CN107679820A - Construction Schedule management method - Google Patents

Construction Schedule management method Download PDF

Info

Publication number
CN107679820A
CN107679820A CN201710760433.0A CN201710760433A CN107679820A CN 107679820 A CN107679820 A CN 107679820A CN 201710760433 A CN201710760433 A CN 201710760433A CN 107679820 A CN107679820 A CN 107679820A
Authority
CN
China
Prior art keywords
construction
progress
project
management platform
management
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710760433.0A
Other languages
Chinese (zh)
Inventor
罗欢畅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Yi Lianzhi Road Technology Co Ltd
Original Assignee
Shenzhen Yi Lianzhi Road Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Yi Lianzhi Road Technology Co Ltd filed Critical Shenzhen Yi Lianzhi Road Technology Co Ltd
Priority to CN201710760433.0A priority Critical patent/CN107679820A/en
Publication of CN107679820A publication Critical patent/CN107679820A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Engineering & Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

A kind of Construction Schedule management method, this method include:A, management platform collection construction plan, work progress, the real time data of construction speed, form electronic data report, and management platform is connected and communicated with the mobile communication terminal of each engineering project director, the progress of project is reported by each engineering project director;B, management platform gathers the video data of project under construction progress and safe condition by the camera of each construction site;C, management platform carries out big data integration, analysis to the electronic data gathered, forms data analysis form, analyzes and find out exception and reason in construction plan, work progress, construction speed;D, management platform carries out automatic risk assessment to the exception and reason that are found, and issues early warning automatically, while adjustment embodiment.The present invention can carry out intelligent management to architectural engineering so that administrative staff can grasp project progress in real time, find and solve problem and timely Adjusted Option in time.

