CN104947681B - 一种超大超深地下室基坑的施工方法 - Google Patents

一种超大超深地下室基坑的施工方法 Download PDF

Info

Publication number
CN104947681B
CN104947681B CN201510393368.3A CN201510393368A CN104947681B CN 104947681 B CN104947681 B CN 104947681B CN 201510393368 A CN201510393368 A CN 201510393368A CN 104947681 B CN104947681 B CN 104947681B
Authority
CN
China
Prior art keywords
area
construction
basement
ground pit
support replacement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510393368.3A
Other languages
English (en)
Other versions
CN104947681A (zh
Inventor
戴旭强
刘波
杨利民
彭建锋
黎平
袁小兵
曾寅
陈颖
陈广照
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Original Assignee
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Engineering Co Ltd of China Construction Third Engineering Division filed Critical Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority to CN201510393368.3A priority Critical patent/CN104947681B/zh
Publication of CN104947681A publication Critical patent/CN104947681A/zh
Application granted granted Critical
Publication of CN104947681B publication Critical patent/CN104947681B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明涉及一种超大超深地下室基坑的施工方法,步骤为:通过地下连续墙和钻孔灌注排桩将整体一分为三,两侧分区同时顺作施工,中间区作为缓冲区后施工;在施工过程中通过环形支撑及换撑梁将基坑所受水平力传至缓冲区以确保基坑开挖过程中的安全稳定;两侧分区地下室结构施工完成后,才进行缓冲区地下室基坑开挖,开挖过程中同样遵循“先撑后挖”原则,待缓冲区地下室结构施工完成后,才从上至下依次拆除各层换撑梁。本发明在施工过程中通过环形支撑及换撑梁抵消基坑所受水平力,保证了基坑的整体稳定性。采用本方法进行施工,既解决了超大、超深基坑施工安全问题,同时大大减小了超大基坑的技术和施工难度提高了基坑施工效率。

Description

一种超大超深地下室基坑的施工方法
技术领域
本发明涉及一种超大超深地下室基坑的施工方法。主要用于超大超深地下室结构施工中。
背景技术
目前建筑工程中,现有的地下室基坑支护体系常采用“先撑后挖环梁支撑体系”,即在基坑开挖前先施工地下连续墙及环梁支撑体系,再进行挖土。该体系适用于一般大型的地下室基坑,对于超大超深地下室基坑不适用。
发明内容
本发明的目的是为了克服上述现有技术存在的时间问题和缺点,提供一种适用于超大超深地下室基坑的施工方法,本发明通过地下连续墙和钻孔灌注排桩将超大超深基坑整体一分为三,两侧分区同时顺作施工,中间区作为缓冲区后施工,在施工过程中通过环形支撑及换撑梁抵消基坑所受水平力,保证了基坑的整体稳定性。
一种超大超深地下室基坑的施工方法,其特征在于按以下步骤进行:
步骤(1)在超大超深地下室基坑中设置地下连续墙和钻孔灌注排桩将整体一分为三,两侧分区同时顺作施工,中间区作为缓冲区后施工;
步骤(2)两侧分区即Ⅰ区和Ⅱ区的基坑开挖施工过程中设置环形支撑,将基坑四周的水平力通过环形支撑传至缓冲区即Ⅲ区以确保基坑开挖过程中的安全稳定;
步骤(3)两侧分区即Ⅰ区和Ⅱ区的每层地下室结构施工达到强度后,需拆除当层环形支撑,同时在楼板结构标高处设置混凝土换撑梁或H型工字钢换撑梁,以确保水平力的传递;
步骤(4)两侧分区即Ⅰ区和Ⅱ区的地下室结构施工完成后,才进行缓冲区即Ⅲ区的地下室基坑开挖,开挖过程中同样遵循“先撑后挖”原则,待缓冲区即Ⅲ区的地下室结构施工完成后,才从上至下依次拆除各层换撑梁。
本发明步骤(3)中具体方法为:地下室楼板结构施工中,在汽车坡道或楼梯间结构空缺处预埋H型工字钢换撑梁的封头板,待该处混凝土浇筑完成后,将H型工字钢换撑梁与预埋的封头板焊接;在地下室两侧分区即Ⅰ区和Ⅱ区与缓冲区即Ⅲ区相接处设置临时换撑板带,换撑板带内增设若干钢筋并与钻孔灌注排桩采用加强筋焊接以确保水平力的传递。
本发明将超大超深地下室基坑进行分区施工,各类材料设备投入总量减少,且周转材料利用率显著增加。地下室基坑两侧分区独立平行施工,减小了施工难度,还缩短了施工工期。
本发明在施工过程中通过环形支撑及换撑梁抵消基坑所受水平力,保证了基坑的整体稳定性。采用本方法进行施工,既解决了超大超深基坑施工安全问题,同时大大减小了超大基坑的技术和施工难度提高了基坑施工效率。
附图说明
图1为本发明的分区及支撑平面示意图。
图2为本发明的地下室结构及换撑梁平面布置图。
图3为本发明的H型钢换撑梁立面示意图。
图4为本发明的换撑板带剖面示意图。
具体实施方式
下面结合附图对本发明进行详细的说明:
如图1、图2、图3、图4所示,一种超大超深地下室基坑的分区施工方法,其特征在于按以下步骤进行:
步骤(1)在超大超深地下室基坑四周设置“二墙合一”地下连续墙3作为基坑围护体,并在基坑内设置临时地连墙1和钻孔灌注排桩2将整体一分为三,两侧分区同时顺作施工,中间区作为缓冲区后施工;
步骤(2)两侧分区即Ⅰ区和Ⅱ区的基坑开挖施工过程中设置环形支撑4,将基坑四周的水平力通过环形支撑4传至缓冲区即Ⅲ区以确保基坑开挖过程中的安全稳定;
步骤(3)两侧分区即Ⅰ区和Ⅱ区的每层地下室结构施工达到强度后,需拆除当层环形支撑4,同时在楼板结构标高处设置混凝土换撑梁6或H型工字钢换撑梁5,以确保水平力的传递;具体方法为:地下室楼板结构施工中,在汽车坡道或楼梯间结构空缺处预埋H型工字 钢换撑梁的封头板8,待该处混凝土浇筑完成后,将H型工字钢换撑梁5与预埋的封头板8焊接;在地下室两侧分区(Ⅰ区和Ⅱ区)与缓冲区(Ⅲ区)相接处设置临时换撑板带7,换撑板带7内增设若干钢筋9并与钻孔灌注排桩2采用加强筋10焊接以确保水平力的传递;
步骤(4)两侧分区即Ⅰ区和Ⅱ区的地下室结构施工完成后,才进行缓冲区即Ⅲ区的地下室基坑开挖,开挖过程中同样遵循“先撑后挖”原则,待缓冲区即Ⅲ区的地下室结构施工完成后,才从上至下依次拆除各层换撑梁。
本发明将超大超深地下室基坑进行分区施工,各类材料设备投入总量减少,且周转材料利用率显著增加。地下室基坑两侧分区独立平行施工,减小了施工难度,节约施工工期,创造较高的经济价值。

