CN111549670A - 一种采用贝雷架的竖向支撑体系及施工方法 - Google Patents
一种采用贝雷架的竖向支撑体系及施工方法 Download PDFInfo
- Publication number
- CN111549670A CN111549670A CN202010367912.8A CN202010367912A CN111549670A CN 111549670 A CN111549670 A CN 111549670A CN 202010367912 A CN202010367912 A CN 202010367912A CN 111549670 A CN111549670 A CN 111549670A
- Authority
- CN
- China
- Prior art keywords
- bailey
- conversion beam
- head
- male
- female head
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Rod-Shaped Construction Members (AREA)
Abstract
本发明涉及建筑施工领域,具体是一种采用贝雷架的竖向支撑体系;其特征是:包括预制混凝土块(1)、母头转换梁(2)、销轴(3)、母头(4)、贝雷片(5)、公头(6)、公头转换梁(7)、加劲肋(8)、钢埋件(9);其中,钢埋件(9)有四个并埋入预制混凝土块(1)内,加劲肋(8)焊接于公头转换梁(7)或母头转换梁(2)的型钢腹板上,销轴(3)使贝雷片(5)与公头(6)或母头(4)连接。本支撑体系构造简单,所需临时措施较小,施工方法方便快捷,减少人力费用。同时,本体系拆组方便,利用标准化贝雷架,可以用车辆实现倒运和重复利用;可根据受力大小不同,增加或减少贝雷片组装数,灵活多变,适用不同施工类型需要。
Description
技术领域
本发明涉及建筑施工领域,具体是一种采用贝雷架的竖向支撑体系及施工方法。
背景技术
通常,贝雷架作为支撑受力体系多使用在桥梁施工领域,并且,根据其架设形式,多为水平受力方向的结构。而建筑施工领域中,往往需要的是竖向支撑结构,对于竖向支撑结构而言多采用脚手架或格构胎架来作为支撑受理体系。对于脚手架或格构胎架而言,其搭建过程相较贝雷架而言更为繁复并且对于脚手架而言,还有损耗率的问题存在。
发明内容
本发明的目的在于克服上述缺陷,提出一种采用贝雷架形式的竖向支撑体系并将其应用在建筑施工领域中。
为了达到上述目的,本发明是这样实现的:
一种采用贝雷架的竖向支撑体系,包括预制混凝土块、母头转换梁、销轴、母头、贝雷片、公头、公头转换梁、加劲肋、钢埋件;其中,钢埋件有四个并埋入预制混凝土块内,用于连接母头的底座,加劲肋焊接于公头转换梁或母头转换梁的型钢腹板上,用于加强型钢受力;销轴使贝雷片与公头或母头连接。
所述采用贝雷架的竖向支撑体系的使用方法,包括
步骤1、采用H型钢、钢板、螺纹钢筋来制作贝雷片;
步骤2、制作钢埋件和预制混凝土块;
步骤3、制作母头和公头并使该两者分别与母头转换梁、公头转换梁焊接,其中,公头转换梁的高度由标准贝雷片的施工余量来确定;
步骤4、组装贝雷并安装到母头上,插入销轴使两者连接;
步骤5、安装公头转换梁,插入销轴使两者连接;
步骤6、将预制混凝土块运至施工地点,确定与受力地面接触良好;
步骤7、利用起重机将贝雷片及附件整块竖直吊运至预制混凝土块的四个钢埋件上,使母头转换梁与钢埋件焊死,然后起重机缓慢松钩;
步骤8、施工结束后先对公头转换梁卸力,然后起重机吊起贝雷架,此时只保证其竖向稳定,不离地面;之后拔掉母头处的销轴,使贝雷架与预制混凝土块分离;
步骤9、将预制混凝土块和贝雷片转移至其他施工区域,重复4-9步骤可完成下一次施工。
本竖向支撑体系具有以下优点:
(1)该支撑体系构造简单,所需临时措施较小,施工方法方便快捷,减少人力费用。
(2)拆组方便,利用标准化贝雷架,可以用车辆实现倒运和重复利用;
(3)可根据受力大小不同,增加或减少贝雷片组装数,灵活多变,适用不同施工类型需要。
附图说明
图1为本发明所提出的贝雷架支撑体系示意图。
图2为本发明所提出的贝雷架支撑体系三维图。
图3为预制混凝土块示意图。
图4为公头示意图。
图5为母头示意图。
图6为母头转换梁模型。
图7为公头转换梁模型。
图8为标准贝雷架安装方法。
具体实施方式
以下通过具体实施例进一步说明本发明。
如图1~图8所示,一种采用贝雷架的竖向支撑体系,包括预制混凝土块1、母头转换梁2、销轴3、母头4、贝雷片5、公头6、公头转换梁7、加劲肋8、钢埋件9;其中,钢埋件9有四个并埋入预制混凝土块1内,用于连接母头4的底座,加劲肋8焊接于公头转换梁7或母头转换梁2的型钢腹板上,用于加强型钢受力;销轴3使贝雷片5与公头6或母头4连接。