Description

Construction Schedule management method
【Technical field】
The present invention relates to construction management technology, more particularly to a kind of Construction Schedule management method.
【Background technology】
At present, with industrialization, the quickening of urbanization process, the construction of building is into normality.People are paying close attention to Also the quality of building and the safety of construction are focused more on while the scale and speed of construction.However, actual conditions are but not It is fully up to expectations.As is known, it is not in place due to technology, management etc. in some architectural engineerings, cause construction quality Difference, potential safety hazard is more and Frequent Accidents.In the management of construction, because the place of many construction is scattered and not solid It is fixed, and building site quantity is more, adds safe construction, the management difficulty of civilized construction and personnel, the supervision difficulty of equipment.It is another Aspect, in architectural engineering, influenceed by many factors such as fund, personnel, material, weather, geological conditions and management, construct into Degree can not often be completed according to plan, for the factors for causing construction speed to complete according to plan, mostly by manual research point Reason is analysed, and adjusts progress, this conventional method cycle is long and efficiency is low, and can influence the progress of engineering.
【The content of the invention】
Present invention seek to address that above mentioned problem, and intelligent management can be carried out architectural engineering by providing one kind so that management Personnel can grasp project progress in real time, find and solve problem, the Construction Schedule management method of timely Adjusted Option in time.
To achieve the above object, the present invention provides a kind of Construction Schedule management method, and this method includes:
A, management platform by LAN gather construction plan, work progress, construction speed real time data, formed Electronic data report, meanwhile, management platform is connected and communicated with the mobile communication terminal of each engineering project director, by each engineering Project leader reports daily progress, Zhou Jindu and the moon progress of project;
B, management platform is by being installed in the camera collection project under construction progress of each construction site and regarding for safe condition Frequency evidence;
C, management platform carries out big data integration, analysis to the electronic data gathered, forms data analysis form, if Project fails to finish on schedule or quality and safety problem be present, then analyze and find out construction plan, work progress, construct into Exception and reason in degree;
D, management platform carries out automatic risk assessment to the exception and reason that are found, and issues early warning automatically, while intelligence Can adjustment and optimal enforcement scheme.
In step a, the management platform includes PC terminals and administrative staff's mobile client, the electronic data report and The daily progress of each engineering project director, Zhou Jindu and the moon progress report can be in the PC terminals and administrative staff's mobile client Real-time display.
Construction plan in the electronic data report include construction management organizational structure, construction period, equipment, material, Personnel, examination, project leader, quality control supervisor, work progress are tested including material preparation, construction process, supervision of construction, quality Receive, construction speed includes target advance, actual progress, in advance or delay time and reason and daily progress, Zhou Jindu and moon progress.
In step c, the data analysis form includes project progress, materials'use, quality surveillance, financial condition and work The reason for journey is overdue and the problem of exist.
In step d, the adjustment embodiment is the data analysis form as described in management platform by machine learning, The problem of automatic evaluation item is overdue or exists caused risk and its reason, and adjustment and Optimizing construction plan and apply Work progress.
The contribution of the present invention is that it efficiently solves the problems of existing construction project time management.The side of the present invention Method can be to construction from plan, the whole intelligent management of overall process implementation of work progress to construction speed, construction progress Various data and form can in management platform and the mobile client real-time display of administrative staff, and can by machine learning from Dynamic adjustment and optimal enforcement scheme, thus contribute to administrative staff to find and solve in time problem.This method can significant increase apply The science and intelligent level of work progress control, help to ensure that engineering is implemented and made smooth advances according to plan.
【Brief description of the drawings】
Fig. 1 is flow chart of the method for the present invention.
【Embodiment】
The following example is further explanation of the present invention, and the present invention is not limited in any way.
The present invention Construction Schedule management method be related to it is a kind of to architectural engineering from plan, work progress to construct into The method that the overall process of degree implements whole intelligent management, for the scientific and intelligent of lifting construction progress control.
Refering to Fig. 1, method of the invention includes:
S10:Management platform is connected to the administrative departments such as the design of architectural engineering, construction by LAN, and collection building is applied Work plan, work progress, the real time data of construction speed, form electronic data report.The construction plan includes but is not limited to Construction management organizational structure, construction period, equipment, material, personnel, examination, project leader, quality control supervisor etc., wherein, apply Work management organizational structure includes the departments such as construction management, technical management, quality management, personal management, respectively to construction speed, skill Art, quality, personnel etc. are managed.Construction period includes the construction period of architectural engineering projects.The equipment, material, people Member has detailed bill.The work progress includes material preparation, construction process, supervision of construction and inspection of quality etc..It is described Construction speed includes target advance, actual progress, in advance or delay time and reason and daily progress, Zhou Jindu and moon progress.Together When, management platform is connected and communicated with the mobile communication terminal of each engineering project director, is reported by each engineering project director Daily progress, Zhou Jindu and the moon progress of project.Described gathered data automatically generates electronic data report by management platform.The step In rapid and following step, the management platform includes PC terminals and administrative staff's mobile client, the electronic data report and The daily progress of each engineering project director, Zhou Jindu and the moon progress report can be in the PC terminals and administrative staff's mobile client Real-time display.
S20:In order to be monitored in real time to work progress, camera is equiped with each construction site, management platform passes through The camera collection project under construction progress in each building site and the real time video data of safe condition, the video data is as data acquisition A part be loaded into the electronic data report, can more intuitively understand project progress accordingly.
S30:Management platform carries out big data integration, analysis to the electronic data gathered, forms electronic data analysis report Table, the electronic data analytical statement include project progress, materials'use, quality surveillance, financial condition and the overdue original of engineering Because and the problem of exist.If project fails to finish on schedule or quality and safety problem be present, analyze and find out construction Exception and reason in plan, work progress, construction speed, as material is unqualified, lack of standardization, violation operation etc. of constructing.
S40:In the step, management platform by data analysis form described in machine learning, automatic evaluation item it is overdue or The caused risk of the problem of existing and its reason, on this basis, management platform issues early warning automatically to possible risk, and Adjustment and optimization are carried out to construction plan and construction speed, construction period is such as adjusted, changes working procedure, standard operation stream Journey and supervision inspection etc..
Take this, the present invention is entered by data acquisition, big data analysis and adjustment and optimization to work progress and progress Row scientific management, thus can significant increase construction project time management science and intelligent level, help to ensure that engineering by Implementing plan and make smooth advances.
Although being disclosed by above example to the present invention, protection scope of the present invention is not limited thereto, Under conditions of without departing from present inventive concept, each component is done to more than deformation, replacements etc. will fall into right of the invention In claimed range.

Claims (5)