Claims (1)

1.一种超大超深地下室基坑的施工方法,其特征在于按以下步骤进行:
步骤(1)在超大超深地下室基坑中设置地下连续墙和钻孔灌注排桩将整体一分为三,两侧分区同时顺作施工,中间区作为缓冲区后施工;
步骤(2)两侧分区即Ⅰ区和Ⅱ区的基坑开挖施工过程中设置环形支撑,将基坑四周的水平力通过环形支撑传至缓冲区即Ⅲ区以确保基坑开挖过程中的安全稳定;
步骤(3)两侧分区即Ⅰ区和Ⅱ区的每层地下室结构施工达到强度后,需拆除当层环形支撑,同时在楼板结构标高处设置混凝土换撑梁或H型工字钢换撑梁,以确保水平力的传递;具体方法为:地下室楼板结构施工中,在汽车坡道或楼梯间结构空缺处预埋H型工字钢换撑梁的封头板,待该处混凝土浇筑完成后,将H型工字钢换撑梁与预埋的封头板焊接;在地下室两侧分区即Ⅰ区和Ⅱ区与缓冲区即Ⅲ区相接处设置临时换撑板带,换撑板带内增设若干钢筋并与钻孔灌注排桩采用加强筋焊接以确保水平力的传递;
步骤(4)两侧分区即Ⅰ区和Ⅱ区的地下室结构施工完成后,才进行缓冲区即Ⅲ区的地下室基坑开挖,开挖过程中同样遵循“先撑后挖”原则,待缓冲区即Ⅲ区的地下室结构施工完成后,才从上至下依次拆除各层换撑梁。
CN201510393368.3A 2015-07-07 2015-07-07 一种超大超深地下室基坑的施工方法 Active CN104947681B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510393368.3A CN104947681B (zh) 2015-07-07 2015-07-07 一种超大超深地下室基坑的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510393368.3A CN104947681B (zh) 2015-07-07 2015-07-07 一种超大超深地下室基坑的施工方法

Publications (2)

Publication Number Publication Date
CN104947681A CN104947681A (zh) 2015-09-30
CN104947681B true CN104947681B (zh) 2017-05-10

Family

ID=54162699

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510393368.3A Active CN104947681B (zh) 2015-07-07 2015-07-07 一种超大超深地下室基坑的施工方法

Country Status (1)

