CN108131494B - 一种钢管与水泥预制管连接的施工方法 - Google Patents
一种钢管与水泥预制管连接的施工方法 Download PDFInfo
- Publication number
- CN108131494B CN108131494B CN201711407081.7A CN201711407081A CN108131494B CN 108131494 B CN108131494 B CN 108131494B CN 201711407081 A CN201711407081 A CN 201711407081A CN 108131494 B CN108131494 B CN 108131494B
- Authority
- CN
- China
- Prior art keywords
- pipe
- steel
- prefabricated
- steel pipe
- concrete prefabricated
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/024—Laying or reclaiming pipes on land, e.g. above the ground
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L13/00—Non-disconnectible pipe-joints, e.g. soldered, adhesive or caulked joints
- F16L13/007—Non-disconnectible pipe-joints, e.g. soldered, adhesive or caulked joints specially adapted for joining pipes of dissimilar materials
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L13/00—Non-disconnectible pipe-joints, e.g. soldered, adhesive or caulked joints
- F16L13/02—Welded joints
- F16L13/029—Welded joints for concrete pipes
Abstract
一种钢管与水泥预制管连接的施工方法,先预制内径大于水泥预制管(3)外径的钢管(1)并预留灌浆口(2),卷制钢制变径管(4),再将预制钢管切割成两块半圆板,在半圆板内侧焊上钢筋头(6),将水泥预制管一端外圆面打磨干净并拉毛,将两片半圆板套装在水泥预制管的打磨拉毛段外并焊接成圆管,用麻辫或橡胶软管(7)缠绕封堵水泥预制管与预制钢管之间的间隙(8),用钢制圆环板(9)点焊在预制钢管尾部;在预制钢管底部连接泄水管(10),从灌浆孔灌入高强无收缩灌浆料(11),将预制钢管与钢制变径管扩径段的大口端焊接连接,钢制变径管的另一端与钢管焊接。本发明解决了钢管与水泥预制管连接的技术难题,提高了施工效率和工程质量。
Description
技术领域
本发明涉及市政工程管道连接施工方法技术领域,具体涉及一种钢管与水泥预制管连接的施工方法。
背景技术
在市政工程施工中,管道连接的方式多种多样,目前钢管与水泥预制管连接的方法是在水泥预制管的端部安置钢箍,再与钢管进行焊接;或是在水泥预制管端部焊接钢板后,与钢管的端部采用法兰连接,这两种方法需要对原有供水管道进行较长时间停水且安装钢箍或钢板时,易造成原有管道损伤,甚至断裂,施工工效低,难以确保接头施工质量,需要大量劳动力,严重影响施工进度。对于城市主供水管道的改造,容易造成停水时间长、停水影响大,停水接点施工工期无法保证等影响。
发明内容
本发明的目的在于提供一种钢管与水泥预制管连接的施工方法,有效解决施工过程中对原有管道损坏的修复,提高施工效率,保证工程质量,缩短停水时间,减少停水影响。
本发明采取的技术方案如下:
钢管与水泥预制管连接的施工方法,包括以下步骤:
a.预制钢管并预留灌浆口,所述预制钢管的内径大于水泥预制管外径;
b.卷制钢制变径管,所述钢制变径管由直管段和扩径段构成,直管段内径与钢管内径相同;
c.将预制钢管沿径向切割成两块半圆板,在半圆板内侧焊上钢筋头若干;
d.将水泥预制管一端外圆面打磨干净并拉毛;
e.将预制钢管的两片半圆板套装在水泥预制管的打磨拉毛段外,并通过钢筋头调整好预制钢管与水泥预制管之间的间隙,然后将两半半圆板焊接牢固形成圆管;
f.在预制钢管的一端用麻辫或橡胶软管缠绕封堵水泥预制管与预制钢管之间的间隙,在预制钢管另一端用钢制圆环板点焊在预制钢管的尾部;
g.在预制钢管的底部下端连接泄水管;
h.从灌浆孔灌入高强无收缩灌浆料;
i.待高强无收缩灌浆料养护达到规定强度后,停水切除未灌浆部分的水泥预制管,将预制钢管与钢制变径管扩径段的大口端焊接连接,钢制变径管的另一端与钢管焊接。
与现有施工方法相比,本发明具有以下优点:
a.制作预制钢管套装在水泥预制管外并与变径钢管连接,可有效避免对原水泥预制管的冲击或损伤;
b.预制钢管可在不影响原有供水管道供水的条件下进行安装,停水节点施工时,只需进行预制钢管与钢制变径管、钢制变径管与钢管的焊接,可加快施工速度,缩短停水时间,减少停水影响;
c.预制钢管与水泥预制管之间采用高强无收缩灌浆料填充,可有效避免因连接材料变形造成的渗水、漏水现象,确保管道连接的施工质量,大大降低使用过程中的返修率;