1. a kind of Construction Schedule management method, it is characterised in that this method includes:
A, management platform by LAN gather construction plan, work progress, construction speed real time data, form electronics Data sheet, meanwhile, management platform is connected and communicated with the mobile communication terminal of each engineering project director, by each engineering project Director reports daily progress, Zhou Jindu and the moon progress of project;
B, management platform gathers the video counts of project under construction progress and safe condition by being installed in the camera of each construction site According to;
C, management platform carries out big data integration, analysis to the electronic data gathered, data analysis form is formed, if project Fail to finish on schedule or quality and safety problem be present, then analyze and find out in construction plan, work progress, construction speed Exception and reason;
D, management platform carries out automatic risk assessment to the exception and reason that are found, and issues early warning automatically, while intelligence is adjusted Whole embodiment.
2. the method as described in claim 1, it is characterised in that in step a, the management platform (30) includes PC terminals (31) With administrative staff's mobile client (32), the daily progress of the electronic data report and each engineering project director, Zhou Jindu and Month progress report can be in the PC terminals (31) and administrative staff's mobile client (32) real-time display.
3. method as claimed in claim 2, it is characterised in that the construction plan in the electronic data report includes construction and managed Organizational structure, construction period, equipment, material, personnel, examination, project leader, quality control supervisor are managed, work progress includes material Preparation, construction process, supervision of construction, inspection of quality are expected, when construction speed includes target advance, actual progress, shifts to an earlier date or delay Between and reason and daily progress, Zhou Jindu and moon progress.
4. the method as described in claim 1, it is characterised in that in step c, the data analysis form includes project progress, The reason for materials'use, quality surveillance, overdue financial condition and engineering and the problem of of presence.
5. the method as described in claim 1, it is characterised in that in step d, the adjustment embodiment is flat by managing Platform by data analysis form described in machine learning, the problem of automatic evaluation item is overdue or exists caused risk and its original Cause, and adjustment and Optimizing construction plan and construction speed.
CN201710760433.0A 2017-08-30 2017-08-30 Construction Schedule management method Pending CN107679820A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710760433.0A CN107679820A (en) 2017-08-30 2017-08-30 Construction Schedule management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710760433.0A CN107679820A (en) 2017-08-30 2017-08-30 Construction Schedule management method

Publications (1)

Publication Number Publication Date
CN107679820A true CN107679820A (en) 2018-02-09

Family

ID=61136186

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710760433.0A Pending CN107679820A (en) 2017-08-30 2017-08-30 Construction Schedule management method

Country Status (1)

Country Link
CN (1) CN107679820A (en)

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108153219A (en) * 2018-02-12 2018-06-12 北京新能正源环境科技有限公司 Construction speed monitoring system, server and terminal device
CN108564198A (en) * 2018-03-06 2018-09-21 宁波诺丁汉大学 A kind of construction speed prediction technique and system based on Building Information Model
CN108681316A (en) * 2018-07-11 2018-10-19 宿州云宏建设安装有限公司 A kind of highway construction environmental monitoring system
CN108985603A (en) * 2018-07-04 2018-12-11 山东华坤地质工程有限公司 A kind of geologic prospect big data analysis management system and method
CN109636675A (en) * 2018-12-12 2019-04-16 上海荷福人工智能科技(集团)有限公司 A kind of management method and system of the construction site based on artificial intelligence
CN109636202A (en) * 2018-12-14 2019-04-16 万翼科技有限公司 The calculation method of effectiveness parameters, device and storage medium per capita
CN109658014A (en) * 2019-01-24 2019-04-19 周瑜 A kind of construction overall management method
CN109670795A (en) * 2018-12-28 2019-04-23 广州易宝信息技术有限公司 Project management system based on big data
CN109726457A (en) * 2018-12-17 2019-05-07 深圳市中行建设工程顾问有限公司 A kind of overall process intelligence engineering supervisory information managing and control system
CN109741090A (en) * 2018-12-18 2019-05-10 刘雨昆 It is a kind of based on multifactor distribution engineering material needing forecasting method
CN109816263A (en) * 2019-02-01 2019-05-28 南通四建集团有限公司 A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision
CN110245920A (en) * 2019-06-19 2019-09-17 刘至瀚 A kind of online digital intelligent finished system and its implementation
CN110264168A (en) * 2019-07-26 2019-09-20 梧州市城建投资发展集团有限公司 A kind of Engineering Project Construction duration monitoring system and method
CN110298584A (en) * 2019-06-28 2019-10-01 裴涛 A kind of civil engineering projects field management BIM system
CN110348799A (en) * 2019-05-23 2019-10-18 北京新研汇医药研发有限公司 A kind of clinical research monitor work inspection method and system
CN110472858A (en) * 2019-08-10 2019-11-19 浙江同洲项目管理有限公司 A kind of Project Supervision approaches to IM
CN110490975A (en) * 2019-08-25 2019-11-22 中铁二局第一工程有限公司 A kind of overall construction site plan production method based on orthography data
CN110688413A (en) * 2019-09-27 2020-01-14 重庆渝高科技产业(集团)股份有限公司 Building data analysis system and method based on big data
CN110852638A (en) * 2019-11-15 2020-02-28 南京慧石建筑科技有限公司 Construction project progress and cost management system
CN111178694A (en) * 2019-12-12 2020-05-19 青岛农业大学 Improved job shop scheduling display system based on big data algorithm
CN111582728A (en) * 2020-05-08 2020-08-25 无锡商业职业技术学院 Multichannel complex building engineering dynamic management system
CN111612523A (en) * 2020-04-26 2020-09-01 四川同兴达建设咨询有限公司 Evaluation method and evaluation system for construction engineering cost operation
CN112200476A (en) * 2020-10-19 2021-01-08 中国十七冶集团有限公司 Assembly type building full life cycle quality monitoring platform and monitoring method based on Internet of things
CN112633920A (en) * 2020-12-15 2021-04-09 广东广建项目管理有限公司 Data research method, device and storage medium
CN114548912A (en) * 2022-01-21 2022-05-27 湖南教建集团有限公司 Whole-process tracking method and system for building engineering project management
CN116050942A (en) * 2023-03-20 2023-05-02 国艺天成建设工程技术有限公司 Fine use management system and management method for engineering construction materials
CN116822925A (en) * 2023-06-26 2023-09-29 中咨海外咨询有限公司 Engineering project management system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104318408A (en) * 2014-11-25 2015-01-28 上海建科工程咨询有限公司 Multi-target and multi-dimension risk management system for large building engineering construction
CN104573892A (en) * 2013-10-17 2015-04-29 王丽华 Whole process visual project management system for engineering construction
US20150134390A1 (en) * 2013-11-13 2015-05-14 Schlumberger Technology Corporation Automatic Wellbore Activity Schedule Adjustment Method and System
CN105303304A (en) * 2015-10-15 2016-02-03 贵州省邮电规划设计院有限公司 Method for engineering field management based on handheld terminal
CN105373875A (en) * 2015-08-26 2016-03-02 吕曼 Intelligent engineering construction project management system
CN106096905A (en) * 2016-05-31 2016-11-09 北京诚公通信工程监理股份有限公司 A kind of project management method and system
CN106408172A (en) * 2016-08-31 2017-02-15 广东达安项目管理股份有限公司 Project management system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104573892A (en) * 2013-10-17 2015-04-29 王丽华 Whole process visual project management system for engineering construction
US20150134390A1 (en) * 2013-11-13 2015-05-14 Schlumberger Technology Corporation Automatic Wellbore Activity Schedule Adjustment Method and System
CN104318408A (en) * 2014-11-25 2015-01-28 上海建科工程咨询有限公司 Multi-target and multi-dimension risk management system for large building engineering construction
CN105373875A (en) * 2015-08-26 2016-03-02 吕曼 Intelligent engineering construction project management system
CN105303304A (en) * 2015-10-15 2016-02-03 贵州省邮电规划设计院有限公司 Method for engineering field management based on handheld terminal
CN106096905A (en) * 2016-05-31 2016-11-09 北京诚公通信工程监理股份有限公司 A kind of project management method and system
CN106408172A (en) * 2016-08-31 2017-02-15 广东达安项目管理股份有限公司 Project management system