所述采用贝雷架的竖向支撑体系的使用方法,包括
步骤1、采用H型钢、钢板、螺纹钢筋来制作贝雷片5;
步骤2、制作钢埋件9和预制混凝土块1;
步骤3、制作母头4和公头6并使该两者分别与母头转换梁2、公头转换梁7焊接,其中,公头转换梁7的高度由标准贝雷片5的施工余量来确定;
步骤4、组装贝雷5并安装到母头4上,插入销轴3使两者连接;
步骤5、安装公头转换梁7,插入销轴3使两者连接;
步骤6、将预制混凝土块1运至施工地点,确定与受力地面接触良好;
步骤7、利用起重机将贝雷片5及附件整块竖直吊运至预制混凝土块1的四个钢埋件9上,使母头转换梁2与钢埋件9焊死,然后起重机缓慢松钩;
步骤8、施工结束后先对公头转换梁7卸力,然后起重机吊起贝雷架,此时只保证其竖向稳定,不离地面;之后拔掉母头4处的销轴3,使贝雷架与预制混凝土块1分离;
步骤9、将预制混凝土块1和贝雷片5转移至其他施工区域,重复4-9步骤可完成下一次施工。
本竖向支撑体系具有以下优点:
(1)该支撑体系构造简单,所需临时措施较小,施工方法方便快捷,减少人力费用。
(2)拆组方便,利用标准化贝雷架,可以用车辆实现倒运和重复利用;
(3)可根据受力大小不同,增加或减少贝雷片组装数,灵活多变,适用不同施工类型需要。
Claims (2)
1. 一种采用贝雷架的竖向支撑体系,其特征是:包括预制混凝土块(1)、母头转换梁(2)、销轴(3)、母头(4)、贝雷片(5)、公头(6)、公头转换梁(7)、加劲肋(8)、钢埋件(9);其中,钢埋件(9)有四个并埋入预制混凝土块(1)内,用于连接母头(4)的底座,加劲肋(8)焊接于公头转换梁(7)或母头转换梁(2)的型钢腹板上,用于加强型钢受力;销轴(3)使贝雷片(5)与公头(6)或母头(4)连接。
2.权利要求1所述采用贝雷架的竖向支撑体系的使用方法,其特征是:包括
步骤1、采用H型钢、钢板、螺纹钢筋来制作贝雷片(5);
步骤2、制作钢埋件(9)和预制混凝土块(1);
步骤3、制作母头(4)和公头(6)并使该两者分别与母头转换梁(2)、公头转换梁(7)焊接,其中,公头转换梁(7)的高度由标准贝雷片(5)的施工余量来确定;
步骤4、组装贝雷(5)并安装到母头(4)上,插入销轴(3)使两者连接;
步骤5、安装公头转换梁(7),插入销轴(3)使两者连接;
步骤6、将预制混凝土块(1)运至施工地点,确定与受力地面接触良好;
步骤7、利用起重机将贝雷片(5)及附件整块竖直吊运至预制混凝土块(1)的四个钢埋件(9)上,使母头转换梁(2)与钢埋件(9)焊死,然后起重机缓慢松钩;
步骤8、施工结束后先对公头转换梁(7)卸力,然后起重机吊起贝雷架,此时只保证其竖向稳定,不离地面;之后拔掉母头(4)处的销轴(3),使贝雷架与预制混凝土块(1)分离;
步骤9、将预制混凝土块(1)和贝雷片(5)转移至其他施工区域,重复4-9步骤可完成下一次施工。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010367912.8A CN111549670A (zh) | 2020-04-30 | 2020-04-30 | 一种采用贝雷架的竖向支撑体系及施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010367912.8A CN111549670A (zh) | 2020-04-30 | 2020-04-30 | 一种采用贝雷架的竖向支撑体系及施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111549670A true CN111549670A (zh) | 2020-08-18 |
Family
ID=72004378
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010367912.8A Pending CN111549670A (zh) | 2020-04-30 | 2020-04-30 | 一种采用贝雷架的竖向支撑体系及施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111549670A (zh) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB607437A (en) * | 1946-02-04 | 1948-08-31 | John Gwynne Whitman | Improvements in or relating to rafting equipment |
CN203846403U (zh) * | 2014-05-14 | 2014-09-24 | 中铁第五勘察设计院集团有限公司 | 一种装配式岸上临时支墩装置 |
