CN201574358U - 步履式平移顶推装置 - Google Patents

步履式平移顶推装置 Download PDF

Info

Publication number
CN201574358U
CN201574358U CN 200920230240 CN200920230240U CN201574358U CN 201574358 U CN201574358 U CN 201574358U CN 200920230240 CN200920230240 CN 200920230240 CN 200920230240 U CN200920230240 U CN 200920230240U CN 201574358 U CN201574358 U CN 201574358U
Authority
CN
China
Prior art keywords
translation
support platform
base
thrustor
pushing tow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 200920230240
Other languages
English (en)
Inventor
张鸿
李宗哲
卞永明
傅琼阁
周光强
姚平
罗自立
秦利升
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI TXMEC TECHNOLOGY Co Ltd
Tongji University
CCCC Second Harbor Engineering Co
CCCC Wuhan Harbour Engineering Design and Research Institute Co Ltd
Original Assignee
SHANGHAI TXMEC TECHNOLOGY Co Ltd
Tongji University
CCCC Second Harbor Engineering Co
CCCC Wuhan Harbour Engineering Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI TXMEC TECHNOLOGY Co Ltd, Tongji University, CCCC Second Harbor Engineering Co, CCCC Wuhan Harbour Engineering Design and Research Institute Co Ltd filed Critical SHANGHAI TXMEC TECHNOLOGY Co Ltd
Priority to CN 200920230240 priority Critical patent/CN201574358U/zh
Application granted granted Critical
Publication of CN201574358U publication Critical patent/CN201574358U/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型公开了一种步履式平移顶推装置,它包括底座,底座顶面上设置平移顶推支撑平台,底座上设有顶升支撑油缸,底座或平移顶推支撑平台上设有用于平移顶推支撑平台纵向移动的顶推装置和用于平移顶推支撑平台横向移动的顶推装置。实用新型自成一体,可以实现顶升、顺桥方向移动,同时还可以实现横桥方向的调整,以适应不同桥型不同方向的线型和坡度要求。并且该套设备将顶推力变为系统的内力,克服了由于其它方法顶推时对桥墩产生的水平推力。可以自动适应顶推拱箱梁的变形,使顶推更安全可靠。