Cited By (32)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108153219A (en) * 2018-02-12 2018-06-12 北京新能正源环境科技有限公司 Construction speed monitoring system, server and terminal device
CN108564198A (en) * 2018-03-06 2018-09-21 宁波诺丁汉大学 A kind of construction speed prediction technique and system based on Building Information Model
CN108985603A (en) * 2018-07-04 2018-12-11 山东华坤地质工程有限公司 A kind of geologic prospect big data analysis management system and method
CN108681316A (en) * 2018-07-11 2018-10-19 宿州云宏建设安装有限公司 A kind of highway construction environmental monitoring system
CN109636675A (en) * 2018-12-12 2019-04-16 上海荷福人工智能科技(集团)有限公司 A kind of management method and system of the construction site based on artificial intelligence
CN109636202A (en) * 2018-12-14 2019-04-16 万翼科技有限公司 The calculation method of effectiveness parameters, device and storage medium per capita
CN109636202B (en) * 2018-12-14 2021-05-18 万翼科技有限公司 Calculation method and device for per-person efficiency parameter and storage medium
CN109726457A (en) * 2018-12-17 2019-05-07 深圳市中行建设工程顾问有限公司 A kind of overall process intelligence engineering supervisory information managing and control system
CN109741090A (en) * 2018-12-18 2019-05-10 刘雨昆 It is a kind of based on multifactor distribution engineering material needing forecasting method
CN109670795A (en) * 2018-12-28 2019-04-23 广州易宝信息技术有限公司 Project management system based on big data
CN109658014A (en) * 2019-01-24 2019-04-19 周瑜 A kind of construction overall management method
CN109816263A (en) * 2019-02-01 2019-05-28 南通四建集团有限公司 A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision
CN110348799A (en) * 2019-05-23 2019-10-18 北京新研汇医药研发有限公司 A kind of clinical research monitor work inspection method and system
CN110245920A (en) * 2019-06-19 2019-09-17 刘至瀚 A kind of online digital intelligent finished system and its implementation
CN110298584A (en) * 2019-06-28 2019-10-01 裴涛 A kind of civil engineering projects field management BIM system
CN110264168A (en) * 2019-07-26 2019-09-20 梧州市城建投资发展集团有限公司 A kind of Engineering Project Construction duration monitoring system and method
CN110472858A (en) * 2019-08-10 2019-11-19 浙江同洲项目管理有限公司 A kind of Project Supervision approaches to IM
CN110490975A (en) * 2019-08-25 2019-11-22 中铁二局第一工程有限公司 A kind of overall construction site plan production method based on orthography data
CN110490975B (en) * 2019-08-25 2022-11-01 中铁二局第一工程有限公司 Construction general plane graph manufacturing method based on orthographic image data
CN110688413A (en) * 2019-09-27 2020-01-14 重庆渝高科技产业(集团)股份有限公司 Building data analysis system and method based on big data
CN110852638A (en) * 2019-11-15 2020-02-28 南京慧石建筑科技有限公司 Construction project progress and cost management system
CN111178694A (en) * 2019-12-12 2020-05-19 青岛农业大学 Improved job shop scheduling display system based on big data algorithm
CN111612523A (en) * 2020-04-26 2020-09-01 四川同兴达建设咨询有限公司 Evaluation method and evaluation system for construction engineering cost operation
CN111582728A (en) * 2020-05-08 2020-08-25 无锡商业职业技术学院 Multichannel complex building engineering dynamic management system
CN111582728B (en) * 2020-05-08 2024-05-17 无锡商业职业技术学院 Multichannel complex building engineering dynamic management system
CN112200476A (en) * 2020-10-19 2021-01-08 中国十七冶集团有限公司 Assembly type building full life cycle quality monitoring platform and monitoring method based on Internet of things
CN112633920A (en) * 2020-12-15 2021-04-09 广东广建项目管理有限公司 Data research method, device and storage medium
CN112633920B (en) * 2020-12-15 2022-10-21 广东广建项目管理有限公司 Data research method, device and storage medium
CN114548912A (en) * 2022-01-21 2022-05-27 湖南教建集团有限公司 Whole-process tracking method and system for building engineering project management
CN116050942A (en) * 2023-03-20 2023-05-02 国艺天成建设工程技术有限公司 Fine use management system and management method for engineering construction materials
CN116822925A (en) * 2023-06-26 2023-09-29 中咨海外咨询有限公司 Engineering project management system
CN116822925B (en) * 2023-06-26 2023-12-19 中咨海外咨询有限公司 Engineering project management system