d.施工安装方便,并可显著提高施工效率。
本发明方法特别适用于市政工程供水管网中钢管与水泥预制管的连接。尤其在供水管网出现漏水、断裂时的工程抢修,维修效率高,施工质量好,可大大缩短停水时间。
附图说明
图1为钢管与水泥预制管连接示意图。
具体实施方式
钢管与水泥预制管连接的施工方法,如图1所示,包括以下步骤:
a.预制2米长的钢管1,并预留500mm×500mm灌浆口2;所述预制钢管1的内径大于水泥预制管3外径80mm;
b.卷制钢制变径管4,所述钢制变径管4由直管段和扩径段构成,直管段内径与钢管5内径相同;
c.将预制钢管沿径向切割成两块半圆板并在切割面切出坡口,然后用角磨机打磨干净,在半圆板内侧焊上直径6mm的钢筋头6若干;
d.用角磨机加钢丝轮将水泥预制管3一端套预制钢管位置的外圆面打磨干净并拉毛;
e.用吊车先将预制钢管的两片半圆板吊运包裹在水泥预制管上,与水泥预制管3的打磨拉毛段进行预组装校正,预装校正完成后,将预制钢管的两片半圆板套装在水泥预制管的打磨拉毛段外,并通过钢筋头调整好预制钢管与水泥预制管之间的间隙,然后将两半半圆板焊接牢固形成圆管;
f.在距预制钢管一端头500mm处用麻辫或橡胶软管7缠绕封堵水泥预制管与预制钢管之间的间隙8,在预制钢管1另一端用钢制圆环板9点焊在预制钢管的尾部,封堵两端相距1.5m;
g.在预制钢管的底部下端连接一段DN200泄水管10并配法兰及盲板,用于节点施工时上游阀门关闭不严时排出管内积水;
h.从灌浆孔2灌入高强无收缩灌浆料11,灌浆料时需边浇灌边用锤在预制钢管1外四周轻轻敲击震动并观察封堵段四周冒浆的情况,以保证灌浆料的密实;
i.待高强无收缩灌浆料养护达到规定强度后进行下一步接管施工,停水切除未灌浆部分的水泥预制管,将预制钢管1与钢制变径管4扩径段的大口端焊接连接,钢制变径管4的另一端与钢管5焊接。
Claims (1)
1.一种钢管与水泥预制管连接的施工方法,其特征在于,包括以下步骤:
a.预制钢管(1)并预留灌浆口(2),所述预制钢管(1)内径大于水泥预制管(3)外径;
b.卷制钢制变径管(4),所述钢制变径管(4)由直管段和扩径段构成,直管段内径与钢管(5)内径相同;
c.将预制钢管沿径向切割成两块半圆板,在半圆板内侧焊上钢筋头(6)若干;
d.将水泥预制管(3)一端外圆面打磨干净并拉毛;
e.将预制钢管的两块 半圆板套装在水泥预制管的打磨拉毛段外,并通过钢筋头调整好预制钢管与水泥预制管之间的间隙,然后将两块 半圆板焊接牢固形成圆管;
f.在预制钢管的一端用麻辫或橡胶软管(7)缠绕封堵水泥预制管与预制钢管之间的间隙(8),在预制钢管的另一端用钢制圆环板(9)点焊在预制钢管的尾部;
g.在预制钢管(1)的底部下端连接泄水管(10);
h.从灌浆孔(2)灌入高强无收缩灌浆料(11);
i.待高强无收缩灌浆料养护达到规定强度后,停水切除未灌浆部分的水泥预制管,将预制钢管(1)与钢制变径管(4)扩径段的大口端焊接连接,钢制变径管(4)的另一端与钢管(5)焊接。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711407081.7A CN108131494B (zh) | 2017-12-22 | 2017-12-22 | 一种钢管与水泥预制管连接的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711407081.7A CN108131494B (zh) | 2017-12-22 | 2017-12-22 | 一种钢管与水泥预制管连接的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108131494A CN108131494A (zh) | 2018-06-08 |
CN108131494B true CN108131494B (zh) | 2019-08-13 |
Family
ID=62392326
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711407081.7A Active CN108131494B (zh) | 2017-12-22 | 2017-12-22 | 一种钢管与水泥预制管连接的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108131494B (zh) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109084080B (zh) * | 2018-09-02 | 2021-05-28 | 青岛安装建设股份有限公司 | 一种csp管道预制施工方法 |
CN111795225B (zh) * | 2020-07-22 | 2022-05-10 | 武汉市年华管业有限公司 | 一种水泥管道防水连接方法 |
CN115163936B (zh) * | 2022-07-28 | 2024-04-19 | 中建八局第二建设有限公司 | 一种不同管径不同管材的连接模块装置及制作方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB191202786A (en) * | 1912-02-03 | 1912-09-12 | Richard Ames | An Improved Pipe Joint. |