Description

步履式平移顶推装置
技术领域
本实用新型属于桥梁施工设备,具体涉及一种桥梁箱梁的平移顶推装置。
背景技术
目前用于桥梁顶推的设备主要有两类,一类是采用钢绞线分散牵引的方式,另一类是采用液压油缸进行顶升平推的方式。钢绞线分散牵引的方式不可避免的使桥墩承受水平载荷,并且由于钢绞线是柔性的,难以控制各点的牵引载荷,这种方式施工需要对桥墩的水平位移严格监控,并且对桥墩进行加固处理,破坏了原来的设计。液压油缸顶推的方式目前在国内尚无应用,美国实用动力公司设计的平推系统应用于法国米劳大桥施工中,该套平推系统的调整油缸为螺母锁紧式,无法灵活适应钢箱梁的坡度和线形变化,顶推机构的楔形块方式效率低、容易滑出,并且系统没有横向调整装置,无法在顶推施工中控制横桥向位移。
发明内容
本实用新型的目的在于为适应不同坡度、不同线形的钢箱梁整体顶推施工,提供一种本实用步履式平移顶推装置,以克服上述顶推装置的缺陷。
本实用新型的技术方案为:步履式平移顶推装置,它包括底座,底座顶面上设置平移顶推支撑平台,底座上设有顶升支撑油缸,底座或平移顶推支撑平台上设有用于平移顶推支撑平台纵向移动的顶推装置和用于平移顶推支撑平台横向移动的顶推装置。
所述平移顶推支撑平台纵向移动的顶推装置包括设在底座或平移顶推支撑平台上油缸,底座或平移顶推支撑平台端部设的顶块。
所述底座两端设有顶块,底座与平移顶推支撑平台的接触表面之间设有滑移摩擦板。
所述底座设平移顶推支撑平台横向移动的顶推装置,所述横向移动的顶推装置包括顶推油缸,油缸的活塞杆端部连接滚轮。
本实用新型通过在底座上设置升油缸,在底座或平移顶推支撑平台上设有用于平移顶推支撑平台纵向移动的顶推装置和用于平移顶推支撑平台横向移动的顶推装置实现箱梁顶升、顺桥方向移动,同时还可以实现横桥方向的调整,以适应不同桥型不同方向的线型和坡度要求;按照机械标准设计制造,调节精度高;全液压系统驱动,整机体积小、重量轻,控制比较平稳,安全性比较高;顶推设备的上下两结构通过油缸实现顺桥方向的移动,该推力为设备自身的内力,克服了由于其它方法顶推时对桥墩产生的水平推力;通过液压系统的控制,可以自动适应顶推拱箱桥梁的变形,使顶推更安全可靠。
附图说明
图1步履式平移顶推装置的主视示意图。
图2步履式平移顶推装置左视示意图。
图3步履式平移顶推装置俯视示意图。
具体实施方式
如图1所示,底座6是框架式支撑结构,在底座1的两侧对成设置连接四个顶升支撑油缸1,顶升支撑油缸1的活塞杆端部与支撑座13连接。底座6上设有顶面上设置平移顶推支撑平台3,平移顶推支撑平台3是支撑架式支撑平台,平移顶推支撑平台3的顶面设有橡胶垫2。底座或平移顶推支撑平台上设有用于平移顶推支撑平台纵向移动的顶推装置和用于平移顶推支撑平台横向移动的顶推装置。
本实施例中如图1所示,用于平移顶推支撑平台纵向移动的顶推装置包括设在底座6两端的顶块14,平移顶推支撑平台3上设具有双向活塞杆的纵向移动顶推油缸4,双向活塞杆端部与顶块相对,顶块14形成纵向移动顶推油缸4的双向活塞杆反力座。
用于平移顶推支撑平台横向移动的顶推装置,如图2所示,它设在底座6上,包括顶推油缸5,顶推油缸5的活塞杆端部连接滚轮15。本实施例中底座6上设有4个顶推油缸5,平移顶推支撑平台3两侧设有横向移动顶推面16,如图3所示。
底座与平移顶推支撑平台的接触表面之间设有滑移摩擦板,滑移摩擦板包括设在平移顶推支撑平台底面的不锈钢板8和设在底座上表面的聚四氟乙烯板7,不锈钢板和聚四氟乙烯板接触。
图1中计算机主控制器9、分控制模块11、油缸压力行程传感器10以及液压泵站12构成本实施例中的顶升支撑油缸1、纵向移动顶推油缸4和横移顶推油缸5的控制系统。
利用液压泵站12来驱动各个顶升支撑油缸1同步上升,误差控制在±1mm之内;当钢箱梁载荷完全转移到支撑顶升支撑油缸上面时,液压泵站12驱动纵向移动顶推油缸4前进一个行程;顶升支撑油缸1再同步下降,直到载荷完全转移到临时支撑墩上面;顶推平移油缸4空载缩回初始位置;继续重复前面一个循环过程。直到钢箱梁到位。
本装置具有如下特点:
1)纠偏功能强大
该设备具有横向调整功能,通过带导向滚轮的横向调整油缸,限制在横桥向的位移,在顶推施工中控制各个横向调整油缸的位移以进行在线纠偏功能。
2)整体调频功能稳定
该设备具有四个竖向顶升油缸,保证竖向支撑稳定;同时,竖向顶升油缸可以实时在线调整,以适应不同坡度、线形的钢箱梁顶推施工。
3)组合方式,安装方便灵活
该顶推设备分为上部顶推结构和下部支撑结构,上下结构由四组对称的结构组成,全部通过法兰连接,可以灵活拆装。通过在法兰之间增减过渡板,可以适应不同宽度和不同长度要求的钢箱梁施工。
4)设备可前进及后退
该套设备设置双出头的平推油缸,即可以向前顶推,也可以向后顶推,以方便在对位时候的精细调整。

Claims (8)

1.一种步履式平移顶推装置,它包括底座,底座顶面上设置平移顶推支撑平台,其特征在于底座上设有顶升支撑油缸,底座或平移顶推支撑平台上设有用于平移顶推支撑平台纵向移动的顶推装置和用于平移顶推支撑平台横向移动的顶推装置。
2.如权利要求1所述步履式平移顶推装置,其特征在于所述平移顶推支撑平台纵向移动的顶推装置包括设在底座或平移顶推支撑平台上油缸,底座或平移顶推支撑平台端部设的顶块。
3.如权利要求1或2所述步履式平移顶推装置,其特征在于底座两端设有顶块,底座与平移顶推支撑平台的接触表面之间设有滑移摩擦板。
4.如权利要求3所述步履式平移顶推装置,其特征在于平移顶推支撑平台上设具有双向活塞杆的纵向移动顶推油缸,双向活塞杆端部与顶块相对。
5.如权利要求3所述步履式平移顶推装置,其特征在于底座设平移顶推支撑平台横向移动的顶推装置,所述横向移动的顶推装置包括顶推油缸,油缸的活塞杆端部连接滚轮。
6.如权利要求1所述步履式平移顶推装置,其特征在于底座上设有四个顶升支撑油缸。
7.如权利要求3所述步履式平移顶推装置,其特征在于平移支撑平台上设有橡胶垫。
8.如权利要求3所述步履式平移顶推装置,其特征在于滑移摩擦板包括设在平移顶推支撑平台底面的不锈钢板和设在底座上表面的聚四氟乙烯板,不锈钢板和聚四氟乙烯板接触。
CN 200920230240 2009-11-24 2009-11-24 步履式平移顶推装置 Expired - Lifetime CN201574358U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200920230240 CN201574358U (zh) 2009-11-24 2009-11-24 步履式平移顶推装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200920230240 CN201574358U (zh) 2009-11-24 2009-11-24 步履式平移顶推装置