Similar Documents

Publication Publication Date Title
CN107679820A (en) Construction Schedule management method
CN111126838B (en) Intelligent engineering management system
CN113313387B (en) Intelligent management and control method and system for major security risk classification of enterprise
CN109754176A (en) A kind of project cost progress control system
CN206921161U (en) It is a kind of to include inspection management and defect processing and the intelligent inspection system of examination
CN112163747A (en) Construction engineering project quality management system
CN103336499A (en) System and method of dynamic management for construction quality of asphalt concrete pavement
CN104503410A (en) Asphalt pavement construction quality control system and method
CN113361975A (en) BIM + wisdom building site management platform system
CN103854137A (en) Method for evaluating economic and technical indexes of engineering project
CN110826981A (en) Transmission tower construction progress control system and method based on Internet of things
CN110888527A (en) Remote support and field management and control system based on Internet of things technology
CN112162531A (en) Industrial system process monitoring and adjusting system based on Internet of things
CN111966034B (en) Intelligent water affair system
CN114997698A (en) Multifunctional intelligent beam yard manufacturing management system
CN208521175U (en) A kind of creation data monitoring analysis system
CN116681199A (en) Intelligent mine beneficiation system
CN117035419A (en) Intelligent management system and method for enterprise project implementation
CN110989042A (en) Intelligent prediction method for highway fog-clustering risk
CN110322218A (en) Intelligent society insurance business operation and monitoring method and system
CN117788223A (en) Building construction management method based on multi-data fusion
CN111335950B (en) Regional coal mine gas disaster risk early warning data acquisition system and acquisition method
CN205857881U (en) A kind of railway communication steel tower supervising device
CN110266811B (en) Workshop abnormal information pushing device and method based on MQTT technology
CN114612069A (en) Safety production management system and method for metallurgical industry

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180209

RJ01 Rejection of invention patent application after publication