CN206418464U (zh) * | 2016-12-20 | 2017-08-18 | 上海建工七建集团有限公司 | 一种贝雷架支撑体系 |
CN109778702A (zh) * | 2019-02-26 | 2019-05-21 | 中铁七局集团有限公司 | 跨既有城市立交钢箱梁顶推模型及其使用方法 |
CN110735525A (zh) * | 2019-10-22 | 2020-01-31 | 武汉建工集团股份有限公司 | 一种预制装配式自立钢管脚手架系统 |
-
2020
- 2020-04-30 CN CN202010367912.8A patent/CN111549670A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB607437A (en) * | 1946-02-04 | 1948-08-31 | John Gwynne Whitman | Improvements in or relating to rafting equipment |
CN203846403U (zh) * | 2014-05-14 | 2014-09-24 | 中铁第五勘察设计院集团有限公司 | 一种装配式岸上临时支墩装置 |
CN206418464U (zh) * | 2016-12-20 | 2017-08-18 | 上海建工七建集团有限公司 | 一种贝雷架支撑体系 |
CN109778702A (zh) * | 2019-02-26 | 2019-05-21 | 中铁七局集团有限公司 | 跨既有城市立交钢箱梁顶推模型及其使用方法 |
CN110735525A (zh) * | 2019-10-22 | 2020-01-31 | 武汉建工集团股份有限公司 | 一种预制装配式自立钢管脚手架系统 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107090932B (zh) | 基于劲性环梁的大跨度薄壁平面拱桁架的施工方法 | |
CN102900024B (zh) | 大型混凝土结构翻升模板的使用方法 | |
CN102251664A (zh) | 现浇楼梯踏步模板一次成型施工方法 | |
CN115467421B (zh) | 一种复杂大跨钢屋盖吊装施工方法 | |
CN109812021A (zh) | 一种大跨度焊接球网架的安装方法 | |
CN102587665B (zh) | 一种双肢剪力墙结构的浇注方法 | |
CN113356056A (zh) | 一种大跨径钢桥工厂装配化整体制造方法 | |
CN110043035B (zh) | 一种后浇带施工支撑方法 | |
CN111561071A (zh) | 一种装配式剪力墙连接装置及安装方法 | |
CN111549670A (zh) | 一种采用贝雷架的竖向支撑体系及施工方法 | |
CN210917711U (zh) | 一种预制装配式基础的装配式建筑 | |
CN211949131U (zh) | 一种组合上弦波纹腹板密肋次梁楼盖系统 | |
CN210288825U (zh) | 一种装配式、现浇组合梁板结构 | |
CN210195036U (zh) | 槽型叠合梁 | |
CN105863261A (zh) | 一种万向可调式悬挂模板系统 | |
CN107762071B (zh) | 一种预制钢筋笼结构、浇筑结构体及结构体施工方法 | |
CN220661246U (zh) | 一种预制箱梁的底模和侧模组合体系及包括其的成型系统 | |
CN111648255A (zh) | 一种适用于快速化施工的变截式悬臂模板和采用变截式悬臂模板的施工方法 | |
CN214614156U (zh) | 一种预制钢筋混凝土胎模 | |
CN219906683U (zh) | 柱钢模与钢筋笼整体成型吊装结构 | |
CN110552422A (zh) | 装配式地下结构构配件 | |
CN114263275B (zh) | 高层装配式钢结构-核心筒同层施工工法 | |
CN218436660U (zh) | 一种快速校正湿接缝钢筋的简易装置 | |
CN112627509B (zh) | 一种用于井筒形钢覆面砼墙的装配式楔形内撑装置及其施工方法 | |
CN220166688U (zh) | 一种楼承板桥面板悬臂吊模支架 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200818 |
|
RJ01 | Rejection of invention patent application after publication |