Publications (1)

Publication Number Publication Date
CN201574358U true CN201574358U (zh) 2010-09-08

Family

ID=42694233

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200920230240 Expired - Lifetime CN201574358U (zh) 2009-11-24 2009-11-24 步履式平移顶推装置

Country Status (1)

Country Link
CN (1) CN201574358U (zh)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102002914A (zh) * 2010-11-17 2011-04-06 中铁二十四局集团有限公司 钢箱梁的架设顶推装置
CN102071642A (zh) * 2010-12-16 2011-05-25 河南省新开元路桥工程咨询有限公司 钢桁梁顶推施工时滑道的改进方法
CN102587291A (zh) * 2012-03-27 2012-07-18 中交四航局第一工程有限公司 一种钢箱梁步履式多点顶推施工方法及施工系统
CN102605715A (zh) * 2012-03-26 2012-07-25 无锡华联科技集团有限公司 桥梁u肋装配机的压紧定位机构
CN102862776A (zh) * 2011-07-05 2013-01-09 上海耐斯特液压设备有限公司 步进式重载滑移移运设备
CN103205935A (zh) * 2013-03-11 2013-07-17 中交武汉港湾工程设计研究院有限公司 模块化钢桁梁自动顶推系统及其施工工艺
CN103266566A (zh) * 2013-04-24 2013-08-28 中交武汉港湾工程设计研究院有限公司 一种步履式连续顶推系统及施工方法
CN103993560A (zh) * 2014-06-06 2014-08-20 上海隧道工程股份有限公司 大跨度钢混结合梁步履式顶推施工方法及装置
CN104030205A (zh) * 2014-06-05 2014-09-10 同济大学 一种基于滚动和滑动摩擦的步履式顶推装置
CN104030204A (zh) * 2014-06-05 2014-09-10 同济大学 一种基于滑动摩擦的步履式顶推装置
CN106065574A (zh) * 2016-06-17 2016-11-02 柳州黔桥工程材料有限公司 步履顶推施工过拼板的方法
CN109594482A (zh) * 2018-11-19 2019-04-09 上海同新机电控制技术有限公司 一种挂胶轮式连续顶推设备
CN111452206A (zh) * 2020-04-13 2020-07-28 中铁(天津)隧道工程勘察设计有限公司 一种无干坞液压顶推沉管隧道管段制作装置及方法
CN111472275A (zh) * 2020-03-19 2020-07-31 中铁十局集团第八工程有限公司 用于橫跨两个铁路营业线的槽型梁支撑装置和顶推就位方法及其应用
CN113513630A (zh) * 2021-04-30 2021-10-19 四川石油天然气建设工程有限责任公司 用于狭窄深谷或宽阔河流的管道跨越顶推系统及其工艺
CN114561875A (zh) * 2022-03-21 2022-05-31 中铁五局集团机械化工程有限责任公司 一种钢箱梁顶推及高位落梁方法