JP2001355771A (ja) * | 2000-06-13 | 2001-12-26 | Mitsubishi Plastics Ind Ltd | 管の離脱防止構造 |
CN1834516A (zh) * | 2006-04-10 | 2006-09-20 | 王宝根 | 新型管道型材及其连接件 |
CN1920364A (zh) * | 2006-08-28 | 2007-02-28 | 阎金波 | 一种薄壁不锈钢管道注胶式无缝承插连接法 |
CN101225913A (zh) * | 2007-01-15 | 2008-07-23 | 北京安科管道工程科技有限公司 | 一种新型的双层结构管道连接方法及制造工艺 |
CN101525910A (zh) * | 2009-04-07 | 2009-09-09 | 同济大学 | 一种带保护件的灌浆套管耗能元件 |
CN202001741U (zh) * | 2011-01-21 | 2011-10-05 | 杨林海 | 一种玻璃钢管节点加固与双密封结构 |
-
2017
- 2017-12-22 CN CN201711407081.7A patent/CN108131494B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB191202786A (en) * | 1912-02-03 | 1912-09-12 | Richard Ames | An Improved Pipe Joint. |
JP2001355771A (ja) * | 2000-06-13 | 2001-12-26 | Mitsubishi Plastics Ind Ltd | 管の離脱防止構造 |
CN1834516A (zh) * | 2006-04-10 | 2006-09-20 | 王宝根 | 新型管道型材及其连接件 |
CN1920364A (zh) * | 2006-08-28 | 2007-02-28 | 阎金波 | 一种薄壁不锈钢管道注胶式无缝承插连接法 |
CN101225913A (zh) * | 2007-01-15 | 2008-07-23 | 北京安科管道工程科技有限公司 | 一种新型的双层结构管道连接方法及制造工艺 |
CN101525910A (zh) * | 2009-04-07 | 2009-09-09 | 同济大学 | 一种带保护件的灌浆套管耗能元件 |
CN202001741U (zh) * | 2011-01-21 | 2011-10-05 | 杨林海 | 一种玻璃钢管节点加固与双密封结构 |
Also Published As
Publication number | Publication date |
---|---|
CN108131494A (zh) | 2018-06-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108131494B (zh) | 一种钢管与水泥预制管连接的施工方法 | |
CN104233960B (zh) | 用于桥梁连续梁腹板灌浆的工件及施工方法 | |
CN106150523A (zh) | 一种高速铁路隧道水沟电缆槽整体模板施工工法 | |
CN107338729A (zh) | 一种预应力管道防堵装置及施工方法 | |
CN207297034U (zh) | 隧道二衬混凝土拱顶回填注浆装置 | |
CN102252147B (zh) | 管道裂纹维修方法 | |
CN103486349B (zh) | 球墨铸铁顶管的制备方法 | |
CN109487813A (zh) | 一种综合管廊过街顶管的一体化预制管节及其施工方法 | |
CN108131506B (zh) | 一种钢管与玻璃钢夹砂管连接的施工方法 | |
CN204080862U (zh) | 带耳环的穿墙防水短管 | |
CN204781608U (zh) | 一种带注浆管接头的精轧螺纹钢锚垫板 | |
CN205101771U (zh) | 用于玻璃钢管线内穿插修复的连接接头 | |
CN107268991A (zh) | 一种电气预埋管路出清水混凝土用预埋件及其施工方法 | |
CN207194452U (zh) | 地下室外壁墙体管路孔洞防水预埋管件装置 | |
CN203907114U (zh) | 一种管道承压补漏装置 | |
CN213898998U (zh) | 一种水工隧洞二次衬砌拱顶防脱空注浆装置 | |
CN202937956U (zh) | 修复铸铁管道用套袖及其修复铸铁管道用工具 | |
CN202992424U (zh) | 顶进施工法用带止水条的钢筋混凝土管 | |
CN205382941U (zh) | 桥梁隧道加固构件插片式灌浆装置 | |
CN211398995U (zh) | 一种压力输水管道钢岔管带水补强装置 | |
CN204922377U (zh) | 一种快速维修管道泄露的装置 | |
CN204112236U (zh) | 用于桥梁连续梁腹板灌浆的工件 | |
CN210343361U (zh) | 盾构隧道区间联络通道二衬混凝土浇筑装置 | |
CN210092836U (zh) | 一种带管座的预制钢筒混凝土圆形电力管廊 | |
CN202580338U (zh) | 顶进施工法用预应力钢筒混凝土管 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |