CN111173304A - 一种砖混结构房屋改造承重墙增设门洞加固方法 - Google Patents
一种砖混结构房屋改造承重墙增设门洞加固方法 Download PDFInfo
- Publication number
- CN111173304A CN111173304A CN201811373390.1A CN201811373390A CN111173304A CN 111173304 A CN111173304 A CN 111173304A CN 201811373390 A CN201811373390 A CN 201811373390A CN 111173304 A CN111173304 A CN 111173304A
- Authority
- CN
- China
- Prior art keywords
- door opening
- steel
- brick
- lintel
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
- E04G23/0222—Replacing or adding wall ties
-
- E—FIXED CONSTRUCTIONS
- E06—DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
- E06B—FIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
- E06B1/00—Border constructions of openings in walls, floors, or ceilings; Frames to be rigidly mounted in such openings
- E06B1/02—Base frames, i.e. template frames for openings in walls or the like, provided with means for securing a further rigidly-mounted frame; Special adaptations of frames to be fixed therein
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Load-Bearing And Curtain Walls (AREA)
Abstract
本发明涉及一种砖混结构房屋改造承重墙增设门洞加固方法,第一步,建模计算替代门洞部位墙体承重所需型钢规格;门洞上方过梁采用两根型钢,两侧立柱采用两根钢管;第二步,进行结构安装工作:首先在墙体拟开门洞过梁位置横向切槽放置钢过梁,紧贴钢过梁上下边缘钻孔设置上下拉接钢筋;然后在墙体拟开门洞立柱位置竖向切槽,放置钢立柱,并在两侧墙体钻孔设置拉结筋固定钢立柱;最后立柱与过梁焊接牢固形成支撑结构;第三步,拆除门洞部位墙体。本发明的砖混结构房屋改造承重墙增设门洞加固方法,通过采用砖混结构房屋改造承重墙增设门洞加固技术,对承重砖墙增设门洞而言,施工安全得到了最大保证,对原结构扰动降到最低,缩短施工周期,创造了极大的经济效益与社会效益。
Description
技术领域
本发明涉及一种砖混结构中因承重墙增设门洞方法,具体涉及一种砖混结构房屋改造承重墙增设门洞加固方法。
背景技术
砖混结构承重墙增设门洞,主要采用先将门洞部位墙体拆除,安装支撑门框装置;该方法施工风险较大,且对原结构有较大扰动,对技术要求相对比较高,且施工周期较长,如果实施不当,后期墙体的使用会有很大的安全隐患。
发明内容
(一)要解决的技术问题
为解决上述问题,本发明提出了一种砖混结构房屋改造承重墙增设门洞加固方法,采用在承重砖墙上切槽安装型钢支撑,降低工作风险。
(二)技术方案
本发明的砖混结构房屋改造承重墙增设门洞加固方法,
1、一种砖混结构房屋改造承重墙增设门洞加固方法,其特征在于:
第一步,建模计算替代门洞部位墙体承重所需型钢规格;门洞上方过梁采用两根型钢,两侧立柱采用两根钢管;
第二步,进行结构安装工作:首先在墙体拟开门洞过梁位置横向切槽放置钢过梁,紧贴钢过梁上下边缘钻孔设置上下拉接钢筋;然后在墙体拟开门洞立柱位置竖向切槽,放置钢立柱,并在两侧墙体钻孔设置拉结筋固定钢立柱;最后立柱与过梁焊接牢固形成支撑结构;
第三步,拆除门洞部位墙体。
优选的,所述的两根对称型钢过梁为槽钢。
优选的,所述的两侧两根钢管立柱为方钢。
优选的,所述的过梁、立柱位置墙体切槽采用静力切割方式。
优选的,所述的拆除门洞部位墙体可采用静力切割,也可采用人工、机械凿除。
(三)有益效果
本发明与现有技术相比较,其具有以下有益效果:本发明的砖混结构房屋改造承重墙增设门洞加固方法,通过采用砖混结构房屋改造承重墙增设门洞加固技术,对承重砖墙增设门洞而言,施工安全得到了最大保证,对原结构扰动降到最低,缩短施工周期,创造了极大的经济效益与社会效益。
附图说明
图1是本发明的墙体开槽安装过梁和钢柱示意图;
图2是本发明的凿除门洞部位后砌体示意图。
图中:1、型钢过梁;2、钢立柱;3、拉接钢筋。
具体实施方式
实施例1:
如图1和图2所示,本发明的砖混结构房屋改造承重墙增设门洞加固方法。
第一步,定位前工作,建模计算代替门洞部位墙体承重所需型钢规格;型钢过梁采用两个槽钢1,两侧立柱采用方钢管2;
第二步,进行定位工作;首先在墙体拟开门洞过梁位置切槽放置钢过梁槽钢1,紧贴槽钢1上下边缘钻孔设置上下拉接钢筋3;在墙体拟开门洞立柱位置墙体切槽,放置方钢管立柱2,并在两侧墙体钻孔设置拉结筋固定钢立柱;最后立柱与过梁焊接牢固形成支撑结构。
第三步,采用静力切割或者人工、机械拆除门洞部位墙体。
上面所述的实施例仅仅是对本发明的优选实施方式进行描述,并非对本发明的构思和范围进行限定。在不脱离本发明设计构思的前提下,本领域普通人员对本发明的技术方案做出的各种变型和改进,均应落入到本发明的保护范围,本发明请求保护的技术内容,已经全部记载在权利要求书中。
Claims (5)
1.一种砖混结构房屋改造承重墙增设门洞加固方法,其特征在于:
第一步,建模计算替代门洞部位墙体承重所需型钢规格;门洞上方过梁采用两根型钢,两侧立柱采用两根钢管;
第二步,进行结构安装工作:首先在墙体拟开门洞过梁位置横向切槽放置钢过梁,紧贴钢过梁上下边缘钻孔设置上下拉接钢筋;然后在墙体拟开门洞立柱位置竖向切槽,放置钢立柱,并在两侧墙体钻孔设置拉结筋固定钢立柱;最后立柱与过梁焊接牢固形成支撑结构;
第三步,拆除门洞部位墙体。
2.根据权利要求1所述的砖混结构房屋改造承重墙增设门洞加固方法其特征在于:所述的两根对称型钢过梁过来为槽钢。
3.根据权利要求1所述的砖混结构房屋改造承重墙增设门洞加固方法其特征在于:所述的两侧两根钢管立柱为方钢。
4.根据权利要求1所述的砖混结构房屋改造承重墙增设门洞加固方法其特征在于:所述的过梁、立柱位置墙体切槽采用静力切割方式。
5.根据权利要求1所述的砖混结构房屋改造承重墙增设门洞加固方法其特征在于:所述的拆除门洞部位墙体可采用静力切割,也可采用人工、机械凿除。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811373390.1A CN111173304A (zh) | 2018-11-13 | 2018-11-13 | 一种砖混结构房屋改造承重墙增设门洞加固方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811373390.1A CN111173304A (zh) | 2018-11-13 | 2018-11-13 | 一种砖混结构房屋改造承重墙增设门洞加固方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111173304A true CN111173304A (zh) | 2020-05-19 |
Family
ID=70657355
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811373390.1A Pending CN111173304A (zh) | 2018-11-13 | 2018-11-13 | 一种砖混结构房屋改造承重墙增设门洞加固方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111173304A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114293805A (zh) * | 2021-12-27 | 2022-04-08 | 上海建工二建集团有限公司 | 承重墙开洞的托换结构及方法 |
CN114635586A (zh) * | 2022-02-22 | 2022-06-17 | 中国华冶科工集团有限公司 | 砖混结构承重墙拆除方法及支撑框架 |
CN115492415A (zh) * | 2022-09-15 | 2022-12-20 | 浙江省送变电工程有限公司 | 一种高安全性的临时门洞加固支撑方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11210236A (ja) * | 1998-01-23 | 1999-08-03 | Alpha Kogyo Kk | 既存壁の静的破砕除去工法 |
CN101638920A (zh) * | 2008-07-29 | 2010-02-03 | 贵阳铝镁设计研究院 | 一种承重墙上的洞口结构及在承重墙上开设洞口的方法 |
CN101831969A (zh) * | 2010-05-07 | 2010-09-15 | 华太建设集团有限公司 | 自平衡式支撑承重墙体开设洞口的方法 |
CN101839029A (zh) * | 2010-05-07 | 2010-09-22 | 华太建设集团有限公司 | 自平衡式托承重墙开设洞口的方法 |
JP2012062714A (ja) * | 2010-09-17 | 2012-03-29 | Taisei Corp | 仕上材撤去方法 |
CN206053397U (zh) * | 2016-09-06 | 2017-03-29 | 上海鼎创建筑设计有限公司 | 砌体结构承重墙体开洞加固结构 |
CN108222540A (zh) * | 2018-03-23 | 2018-06-29 | 兰州理工大学 | 砖混结构改为框架结构的承重墙改梁结构及施工方法 |
-
2018
- 2018-11-13 CN CN201811373390.1A patent/CN111173304A/zh active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11210236A (ja) * | 1998-01-23 | 1999-08-03 | Alpha Kogyo Kk | 既存壁の静的破砕除去工法 |
CN101638920A (zh) * | 2008-07-29 | 2010-02-03 | 贵阳铝镁设计研究院 | 一种承重墙上的洞口结构及在承重墙上开设洞口的方法 |
CN101831969A (zh) * | 2010-05-07 | 2010-09-15 | 华太建设集团有限公司 | 自平衡式支撑承重墙体开设洞口的方法 |
CN101839029A (zh) * | 2010-05-07 | 2010-09-22 | 华太建设集团有限公司 | 自平衡式托承重墙开设洞口的方法 |
JP2012062714A (ja) * | 2010-09-17 | 2012-03-29 | Taisei Corp | 仕上材撤去方法 |
CN206053397U (zh) * | 2016-09-06 | 2017-03-29 | 上海鼎创建筑设计有限公司 | 砌体结构承重墙体开洞加固结构 |
CN108222540A (zh) * | 2018-03-23 | 2018-06-29 | 兰州理工大学 | 砖混结构改为框架结构的承重墙改梁结构及施工方法 |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114293805A (zh) * | 2021-12-27 | 2022-04-08 | 上海建工二建集团有限公司 | 承重墙开洞的托换结构及方法 |
CN114635586A (zh) * | 2022-02-22 | 2022-06-17 | 中国华冶科工集团有限公司 | 砖混结构承重墙拆除方法及支撑框架 |
CN114635586B (zh) * | 2022-02-22 | 2023-12-01 | 中国华冶科工集团有限公司 | 砖混结构承重墙拆除方法及支撑框架 |
CN115492415A (zh) * | 2022-09-15 | 2022-12-20 | 浙江省送变电工程有限公司 | 一种高安全性的临时门洞加固支撑方法 |
CN115492415B (zh) * | 2022-09-15 | 2024-08-16 | 浙江省送变电工程有限公司 | 一种高安全性的临时门洞加固支撑方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111173304A (zh) | 一种砖混结构房屋改造承重墙增设门洞加固方法 | |
CN108396780B (zh) | 一种既有检查井改建方法 | |
CN104947681B (zh) | 一种超大超深地下室基坑的施工方法 | |
CN103132537A (zh) | 钢格构柱回字型混凝土承台组合式塔吊基础结构及施工方法 | |
CN101603338A (zh) | 装配整体式预制混凝土剪力墙及施工方法 | |
CN106088102A (zh) | 格构式组合钢板桩水泥土复合桩及其施工方法 | |
CN104594655A (zh) | 一种砖混结构墙体拆除临时支撑的应用方法 | |
CN107355008B (zh) | 一种新增钢管混凝土柱与既有结构的预制连接结构及方法 | |
CN112096425A (zh) | 一种马头门位置的横通道支护系统及其施工方法 | |
CN203200745U (zh) | 一种逆作法施工中地下连续墙的加固支撑 | |
CN214883827U (zh) | 一种施工升降机悬挑基础支撑体系装置 | |
CN208518680U (zh) | 一种用于公路隧道波纹钢初期支护的喷砼封堵结构 | |
CN202595747U (zh) | 用于u形混凝土板桩沉桩的型钢导向架 | |
CN102400564A (zh) | 砌体结构承重墙后开洞口的临时托换体系及其施工方法 | |
CN218479176U (zh) | 一种用于钢筋混凝土基坑支撑内的外框柱安装节点 | |
CN210598156U (zh) | 一种钢支撑拆除辅助装置 | |
CN205046558U (zh) | 逆作法中基坑出土洞口的内支撑梁结构 | |
CN209760799U (zh) | 一种应用于装配式现浇段无支撑工具化模板体系 | |
CN211257025U (zh) | 一种具有注浆平台的钢板桩围堰 | |
CN106761770B (zh) | 暗挖隧道受力体系二次转换施工方法 | |
CN211547754U (zh) | 高边坡锚杆支护工作平台 | |
CN208517947U (zh) | 组合式可回收钢管柱 | |
CN102677679A (zh) | 建筑基坑用现浇异型钢筋混凝土桩芯水泥土地下连续墙 | |
KR20040076245A (ko) | 철근콘크리트 벽식구조 철근망 지상조립(공장조립) 인양설치 공법 | |
CN107938663B (zh) | 穿越主体结构部位的phc管桩作支撑体系格构柱连接器 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20200519 |