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102002914A (zh) * 2010-11-17 2011-04-06 中铁二十四局集团有限公司 钢箱梁的架设顶推装置
CN102071642A (zh) * 2010-12-16 2011-05-25 河南省新开元路桥工程咨询有限公司 钢桁梁顶推施工时滑道的改进方法
CN102071642B (zh) * 2010-12-16 2013-01-23 河南省新开元路桥工程咨询有限公司 钢桁梁顶推施工时滑道的改进方法
CN102862776A (zh) * 2011-07-05 2013-01-09 上海耐斯特液压设备有限公司 步进式重载滑移移运设备
CN102605715A (zh) * 2012-03-26 2012-07-25 无锡华联科技集团有限公司 桥梁u肋装配机的压紧定位机构
CN102605715B (zh) * 2012-03-26 2014-07-23 武船重型工程股份有限公司 桥梁u肋装配机的压紧定位机构
CN102587291B (zh) * 2012-03-27 2014-11-05 中交四航局第一工程有限公司 一种钢箱梁步履式多点顶推施工方法及施工系统
CN102587291A (zh) * 2012-03-27 2012-07-18 中交四航局第一工程有限公司 一种钢箱梁步履式多点顶推施工方法及施工系统
CN103205935A (zh) * 2013-03-11 2013-07-17 中交武汉港湾工程设计研究院有限公司 模块化钢桁梁自动顶推系统及其施工工艺
CN103205935B (zh) * 2013-03-11 2015-06-24 中交武汉港湾工程设计研究院有限公司 模块化钢桁梁自动顶推系统及其施工工艺
CN103266566A (zh) * 2013-04-24 2013-08-28 中交武汉港湾工程设计研究院有限公司 一种步履式连续顶推系统及施工方法
CN104030205A (zh) * 2014-06-05 2014-09-10 同济大学 一种基于滚动和滑动摩擦的步履式顶推装置
CN104030204A (zh) * 2014-06-05 2014-09-10 同济大学 一种基于滑动摩擦的步履式顶推装置
CN104030205B (zh) * 2014-06-05 2016-05-18 同济大学 一种基于滚动和滑动摩擦的步履式顶推装置
CN103993560A (zh) * 2014-06-06 2014-08-20 上海隧道工程股份有限公司 大跨度钢混结合梁步履式顶推施工方法及装置
CN103993560B (zh) * 2014-06-06 2016-04-13 上海隧道工程有限公司 大跨度钢混结合梁步履式顶推施工方法及装置
CN106065574A (zh) * 2016-06-17 2016-11-02 柳州黔桥工程材料有限公司 步履顶推施工过拼板的方法
CN109594482A (zh) * 2018-11-19 2019-04-09 上海同新机电控制技术有限公司 一种挂胶轮式连续顶推设备
CN111472275A (zh) * 2020-03-19 2020-07-31 中铁十局集团第八工程有限公司 用于橫跨两个铁路营业线的槽型梁支撑装置和顶推就位方法及其应用
CN111452206A (zh) * 2020-04-13 2020-07-28 中铁(天津)隧道工程勘察设计有限公司 一种无干坞液压顶推沉管隧道管段制作装置及方法
CN113513630A (zh) * 2021-04-30 2021-10-19 四川石油天然气建设工程有限责任公司 用于狭窄深谷或宽阔河流的管道跨越顶推系统及其工艺
CN114561875A (zh) * 2022-03-21 2022-05-31 中铁五局集团机械化工程有限责任公司 一种钢箱梁顶推及高位落梁方法

Similar Documents

Publication Publication Date Title
CN201574358U (zh) 步履式平移顶推装置
CN201428114Y (zh) 大型钢拱梁、钢箱梁施工用顶推设备
CN201161902Y (zh) 液压双缸驱动升降装置
CN204875552U (zh) 一种架桥机垂直升降结构
CN104477734A (zh) 一种超深立井罐道钢丝绳张紧装置及张紧方法
CN106087747A (zh) 步履顶推施工纠偏方法
CN102745593A (zh) 一种驾驶室升降器
CN203794570U (zh) 一种标准节顶升装置
CN108691277A (zh) 用于节段预制拼装梁在架设过程中定位的三维调整工装
CN109081259B (zh) 一种在狭窄空间内实现燃机大型pcc设备安装就位的方法
CN102229401B (zh) 井下维修行车支架
CN202250224U (zh) 一种转载机自移装置及其锚固装置
CN218667177U (zh) 一种桥梁液压可调式重物移运器
CN106065574A (zh) 步履顶推施工过拼板的方法
CN106012853A (zh) 步履顶推施工方法
CN202729618U (zh) 驾驶室升降器
CN206970027U (zh) 主机机架起升装置
CN102305035B (zh) 车载式修井机整机对中井口调整装置
CN206591444U (zh) 一种用于快速更换桥梁支座的系统
CN214301282U (zh) 桥梁用楔型推进装置
CN114348868A (zh) 一种用于煤矿单轨吊机车的伸缩式起吊梁
CN210341677U (zh) 一种顶升单元水平调整结构
CN203402798U (zh) 锁罐摇台
CN201554467U (zh) 上置针梁式液压钢模台车
CN221118269U (zh) 一种桥梁移梁装置

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20100908