Country Link
CN (1) CN104947681B (zh)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105756067B (zh) * 2016-03-11 2018-02-02 天津市建工工程总承包有限公司 一种深基坑内水平临时支撑换撑的方法
CN105804085B (zh) * 2016-04-19 2017-08-25 江苏东合南岩土科技股份有限公司 多单元井筒式地下立体车库分区施工方法
CN105926630B (zh) * 2016-04-27 2018-03-13 中天建设集团有限公司 一种加快深大地下结构施工的环形换撑及跳仓施工方法
CN106522241B (zh) * 2016-12-14 2019-04-12 上海建工一建集团有限公司 超大层高地下室结构的深基坑支护方法
CN108643196A (zh) * 2018-06-28 2018-10-12 华东交通大学 一种适用于任意形状深大基坑的环形内支撑结构设计方法
CN109371981A (zh) * 2018-11-30 2019-02-22 中国人民解放军63926部队 适用于割圆型组合基坑支护结构的设计方法
CN109723085B (zh) * 2019-01-17 2020-11-27 中建三局集团有限公司 一种深基坑分坑施工肋墙换撑结构及其施工方法
CN110644499A (zh) * 2019-09-23 2020-01-03 中天建设集团有限公司 一种基坑非同步施工转换支撑的施工工具和施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1837506A (zh) * 2006-04-12 2006-09-27 上海市政工程设计研究总院 一种在运营中的隧道上方开挖箱形结构的施工方法
CN103510520A (zh) * 2013-10-09 2014-01-15 上海市建工设计研究院有限公司 深大基坑的分区施工方法
CN103590406A (zh) * 2013-11-29 2014-02-19 中船第九设计研究院工程有限公司 一种超大型深基坑分区同步开挖的施工方法
CN103696429A (zh) * 2013-12-03 2014-04-02 中铁十三局集团第三工程有限公司 一种异形基坑的砼支撑加鱼腹梁的组合支撑体系及施工方法
CN203821399U (zh) * 2014-03-22 2014-09-10 王继远 一种深基坑支护结构

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101034398B1 (ko) * 2007-06-28 2011-05-16 (주)바로건설기술 지하 흙막이 공법을 겸한 지하구조물 축조공법

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1837506A (zh) * 2006-04-12 2006-09-27 上海市政工程设计研究总院 一种在运营中的隧道上方开挖箱形结构的施工方法
CN103510520A (zh) * 2013-10-09 2014-01-15 上海市建工设计研究院有限公司 深大基坑的分区施工方法
CN103590406A (zh) * 2013-11-29 2014-02-19 中船第九设计研究院工程有限公司 一种超大型深基坑分区同步开挖的施工方法
CN103696429A (zh) * 2013-12-03 2014-04-02 中铁十三局集团第三工程有限公司 一种异形基坑的砼支撑加鱼腹梁的组合支撑体系及施工方法
CN203821399U (zh) * 2014-03-22 2014-09-10 王继远 一种深基坑支护结构

Also Published As

Publication number Publication date
CN104947681A (zh) 2015-09-30

Similar Documents

Publication Publication Date Title
CN104947681B (zh) 一种超大超深地下室基坑的施工方法
US20210040703A1 (en) Construction method for foundation pit support utilizing prefabricated large-diameter pipe pile
CN106065577B (zh) 一种新的桩基托换的结构与方法
CN103669866B (zh) 地下室钢筋混凝土柱节点连接结构的施工方法
CN104975606B (zh) 逆作基坑与相邻基坑相邻处高低跨处理方法
CN113062354A (zh) 明挖桩撑体系预制装配式地铁车站拼装方法
WO2023066327A1 (zh) 用于由沉墙基础组成的地下建筑的施工法
CN102305091A (zh) 一种硬岩大断面隧道施工的支撑结构及其施工方法
CN204715366U (zh) 一种大面积深基坑分区顺逆工况下的支撑体系
CN107387129B (zh) 一种控制隧道挤压型变形的快速施工方法
CN113153355A (zh) 一种下穿隧道超前管幕施工方法
CN106760851A (zh) 既有砖混结构新增隔震层的施工方法
CN106592600B (zh) 紧邻运行地铁复杂环境预警支护体系施工方法
CN106065668B (zh) 一种建筑施工方法
CN108979663B (zh) 一种采用临时中隔柱支撑的地铁车站主体结构施工方法
KR101187170B1 (ko) 마이크로파일로 전달하는 경사기둥과 기초부 연장 기둥을 라멘골조로 이용한 수직하향증축 시공방법
CN102493458A (zh) 软土地基管沟及电力隧道工程深基坑钢板桩封底施工方法
CN101509258A (zh) 预先控制沉井下沉倾斜的方法
CN103122642A (zh) 一种竖向支柱换撑的施工方法
CN210766861U (zh) 一种狭小空间下门架式建筑物桩基托换结构
CN208167749U (zh) 地铁车站深基坑开挖过程中稳定的钢围檩支撑体系
CN217629964U (zh) 地下室深基坑替换撑
CN204040042U (zh) 一种超大超深人工挖孔桩支护结构
CN111042104A (zh) 在既有地下结构处施工地连墙的方法
CN103132531A (zh) 基坑支护体系施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant