN104153586B (en) A kind of suspension cable hangs the construction method of mounting purlines
CN206636168U (en) Overhanging type scaffold system
CN102116085B (en) Construction method of outpacking structure of steel pipe column with asymmetric steel hanging structure and scaffold
CN205369044U (en) Integration prestressing force stretch -draw frame construction
CN209384613U (en) A kind of soft platform for steel structure installation of daylighting roof
CN208578156U (en) Fast assembling-disassembling can plug-type heat preservation steel structure
CN204081433U (en) Steel structural roof liner profiled sheet construction Special-purpose hanger basket support
CN203257070U (en) Slippage frame operating platform for gallery daylighting roof curtain wall installation
CN103206077B (en) Structure for steel structure roof inner slab installation foot hand cradle
CN203795459U (en) Foundation structure of tower crane for high-altitude roofs

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant